REMARKS: - INSTALLING THE CABLE FEEDERS TO THESE BOARDS, CURRENT SYSTEMS & LOW VOLTAGE POWER CABLES IS
1.THE LAYOUT DRAWINGS DO NOT SHOW ALL THE SYSTEMS , HOOKING UP OF EQUIPMENT WILL BE THE SYSTEM SUPPLIER 300MM.
ITEMS, OR ACCESSORIES COVERED UNDER THE SCOPE OF RESPONSIBILITY. .23 THE MAXIMUM FILLING RATIO FOR POWER &
ELECTRICAL WORKS TO BE EXECUTED THE LAYOUT .10 CONDUCTORS FOR SINGLE PHASE SOCKETS OUTLETS COMMUNICATION CONDUITS IN SITE WORK ARE:
DRAWINGS SHALL BE READ IN CONJUNCTION WITH ALL CIRCUITS SHALL BE 4MM COPPER CONDUCTORS AND · MIN50. MMD FOR POWER CABLE WITH MAX 40%.
RELEVANT OR SPECIALIST DRAWINGS AND SPECIFICATIONS . PROTECTED BY 16A CIRCUIT BREAKERS UNLESS OTHERWISE OF CONDUIT CAPACITY.
2.DO NOT SCALE FROM THE LAYOUT DRAWINGS WORK INDICATED. · MIN50. MMD FOR LOW CURRENT SYSTEMS WITH
ACCORDING TO ARCHITECTURAL OR ELECTRICAL DETAILS .11 IN THE ABSENCE OF ANY INDICATION ON THE DRAWINGS MAX 40%. OF CONDUIT CAPACITY.
UNLESS OTHERWISE AUTHORIZED . OR THE SPECIFICATIONS, THE INSTALLATIONS SHALL BE .24 ALL C.BS WITH FRAME RATING LARGER THAN 100A
3.ALL EQUIPMENT LAYOUTS ARE PROVISIONAL . FINAL DONE TO THE SATISFACTION OF THE ENGINEER. SHOULD HAVE ADJUSTABLE THERMAL OVERLOAD SETTING.
LAYOUT SHALL BE DETERMINED BY THE CONTRACTOR FROM .12 THE CONTRACTOR SHALL PROVIDE ALL IRON ANGLES, .25 CONTRACTOR SHALL PROVIDE CONTROL CONDUIT &
THE CONSTRUCTION /SHOP DRAWINGS AND AFTER AND FIXING ACCESSORIES REQUIRED FOR COMPLETE WIRING AS PER OPERATIONAL REQUIREMENTS SHOWN ON
COORDINATION WITH OTHER TRADES . INSTALLATION OF LIGHTING FIXTURES, OUTLETS & ROUTES. HVAC AND PLUMBING DRAWING.
4.THE SIZE OF CONDUITS AND /OR CABLE TRAYS IS IN .13 FOR EXACT QUANTITY, TYPE & LOCATION OF ELECTRICAL .26 EXACT METHOD OF JOINING CABLE TRAYS,AND CABLE
GENERAL NOT SHOWN ON DRAWINGS . THE SIZE OF ALL OUTLETS REFER TO INTERIOR DESIGN DOCUMENT. TRUNKING SHALL BE IN ACCORDANCE WITH THE
CONDUITS AND/OR CABLE TRAYS SHALL BE SELECTED BY .14 THE CONTRACTOR SHALL BE RESPONSIBLE FOR RESPECTIVE MANUFACTURERS RECOMMENDATION USING
THE CONTRACTOR IN ACCORDANCE WITH BOQ , MODIFYING THE NO. OF CIRCUIT BREAKERS, RATING, AND PROPER COMPONENT.
REGULATIONS AND /OR STANDARDS AND WILL BE FUNCTION WIRING ACCORDING TO MANUFACTURER DATA WITHOUT .27 GROUNDING TO LOW CURRENT SYSTEMS SHALL BE
OF THE NUMBER AND SIZE OF THE RESPECTIVE ANY EXTRA COST. SEPARATE GROUNDING PIT AND CONNECTED TO BUILDING
CONDUCTORS. .15 ALL DISCONNECT SWITCHES FOR A/C SHALL BE GROUNDING NETWORK.
