Homework/Assignment: Full Name of submitter: Nguyễn Ngọc Hân Student ID: IEIEIU18152
Homework/Assignment: Full Name of submitter: Nguyễn Ngọc Hân Student ID: IEIEIU18152
(Cellular Manufacturing)
Operatin
Product Fe Ma Ap Ju Au Se
g time Jan May Jun Oct Nov Dec
s b r r l g p
(s)
17(*
A 90 17 17 17 17 17 17 17 17 17 17 17
)
B 60 30 30 30 30 30 30 30 30 30 30 30 30
C 120 40 40 40 40 40 40 40 40 40 40 40 40
D 210 20 20 20 20 20 20 20 20 20 20 20 20
(*): in thousands
a) Design assembly line(s) based on the following inputs.
- The line also can meet demand as demand goes up by 30%
1
- To avoid ergonomics issues related to repetitiveness, minimum cycle time of a workstation
is not lower than 15 seconds.
- Working time: 304 working days per year, 7 hours per day, and 2 shifts per day.
Hints
- Select a representative product.
- Design assembly lines which meet demand and use minimum resources. Fill in the below table
(please show your work as well).
6 Number of cells
b) If forecast increases by 20%, how many extra operators required per cell?
2. Given this precedence diagram:
Takt time = 12 min
A 4
B (after A) 5
C (after B) 2
2
D (after A) 10
E (after D&C) 3
- Continue using this form to complete your works and submit on Blackboard
- Name your file
o If you submit individually: 21Lean_HW6_StudentID_FullName
o If you submit for a group (Group # are as per the number you have registered as guided
in the file “Semester Project Requirement” and be finalized by lecturer):21
Lean_HW6_G#
- Due Date is defined in detail at each “ ASSIGNMENT INFORMATION” from Blackboard
- Maximum score of late submission is two third of “Point Possible”
- If you can’t submit on Blackboard: Email your work to TA, copy it to your Lecturer, attached also
the screenshot of your Blackboard showing error in that transaction
---------
Answers/Works
Contribution:
Question 1:
3
Operating Total
Products Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
time (s) demand
A 90 17 17 17 17 17 17 17 17 17 17 17 17 204
B 60 30 30 30 30 30 30 30 30 30 30 30 30 360
C 120 40 40 40 40 40 40 40 40 40 40 40 40 480
D 210 20 20 20 20 20 20 20 20 20 20 20 20 240
a) Representative product :
Product C has the highest running time, we choose C as the Representative Product.
Annual available time = Working days * Hours per day * Shifts * Seconds
Takt time = Total yearly available time / Total demand of the family
Number of operators required = Operating time (representative product) / Takt time = 120 / 11.93 =
10,06 operators 11 operators
4
Number of cells = Number of workstations / Number of workstations per cell
Real elasticity = Number of workstations per cell / Number of operators per cell
= 8 / 6.17 = 1.3
Cycle time per workstation = Operating time / Number of workstations per cell = 120 / 8 = 15s
Cycle time per operator = Operating time / Number of operators per cell = 120 / 6.17 = 19.45 s
Capacity per cell per hour = 3600 / Cycle time per operator = 3600 / 19.45 = 185.09 pieces / hours
Total capacity per hour = Capacity per cell per hour * Number of cells = 185.09 * 1.63 = 301.7
pieces / hours
b) Since the Elasticity coefficient ensure the production line still able to meet up 30% higher
in demand, therefore, no extra operators are needed.
Question 2:
5
Activity Duration (min)
A 4
B (after A) 5
C (after B) 2
D (after A) 10
E (after D&C) 3
Total: 24
A B C
D E
Second, we group elements into workstations so that the sum of the element times at each
workstation is less than or equal to the desired cycle time of 12 minutes.
Assembly-line diagram:
6
A, B C,D E
Total completiontime 24
Effciency = = = 0.66 = 66%
Actual number of workstation × Actual cycle time 3 x 12
By traditional straight assembly-line diagram, there is no way that satisfies the condition with the
smallest number of workstation.
7
Total completiontime 24
E= = =1=100 %
Actua l number of workstation × Actual cycle time 2 x 12
This design has the fewest number of workstations, highest efficiency.