8 Revised1 - Brgy. Panlautan
8 Revised1 - Brgy. Panlautan
Municipality of Siquijor
Barangay Panlautan
Source of Fund
Breakdown of Estimated Project Cost KALAHI-CIDSS Community Contribution BLGU MLGU Other Sources
Total Cost
Grant
Male Female Cash In-Kind Cash In-Kind Cash In-Kind
A. Direct Cost
Materials 1,840,250.00 1,840,250.00
Equipment 153,500.00 153,500.00
Labor
1) Skilled 15,000.00 - - 15,000.00
1) Unskilled 75,600.00 6,625.00 1,250.00 83,475.00
Sub-Total ( A ) 2,084,350.00 6,625.00 1,250.00 2,092,225.00
B. Indirect cost
Pre-Engineering 1,000.00 1,000.00
Pow Preparation 5,800.00 5,800.00
TA in Project Implementation 12,000.00 12,000.00
Project Supervision - 7,475.00 7,475.00
Project Billboard 12,000.00 12,000.00
Material Testing 10,000.00 10,000.00
Administrative/Operating Cost 18,115.00 18,115.00
Hand Tools/PPE 15,410.00 15,410.00
Treasurer's Bond - 5,253.75 5,253.75
Over Head Cost 10,500.00 10,500.00
Contractors Profit 166,748.00 166,748.00
Tax 145,904.50 145,904.50
Environmental Mitigating Measure 2,220.00 - 2,220.00
Filling Cabinet 10,000.00 10,000.00
Sub-Total (B) 390,897.50 12,728.75 18,800.00 422,426.25
Noted by :
587,400.00
693,100.00
208,435.00
145,904.50
39,403.75
-
1,399,125.00
52,530.16
818.59
-
Name of Poject: Concreting of 0.400 km Barangay Panlautan Access Road
Location: Barangay Panlautan, Siquijor, Siquijor
BILL OF QUANTITIES
ITEM
RATE PER
NO. No. of DAY/
ITEM DESCRIPTION QUANTITY UNIT Total COMMUNITY CON
Crew/ UNIT KALAHI-CIDSS
COST GRANT
MALE
L = 400.00 m
W1 = 5.00 m
W2 = 7.00 m
Th = 0.15 m
Page 4
ITEM
RATE PER
NO. No. of DAY/
ITEM DESCRIPTION QUANTITY UNIT Total COMMUNITY CON
Crew/ UNIT KALAHI-CIDSS
COST GRANT
B. Labor:
Mason 25.00 Day/s 2.00 300.00 15,000.00 15,000.00
Laborer 25.00 Day/s 12.00 265.00 79,500.00 72,000.00 6,250.00
Sub-Total 94,500.00 87,000.00 6,250.00
C. Equipment
Bagger Mixer 25.00 Day/s 1.00 950.00 23,750.00 23,750.00
Concrete Vibrator 25.00 Day/s 1.00 450.00 11,250.00 11,250.00
Sub-Total 35,000.00 35,000.00
Total for Portland Cement Concrete Pavement 1,744,750.00 1,737,250.00 6,250.00
Page 5
ITEM
RATE PER
NO. No. of DAY/
ITEM DESCRIPTION QUANTITY UNIT Total COMMUNITY CON
Crew/ UNIT KALAHI-CIDSS
COST GRANT
A. DIRECT COST
MATERIALS 1,840,250.00 1,840,250.00
EQUIPMENT 153,500.00 153,500.00
LABOR COST
SKILLED 15,000.00 15,000.00 -
UN-SKILLED 83,475.00 75,600.00 6,625.00
TOTAL DIRECT COST 2,092,225.00 2,084,350.00 6,625.00
B. INDIRECT COST
Pre-Engineering
Municipal Engineer 1.00 PD 1.00 1,000.00 1,000.00
Pow Preparation
Municipal Engineer 4.00 PD 1.00 1,000.00 4,000.00
Draftsman 4.00 PD 1.00 450.00 1,800.00
TA in Project Implementation
Municipal Engineer 12.00 PD 1.00 1,000.00 12,000.00
Project Supervision
Community Volunteers 30.00 PD 1.00 250.00 7,475.00
Project Billboard
4" X 8" Project Billboard 1.00 pc 1.00 12,000.00 12,000.00 12,000.00
Material Testing
Material Testing 1.00 lot 1.00 10,000.00 10,000.00 10,000.00
Administrative Operating Cost (see attached cost derivation)
TE for opening of BSPMC LBP Bank account of CV's 1.00 Is 1.00 1,360.00 1,360.00 1,360.00
TE for procurement transactions for CV's 1.00 Is 1.00 1,800.00 1,800.00 1,800.00
Project meetings 1.00 Is 1.00 1,680.00 1,680.00 1,680.00
MCT - Initiated meetings 1.00 Is 1.00 5,750.00 5,750.00 5,750.00