5.PERFORATED CABLE TRAY SHALL BE FIXED AND COVER ADJACENT TO THE UNIT.. .28 THE DISTANCE BETWEEN EARTH PIT SHALL BE DOUBLE
PROPERLY AND SHALL NOT FIXED DIRECT TO ROOF SLAB . .16 UNLESS OTHERWISE INDICATED MINIMUM SIZE CONDUIT; OR MORE THAN LENGTH OF EARTHING ROD.
6.TEARTH CONTINUITY CONDUCTORS ARE NOT INDICATED · FOR EXTERIOR INSTALLATION IS 25MM DIAMETER .29 THE CONTRACTOR SHOULD PROVIDE COMPLETE
ON THE DRAWINGS , BUT SHALL BE RUN WITH ALL CIRCUITS OR AS SHOWN IN PANEL SCHEDULE. CENTRAL INTERFACE BETWEEN THE SOLAR GENERATION
IN ACCORDANCE WITH SPECIFICATIONS , REGULATIONS · FOR INTERIOR INSTALLATION IS 25MM DIAMETER SYSTEM & GENERATOR SET.
AND/OR STANDARDS. OR AS SHOWN IN PANEL SCHEDULE. .30 THE DIMENSION OF ELECTRICAL PANELS AND
7.THE COLOR CODE FOR A FOUR WIRE CIRCUIT IS - ONE .17 CONTRACTOR SHALL PROVIDE MATCHING PLUG IN FOR EQUIPMENT'S SHALL BE AS PER APPROVED FABRICATOR /
BLACK, - ONE RED , ONE BLUE AND ONE YELLOW ANY ALL SPECIAL OUTLETS. SUPPLIER SHOP DRAWING.
CONDUCTOR INTENDED FOR GROUNDING PURPOSE SHALL .18 CONTRACTOR RESPONSIBLE FOR CHANGE ALL EXISTING .31 CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALL
BE GREEN WITH YELLOW STRIPE . FLORESCENT TUBE (T) 8LIGHT BY LED TUBE (T) 8INCLUDE SUITABLE VENTILATION SYSTEM IN BATTERY ROOM TO
8.CONTRACTOR RESPONSIBLE TO DISCONNECT ALL WIRING ALL OPERATION ACCESSORIES FOR ALL LIGHTING FIXTURES ASSURING REFRESHING AIR FLOW INSIDE ROOM .
IN EXISTING DISTRIBUTION BOARD AND RECONNECTED IN AS PER BOQ. .32 CONTRACTOR RESPONSIBLE TO DISTRIBUTE ALL
NEW DISTRIBUTION BOARD AS PER SINGLE LINE DIAGRAM . .19 LED LAMPS SHALL BE FURNISHED AND INSTALLED IN ALL DISTANCE BETWEEN ALL SYSTEM COMPONENTS INSIDE
9.THE CONTROL AND /OR SWITCHBOARDS FOR THE LIGHTING FIXTURES. BATTERY ROOM AS PER MANUFACTURE INSTALLATION
DIFFERENT SYSTEMS SUCH AS THE AIR CONDITIONING .20 ALL OUTDOOR WIRING ACCESSORIES SHALL BE WEATHER INSTRUCTION.
EQUIPMENT MACHINES , ....ETC . WILL BE IN THE SCOPE OF PROOF TYPE.
SUPPLY OF THE SYSTEM SUPPLIER . THE ELECTRICAL .21 FOR GROUND-FAULT CIRCUIT INTERRUPT (GFCI) REFER
CONTRACTOR WILL BE RESPONSIBLE FOR FURNISHING AND TO PLANS AND PANEL SCHEDULES.
.22 THE MINIMUM SEPARATE DISTANCE BETWEEN LOW
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
DESIGNED BY: A3 AS SHOWN OF ISSUE
13/7/2019
Aisha School MAIN REMARK IFA
S-00
REVIEWED BY: PROJECT NO:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2
FOR RESULTS THAT MATTER. DRAWING TYPE: APPROVED BY: DATE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRICAL DESIGN UNOPS DESIGN REVIEW JULY /13/2019
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
WATER PROOF 2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
BOX 15CM X 15CM ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. ALL OUTDOOR OUTLETS, SOCKET OR WIRING
ACCESSORIES SHALL BE WEATHER PROOF TYPE.
5. ALL DISTANCE BETWEEN SYSTEM COMPONENTS INSIDE
3/4" PVC PIPE BATTERY ROOM TO BE DISTRIBUTE AS PER MANUFACTURE
SCH. 40.
