Guidelines On LD P2M2.PDF Part 2
Guidelines On LD P2M2.PDF Part 2
ISBN 978-983-3895-58-8
ACKNOWLEDGEMENT
for their cooperation and contribution throughout the study. Finally, the consultant would like
to thank the bodies and individuals who assisted the work of the consultant with submissions
and information.
GUIDELINES ON LD-P2M2
BACKGROUND
There has been an increase in concern with regard to soil erosion issues which resulted in
sedimentation and deterioration of river water quality due to earthwork activities of development
projects. The deterioration of river water quality brought about by soil erosion originating from
surface water runoff, erosion and sedimentation requires more effective prevention and
mitigation measures in the construction practices. In the context of current regulations,
fundamental prevention practices which are more effective are needed to control pollution caused
by surface runoff, erosion and sedimentation.
The effect of surface runoff resulting in soil erosion and sedimentation on the environment has
long been one of the agenda of concern in Malaysia, particularly to the Department of
Environment (DOE) which is entrusted with the task of ensuring a sustainable development. A
review of the existing guidelines for the prevention and control of surface runoff, soil erosion and
sedimentation is therefore timely and to be enhanced with pollution controls which are more
practical and effective.
The first formal document to assist planners, practitioners and developers to control erosion was
prepared by the DOE in 1978. The guidelines which were formulated at that time were produced
to address the issues of surface runoff, erosion and sedimentation.
In 1992, various Government departmental agencies and academic institutions were called upon
to identify activities that could cause erosion and sedimentation and to recommend measures to
check these issues. The DOE Guidelines (1978) were reviewed and a new document entitled
“Guidelines for the Prevention and Control of Soil Erosion and Siltation” was produced in 1978.
It contained most of the 1978 guidelines together with additional new methodologies for the
prevention of erosion.
Between 1994 and early 1996, the DOE produced guidelines relating to the preparation of
environmental impact assessments (EIA) for each of the 19 prescribed activities listed in the
Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987.
Each of these documents contains general guidelines pertaining to the control of erosion and
sedimentation.
Under the “Teras ke-4 RMKe-11” i.e., “Heading Toward Green Growth in the Main Focus Field
(BFU) in Climate Change/Environment”, the Government has approved an allocation to execute
the Strengthening Environmental Sustainability project (Project Code: P23072004114001) for
2016 and 2017. One of the project scopes which the DOE will need to execute is on
Strengthening in Execution of EIA Procedures in Malaysia under Environmental Quality Act
1974 (Amendment 2012): Formation of Environmental Guidelines: Guidelines on Erosion and
Sedimentation.
In connection with the DOE’s effort to foster the culture of self-regulation in the regulated
sectors, mainstreaming the environmental agenda represents an important element in all the
procedures executed by the DOE, including the EIA procedures. From the EIA perspective,
GUIDELINES ON LD-P2M2
environment mainstreaming ought to be internalized and executed in all fields which are related
with the development of EIA projects such as, in all levels of the developer’s project organization
structure; in all levels of the process development making project decision; and in all levels
during project development phases (planning, construction and operation). Consideration,
specification and details that are contained in this Guidelines are consistent with the
mainstreaming spirit underlined in the latest EIA Guidelines.
In view of the above, this Guidelines on Land Disturbing Pollution Prevention and Mitigation
Measures (LD-P2M2) has been produced to introduce erosion and sedimentation control
measures which are practical and effective to protect river water quality and to minimize the
degradation and deterioration of the environment due to earthworks activities.
GUIDELINES ON LD-P2M2
AIM OF GUIDELINES
The Guidelines on LD-P2M2 is a document to identify, cover and address matters relating to the
prevention, mitigation and control of the discharge from the development area containing the
major pollutant (suspended solids) resulting from land disturbing activities in an EIA project.
The Guidelines on LD-P2M2 has been prepared to improve on the “Guidelines For Prevention
and Control of Soil Erosion and Siltation in Malaysia” (DOE, Nov 2008), as well as to provide
more details and understanding on the referred LD-P2M2 Document required for the submission
of EIA Report and EMP.
The main purpose of this Guidelines is to integrate the established erosion and sedimentation
control measures with the principles, techniques and methods in the execution of earthwork
activities for developmental projects by controlling, preventing and minimizing the effect of
pollution from erosion and sedimentation.
This Guidelines represents one of the efforts of environmental mainstreaming towards ensuring
environmental sustainability.
As mentioned above, this Guidelines is not meant to replace but to enhance the existing
guidelines/documents (Manual Panduan Pemeriksaan BMPs (Best Management Practices)
Untuk Kawalan Hakisan and Sedimen, and Guidelines For Prevention and Control of Soil
Erosion and Siltation in Malaysia), and to complement the existing methods that are currently
being used by the relevant project parties.
This Guidelines aims to explain the usage and application of pollution prevention and mitigation
measures prior to and during land disturbing activities, for the purposes of complying with the
prescribed EIA Conditions of Approval.
GUIDELINES ON LD-P2M2
GUIDELINES USAGE
At the moment, the Guidelines has been prepared primarily for the application into development
projects that are classified as Prescribed Activity under the latest Environmental Quality
(Prescribed Activities) (Environmental Impact Assessment) Order 2015.
The proposed Guidelines is mainly intended to be used for the preparation of EIA
Reports/Environmental Management Plans, as well as a tool for field inspection of EIA projects.
The document has been prepared for a wide audience who are involved in land development
planning, implementation and assessment, including Federal and State Government Departmental
and Agency staff, as well as for the private sector including planners, developers, contractors and
sub-contractors.
It is envisioned that this Guidelines is able to enhance the understanding of the DOE officers
when undertaking assessment of information related to document, maps and drawings associated
with project execution.
Additionally, the Guidelines aims to assist the project proponents and EIA consultants in the
understanding of LD-P2M2, as well as in the preparation of the LD-P2M2 Document. It also
standardizes the format of the LD-P2M2 Document that is required to be submitted at the EIA
stage, and which includes maps, plans and drawings, information required and procedures for
LD-P2M2 submission. Last but not least, this Guidelines should also assist the project proponent
personnel, especially the Environment Officer in the supervision of the overall implementation of
the LD-P2M2.
The chapters in this Guidelines are arranged in a logical sequence to explain the successive steps
necessary to control and manage erosion and sedimentation problems.
Chapter 1 gives an introduction on what LD-P2M2 is and the driving forces behind the need for
LD-P2M2.
Chapter 2 then presents the basic fundamentals of erosion and BMPs, including amongst others,
a summary of the existing Malaysian laws and regulation which encapsulate the requirements for
controlling erosion and sediment in project sites; an understanding of the processes of erosion
and sedimentation and highlights their resulted impacts; and the current methods used in
quantifying and prediction of potential soil losses from land disturbing activities of development
projects. Additionally, a discussion on the possible types of BMPs that are applicable in
Malaysia is also included in this chapter.
GUIDELINES ON LD-P2M2
Chapter 3 subsequently highlights a list of potential land disturbing activities with selected
examples, whilst Chapter 4 provides the readers with a basic understanding of project
implementation characteristics including the identification of project phases, project components,
work breakdown structures, and work scheduling, staging & sequencing.
Chapter 5 discusses the aspects of project implementation including techniques to apply the
mitigation measures into the phases of the construction and the methodology for preparing a LD-
P2M2 document in accordance to DOE’s requirements.
Lastly Chapter 6 covers IIM (Inspect, Install, Maintain); Compliance Monitoring, Impact
Monitoring, Performance Monitoring; Reporting & Documentation; and Environmental
Auditing.
i
GUIDELINES ON LD-P2M2
CONTENT
PAGE
TABLE OF CONTENTS i
LIST OF TABLES vii
LIST OF FIGURES viii
LIST OF APPENDICS x
List of Tables
List of Figures
PAGE
Figure 1.1 Elements of LD-P2M2 1-2
Figure 1.2 Needs for LD-P2M2 1-3
Figure 1.3 Examples of Amenity Losses 1-8
Figure 1.4 Examples of Public Disruptions 1-12
Figure 1.5 BMP Categories 1-19
Figure 1.6 Typical Project Flow 1-21
Figure 1.7 Progression of LD-P2M2 from Planning to Construction 1-22
Figure 1.8 LD-P2M2 During EIA Process Stage 1-23
Figure 1.9 LD-P2M2 After EIA Approval Stage 1-24
Figure 2.1 Parties Involved in Erosion & Sediment 2-18
Figure 4.1 Large Scale Earthworks with No Proper BMPs Installed 4-3
Figure 4.2 Effects of Erosion and Sedimentation on River Downstream 4-4
Figure 4.3 Damages to Vegetation from Soil Erosion 4-4
Figure 4.4 Vast Land Clearing with Lack of Phasing Planning 4-5
Figure 4.5 Massive Scouring of Ground Surface due to Erosion of 4-6
Unprotected Surfaces
Figure 4.6 Impacts from Poor Planning in Phasing of Site Works 4-7
Figure 4.7 Erosion and Surface Runoff from a Poorly Managed Work Site 4-8
Figure 4.8 No Indication of Works Phasing Implemented 4-9
Figure 4.9 Erosion and Landslides Resulted from Lack of Activities 4-9
Phasing
Figure 4.10 Erosion and Surface Runoff from a Poorly Managed Work Site 4-11
Figure 4.11 Typical Flow of a Project 4-13
Figure 4.12 Typical Pre-Site Activities 4-17
Figure 4.13 Purpose of Defining Activities in Project Management 4-20
Figure 4.14 Possible Phasing 4-26
Figure 4.15 Possible Phasing 4-30
Figure 4.16 Possible Phasing 4-32
Figure 4.17 WBS for Addressing Erosion and Sedimentation 4-37
Figure 4.18 Example of a Civil Engineering Project 4-39
Figure 4.19 Possible Component Breakdown of STW Project (based on 4-42
disciplines)
Figure 4.20 Components of A Highway Project 4-44
Figure 4.21 A Simpler Alternative to Component Breakdown of STW 4-46
Project
Figure 4.22 Layout of a New 10 km Highway Project 4-49
Figure 4.23 A Simpler Alternative to Component Breakdown of A Highway 4-50
Project
Figure 4.24 Layout of A Housing Development Project 4-54
Figure 4.25 Components of A Housing Development Project 4-55
Figure 4.26 Alternative Component Breakdown of A Housing Development 4-56
ix
GUIDELINES ON LD-P2M2
Project
Figure 4.27 Components of Main Drainage Project 4-59
Figure 4.28 Conventional Breakdown of A Main Drainage Project 4-60
Figure 4.29 Alternative Component Breakdown of A Main Drainage Project 4-61
Figure 4.30 Components of A River Check Dam Project 4-63
Figure 4.31 Alternative Component Breakdown of A River Check Dam 4-64
Project
Figure 4.32 Components of A Forest Redevelopment Project 4-67
Figure 4.33 Alternative Component Breakdown of A Forest Redevelopment 4-68
Project
Figure 4.34 Identification of Possible Project Activities of STW Project 4-83
Figure 4.35 Identification of Possible Project Activities of STW Project 4-84
Figure 4.36 Possible Project Activities of a Highway Project 4-96
Figure 4.37 Identification of Possible Scope of Work of Highway Project 4-97
Figure 4.38 Possible Project Activities of a Housing Development Project 4-102
Figure 4.39 Possible Scope of Work of a Housing Development 4-103
Figure 4.40 Possible Project Activities of a Main Drainage Project 4-106
Figure 4.41 Possible Scope of Work of a Main Drainage Project 4-107
Figure 4.42 Possible Project Activities of a River Check Dam Project 4-110
Figure 4.43 Possible Scope of Work of a River Check Dam Project 4-111
Figure 4.44 Possible Project Activities of a Forest Redevelopment Project 4-115
Figure 4.45 Possible Scope of Work of a Forest Redevelopment Project 4-116
Figure 4.46 Environmental Method Statements for STW Project 4-121
Figure 4.47 Environmental Method Statements for Highway Project 4-122
Figure 4.48 Environmental Method Statements for Housing Project 4-124
Figure 4.49 Environmental Method Statements for Drainage Project 4-126
Figure 4.50 Environmental Method Statements for River Check Dam Project 4-128
Figure 4.51 Environmental Method Statements for Forest Redevelopment 4-129
Project
Figure 4.52 Recommended Project Sequence for Phases of Work for STW 4-135
Project
Figure 4.53 Proposed Phasing for Sewage Treatment Works Project 4-136
Figure 4.54 Proposed Project Sequence for Phase 1 4-137
Figure 4.55 Proposed Project Sequence for Phase 2 4-137
Figure 4.56 Proposed Phasing for Highway Project 4-143
Figure 4.57 Proposed Phasing for Housing Project 4-144
Figure 4.58 Proposed Phasing for Drainage Project 4-145
Figure 5.1 Information for LD-P2M2 Analysis 5-10
Figure 5.2 LD-P2M2 Implementation Framework 5-13
Figure 5.3 Weather/Rainfall Data and Related P2M2s 5-15
Figure 5.4 Runoff Velocity /Flow rate and Related P2M2s 5-16
Figure 5.5 Earthwork Volumes and Related P2M2s 5-17
Figure 5.6 Soil Characteristics and Related P2M2s 5-18
Figure 5.7 Erosion/Sedimentation Sensitive Receivers and Related P2M2s 5-19
x
GUIDELINES ON LD-P2M2
List of Appendices
Abbreviations
EM Environmental Mainstreaming
EO Environmental Officer
EP Environmental Policy
EPMC Environmental Performance Monitoring Committee
EPMD Environmental Performance Monitoring Document
EQA Environmental Quality Act 1974
ESCP Erosion and Sediment Control Plan
HVF High Visibility Fencing
IIM Inspect, Install, Maintain
IM Impact Monitoring
JPS Department of Drainage and Irrigation
LD-P2M2 Land Disturbing Pollution Prevention and Mitigation Measures
MSMA Manual Saliran Mesra Alam
MUSLE Modified Universal Soil Loss Equation
P2M2s Pollution Prevention and Mitigation Measures
PBT Local Authority
PE Professional Engineer
PM Performance Monitoring
PMD Performance Monitoring Document
PMR Performance Monitoring Report
PP Project Proponent
RECPs Rolled Erosion Control Products
ROW Right of Way
STW Sewage Treatment Works
TNB Tenaga National Berhad
TRM Turf Reinforcement Mat
USLE Universal Soil Loss Equation
WBS Work Breakdown Structure
1-1
Q GUIDELINES ON LD-P2M2
CHAPTER 1
INTRODUCTION
In the context of this Guidelines on Land Disturbing Pollution Prevention and Mitigation
Measures (LD-P2M2), “Land Disturbing” (LD) refers to “any project development that is
subject to Section 34A EQA 1974” which can possibly involve activities such as clearing
of trees or vegetation, excavating, raising or sloping of ground, stripping, grading,
grubbing, trenching, excavating, filling, logging, storing of materials and blasting.
In other word, “land disturbing” also means any activity that changes the physical
conditions of land form, vegetation and hydrology, and during the process, creates bare
soil, or otherwise may cause erosion or sediment issues.
“Pollution Prevention and Mitigation Measures” (P2M2) refer to the “Best Management
Practices (BMPs) that include activities, facilities, measures, planning or procedures used
to minimize accelerated erosion and sedimentation as well as other pollutants resulting
from land disturbing activities and to manage runoff water to protect and maintain the
quality of soil or inland or Malaysian waters and the existing and designated uses of
waters before, during, and after land disturbing activities”.
To assist the site operators involved in the land disturbing activities, especially the
Environment Officer, in supervising the overall implementation of LD-P2M2 that
include the installation, inspection and maintenance (2I’s1M) of pollution prevention
and mitigation measures as well as in preparing the required documentation and
reports (photographs, data collections and corrective actions) on 2I’s1M.
Following on from the above, the major elements of LD-P2M2 are shown in Figure 1.1.
The analysis of and findings on LD-P2M2 are ultimately documented in the LD-P2M2
Document which can be described as follows:
The focus of a LD-P2M2 Document will be on the prevention, mitigation and control
of the discharge from the development area containing the major pollutant
(suspended solids) resulting from the project’s land disturbing activities.
1-3
Q GUIDELINES ON LD-P2M2
In Malaysia, especially due to events related to erosion and sediment arising from
construction projects that have occurred in recent times, various factors are perceived to
be the driving forces for the need to formally formulate and implement the concept of
LD-P2M2 into the EIA projects, at least at this initial stage. Figure 1.2: Needs for LD-
P2M2 below shows diagrammatically the myriad of driving forces as mentioned earlier.
Section 34A of the EQA stipulates that an EIA report shall be undertaken in
accordance with the guidelines as prescribed by the Director General, and shall
contain “the proposed measures that shall be undertaken to prevent, reduce or
control the adverse impact on the environment.” This Section further stipulates
that the person carrying out the prescribed activity “shall provide sufficient proof
that the conditions attached to the report (if any) are being complied with and that
the proposed measures to be taken to prevent, reduce or control the adverse impact
on the environment are being incorporated into the design, construction and
operation of the prescribed activity.”
1-4
Q GUIDELINES ON LD-P2M2
In summary, there are currently existing laws and regulation in the Malaysian
construction practice that prohibit the acts of polluting the environment as a result
from erosion and sediment issues generated from site activities.
Under the Government’s “Heading Toward Green Growth in the Main Focus Field
(BFU) in Climate Change/Environment” programme, an allocation has been
approved to strengthen the Execution of EIA Procedures in Malaysia under
Environmental Quality Act 1974 (Amendment 2012): Formation of Environmental
Guidelines: Guidelines on Erosion and Sedimentation. The introduction of LD-
P2M2 hence is in line with the above national planning goal.
1.2.3 Self-Regulation
In the strive to solicit active participation of all project parties in their roles in
relation to environmental protection, including erosion and sediment control, DOE
has adopted the “self-regulation” policy, i.e., by ensuring mainstreaming of
environmental agenda as an integral part and parcel of all the procedures
implemented by the DOE, including the EIA procedure. With this, all levels of the
project developer’s organizational structure, the project development decision
making process, and the project development phases (planning, construction, and
operation) are required to be well versed on their project-related environmental
issues, as well as to ensure constant regulatory compliance of the project by,
amongst other things, monitoring the environmental performance and
effectiveness of pollution prevention and mitigation measures (P2M2s) of the
project through the project-appointed “Environmental Performance Monitoring
Committee” (EPMC).
In this regard, the LD-P2M2 Guidelines will need to be well balanced as well as
comprehensive so that all parties using this document have a common
understanding pertaining to land-disturbing pollution prevention and mitigation
measures.
“The EIA procedure, a preventive strategy of the DOE also needs to embrace the
environmental mainstreaming and self-regulation goal in order to enhance its
effectiveness in mitigating the adverse impacts from development projects on the
environment at every stage of the EIA procedure. Self-regulation culture in EIAs
means that the Project Proponent will be charged with full responsibility and
accountability for taking environmental friendly options and instituting effective
pollution prevention and mitigation measures (P2M2) and self-demonstration of
regulatory compliance of the EIA procedure at all stages of project
implementation.”
The Guideline also directly holds the Project Proponent to be legally responsible
“towards ensuring regulatory compliance of his project with the EIA procedure at
all stages of project planning and implementation.” The Project Proponent is also
tasked to allocate sufficient funds for every stage of project planning and
implementation, and amongst others, “for implementation of Environmental
Management Plan (EMP) including temporary pollution prevention and mitigation
measures (P2M2). P2M2 shall be those which can be described as state of the art
technologies, best available technologies (BATs), or industry best practices.”
The other elements under the new EIA Guideline that would drive the increase
effort in controlling erosion and sediment issues are summarized below:
Clause Section 34A (1): “The Minister, after consultation with the Council, may
by order prescribe any activity which may have significant environmental impact
as prescribed activity.”
Clause Section 34A (2): “Any person intending to carry out any prescribed
activity shall appoint a qualified person to conduct an environmental impact
assessment and to submit a report thereof to the Director General in the manner
as the Director General may prescribe.”
Clause Section 34A (2C): “The report shall be in accordance with the guidelines
as the Director General may prescribe and shall contain: (a) an assessment of the
impact such activity will have or is likely to have on the environment; and (b) the
proposed measures that shall be undertaken to prevent, reduce or control the
adverse impact on the environment.”
Clause Section 34A (7): “If the Director General approves the report, the person
carrying out the prescribed activity, in the course of carrying out such activity,
shall provide sufficient proof that the conditions attached to the report (if any) are
being complied with and that the proposed measures to be taken to prevent,
reduce or control the adverse impact on the environment are being incorporated
into the design, construction and operation of the prescribed activity.”
1-6
Q GUIDELINES ON LD-P2M2
Clause Section 34AA: “(1) The Director General may issue a prohibition order
or stop work order to the person carrying out the prescribed activities –
(2) The prohibition order or stop work order may be issued for the purpose of
preventing the prescribed activities from continuing –
Also stated in DOE’s guidelines is the following: “All activities subject to EIA
Order, 2015 which involve land disturbing or site preparation activities are
required to prepare a LD-P2M2 as part of the EMP submission requirement.
Non-compliance with the specifications stipulated in this Guidelines may be a
cause for the rejection of the EMP or will cause a delay in the EMP processing.”
The direct physical and environmental impacts from the effects of erosion and
sedimentation can be summarized as follows:
1-7
Q GUIDELINES ON LD-P2M2
Physical Effects
Costly damage to aquatic areas and to private and public lands.
Obstruction of stream channels and navigable rivers.
Increase in flood crests resulting in flood damages.
Functionally impair storm water conveyances such as culverts and piping
systems from sediment influx.
Loss in storage capacity of municipal and industrial water supply
reservoirs.
Impairment of recreational impoundment.
Decrease in navigability of channels.
Environmental Impacts
Eroded soil contains nitrogen, phosphorus, and other nutrients, and when
carried into water bodies, triggers algal blooms that reduce water clarity,
deplete oxygen, lead to fish kills, and create odors.
Erosion of stream banks and adjacent areas destroys streamside
vegetation that provides aquatic and wildlife habitats.
Excessive deposition of sediments in streams smothers the bottom fauna,
seals stream beds, and destroys fish spawning habitat.
Turbidity from sediment reduces in-stream photosynthesis, which leads to
reduced food supply and habitat.
Turbidity increases the amount of sunlight absorbed in water, raising
stream temperatures.
Suspended sediment abrades and coats aquatic organisms.
Erosion removes the smaller and less dense constituents of topsoil which
hold nutrients that plants require for healthy establishment. The remaining
subsoil is often hard, rocky, infertile, and droughty; thus making
reestablishment of vegetation difficult.
Eroded soil in aquatic environment reduces both the kinds and the
amounts of organisms present in an aquatic system.
The loss of amenities associated with the above impacts is shown in the following
few examples.
1-8
Q GUIDELINES ON LD-P2M2
Example 1(a):
Effects of
sediment in the
river seen in this
water treatment
plant, where the
polluted river
serves as the raw
water source for
the plant. Root
cause of reservoir
pollution tracked
back to the plant
intake point,
where incoming
water quality
exceeded the
acceptable limits.
Example 1(b):
The plant had to
be shut down for
days to facilitate
cleanup of its
storage reservoir.
1-9
Q GUIDELINES ON LD-P2M2
Example 2:
Heavily polluted
reservoir of a
hydroelectric
plant, diminishing
the reservoir’s
design storage
capacity.
Example 3:
Loss of use of
rivers as an
amenity due to
high loads of silt
in river waters.
Example 4:
Another heavily
polluted river due
to eroded
sediment.
1-10
Q GUIDELINES ON LD-P2M2
Example 5:
Heavy
sedimentation to a
river located
adjacent to a
massive land
clearing site.
Example 6:
Temporary loss of
use of a public
road due to
sediment being
carried onto the
road surface.
Example 7:
Another polluted
river? No, this is a
road under heavily
sediment-laden
runoff after a
rainfall. Evidently,
the road acted as a
drainage path to
transport sediment
to the drainage
system.
1-11
Q GUIDELINES ON LD-P2M2
Example 8:
Disruption to road
users due to highly
silted runoff from
an adjacent
hillside.
Example 9:
Gradual
encroachment of
silt materials onto
residential areas.
Example 10:
Concentrated
discharge into
storm water
system will cause
blockage to the
drains and costly
to maintain.
1-12
Q GUIDELINES ON LD-P2M2
Example 11:
Indiscriminate
discharge of
construction
wastewater
(concrete
washout) expected
to damage the
adjacent
environment.
Impacts of erosion and sedimentation which affect populated areas will inevitably
raise the public interest and awareness, particularly if private properties are
damaged or in even more drastic cases, fatalities or injuries resulted from these
impacts. This heightened interest and awareness of the public poses the pressure
for more effort in controlling the current construction practices in dealing with
erosion and sedimentation. Additionally, the continued deterioration of the river
quality in Malaysia due to eroded soils from project sites is receiving a great
amount of attention from the relevant authorities.
The selected examples below highlight the frequent concerns faced by the public
in recent times.
Example 1(a):
A significant
flood event due
to runoff
carrying eroded
soils from
upstream
catchment of
town, affecting
residents in the
affected areas.
1-13
Q GUIDELINES ON LD-P2M2
Example 1(b):
Another part of
the same town
above subject to
flood waters,
causing major
disruption to
affected road
users.
Example 2:
Another
township under
flood waters
knowingly due
to serious cases
of erosion at the
upper
catchment of
the area,
resulting in
large scale
property
damages.
Example 3:
Discharge of
sediment-laden
waters from a
construction in
a urban area,
causing major
disruption to
affected road
users.
1-14
Q GUIDELINES ON LD-P2M2
Example 4:
Discharge of
sediment-laden
waters to a
major roadway,
causing major
disruption to
road users.
Example 5:
Discharge of
sediment-laden
waters from an
open
construction
site, resulting in
dangerous road
conditions.
Example 6:
Another
example of
dangerous road
conditions due
to sediment-
laden runoff.
1-15
Q GUIDELINES ON LD-P2M2
Example 7(a):
Significant
mudflow
causing major
damages to
properties.
Example 7(b):
More photos of
damages to
public
properties.
Example 7(c):
More photos of
damages to
public
properties.
Many economic impacts of erosion and sedimentation are hard to quantify. How
can a dollar value be assigned to loss of aquatic habitat or diminished water
clarity? Other impacts may be readily quantified, for example the cost of dredging
and disposing of the accumulated sediment in a silted-up reservoir. Other
economic impacts include the following:
b. The cost of building new reservoirs to replace lost reservoir capacity is high.
Increasing land values and lack of available sites are making this alternative
much less feasible.
d. Erosion severely diminishes the ability of the soil to support plant growth.
To restore this ability is costly.
e. Listing additional wildlife as endangered species increases time and fees for
permitting, design, and construction in the affected watersheds. Some costs
are directly assessed to specific projects while many other costs are
distributed statewide by spending additional monies for habitat restoration.
One of the key project concerns driving the need for LD-P2M2 is that currently,
projects are typically awarded before the specific issues potentially faced by
construction projects in dealing with erosion and sediment in their sites have been
adequately studied during the planning stage. As a result of this, provision for
adequate budget or requirements for the necessary mitigation measures to be
implemented on site could not be timely included into the tendering process by the
project proponent nor incorporated into the Contractor’s construction budget.
With LD-P2M2, which is required to be resolved as early as during the submission
of EIA report, this should allow sufficient time for the appropriate resources
needed for the pollution prevention and mitigation measures to be included into
the tender documentation.
Also related to project concerns, the issues of erosion and sediment have been
observed and documented over the years by DOE based on inspections of the
various projects in Malaysia. In 2011, when DOE first published the “Manual
Panduan Pemeriksaan BMPs (Best Management Practices) Untuk Kawalan
Hakisan and Sedimen”, the top ten non-compliances of erosion and sediment
control were identified as follows:
In the recent years, the above list has expanded to include a more comprehensive
account of the overall issues resulting in erosion and sediment non-compliances on
project sites, including the following:
Well established BAT for addressing erosion and sediment are currently available
in the market but it is fair to say that the full potential and benefits of them are not
being fully taken advantage of in most of the project sites. Chapter 2 of this
Guidelines will present a comprehensive list of these BAT, which are covered
under one of more of the following categories:
The following discussion gives some insight on how the current practice of
involving JPS’ ESCP into EIA projects may also play a role in driving the
direction for LD-P2M2. First of all, it should be reiterated herein that the LD-
P2M2 Document is required to be submitted as part of the EIA Report for DOE’s
approval, and subsequently to be submitted together with the Environmental
Management Plan, and to be stipulated in the EIA’s Conditions of Approval
(COA).
For EIA projects, even though the Consultants are now not required to attach the
ESCP with the EIA Report submission (as was done previously) but rather to
include the LD-P2M2 Document with the submission, the Department of Drainage
1-20
Q GUIDELINES ON LD-P2M2
and Irrigation (JPS) can still require an ESCP to be submitted for an EIA project, if
it so desires, through the common practice when the project application is made by
the Project Proponent to the One Stop Centre (OSC) of the local government. For
non-EIA projects, JPS continues the same practice for the Project Proponent or
Contractor to submit an ESCP for their project, and such ESCP is enforceable by
JPS and/or the Local Authority (PBT).
With the LD-P2M2 document being submitted as part of the EIA Report, DOE
will have a control over the document pertaining to the erosion and sediment
control measures and to hold project parties accountable for inaction on site for
EIA Projects. The LD-P2M2 document is formulated at the EIA stage and
implemented at the construction stage, and one of the main emphases of LD-P2M2
is on the progressive states of the site and interim BMPs are expected to be
highlighted. Where site conditions or construction methods change significantly
on site, the Contractor is required to update the previously approved LD-P2M2
document (prepared at the EIA stage) for resubmission to DOE. The resubmission
of the LD-P2M2 document directly to and for DOE’s approval allows the
Department’s project officers to be informed of the site changes more
expeditiously, and thus enhancing the effectiveness of DOE’s site inspections.
In a way, the implementation of LD-P2M2 may somewhat relieve the load on JPS’
manpower requirements to review iterative resubmission of ESCPs (if the
Contractor upholds his commitment to revise the approved ESCP in view of
changing/evolving site conditions) for the same project. With LD-P2M2, this also
reduces DOE’s dependence to summon JPS’ technical personnel to be witnesses in
proceeding case.
Part of the LD-P2M2 substances are based on the Guidelines of Erosion and
Sediment Control published by JPS, e.g., the fundamental, principle, standard and
specification of erosion and sediment control measures. As such, the gathered
technical information during the EIA study and reported under the LD-P2M2
document will definitely be useful for designing the ESCP. In the event of an
ineffective LD-P2M2 document, the effective ESCP can be used instead, by
requesting the Project Proponent to revise the LD-P2M2 document according to
the effective one. Lastly, with LD-P2M2, this will avoid issues of competency or
certified DOE inspector to inspect project with reference to ESCP, since the DOE
inspectors are not certified to the technicality of the ESCP which is designed by
Professional Engineer (PE).
