BUNKER RENOVATION
1. Bunker Sand Core-Out & Stockpile
2. Remove Existing Bunker Liner
3. Check & Flush Existing Drainage
4. Bunker Edging & Lower Bunker Faces
5. Re-Install Existing Bunker Sand
6. Sod Bunker Faces
PROJECT DETAIL:
# 4 - Reshape and liner removed
# 9 - 2 Bunkers Reshaped and Liner removed
#14 - Minimize 2 Bunkers and Liner Removed
#17 - Reshape Bunker and Liner Removed
#18 - Reshape Bunker
2
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
TEE COMPLEXES
1. Sod Strip Tee Tops & Surrounds
2. Laser Level Tee Top
3. Sod Tee Surrounds
4. Bluegrass Seed Tee Top
PROJECT DETAIL:
# 2 , # 4, # 5, # 6
# 7 - Men’s Tee Complex
# 8 - Men's White Tee Complex
# 8 - Men's Blue Tee Complex
# 9 - Men's White Tee Complex
#14 Men's Blue Tee Complex
#14 - Men's White Tee Complex
#17 - Men's Tee Complex
#18 – Men’s Tee Complex
3
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
CART PATHS
1. Cart Path Cut-In & Compaction
2. 6’ Wide Concrete Cart Path Extension – Avg. of 100 LF / proposed golf holes
3. Backfill & Prep Cart Path Edges
4. Sod Cart Path Edges
PROJECT DETAIL:
# 3 Tee
# 3 Green
# 4 Tee - Green Run
# 5 Green
# 6 Green
# 7 Tee
# 7 Green
# 9 Tee
#11 Tee
#12 Tee
#12 Green
#13 Tee
#13 Green
#15 Green
#16 Tee
#17 Tee - Green Run
#18 Tee
4
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
#11 POND
1. Remove Existing Rip Rap Shoreline & Stockpile
2. Lake Excavation – Avg. 4’ Depth
3. 30 Mil PVC Liner w/ Soil Cover
4. Re-Install Existing Rip Rap Shoreline
5
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
#8 POND SHORELINE
1. Remove Existing RR Tie Wall & Dispose Off-Site
2. Sod Strip Disturbed Area
3. Grade Shoreline
4. Seedbed Prep
5. Sod Shoreline
6
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
PHASE II
Golf Course Renovation Proposal
7
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
PHASE II
SHORT GAME AREA
1. Topsoil Management
2. Earthwork
3. Shaping
4. Drainage
5. Irrigation
6. California Greens Construction
7. Finish Grading & Seedbed Prep
8. Fertilizer
9. Grassing
8
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
9
PLATTEVIEW GOLF CLUB
Golf Course Renovation Proposal
DRIVING RANGE
1. Topsoil Management
2. Earthwork
3. Rough Shaping
4. Drainage
5. Irrigation
6. DR Tee Construction w/ 4” Tee Sand
7. Concrete Cart Path
8. Finish Grading & Seedbed Prep
9. Fertilizer
10. Grassing