INSTALLATION INSTRUCTION.
3*4sqmm cable
EMERGENCY MAIN
EMDB DISTRIBUTION BOARD.
AC COUPLING PANEL
OLD SDB
WATER PROOF
CONNECTION BOX
SDB
BETWEEN CHARGE
CONTROLLER AND
BATTERY RACK
BATTERY RACK.
SDB
EMDB MTS
AC
COUPLING
PANEL
2RACKS 2RACKS
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
NEW ELECTRICAL DISTRIBUTION TENDER DOCUMENTS.
UNOPS
S2-01
Aisha School PLAN
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 1:1
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. ALL OUTDOOR OUTLETS, SOCKET OR WIRING
ACCESSORIES SHALL BE WEATHER PROOF TYPE.
5. ALL DISTANCE BETWEEN SYSTEM COMPONENTS INSIDE
BATTERY ROOM TO BE DISTRIBUTE AS PER MANUFACTURE
INSTALLATION INSTRUCTION.
AC
COUPLING
PANEL
CONNECTION BOX
S&H D BETWEEN CHARGE
CONTROLLER AND
BATTERY RACK
AC≈
HYBRID INVERTER
DC=
BATTERY RACK.
AC COUPLING PANEL
EXHAUST FAN
S&H D
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
CONTROL ROOM TENDER DOCUMENTS.
UNOPS
S2-02
Aisha School
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 1:4
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. ALL CABLE SHALL BE ROUTE IN PERFORATED GI
CABLE TRAY.
5. CABLE TRAY SHALL BE FIXED ABOVE UNISTRUT NOT
DIRECT IN ROOFTOP.
PHOTOVOLTAIC MODULE
+
_
DC-COMBINER
BOX COMBINER BOX
_
+
+
DC-COMBINER
BOX-2
_
_
DC-COMBINER
BOX-1
+
+
_
_
+
100
_
_
+
CABLE TRAY
DC-COMBINER
_
BOX-3
+
50
GI CABLE TRAY
_
TO CONTROL ROOM
ANCHOR
BOLT
NOT TO SCALE.
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
PV MODULE DISTRIBUTION TENDER DOCUMENTS.
UNOPS
S2-03
Aisha School ROOFTOP PLAN DETAILS.
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY:UNOPS DESIGN REVIEW
JULY /13/2019 1:1
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. LIGHTNING ARRESTER SHALL BE INSTALL IN
SUITABLE LOCATION AND HEIGHT TO COVER ALL
ROOFTOP AREA.
5. ALL EACH PV STRINGS SHALL BE EARTHED
SEPARATELY UP TO EARTHING BUS BAR IN
ROOFTOP.
PHOTOVOLTAIC MODULE
+
_
DC-COMBINER
BOX COMBINER BOX
EARTHING CABLE
EXT. WALL
H=68CM LIGHTNING ARRESTOR
W=19CM
LIGHTNING
ARRESTOR.
1C*10SQ.MM
TO EARTHING
_
PIT 1C*25SQ.MM
+
+
DC-COMBINER
BOX-2
_
_
DC-COMBINER
1C*6SQ.MM
BOX-1
+
+
_
_
+
+
_
_
+
CABLE TRAY
DC-COMBINER
_
BOX-3
1C*6SQ.MM
+
+
_
_
+
TO EARTHING
TO LIGHTNING PIT 1C*16SQ.MM
ARRESTER
1C*25 SQ.MM
TO EARTHING EARTHING
BUS BAR NO.2 BUS BAR NO.1
1C*16SQ.MM
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
PV STRINGS & COMBINER BOX TENDER DOCUMENTS.
UNOPS
S2-04
Aisha School EARTHING PLAN DETAILS.
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 1:50
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. EARTHING PIT SHALL BE CARRY OUT AS BE SITE
ENGINEER INSTRUCTION.
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
EARTNING DETAILS. TENDER DOCUMENTS.
UNOPS
S2-05
Aisha School
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 AS SHOWEN.
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
4. NEW DISTRIBUTION BOARD SHALL BE INSTALL IN
THE SAME LOCATION OF EXISTING ONE.