The birth of all projects almost always commences from the same starting point, i.e., the
Project Proponent’s need or desire for a “product”. “Project Proponent” in this context
can be a private entity or government institutions or semi-government bodies. In the case
1-21
Q GUIDELINES ON LD-P2M2
of a civil engineering project, this “product” can be in many forms, such as an entirely
new development project (either residential, commercial or industrial), utility facilities
(such as sewage treatment plants, water treatment plants, power stations, major drainage
or sewerage schemes, etc.), agricultural projects (such as oil palm plantation, etc.), new
infrastructural networks (such as highways, bridges, canals, airports, ports, etc.), and so
on. Most, if not all, of these projects (requiring an EIA study to be conducted) will have
to go through a typical flow as shown in Figure 1.6.
With regard to the preparation of the LD-P2M2 Document, the EIA Guidelines (issued by
DOE in 2016) stipulates that this document shall be submitted as part of the EIA Report,
as covered in the following clauses in the EIA Guidelines:
The process flow of the LD-P2M2 Document and its usage is illustrated below in Figure
1.7, noting the essential key points as follows:
1
To be replaced by this Guidelines
1-22
Q GUIDELINES ON LD-P2M2
The following Figure 1.8 and Figure 1.9 illustrate “physically” where the LD-P2M2 Document
will be needed. In the first figure, it shows that the initial LD-P2M2 Document shall be
formulated during the EIA report stage, and to be submitted as part of the overall EIA report to
DOE for approval. It is acknowledged that at this point in time, some of the information may not
be available to the PP and EIA Consultant (such as Contractor’s work methodologies, resources
involved in the works, etc.) and some parts of the LD-P2M2 Document may indeed be written
based on “best practices” or the preparer’s experience. In such instances, it is advisable to include
the assumptions used for preparing these parts of the document. On the other hand,
notwithstanding the above, there will be various information that will be made available in the
course of the EIA study that will be useful for preparation of the LD-P2M2 Document, such as,
data on topography, climate, project components, soil information, sensitive receivers, to name a
few. The initial LD-P2M2 Document prepared using these data provides a large degree of
information to the Project Proponent and his engineering consultants in terms of the associated
P2M2s that are anticipated as well as their possible costing.
1-23
Q GUIDELINES ON LD-P2M2
Following the approval of the EIA report and issuance of the EIA Conditions of Approval
(COA) by DOE, an updated LD-P2M2 Document will be submitted together with the
EMP to DOE for approval. Typically, at this point in time, the PP or EIA Consultant
would have received more detailed information on the project works to enable the LD-
P2M2 Document to be refined or updated with new information. As shown in Figure 1.8,
other windows for revising the currently LD-P2M2 Document still exist even after the
contract has been awarded to the Contractor.
One can start to appreciate the flexibility of this LD-P2M2 process, in that DOE regards
the document (even after it has been approved) to be a “live” one (just like the EMP) and
can be subject to refinement and upgrade when justifiable. As such, the Project Proponent
or the Contractor are given the flexibility to revise the approved LD-P2M2 Document to
suit the evolving site conditions (if previously not accounted for) or change in design or
construction methodologies. The resubmission of the revised LD-P2M2 Document allows
DOE’s project officers to be informed of these site changes more expeditiously, and thus
enhancing the effectiveness of DOE’s site inspections.
1-24
Q GUIDELINES ON LD-P2M2
In view of the above discussion, it is recognized that in order to tackle the problems of
erosion and sediment at project development sites, there is a need to gain further
understanding of various specific related topics, namely, the fundamentals of erosion and
sediment, best management practices (BMPs) and their application, essence of land
disturbing activities, phases of construction, to name a few.
In this regard, the framework for this Guidelines covered the domains of the “5-Ws”
(What, Why, Where, Who and When) and “1-H” (How) of the LD-P2M2 document to
include the following objectives:
Chapter 1: Introduction
Chapter 2: Fundamentals of Erosion and BMPs
Chapter 3: Identifying Land Disturbing Activities
Chapter 4: Identifying Phases in A Project
Chapter 5: Project Implementation Techniques
Chapter 6: Monitoring, Reporting & Documentation
2-1
GUIDELINES ON LD-P2M2
CHAPTER 2
This section presents a review of the current legal framework within which the
construction industry in Malaysia is working under, with regard to the prevention of
erosion and sedimentation in their projects. In addition, some related existing guidelines
are also discussed to explore the limitations, constraints and opportunities in these
guidelines on the process for prevention of erosion and sedimentation, to be addressed in
the Guidelines.
Section 34A of the EQA stipulates that an environmental impact assessment (EIA)
shall be conducted by a qualified person for any prescribed activity and submitted
to the Director General for his approval. The EIA report shall be undertaken in
accordance with the guidelines as prescribed by the Director General, and shall
contain “the proposed measures that shall be undertaken to prevent, reduce or
control the adverse impact on the environment.” This Section further stipulates
that the person carrying out the prescribed activity “shall provide sufficient proof
that the conditions attached to the report (if any) are being complied with and that
the proposed measures to be taken to prevent, reduce or control the adverse
impact on the environment are being incorporated into the design, construction
and operation of the prescribed activity.”
Based on the review of the existing legal framework currently being implemented
in Malaysia in relation to the pollution of the environment due to erosion and
sediment discharges, it is evident that sufficient mechanisms are in place by the
Director General to prevent and monitor the event of environmental pollution of
this nature from any construction sites or premises. This is more pronounced for
those prescribed activities whereby an EIA report shall be required to be approved
prior to commencement of the site works and to adequately address the means to
prevent, reduce or control the possibility of environmental pollution due to erosion
and sediment discharges to the inland or Malaysian waters.
Pursuant to Part IV, Section 34A of the above Act, pertinent excerpts from the
“Environmental Impact Assessment Guideline in Malaysia, 2016” which are
2-2
GUIDELINES ON LD-P2M2
“The EIA procedure, a preventive strategy of the DOE also needs to embrace
the environmental mainstreaming and self-regulation goal in order to enhance
its effectiveness in mitigating the adverse impacts from development projects on
the environment at every stage of the EIA procedure. Self-regulation culture in
EIAs means that the Project Proponent will be charged with full responsibility
and accountability for taking environmental friendly options and instituting
effective pollution prevention and mitigation measures (P2M2) and self-
demonstration of regulatory compliance of the EIA procedure at all stages of
project implementation.”
“Allocating sufficient funds for all steps in the EIA process and every stage of
project planning and implementation with itemized budget required for water
quality monitoring, air quality and noise monitoring, for comprehensive site
survey and investigation of the specific existing site conditions, for
implementation of Environmental Management Plan (EMP) including
temporary pollution prevention and mitigation measures (P2M2). P2M2 shall
be those which can be described as state of the art technologies, best available
technologies (BATs), or industry best practices.”
The above is in line with the intent of the Act in an attempt to address erosion and
sediment issues in the construction industry. In essence, the key objectives of
LD-P2M2 are not distinctly different from DOE‟s previous erosion control and
sediment documents or requirements. The topic on soil erosion and siltation
prevention and control is not a new subject in DOE, with various guidelines
2-3
GUIDELINES ON LD-P2M2
issued on the very subject. In fact, DOE has kept up with the evolution of this
subject, which culminated in the issue of various document and articles, as
discussed in the following sections.
2.1.3 Guidelines for Prevention and Control of Soil Erosion and Siltation in
Malaysia, DOE, 1996
This document was prepared after an overall review of the first document on
erosion and siltation was issued by DOE in 1978, namely the “Guidelines for
Prevention and Control of Erosion and Siltation (also referred to as ANNEX I), as
well as the review of its latter version, the “Guidelines for Prevention and Control
of Erosion and Siltation (also referred to as ANNEX III) issued by DOE in 1992.
The main purpose of the 1996 Guidelines is to “provide a checklist of existing
information pertaining to soil erosion and sedimentation so that developmental
activities can be planned and executed in a judicious manner with minimum
degradation”1.
It is also acknowledged in this document that the Guidelines “are not a substitute
for professional experience, training and local knowledge”.
Strength of Document: The 1996 Guidelines for Prevention and Control of Soil
Erosion and Siltation in Malaysia serves as a useful document to provide some
background information on the process of erosion and sedimentation typically
encountered in projects undertaken in Malaysia. It also goes as far to generically
cover the possible erosion risks for the “List of Prescribed and New Activities”
under the Environmental Quality (Prescribed Activities) (Environmental Impact
Assessment) Order 1987. Additionally, it also outlines the procedures in preparing
an Erosion and Control Plan (ESCP) and provides a variety of pictorial examples
of drainage control measures, erosion control measures and sediment control
measures. Last but not least, the 1996 Guidelines also presented some factors to
be considered during the costing of erosion control measures.
Gap Analysis: Although the 1996 Guidelines for Prevention and Control of Soil
Erosion and Siltation in Malaysia represent a good overall technical document to
address erosion and sedimentation matters, it could be perceived to be more suited
for persons who already possess professional experience, training and local
knowledge in the fields of design and construction. The Guidelines acknowledges
1
Guidelines for Prevention and Control of Soil Erosion and Siltation in Malaysia, DOE, 1996
2-4
GUIDELINES ON LD-P2M2
2.1.4 Certified Erosion, Sediment and Storm Water Inspector Manual, US Version,
EnviroCert International, Inc., November 2011
Strength of Document: As the title of this document suggests, the Manual is more
tailored for personnel who are involved in the inspection or provision of erosion,
sediment and stormwater mitigation measures on a project site. It provides
detailed procedures for an inspector to be prepared before, during and after site
inspection on matters related to erosion. The CESSWI Manual also included a
variety of proven BMPs covering site planning and management, erosion controls,
sediment controls, runoff controls, good housekeeping/materials management, and
post-construction management.
Gap Analysis: Although the 2011 CESSWI Inspector Manual represents a useful
handbook for persons involved in the inspection of a site pertaining to erosion and
sediment pollution, the document does not cover the earlier stages of the project,
i.e. the consideration of erosion during the planning and design stages of the
project. Additionally, limited discussion is found in the Manual to address the
progressive state of a project site and how to address these changing site
conditions in erosion and sediment controls. Another important point to note is
that this Manual has been written within the context of the US regulation on
environmental protection.
2-5
GUIDELINES ON LD-P2M2
2.1.5 Erosion and Sediment Control Planning and Design Manual, North Carolina
Department of Environment and Natural Resources
This document was prepared as a cooperative effort between the North Carolina
Sedimentation Control Commission, North Carolina Department of Environment
and Natural Resources and the North Carolina Department of Transportation, to
cover effectively all land-disturbing activities (except agriculture and mining) in
North Carolina.
Gap Analysis: It is noted that this Manual has been written within the context of
the US regulation on environmental protection. Although certain aspects of the
standards and specifications may be reviewed for its appropriateness to be used in
Malaysia, much of the practices have been written for USA application. In
addition, the North Carolina appears to be tailored for the use of persons with
engineering background. One of the important factors that need to be considered
during the formulation of the Guidelines on LD-P2M2 will be that it should be a
user-friendly document and easily understood also by persons without engineering
background.
2.1.6 Chapter 12 Erosion and Sediment Control, Manual Saliran Mesra Alam
(MSMA), JPS, 2012
This chapter was prepared by the Department of Irrigation and Drainage (JPS) to
provide relevant guidelines and procedures for reduction and control of erosion
and sedimentation during project development in order to minimize land, water
quality and environmental degradation.
Design Guidelines for Erosion and Sediment Control BMPs; and Preparation of
Erosion and Sediment Control Plan (ESCP).
Gap Analysis: Under the subsection 12.5.4.1 Site Inspection & Monitoring in this
Chapter 12, it is mentioned that the monitoring programme should consist of
regular inspection to determine, amongst others, “changes in drainage patterns,
whereby all runoff whether disturbed or natural flows should be ensured to be well
managed, including those runoff arising from changes in drainage patterns due to
earthwork or to other unanticipated manner”. Additionally, it is also noted that
during the course of construction, “unexpected schedule changes, phasing changes,
staging area modification, off-site drainage impacts, and repeated failures of
design controls” must be made known and “the ESCP revised accordingly”.
Despite the above being mentioned, there is however limited elaboration on how
the above issues should be mitigated during the planning and design phases, i.e.,
prior to commencement of construction works. Additionally, this document does
not include appropriate BMPs that are endorsed by any parties. During the
formulation of the Guidelines on LD-P2M2, this gap will need to be addressed by
inclusion of topics that deal with CPM as well as understanding construction
sequences and drawings.
2.1.7 Summary
It is seen from the above that although much has been written on the subject of
erosion and sediment in the construction practice, there is still a gap on how issues
such as “unexpected schedule changes, phasing changes, staging area
modification, off-site drainage impacts, and repeated failures of design controls”
should be mitigated during the planning and design phases, i.e., prior to
commencement of construction works. There is also limited discussion to address
the progressive state of a project site and how to address these changing site
conditions in erosion and sediment controls. Although some of the literature
acknowledges the importance of maintaining the robustness of an erosion and
sediment control programme, they however do not provide further illustrations or
examples on how this programme evolves with the construction sequence and
activity scheduling. In this regard, the LD-P2M2 seeks to take into account the
2-7
GUIDELINES ON LD-P2M2
above gaps in order to minimize the impacts of erosion and sediment in our
construction sites.
There are currently numerous literatures that discuss in detail the phenomena of erosion
and sedimentation, and it is not the intention of this Guidelines to reproduce such
discussion herein. Nevertheless, for the purposes of completeness, the description for
some of the commonly used terms throughout this Guidelines on LD-P2M2 is included
below. In the context of this Guidelines, erosion caused by snow and wind is not
considered since it is not relevant in Malaysia.
2.2.1 Erosion
Raindrop Erosion
Raindrops detach soil particles and splash them
into the air. These detached particles are then
vulnerable to stormwater runoff.
Sheet Erosion
Rill Erosion
As the flow changes from a shallow sheet to a
concentrated flow, the velocity and turbulence of
the flow increases. The energy of the
concentrated flow is able to detach and transport
soil particles. This action begins to cut into the
soil mantle and form tiny channels. Rills are
small, but well-defined channels that are only a
few inches deep. Rill erosion
Gully Erosion
Rills gradually come together to form gullies.
Whereas rill erosion can be eliminated or
repaired fairly easily, gully erosion requires
major work to regrade and stabilize
Gully erosion
Channel Erosion
2.2.2 Sedimentation
Wind and water pick up soil particles to deposit them elsewhere. This is the
process of sedimentation. In a river, sediment moves slowly downstream
especially during high flows following rainfall. This can cause property damage,
increase maintenance costs, impair habitat and water quality.
This is probably one of the more significant contributions to erosion and sediment
issues on site. More often than not, the expectation and requirement on dealing
with land disturbance activities for an EIA project are not adequately or clearly
expressed between Project Proponent and Contractor, and even within the
Contractor‟s internal project team. In this regard, the LD-P2M2 Document, to be
prepared in the early stage of the project, namely during the EIA stage, will serve
as a reference document for all project parties involved to understand and identify
site constraints, areas of concern, problem areas, designated and potential
discharge points of runoffs, and to develop early planning on how, what, why,
where and when to effectively implement the pollution prevention and mitigation
measures at the development site. The LD-P2M2 Document also seeks to
standardize the information to be highlighted, by including the minimum standard
requirements of pollution prevention and mitigation measures (as discussed in
Chapter 5) that will be adopted, applied, and implemented in the process of
carrying out land disturbing activities at the development site for all EIA projects.
Particularly with regard to this issue of coordination & communication, the
relevant minimum standard requirements are generally covered under the
following areas:
2-11
GUIDELINES ON LD-P2M2
Traditionally, the project parties are generally reactive towards the issues of
erosion on their project sites. At site, deficiency or non-compliances may be
spotted and called out by the site management but the question is: how many times
are these instructions actually attended to or followed through? Although there
may be the element of “command” from the site management but it would appear
a lack of “control” to see through the “command”. Many times, actions are only
taken to address these issues only after a citation is issued by the authorities from
site inspection or a public complaint has been received. In this regard, the LD-
P2M2 is in line with DOE‟s proposed self-regulation policy requiring all parties
(project proponent, consultants, contractors and environmental officers) to increase
their vigilance and efforts to address erosion and sediment issues much earlier
before the site activities commence, and to prevent these issues from occurring
during the project. The minimum standards requirements of P2M2 in this regard
are covered by the following clause:
Conventionally, the Contractor‟s work program is more concern with “getting the
work done” and even when the program does include reference to tasks dealing
with erosion and sediment, the extent of such activities is either with limited
details or too general to allow a more precise estimate of the site events to pre-
empt erosion and sediment from occurring. In this regard, the LD-P2M2
Document seeks to breakdown the project into a dedicated work breakdown
structure (WBS) which focuses more on land disturbance activities that are likely
to generate erosion and sediment. This allows a supplementary work program to
be prepared to predict with a higher level of confidence the types and details of
application of P2M2s into the project. The minimum standards requirements of
P2M2 in this regard is covered by the following clause:
Similar to the above, the Contractor conventionally is more interested to get to the
end point, and this resulted in simultaneous work activities taking place on the site
2-12
GUIDELINES ON LD-P2M2
and in many cases, with little or poor planning towards addressing erosion and
sediment issues. In this regard, the concept of LD-P2M2 puts the onus on all the
project parties to conduct their construction activities in a more systematic manner,
particularly on land disturbing activities, so as to have a better control over the
potential effects of these activities. Again, this issue is covered by the minimum
standards requirements of P2M2 relating to Schedule of Phasing, Staging and
Sequencing.
Conventionally, the lack of project construction scheduling to cater for all major
land-disturbing activities which include work zones, phasing of construction
within the work zones, staging and sequencing within the phases of construction
that coincides with the installation of P2M2s represents a major reason for the
issues of erosion and sediment in our construction practice. In this regard, the
concept of LD-P2M2 which emphasizes one the minimum standards requirements
of P2M2 relating to Schedule of Phasing, Staging and Sequencing attempts to
overcome this issue.
Method Statements are commonly used in construction projects, and most times,
they are a “must”. However, the current practice in Malaysia focuses primarily on
“technical” method statements that are more concerned with the methodologies to
complete the tasks to arrive to the final products, and limited efforts have been
expanded into producing “environmental method statements”. In this regard, the
LD-P2M2 Document seeks to include environmental method statements which
target those tasks that are needed throughout the land disturbing activities through
the implementation of the “minimum standard requirements” of pollution
prevention and mitigation measures. The minimum standards requirements of
P2M2 in this regard is covered by the following clause:
This issue is somewhat along the same line of the above issues for work
programme, scheduling and activities, but also extends to the lack of planning in
terms of management of the site from the perspective of its surrounding
environment. In LD-P2M2, one of the basic principles emphasizes integration of
project design with site constraints, which requires careful planning of site
management and implementation of pollution prevention and mitigation measures.
During implementation, the LD-P2M2 Document shall be used as a reference
document especially for the Environment Officer (EO) to understand and identify
2-13
GUIDELINES ON LD-P2M2
Again, another long time “mistake” committed by major projects which involve
extensive land disturbing activities is in the lack of project staging and phasing,
which ultimately resulted in large tract of land cleared of its natural vegetation and
suffering the consequences of erosion and sediment issues. this regard, the LD-
P2M2 Document seeks to focus on ways to parcel the project implementation into
phases to ensure the amount and duration of soil exposed (from the land disturbing
activities) to erosion is reduced as much as practicable at any one time by
implementing and maintaining the suitable BMPs in coordination with the
sequence of construction activities, as required as one of the minimum standards
requirements of P2M2 relating to Schedule of Phasing, Staging and Sequencing.
The lack or “wrong” work sequence executed on site will inevitably lead to
erosion and sediment control issues, which sometimes render the problem too
difficult or very costly to be remedied. In this regard, the LD-P2M2 Document
seeks to identify the respective work sequence in tandem with project phasing so
that the relevant project parties are clear on how the project activities should
proceed in the right order, and the necessary P2M2s to be implemented at any
particular point in time during the site works. The concept of LD-P2M2 which
emphasizes the minimum standards requirements of P2M2 relating to Schedule of
Phasing, Staging and Sequencing attempts to overcome this issue.
The worst thing which can happen during a river/stream diversion works is the
lack of planning and foresight given to potential erosion and sediment issues. Once
the existing river/stream has been rerouted to the diversion channel, nothing
effective much can be done to the now “live” river/stream which will continuously
carry eroded materials to the downstream side. In this regard, the LD-P2M2
Document seeks to include the appropriate environmental method statements
through the implementation of “minimum standard requirements” covered under
the following clause:
The lack of resources being a reason for why BMPs are not provided or installed
should not be an issue in the future, by instituting that the LD-P2M2 Document is
a legal pledge to be made by the Project Proponent to take efforts, measures,
actions or due diligence in accomplishing the overarching goal of protecting the
environment and in mitigating the environmental impact in the process of
implementation of the proposed development. As a result, the PP shall be
responsible for the implementation of the LD-P2M2 which shall incorporate the
P2M2s identified to be installed at the land disturbing development areas into the
design, construction and operation stage of the development project as stipulated
in Section 34A (7) of the EQA.
2.3.14 Issue of cost and benefit analyses (double handling and timeline)
Although the BSI British Standards BS 6031 2009: Code of practice for
earthworks is almost always included in the contract Specifications for most civil
engineering project that would involve extensive or significant land disturbing
activities, the physical practices encountered on project sites at times do not
comply with the guidelines, recommendations and even requirements as stipulated
under the code. In this regard, Chapter 4 of this Guidelines will recapture the
relevant excerpts from BSI British Standards BS 6031 2009: Code of practice for
earthworks on erosion and sediment controls for reference.
The key problem with the above issue is that whilst the work teams are basically
complete to deal with the permanent works construction, no one is basically tasked
to address erosion and sediment issue which will inevitably occur during their
works. Even the Stabilization Team is likely to be focussing on the „permanent‟
stabilization as required in the contract drawings and specification. In this regard,
the LD-P2M2 which emphasizes on Schedule of Phasing, Staging and Sequencing,
and environmental method statements shall clearly show the need for
implementation of temporary BMPs.
Changes in project design and construction methods during the execution of the
construction works are not uncommon and typically accepted, due to sometimes
unforeseen circumstances on the site or late add-ons by the Project Proponent.
That is why it is important to have a LD-P2M2 Document that is in-place at the
start of the contract works to document the planning and proposed implementation
of the P2M2 based on the original intent of the Project Proponent‟s design. As
shown later in this chapter, the LD-P2M2 Document will be subject to being
updated as necessary, particularly to address design changes and evolving site
conditions. In any case, the Standards and Specifications for P2M2s will remain to
be consistent through the change process, whereby it is stated under the minimum
standards requirement that all P2M2s shall be designed, constructed, installed, and
maintained in accordance with good engineering practices and applicable design
specifications, and that their application onsite shall be in accordance with the
various standards and specifications of the Department of Irrigation and Drainage
(DID), amongst others.
2-16
GUIDELINES ON LD-P2M2
2.3.18 Issue of erosion and sediment control measures designer/preparer not the
supervising consultant at jobsite
In this regard, all activities subject to EIA Order, 2015 which involve land
disturbing or site preparation activities are required to prepare a LD-P2M2 as part
of the EMP submission requirement, and the LD-P2M2 Document is to be used as
a reference document especially for the Environment Officer (EO) to understand
and identify site constraints, areas of concern, problem areas, designated and
potential discharge points of runoffs, and to develop early planning on how, what,
where, why, and when to effectively implement the pollution prevention and
mitigation measures at the development site. To this end, the EO refers to the
person who has been certified by the DOE and officially appointed or engaged by
the PP to be responsible for environmental performance of the project.
2-17
GUIDELINES ON LD-P2M2
The cumulative effect of all or some of the issues discussed above taking place
during the pre-construction and/or construction stage of a project will ultimately
result in BMPs not installed or implemented on site. In addition to the minimum
standards requirements of LD-P2M2 already discussed above, the following
standards requirements are also needed to be stipulated in the LD-P2M2
Document:
Construction Markers
Stabilized Construction Entrance
Stream/drainage way/waterway/watercourse buffers
Perimeter Control
Sediment Basin/Trap
Runoff Management
Temporary or permanent roadways
Temporary Stabilization
Stockpile Soil
Spoil Management Area (Disposal Area)
Dewatering practices
Active Treatment System (ATS)
Discharge
Corrective Actions
Graphical illustrations of the above issues relating to erosion and sediment are included in
Appendix A, whilst more details on the minimum standards requirements are presented in
Appendix B of this Guidelines.
The major parties who may either directly or indirectly contribute to or are
involved in the issues of erosion and sedimentation in an EIA project are shown
below.
2-18
GUIDELINES ON LD-P2M2
The Project Proponent (PP) is directly involved in these issues even though he is
not actually „executing‟ the works at the site, because by nature of his status, he is
the ultimate owner of the project. The PP is responsible for the preparation and
submission of the EIA report, and in this report, he has declared his commitment
to protect the environment and to keep any potential environmental pollution
resulting from the project implementation to the acceptable levels or as stipulated
in the conditions of approval of the approved EIA report. During project
execution, it is not uncommon for the PP to also appoint an Environmental Officer
(EO) to represent the PP in the monitoring and auditing the performance of
environmental compliance of the project. In turn, the EO needs to suitably
experienced and knowledgeable in all matters of environmental management,
including those related to erosion and sediment control, to properly monitor,
review, audit and correct the performance and effectiveness of the P2M2s
implemented on site.
In most cases, the PP will engage external and qualified Consultants to undertake
the EIA study, and to perform the other engineering tasks such as design and
construction supervision. Traditionally, the issues on erosion and sediment have
not been given much attention by these consultants, and one of the reasons being
limited construction information is available prior to the tender process. Another
likely reason may have been the misconception that dealing with erosion and
sediment issues on site should primarily be the responsibility of the Contractor
who is executing the works on site. Such perception will need to be changed soon,
because with implementation of LD-P2M2 along with self-regulation, all parties
2-19
GUIDELINES ON LD-P2M2
will be accountable for erosion and sediment issues, right from the EIA stage and
though the design and tendering process of the project.
Many times, the Contractor who is ultimately executing the project on site gets all
the blame if some untoward events occur relating to his site activities. To
overcome such adversarial relationship between the Contractor and Project
Proponents (and his Consultants), the LD-P2M2 can be used as a referencing
platform for all parties to at least have an overall understanding on the
requirements and expectation for addressing erosion and sediment issues. The key
to this common understanding of LD-P2M2 is the “minimum standard
requirements” on P2M2s that are expected to be implemented into the project.
Regulatory agencies such as DOE make frequent site inspections to EIA projects
during the implementation phase, either under a periodic inspection schedule or
adhoc site visits. The involvement of such agencies would primarily be to assess
the compliance (or non-compliance) to the COA of the approved EIA reports, as
well as to gain some general assessment of the site‟s overall environmental
performance via visual observations. Where non-compliances are encountered,
such agencies may consider to take further actions by virtue of the powers and
duties delegated to the agencies under the appropriate legislation.
It is not the intention of this Guidelines to recapture the theories behind the techniques in
quantifying and predicting soil loss from erosion process, and the resulting sediment
yield. However, a sample calculation worksheet for the above has been included in
Appendix D for reference to this aspect.
The focus of the LD-P2M2 is on the prevention, mitigation and control of the
discharge from the development area containing the major pollutant (suspended
solids) resulting from land disturbing activities. Controlling the sediment-laden
2-20
GUIDELINES ON LD-P2M2
runoffs means to control the discharge of other pollutants that may contain in the
sediment strains such as nutrients, bacteria, oxygen demanding materials, heavy
metals, petroleum hydrocarbons and synthetic organics. Everyone involved with
land disturbing activity shall make the most of the following basic principles in
every stage of development when implementing the pollution prevention and
mitigation measures:
c. Erosion and Sediment Control Planning and Design Manual issued by North
Carolina Department of Environment and Natural Resources2
2
Note: This manual can be accessed at https://enviro.doe.gov.my/
3
Note: This manual can be accessed at https://enviro.doe.gov.my/
2-21
GUIDELINES ON LD-P2M2
This section lists the suitable BMPs that are applicable for use in Malaysia,
consisting of five categories in different applications namely, Site Planning and
Management; Erosion Control; Runoff Control, Sediment Control; and General
Construction Control. A comprehensive collection of the examples for each of the
above categories is contained in Appendix E, as well as a presentation of a recent
initiative by the DOE to observe and study the effectiveness of certain BMPs in
the market.
Biomass
Preserve Existing Trees & Vegetation
Resource On-Site Rocks
Stockpile Topsoil
Salvage Trees (Translocation)
Establish Nursery
Diversion
Check Dam
Dissipator
Pipe Slope Drain
Temporary Cut-off Drain
Soil Retention
Flume / Chute
Rolling Dip
2-22
GUIDELINES ON LD-P2M2
Inlet Protection
Outlet Protection
Level Spreader
Riprap
Street Cleaning
Water Browser
Secondary Containment System
Sanitation
Concrete Washout
3-1
GUIDELINES ON LD-P2M2
CHAPTER 3
3.1 DEFINITION
The definition of “Land Disturbing” has been given in Chapter 3 to mean “any
project development that is subject to Section 34A EQA 1974” which can possibly
involve activities such as clearing of trees or vegetation, grubbing, stripping, grading,
raising or sloping of ground, excavating, trenching, filling, logging, storing of
materials and blasting. In other word, “land disturbing” also means any activity that
changes the physical conditions of land form, vegetation and hydrology, and during
the process, creates bare soil, or otherwise may cause erosion or sediment issues”. It
can be taken that land disturbing activities will involve any clearing, excavation,
grading or manipulation of the natural terrain which exposes soils to erosion hazards
or alters the natural condition of the site.
It should be cautioned that the term “land disturbing” should not be used loosely to
equate it to the words “earthwork” or “earthworks” as utilized in the practice of civil
engineering. In the civil engineering practice, the words “earthwork” or “earthworks”
have their own dedicated definition; in accordance with the BSI British Standards BS
6031:2009 Code of practice for earthworks, the meanings of these two terms are given
as below:
It is clear from the above definitions then that “land disturbing” in the context of this
Guidance Document therefore has a wider coverage than the typical “earthwork” or
“earthworks” typically used in civil engineering. Nonetheless, the British Standards
BS 6031:2009 does contain a variety of recommendations targeted to the planning,
design and construction of earthworks which are also pertinent to the subject of LD-
P2M2. A brief discussion of these relevant excerpts from the British Standards BS
6031:2009 is included in Appendix A.
The overall objective of this Guidance Document is to ensure that good quality LD-
P2M2 Documents are prepared by competent professionals and that the LD-P2M2s are
effectively implemented to mitigate and minimize environmental and pollution
impacts of the land disturbing activities. The LD-P2M2 shall incorporate the P2M2s
identified to be installed at the land disturbing development areas into the design,
construction and operation stage of the development project as stipulated in Section
34A (7) of the EQA. The P2M2s shall be effective in preventing, reducing and
controlling pollution as well as preventing non-compliant pollution discharges from
reaching any water bodies.
In a nutshell, site clearing consists of the activities to prepare the work area by
removing all trees, brush, buildings, and other objectionable material and obstructions
that may interfere with the construction works. In this regard, site clearing is also
considered to be a “pre-construction” activity.
Clearing shall consist of the cutting, taking down, removing, and disposal of
everything above ground level including demolition and disposal of structures.
