PPAP Checklist Generic
PPAP Checklist Generic
(PPAP/ISIR/ISR)
Submission Date:
Supplier
Supplier: XXXXXX QE:
Rep:
ndc (number of discriminate units) should be equal to or greater than 5, and should be equal to
or greater than 10 of used for variable SPC
d Gage error over 30% is not allowed. Actions must be taken and documented to reduce gage error.
e Gage Study must be current within one (1) calendar year
f Other requirements:
c All notes must be sequentially ballooned/numbered (see item #1) including material and test specifications.
Must be reported on the current AIAG Production Part Approval, Dimensional Results (Form # CFG – 1003,
d
current revision) or XXXXXX approved format.
e Samples must be identified as Sample #1 to Sample #5, which correlate to the dimensional report.
If drawing does not specify SC's, supplier is required to choose significant characteristics to measure based
f
upon their expertise of the product and provide data.
g Supplier must identify and retain one of the parts measured from each cavity as the master sample.
h Other requirements:
If any requirements cannot be met by the supplier, it is the supplier's responsibility to complete and submit a
request for a written deviation or waiver with the package, detailing the deviation request and number of parts
effected and/or length of time needed.
These requirements have been reviewed by XXXXXX quality representative for product approval.
Submission is: Approved Interim Approval until: Rejected
Other Notes:
n/a
d n/aGage error over 30% is not allowed. Actions must be taken and documented to reduce gage error.
n/aWhen a commercial laboratory is used, test results must be submitted on the laboratory letterhead or
e
normal laboratory report format.
f n/aOther requirements:
Manufacturing Floor Plan must illustrate entire manufacturing process from receiving of raw materials
e
through shipping operations.
f ✘ Must be submitted in a tabbed, soft-sided three-ring binder.
g ✘ Completed, signed checklist submitted with the package.
Packaging design form (carton and pallet size, cartons per pallet, parts per carton, expendable vs.
h
returnable).
i Process Mapping (reference Supplier Manual).
j ✘ Supplier contact list.
k ✘ Sample barcode label to Hi-Stat specifications (reference Supplier Manual).
Customs Documentation (see Hi-Stat Supplier Manual, Section XI, Miscellaneous, Paragraph D,
l
Customs Documentation) if applicable.
m ✘ Digital picture of each component with accompanying terminology for identification.
n ✘ Bright pink labels marked ____________ on outside of each container shipped - (prototype).
o ✘ Yellow labels marked ___________ on outside of each container shipped - (pre-production).
p ✘ Green labels marked ___________ on outside of each container shipped - (production).
q Sub-component approvals (warrants, MATSPC, etc).
r Early production containment is required for 45 days after Start of Production.
s Other requirements:
If any requirements cannot be met by the supplier, it is the supplier's responsibility to complete and submit a
request for Deviation/Waiver with the package, detailing the deviation request and number of parts effected and/or
length of time needed.
These requirements have been reviewed by Hi-Stat quality representative for product approval.
Submission is: ✘ Approved Interim Approval until: ✘ Rejected
Other Notes:
Bob Doering
APQP Engineer
Hi-Stat Mfg. - A Division of Stoneridge
345 South Mill Street
Lexington, Ohio 44904