AC FUSE
CIRCUIT BREAKER
(MCCB/MCB)
HYBRID SOLAR SYSTEM INVERTER OUTPUT AC FUSE
MTS 100A
NEW EMDB
MCB, 4P
100A,25KA
RCB, 4P
100A,300mA
63A, 3P 63A, 3P 40A, 3P 40A, 3P 25A, 1P 25A, 1P 20A, 1P 16A, 1P 16A, 1P 10A, 1P
MCB 10kA
MCB, MCB, 10kA MCB, 10kA MCB, 10kA MCB, 10kA MCB 10kA
MCB, MCB
MCB, 10kA MCB
MCB, 10kA MCB 10kA
MCB, MCB, 10kA
CLASS B CLASS B CLASS B CLASS B CLASS B CLASS B CLASS B CLASS B CLASS B CLASS B
OUTDOOR
SDB1 SDB2 SPARE SPARE SPARE SPARE SPARE SPARE SPARE LIGHTING
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
SINGLE LINE DIAGRAM DETAILS. TENDER DOCUMENTS.
UNOPS
S2-06
Aisha School
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 AS SHOWEN.
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
2. ALL DIMENSIONS TO BE CHECKED AND CONFIRMED
ON SITE BEFORE COMMENCEMENT OF ANY WORK.
3. ANY DISCREPANCY TO BE REPORTED TO THE
UNOPS SITE ENGINEER/ PROJECT MANAGER
PROMPTLY BEFORE PROCEEDING.
Inside View Front View Side View 4. NEW DISTRIBUTION BOARD SHALL BE INSTALL IN
THE SAME LOCATION OF EXISTING ONE.
63A , 10 kA 25A , 10 kA
63A , 10 kA 20 A , 10 kA
40 A , 10 kA 16 A , 10 kA
40 A , 10 kA 16A , 10 kA
25 A , 10 kA 10 A , 10 kA
PUSH
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
NEW EMDB BLOCK DIAGRAM TENDER DOCUMENTS.
UNOPS
S2-07
Aisha School
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 AS SHOWEN.
1. ALL DIMENSIONS AND ELEVATIONS ARE IN
PV Module Combiner Box Battery Charger CENTIMETERS AND METERS RESPECTIVELY,
UNLESS OVER WISE MENTIONED.
85A
150 VDC
_
+
Total: 0.99Kwp
3 PV MODULE
STR NO.3
PHOTOVOLTAIC MODULE
+
_
_
+
DC =
AC≈
HYBRID INVERTER
Total: 0.99Kwp
3 PV MODULE
STR NO.4
_
+
SURGE ARRESTER
_
+
85A
150 VDC XPLE/PVC/CU1.0KV
XPLE/PVC/CU1.0KV
CIRCUIT BREAKER (MCB)
Total: 0.99Kwp
3 PV MODULE
STR NO.6
4X6 SQ.mm
3X6 SQ.mm
_
+
XPLE/PVC/CU1.0KV
3X6 SQ.mm DC FUSE
_
+
2(1x50 SQ.mm)
XPLE/PVC/CU1.0KV
3X6 SQ.mm
DC SWITCH ISOLATOR
_
(RED& BLACK)
+
2(1x50 SQ.mm)
85A (RED& BLACK)
2(1x50 SQ.mm)
STR NO.10 STR NO.9
(RED& BLACK)
_
+
2(1x35 SQ.mm)
(RED& BLACK)
_
+
2(1x50 SQ.mm)
(RED& BLACK)
2(1x50 SQ.mm)
(RED& BLACK)
150 A, 2P 150 A, 2P
Battery Rack Battery Rack
24 Batteries 24 Batteries
2V ,800 Ah 2V ,800 Ah
48 Volt 48 Volt
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: DESIGN BY: STATUS: NORTH: DRAWING NO:
SOLAR SYSTEM SCHEMATIC TENDER DOCUMENTS.
UNOPS
S2-08
Aisha School DIAGRAM
CHECKED BY: PROJECT NO: PAPER SIZE:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2 A3.
FOR RESULTS THAT MATTER. WORLD BANK GROUP. PROJECT LOCATION: DRAWING TYPE: DATE: SCALE:
SANA'A - YEMEN. Amran CITY-YEMEN ELECTRIC PLANS. APPROVED BY: UNOPS DESIGN REVIEW
JULY /13/2019 AS SHOWEN.