Consequently, the clearing materials may include but not limited to organic wastes
such as trees, stumps, logs, bushes, undergrowth, long grasses, crops, and vegetation,
as well as inert wastes such as soil, demolished concrete structures, terraces, ditches,
etc.
3-3
GUIDELINES ON LD-P2M2
The following figures illustrate typical land disturbing activity involving site land
clearing. Unless otherwise specified, the depicted photos below are selected and
collated from DOE‟s database.
Prior to any land disturbing activity relating to site clearance, an initial assessment of
the site should be conducted to identify sensitive environmental areas or uses that
require protection, which may include:
Map of soil types together with their characteristics such as erosion potential, soil
test erodibility, soil hydrologic group, percentage of dispersible material (fine
clay) to determine the type and effectiveness of erosion and sediment mitigation
measures to be implemented;
Climate, weather patterns, rainfall data and stream flows, particular for the
purposes of avoiding land disturbing activities during the wet and rainy periods;
Construction programme showing sequences and timing of the key land disturbing
activities;
Anticipated excavation depth for the proposed land disturbing activity, to not only
make use of the data on soil characteristics on determining types and effectiveness
P2M2 but to also prepare for dewatering and treatment requirements;
Details of areas of cleared land at each stage of the development, and period of
time that each section will be exposed;
Description of adjacent areas, such as streams, lakes, residential areas, and roads
that might be affected by the land disturbance;
Calculation of stormwater flows within micro-catchments within the site, for each
stage of the project;
Location of stockpiles, haul roads and cuts, particularly for those work sites
located near sensitive areas such as rivers, public roads, other sensitive areas, etc;
and
Nature and location of works that will occur in near proximity, say 20m of a
natural waterway or other sensitive environmental area.
In view of the above illustrations and planning consideration discussed, the pertinent
basic principles as mentioned in Chapter 3 that need to be taken into account when
implementing the pollution prevention and mitigation measures for this land disturbing
activity include the following :
In addition, the minimum standards requirements that may be relevant to this land
disturbing activity include the following:
c. Construction Markers to physically mark on site to show the limit of the: site
clearance works from any drainage way/waterway/watercourse within project
site; areas not to be worked or disturbed, and buffer area or/and existing
vegetation meant for temporary or permanent preservation and for protection.
The construction markers can comprise fences, signs, tapes, flags or other
similar marking device.
f. Perimeter Control shall be first constructed and made operational before the
site clearing activities are executed, and may include filter or perimeter
berms, silt fences, sediment traps, sediment basins, construction entrance,
temporary diversion dikes or earth bunds and diversion drains that control
discharges from the site.
with gravels or stone pad and water bar to prevent sediment traction onto the
crossing that may potentially enter the stream.
q. Discharge of all runoff water from any land-disturbing activities such as land
site clearing shall be made through a sediment control P2M2 such as
sediment basin or trap or any other erosion and sediment controls which is
regarded as the designated final discharge(s).
3.3 GRUBBING
Land site clearing and grubbing sometimes may be undertaken in one operation.
Whilst site clearing essentially removes most of the aboveground natural or manmade
obstacles to prepare the work areas, grubbing on the other hand, provides for
additional preparation of the work area by removing the remaining stumps, roots, and
other obstructions which exist on or in the ground in all areas designated for grubbing.
The following figures illustrate typical land disturbing activity involving grubbing.
3-11
GUIDELINES ON LD-P2M2
Complete grubbing may not be required under embankments where the fill height
above natural ground, as measured to subgrade or embankment slope elevation,
exceeds a certain depth as specified in the contract specifications or drawings.
3-12
GUIDELINES ON LD-P2M2
However, where for those areas where a structure must be built, subdrainage trenches
are to be excavated, unsuitable material is to be removed, or where hillsides or existing
embankments are to be terraced, then complete grubbing is most certainly required.
Additionally, grubbing is important to the structural quality of the roadway and every
effort should be made to obtain a thorough job. Grubbing should be completed at least
in advance of grading operations.
The applicable minimum standards requirements for grubbing shall be similar to those
prescribed for land site clearing mentioned above.
3.4 STRIPPING
The following figures illustrate typical land disturbing activity involving stripping of
topsoil.
3-13
GUIDELINES ON LD-P2M2
As the main purpose of topsoil stripping is primarily to save the topsoil for future
reuse, stripping should be limited only those areas that will be affected by the
proposed construction or development. As mentioned above, the depth of normal
stripping of the topsoil should be to a depth of 150mm below ground level, or to the
bottom of the grassroots zone whichever is typically between 125 – 150mm, but
deeper depths may be satisfactory if the soil is suitable and undercutting is allowable
in locations such as buildings, water-impoundment structures, roadways, etc.
Appropriate sediment-control measures such as sediment barriers, sediment basins,
inlet protection, etc., should be in place before the topsoil is stripped. Stripping should
not be done on areas intended to support conventional, on-site effluent, disposal lines
(field lines).
g. Discharge of all runoff water shall be made through a sediment control P2M2
such as sediment basin or trap or any other erosion and sediment controls
which is regarded as the designated final discharge(s).
3-16
GUIDELINES ON LD-P2M2
3.5 GRADING
“Grading” typically occurs after land site clearing, grubbing and topsoil stripping, and
it involves the reshaping of the ground surface to provide suitable topography for
buildings, facilities, and other land uses; to control surface runoff; and to minimize soil
erosion and sedimentation, both during and after construction. The practice of grading
can be applied to existing topography which is required to be modified to prepare for
another land use. It can also be used to adapt proposed development to the existing
landscape to reduce the erosion potential of the site and the cost of installing erosion-
and sediment control measures. In some instances, other practices such as diversions
can be used to reduce the length of continuous slopes and reduce erosion potential.
The following figures illustrate typical land disturbing activity involving land grading.
A detailed plan should be developed for all land grading activities, to show the areas to
be disturbed, the areas of cut, areas of fill, and the finished elevation for all graded
areas. The grading plan should also indicate the means for protection of existing
vegetation where possible, especially around natural drainageways. Grading activities
should be scheduled to minimize the area disturbed at any one time during the
construction process. The plan should include provisions for stabilizing disturbed areas
immediately after final grading is completed. Provisions should also be made to
protect existing underground utilities.
Due to the similarity of the nature of this land disturbing activity to the precedent
activities including stripping and site clearing, albeit for different reasons, the
minimum standards requirements will also be quite similar, including the following:
Schedule of Phasing, Staging and Sequencing; Scheduled Site Meeting;
Construction Markers; Stream/drainage way/waterway/watercourse buffers;
Perimeter Controls; Sediment Basin/Trap; Runoff Management; Temporary
Stabilization; Stockpile Soil Management; Spoil Management Area (Disposal Area);
and Discharge.
3-18
GUIDELINES ON LD-P2M2
In simple terms, raising or sloping of ground consists of the activities to prepare work
areas which are connected or adjacent to one another but with differing platform
elevations. There are many reasons for creating platforms at different levels of which
one could be for architectural reason, but it is more likely they are more of functional
or engineering reasons. Regardless the reasons, to raise or slope the ground constitutes
a land disturbing activity, because the final platforms will need to be “carved out”
from the existing ground topography.
This land disturbing activity is likely to involve some of physical actions previously
covered for “land site clearing”, such as cutting, taking down, removing, and disposal
of everything above ground level including demolition and disposal of structures,
except that the raising or sloping of the ground will further involve more „cutting” of
the ground to form the raised platform or slopes. In this regard, raising or sloping of
the ground is also considered to be a “pre-construction” activity.
This land disturbing` activity is expected to generate a larger volume of inert materials
such as excavated soil, on top of some clearing materials.
The following figures illustrate typical land disturbing activity involving raising or
sloping of ground. Unless otherwise specified, the depicted photos below are selected
and collated from DOE‟s database.
3-19
GUIDELINES ON LD-P2M2
As indicated earlier, some form of land site clearing activities would have been
provided to the work site prior to the further raising or sloping of the ground, to form
the desired platform levels as per the construction drawings. Assuming planning
considerations have previously been given to the site clearing works, the consideration
that would be applicable to this subsequent land disturbing activity may include
further assessment of this particular works area to identify the specific sensitive
environmental areas or uses that require protection, which may include:
Soil types together with their characteristics such as erosion potential, soil test
erodibility, soil hydrologic group, percentage of dispersible material (fine
clay) at the particular earthwork areas to form the raised platforms or slopes,
so as to determine the type and effectiveness of erosion and sediment
mitigation measures to be implemented;
Since the velocity and flow rates of any potential surface runoffs from the
disturbed areas for this land disturbing activity could likely be high, because
of sloping grounds (compare to flatter ground for site clearing works only), it
will be important to avoid this land disturbing activity during the wet and
rainy periods;
Location of stockpiles, haul roads and cuts, particularly for those work sites
located near sensitive areas such as rivers, public roads, other sensitive areas,
etc; and
Nature and location of works that will occur in near proximity, say 20m of a
natural waterway or other sensitive environmental area.
3-22
GUIDELINES ON LD-P2M2
The incorporation of the pertinent basic principles for this land disturbing activity will
inevitably include the following minimum standards requirements:
to exposed areas that may not be at final grade but will remain unattended for
longer than fourteen (14) days.
k. Discharge of all runoff water shall be made through a sediment control P2M2
such as sediment basin or trap or any other erosion and sediment controls
which is regarded as the designated final discharge(s).
3.7 EXCAVATING
“Excavation” means the mechanical removal of earth material, whether the purpose is
to form a deep cavity for underground construction or a trench for utilities
laying. This land disturbing activity involves the process of moving earth, rock or
other materials with tools, machineries, equipment or explosives, and can include
earthwork, trenching, wall shafts, tunneling and basement works.
3-24
GUIDELINES ON LD-P2M2
The following figures illustrate typical land disturbing activity involving site land
clearing. Unless otherwise specified, the depicted photos below are selected and
collated from DOE‟s database.
Another form of specialized excavation works which also involves the removal of earth
from underground for the purposes of constructing foundation works is “borehole
drilling”. In this special type of excavation works, the dedicated equipment used for the
earthmoving is a rotary drilling machine, where a drill bit is attached to a length of
connected drill pipe. The drill bit will be made of tough metals such as tungsten, and as
the drill is rotated the bit grind up the rock. The drill fluids (sometimes bentonite is used
and also referred to as drilling mud) are circulated through the drill string into the
borehole and back to the surface and carries (flush) the broken pieces (cuttings)
upwards and out of the hole. This fluid also serves as a formation stabilizer preventing
possible cave-in of unstable sands or crumbly rock before the well casing or well screen
is installed. Furthermore, this fluid acts as drill bit lubricant. In general, bored piles offer
the most economical foundation as they can be constructed in a wide choice of
diameters, typically ranging from 300mm to 1800mm, and to depths of up to 70m.
3-26
GUIDELINES ON LD-P2M2
Assuming a bored pile diameter of 1500mm with a depth of 50m, an estimated 90 cubic
meter of excavated soil will be displaced from the bored location. This translates to
about 20 nos. of lorries to be used for transporting out these materials. The following
figures illustrate the typical land disturbing activity involving borehole drilling. Unless
otherwise specified, the depicted photos below are selected and collated from DOE‟s
database.
When planning for any excavation works from the perspective of erosion and sediment
control, it is important to remember that such land disturbing activity will always
likely to result in one or more of the following observations:
The process of excavating will dislodge the once stable ground soil and render the
soil materials to be in a “loosed” form which can be easily eroded or carried away
by surface runoff;
3-28
GUIDELINES ON LD-P2M2
The excavation works will create cavities or large holes in the ground whereby
after rainy events, accumulated water will need to be dewatered or pumped offsite
to allow works to continue. Often this water is contaminated with suspended
sediment so it is essential that its disposal should not contribute to water pollution;
During the boring activity, soil stabilisation agent such as bentonite as well as a
large amount of water is likely to be used, which will generate wastewaters during
the excavation process. These solid waste and wastewaters will need special
attention for their collection, temporary storage and treatment before disposal or
discharge off site.
In view of the above, appropriate BMPs are needed to address the above inevitable
erosion and sediment issues.
The pertinent basic principles to be taken into account when executing this land
disturbing activity include the following :
In addition, the minimum standards requirements that may be relevant to this land
disturbing activity include the following:
e. Perimeter Control shall be first constructed and made operational before the
excavating activities are executed to control discharges from the site.
installing plastic sheeting canvas along the channel with extend across the
side slope in combination with constructed check dams or sump slot checks.
berms, dikes, fiber rolls, silt fences, sandbags and gravel bags. All
anticipated runoff flowing from any disposal area shall be drained into a
sediment trap/basin prior to discharge.
3.8 TRENCHING
This is another form of land disturbing activity, and strictly speaking can be generally
grouped under the category of “excavating”, exhibiting similar works nature and
impacts to erosion and sediment. One of the key differences of trenching and the other
excavating works is that for the former, it may involve a more “linear-type”
construction, meaning the trench may extend for significant distance, while the other
excavating works have a more “stationary” footprint.
3-32
GUIDELINES ON LD-P2M2
During the course of trenching activities (as well as other excavation works), there
may occasions where river channel crossings or diversions may be involved. Even
though these watercourse works are not directly related to the trenching works, the
methodology of the construction may arguably be similar from the perspective that the
works are undertaken within a channel, i.e. constrained by two banks. Examples of
stream or river diversion and/or crossing activities are shown below.
3-33
GUIDELINES ON LD-P2M2
Another activity which is related to trenching and also the excavating land disturbing
activities is the dewatering process. Due to the cavities or holes in the ground and the
need to maintain a dry workable working area, dewatering is almost always required
especially when working during the rainy season or within areas with high water
tables. Wastewaters generated from this activity are usually highly contaminated with
sediment and high turbidity which need to be properly treated prior to discharge off
site to the nearest sensitive receivers such as rivers or streams. Photos illustrating the
dewatering process are given below.
Under the above categories of land disturbing activities, other than the erosion and
sediment issues, control of the associated wastewaters is also a concern. The
consideration for handling the solid part of the issue has been discussed previously in
the precedent section. Often the wastewater is contaminated with suspended sediment
so it is essential that its disposal should not contribute to water pollution. To remove
water from the work area, the pump intake should be kept as close to the surface of
pool as possible. Floating intakes should be used when the depth of water is sufficient.
Care must be taken to avoid pumping from the bottom of ponds, and constant
supervision is required during pumping operations to ensure this does not happen.
Treatment is required before discharging sediment-laden runoff to a natural waterway
or stormwater system.
3-36
GUIDELINES ON LD-P2M2
The minimum standards requirements that are applicable for the above various
activities include the following:
o. Discharge of all runoff water from any excavating activities shall be made
through a sediment control P2M2 such as sediment basin or trap or any other
erosion and sediment controls which is regarded as the designated final
discharge(s).
Similarly, the minimum requirements prescribed for the previous excavating are also
applicable for the current land activity of filling or embankment, including the
following: Schedule of Phasing, Staging and Sequencing; Scheduled Site Meeting;
Construction Markers; Stream/drainage way/waterway/watercourse buffers;
Perimeter Controls; Sediment Basin/Trap; Runoff Management; Temporary
Stabilization; Stockpile Soil Management; Spoil Management Area (Disposal Area);
and Discharge.
3-40
GUIDELINES ON LD-P2M2
3.10 LOGGING
Logging or “deforestation” involves the cutting down of mature trees in a forest and in
Malaysia, it is done for a variety of reasons, including: dam construction; housing
development; Oil palm plantations; roads and timber plantations.
In a way, logging as a land disturbing activity is quite similar to land site clearing
discussed in the early section of this chapter. The key difference between the two is
that for land site clearing, the key purpose of the activity is to prepare an existing land
for constructing a project, whilst for logging, the main interest is to remove the trees
for their economic values.
Although logging is not strictly a construction project, the impacts on erosion and
sediment cannot be underestimated, given that the coverage of logging activities can
sometimes be up to several hundred hectares at a single time. Noting from the above
illustrations, the pertinent basic principles as mentioned in Chapter 3 which are
mostly focused on civil construction projects, are also applicable for the logging
activity and need to be taken into account when implementing the pollution prevention
and mitigation measures:
The minimum standards requirements that may be relevant to this land disturbing
activity include the following:
e. Perimeter Control shall be first constructed and made operational before the
logging clearing activities are executed.
k. Discharge of all runoff water from any land-disturbing activities such as land
site clearing shall be made through a sediment control P2M2 such as
sediment basin or trap or any other erosion and sediment controls which is
regarded as the designated final discharge(s).
Throughout the duration of the project site activities, there will be numerous occasions
whereby construction materials will be stockpiled or stacked on site, including the
likes of biomass (trees and vegetation), excavated earth materials, rocks, topsoil,
construction materials such as sand, gravels, stones.
The stockpile location should be out of drainageways and traffic routes. Stockpiles
should not be placed on steep slopes where undue erosion will take place. Measures
should be taken to prevent erosion of the stockpiles, including mulching the stockpile
when it is left inactive for 14 days or longer; planting temporary vegetation when the
stockpile is to be inactive over 30 days; covering the stockpile with plastic whenever
the piles are small or any soil loss would damage existing buildings or facilities;
planting permanent vegetation when the stockpile use will be inactive over 12 months,
and in cases where the stockpile is small and will be removed in fewer than 14 days, it
may be more practical to use a sediment barrier than an erosion-control practice.
Additionally, locate stockpiles away from drainage lines to where they are protected
from wind. Wherever possible, minimise the number and size of stockpiles and keep
topsoil separate from underburden when stockpiling soil. Construct the stockpile with
3-45
GUIDELINES ON LD-P2M2
no slope greater than 2:1 (horizontal to vertical), and a less steep slope may be
required where the erosion risk is high. Lastly, hand water or install temporary
sprinklers to suppress dust from unstabilized stockpiles and batters, and finish and
contour any stockpiles located on a floodplain so as to minimise loss of material in a
flood or rainfall event.
f. Discharge of all runoff water from the stockpile areas shall be made through a
sediment control P2M2 such as sediment basin or trap or any other erosion
and sediment controls which is regarded as the designated final discharge(s).
3-46
GUIDELINES ON LD-P2M2
3.12 BLASTING
Besides dust and noise being the obvious environmental impacts from a blasting
activity, the loosening of soft soil materials, stockpile of blast materials and surface
runoff from the excavated faces are also key issues from the perspective of erosion and
sediment. For safety reasons, a large no work zone will be required to sterilize the
immediate surroundings of a blast zone. Designated areas for stockpiling the
excavated materials are also required.
The minimum standards requirements that are applicable for the above blasting
activity include the following:
a. Schedule of Phasing, Staging and Sequencing, to lay out the project schedule
for the key activities including survey of work zones and areas for P2M2s
implementation, identification of site and work zone boundaries, including
interfaces with surrounding projects or facilities and clearance extent;
implementation of BMPs and schedule; and undertaking blasting works;
j. Discharge of all runoff water from any excavating activities shall be made
through a sediment control P2M2 such as sediment basin or trap or any other
erosion and sediment controls which is regarded as the designated final
discharge(s).
4-1
GUIDELINES ON LD-P2M2
CHAPTER 4
4.1 INTRODUCTION
The above notion is also true when planning a strategy to address and control
potential erosion and sediment that may result from project site activities. In
developing such a strategy, the “ingredients” as mentioned above for
construction project management also hold true, as elaborated below.
In Chapter 4, we looked at the various land disturbing activities that are typically
encountered during the construction of a civil or building project. It was also
noted that these activities are likely to occur at the early stage of the project
during the preliminary and advanced works, but could also occur during the
main construction works. In this regard and with reference to addressing
potential erosion and sediment issues, it is critical to understand phases in a
project so as to identify where and when land disturbing activities may take
place at the work site, with the ultimate objective to determine the suitable
choice(s) of BMPs (i.e, technologies to control erosion and sediment issues) to
be implemented to reduce the risk of erosion and sedimentation. With this
understanding, the LD-P2M2 practitioners will be able to surgically pinpoint the
types of BMP that should be implemented at the appropriate locations as well as
at the suitable time.
In concurrent to the identifying the project phases, one should be also able to
decipher the key components of the project, so as to establish the associated
project activities or work tasks, especially those related to land disturbing
activities. Also, important in the above process includes the understanding of
4-2
GUIDELINES ON LD-P2M2
the possible construction sequences and subsequently, with all the information
collated, appropriate environmental method statements can be prepared. For the
Project Proponent, such a strategy provides his planners with key information to
undertake an estimation of the required resources and durations for the
respective individual tasks, and the identification of any interactions among the
different work tasks. For the Contractor, this strategy would contain to some
extent certain technical aspects which could be integrated into his construction
planning, so as to enable the Contractor to plan his overall works programme to
cater for the control of erosion and sediment, as well as to make the appropriate
organizational decisions about the relationships between project parties within
his own teams in the project.
4.2.1 Example 1
In the subsequent Figure 4.2 and Figure 4.3, the direct impacts from this
particular land clearing activities without apparent phasing implementation are
evident. From Figure 4.2, it is observed that surface runoff had transported the
eroded materials from the exposed ground surfaces of the site and discharged the
loose sediment into the adjacent watercourse. Note the significant water
pollution (highly turbid water quality) that has occurred in the river. Notably
such impact could have been avoided had there been a proper planning and
management of site through implementation of phasing and work sequencing
4-3
GUIDELINES ON LD-P2M2
throughout the land clearing activities, which is the main objective of this
Chapter.
The impact to the flora ecology in the vicinity of the same site is shown in
Figure 4.3. Here, it is observed that a large amount of earth materials has either
been pushed over onto the slopes intentionally or has dislodged naturally and
slipped on the slope side by the force of gravity. This was likely due to the
unprotected bare ground surface as well as due to basically no buffer zone
provided between the cleared land and the hill side. The slipped material is
expected to cause damages to the vegetation located in its path.
The above is also in line with several of the commonly found non-compliances
of erosion and sediment control as identified in DOE‟s “Manual Panduan
Pemeriksaan BMPs (Best Management Practices) Untuk Kawalan Hakisan
and Sedimen”, namely the following:
4.2.2 Example 2
Figure 4.4 and Figure 4.5 give another good example of a site (nature of project
unknown) with which limited phasing has been implemented during the clearing
works. In this example, as in Example 1, a large tract of land evidently has been
cleared at an area which is surrounded by existing forested area.
Based on the aerial photographs, it is shown that a large extent of ground surface
has been exposed of its cover crops (presumably from land clearing activities),
with lack of the suitable BMPs installed. Based on a visual examination of the
site conditions, it is believed that this exposed condition has been left unattended
for a relatively long period of time, or at least long enough to result in major
scouring of the ground surface as the evidence show. In Figure 4.5, rills and
deep gullies are shown to have occurred at the majority of the site area covered
by this photo. If we consider the adjacent sensitive receivers surrounding this
site area, namely the forested area, the impact of surface runoff carrying loose
soil materials and sediment during event of heavy rain can be considered to be
relatively significant, as no perimeter controls or buffer zones are apprarent at
the site. Other sensitive receivers (not seen in this photo) such as streams or
rivers which may likely be found at the lower elevation will also be adversely
impacted from these potentially polluted runoff discharges.
Figure 4.5: Massive Scouring of Ground Surface due to Erosion of Unprotected Surfaces
As in Example 1, the issues with this second example appear to include the
following, which resulted in the consequences as shown in Figure 4.4 and
Figure 4.5:
Issue of work programme;
Construction activity;
Construction schedule;
Construction methodology;
Issue of planning;
Issue of work stages;
Issue of project phasing;
Issue of work sequence;
Issue of upholding the Code of Practice in Earthwork;
Issue of erosion and sediment control measures not supervised properly; and
Issue of BMPs not in place.
4.2.3 Example 3
The following Figure 4.6 provides a further example to indicate the potential
adverse impacts brought about by, amongst other factors, inadequate planning on
site activities phasing. In this example, the impacts of erosion such as rills and
gullies are observed to have formed on this exposed slope, mostly likely due to
erosion caused by rain and surface runoff. Note also the haphazard method of
site work at this site whereby clusters of vegetation were left untouched but the
ground area around them has been stripped clear of its natural vegetation. It is
predicted that if the exposed surface is left untreated for a further period of time,
4-7
GUIDELINES ON LD-P2M2
continual erosion and surface runoff would eventually cause these vegetation to
be uprooted, and possibly causing further damages to the downstream side of the
slope.
4.2.4 Example 4
This example (Figure 4.7) illustrates what happens when an active work area is
not provided with proper identification of land disturbing activities and the
associated phasing, and is subject to the element of the weather. As a
consequence, erosion and surface runoff occurred inevitably during a rain event,
and note the extent of sediment being transported via the surface runoff into the
adjacent drainage, and presumably, eventually to a nearby watercourse.
Figure 4.7: Erosion and Surface Runoff from a Poorly Managed Work Site
4.2.5 Example 5
Figure 4.9: Erosion and Landslides Resulted from Lack of Activities Phasing
4-10
GUIDELINES ON LD-P2M2
4.2.6 Example 6
The potential issues associated with this last example include the following:
Issue of work programme;
Construction activity;
Construction schedule;
Construction methodology;
Issue of planning;
Issue of work stages;
Issue of project phasing;
Issue of work sequence;
Issue of upholding the Code of Practice in Earthwork;
Issue of erosion and sediment control measures not supervised properly; and
Issue of BMPs not in place.
4-11
GUIDELINES ON LD-P2M2
Figure 4.10: Erosion and Surface Runoff from a Poorly Managed Work Site
4.2.7 Discussion
All of the above examples and photos illustrate only a sample of work sites
found to be facing erosion and sediment issues due to their site activities, but in
reality, these occurrences are believed to be relatively typical throughout the
civil projects in Malaysia. Based on the possible issues or causes that have
resulted in the observed situations as seen in the above photographic evidence, it
is strongly believed that had proper planning and phasing of the site activities
been implemented prior to the land disturbing activities, most of the adverse
erosion and sediment impacts could have been avoided. For instance, in nearly
all of the work sites shown above, phasing of the activities would need to be
integrated into the planning of the works in order to control the erosion and
surface runoff issues. One of the factors that need to be considered during the
phasing of the site works would be the „division‟ of the works area footprint into
smaller and manageable work parcels. Once a smaller footprint is defined, then
the application of minimum requirements for the Land Disturbance Pollution
Prevention and Mitigation Measures would follow for this parcel in relation to
the work scheduling and sequencing to control erosion and sediment discharge.
The remaining of this Chapter will be dedicated to discussing the process of
identifying phases and other associated aspects in this regard.
4-12
GUIDELINES ON LD-P2M2
The cycle of any project always commences from the same starting point, i.e.,
the Project Proponent‟s need or desire for a “product”. “Project Proponent” in
this context can be a private entity or government institutions or semi-
government bodies. In the case of a civil engineering project, this “product” can
be in many forms, such as an entirely new development project (either
residential, commercial or industrial), utility facilities (such as sewage treatment
plants, water treatment plants, power stations, major drainage or sewerage
schemes, etc.), agricultural projects (such as oil palm plantation, etc.), new
infrastructural networks (such as highways, bridges, canals, airports, ports, etc.),
and so on. The reasons for the above needs can vary between a wide spectrum
of needs, ranging from a purely economic reason (in the case of privately
initiated projects) to that of national interests (such as infrastructural and utilities
projects). Regardless of the status of the project initiator, i.e., Project Proponent
1
Collins English Dictionary
4-13
GUIDELINES ON LD-P2M2
and the reasons for the need of the project, most, if not all, of these projects will
have to go through this simplified flow as shown in Figure 4.11.
Once the Project Proponent (PP) decides to pursue further or proceed with his
desire to materialise his ideas or needs, the next step would typically be the
appointment of a consultant to investigate the feasibility of the project. This
would likely involve the evaluation of the project feasibility from the
perspectives of technical, economical, social, environmental and safety, and
normally requires the consultant to review and assess the various options or
alternatives to implement the PP‟s ideas by comparing each of these options or
alternatives against a set of agreed parameters for comparison. Depending on
the complexity of the proposed project, the duration of a feasibility study can
range anywhere from as little as six (6) months (or less) for a relatively straight
forward project, to even to eighteen (18) months (or more) for mega or major
projects. Ultimately, the objective of this step in the project‟s flow will be to
ascertain the feasibility of the proposed project based on the given assessment
criteria (i.e., technical, economical, social, environmental, safety, etc.). If it were
found that the project is not feasible due to whatsoever reasons, the PP may wish
to reconsider and adjust the original scope of the project, or to totally abandon
the whole idea of pursuing further with his idea (if the feasibility study
discovered insurmountable issues that cannot be resolved). If the PP chooses the
former, then a separate feasibility may be undertaken to confirm the feasibility
of the revised plan. Conversely, if the feasibility study recommends that it is
viable for the project to proceed, then the project will move into the next step,
that is, typically the Preliminary Design stage.
Once the feasibility of the PP‟s idea is ascertained, the PP may normally engage
an engineering consultant (which could be the same consultant who have
previously undertaken the Feasibility Study) to provide the preliminary designs
of the proposed project. Typically, the basic engineering information on the
project is obtained and compiled to enable the formulation of a preliminary
visualisation of what the project might look like upon construction. To this end,
the preliminary designs may entail the compilation of initial soil and site
investigation data, project boundary and Right of Way (ROW), pre- and post-
development formation levels, footprint of the final works (buildings, roads,
drainage, etc), layouts of associated utility services (such as sewerage, drainage,
water supply, electricity, gas, telecommunication, etc), and usually the build-up
drawings of the final works. The main objective of this step in the project can be
perceived to enable the PP to achieve the following goals:
Again, depending on the complexity of the project, the duration for completing
the preliminary designs can range anywhere between another nine (9) to
eighteen (18) months. It should be noted that that these durations are provided
herein solely for the reader‟s information only, so as to get some sense on the
effort needed for such an activity. The duration cited in this section are
estimates only based experience from other projects and should not be used for
any other purposes outside of this Guidelines. Ultimately, the objective of step 3
in the project will be to produce a set of initial designs for the PP, with enough
information so as to fulfil the above goals, but yet to be finalised with adequate
detailed information for tender documentation and construction purposes.
With the preliminary designs completed to the satisfaction of the PP, step 4 will
likely involve the commencement of the EIA study, to evaluate the
4-15
GUIDELINES ON LD-P2M2
The duration for the EIA study can range between six (6) months to twelve (12)
months. Ultimately, the objective of step 4 is to produce an approved EIA
report, with or without associated conditions of approval by the DOE.
for the preparation of the detailed designs and tender documentation may take
another nine (9) months to eighteen (18) months, depending on the complexity
of the project.
Upon completion of the detailed designs and the associated tender documents,
the Project Proponent may need to assure himself that all the necessary legal
procedures have been undertaken and accomplished, so as to make sure that the
project can be implemented smoothly once the successful contractor has been
selected. Some of these procedures may be those required on the federal or state
level. Once all the necessary procedures are completed, the PP can then proceed
with the tender exercise, i.e., to invite qualified tenderers to submit their
proposals (technical and financial) to execute the project. Upon receipt of the
tenders, the PP and his team will then assess and evaluate the submission based
on a set of agreed assessment criteria, with the ultimate aim to select one
contractor who is deemed to be technically and financially sound to carry out the
construction works. The outcome of this step is then to select the successful
tenderer and subsequently, to award the contract for the project to this
contractor.
Once the contract has been awarded, the Contractor then commences his site
activities and implements the works activities in accordance to the requirements
of the Contract Document, which collectively includes the Drawings,
Specifications and all other documents that are deemed to be part of the Contract
Document, for example, the approved EIA report and EMP, amongst others. In
other word, the contractor is obliged to operate and manage the construction site
to comply with not only the Contract Document which he entered into an
agreement with the PP, but also with the recommendations as prescribed in the
EIA report which was previously approved at the earlier stage of the project‟s
cycle. It is important for the reader to remember this point because as we will
see later, this obligation plays a key role for the applying LD-P2M2 into the
construction stage. At the completion of all the works covered in the contract
document, the Contractor eventually hands over the completed project to the
Project Proponent for the operation and maintenance stage.
As discussed above, there are various major steps that are needed to be
accomplished before a project can commence its physical works at site,
including the feasibility studies and investigation, designs, Environmental
Impact Assessment, and tendering & assessment, or graphically shown in Figure
4.12:
4-17
GUIDELINES ON LD-P2M2
Feasibility Study
Preliminary Design
Detailed Site
Investigation
Environmental
Impact Assessment
Detailed Design
Tendering
Contract Award
Rates allowed for temporary BMPs normally on the low side and often
considered as items with negative profit, and thus, given low priority in
construction planning;
Contractor’s erosion and sediment control programme may address only the
initial and final phase of construction but not the interim construction phases
with adequate temporary BMPs.
To overcome the above scenarios (which are not uncommon in most projects
unfortunately), the timing to kick off the process for handling erosion and
sedimentation issues becomes critical. This is where the application of LD-P2M2
theory can assist. For the entire concept of LD-P2M2 to be effective, it is
imperative for the preparer of the LD-P2M2 Document to understand that the
process for handling erosion and sedimentation issues on a project site actually
begins even much earlier before the physical activities start.
With the above attention and consideration given to handling erosion and
sedimentation issues by the Project Proponent and his Consultants, requirements
for the minimum actions to be implemented on site to control erosion and
sedimentation by the Contractor will become transparent, and even contractually
and legally binding, since the approved EIA report and all its content therein
normally form part of the Contract Document.
For relatively large projects, it is not uncommon for the Project Proponent to
manage his project by dividing the development into several phases. It is noted
that such type of development phases is different from and not similar to the
concept of project phases that this Guidelines is advocating. Further clarification
on these two concepts is provided in the subsequent Section 5.3.3. After the
contract has been awarded, it is normal for the Contractor to break down the
project (or the Works to be performed to deliver the project) into distinct
categories, such as pre-construction, construction, commissioning, handover.
Work breakdown structures will then be prepared under each of these categories,
so as to enable the Contractor to effectively manage his resources (materials,
equipment, labour) within the prescribed programme and budget of his contract.
2
Per DOE’s latest “EIA Guidelines in Malaysia, 2016”
4-19
GUIDELINES ON LD-P2M2
For the LD-P2M2 to become effective, it is imperative that the preparer or user of
the LD-P2M2 Document has some basic knowledge in identifying the key
elements in reference to the above-mentioned work breakdown structures,
particularly in the context of controlling erosion and sedimentation that may arise
from the site activities. Description on these terminologies is given below.
In Section 5.3.2.14, it was mentioned that the Contractor may break down the
project (or the Works to be performed to deliver the project) into distinct
categories, such as pre-construction, construction, and so on. Perhaps some
clarification should be made here to distinguish these two terminologies, in the
context of this Guidelines.
4-20
GUIDELINES ON LD-P2M2
3
Project Management Body of Knowledge (PMBOK 5)
4
Source: http://www.free-management-ebooks.com
4-21
GUIDELINES ON LD-P2M2
As seen above, when the work packages are decomposed into activities in this
way the result is to create an activity list, which can then be used to develop the
project schedule. As mentioned earlier, the work packages are product or
deliverable based to deliver the scope of the project, whereas activities' focus on
the work that needs to be carried out in order to execute such work packages.
An activity has an expected duration and consumes resources in terms of
manpower and/or budget. If duration cannot be meaningfully assigned to it then
it should be considered a milestone. The technique of decomposition, as applied
to defining activities, involves subdividing the project work packages into
smaller, more manageable components called activities. Activities represent the
effort needed to complete a work package.
4-22
GUIDELINES ON LD-P2M2
With the clarification of the several key terminologies above, let‟s continue with
the following sections on how one should identify project phases, project
components, project activities, and work sequences from the angle of minimising
erosion and sediment in a project.
The meanings of “phase” are given above in Section 5.3, as well as for the
project phases from the perspective of controlling erosion and sedimentation
issues at site. For the purposes of this Guidelines, we shall further extend the
meaning of “phasing” to involve the planning and development of a schedule of
construction activities, and to match these activities with recommendation of the
appropriate P2M2’s or BMPs at that particular stage of the project. The main
purpose of introducing phasing in such a manner is to ensure that the amount
and duration of soil exposed (from the land disturbing activities) to erosion is
reduced as much as practicable at any one time by implementing and
maintaining the suitable BMPs in coordination with the sequence of construction
activities.
In view of the context as discussed above, it should be evident that the intent for
the use of the concept of phasing in this Guidelines is focused on those site
works which will involve land disturbing activities. The key to developing an
effective “phasing plan” should be that it is not undertaken prior to the
mobilisation of the Contractor‟s team to the project site, but rather at much
earlier stages of the project (as discussed in Section 5.3 previously). This plan
should also emphasize the concept in which any disturbed areas in one phase
should be stabilized before disturbing the subsequent phases.
There is no hard or fast rule to establish the size and extent of a phase for any
particular project. In the process of identifying possible phases in a project,
several factors will need to be considered.
4-23
GUIDELINES ON LD-P2M2
Size of site: No matter what the project‟s footprint or size is, phasing can in
principle be applied for the purposes of controlling erosion and sedimentation
from the impending land disturbing activities. In other word, phasing is
applicable to a project with a footprint of 10 hectares, as well as to another
project which covers only 1000 m2, just as long both projects involve land
disturbing activities. The key difference in the phasing between these two
projects will depend on the other relevant factors as discussed below. In most
cases, the number of phases will increase to correspond to the complexity of the
project, with size being one of these contributing factors. Nevertheless, the
actual phasing will depend also on the types of land disturbing activities that are
involved, topography of the site, existing conditions of the site, and so on.
Existing land use: The existing condition of the site where works will be
undertaken will also determine how phasing would be planned out. A project
site which is covered by virgin forest inevitably will need to be treated
differently than a site which is already disturbed or is currently relatively
established (for example, with available access roads or drainage, etc). For those
sites which are relatively undisturbed and land disturbance activities will be
involved in the site works, phasing of such sites will need to pay particular
attention to the construction sequence of works and the provision of suitable
BMPs in order to reduce the amount and duration of exposed disturbed surfaces.
Types of land disturbance activities: The extent of phasing for a site will
depend heavily on the type of land disturbance activities that might occur in the
construction sequence. A project site with a footprint of 1 ha requiring a
concrete platform to be constructed on the entire site which is currently occupied
by dense forest, when compared to another project site with the same footprint
but only requiring a three meter wide road to be constructed with some spot
excavation for structure foundations spaced every 20 m, will have a significantly
different extent of phasing. For the former, the site activities are predicted to
incur large scale land clearance and vegetation removal (over the entire 1 ha of
land), cut and fill for land formation, excavation works for access roads,
drainage & platform foundation, materials transport, amongst others. The latter
project, on the other hand, may require some land clearance and vegetation
removal but on a much smaller scale, i.e., along a strip of land, say 10 m wide,
as well as some excavation for the road foundation and structure foundation. It
is obvious from the above description the platform project will incur more land
disturbing activities and hence a larger area of ground surface being exposed to
the elements which could result in erosion, as compared to the second project.
Under such circumstances, phasing of the first project will likely involve more
and smaller parcels of work areas (to control erosion), and the second project,
whilst still requiring some phasing to be provided, can afford to have fewer but
larger extent of parcel of work areas.
4-24
GUIDELINES ON LD-P2M2
Topography: This factor will influence the phasing of a site from the perspective
of controlling surface runoff. By taking into account of the ground topography
during identification of the site phasing, one can not only “contain” the surface
runoff for that particular parcel of work area, but also introduce some
engineering economics by optimizing the natural flow paths within a site.
Weather: Weather plays a critical role in phasing in conjunction with the work
sequence. When identifying the phasing for a particular site, one needs to know
the type of site activities that are needed as well as the season of the year during
which these activities are taking place. Where possible, land disturbance and
construction activities in and around waterways should be scheduled during the
dry weather, to minimise opened ground surface exposed to the elements of rain.
Type of soil: The ease for the soil materials to be dislodged from the land
disturbing activities as well as the difficulty in treating the captured eroded
materials also play a part in establishing the suitable phasing for particular site.
Ground conditions comprising easily loosened soil materials and difficult to treat
(for instance, fine silt) should be subjected to a more manageable (i.e., smaller)
parcels of phased work areas.
Practicality of BMP installation: How fast can the BMP(s) be installed on site
depends on the type of BMPs (silt fence or sedimentation pond), whether access
is available, how much resources will be provided to install BMPs, type of
terrain BMPs to be sited on, weather conditions, etc. A site which faces
challenges when answering the above queries should be phased carefully, i.e.,
with smaller work areas and coordinated closely with the construction sequence,
to reduce the amount and duration of soil exposed from land disturbing
activities.
Rate of production: Rate of production refers to the how rapid the site activities
could be carried out. Evidently then this depends on the number of resources
(equipment, machinery, labour) deployed by the Contractor, as well as on the
type of terrain (flat or hilly grounds) and weather. Another factor to be
considered concurrently is the rate the BMPs can be installed; if it is anticipated
that the rate of site activities were able to proceed at a much greater rate than the
BMPs could be installed, there is then a need to assess the phasing such that to
avoid a scenario whereby large areas of exposed ground are left unattended to.
4-25
GUIDELINES ON LD-P2M2
Based on the above discussion, it should be clear why it was stated earlier there
is no fast and hard rule to establish the size and extent of a phase for a particular
project, because every project is distinctly different. There is no right or wrong
answer to whether a phasing has been done correctly or not, but for each planned
phasing, adequate justification should be provided behind the basis for the
planning. It should always be remembered that the ultimate objective of
introducing phasing to a project site is to ensure the amount and duration of soil
exposed (from the land disturbing activities) to erosion is reduced as much as
practicable at any one time by implementing and maintaining the suitable BMPs
in coordination with the sequence of construction activities.
Without going into the specific details as recommended in Section 5.4.2 above,
let‟s take a look at some examples of possible phasing that could be considered
using the site scenarios presented earlier in this Chapter.
To recap, Figure 4.1 is reproduced below. Key issues relating to erosion and
sedimentation that can be captured from this photo include the following:
Previous Figure 4.1: Large Scale Earthworks with No Proper BMPs Installed
4-26
GUIDELINES ON LD-P2M2
Based on only the above observations (and not having enough data to take into
account the other factors as discussed in Section 5.4.2), one could even plan a
preliminary phasing programme which might have lessened the impacts of
erosion from this site. Figure 4.14 below presents a simple graphical illustration
one of the possible ways to phase the activities on this site. It should be stressed
again that there is no right or wrong way to plan a phasing, as long as adequate
justification is provided for the basis of the planning. Ultimately, the final
objective is to ensure the amount and duration of soil exposed is reduced as
much as practicable. In this regard, the notes associated with the proposed
phasing in Figure 4.14 are as follows:
Assuming this photo has covered all of the site to be worked on, the
approximate area shown to be currently exposed is about 1.5 ha.
Assuming the lowest elevation is at the bottom of the photo, and the top of
the ridge is at around middle of the photo, “Phase 1” should start from the
lowest portion of the site, as indicated. Concurrently, clearing can also start
at the presumed low point at the top right corner of the photo.
The width of the lower Phase 1 region is approximately half the distance
between the low point and the ridge top, to allow adequate BMPs to be
installed at the lower half of the sloping surface or toe of the slope before
exposing the slope side at the higher elevation. The length of this phase
extends from the left most of the site towards the right until the edge of the
flat surface. If adequate resources are available, two “Phase 1” areas have
been proposed to allow simultaneous works to proceed on this site.
level, and hence, imperative for the BMPs to be installed before works
proceed to the higher ground. The benefit of such planning is that when land
disturbing activities begin at the higher ground, the exposed surfaces at the
lower ground would have been provided with temporary stabilization as well
as the appropriate BMPs installed such as perimeter controls, buffer zones,
sediment basins, etc. Thereafter when the works at the higher ground
commences, sediment discharges and/or runoff from this latter phase would
be “captured” by the existing BMPs at the lower ground, hence minimising
the deposition of these runoff materials to the downstream sensitive receptors
such as rivers and watercourses. At the completion of Phase 2, the following
phases would follow suit.
Had this been a proper phasing exercise, the next steps would be
identifying the project components within this parcel of work area, and
establishing the construction sequence with the intention of identifying
BMP recommendation to be provided herein. For example, looking at the
site conditions, some of the possible BMPs that may be relevant within this
area include the following:
Slope drains, flexible pipe slope drains or downpipe, rock lined drainage
chutes or flume, cascade drain shall be applied to convey upslope runoff
down slope without affecting the slope surface;
More illustration on possible phasing to the earlier Figure 4.4 and Figure 4.8
is presented next page.
4-30
GUIDELINES ON LD-P2M2
As shown in Figure 4.15 (previous Figure 4.4), the key issues relating to
erosion and sedimentation at this site include the following:
Again, Phase 1 is first designated for those area at the lower ground, to ensure
the suitable BMPs are installed foremost for this site prior to other works. In
view of the landscape and topography of this particular site, some of the relevant
BMPs that would be suitable to reduce the potential impacts of erosion, surface
runoff, sedimentation and vegetation damages include the following:
Similar to the previous example, two Phase 1 areas have been planned into the
construction sequence of this work site, as both being considered to be the
lowest points on this site. Phase 2 then follows suit after the completion of
Phase 1, and this can be seen in Figure 4.15 to be the area to the left of the
Phase 1 area, which is deemed to be at a higher elevation than Phase 1. Once
Phase 2 is completed, Phase 3 can then proceed followed by Phase 4.
The previous Figure 4.8 indicated a linear-type land clearance work along a
mountain ridge. Some of the key issues relating to erosion and sedimentation at
this site are shown in Figure 4.16:
Again, the relevant BMPs that would have been considered for this site location include
the following:
Physical markers to show the limit of land disturbing activities;
Buffer areas for vegetation preservation;
Entrance/exit roads with proper stabilization;
Perimeter controls including filter or perimeter berms, silt fences, sediment traps,
sediment basins, construction entrance, temporary diversion dikes or earth bunds
and diversion drains;
Principal sediment basin/trap;
Runoff control measures including temporary earth drain, diversion channel and
conveyance system;
Slope drains, flexible pipe slope drains or downpipe, rock lined drainage chutes or
flume, cascade drain;
Runoff conveyance system such as road ditch, temporary earth drain, catch drains,
berm drains, toe drains, slope drains and in-slope or out-slope diversion:
Temporary soil stabilization including temporary seeding, geotextiles, mulches,
and other techniques; and
Suitable stockpiles and disposal areas.
The selected examples above should give the readers a little more idea now of
what implementing phasing into a project entails. Some of the overarching
guidelines which were listed in Section 5.4.2 were taken into consideration in the
phasing planning for the examples, as discussed below.
Existing land use: In the examples shown, it is believed that the pre-
development conditions of the site were largely relatively undisturbed. As such,
it would be fair to assume that pre-construction activities would have constituted
land disturbance activities which would expose the previously vegetated or
forested land (which indeed did happen!). Due to the undisturbed conditions of
4-33
GUIDELINES ON LD-P2M2
the site, phasing of such sites will need to pay particular attention to the
construction sequence of works and the provision of suitable BMPs in order to
reduce the amount and duration of exposed disturbed surfaces. The anticipated
activities falling under the project phases would include: establishment of
perimeter control and buffer zones, tree felling, vegetation clearing, stockpile or
transport of biomass, site grading, construction of access road and drainage,
and installation of silt fences, silt traps, sedimentation ponds & cover crops. In
formulation the extent of the phase areas, one would need to take into account
that some of the above activities will need be undertaken sequentially or
concurrently, and this factor (together with the other considerations) would have
an effect of the phase sizing.
One of the considerations which plays a role in deciding the extent of a phase is
the requirement that “any ground surfaces or slopes exposed by the land
disturbance activities must be temporarily protected with suitable material to
prevent erosion within 7 days of the exposure”. To comply with this
requirement, it makes sense then for the phasing to be sensibly sized such that no
exposed surfaces are left unattended for more than 7 days or that suitable BMPs
are able to be installed at a “rate” faster to the surface exposure activities.
Types of land disturbance activities: The extent of phasing for a site will
depend heavily on the type of land disturbance activities that might occur in the
construction sequence. In the previous examples, and assuming the pre-
development sites to comprise relatively undisturbed forested or vegetated areas,
land disturbance activities are anticipated: tree felling, crops or vegetation
clearing, stockpile and/or transport of biomass, earthwork to raise platforms,
site grading, and excavation for construction of access road and drainage.
As seen above, the initial site activities in the three examples most likely
involved site clearing – first for the formation of access roads, and then later for
the platform formation; stockpiling of biomass prior to disposal off site; access
road and drainage formation, and site grading. These initial activities basically
dictate the extent of the phasing requirements, underlined by the need to
“maintain the amount and duration of soil exposed (from the land disturbing
activities) to erosion is reduced as much as practicable at any one time by
implementing the suitable BMPs in coordination with the sequence of
construction activities”, as well as the “7 day requirement to temporarily protect
or cover exposed surfaces with suitable materials”. In fact, this criterion can be
viewed hand-in-hand with the previous factor regarding land use.
Topography: This factor is evident in the first two examples, where the initial
phases (i.e., Phase 1) of the works are focused at the low grounds. Primarily, the
rationale for commencing Phase 1 at the low points will allow for the necessary
BMPs such as silt traps or sediment ponds to be constructed first so as to be
available to capture potential surface runoffs flowing from the higher grounds.
4-34
GUIDELINES ON LD-P2M2
Weather: This factor was not reflected in the previous examples as the project
programmes were not available for assessment. The principle for the phasing in
relation to this factor would have simply been the avoidance of land disturbance
activities during the rainy and wet season.
Type of soil: Again, this information was not available for review, but
essentially, areas with soil type which exhibit high erodibility (e.g., fine silt,
sandy) should be subjected to a more manageable (i.e., smaller) parcels of
phased work areas so as to provide a tighter control on the extent of erosion and
sediment, as compared to a site consisting of soil type of lesser erodibility (e.g.,
rock or clay).
Practicality of BMP installation: This factor, as well as the following one, again
cannot be assessed in the previous examples in view of lack of such information.
Consideration on the extent of BMP required, how quickly the BMP(s) can be
installed, accessibility, available resources, site conditions, and so on must be
taken into account. A site which faces challenges when answering the above
queries should be phased carefully, i.e., with smaller work areas and coordinated
closely with the construction sequence, to reduce the amount and duration of soil
exposed from land disturbing activities.
4.4.4 Summary
In summary, the key points to take note during the identifying of project phases
are as follows:
“Project phasing” in the context of this Guidelines is different from the project‟s
overall “development phase”. Here, we are talking about breaking down a
“whole” project into smaller divisions of work from the perspective of
4-35
GUIDELINES ON LD-P2M2
controlling erosion and sediment, and is more like a “phase within a phase”.
The “phasing” for the purposes of controlling erosion and sediment is more an
internal subdivision of the project into smaller packages so as to manage the
work sequences within these packages to minimise the erosion and sediment
events, by facilitating the implementation of erosion and sediment controls or
BMPs in a sequential or systematic manner.
The main purpose of introducing phasing is to ensure that the amount and
duration of soil exposed (from the land disturbing activities) to erosion is
reduced as much as practicable at any one time by implementing and
maintaining the suitable BMPs in coordination with the sequence of construction
activities.
There is no hard or fast rule to establish the size and extent of a phase for any
particular project. However, the rationale for planning the phasing of a site can
be underlined by the following two criteria:
o To maintain the amount and duration of soil exposed (from the land
disturbing activities) to erosion is reduced as much as practicable at any
one time by implementing the suitable BMPs in coordination with the
sequence of construction activities; and
Other related key considerations for planning the extent of phases include the
following:
o Existing land use
o Types of land disturbance activities
o Topography
o Weather
o Type of soil
o Environmental Sensitive areas
o Practicality of BMP installation
o Rate of production
More examples of project phasing will be illustrated in the latter sections of this Chapter.
In the following sections, we will discuss next on some of the other techniques that are
needed to commensurate the skills for identifying phasing.
4-36
GUIDELINES ON LD-P2M2
The above definition for identifying project activities from the view of project
management can also be applied for the purposes of addressing erosion and
sedimentation. Following on from the discussion in Section 5.4 on project
phasing, the concept of work breakdown structures and their associated elements
can be deployed to recognize the respective works particularly those related to
land disturbing activities. For illustration, the WBS for the purposes of this
Guidelines can be illustrated below in Figure 4.17.
4-37
GUIDELINES ON LD-P2M2
To this end, the meaning and examples of elements of the WBS in the context of
erosion and sediment control, namely, project component, project activities,
scope of work and environmental method statements are demonstrated further in
the following sections.
More often than not, a project entails hundreds, if not thousands, of pieces
information to enable the Contractor to build or assemble the final product of
this project in a systematic manner to reach to the end point. In this regard, a
part of his construction planning involves breaking down his project to various
distinct components to clearly delineate the „deliverables‟ or „responsibilities‟ to
be accomplished in a progressive manner (since no project is completed in a
single day!). Conventionally, the breakdown of these components of a project is
done by grouping all the relevant tasks and deliverable under the respective
engineering disciplines, to give a holistic picture of the overall resource
requirements in terms of specialist needs, labour, material & equipment, time
and financial.
For illustration, let‟s take a look on how a civil engineering project might be
broken down into its project components from the perspective of the Contractor,
because as shown later, there are some distinct differences in terms of
identifying components for the purposes of “constructing the project” and for the
purposes of “controlling erosion and sedimentation”.
Firstly, let‟s assume a fictional project as shown in the simple sketch in Figure
4.18. Essentially, this project will involve constructing a new Sewage Treatment
Works (STW) which is to be located in the vicinity of a forest reserve.
4-39
GUIDELINES ON LD-P2M2
TO TOWN A
APPROX 2 km
+ 539
+ 540
EXISTING PRISTINE + 518 EXISTING RIVER
FOREST RESERVE (AVG WIDTH 200m;
+ 520 DEPTH 2m
+ 539 + 536
+ 538
+ 525
+ 518
NEW 4m WIDE STEEL
+ 540 + 538 BRIDGE ABLE TO + 538
EXISTING 2-LANE CARRY 200T VEHICLES
ROAD (7M WIDE) IN THE FUTURE + 530 + 540
+ 520 + 517
+ 537
+ 524
+ 537
+ 537
TO TOWN B
Some of the key features of this project site are observed as follows:
All of the permanent works including roads and STW will be sitting on soft
grounds, meaning some form of foundation is needed to support these
structures;
The low ground of this site is generally along the alignment of the river, with a
new river crossing structure (bridge) to be constructed to connect the new
road;
Forest clearing will be required to construct the access road, as well as for the
platform for the STW;
Typically, the Contractor will begin to break down the project based on disciplines into
the following major sectors: Infrastructure; Geotechnical; Civil; Structure; Electrical;
Mechanical; and Architectural. Under of each of these disciplinary sectors is then listed
all those possible components of works related to the STW project, which may
potentially include the following:
Infrastructure
o Access to STW
Geotechnical
o Foundation works for the Roads
o Foundation works for the STW Building
Architectural
o Finishing works for STW
Civil
o STW exterior works
o Guard house
o Landscape works
o Fencing
The above breakdown is illustrated in Figure 4.19. Subsequently, each of these project
components can be broken down into smaller packages, where for this example, are
called Project Activities. For instance, for the Component “Access to STW”, it comprises
five major project activities, namely, access road, site formation, foundation, bridge
columns and elevated structure, and so on.
Although the example breakdown shown in Figure 4.19 provides a good starting point
for the Contractor to plan his resource requirements, it however does little to bring out the
elements relating to erosion and sedimentation controls needed for the project. The main
reason is such a WBS is product or deliverable oriented, whereby the focus or purpose of
the breakdown is more geared towards getting to the endpoint, i.e., delivery of the final
products.
4-42
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
Let‟s look at another example on how conventionally the project components might be
identified. This example illustrates a proposed new highway construction through a
remote and rural area in Pahang. It is envisaged that for this 10 km long highway project,
the project team will likely subdivide the project into its respective disciplines as follows:
Infrastructure Works, which would provide the temporary access into the
highway works areas. Based on the project title, it is also anticipated that the
provision of these access roads would entail some degree of vegetation and
forest clearing, land formation, slope cutting and filling, watercourse diversion
and crossing, to name a few;
Geotechnical Works, which would entail foundation works for the new highway.
In the absence of more details on the form of foundation to be provided, it is
reasonable to assume that for any kind of foundation that is to be deployed,
some form of excavation will be needed for the works, with associated
temporary stockpile of earthwork materials on site;
Civil & Structural Works to cater for the likes of the new highway construction,
along with the associated road drainages, pavement, river crossings, and other
road fixture and installations. The civil/structure team will also be responsible
for establishing the site offices and staff quarters for the project;
Electrical & Mechanical Works will cover all the ancillary E&M installation,
testing and commissioning including street lighting, solar energy and power
supply, and other instrumentation equipment;
Utility Works, which covers the provision of common trenching for the
installation of various utility services including water supply, sewer lines,
electricity and telecommunication cables; and lastly,
General Civil Works for the finishing works for the completed highway
including landscaping, and road safety features such as guard rails and fencing.
Figure 4.20 illustrates the possible breakdown of the highway project as described.
4-44
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
Again, the above WBS is geared towards deliverable-oriented, and thus does
little to bring out the elements relating to erosion and sedimentation controls
needed for the project.
To breakdown the overall project into a simpler form which comprises the major
and significant final deliverables of the project. Although it is not a
straightforward exercise to discern what components constitute major and
significant, the general guideline would be to preferably break down an overall
project into no more of five or six components, depending on the complexity of
the project.
The following sections will illustrate how project components can be identified
to focus on erosion and sediment.
For the purposes of addressing erosion and sediment issues in this Guidelines, a
logical and simpler approach is used to arrange the parceling of the project
components, keeping in constant awareness the ultimate objective of LD-P2M2.
Let‟s first start with the previous STW example, previously provided with a
possible conventional breakdown to include Infrastructure, Geotechnical, Civil,
Structure, Electrical, Mechanical and Architectural, and depicted in Figure
4.19. However, from the perspective of identifying those deliverables and
focusing those with possible land disturbing consequences, an alternative
breakdown of the above example project could take the following form, as
illustrated in Figure 4.21.
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
In this simpler breakdown, the project components are now restricted to three
major physical assets of the project, namely the road, bridge and the STW
building package. In this approach, no distinction is made on the types of
disciplines of work such as civil, structure, geotechnical, and so on, but rather,
the focus is on the major types of physical structures that will be constructed for
the project. Identifying the project components in this way will enable easier
follow-on breakdown of project activities for each component so that all the
related land disturbing activities (discussed in Chapter 3) can be readily
identified and further environmental method statements be formulated to address
potential erosion and sedimentation issues associated with such activities.
From the simple layout sketch in Figure 4.18, and if we disregard the numerous
details that might be associated with the delivery of this project, effectively the
whole project can be simply “represented” by the 3 components: the road, bridge
and STW building site. This is in line with the purpose for the project
breakdown so as to focus on those deliverables that will involve land disturbance
activities. For instance, for the above example of project component
restructuring, the following associated land disturbing and other associated
activities are envisaged to complement the construction of these components:
As shown in Figure 4.23, the key project components now are limited to:
temporary roads; permanent roads; drainage systems, and river crossings. In
the next Section, we will see how restructuring the project in such manner can
easily facilitate the identification of the common project activities associated
with these individual components to allow formulation of further environmental
method statements be formulated to address potential erosion and sedimentation
issues associated with such activities. As such, it is worth noting that a general
rule of thumb to identifying project components for the purposes of addressing
erosion and sedimentation is to first recognise the potential activities that are
associated with these respective components that may comprise land disturbing
activities that need to be adequately controlled and protected against the
elements of erosion and sedimentation from occurring.
For instance, for the above example of project component restructuring, the
following associated land disturbing activities are envisaged to complement the
construction of these components:
4-49
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
With the above identification, one can then have a better understanding of
where and when erosion might occur due to the exposure of ground
surfaces as a result of these land disturbing actions, and thereafter, pollution
prevention and mitigation measures (P2M2) can be recommended
accordingly.
Geotechnical Works, which would entail foundation works for the buildings
and possibly roads as well due to the forest setting. Extensive excavation
4-52
GUIDELINES ON LD-P2M2
will be anticipated for these structures, with the associated requirement for
temporary stockpile of earthwork materials on site;
Civil Works to cater for the various engineering features of the project
including access roads and pavement, drainage works, pump house, open
space, landscape works, and a boundary wall. All of the above would
involve land disturbing activities such as site clearing, excavation, slope
works, and stockpile of construction & earthwork materials as well as
chemicals and scheduled wastes;
Electrical & Mechanical Works will cover all the ancillary E&M
installation, testing and commissioning including street lighting, power
supply to the project for the apartments as well as the STW and clubhouse,
and other instrumentation equipment;
Utility Works, which covers the provision of common trenching for the
installation of various utility services including water supply, sewer lines,
gas pipes, electricity and telecommunication cables; and lastly,
COMPONENTS OF PROJECT
COMPONENTS OF PROJECT
For the next example, the objective of the project is to construct a 3 km long
drainage channel to convey stormwater in an urban setting to a final waterbody
downstream, diagrammatically illustrated in Figure 4.27. It is envisaged that for
water-related project, the project team will likely subdivide the project into its
respective disciplines as follows:
Earthworks, which would include some land clearing activities and followed by
creating a trench for the laying of the large drainage structures. The land
clearing activities is anticipated to involve some degree of tree felling and
removal of existing vegetation. However, the more extensive land disturbance
activity from this discipline of work would be the excavation of a wide trench to
provide for working space as well as a platform for construction of the drainage
structure which will consist of cast in-situ box culverts;
Geotechnical Works, which would entail foundation works which are required
for slope stabilization to cater for the deep trench, and also for the proposed
drainage pump house and substation;
Civil Works to cater for the civil construction of access roads and drainage,
connectors of the existing drainage network to the new main drainage channel,
associated manholes and gullies as well as for the finishing works including
landscaping, railing and boundary wall upon completion of the drainage
structures;
Electrical & Mechanical Works will cover all the ancillary E&M installation,
testing and commissioning for the storm water pump house, street lighting,
power supply, and other related instrumentation equipment;
As shown in Figure 4.29, the key project components now are proposed to be:
trenching; roads; drainage; and pump house. Such restructuring allows the
4-58
GUIDELINES ON LD-P2M2
Trenching works: land clearing, excavation works, cut and fill for slope
formation, stockpiling of earthwork materials, dewatering of trench;
Drainage: earthworks consisting of cutting and filling for slope and land
formation, stockpiling of earthwork materials, excavation for drainage;
With the above identification, one can then have a better understanding of where
and when erosion might occur due to the exposure of ground surfaces as a result
of the land disturbing actions, and thereafter, pollution prevention and mitigation
measures (P2M2) can be recommended accordingly.