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
S2-09
REVIEWED BY:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2
FOR RESULTS THAT MATTER. DRAWING TYPE:
SANA'A - YEMEN. Amran CITY-YEMEN STRUCTURAL DESIGN APPROVED BY:
UNOPS DESIGN REVIEW
DATE:
JULY /13/2019
GALV (L)
50x50x3
STAINLESS
STEEL BOLTS ∅8 3mm
E-70 Channel C 80x40x1.25
GROUT
A B
2400
GALVANIZED BASE
PLATE 200x150x4 mm
1.25
80
350
2 2
10
4∅ 10 ANCHOR
GALVANIZED CONCRETE BOLTS 40
C 80x40x1.25 14cm LENGTH
FOR ALL POSTS
350 Channel C 60x30x1.25
2900
2 BASE PLATE - PLAN
STRUCTURE DETAILS
60
1.25
4∅ 10 ANCHOR
CONCRETE BOLTS
30
14cm LENGTH CONCRETE WITH
GALVANIZED EPOXY GROUT
BASE PLATE
1 1 4 mm THICK
GALV (L)
50x50x3 MASTER
SEAL 470
ROOF TILES RSH 43 in DN
100
120
A B CEMENT
MORTAL 1.5mm
in
EXISTING 3/4
MASTER FLOW ROOF SLAB
GROUT
932 AN(EPOXY)
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
6PV MOUNTING DESIGNED BY: A3 AS SHOWN OF ISSUE
13/7/2019
Aisha School ANCHOR BOLTS PLAN PROJECT NO:
IFA
S2-10
REVIEWED BY:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2
FOR RESULTS THAT MATTER. DRAWING TYPE: DATE:
SANA'A - YEMEN. Amran CITY-YEMEN STRUCTURAL DESIGN APPROVED BY:
UNOPS DESIGN REVIEW JULY /13/2019
A B
A B
350 2400 350
2 2
2 2
C (60x30x1.25)
C (60x30x1.25)
C 80x40x1.25
C 80x40x1.25
C (60x30x1.25)
C (60x30x1.25)
1 1 1 1
A
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
DESIGNED BY: A3 AS SHOWN OF ISSUE
13/7/2019
Aisha School 6PV MOUNTING IFA
PROJECT NO:
FULL PLAN
S2-11
REVIEWED BY:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2
FOR RESULTS THAT MATTER. DRAWING TYPE: DATE:
SANA'A - YEMEN. Amran CITY-YEMEN STRUCTURAL DESIGN APPROVED BY:
UNOPS DESIGN REVIEW JULY /13/2019
GALV (L) SECTION
GALV (C) SECTION
(40x40x3) mm
(60x30x1.25) mm
4 STAINLESS
2 STAINLESS STEEL BOLTS ∅6
STEEL BOLTS ∅6
420
50 860 DETAIL A
4 STAINLESS
420
420 STEEL BOLTS ∅8
860
420
2 JOINT - DETAIL A
STRUCTURE DETAILS
RSH 43 in DN,
1.5mm THICK C 80x40x1.25
DETAIL B
2 STAINLESS
SIDE SECTION A-A STEEL BOLTS ∅8
1 STRUCTURE DETAILS
3 JOINT - DETAIL B
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
DETAIL A
L25X1.25
BACK ELEVATION
1 STRUCTURE DETAILS
2 1
C 80x40x1.25
GALV (L25x1.25) 2 08mm
PL 3mm
L25x1.25
2 08mm
JOINT - DETAIL A 3 JOINT - DETAIL B
2 STRUCTURE DETAILS STRUCTURE DETAILS
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
APPROVED BY:
PROJECT NO:
IUS-OPS-ECS-AMR-003.2
DATE:
S2-13
SANA'A - YEMEN. STRUCTURAL DESIGN UNOPS DESIGN REVIEW JULY /13/2019
A 2
B 1
3D VIEW
1 STRUCTURE DETAILS
PREPARED BY: FUNED BY: PROJECT TITLE: DRAWING TITLE: T-DSGN-BY PAPER SIZE: SCALE: PURPOSE REV. DATE DRAWING NO:
S2-14
REVIEWED BY:
OPERATIONAL EXCELLENCE IUS-OPS-ECS-AMR-003.2
FOR RESULTS THAT MATTER. DRAWING TYPE: DATE:
SANA'A - YEMEN. Amran CITY-YEMEN STRUCTURAL DESIGN APPROVED BY:
UNOPS DESIGN REVIEW JULY /13/2019