4-59
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
COMPONENTS OF PROJECT
The next example is a project to construct a river check dam. Due to the
nature of the project, only three main disciplines are envisaged to dominate
the implementation of this project, namely, civil, geotechnical and
structural (Figure 4.30). However, to facilitate the control of erosion and
sedimentation, Figure 4.31 illustrates a more practical breakdown of
project components into river works and dam structures.
Typically for such type of project, the possible primary sequence of works
comprises the following:
COMPONENTS OF PROJECT
LANDSCAPING
COMPONENTS OF PROJECT
Earthworks, which would provide for the clearing of the existing project
site of the existing forest or other non-related vegetation and for the
forming of a suitable platform for the plantation of the new crop;
Civil Works, which would cater for the likes of the access road construction,
along with the associated road drainages, pavement, river crossings, utility
services and site boundary wall;
Horticultural works which would involve the setting up of a nursery for the
new crops and the subsequent transplantation of these new plantation.
To cater for the potential erosion and sedimentation risks from this
development, we can identify project components in the following way,
along with their associated land disturbing activities, as shown in Figure
4.33:
COMPONENTS OF PROJECT
BOUNDARY WALL
COMPONENTS OF PROJECT
4.6.9 Summary
The WBS in the context of this Guidelines is not strictly intended to define and
resources and duration to achieve the final deliverables under the scope of the
project, but rather to emphasize or highlight those final products of the project
that would contribute to erosion and sediment issues during project
implementation. This WBS can then be complemented or integrated with the
“overall WBS” of the Contractor for the project.
To this end, those deliverables that would involve any activity that changes the
physical conditions of land form, vegetation and hydrology, creates bare soil, or
otherwise may cause erosion or sedimentation such as, site clearing, removal of
vegetation, stripping, grading, grubbing, excavating, filling, logging and storing
of materials, etc. would be given more attention when creating these groups of
project components.
In the above sections, we have discussed the need to break down a project into
manageable phases as well as to restructure a project by identifying relevant
project components, for the benefit of controlling erosion and sedimentation that
may arise during the implementation of a project.
In this section, we will look at the subsequent step to be taken once we have
identified those project components of a project that we believe which will
involve land disturbing activities that may contribute to accelerated erosion and
sedimentation issues on site. It should be stressed at this point that the key
objective of these identification (whether of phasing, project components or
project activities) is not to dictate or define the methodology on how the
Contractor should carry out his works, but more so for assisting his project team
to be aware of those activities that would typically alter a stable site condition
into one where the rate of erosion and sedimentation becomes accelerated (as
compared to the natural process), to the extent that such alterations of the natural
conditions are likely to pollute the downstream sensitive receivers such as rivers
or water intakes.
Having said the above, the LD-P2M2 practitioners should always keep in mind
that there is always more than one way in dealing with the identification of the
4-71
GUIDELINES ON LD-P2M2
project activities (as well as the project components in the previous section), and
that all projects are different from one another. Therefore, a particular approach
for activity identification that is suitable for one project may not be applicable
for another project which is situated at a different location or of a different
nature. The most important point to remember is that in whatever form a project
is restructured, whether it is based on project components and/or project
activities, the key justification that ought to accompany such approach is that
land disturbing activities that need to be adequately controlled and protected
against the elements of erosion and sedimentation from occurring should be
readily be identified.
The above definition for identifying project activities from the view of project
management can also be applied for the purposes of addressing erosion and
sedimentation. Following on from the above discussions on work breakdown
structures, identifying phasing and project components, let‟s now look at the
approach to identify project activities and their associated scope of work.
The simple rule to remember is this: the key purpose of this Guidelines of going
through with these identification exercises is that we are not trying to override
the way on how the Contractor executes his project, but rather to highlight to the
attention of the Project Proponent and his Contractor on the “where” and “when”
and “how” erosion and sedimentation may occur from their particular project
site, so that early attention could be given by these parties on the resources
required and the measures to be implemented prior to the actual physical works.
With that in mind, one should not be intimidated during the formulation of the
WBS in the context of erosion and sedimentation, and should not be overly
worried about not producing a comprehensive enough list of project activities or
scope of work for the identified project components. The most important thing
to note, however, is that the WBS and associated project activities have
adequately covered the major land disturbance activities that would be involved
for those particular project components, and this should be a relatively easier
task to undertake. With these critical elements identified and documented, the
Project Proponent and Contractor would have been then made aware of these
potential issues, if they don‟t already know, and could be prepared to take the
appropriate actions to minimize the occurrence of these issues.
Following from the above discussion, let‟s now take a look at how to expand the
simple work breakdown structures for the few examples previously created in
the preceding section. Firstly, let‟s review the proposed sewage treatment plant
project as shown in Figure 4.18.
In this earlier example, it was identified previously the project components could
be broken down to three parts, in lieu of the typical breakdown based on
disciplines, namely, Road, Bridge and Building Site. Following on from these
components, we can then identify the possible project activities for each
component as follows:
a) Component 1 – Road
Project Activities: Typically the construction of roads will involve site
clearance, grading and laying of road works including its drainage. Preparing
the road right-of-way or construction area will normally involve clearing and
grubbing activities, and particularly so for this project which is within a forest
area. During the clearing phase, trees are felled, while the grubbing activity
4-73
GUIDELINES ON LD-P2M2
refers to the clearing and removal of stumps and organic debris. After the
clearing works are completed, the following major activity will involve
earthworks which will involve excavation of the existing land to a suitable level
so that road construction may begin. The earthworks can take the form of either
excavation in the form of cuts or the construction of embankments to carry an
elevated highway; typically, both will be necessary and movement of earth from
one part of the site to the next will be inevitable. Such cut and fill would be
done with as little waste created or as little extra material required as disposal or
collection due to the cost involved in material transportation. Also under this
earthwork will be the provision of drainage and compaction of the road materials
to the appropriate level.
Some of the typical earthmoving equipment that will be used for the above
works include the following:
Drag Line, which allows excavation below its own level and is essentially
equipped with a bucket on the end of a jib for bulk excavation;
Dump Lorries, which will be used for transferring material from one part
of the site to another;
Shovels, which are normally wheeled vehicles and are used to fill up the
lorries;
Hydraulic Excavators, which are typically used due to their small capacity
and flexibility, for excavating below lorry level;
Grader, which will be used to level out deposited fill, to be ready for
compaction; and
In summary, the project activities that are identified for the Project Component
Road include the following: site clearance, site grading, and drainage works.
4-74
GUIDELINES ON LD-P2M2
b) Component 2 - Bridge
Project Activities: To simplify the analysis for the bridge construction,
particularly with a view to focus only on those activities that may give rise to
erosion and sedimentation, one can basically narrow down the related key
activities to involve site clearance for the construction of the bridge piers,
although the extent of the clearing works would be more limited and confined
to the footprint of the piers (as compared to the extent required for the initial
site clearance for the road works. Upon completion of establishing the work
zones for the piers, the next key activity will involve excavation for the pier
foundation. This could involve borehole drilling for the foundation structure,
which is then followed by the erecting of the pier and elevated structures. In
summary, the project activities that are identified for the Project Component
Bridge include simply the following: site clearance, borehole drilling, and
column and elevated structures.
Subsequent to the above identification of the project activities, the next task
will be the further expansion of the WBS for the project, by identifying the
corresponding list of activities or the scope of work. Again, the key to this
identification is not to be bogged down by the engineering technicality or
complexity on the actual work itself but rather to look at the process of work in
a simple manner but adequate to describe the activities required. Let‟s take a
look at how each of the project activities identified above is described with its
dedicated scope of work, and again, keeping the attention on activities related
to or contributing to erosion and sediment issues, and not to be distracted by
the technical methodologies in the executing the works.
Component - Road; Activity - Site Grading: Under this activity, which was
preceded by the previous site clearance works, the scope of work that could be
prescribed include the following:
a. Identify flowpath - For road works, it common for the drainage flow to be
compatible with the road elevation but sometimes not practical as the road
elevation might take an “uphill‟ and „downhill” grades. As such, it is important
for the drainage team to clearly mark physically on the site the proposed final
invert levels of the finished drainage works, which are typically laid adjacent to
the road;
c. Mark storage zones – This involves physically marking on the ground the
dedicated areas reserved for stockpiling both excavated materials from the
drainage works, as well as material storage areas for the construction materials
and machineries;
d. Excavate trench - Upon the identification of the above, the next work
activity will involve the excavation of the trench for the drainage placement.
This activity is expected to generate construction waste materials from the
excavation works, and once the trench is formed, possible dewatering works
to maintain the trench in a dry condition to lay the drainage works.
e. Drainage works – This step under the project activity involves several
elements including laying of the drainage parts, water tests, and backfilling of
the trench. More often than not, the drainage works may take place in
concurrent with the road construction activity (Note: a separate road
construction activity has not been included here for simplicity but it is
assumed that the road works are being carried out at the same time with the
drainage works).
Component - Bridge; Activity - Site Clearance: The scopes of work for this
activity are more or less similar to the same activity identified under the Road
Construction in that the scope would also involve undertaking survey,
marking site boundary, identifying interfaces, identifying clearance extent
and clearing works. However, there is a distinct difference between the
clearing works for the Road and for the Bridge construction due to the nature
and location of these components, and hence in the types of the pollution
4-78
GUIDELINES ON LD-P2M2
a) Undertake survey – The site survey under this scope is to identify the
locations of the permanent structures of the bridge, in relation to the river that
the bridge will cross over. In terms of erosion and sediment, the most critical
of these structures would be the foundations of the bridge, as well as the
surrounding permanent works to protect the river banks and slopes;
ancillary activities other than the physical borehole sizes should be allowed,
such as space to accommodate the heavy machineries that will be deployed
during the drilling, space to implement relevant pollution prevention
mitigation measures such as noise or visual barriers; buffer zones, dewatering
activities, silt traps, sediment ponds or settling basins, drainage, to name a
few;
d) Export excavated soil – Exporting the excavated soil or earth materials out
of drilling site, as well as by-products from the treatment of the construction
wastewaters.
a) Undertake survey – The site survey under this scope would be to identify
the location of the footprint for the STW building structure. In terms of
erosion and sediment, the site clearing works would involve a larger footprint
as compared to the previous two components, and consequently, the amount
4-80
GUIDELINES ON LD-P2M2
b) Mark buffer zones – This involves physically marking on the ground the
boundaries of the buffer zones to protect the nearby sensitive receivers. The
purpose of this scope is to provide a constant and visible reminder to the
workers on site to avoid carrying out their works outside of the stated limits;
4-81
GUIDELINES ON LD-P2M2
e) Export excavated soil – Exporting the excavated soil or earth materials out
of excavation site, as well as by-products from the treatment of the
construction wastewaters.
The above discussion on the proposed WBS for the sewage treatment project is
illustrated in the following figures. In summary, it is important to remember
that the proposed WBS is not meant to be an „engineering‟ work breakdown,
but rather for the purposes of this Guidelines, which is to identify the potential
sources of land disturbing activities that are likely to result in erosion and
sedimentation issues during the construction works. As can be seen, some of
the scope of work appears to be iterative for the different activities, but if these
are reviewed from the perspective of the potential erosion and sediment issues
resulting from the nature of their activities, then it would make sense that why
some of the scope of work is so fundamental for land disturbing activities. The
problem with today‟s site activities is that these fundamentals are either by-
passed or “forgotten” for the sake of achieving progress or to save some
money, which ultimately, resulted in the type of environmental catastrophes
that we see today.
4-82
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
BOREHOLE EXCAVATION
SITE DRILLING
GRADING
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
ROAD BRIDGE
BUILDING SITE
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake Undertake Identify Undertake Mark work Formwork Undertake Mark work Formwork
survey survey flowpath survey zones survey zones
Steelwork Steelwork
Mark site Mark surface Mark work/ Mark site Mark storage Mark site Mark buffer
Concrete pour Concrete pour
boundary elevation buffer zones boundary zones boundary zones
Remove Remove
Identify Mark work/ Mark storage Identify Drilling works Identify Mark storage
formwork formwork
interfaces buffer zones zones interfaces interfaces zones
Export
Identify Grading works Excavate Identify excavated soil Identify Excavate
clearance trench clearance clearance foundation
extent extent extent Export
Drainage works
Clearing works Clearing works Clearing works excavated soil
In this example, let‟s take a look at how possible project activities could be
identified for the project components for a proposed highway project as
illustrated in Figure 4.22, namely, Temporary Roads, Permanent Roads,
Drainage System and River Crossings. Following on from these components,
we can then identify the possible project activities for each component as
shown in Figure 4.36:
Site Clearance
Site Grading
Temporary Drainage, and
Road Formation
Site Grading
Permanent Drainage, and
4-86
GUIDELINES ON LD-P2M2
Roadworks
This second component will involve the almost similar activities as the
previous component, except that now, the permanent road will be laid.
Whilst the temporary road provides initial access to the work site, the
permanent road will be the final product to be delivered by the Contractor.
After the site clearance has been completed, the anticipated activities will
involve: site grading of the cleared land to form the ground for the
permanent roadworks; creation of the permanent road drainage which is
typically located within or adjacent to the road; and finally, the construction
of the road. During the grading phase, more biomass or inert wastes will be
generated, leaving the ground exposed. The permanent road and drainage
works also will generate similar waste materials.
Component – Temporary Roads; Activity - Site Clearance: Under the activity “Site
Clearance”, it is anticipated that the typical scope of work to be undertaken (from a
simplified perspective) might include the following:
Component – Temporary Roads; Activity - Site Grading: Under this activity, which was
preceded by the previous site clearance works, the scope of work that could be
prescribed include the following:
b) Mark surface elevation – For road works, this is a relatively important task,
which involve marking physically on site the final surface levels of the
finished road. Not undertaking this step may involve abortive work at the
later stage, or if not rectified after the road construction, may result in
defects in terms of incorrect surface runoff flows, ponding, etc.;
and replaced by the permanent drainage. The likely scope of work for this project
activity may include the following:
c. Mark storage zones – This involves physically marking the dedicated areas
reserved for stockpiling both excavated materials from the drainage works,
as well as material storage areas for the construction materials and
machineries;
d. Excavate trench – This activity involves the excavation of the trench for
forming the temporary drainage, which will generate construction waste
materials from the excavation works and erosion potential, and hence
requiring dewatering and stockpiling provisions;
Component - Temporary Roads; Activity – Road Formation: This activity shall come
after the completion of the above drainage works, which were created as a BMP to
cater for runoff and sediment discharge from the temporary road works. The likely
scope of work for this project activity includes the following:
c) Mark work/buffer zones – Marking the boundaries for the buffer limits or
zones to avoid encroachment into areas outside of the limits, protect the
nearby sensitive receivers, including trees and forested area for this example,
to provide visible reminder to the workers on site to avoid venturing into
these areas or damaging the environment outside of their work areas
including any existing facilities in the surrounding vicinity of the project
site, roads, rivers, vegetation, residences, etc;
d) Mark storage zones – Marking the dedicated areas reserved for stockpiling
both excavated materials from the temporary road works, as well as material
storage areas for the construction materials and machineries; and
b) Mark surface elevation – This involves marking physically on site the final
surface levels of the finished permanent road surface levels. Not
undertaking this step may involve abortive work at the later stage, or if not
rectified after the road construction, may result in defects in terms of
incorrect surface runoff flows, ponding, etc.;
c) Mark work/buffer zones – This covers marking of work limits and buffer
zones to protect surrounding environment;
previous temporary drainage alignment. The likely scope of work for this project
activity includes the following:
c. Mark storage zones – This involves physically marking the dedicated areas
reserved for stockpiling of both excavated materials from the drainage
works, as well as material storage areas for the construction materials and
machineries;
d. Excavate trench – This activity involves the excavation of the trench for
forming the permanent drainage;
Component - Permanent Roads; Activity – Road Formation: This activity may run
concurrently with the permanent drainage works, but shall be after the completion of
the site grading works. The likely scope of work for this project activity includes the
following:
c) Mark work/buffer zones – Marking the boundaries for the buffer limits
or zones to avoid encroachment into areas outside of the limits, protect
the nearby sensitive receivers, including trees and forested area, and to
provide visible reminder to the workers on site to work within the
prescribed limits so as to protect the environment and any existing
4-92
GUIDELINES ON LD-P2M2
b) Mark buffer zones – This involves physically marking on the ground the
boundaries of the buffer zones to protect the nearby sensitive receivers
during the excavation works. This marking will help to remind the workers
on site to avoid carrying out their works outside of the stated limits to
protect the nearby environment;
e) Export excavated soil – Exporting the excavated soil or earth materials out
of excavation site, as well as by-products from the treatment of the
construction wastewaters.
c. Mark storage zones – Marking on the ground the dedicated areas reserved
for stockpiling both excavated materials from the drainage works, as well as
material storage areas for the construction materials and machineries;
d. Excavate trench - Excavation of the trench for the drainage placement. This
activity is expected to generate construction waste materials from the
excavation works, and once the trench is formed, possible dewatering works
to maintain the trench in a dry condition to lay the drainage works.
a. Mark storage zones - Marking the dedicated areas reserved for stockpiling
backfill materials which will be imported into the site, as well as storage
areas for other construction materials and machineries;
The backfill materials shall be stored and protected from the rain at the
designated storage areas mentioned above;
c. Compaction – Upon backfilling the trench, compaction will take place and
limited erosion and sediment issues are expected from this activity.
Component – River Crossing; Activity - Site Clearance: The scope of work for this
activity shall be carefully planned due to proximity of the works to residential areas as
well as sensitive receivers such as the rivers or streams. Due to the nature and location
of this component, the likely scope of work include the following:
b) Mark site boundary - Marking the site boundaries of the physical structures
of the river crossing such as its foundation in the form of piers or columns,
or any embankments which is part of the river crossing‟s design, with the
aim to make sure that the works team is aware of where the prescribed
works area within which the structural construction is confined to, and to
avoid encroachment into areas outside of the footprint of these structures;
Component – River Crossing; Activity – Foundation Works: Under this activity and
viewing the process of this foundation work from a simplified perspective, the scope of
work for this activity includes the following:
a) Mark work zones – It is important to mark the required working zones and
limits for the construction of the foundation works, noting that adequate
working space for other ancillary activities other than the physical column
sizes shall be allowed. This allows space to accommodate the heavy
machineries that will be deployed during the excavation, and also space to
implement the relevant pollution prevention mitigation measures;
Component – River Crossing; Activity – Elevated Structures: The scope of work for this
activity has been formulated to simply include the following works: formwork;
steelwork; concrete pour; and formwork removal. As the scope of work has suggested,
there are limited land disturbance activities that would be involved during the above
works, except for the need to identify proper areas for stockpiling and storing the
construction materials needed for the works and construction wastes generated from
these scopes of work.
4-96
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
Scope of work Scope of Scope of work Scope of work Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work
work work
Undertake Identify Undertake Identify Mark work zones Mark storage Undertake Mark work zones Formwork
survey Undertake flowpath survey flowpath Identify zones survey
Mark buffer Mark storage Steelwork
survey flowpath
Mark site Mark work/ Mark site Mark work/ zones Import Mark site zones
boundary Mark boundary Concrete pour
buffer zones boundary buffer zones Mark work/ backfill
Mark storage Mark buffer
surface buffer zones Remove
Identify Mark storage Mark work/ Mark storage zones Compaction Identify zones
elevation formwork
interfaces zones buffer zones zones Mark storage interfaces
Excavate Excavate
Mark work/ zones
Identify Excavate Mark storage Excavate trench foundation Identify foundation
buffer
clearance trench zones Excavate clearance extent
zones Drainage works Export excavated Formwork/Steel
extent trench
Drainage Road works soil Clearing works work
Grading
Clearing works works Drainage
works Concrete pour
SITE ROAD works
GRADING WORKS
b) Component 2 - Roads
For this project component, the potential activities include the following:
Site Grading
Roadworks
Drainage
c) Component 3 – Drainage
The project activities associated with this component include:
Excavation
Drainage works
Backfill
d) Component 4 – Buildings
For this project component, the potential activities include the following:
Site Clearance
Excavation
Foundation
e) Component 5 – Pumphouse/STW
For this project component, the potential activities include the following:
4-99
GUIDELINES ON LD-P2M2
Site Clearance
Excavation
Foundation
Again, a simple comparison of the above project activities with those described
for the STW and Highway examples reveals much similarities. To avoid
repetitions, the corresponding scope of work for each of the project activities
will only be listed below without detailed elaboration, except for those scopes of
work which were not covered previously above.
Coincidently, the project activities and scope of work for the Component –
Pumphouse/STW are the same as the preceding component; therefore, the list is not
repeated here.
The overall scope of work for all the project components and activities is illustrated in
Figure 4.39.
4-102
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
DRAINAGE
PROJECT ACTIVITIES
COMPONENTS OF PROJECT
SITE TEMPORARY ROAD EXCAVATION DRAINAGE BACKFILL EXCAVATION SITE EXCAVATION FOUNDATION
CLEARANCE ROADS WORKS WORKS CLEARANCE
Scope of work Scope of Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work Scope of work
work work
Undertake Undertake Mark work zones Mark storage Mark work zones Undertake Mark work zones Mark work
survey Undertake survey Identify zones survey zones
Mark buffer Mark buffer zones Mark buffer
survey flowpath
Mark site Mark site zones Import Mark site zones Mark storage
boundary Mark site boundary Mark work/ backfill Mark storage boundary zones
Mark storage zones Mark storage
boundary buffer zones
Identify Mark work/ zones Compaction Identify zones Mark buffer
interfaces Mark work/ buffer zones Mark storage Excavate interfaces zones
Excavate foundation Excavate
buffer zones zones
Identify Mark storage foundation Identify foundation Excavate
clearance Mark storage zones Excavate Export excavated clearance extent foundation
Export excavated soil Export excavated
extent zones trench
Road works soil Clearing works soil Formwork/Steel
Clearing works Road works Drainage work
works SITE
FOUNDATION Concrete pour
SITE CLEARANCE
DRAINAGE
GRADING
Scope of work
Scope of work
Scope of work Scope of work Mark work zones
Undertake survey
Undertake survey Identify flowpath Mark storage zones
Mark site boundary
Mark surface elevation Mark work/ buffer zones Mark buffer zones
Identify interfaces
Mark work/ buffer zones Mark storage zones Excavate foundation
Identify clearance extent
Grading works Excavate trench Formwork/Steelwork
Clearing works
Drainage works Concrete pour
For the proposed project layout as indicated in Figure 4.27 for this main
drainage development, the key project components have been previously
identified to be trenching; roads; drainage; and pump house, with possible
land disturbing activities comprising the following:
Land clearing
Excavation works
Cut and fill for slope formation
Stockpiling of earthwork materials
Dewatering of trench
Earthworks for land formation
Roadworks and drainage;and
Backfilling
Again, the project activities associated with their relevant components for this
example project are quite similar to the previous examples already discussed
in the above sections, and are listed in Table 4.1 below:
Description of the scope of work for nearly all of the project activities listed
in the above table has previously been discussed for the earlier example
projects, except for the activity “Road Diversion”. As seen in Figure 4.27,
the new main drainage consisting of 1500mm x 1500mm box culvert is
proposed to be laid below an existing 4.5m wide road, which is currently a
“live road”. To facilitate the drainage works, some form of traffic diversion
4-105
GUIDELINES ON LD-P2M2
a) Undertake survey
b) Mark site boundary
c) Mark work/buffer zones
d) Mark storage zones
e) Roadworks
The overall scope of work for all the project components and activities for this
example project is illustrated in Figure 4.41.
4-106
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
SITE ROAD
DRAINAGE
GRADING WORKS
COMPONENTS OF PROJECT
Scope of work Scope of Scope of work Scope of Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work
work work work
Undertake Mark work Undertake Mark work zones Mark storage Undertake Mark work zones Formwork
survey Undertake zones Mark storage survey Identify zones survey
Mark buffer Mark buffer Steelwork
survey zones flowpath
Mark site Mark buffer Mark site zones Import Mark site zones
boundary Mark site boundary Concrete pour
zones Import boundary Mark work/ backfill
Mark storage Mark storage
boundary backfill buffer zones Remove
Identify Mark storage Mark work/ zones Compaction Identify zones
interfaces Mark work/ interfaces formwork
zones Compaction buffer zones Mark storage
Excavate Excavate
buffer zones
Identify Excavate Mark storage foundation Identify foundation
zones
clearance foundation zones Excavate clearance extent
extent Export excavated Export excavated
Mark trench
Export Road works soil Clearing works soil
storage
Clearing works excavated soil Drainage
zones
SITE DRAINAGE works
Road GRADING
works
A river check dam is typically provided for various reasons, including for a
water supply source (for irrigation, potable use, etc), for small scale power
generation facilities, or for application of some form of physical treatment to
the water (e.g., sediment removal). Regardless of the purposes for creating a
river check dam, the major civil engineering processes that would be involved
in the check dam creation normally consist of:
Land clearing
Excavation of diversion channel
Protection of channel bed, slopes and bank
Stockpiling of earthwork materials
Excavation of river bed for dam foundations
Dewatering, and
Concreting
The project activities associated with their relevant components for this
example project are listed in Table 4.2:
4-109
GUIDELINES ON LD-P2M2
Except for the activity “Diversion Works”, description of the scope of work
for the other project activities listed in the above table has previously been
discussed. In simple terms, the creation of a diversion channel comprises
excavating a new trench or channel on the adjacent ground next to the existing
river, with the alignment of the diversion channel more or less being parallel
to the section of the existing river where works will take place. At the
upstream and downstream ends of the connections (or diversion) points
between the existing river and the new channel, cofferdams will be built to act
as separator between these two watercourses. Essentially, once the
“diversion” has been made, the diversion channel will act as if the existing
river is still there, but in fact, that section of the existing river is actually now
dry to allow construction works to take place. Once the check dam or any
other intended works are completed in the dry river section, the river flow
from the diversion channel will then be diverted back to the original river
alignment, and the temporary channel will be backfill to ground level
followed by removal of the cofferdams. In this regard, the scope of work for
this particular project activity includes:
The overall scope of work for all the project components and activities for this
example project is illustrated in Figure 4.43.
4-110
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
DRAINAGE
COMPONENTS OF PROJECT
RIVER WORKS
DAM STRUCTURES
Scope of work Scope of Scope of work Scope of Scope of work Scope of Scope of Scope of work Scope of work
work work work work
Undertake Mark work Mark work zones Mark work Formwork
survey Undertake zones Mark work Undertake Identify zones
Mark buffer Steelwork
survey zones survey flowpath
Mark site Mark buffer zones Mark storage
Concrete pour
boundary Mark site zones Mark buffer Mark site Mark work/ zones
Mark storage
boundary zones boundary buffer zones Remove
Identify Mark storage zones Mark buffer
formwork
interfaces Mark work/ zones Create Mark work/ Mark storage zones
Excavate
buffer zones diversion buffer zones zones
Identify Excavate foundation Excavate
clearance Mark storage foundation Mark storage Excavate foundation
Export excavated
extent zones zones trench
Export soil Formwork/Steel
Clearing Lay crossing excavated soil Road works Drainage work
works works Concrete pour
The project activities for this example project are listed in Table 4.3 below:
The overall scope of work for this example project is illustrated in Figure
4.45.
4.7.8 Summary
The term “project activities” is taken to mean the specific tasks needed to be
done in order to produce the project's deliverables in project management,
4-113
GUIDELINES ON LD-P2M2
but can also be applied to the topic of erosion and sediment control by
identifying the related project activities and their associated scope of work
following the identification of the project components.
It was shown in the few examples that regardless of the nature of a major civil
engineering project, the pre-construction activities which mainly involve land
disturbing activities are basically quite similar when compared to other
projects except for certain site specific conditions. The key point to
remember during the breaking down or identifying these activities and/or
scope of work is that the purpose is to establish these project activities
particularly to those relating to land disturbing activities so that suitable
environmental method statements can subsequently be developed.
Again, it should be stressed that the key objective of these identification is not
to dictate or define the methodology on how the Contractor should carry out
his works, but more so for assisting his project team to be aware of those
activities that would typically alter a stable site condition into one where the
rate of erosion and sedimentation becomes accelerated (as compared to the
natural process), to the extent that such alterations of the natural conditions
are likely to pollute the downstream sensitive receivers such as rivers or water
intakes.
on how the Contractor executes his project, but rather to highlight to the
attention of the Project Proponent and his Contractor on the “where” and
“when” and “how” erosion and sedimentation may occur from their particular
project site, so that early attention could be given by these parties on the
resources required and the measures to be implemented prior to the actual
physical works. The important thing to note is that the WBS and associated
project activities have adequately covered the major land disturbance
activities that would be involved for those particular project components, and
this should be a relatively easier task to undertake.
4-115
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
TEMPORARY DRAINAGE
ROADS WORKS
COMPONENTS OF PROJECT
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake Undertake Undertake survey Undertake Undertake Mark work Identify Mark storage
survey survey survey survey zones flowpath zones
Mark site boundary
Mark site Mark site Mark surface Mark site Mark buffer Mark work/ Import backfill
Mark work/ buffer
boundary boundary elevation boundary zones buffer zones
zones Compaction
Identify Mark work/ Mark work/ Mark work/ Mark storage Mark storage
Grading works
interfaces buffer zones buffer zones buffer zones zones zones
Identify Mark storage Grading works Mark storage Excavate Excavate trench
clearance zones zones foundation
extent Drainage works
Road works Road works Export
Clearing excavated soil
works
For each of the WBS formulated for the preceding six example projects, the
associated EMS for the identified project activities are listed in the following
Figures 4.46 to 4.51. As can be seen from these figures, the attention given
by these EMS is not on the “technical knowhow” on how to do the work, but
rather on the pollution prevention and mitigation measures that shall be
implemented during the undertaking of the scope of work for that particular
project activity.
zones controls
- Location of silt fences - Mark temporary drainage
- Indicate limits of works - Indicate silt traps/sediment
- Indicate type/extent of ponds
erosion controls Add Construction Notes
- Mark temporary drainage
- Indicate silt traps location
Add Construction Notes
PROJECT ACTIVITY: PROJECT ACTIVITY:
DRAINAGE BOREHOLE DRILLING
Identify dewatering discharge Identify dewatering discharge
location location
Identify/mark perimeter controls Identify/mark perimeter controls
Identify/mark environmental Identify/mark environmental
buffer zones buffer zones
Identify limits of works, 100m Identify limits of works, 100m
clearance clearance
Identify stockpile locations Identify stockpile locations
Mark BMPs on drawings: Mark BMPs on drawings:
- Boundary for environmental - Boundary for environmental
buffer zones buffer zones
- Location of sediment pond - Location of silt fences
location - Location of sediment pond
- Indicate limits of works location
- Indicate type/extent of - Indicate limits of works
erosion controls - Indicate type/extent of
Add Construction Notes erosion controls
Add Construction Notes
PROJECT ACTIVITY: PROJECT ACTIVITY:
ELEVATED STRUCTURES EXCAVATION
Identify limits of works, 100m Identify dewatering discharge
clearance location
Identify stockpile locations Identify/mark perimeter controls
Mark BMPs on drawings: Identify/mark environmental
- Perimeter drainage along site buffer zones
boundary Identify limits of works, 100m
- Location of silt fences clearance
- Indicate limits of works Identify stockpile locations
- Indicate stockpile location Mark BMPs on drawings:
- Mark temporary drainage - Boundary for environmental
- Indicate silt traps location buffer zones
4-119
GUIDELINES ON LD-P2M2
PROJECT ACTIVITY:
CONCRETING
Identify/mark perimeter controls
Identify limits of works, 100m
clearance
Identify stockpile locations
Mark BMPs on drawings:
- Perimeter drainage along site
boundary
- Indicate sediment pond
location
- Indicate limits of works
- Mark temporary drainage
- Indicate type/extent of
erosion controls
Add Construction Notes
As seen from the above table, one may wonder why the majority of the EMS
listed above is quite similar to one another even though the EMS are
dedicated for different project activities. The answer is really quite
straightforward, and it is because the sole objective of these EMS is to control
erosion and sediment issues due to these land disturbing activities. As such, if
the basic principles of LD-P2M2 are applied diligently into each of the land
disturbing activities, it is not surprising then to see a set of the environmental
method statements being reapplied from one project activity to another, all for
the sake of achieving the same goal: to minimise (or prevent if possible) the
impacts of erosion and sediment from these activities.
The basic principles of LD-P2M2 are discussed and elaborated in the other
Chapters of this Guidelines, but are listed below again in view of their
importance:
4-120
GUIDELINES ON LD-P2M2
The above EMS has been formulated specifically for the various project
activities that were identified in the example projects for illustration purposes.
EMS can also be formulated generically to target each of the land disturbing
activities which were discussed in Chapter 3 and these are included in the
Appendix.
4-121
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) ADJACENT TO FOREST RESERVE
COMPONENTS OF PROJECT
ROAD BRIDGE
BUILDING SITE
SITE CLEARANCE SITE GRADING DRAINAGE SITE CLEARANCE BOREHOLE ELEVATED SITE CLEARANCE EXCAVATION CONCRETING
DRILLING STRUCTURES
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Scope of work Scope of work
Undertake survey Undertake survey Identify flowpath Undertake survey Undertake survey Mark work zones Formwork
Mark work zones Formwork
Mark site boundary Mark surface Mark work/ buffer Mark site boundary Mark site boundary Mark buffer zones Steelwork
elevation zones Mark storage zones Steelwork
Identify interfaces Identify interfaces Identify interfaces Mark storage zones Concrete pour
Mark work/ buffer Mark storage zones Drilling works Concrete pour
Identify clearance Identify clearance Identify clearance Excavate foundation Remove formwork
zones Export excavated
extent Excavate trench extent Remove formwork extent
soil Export excavated
Grading works soil
Clearing works Drainage works Clearing works Clearing works
SITE CLEARANCE SITE GRADING DRAINAGE SITE CLEARANCE BOREHOLE DRILLING ELEVATED SITE CLEARANCE EXCAVATION CONCRETING
A. Identify sensitive receivers A. Identify/mark perimeter A. Identify dewatering A. Identify sensitive receivers A. Identify dewatering STRUCTURES A. Identify sensitive A. Identify dewatering A. Identify/mark perimeter
B. Identify/mark perimeter controls discharge location B. Identify/mark perimeter discharge location A. Identify limits of receivers discharge location controls
controls B. Identify/mark B. Identify/mark perimeter controls B. Identify/mark perimeter works, 100m B. Identify/mark perimeter B. Identify/mark perimeter B. Identify limits of works,
C. Identify/mark environmental buffer zones controls C. Identify/mark controls clearance controls controls 100m clearance
environmental buffer zones C. Identify limits of works, C. Identify/mark environmental buffer zones C. Identify/mark B. Identify stockpile C. Identify/mark C. Identify/mark C. Identify stockpile
D. Identify limits of works, 100m clearance environmental buffer zones D. Identify limits of works, environmental buffer zones locations environmental buffer zones environmental buffer zones locations
100m clearance D. Identify stockpile locations D. Identify limits of works, 100m clearance D. Identify limits of works, C. Mark BMPs on D. Identify limits of works, D. Identify limits of works, D. Mark BMPs on
E. Identify stockpile locations E. Mark BMPs on drawings: 100m clearance E. Identify stockpile locations 100m clearance drawings: 100m clearance 100m clearance drawings:
F. Mark BMPs on drawings: - Perimeter drainage along E. Identify stockpile F. Mark BMPs on drawings: E. Identify stockpile - Perimeter E. Identify stockpile E. Identify stockpile - Perimeter drainage
- Perimeter drainage along site boundary locations - Perimeter drainage along locations drainage along site locations locations along site boundary
site boundary - Boundary for F. Mark BMPs on drawings: site boundary F. Mark BMPs on drawings: boundary F. Mark BMPs on drawings: F. Mark BMPs on drawings: - Indicate sediment pond
- Entrance controls for environmental buffer zones - Boundary for - Boundary for - Boundary for - Location of silt - Perimeter drainage along - Boundary for location
vehicles - Location of silt fences environmental buffer zones environmental buffer zones environmental buffer zones fences site boundary environmental buffer zones - Indicate limits of works
- Boundary for - Indicate limits of works - Location of sediment - Location of silt fences - Location of silt fences - Indicate limits of - Boundary for - Location of silt fences - Mark temporary
environmental buffer zones - Indicate type/extent of pond location - Indicate limits of works - Location of sediment works environmental buffer zones - Location of sediment drainage
- Location of silt fences erosion controls - Indicate limits of works - Indicate type/extent of pond location - Indicate stockpile - Location of silt fences pond location - Indicate type/extent of
- Indicate limits of works - Mark temporary drainage - Indicate type/extent of erosion controls - Indicate limits of works location - Indicate limits of works - Indicate limits of works erosion controls
- Indicate type/extent of - Indicate silt traps/sediment erosion controls - Mark temporary drainage - Indicate type/extent of - Mark temporary - Indicate type/extent of - Indicate type/extent of F. Add construction notes
erosion controls ponds - Mark temporary drainage - Indicate silt traps location erosion controls drainage erosion controls erosion controls
- Mark temporary drainage F. Add construction notes - Indicate silt G. Add construction notes G. Add construction notes - Indicate silt traps - Mark temporary drainage G. Add construction notes
- Indicate silt traps location traps/sediment ponds location - Indicate silt traps location
G. Add construction notes F. Add construction notes D. Add construction G. Add construction notes
notes
Figure 4.46: Environmental Method Statements for STW Project
4-122
GUIDELINES ON LD-P2M2
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
Scope of work Scope of Scope of work Scope of work Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work
work work
Undertake Identify Undertake Identify Mark work zones Mark storage Undertake Mark work zones Formwork
survey Undertake flowpath survey flowpath Identify zones survey
Mark buffer Mark storage Steelwork
survey flowpath
Mark site Mark work/ Mark site Mark work/ zones Import Mark site zones
boundary Mark boundary Concrete pour
buffer zones boundary buffer zones Mark work/ backfill
Mark storage Mark buffer
surface buffer zones Remove
Identify Mark storage Mark work/ Mark storage zones Compaction Identify zones
elevation formwork
interfaces zones buffer zones zones Mark storage interfaces
Excavate Excavate
Mark work/ zones
Identify Excavate Mark storage Excavate trench foundation Identify foundation
buffer
clearance trench zones Excavate clearance extent
zones Drainage works Export excavated Formwork/Steel
extent trench
Drainage Road works soil Clearing works work
Grading
Clearing works works Drainage
works Concrete pour
SITE ROAD works
GRADING WORKS
PROJECT TITLE: PROPOSED 10 KILOMETER NEW HIGHWAY THROUGH REMOTE RURAL AREA
COMPONENTS OF PROJECT
SITE TEMPORARY ROAD EXCAVATION DRAINAGE BACKFILL EXCAVATION SITE EXCAVATION FOUNDATION
CLEARANCE ROADS WORKS WORKS CLEARANCE
Scope of work Scope of Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work Scope of work
work work
Undertake Undertake Mark work zones Mark storage Mark work zones Undertake Mark work zones Mark work
survey Undertake survey Identify zones survey zones
Mark buffer Mark buffer zones Mark buffer
survey flowpath
Mark site Mark site zones Import Mark site zones Mark storage
boundary Mark site boundary Mark work/ backfill Mark storage boundary zones
Mark storage zones Mark storage
boundary buffer zones
Identify Mark work/ zones Compaction Identify zones Mark buffer
interfaces Mark work/ buffer zones Mark storage Excavate interfaces zones
Excavate foundation Excavate
buffer zones zones
Identify Mark storage foundation Identify foundation Excavate
clearance Mark storage zones Excavate Export excavated clearance extent foundation
Export excavated soil Export excavated
extent zones trench
Road works soil Clearing works soil Formwork/Steel
Clearing works Road works Drainage work
works SITE
FOUNDATION Concrete pour
SITE CLEARANCE
DRAINAGE
GRADING
Scope of work
Scope of work
Scope of work Scope of work Mark work zones
Undertake survey
Undertake survey Identify flowpath Mark storage zones
Mark site boundary
Mark surface elevation Mark work/ buffer zones Mark buffer zones
Identify interfaces
Mark work/ buffer zones Mark storage zones Excavate foundation
Identify clearance extent
Grading works Excavate trench Formwork/Steelwork
Clearing works
Drainage works Concrete pour
COMPONENTS OF PROJECT
PROJECT ACTIVITIES
PROJECT ACTIVITIES PROJECT ACTIVITIES PROJECT ACTIVITIES
PROJECT ACTIVITIES
A.Identifysensitive A.Identify/mark A.Identify/mark A.Identify/mark A.Identifydewatering A.Identifydewatering A.Identifydewatering A.Identify/mark A.Identifysensitive A.Identifydewatering A.Identifydewatering A.Identifydewatering
receivers perimetercontrols A.Identifysensitive A.Identifydewatering
perimetercontrols perimetercontrols dischargelocation dischargelocation perimetercontrols receivers
B.Identify/mark B.Identify/mark dischargelocation dischargelocation dischargelocation receivers dischargelocation dischargelocation
B.Identify/mark B.Identify/mark B.Identify/mark B.Identify/mark B. Identifystockpile B.Identify/markperimeter
perimetercontrols environmentalbuffer B.Identify/mark B.Identify/mark B.Identify/mark B.Identify/markperimeter B.Identify/mark B.Identify/mark
environmentalbuffer environmentalbuffer perimetercontrols perimetercontrols locations controls
C.Identify/mark zones perimetercontrols perimetercontrols perimetercontrols controls perimetercontrols perimetercontrols
zones zones C.Identify/mark C.Identify/mark C.MarkBMPson C.Identify/mark
environmentalbuffer C.Identifylimitsof C.Identify/mark C.Identify/mark C.Identify/mark C.Identify/mark C.Identify/mark C.Identify/mark
C.Identifylimitsof C.Identifylimitsof environmentalbuffer environmentalbuffer drawings: environmentalbufferzones
zones works,100m environmentalbuffer environmentalbuffer environmentalbuffer environmentalbufferzones environmentalbuffer environmentalbuffer
works,100mclearance works,100mclearance zones zones -Perimeterdrainage D.Identifylimitsofworks,
D.Identifylimitsof clearance zones zones zones D.Identifylimitsofworks, zones zones
D.Identifystockpile D.Identifystockpile D.Identifylimitsof D.Identifylimitsof alongsiteboundary 100mclearance
works,100m D.Identifystockpile D.Identifylimitsof D.Identifylimitsof D.Identifylimitsof 100mclearance D.Identifylimitsof D.Identifylimitsof
locations locations works,100m works,100mclearance -Indicatelimitsof E.Identifystockpile
clearance locations works,100mclearance works,100mclearance works,100m E.Identifystockpile works,100mclearance works,100m
E.MarkBMPson E.MarkBMPson clearance E.Identifystockpile works locations
E.Identifystockpile E.MarkBMPson E.Identifystockpile E.Identifystockpile clearance locations E.Identifystockpile clearance
drawings: drawings: E.Identifystockpile locations -Indicatetype/extentof F.MarkBMPson
locations drawings: locations locations E.Identifystockpile F.MarkBMPson locations E.Identifystockpile
-Perimeterdrainage -Perimeterdrainage locations F.MarkBMPson erosioncontrols drawings:
F.MarkBMPson -Perimeterdrainage F.MarkBMPson F.MarkBMPson locations drawings: F.MarkBMPson locations
alongsiteboundary alongsiteboundary F.MarkBMPson drawings: D.Addconstruction -Perimeterdrainagealong
drawings: alongsiteboundary drawings: drawings: F.MarkBMPson -Perimeterdrainagealong drawings: F.MarkBMPson
-Boundaryfor -Boundaryfor drawings: -Boundaryfor notes siteboundary
-Perimeterdrainage -Boundaryfor -Boundaryfor -Boundaryfor drawings: siteboundary -Boundaryfor drawings:
environmentalbuffer environmentalbuffer -Boundaryfor environmentalbuffer -Entrancecontrolsfor
alongsiteboundary environmentalbuffer environmentalbuffer environmentalbuffer -Boundaryfor -Entrancecontrolsfor environmentalbuffer -Boundaryfor
zones zones environmentalbuffer zones vehicles
-Entrancecontrols zones zones zones environmentalbuffer vehicles zones environmentalbuffer
-Locationofsiltfences -Locationofsiltfences zones -Locationofsediment -Boundaryfor
forvehicles -Locationofsilt -Locationofsiltfences -Locationofsiltfences zones -Boundaryfor -Locationofsiltfences zones
-Indicatelimitsofworks -Indicatelimitsofworks -Locationof pondlocation environmentalbuffer
-Boundaryfor fences -Locationofsediment -Locationofsediment -Locationofsilt environmentalbuffer -Locationofsediment -Locationofsilt
-Indicatetype/extentof -Indicatetype/extentof sedimentpondlocation -Indicatelimitsofworks zones
environmental -Indicatelimitsof pondlocation pondlocation fences zones pondlocation fences
erosioncontrols erosioncontrols -Indicatelimitsof -Indicatetype/extentof -Locationofsiltfences
bufferzones works -Indicatelimitsofworks -Indicatelimitsof -Locationof -Locationofsiltfences -Indicatelimitsof -Locationof
-Marktemporary -Indicatesilttraps/fence works erosioncontrols -Indicatelimitsofworks
-Locationofsilt -Indicatetype/extent -Indicatetype/extentof works sedimentpond -Indicatelimitsofworks works sedimentpond
drainage location -Indicatetype/extent G.Addconstruction -Indicatetype/extentof
fences oferosioncontrols erosioncontrols -Indicatetype/extentof location -Indicatetype/extentof -Indicatetype/extentof location
-Indicatesilt F.Addconstructionnotes oferosioncontrols notes erosioncontrols
-Indicatelimitsof -Indicatesilt G.Addconstruction erosioncontrols -Indicatelimitsof erosioncontrols erosioncontrols -Indicatelimitsof
traps/sedimentponds G.Addconstruction -Marktemporarydrainage
works traps/fencelocation notes G.Addconstruction works -Marktemporarydrainage G.Addconstruction works
F.Addconstructionnotes notes -Indicatesilttrapslocation
-Indicatetype/extent F.Addconstruction notes -Indicatetype/extent -Indicatesilttrapslocation notes -Indicatetype/extent
G.Addconstructionnotes oferosioncontrols oferosioncontrols
oferosioncontrols notes G.Addconstructionnotes
-Marktemporary G.Addconstruction G.Addconstruction
drainage notes notes
-Indicatesilttraps
location Figure 4.48: Environmental Method Statements for Housing Project (Cont.)
G.Addconstruction
notes
4-126
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
Scope of work Scope of Scope of work Scope of Scope of work Scope of work Scope of Scope of work Scope of work Scope of work Scope of work
work work work
Undertake Mark work Undertake Mark work zones Mark storage Undertake Mark work zones Formwork
survey Undertake zones Mark storage survey Identify zones survey
Mark buffer Mark buffer Steelwork
survey zones flowpath
Mark site Mark buffer Mark site zones Import Mark site zones
boundary Mark site boundary Concrete pour
zones Import boundary Mark work/ backfill
Mark storage Mark storage
boundary backfill buffer zones Remove
Identify Mark storage Mark work/ zones Compaction Identify zones
interfaces Mark work/ interfaces formwork
zones Compaction buffer zones Mark storage
Excavate Excavate
buffer zones
Identify Excavate Mark storage foundation Identify foundation
zones
clearance foundation zones Excavate clearance extent
Export excavated Export excavated
extent Mark trench
Export Road works soil Clearing works soil
storage
Clearing works excavated soil Drainage
zones
SITE DRAINAGE works
Road GRADING
works
ROAD WORKS
SITE TEMPORARY EXCAVATION DRAINAGE BACKFILL SITE CLEARANCE
EXCAVATION BACKFILL
CLEARANCE ROADS A. Identify/mark WORKS EXCAVATION CONCRETING
perimeter controls
A. Identify sensitive A. Identify dewatering A. Identify/ A. Identify dewatering A. Identify dewatering A. Identify sensitive
A. Identify/mark B. Identify/mark
discharge location mark discharge location A. Identify/ receivers
receivers perimeter controls environmental buffer discharge location A. Identify/mark
B. Identify/mark perimeter perimeter B. Identify/mark perimeter mark B. Identify/mark A. Identify dewatering
B. Identify/mark B. Identify/mark zones B. Identify/mark perimeter controls
controls controls controls perimeter perimeter controls discharge location
perimeter controls environmental buffer C. Identify limits of perimeter controls B. Identify limits of
C. Identify/mark B. Identify C. Identify/mark controls C. Identify/mark B. Identify/mark
C. Identify/mark zones works, 100m clearance C. Identify/mark works, 100m clearance
environmental buffer zones stockpile environmental buffer B. Identify environmental buffer perimeter controls
environmental C. Identify limits of D. Identify stockpile environmental buffer C. Identify stockpile
D. Identify limits of works, locations zones stockpile zones C. Identify/mark
buffer zones works, 100m locations zones locations
100m clearance C. Mark BMPs D. Identify limits of locations D. Identify limits of environmental buffer
D. Identify limits of clearance E. Mark BMPs on D. Identify limits of D. Mark BMPs on
E. Identify stockpile on drawings: works, 100m clearance C. Mark works, 100m zones
works, 100m D. Identify stockpile drawings: works, 100m clearance drawings:
locations - Perimeter E. Identify stockpile BMPs on clearance D. Identify limits of
clearance locations - Perimeter drainage E. Identify stockpile - Perimeter drainage
F. Mark BMPs on drainage locations drawings: E. Identify stockpile works, 100m
E. Identify stockpile E. Mark BMPs on along site boundary locations along site boundary
drawings: along site F. Mark BMPs on - Perimeter locations clearance
locations drawings: - Boundary for F. Mark BMPs on - Indicate sediment
- Boundary for boundary drawings: drainage F. Mark BMPs on E. Identify stockpile
F. Mark BMPs on - Perimeter drainage environmental buffer drawings: pond location
environmental buffer - Indicate - Boundary for along site drawings: locations
drawings: along site boundary zones - Boundary for - Indicate limits of
zones limits of works environmental buffer boundary - Perimeter drainage F. Mark BMPs on
- Perimeter - Boundary for - Location of silt fences environmental buffer works
- Location of silt fences - Indicate zones - Indicate along site boundary drawings:
drainage along site environmental - Indicate limits of zones - Mark temporary
- Location of sediment type/extent of - Location of silt fences limits of - Entrance controls - Boundary for
boundary buffer zones works - Location of drainage
pond location erosion - Location of sediment works for vehicles environmental buffer
- Entrance controls - Location of silt - Indicate type/extent of sediment pond location - Indicate type/extent
- Indicate limits of works controls pond location - Indicate - Boundary for zones
for vehicles fences erosion controls - Indicate limits of of erosion controls
- Indicate type/extent of D. Add - Indicate limits of works type/extent of environmental - Location of silt
- Boundary for - Indicate limits of - Indicate silt works F. Add construction
erosion controls construction - Indicate type/extent of erosion buffer zones fences
environmental works traps/fence location - Indicate type/extent notes
G. Add construction notes notes erosion controls controls - Location of silt - Location of
buffer zones - Indicate F. Add construction notes of erosion controls
G. Add construction D. Add fences sediment pond
- Location of silt type/extent of G. Add construction
SITE GRADING notes construction - Indicate limits of location
fences erosion controls notes
notes works - Indicate limits of
- Indicate limits of - Indicate silt
works A. Identify/mark perimeter controls DRAINAGE - Indicate works
traps/fence location
- Indicate B. Identify/mark environmental buffer zones type/extent of erosion - Indicate type/extent
F. Add construction
type/extent of C. Identify limits of works, 100m clearance A. Identify dewatering discharge location controls of erosion controls
notes
erosion controls D. Identify stockpile locations B. Identify/mark perimeter controls - Mark temporary G. Add construction
- Mark temporary E. Mark BMPs on drawings: C. Identify/mark environmental buffer zones drainage notes
drainage - Perimeter drainage along site boundary D. Identify limits of works, 100m clearance - Indicate silt traps
- Indicate silt traps - Boundary for environmental buffer zones E. Identify stockpile locations location
location - Location of silt fences F. Mark BMPs on drawings: G. Add construction
G. Add construction - Indicate limits of works - Boundary for environmental buffer zones notes
notes - Indicate type/extent of erosion controls - Location of sediment pond location
- Mark temporary drainage - Indicate limits of works
- Indicate silt traps/sediment ponds - Indicate type/extent of erosion controls
F. Add construction notes G. Add construction notes
Figure 4.49: Environmental Method Statements for Drainage Project (Cont.)
4-128
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
SITE CLEARANCE RIVER CROSSING EXCAVATION DIVERSION WORKS EXCAVATION ROADWORKS DRAINAGE FOUNDATION CONCRETING
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Scope of work Scope of work
Undertake survey Undertake survey Mark work zones Mark work zones Identify flowpath Mark work zones Formwork
Mark work zones Undertake survey
Mark site boundary Mark site boundary Mark buffer zones Mark buffer zones Mark work/buffer Mark storage zones Steelwork
Mark buffer zones Mark site boundary zones
Identify interfaces Mark work/ buffer Mark storage zones Create diversion Mark buffer zones Concrete pour
Mark storage zones Mark work/ buffer zones
zones Mark storage zones
Identify clearance Excavate foundation Excavate foundation Remove formwork
Excavate foundation Mark storage zones
extent Mark storage zones Excavate trench
Export excavated Formwork/ Steelwork
Export excavated Road works
Clearing works Lay crossing soil Drainage works
soil Concrete pour
SITE CLEARANCE RIVER CROSSING EXCAVATION DIVERSION WORKS EXCAVATION ROAD WORKS DRAINAGE FOUNDATION CONCRETING
A. Identify sensitive receivers A. Identify/mark perimeter A. Identify dewatering A. Identify/mark perimeter A. Identify dewatering A. Identify/mark perimeter A. Identify dewatering A. Identify dewatering A. Identify/mark
B. Identify/mark perimeter controls discharge location controls discharge location controls discharge location discharge location perimeter controls
controls B. Identify/mark B. Identify/mark perimeter B. Identify/mark B. Identify/mark perimeter B. Identify/mark B. Identify/mark B. Identify/mark perimeter B. Identify limits of
C. Identify/mark environmental buffer zones controls environmental buffer zones controls environmental buffer zones perimeter controls controls works, 100m clearance
environmental buffer zones C. Identify limits of works, C. Identify/mark C. Identify limits of works, C. Identify/mark C. Identify limits of works, C. Identify/mark C. Identify/mark C. Identify stockpile
D. Identify limits of works, 100m clearance environmental buffer zones 100m clearance environmental buffer zones 100m clearance environmental buffer environmental buffer zones locations
100m clearance D. Identify stockpile locations D. Identify limits of works, D. Mark BMPs on drawings: D. Identify limits of works, D. Identify stockpile zones D. Identify limits of works, D. Mark BMPs on
E. Identify stockpile locations E. Mark BMPs on drawings: 100m clearance - Perimeter drainage along 100m clearance locations D. Identify limits of 100m clearance drawings:
F. Mark BMPs on drawings: - Perimeter drainage along E. Identify stockpile site boundary E. Identify stockpile E. Mark BMPs on drawings: works, 100m clearance E. Identify stockpile - Perimeter drainage
- Perimeter drainage along site boundary locations - Boundary for locations - Perimeter drainage along E. Identify stockpile locations along site boundary
site boundary - Boundary for F. Mark BMPs on drawings: environmental buffer zones F. Mark BMPs on drawings: site boundary locations F. Mark BMPs on - Indicate sediment
- Entrance controls for environmental buffer zones - Boundary for - Location of silt fences - Boundary for - Boundary for F. Mark BMPs on drawings: pond location
vehicles - Location of silt fences environmental buffer zones - Indicate limits of works environmental buffer zones environmental buffer zones drawings: - Boundary for - Indicate limits of
- Boundary for - Indicate limits of works - Location of silt fences - Indicate type/extent of - Location of silt fences - Location of silt fences - Boundary for environmental buffer works
environmental buffer zones - Indicate type/extent of - Location of sediment erosion controls - Location of sediment - Indicate limits of works environmental buffer zones - Mark temporary
- Location of silt fences erosion controls pond location - Mark temporary drainage pond location - Indicate type/extent of zones - Location of silt fences drainage
- Indicate limits of works - Mark temporary drainage - Indicate limits of works - Indicate silt traps location - Indicate limits of works erosion controls - Location of sediment - Location of sediment - Indicate type/extent
- Indicate type/extent of - Indicate silt traps/sediment - Indicate type/extent of E. Add construction notes - Indicate type/extent of - Indicate silt traps/fence pond location pond location of erosion controls
erosion controls ponds erosion controls erosion controls location - Indicate limits of works - Indicate limits of works F. Add construction
- Mark temporary drainage F. Add construction notes G. Add construction notes G. Add construction notes F. Add construction notes - Indicate type/extent of - Indicate type/extent of notes
- Indicate silt traps location erosion controls erosion controls
G. Add construction notes G. Add construction notes G. Add construction notes
Figure 4.50: Environmental Method Statements for River Check Dam Project
4-129
GUIDELINES ON LD-P2M2
COMPONENTS OF PROJECT
SITE CLEARANCE TEMPORARY ROADS SITE GRADING ROAD WORKS EXCAVATION DRAINAGE WORKS BACKFILL
FIELD ESTABLISHMENT
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake survey Undertake survey Undertake survey Undertake survey Undertake survey Mark work zones Identify flowpath Mark storage zones
Mark site boundary Mark site boundary Mark site boundary Mark surface Mark site boundary Mark buffer zones Mark work/buffer Import backfill
elevation zones
Identify interfaces Mark work/ buffer Mark work/ buffer Mark work/ buffer zones Mark storage zones Compaction
zones zones Mark work buffer Mark storage zones
Identify clearance zones Mark storage zones Excavate foundation
extent Mark storage zones Grading works Excavate trench
Grading works Road works Export excavated
Clearing works Road works soil Drainage works
SITE CLEARANCE TEMPORARY ROADS FIELD ESTABLISHMENT SITE GRADING ROAD WORKS EXCAVATION DRAINAGE WORKS BACKFILL
A. Identify sensitive receivers A. Identify/mark perimeter A. Identify/mark perimeter A. Identify/mark perimeter A. Identify/mark perimeter A. Identify dewatering A. Identify dewatering A. Identify/mark
B. Identify/mark perimeter controls controls controls controls discharge location discharge location perimeter controls
controls B. Identify/mark B. Identify/mark B. Identify/mark B. Identify/mark B. Identify/mark perimeter B. Identify/mark perimeter B. Identify stockpile
C. Identify/mark environmental buffer zones environmental buffer zones environmental buffer zones environmental buffer zones controls controls locations
environmental buffer zones C. Identify limits of works, C. Identify limits of works, C. Identify limits of works, C. Identify limits of works, C. Identify/mark C. Identify/mark C. Mark BMPs on
D. Identify limits of works, 100m clearance 100m clearance 100m clearance 100m clearance environmental buffer zones environmental buffer zones drawings:
100m clearance D. Identify stockpile locations D. Identify stockpile D. Identify stockpile locations D. Identify stockpile D. Identify limits of works, D. Identify limits of works, - Perimeter drainage
E. Identify stockpile locations E. Mark BMPs on drawings: locations E. Mark BMPs on drawings: locations 100m clearance 100m clearance along site boundary
F. Mark BMPs on drawings: - Perimeter drainage along E. Mark BMPs on drawings: - Perimeter drainage along E. Mark BMPs on E. Identify stockpile E. Identify stockpile - Indicate limits of
- Perimeter drainage along site boundary - Perimeter drainage along site boundary drawings: locations locations works
site boundary - Boundary for site boundary - Boundary for - Perimeter drainage along F. Mark BMPs on drawings: F. Mark BMPs on drawings: - Indicate type/extent
- Entrance controls for environmental buffer zones - Boundary for environmental buffer zones site boundary - Boundary for - Boundary for of erosion controls
vehicles - Location of silt fences environmental buffer zones - Location of silt fences - Boundary for environmental buffer zones environmental buffer zones D. Add construction
- Boundary for - Indicate limits of works - Location of silt fences - Indicate limits of works environmental buffer - Location of silt fence s - Location of sediment notes
environmental buffer zones - Indicate type/extent of - Indicate limits of works - Indicate type/extent of zones - Location of sediment pond location
- Location of silt fences erosion controls - Indicate type/extent of erosion controls - Location of silt fences pond location - Indicate limits of works
- Indicate limits of works - Indicate silt traps/fence erosion controls - Mark temporary drainage - Indicate limits of works - Indicate limits of works - Indicate type/extent of
- Indicate type/extent of location - Mark temporary drainage - Indicate silt traps/sediment - Indicate type/extent of - Indicate type/extent of erosion controls
erosion controls F. Add construction notes - Indicate silt ponds erosion controls erosion controls G. Add construction notes
- Mark temporary drainage traps/sediment ponds F. Add construction notes - Indicate silt traps/fe nce G. Add construction notes
- Indicate silt traps location F. Add construction notes location
G. Add construction notes F. Add construction notes
One of the major issues associated with erosion and sediment in our
construction sites today is the lack of project phasing and
sequencing/scheduling of the site activities, which as a result, subjected the
construction sites to large extent of unprotected exposed ground surfaces or
absence of appropriate mitigation measures during the land disturbing
activities. The aspect of project phasing has been discussed earlier in this
Chapter.
All construction projects can benefit from upfront planning to phase and
sequence construction activities to minimize the extent, duration and
potential impacts of the inevitable land disturbing activities. Larger projects
and linear construction projects may benefit most from construction
sequencing or phasing, but even small projects can benefit from construction
sequencing that minimizes the duration of disturbance. Typically, erosion
and sediment controls needed at a site will change as a site progresses
through the major phases of construction.
In the earlier section, we have looked at how the STW project can be broken
down to its project components, project activities, scope of work, and
environmental method statements, all done from the point of view to focus on
land disturbing activities that will result in erosion and sediment issues
during a construction of an EIA project.
Recall from the earlier sections that this example project was divided into
three 3 project components, namely, Road, Bridge and Building Site:
basically a combination of linear-type (road) and concentrated-type (bridge
& building) construction works. The factors to be considered when planning
for the phasing of a project were discussed in Section 5.4.
For the purposes of this STW example, the information adopted to respond to
the above factors of consideration is shown in Table 4.5.
In view of the above consideration, it can be proposed for the STW project to
be broken down into the several phases:
Phase 1: To construct the first one (1) kilometre section of the proposed
4m wide road, commencing from the existing road, in the river direction;
Phase 2: To construct the second one (1) kilometre section of the proposed
4m wide road, continuing from Phase 1 works;
The general sequence of the phasing works, and the arrangement of the project
phases are shown in Figure 4.52 and Figure 4.53, respectively.
4-133
GUIDELINES ON LD-P2M2
Based on the above project phasing, the potential land disturbing activities that
can be identified for the individual phases are shown in Table 4.6.
In view of the above land disturbance activities and the planned project phases as
discussed above, project sequences for the initial phases is shown in Figures 4.54
and 4.55, respectively.
4-135
GUIDELINES ON LD-P2M2
Figure 4.52: Recommended Project Sequence for Phases of Work for STW Project
4-136
GUIDELINES ON LD-P2M2
Site Grading
Survey Works
Mark Excavation
Limits Works
Mark Work
Zone/Limit
Mark Excavation
Limits Works
Mark Work
Zone/Limit
Upon completion of the Phase 1 works, Phase 2 can then commence, with
its general sequences described below.
facilities
G. Install new or upgrade sediment pond
H. Commence drilling works
I. Export excavated soil & wastewater
J. Inspect & maintain silt fences / sediment ponds
Phase 4 shall start only after completion of Phase 3, and its project
sequences are similar to those for Phase 2 and are not repeated here.
Upon and after completion of Phase 4, the last phase of this STW project
can then commence, with the majority of the works involving structural and
building works but also covering some land disturbing activities (some of
which are quite significant also, such as excavation works for the STW
foundation structures. The project sequences for Phase 5 are described
below.
The same application in identifying project phasing and sequencing for the
other example projects previously discussed in this Chapter can also be
performed, based on the following proposals.
4-143
GUIDELINES ON LD-P2M2
NORT
10 km
+ 40
EXISTING RIVER
(AVG WIDTH 10M)
+ 38
+ 39 + 36
+
EXISTING 2-
LANE HIGHWAY
(7M WIDE) + 38
+ +
Phase 1 NEW 7M WIDE HIGHWAY
Phase 3 Phase 2 Phase 1 + 36
+
+ 40
+ 537
+ 524
+
Phase 2 EXISTING 2-
LANE ROAD (7M
NEW RIVER
+ 36 CROSSINGS
+ 39 EXISTING + 36
+ 39 VILLAGE
COMMUNITIES
WITH MOSQUES
+ 35
+
+ 34
+ 35
+ 37
BOUNDARY
Phase 1
Phase 3
+ 518
+ 520
EXISTING
2-LANE + 538
ROAD (7M
+ 518
40-UNITS NEW 4m WIDE STEEL
+ 538 BRIDGE ABLE TO
BUNGALOW-
CARRY 200T VEHICLES
TYPE HOMES IN THE FUTURE 8 UNITS 20-
STOREY
APPROX 250M
CLUB- + 520 + 517
NEW ACCESS
ROADS TO HOUS + 537
HOUSING
DEVELOPMEN
+ 517
+ 537
Phase 2 65-UNITS
DUPLEX-TYPE
+ 525
STW
EXISTING PRISTINE + 516
FOREST RESERVE
540
Phase 2
Phase 1
525
Phase 2
548
548
516
4.9.5 Summary
CHAPTER 5
Up to this point, the Guidelines has covered the essential fundamentals and elements of land
disturbing pollution prevention and mitigation measures, and how erosion and sediment
issues in a construction site can be effectively controlled or minimized during the site
activities. This Chapter will discuss some of the techniques to be used to apply the LD-P2M2
measures into the construction activities.
Foremost, let’s review the overarching requirements for the application of LD-P2M2 into an
EIA project, most of which have been already covered elsewhere:
Legal obligations;
Maximizing the most of LD-P2M2 basic principles;
LD-P2M2’s minimum standards requirements;
Roles and responsibilities of project parties; and
Site application practices
The legal requirements for the planning and implementation of LD-P2M2 are
discussed in Chapter 2 of this Guideline, covered under Section 34A of the EQA
1974 (Amended) 2012. In short, it is not a choice whether the Project Proponent and
Contractor will or will not implement LD-P2M2 in an EIA project and associated site
activities, as both are required to do so under the Act.
Maximizing the basic principles of LD-P2M2 in land disturbing activities have been covered
in several preceding chapters, and these represent the core fundamentals to be adopted to
prevent and minimize the occurrence of erosion and sediment issues at the project sites, if
diligently applied:
The above standard requirements are covered repeatedly in various forms throughout
the remaining of this Chapter.
5-3
GUIDELINES ON LD-P2M2
The main project parties who would be involved in applying LD-P2M2 are discussed in
Chapter 2, with specific roles being played by the Project Proponent (PP), Consultants,
Contractors and Environmental Officers (EO). Essentially, all the principles, standards
requirements, tools and documents on their own are pretty much non-functional unless they
are effectively applied to the construction sites by these pertinent parties. The techniques
for the application of LD-P2M2 into the construction phases shall commence from the
planning stage and brought down to the construction phases.
The stakeholders who will be involved in LD-P2M2 consist namely the following
parties:
Project Proponent;
Consultants;
Contractors;
Environmental Officers; and
Government Agencies
The PP is not only legally responsible for ensuring regulatory compliance, but is
the driver for mainstreaming the environmental agenda in all stages of project
implementation. In principle, the Project Proponent (PP) shall be responsible for
the implementation of the LD-P2M2.
The PP may be from the public or the private sector and he may be represented by
a consultant. The PP is responsible for all aspects related to the development of the
project including the environmental planning of the project and its associated cost.
He may delegate the task of conducting the environmental impact assessment of
the project to his project consultant or to another organization but he remains
ultimately responsible for the content of the EIA Report on his project.
mitigation measures (P2M2) are integrated into every stage of project planning
and implementation.
The PP is responsible for allocating sufficient funds for all steps in the EIA
process and every stage of project planning and implementation with itemized
budget required for amongst other environmental aspects, for implementation of
Environmental Management Plan (EMP) and LD-P2M2 including temporary
pollution prevention and mitigation measures (P2M2). P2M2 shall be those which
can be described as state of the art technologies, best available technologies
(BATs), or industry best practices.
5.3.3 Consultants
The EIA Consultant is an individual who has been tasked by the Project Proponent
to conduct the Environmental Impact Assessment (EIA) of the project. The
Consultant is typically the leader of a team of consultants from various disciplines
relevant to the proposed project and is responsible to the Project Proponent. The EIA
team leader who may work for an EIA consulting firm and the subject matter experts
shall be DOE-registered consultants who shall maintain professionalism in
5-5
GUIDELINES ON LD-P2M2
conducting a comprehensive EIA study and produce a quality EIA Report that is
useful for decision-making purposes.
The EIA Consultant plays a major role in the preparation of the EIA report,
including the LD-P2M2 Document and environmental monitoring programmes in
accordance with the objectives and requirements of the EIA, whilst ensuring
compliance with the relevant regulations and standards. He is entrusted with the
responsibilities for ensuring environmental impacts from a project are correctly
identified, assessed, and mitigated.
When preparing the LD-P2M2 Document, the Consultant is responsible to obtain all
the relevant information for analysis and interpretation, in order to produce the
requirements to address erosion and sediment issues during the execution of the
project. Amongst the key information include the following:
5.3.4 Contractors
The Contractor who successfully wins the tender for the project will go into an
agreement with the PP to execute the construction of the project in accordance with
the contract drawings, specification and all documents that are contractually bound to
the agreement.
The Contractor is responsible to review and understand the contents of the approved
LD-P2M2 Document, and where applicable, to integrate the findings of the document
into his work plans to fulfill the contract. As mentioned earlier, the LD-P2M2
Document may require updating based on the availability of more detailed
information.
The Environmental Officer (EO) is the main project personnel responsible for
ensuring regulatory compliance at the project implementation stage (post submission
of EIA Report).
First of all, the planning stage herein includes all those activities since the
conception of the project up to the award of the contract, which covers, amongst
other things, the EIA, detailed design, and tender documentation processes.
To effectively apply LD-P2M2 at this stage of the project, the Project Proponent
(and his Consultants) shall:
o Make a real commitment to address soil erosion and sediment matter at the very
stage of the Project;
o Proactively obtain and/or collect all the pertinent information relating to this
subject matter, as shown in Figure 5.1;
o Review the potential construction sequencing and site operations prior to award
of construction contracts, particularly with respect to land disturbing activities;
o Prepare LD-P2M2 Document as part of submission with EIA Report for DOE’s
approval, and update LD-P2M2 Document during the EMP submission if
required;
o Ensure that the Contract Documents include provisions for compliance with
environmental requirements including for LD-P2M2 and its associated drawing
(a sample of such drawing is shown in Plate 1 and associated sample
calculation for an active construction site is shown in Appendix I which
incorporated the concept of project phasing);
o Ensure all the environmental requirements relating to erosion and sediment are
included in the Contract Documents for the Contractor’s information and
incorporation into his plan of work.
o Ensure the EMP is implemented diligently, and that all temporary and
permanent P2M2s are correctly installed as required;
o Integrate the requirements of LD-P2M2 Document into his master planning for
site works and update this Document as necessary for submission to DOE;
o Apply diligently all the relevant elements of erosion and sediment controls into
the project, as illustrated in the LD-P2M2 framework in Figure 5.2;
o Plan and implement measures for controlling erosion and sediment issues,
operation of environment mitigation measures, and monitoring program;
In Figure 5.1 above, information to be used for the analysis of LD-P2M2 for a
project site included the following:
Soil characteristics;
Erosion and sedimentation sensitive receivers;
Waste management; and
List of proposed P2M2s
This section will assist the relevant project parties in their planning of
identifying risk analysis of potential erosion and sediment issues, and of
identifying & selecting the P2M2s and BMPs that might be used to manage the
risks. It should however be noted that such planning is subject to change once
construction begins to suit the evolving site conditions. It should also be
pointed out that the below discussion may not necessary follow the same order
of the above principles, as some site conditions may warrant more than 1
principle to be incorporated.
5.6.2.1 Principles 1 & 5: Integrate project design with site constraints &
Install perimeter controls
5.6.2.2 Principles 2 & 9: Preserve and stabilize drainage ways & Protect
inlets, storm drain outfalls, and culverts
Protect all drain inlets from sediment with approved inlet BMPs.
Inlet protection devices must be capable of being maintained
without losing sediment or material into the catch basin and must be
inspected weekly to ensure discharge treatment is occurring.
Design drainages to account for both on- and off-site water sources
(divert or tight-line off-site sources of water where feasible).
Control discharges to protect downstream properties and waterways
from erosion by preventing increases in the volume, velocity, and
peak flow rate of stormwater leaving the site during construction.
Control peak flow and discharge rates to minimize erosion at outlets
and downstream channels or streambanks.
If the contractor feels that the area limitation for land disturbing
activities such as site clearance, grading and grubbing is too
restrictive, he shall update the LD-P2M2 document to incorporate a
larger area, as well as a plan and schedule for additional BMPs that
are necessary to manage increased erosion-related risks.
Select BMPs based on the soil type and potential for erosion.
Reduce continuous length or gradient of slopes with terracing
or diversions.
Add surface texture to slope to slow, disperse, or dissipate
flows (e.g., blanket, mulch, compost sock).
Use top of slope BMPs to divert erosive flows away from the
slope, such as interceptor dikes, swales, stabilized channels, or
temporary pipe slope drains.
BMPs used to cover slopes, such as plastic covers, do not hold up to
concentrated flows, which is why other BMPs must be used to
prevent concentrated flows from developing or hitting slopes.
Manage overland flow or off-site water run-on to minimize erosion
on slopes. Ensure concentrated flows or drips coming off overhead
structures do not create erosion on slopes.
Silt fence can create erosion problems, the majority of which are
related to installation errors. Do not install silt fence in areas that
receive concentrated flows. Water filters through silt fence very
slowly—too slowly to treat concentrated flow. Concentrated flows
will overtop silt fence or collapse it altogether. Trench in silt fence
and install it on the contour of the slope or it will create concentrated
flow where there was none before.
Wherever feasible:
Limit access points to the fewest number possible, using only
one wherever feasible (or one entrance and one exit);
5-28
GUIDELINES ON LD-P2M2
Manage the contract and apply the following actions on all projects:
5-30
GUIDELINES ON LD-P2M2
The requirements to address soil erosion and sediment control aspects are firstly
stipulated in the Environmental Impact Assessment Guidelines in Malaysia 2016
in “Appendix 3 - Guidance Document For Addressing Soil Erosion And Sediment
Control Aspects In The Environmental Impact Assessment”, but also serve as
useful reference for preparing a LD-P2M2 Document.
5-31
GUIDELINES ON LD-P2M2
a. During development/construction:
i. Without mitigating measures (worst case
scenario).
ii. With mitigating measures.
Instructions
(i) All relevant items cited in Section 8.1, 8.2, 8.3 and 8.4 checklist are
required to be identified, addressed, discussed, assessed, evaluated and
presented in the LD-P2M2 document according to appropriate chapters.
(ii) All relevant items cited in Section 8.3 and 8.4 checklist are required
to be illustrated or depicted in a minimum of three (3) sheets of plan or
map or drawing to be referred to as LD-P2M2 Plan which contains the
following:
(a) Map of site plan with the existing site conditions (pre-
development),
(b) Map of site development plan (during development) and
(c) Overlaid map of (a) and (b).
(iii) Maps shall be clear and legible where they may be provided with
more than one sheet to commensurate with the size and complexity of the
drainage areas as well as the terrain of the project site.
(iv) The LD-P2M2 document shall include a legal pledge by the Project
Proponent (PP) to comply with the Minimum Standards requirement of
P2M2s as outlined in Section 7 of this Guidelines (PP).
5-36
GUIDELINES ON LD-P2M2
Applicable
(e) List of streams and rivers identified on-
site. (Use coding for unnamed streams and
rivers).
(f) List of receiving streams and rivers. (Use
coding for unnamed streams and rivers).
(g) List of existing drainage identified on-
site.
(h) List of P2M2s proposed. Please also
make reference to P2M2s Description can be
accessed through: https://enviro.doe.gov.my
(i) Identify access roads and other
outsourced components (such as mobile
batching or premix plant) that are located
outside the proximity of the project
boundary.
(j) Earthworks cut and fill volume.
(k) Availability of rocks material.
(l) Biomass management.
(m) Solid (construction waste) and domestic
waste management.
(n) Spill Prevention and Control from fuel
and chemical use or storage.
(o) Hazardous Waste Management.
(p) Soil loss prediction using the Universal
Soil Loss Equation (USLE), sediment yield
calculation using Modified Universal Soil
Loss Equation (MUSLE) and runoff
estimation for pre, during and post
development accounted for both with and
without the implementation of LDP2M2s.
All of the data and parameters used in the
calculations shall be measured or rationally
determined, and identified. If secondary
sources are used, they shall be clearly
identified.
1 PROJECT DESCRIPTION
Screening chamber;
Grit chamber;
Distribution tank;
Oxidation ditches;
Blower house and control rooms;
Clarifiers;
Sludge pump houses;
Sludge treatment building;
Sludge thickening building;
Administration building;
Workshop;
Electrical building;
Disinfection building;
Power receiving station/TNB substation; and
Ancillary facilities such as roads, drainage, utilities, etc.
5-42
GUIDELINES ON LD-P2M2
For this STW example, the information adopted to respond to the factors of consideration
for the purposes of phasing the project is shown below:
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) EXTENSION AT STW OLD
COMPONENTS OF PROJECT
SITE CLEARING SITE GRADING ROADS/DRAINS SITE CLEARING / DEEP SUB-STRUCTURE SITE CLEARING / FOUNDATION SUPERSTRUCTURE
FORMATION LAND FORMATION EXCAVATION CONSTRUCTION LAND FORMATION EXCAVATION CONSTRUCTION
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake survey Undertake survey Identify flowpath Undertake survey Mark work zones Formwork Undertake survey Mark work zones Formwork
Mark site boundary Mark surface elevation Mark buffer zones Mark site boundary Mark storage zones Steelwork Mark site boundary Mark storage zones Steelwork
Identify interfaces Mark work/buffer zones Mark storage zones Identify interfaces Excavation works Concrete pour Identify interfaces Excavation works Concrete pour
Identify clearance extent Grading works Excavate trench Identify clearance extent Dewatering Identify clearance extent Dewatering
Clearing works Road/Drainage works Clearing / formation Export excavated soil Clearing / formation Export excavated soil
SITE CLEARANCE SITE GRADING DRAINAGE SITE CLEARANCE BOREHOLE DRILLING ELEVATED STRUCTURES SITE CLEARANCE EXCAVATION CONCRETING
A. Identify sensitive receivers A. Identify/mark perimeter controls A. Identify dewatering discharge location A. Identify sensitive receivers A. Identify dewatering discharge location A. Identify limits of works, 100m clearance A. Identify sensitive receivers A. Identify dewatering discharge location A. Identify/mark perimeter controls
B. Identify/mark perimeter controls B. Identify/mark environmental buffer zones B. Identify/mark perimeter controls B. Identify/mark perimeter controls B. Identify/mark perimeter controls B. Identify stockpile locations B. Identify/mark perimeter controls B. Identify/mark perimeter controls B. Identify limits of works, 100m clearance
C. Identify/mark environmental buffer zones C. Identify limits of works, 100m clearance C. Identify/mark environmental buffer zones C. Identify/mark environmental buffer zones C. Identify/mark environmental buffer zones C. Mark BMPs on drawings: C. Identify/mark environmental buffer zones C. Identify/mark environmental buffer zones C. Identify stockpile locations
D. Identify limits of works, 100m clearance D. Identify stockpile locations D. Identify limits of works, 100m clearance D. Identify limits of works, 100m clearance D. Identify limits of works, 100m clearance - Perimeter drainage along site boundary D. Identify limits of works, 100m clearance D. Identify limits of works, 100m clearance D. Mark BMPs on drawings:
E. Identify stockpile locations E. Mark BMPs on drawings: E. Identify stockpile locations E. Identify stockpile locations E. Identify stockpile locations - Location of silt fences E. Identify stockpile locations E. Identify stockpile locations - Perimeter drainage along site boundary
F. Mark BMPs on drawings: - Perimeter drainage along site boundary F. Mark BMPs on drawings: F. Mark BMPs on drawings: F. Mark BMPs on drawings: - Indicate limits of works F. Mark BMPs on drawings: F. Mark BMPs on drawings: - Indicate sediment pond location
- Perimeter drainage along site boundary - Boundary for environmental buffer zones - Boundary for environmental buffer zones - Perimeter drainage along site boundary - Boundary for environmental buffer zones - Indicate stockpile location - Perimeter drainage along site boundary - Boundary for environmental buffer zones - Indicate limits of works
- Entrance controls for vehicles - Location of silt fences - Location of sediment pond location - Boundary for environmental buffer zones - Location of silt fences - Mark temporary drainage - Boundary for environmental buffer zones - Location of silt fences - Mark temporary drainage
- Boundary for environmental buffer zones - Indicate limits of works - Indicate limits of works - Location of silt fences - Location of sediment pond location - Indicate silt traps location - Location of silt fences - Location of sediment pond location - Indicate type/extent of erosion controls
- Location of silt fences - Indicate type/extent of erosion controls - Indicate type/extent of erosion controls - Indicate limits of works - Indicate limits of works D. Add Construction Notes - Indicate limits of works - Indicate limits of works E. Add Construction Notes
- Indicate limits of works - Mark temporary drainage G. Add Construction Notes - Indicate type/extent of erosion controls - Indicate type/extent of erosion controls - Indicate type/extent of erosion controls - Indicate type/extent of erosion controls
- Indicate type/extent of erosion controls - Indicate silt traps/sediment ponds - Mark temporary drainage G. Add Construction Notes - Mark temporary drainage G. Add Construction Notes
- Mark temporary drainage F. Add Construction Notes - Indicate silt traps location - Indicate silt traps location
- Indicate silt traps location G. Add Construction Notes G. Add Construction Notes
G. Add Construction Notes
In view of the above consideration and considering the site is relatively small and
manageable, it can be proposed for the STW Extension project to be broken down into the
following phases, namely:
Pre-development Phase: To provide and install all the necessary protection and
mitigation measures prior to commencement of Phase 1;
Phase 2: To construct the remaining half of the site which will involve mostly
fill work to form the final platform of the STW; and
drainage works
Disposal area management Disposal sites for the biomass and excavated soil materials
Phase 2
Site clearing Site clearance works to be provided to remove existing
trees and vegetation from the project site.
Site grading Site grading to prepare works area for roadworks, drainage,
land formation
Excavation Excavation for permanent drainage and road foundation
Earthworks Cut and fill of area within Phase 2
Stockpile & solid waste Stockpiling of biomass from forest clearing works;
management Stockpiling of excavated soil materials;
Stockpiling of construction materials for the road &
drainage works
Disposal area management Disposal sites for the biomass and excavated soil materials
Disposal area management Disposal sites for excavated soil materials
Phase 3
Deep excavation Excavation of foundations, subsurface voids for water-
retaining structures, building basements, utility trenches
Dewatering Dewatering to excavated areas for subsurface works
Stockpile management Stockpiling of excavated soil materials;
Stockpiling of construction materials for the road &
drainage works
Disposal area management Disposal sites for the biomass and excavated soil materials
To describe the sequence for the Phase 1 works, it will be useful to first prepare another
WBS, dedicated for the Phase 1 works only, noting that a WBS has been done previously
but for the entire project. The breakdown of the various project components, project
activities, scope of work and environmental method statements is shown in Figure 2.
With the key components identified, 3 distinct sets of project sequence of works can now
be prepared as below:
To describe the sequence for the Phase 2 works, another WBS will prepared namely for
the Phase 2 works only, and based on the various project components, project activities,
scope of work and environmental method statements as shown in Figure 3, the sequence
of works can then be prepared. This is similar also to the last phase, Phase 3 of the
project.
11. Repeat items 2,3,4,5 and 6 as the cutting works progress to upgrade or revise
or replace BMPs accordingly.
12. Once Phase 1 earthworks completed, remove those BMPs that are not needed
any longer.
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) EXTENSION AT STW OLD
COMPONENTS OF PHASE 1
Scope of work Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake survey Identify location for discharge Identify stockpile Undertake survey Undertake survey Mark work zones & limits
Mark work limits Dewater confined area Bacfilling Mark works limits/cut extent Mark works limits Mark storage & buffer zones
Install silt curtains Cutting works Loading/unloading Excavation for drainage/road foundations
Install sheetpiles Stockpile earth materials Filling & land formation Lay road/drainage materials
PROJECT TITLE: PROPOSED SEWAGE TREATMENT WORKS (STW) EXTENSION AT STW OLD
COMPONENTS OF PHASE 2
COMPONENTS OF PHASE 3
Scope of work Scope of work Scope of work Scope of work Scope of work
Undertake survey Identify location for discharge Identify stockpile areas Undertake survey Mark works limits
Mark works limits/cut extent Formwork Bacfilling Mark works limits/cut extent Formwork
Cutting works Steelwork Cutting works Steelwork
Stockpile earth materials Concrete pour Stockpile earth materials Concrete pour
(h) List of P2M2s P2M2s related to the principles in erosion and sediment
proposed. Please also control have been proposed for this STW Extension
make reference to P2M2s project, with brief descriptions provided below:
Description can bea. Integrate project design with site constraints:
accessed through:Project phasing has been planned based on the topography
https://enviro.doe.gov.my of the project site, and the need to achieve equal cut and fill
volumes. Based on various considerations, the works will
be phased into Phase 1 and Phase 2, as shown in the
attached Drawings.
b. Preserve and stabilize drainageways: Drainage
within the project site will be lined to minimize erosion of
their banks.
c. Minimize the extent and duration of disturbance:
Exposed ground surfaces will be covered by stabilization
materials such as by hydroseeding or gravel if surfaces will
be left open for more than 14 days.
d. Control runoff flows onto, through, and from the
site in stable drainage structures: Various drainage
structures are being proposed to convey potential runoffs.
e. Install perimeter control: Perimeter controls are
provided to control both surface runoff from outside the
site to enter the project site, and prevent runoff from
project site to discharge to outside the site.
f. Stabilize disturbed areas promptly in a timely
manner: Stabilization provided to areas being disturbed to
minimize erosion potentials.
g. Protect steep slopes: Runoff and sediment controls
provided to cater for construction runoffs.
h. Use sediment controls to prevent off-site damage:
Sediment ponds, silt traps and silt fences provided to
control sediment.
i. Protect inlets, storm drain outfalls, and culverts:
Provided.
j. Provide access and general construction controls:
One of the first controls that shall be provided.
(i) Identify access There is currently an access road that ends at the boundary
roads and other of the project site, previously constructed as part of the
outsourced asset of the existing STW OLD.
components
(such as mobile No other outsourced components such as mobile batching
batching or or premix plant will be used.
premix plant)
that are located
5-55
GUIDELINES ON LD-P2M2
outside the
proximity of
the project
boundary.
1 : 1000
PROJECT SEWAGE TREATMENT WORK EXTENSION
CONSTRUCTION
ACTIVITIES
30.982
DI PERIKSA
36
30.982
SKALA
SKALA 1 : 1000
SPOT HEIGHT
N
PROJECT ROW
BOUNDARY
EXISTING
CONTOUR
FOREST
SWAMP
Phase 1
Phase 2
ENGINEER SIGNATURE :
OWNER SIGNATURE :
001
PROJECT TITLE :
SUB - TITLE :
22084
LEGEND :
NO. LUKISAN
DI LUKIS
TARIKH
SUMP
E -1600
44.353 42.725
32
32.498
BERM
35.312 34 35.073
WORK
E -1200
44.371 30.286
EP
28.884IL 30.623
45.416 28.874 35.211
43.512 45.251IL 46.703 30.037
43.323 35.387
47.856 50.185 40.118 45.180 45.339 29.275 30.821
43.514 45.442 45.194 42.277 30.885
40.360 34.253
EP
39.646 40.027
m 45.438
0.5 34.329 37.235
EXISTING
45.377 29.765
FENCING
43.513 40.042IL
AK
51.045 39.740
35
40.828
MH
NK
29.200IL 31.376
A.L=36.403m
38.557
AN
TBM 2
45.304 30.473
43.485 38.493 36.556 30.396 40.715
EP
48
50.514 32.374
LU
42.924
SUMP
50.645 39.042
MH
50.529 31.258
36.050 40.564
35.858 34.428 34.899
MH
37.673
50
S.B*
44.889 37.902 Da
32.675
48
43.458 42.397
50.312 32.662
43.843 39.333
50.236 39.423
30.702 39.958
43.189 45.704 30.306
31.262IL KI 39.585
36.592 KA
34
43.605 N 36.370
LA 36.986
42.921 45.313 34.103 32.988 JA 35.810
45.265 44.117 41.281 37.975 35.241 34.122 PE
44.262
31.157 AN 46.530
40.254
PAYA
50
50.295 40.525 30.527 38.863 40.660 42.342
35.564 41.510
37.335 39.785
45.627 39.058 40.091
43.089 42.911 50.266 43.497 33.936
45.556 30.298
30.974IL 31.392 33.380 39.123 42.012
44.701 31.156
43.099 38.447 36.763
44.337 ARAS AIR =31.192m 35.510 45.058 46.901
SUMP
45.218 40.172
42.998 PADA 8.25am 46.830
45.253 39.844
Phase1
46
45.708
44
45.239 45.254 45.236 45.386 42.947 31.206
45.149 44.493IL 40.596 44.285 30.921IL
44.603 45.133 45.143 45.371 33.722
44.586 36.080 41.271
MH
44.540
MH
45.195 45.264
SUMP
32.310
40
33.982 31.272
35.502 38.626
45.576IL
45.743 38.433 35.738 32.686 32.162
40.767 40.779 45.550
32.282 44.628
40.819 39.335
32.479 31.692 AS 40.489
40.781 ARAS AIR =42.267m 31.633 39.112
PADA 11.15am 45.367 31.331 31.239 31.704
R E G
37.358 34.156
VE
04/08/2001
S LIN AS
40.776 32.794
45.52450.004
ER
44.070
AI E N
45.230 45.433 42.719
H PIP RO
ES
40.761 44.665 31.298 PONDOK 32.729
33.144 33.103 31.462
36
32.903
T
32.767
PE
50.210 31.692 35.844
45.498 36.754
N
40.791 34.611 31.329
45.352IL 32.648
KOLAM OKSIDASI
40.775 40.780
33.091 45.565
40.789 38.737
C
37.581
2
31.271
31.611
40.788 34.780 34.390
33.695 33.426
37.214
EXIST.
31.959
38.187 34.438 38
33.531
40.799 44.882IL 45.393 38.517
45.374 50.199 44.480IL 31.674 39.922
45.130
21936
40.816 44.601 45.279 45.312 40.480 33.592 32.422 35.468
40.796 45.426 39.128
SUMP
42
40.808 50.041 32.994 35.562
32.664
40
36.832 37.770
34.188
40.804
40.795 44.627 45.346IL 32.637
40.8009 45.161 32.149 31.868
45.349 50.176 45.409 36.075
44.574
45.222 35.139 35.589
44.639 44.579 44.683 45.352
45.171 38.756 32.221
34
S.B*
45.195
45.185 37.042
45.049IL 45.271 45.027IL 44.800IL
37.851 38.464
34
35.842
MH
3819
50.256 50.141
36
33.565
45.699
45.205IL
47.321
45.268
44.882
38
45.000 36.254
43.289 40.000
35.420 34.103
41.100 40.772 36.179 34.739
41.469 38.743 34.876
43.016 38.606
33.140
40.377 40.030 40.247 41.740
6257
32.450
34.277 32.283
43.440 33.558 41.017
41.775 32.669
32.544 34.752
38.043 36.410
39.876
3
36.071
08
34.549
S.B*
22
41.446
43.035 42.383
35.465
40.369 38.846
34.602 N -9400
36.949 35.703 33.622 41.963
35.511
35.047
33.087 44.227 42.584
33.920
35.969
44
33.184 39.777
46
38.007
45.684
43.180 40.308 36.075 33.138
39.404
35.254 34.052
38.628 44.216
36.965 44.696
33.439
43.345
33.549
Phase 2
44
47.056
42
43.121
41.987 36.348
52.793
44.275 39.537
34.749
36.767 43.494 47.586
6256
36.690 34.276 41.053 45.021
48.260
43.500
37.105
34.599 38
53.004 43.522
48.335 41.515
49.989
S.B*
50.384 45.111
48
46.466
6260
53.775
36.796 44.714 43.107
33.397
40" 23' 90°
53.416 144.277
49.489
40
45.325 46
52
36.423 49.055
42
S.B*
35.262 49.353
34.453
40
43.765 54.957
N KAKI
50.829
47.370 39.524 53.084 45.324
39.122
50
PEJALA
53.684 51.476
52.638 51.814
58
50.339
50.340
43.137
36.192 39.816
50.968 52
LALUAN
36.750 34.013 53.338 48.522
51.065
55.826
35.367 40.333 51.427
40.201
47.573
51.088 54.379
52.436
S.B*
56
52.257
44.108 60.985
52.924 36.314
36.687
35.804
6261
51.061 54
36
42.274 53.636
52.102 41.808
40.494 36.367 37.680
S.B*
45.480
48
35.597
36.117 38.155
45.374 33.262 61.475
46.329
39.303
38.688 N -9600
50
46.595 37.494 40.885
39.038
44
40.019
42.268 41.752 47.739
36.675 40.897 56
21935
34.371 39.728 61.520
6262
36.704 41.303
39.224 36.670
47.381 57.736
37.470
60
34.859 36.297
44.684 38 45.705
52.781
3966
40.342 38.416
41.580
45.144
58
34.955 38.150
36.426
40
E -1600
35.369 48.425
63.137
56
44.226 41.425 42
6263
62.289
36.152
47.946
60.732
36.719
48 59.811
59.514
6265
43.110 44.406
43.532 51.040
52
39.173 50 49.726
44
56
TEMPORARY SAND BAG BARRIER
PRE - CONSTRUCTION
STABILISED ENTRANCE/EXIT
ROCK OUTLET PROTECTION
TEMPORARY EARTHDRAIN
SILT TRAP WITH BAFFLES
1 : 1000
PROJECT SEWAGE TREATMENT WORK EXTENSION
The details of construction work for pre
CHECK DAM
development phase can be refer to
DI PERIKSA
TROUGH
RIP RAP
WASH
SKALA
SKALA 1 : 1000
ENGINEER SIGNATURE :
30.982
OWNER SIGNATURE :
X
30.982
002
X
PROJECT TITLE :
HOARDING
SPOT HEIGHT
PHASE 2 WORK
PHASE 1 WORK
BOUNDARY
PROJECT ROW
PROJECT
BOUNDARY
SUB - TITLE :
EXISTING
SWAMP
CURTAIN
BERM
WORK
FENCE
NO. LUKISAN
SILT
SILT
DI LUKIS
TARIKH
39.646 40.027
m
0.5 45.438 34.329 37.235
EXISTING
45.377 29.765
FENCING
43.513 40.042IL
AK
51.045 39.740
35
MH
39.656
EP
41.077 34.313
SUMP
40.082
MH
38.557
AN
TBM 2
45.304 30.473
43.485 38.493 36.556 30.396 40.715
EP
48
50.514 32.374
LU
42.924
39.042
SUMP
50.645 43.488
MH
39.309 34.359
LA
50.529 31.258
36.050 40.564
35.858 34.428 34.899
MH
44.776IL 45.318
S.B*
37.673
50
29.395
45.531 42.685
39.324 39.234 42.289
45.085 39.757 N -9100
ARAS AIR =44.857m 43.509 37.566 39.767
50.155 39.670
PADA 2.38pm 44.776CULV 33.268 39.188 38.487 39.468
36.954 40.627
04/08/2001 50.211
43.482 32.007 32.043 32.063
45.379 44.458
37.703
45.305 45.699
h 32.518 an
oug
45.330 29.640 X X
X
mb
45.242
r X X
sh T
40.997
43.356 44.262 33.459 31.281 X
33.365 ere 45.805
Wa 33.402 ri S
X
44
X
S.B*
44.889 37.902 Da
32.675
48
X
X
43.458 42.397
50.312 X
43.843 39.333
50.236 39.423
X
30.702 39.958
43.189 45.704 30.306
31.262IL KI 39.585
X
36.592
X
KA
34
ap
43.605 N 36.370
CD
LA 36.986
42.921 45.313 34.103 JA 35.810
X
32.988
Tr
35.241
X
31.157 AN 46.530
lt
PAYA
LU 40.254
X
Si
rta
Cu
50
40.525 30.527 42.342
X
37.335 39.785
lt
Si
33.936
45.556 30.298
30.974IL 31.392 33.380 39.123 42.012
X
44.701 31.156
X
33.549 36.763
43.099 38.447
44.337 ARAS AIR =31.192m 35.510 45.058 46.901
SUMP
45.218 40.172
42.998 PADA 8.25am 46.830
45.253 39.986 39.844 48.077
32.370 05/08/2001 41.886 40.095
44.279 44.919IL
X
38.086
MH
46
45.708
44.493IL 45.254
40.596
45.236
44.285
45.386
45.371
42.947 31.206
30.921IL
44
45.133 45.143 33.722
44.586 36.080 41.271
MH
44.540
MH
45.195 45.264
X
32.310
40
45.873
46.008
40.790
37.957 31.443
rain
30.384
31.252IL 31.687
42
33.982 31.272
35.502 38.626
45.576IL
d
45.550
arth
40.819 39.335
32.479 31.692 40.489
en
AS
39.112
X
31.633 49.502
lt F
34.156
ap
VE
04/08/2001 37.358
N L AS
40.776
Si
32.794
X
45.52450.004
Tr
ER
pora
44.070
AI E N
S IN
45.230
X
45.433 42.719
H PIP RO
X
ES
40.761 44.665
lt
X
33.103 PONDOKX
32.729
33.144
Si
36
32.903
T
32.767
PE
35.844
Tem
50.210 36.754
40.791 45.498
45.352IL 34.611
34.611 32.648
KOLAM OKSIDASI
40.780
33.091
X
37.581
2
X
CD
38
40.799 44.882IL 42.181
45.393 38.517
45.374 50.199 44.480IL 31.674 39.922
X
45.130
21936
44.601 45.279 45.312 40.480 33.592 32.422 35.468
40.796 45.426 39.128
SUMP
37.673 N -9300
42
40.808 50.041 32.994 35.562
32.664
40
36.832 37.770
34.188
X
S.B*
X
45.185 37.042
45.271 45.027IL 44.800IL
H
37.851 38.464 40.058
35.842
34
X
MH
46.672 50.256
47.868
MH
3819
50.256 50.141
X
45.699
45.205IL
45.268
44.882
X
38
45.000 36.254
43.289 40.000
35.420 34.103
41.100 40.772 36.179 34.739
in
X
38.743
dra
41.469 34.876
43.016 38.606
33.140
rth 40.377 40.030 41.740
Ea
40.247
6257
X
32.450
ry 34.277 32.283
ora 36.410
H
43.440 33.558 41.017
mp
X
41.775 32.669
32.544 34.752
38.043
39.876
Te
83
36.071 34.549
S.B*
22
X
41.446
CD
43.035 42.383
X
35.465
40.369 38.846
34.602 N -9400
36.949 35.703 33.622 41.963
35.511
X
35.047
33.087 44.227 42.584
33.920
S.B*
X
35.969
33.184
44
39.777
46
H
45.797
38.007
X
45.684
S.B*
47.919
43.180 40.308 36.075 33.138
X
39.404
S.B*
35.254 34.052
38.628 44.216
X
36.965 44.696
33.439
43.345
X
33.549
X X X X X X X X X X X X X
35.460 38.897
44
47.056 42.833
CD
42
43.121
41.987 36.348
H
CD
44.275 39.537
Perimeter Control-Cut Off Drain
34.749
X
36.767 43.494 47.586
S.B*
6256
36.690 34.276 45.021
41.053
52.298
X
CD
48.260
Temporary Earthdrain
43.500 34.599 38
X
37.105
43.522
48.335 41.515
49.989
S.B*
N -9500
X
50.384 45.111
48
46.466
6260
53.775
36.796
33.397 53.416 H 44.714
40"
43.107
23' 90° 144.277 56.440
Temporary Sandbag Barrier
49.489
40
45.325 46
X
36.423 49.055
42
S.B*
Earth Drain
35.262 49.353
34.453
40
54.957
X
43.765
N KAKI
50.829
47.370 39.524 53.084 45.324
X
39.122
50
PEJALA
53.684 51.476
51.814
58
X
50.339
50.340
43.137
36.192
50.968 52
LALUAN
39.816
H
36.750 34.013 53.338 48.522
X
51.065
55.826
35.367 40.333 51.427
X
40.201
47.573
51.088 54.379
52.436
S.B*
56
52.257
X
44.108 60.985
52.924 36.314
36.687
35.804
6261
CD
51.061
CD
54
36
42.274 53.636
41.808
40.494 36.367
Perimeter Control-Cut Off Drain 37.680
S.B*
45.480
48
35.597
36.117 38.155
45.374 33.262 61.475
46.329
39.303
38.688 N -9600
50
46.595 37.494 40.885
39.038
44
40.019
42.268 41.752 47.739
36.675 40.897 56
54
21935
34.371 39.728 61.520
6262
36.704 41.303
39.224 36.670
47.381 57.736
37.470
60
34.859 36.297
38 45.705
52.781
3966
40.342 38.416
41.580
58
34.955 38.150
Run On from
36.426
40 35.369 48.425
63.137
56
44.226 41.425 42
6263
62.289
36.152
47.946
60.732
36.719
48 59.811
44.406 59.514
43.110 51.040
43.532
52
39.173 50 49.726
44
56
52.138 44.266
47.345 46.181 52.388 N -9700
46
6264
50.388
46.740
58
E -1400
55.839
E -1100
45.070
E -1500
E -1300
38.147 57.793
48.377 52.317 51.583 49.405 53.459 59.940
42.864
52.343
48.425
37.895
TEMPORARY SAND BAG BARRIER
TEMPORARY EARTHDRAIN
SILT TRAP WITH BAFFLES
CONSTRUCTION
PROJECT SEWAGE TREATMENT WORK EXTENSION
1 : 700
The details of construction work for during
HYDROSEEDING
(PHASE 1)
(DISPOSAL A)
DURING
CHECK DAM
development phase can be refer to
ROCK FILL
CULVERT
DI PERIKSA
TROUGH
RIP RAP
WASH
SKALA
SKALA 1 : 1000
CUT
N
ENGINEER SIGNATURE :
30.982
OWNER SIGNATURE :
PL
30.982
003
X
PROJECT TITLE :
HOARDING
SPOT HEIGHT
PHASE 2 WORK
PHASE 1 WORK
BOUNDARY
BOUNDARY
PROJECT
PLATFORM
EXISTING
SUB - TITLE :
SWAMP
CURTAIN
BERM
WORK
FILL
FENCE
NO. LUKISAN
LEVEL
E -1300
SILT
SILT
E -1200
DI LUKIS
TARIKH
43.820 39.940
E -1400
45.416
45.251IL 46.703
43.323
47.856 50.185 40.118 45.180 45.339
45.442 45.194 42.277
40.360 34.253
EP
39.646 40.027
m 45.438
0.5 34.329 37.235
EXISTING
45.377 29.765
FENCING
38.557
E -1178.908
TBM 2
45.304
H H H 38.493 H H 36.556 30.473 30.396
EP
48
50.645 43.488
MH
31.258
36.050
35.858 34.428
MH
44.776IL 45.318
S.B*
33.828
37.673
50
36.557 29.933
31.473
29.395
45.531 42.685
39.324 39.234
45.085 39.757
43.509 37.566 39.767
50.155
44.776CULV 33.268 39.188
36.954
50.211
32.007 32.043 32.063
45.379 44.458
h
oug
45.305 45.699 32.518 37.703 an
29.640
h Tr
X
45.330 X
45.242 X
X
mb
Was ere
44.262 33.459 31.281 X
33.365
33.402 ri S
X
44
44.889 37.902 Da
32.675
X
50.312 X
50.236 43.843
X
30.702 39.958
45.704 30.306
31.262IL X
KI 39.585
36.592
X
KA
34
43.605 N
ap
CD
LA 36.986
45.313 34.103 JA 35.810
X
in 32.988
Temporary Earthdra
Tr
PAYA
LU
X
42.982 44.731IL
Si
LA
CD
LONGKANG 0.4m
X
45.627
50.266 43.497 33.936 t r
30.298
30.974IL 31.392 33.380
Cu
45.556
X
44.701 31.156
38.447 36.763
lt
Si
44.337 ARAS AIR =31.192m 35.510
45.218 PADA 8.25am
45.253 39.986 05/08/2001
44.279 44.919IL 41.743 32.370
33.429
45.224 40.673 32.220
45.239 50.362 45.665 42.294 31.728
45.708
45.386 42.947 31.206
Hydroseeding
44.688 45.390
45.164 45.216 48.135
44.579
FILL
37.957 31.443 31.687
33.982 30.384
31.252IL
42
31.272
35.502
Phase 1
45.576IL
45.743 38.433 35.738 32.686 32.162
40.779 45.550 32.282
40.819 39.335
32.479 31.692
AS
45.367 31.239 31.704
R E G
34.156
VE
37.358
ra
N L AS
32.794
45.52450.004
ER
H
tT
AI E N
S IN
45.230 45.433
H IP O
ES
44.665 33.103 PONDOK 32.729
C P TR
l
33.144
Si
36
32.767 32.903
PE
50.210 35.844
40.791 45.498
45.352IL 34.611 32.648
40.780
33.091
X
38.737
37.581
2
X
X
34.780 34.390
33.695 33.426
CUT
31.959
CD
38.187 34.438 33.531
44.882IL 45.393
50.199 44.480IL 31.674
X
45.130 45.374
44.601 45.279 45.312 40.480 33.592 32.422
40.796 45.426 39.128
SUMP
X
34.903 33.926
37.673 N -9300
X
50.041 32.994
32.664
34.188
X
CD
H
31.868
45.349 50.176 45.409 36.075
44.574
38 ary Earthdrain
45.222
X
44.683 45.352 32.221
38.756
34
45.155 45.423 40.357 34.594
X
45.185 37.042
45.027IL 44.800IL
X
34
35.842
MH
50.190 32.278
50.256
X
47.868
3819
50.141
36
33.565
45.699
H
45.205IL
45.268
44.882
X
Tempor
36.254
43.289 40.000
35.420 34.103
X
40.772 36.179 34.739
X
43.016 33.140
6257
X
32.450
34.277 32.283
H
X
41.775 33.558
38.043 32.669
32.544 34.752
39.876 36.410
X
36.071 34.549
X
X
35.465
38.846
34.602 N -9400
X
40.369 36.949 35.703 33.622
35.511
H
X
35.047
33.087
X
33.920
35.969
33.184 39.777
X
38.007
X
40.308 36.075 33.138
Phase 2
X
39.404
35.254 34.052
H
X
38.628
33.439 36.965
X
X
33.549
X X X X X X X X X X X X X X X X X X X
35.460 38.897 42.833
CD
X
42
43.121
41.987 36.348
CD
39.537
Perimeter Control-Cut Off Drain
H
34.749
X
36.767
6256
36.690 34.276 41.053
X
TEMPORARY SAND BAG BARRIER
TEMPORARY EARTHDRAIN
SPOIL MANAGEMENT AREA
SILT TRAP WITH BAFFLES
CONSTRUCTION
PROJECT SEWAGE TREATMENT WORK EXTENSION
1 : 700
The details of construction work for during
HYDROSEEDING
(PHASE 2)
(DISPOSAL A)
DURING
development phase can be refer to
CHECK DAM
ROCK FILL
CULVERT
DI PERIKSA
TROUGH
RIP RAP
SKALA
WASH
SKALA 1 : 1000
CUT
N
ENGINEER SIGNATURE :
OWNER SIGNATURE :
30.982
PL
30.982
004
X
PROJECT TITLE :
HOARDING
SPOT HEIGHT
PHASE 2 WORK
PHASE 1 WORK
BOUNDARY
BOUNDARY
PROJECT
SUB - TITLE :
PLATFORM
EXISTING
SWAMP
CURTAIN
BERM
NO. LUKISAN
WORK
FILL
FENCE
LEVEL
SILT
SILT
DI LUKIS
TARIKH
40
45.216 48.135
37.957 31.443 30.384
31.252IL 31.687
33.982
42
31.272
35.502
45.576IL
45.743 38.433 35.738 32.686 32.162
45.550 32.282
40.819 39.335
32.479 31.692
PL 35.00
AS
34.156
ap
VE
37.358
S I S
32.794
N L A
45.52450.004
ER
Tr
AI E N
45.433
H IP O
ES
PONDOK
lt
33.103 32.729
C P TR
33.144
Si
36
32.767 32.903
CD
PE
50.210 35.844
45.498 36.754
45.352IL 34.611 32.648
40.780
33.091
X
38.737
PL 35.00
el
37.581
2
X
nn
Phase 1
ha
X
34.780 34.390
33.695 33.426
C31.959
X
CD
ion
38.187 34.438 33.531
ers
44.882IL 45.393
50.199 44.480IL 31.674
Div
X
45.374
45.279 45.312 40.480 33.592 32.422 35.468
45.426 39.128
SUMP
34.903 33.926
37.673 N -9300
Hydroseeding
X
CD
45.346IL 32.637
32.149
X
31.868
45.349 50.176 45.409 36.075
38 ary Earthdrain
35.139
X
45.352
38.756 32.221
34
45.185 37.042
44.800IL
X
34
35.842
MH
50.190 32.278
50.256 l
ne
X
47.868
3819
50.141
36
an 33.565
Ch
45.699
X
45.205IL
ion
45.268
44.882
X
ers
FILL
Tempor
36.254
40.000
Div
35.420 34.103
X
33.140
6257
32.450
34.277 32.283
X
H
33.558
38.043 32.669
32.544 34.752
39.876 36.410
X
36.071 34.549
X
X
35.465
38.846
34.602 N -9400
X
36.949 35.703 33.622
35.511
H
X
35.047
33.087
X
33.920
35.969
33.184 39.777
X
38.007
X
36.075 33.138
Phase 2
X
39.404
35.254 34.052
H
X
38.628
33.439 36.965
X
X
33.549
X X X X X X X X X X X X X X X X X X X
35.460 38.897 42.833
CD
X
42
43.121
36.348
X
CD
39.537
Perimeter Control-Cut Off Drain
H
CUT
34.749
X
36.767
6256
36.690 34.276 41.053
X
CD
48.260
X
38
Perimeter Control-Cut Off Drain
34.599
X
37.105
43.522
41.515
X
50.384 H
X
H
Temporary Earthdrain
43.107
Temporary Sand Bag Barrier
36.796 44.714
33.397
40" 23' 90°
53.416
H
40
46
X
36.423 49.055
42
Earth Drain
35.262 49.353
X
34.453
40
43.765
I
N KAK
50.829
X
39.524 53.084 45.324
X
39.122
PEJALA
H
53.684
X
51.814
50.339
50.340
X
43.137
36.192 39.816
N
X
X
35.367 40.333 51.427
40.201
47.573
51.088
X
52.436
H
52.257
X
36.314
36.687
35.804
CD
51.061
CD
54
36
42.274 53.636
41.808
40.494 36.367 37.680
Perimeter Control-Cut Off Drain 45.480
48
35.597
36.117 38.155
33.262
38.688
50
37.494 40.885
39.038
44
41.752 47.739
36.675 40.897 56
21935
34.371 39.728 61.520
6262
36.670 41.303
47.381 57.736
37.470
34.859 36.297
38 45.705
52.781
3966
41.580
45.144
58
34.955 38.150
Run On from
35.369 48.425
63.137
44.226 41.425 42
6263
62.289
36.152
47.946
60.732
48 59.811
44.406 59.514
43.110 51.040
43.532
52
50 49.726
44
56
52.138 44.266
47.345 46.181 52.388
46
6264
50.388
46.740
E -1400
55.839
45.070
E -1500
E -1300
52.317 51.583 49.405 53.459 57.793 59.940
48.377
52.343
48.425
6-1
GUIDELINES ON LD-P2M2
CHAPTER 6
The project implementation of the LD-P2M2 Document basically boils down to the
notion of “IIM”, or the conducting the processes of “Install”, “Inspect” and
“Maintain”. Different projects may adopt differing approaches to conduct IIM but the
ultimate purposes of these varying approaches remains the same, and are likely include
the following:
6.1.1 Install
Install and construct the appropriate P2M2s including BMPs at the project
site during the pre-construction and construction stages of the project, in
accordance with the LD-P2M2 plans and other related plans;
Install the P2M2s and BMPs for land disturbing activities in accordance
with the basic principles mentioned in the preceding chapters:
6.1.2 Inspect
The minimum information encompassing the inspection activities from day one
of the construction commencement through completion of the project includes:
Inspector’s Daily Logs; Project Log Book (Field Diaries); Photographs labeled
and dated for record purposes, and Construction Progress. In addition, any
inspectors of P2M2s for land disturbing activities have to be prepared and
possess knowledge on the following elements:
The Inspector must consider safety first during his line of inspection duties.
When conducting site inspections, the EO should take due consideration of the
following potential health and safety hazards on project sites:
Insects
Animals and Plants
Exposure to the Elements
Vehicle and Equipment
Scrapes, Scratches and Cuts
Slips, Trips and Fall Hazards
Falling Objects
Utilities
Trenching
6-5
GUIDELINES ON LD-P2M2
Confined-Space Inspections
Excessive Noise
Dust and Airborne Particulates
Traffic Safety (Driving, Stopping and Parking)
Hazardous Material Areas
Asbestos Exposure
Pesticides Exposure
Chemicals/Compounds
Gas/Fuel
Spill Prevention
Blasting and Explosives
Protective Clothing
Information from site observations and inspections is only useful if only such
information can be effectively communicated to the responsible parties, and one
of the most critical factors in ensuring the success of this communication is
through the attitude and ethic of the EO. In this regard, the following guidelines
should be adhered to during any site inspections:
Does this person have the authority to direct resources and make changes
in an emergency situation?
Discuss the plans and specifications for the project, traffic control
techniques, and define lines of authority;
Be proactive by understanding the project from the contractor’s point of
view but does not permit reduced quality in order to increase the
contractor’s productivity;
Influences the construction process to obtain the best possible results;
Offer assistance while being careful not to supervise construction;
To be prepared to respond to the following common claims or statements
from Developers, Contractors and relevant parties in the context of erosion
and sediment control:
It’s normal to cause little pollution (sedimentation) during any land
development.
Lack the knowledge in handling erosion and sediment control since we
are not so called technical guys.
It’s costly and expensive to implement ESC.
6.1.2.1 Checklist
Regulatory compliance
Performance of P2M2
P2M2 installations
Performance monitoring
P2M2 suitability
Maintenance
Documentation/reporting
P2M2 closure
6.1.3 Maintain
After the installation, all the erosion and sediment controls must remain in
effective operating condition during the construction period and be protected
6-7
GUIDELINES ON LD-P2M2
from activities that would reduce their effectiveness. Maintenance differs from
the other activities in that it must begin as soon as the first practice is installed
and must continue through all the succeeding activities until the permanent
erosion control measures are established and functioning.
iii. Document the schedule for installing the erosion or sediment control and
making them operational as soon as practicable after the 72-hour
timeframe. Where these actions result in changes to any of the erosion or
sediment controls or procedures documented in the LD-P2M2 Document,
this document must be modified accordingly within 7 calendar days of
completing this work, and submitted to the relevant authorities.
6.2.1 General
6.3.1 Definition
6.4.1 Definition
6.5.1 Definition
To be certain that all erosion and sediment control measures in the approved
plan have been properly installed and maintained;
Compliance.
In outlining the strategy during the planning stage, the basic principles of LD-
P2M2 as listed in Section 6.1.2 will need to be taken into consideration into the
strategy. Additionally, the elements to be included in the Performance
Monitoring will need to be briefly described, such as: Mark Clearing Limits;
Establish Construction Access; Control Flow Rates; Install Sediment Controls;
Stabilize Soils; Protect Slopes; Protect Drain Inlets; Stabilize Channels and
Outlets, Control Pollutants; Control Dewatering; Maintain BMPs; Manage the
6-10
GUIDELINES ON LD-P2M2
Project; and Training, CPESC AND CESSWI certified. Alongside these will be
to list all of the suggested / proposed BMPs as per the LD-P2M2 Document.
To inspect all erosion and sediment controls once every 7 days and within
24 hours after each rainfall of 25mm (0.5 inch) or greater.
To hold site meeting every two (2) weeks with the project developer and
contractor.
identifying best and worst practices while pointing out correlations and changes
that have occurred throughout the project implementation.
6.6.1 General
Whether we are talking about a small project with a footprint of 10ha or another
mage project commanding a footprint of 10,000ha, the first and foremost record
that the EO should create in the process of LD-P2M2 implementation is a
“Master List of Installation”. This list aims to provide a master record for future
easy reference on the status of all the installed P2M2s for any single project
component. As anticipated, the list of P2M2 and BMP installation will become
longer and harder to manage as the project progresses, if such a list is not
available.
6-12
GUIDELINES ON LD-P2M2
When a P2M2 or BMP is first installed on site, it is important to check and verify that it
has been correctly installed. In this regard, this “Installed P2M2 Verification” record
provides the evidence to confirm that all the P2M2s were checked to be correctly built
prior to being used.
The objective of this record is to maintain a status of all the P2M2’s during their first
installation, by documenting the following information:
Comply Production
Proposed
with Std / If does not comply, describe Suggested Corrective Team Reference Remarks /
Parameters for checking Details Rectification Status
Dwg / discrepancies Actions Informed Photos Instructions
Date
Spec? Date
Drawing reference Dwg ABCD, Rev 1 No Length specified 40m but actual See below 5.1.2011 See below F 1,2
built 20m
Standard & Specification NA NA - - - - - - -
Location Ch 0+750, adjacent Sg AAA Yes - - - - P 10 -
Size All ok except for length No Length is short by 20m See below 5.1.2011 See below P/F 1,2,3,4
Materials of construction Concrete Yes - - - - P - -
Physical condition Incorrect length No Length is short by 20m Rectify to comply to 5.1.2011 19.1.2011 F 1,2 Upstream
approved drawings activities to ST1
cannot
commence
Clear of construction Yes NA - - - - P 5
waste/debris
Inlet point protected? Yes NA - - - - P 6
Discharge point protected? Yes NA - - - - P 7
Discharge lower than inlet Yes Yes - - - - P 8
Accessories provided Water/Depth measuring poles Yes - - - - P 9
Comply Production
Proposed
with Std / If does not comply, describe Suggested Corrective Team Reference Remarks /
Parameters for checking Details Rectification Status
Dwg / discrepancies Actions Informed Photos Instructions
Date
Spec? Date
Drawing reference Ok as per 1st inspection
Standard & Specification Ok as per 1st inspection
Location Ok as per 1st inspection
Size Ok Yes Actual length = 40m - - - P 12,13
Materials of construction Ok as per 1st inspection
Physical condition Length rectified Yes - - - - P 12,13
Clear of construction Yes NA - - - - P 11
waste/debris
Inlet point protected? No NA New concrete waste plugging Remove plugged waste 22.1.2011 22.1.2011 F 14,15 Upstream
inlet activities to ST1
cannot
commence
Discharge point protected? Yes NA - - - - P 16
Discharge lower than inlet Ok as per 1st inspection
Accessories provided Ok as per 1st inspection
3rd Inspection Date & Time: 24.1.2011; 10.00am EO/EO Rep:_______________________ Production Team Rep:_______________________
Comply Production
Proposed
with Std / If does not comply, describe Suggested Corrective Team Reference Remarks /
Parameters for checking Details Rectification Status
Dwg / discrepancies Actions Informed Photos Instructions
Date
Spec? Date
Drawing reference Ok as per 1st inspection
Standard & Specification Ok as per 1st inspection
Location Ok as per 1st inspection
Size Ok as per 2nd inspection
Materials of construction Ok as per 1st inspection
Physical condition Ok as per 2nd inspection
Clear of construction Yes NA - - - - P 20
waste/debris
Inlet point protected? Yes NA - - - - P 20,21
Discharge point protected? Yes NA - - - - P 22
Discharge lower than inlet Ok as per 1st inspection
Accessories provided Ok as per 1st inspection
Following the successful installation of the specific P2M2 or BMP, i.e., the installation
has passed the inspection of the EO to be in compliance with the specifications or
drawings, periodic inspections of the said installation will be undertaken. The “Follow-
up Inspections” record will thus provide the evidence on the functionality and
effectiveness of these installed P2M2s during their operation and throughout their life.
Inspection Record
Component: Silt Trap Base Elev: 510.0m Inlet Inv Level: 512.5m Sediment Depth Trigger Elev:
511.05m
Label: ST1 Bank Elev: 512.5m Outlet Inv Level: 511.7m Water Depth Trigger Elev: 512.40m
Installed
Date: 1.1.2011 Freeboard: 0.3m
Maintenance Record
Component: Silt Trap Base El: 510.0m Inlet IL: 512.5m Sediment Depth Trigger Elev: 511.05m
Label: ST1 Bank El: 512.5m Outlet IL: 511.7m Water Depth Trigger Elev: 512.40m
Installed Date:1.1.2011 Freeboard: 0.3m
A proper accounting of all the sampling results based on the dedicated monitoring
points as stipulated in the EMP shall be maintained. Such database will provide the
record on the planned and ad-hoc sampling events undertaken, to verify the
effectiveness of the installed P2M2s. The database should include the following
information:
Based on the sampling results and field observations, a simple analysis of the collected
data shall be undertaken to provide the project stakeholders with some information on
the performance of the P2M2s, such as the trending record on the performance of the
installed P2M2’s, by documenting the following information:
Component: Silt Trap Base Elevation: 510.0m Inlet IL: 512.5m Sediment Depth Trigger511.05m
Elevation:
Label: ST1 Bank Elevation: 512.5m Outlet IL: 511.7m Water Depth Trigger Elevation:
512.40m
Installed Date: 1.1.2011 Freeboard: 0.3m
- flow conditions inside silt trap Normal - no observed shortcircuiting 23.1.2011 4a 0.2
24.1.2011 4a 0
25.1.2011 4a 8
Hill near Ch
ST1 - Sediment & Water Depths 26.1.2011 4a 11
0+300
27.1.2011 4a 5
for the period 1.1.2011 - 31.1.2011
28.1.2011 4a 8
513.0
29.1.2011 4a 8
512.5 30.1.2011 4a 13
31.1.2011 4a 15
512.0
511.5
Water Depth, m
511.0
El ev, m
Sediment Trigger
509.5 Discharge IL
509.0
508.5
22.1.2011 25.1.2011 26.1.2011 30.1.2011 31.1.2011
Dates
6.6.8 Reporting
Thereafter, a simple shall be prepared to provide a summary of the above analysis and
interpretation, and decision making based on administrative and technical findings.
The audit team shall make reference to the following information in conducting the
audit:
All auditors must be registered with DOE. Auditor for the development stage should
also possess the CESSWI Certificate (competency to inspect the LD-P2M2 and erosion
and sedimentation control plans).