Treasurer's Payroll Processing 1.00 Is 1.00 1,840.00 1,840.00 1,840.00
Forms/Supplies and reproduction 1.00 Is 1.00 5,085.00 5,085.00 5,085.00
Notarial Fees and Permits 1.00 ls 1.00 600.00 600.00 600.00
PPE/HandTools
Hard Hat 14.00 pcs 1.00 450.00 6,300.00 6,300.00
Safety Rubber Boots 14.00 pcs 1.00 420.00 5,880.00 5,880.00
Rubber Gloves 14.00 pcs 1.00 50.00 700.00 700.00
Dust Mask 14.00 pcs 1.00 20.00 280.00 280.00
Shovel with Handle 5.00 pcs 1.00 450.00 2,250.00 2,250.00
Treasurer's Bond
Treasurer's Bond 1.00 ls 1.00 5,253.75 5,253.75
Over Head Cost
Over Head Cost 30.00 PD 1.00 350.00 10,500.00 10,500.00
Contractors Profit
Contractors Profit 1.00 ls 1.00 166,748.00 166,748.00 166,748.00
Tax
Tax 1.00 ls 1.00 145,904.50 145,904.50 145,904.50
Filling Cabinet
Filling Cabinet 1.00 lot 1.00 10,000.00 10,000.00 10,000.00
Environmental Mitigating Measure
10 - 2" x 2" Tarpuline Printing 40.00 sq.ft 1.00 30.00 1,200.00 1,200.00
Caution Tape 1.00 roll 1.00 1,020.00 1,020.00 1,020.00
TOTAL INDIRECT COST 422,426.25 390,897.50
C. Contingency 53,348.75 53,348.75
TOTAL CONSTRUCTION COST 2,568,000.00 2,528,596.25 6,625.00
Page 6
ITEM
RATE PER
NO. No. of DAY/
ITEM DESCRIPTION QUANTITY UNIT Total COMMUNITY CON
Crew/ UNIT KALAHI-CIDSS
COST GRANT
Page 7
COST SHARING
LGU
NITY CONTRIBUTION OTHERS
BRGY. MUN.
Page 8
COST SHARING
LGU
NITY CONTRIBUTION OTHERS
BRGY. MUN.
1,250.00
1,250.00
1,250.00
Page 9
COST SHARING
LGU
NITY CONTRIBUTION OTHERS
BRGY. MUN.
1,250.00
1,250.00
1,000.00
4,000.00
1,800.00
12,000.00
7,475.00
5,253.75
12,728.75 18,800.00
Page 10
COST SHARING
LGU
NITY CONTRIBUTION OTHERS
BRGY. MUN.
URSULA G. OCAO
BSPMC
Page 11
INDIRECT COST BREACKDOWN
INDIRECT COST
Pre-Engineering
Municipal Engineer 1.00 PD 1.00 1,000.00 1,000.00
Pow Preparation
Municipal Engineer 4.00 PD 1.00 1,000.00 4,000.00
Draftsman 4.00 PD 1.00 450.00 1,800.00
TA in Project Implementation
Municipal Engineer 12.00 PD 1.00 1,000.00 12,000.00
Project Supervision
Community Volunteers 30.00 PD 1.00 250.00 7,475.00
Project Billboard
4" X 8" Project Billboard 1.00 pc 1.00 12,000.00 12,000.00 12,000.00
Material Testing
Material Testing 1.00 lot 1.00 10,000.00 10,000.00 10,000.00
Administrative Operating Cost (see attached cost derivation)
TE for opening of BSPMC LBP Bank account of CV's 1.00 Is 1.00 1,360.00 1,360.00 1,360.00
TE for procurement transactions for CV's 1.00 Is 1.00 1,800.00 1,800.00 1,800.00
Project meetings 1.00 Is 1.00 1,680.00 1,680.00 1,680.00
MCT - Initiated meetings 1.00 Is 1.00 5,750.00 5,750.00 5,750.00
Treasurer's Payroll Processing 1.00 Is 1.00 1,840.00 1,840.00 1,840.00
Forms/Supplies and reproduction 1.00 Is 1.00 5,085.00 5,085.00 5,085.00
Notarial Fees and Permts 1.00 ls 1.00 600.00 600.00 600.00
PPE -
Hard Hat 14.00 pcs 1.00 450.00 6,300.00 6,300.00
Safety Rubber Boots 14.00 pcs 1.00 420.00 5,880.00 5,880.00
Rubber Gloves 14.00 pcs 1.00 50.00 700.00 700.00
Dust Mask 14.00 pcs 1.00 20.00 280.00 280.00
Shovel with Handle 5.00 pcs 1.00 450.00 2,250.00 2,250.00
Treasurer's Bond
Treasurer's Bond 1.00 ls 1.00 5,253.75 5,253.75
Over Head Cost
Over Head Cost 30.00 PD 1.00 350.00 10,500.00 10,500.00
Contractors Profit (10%)
Contractors Profit (10%) 1.00 ls 1.00 166,748.00 166,748.00 166,748.00
Tax (7%)
Tax (7%) 1.00 ls 1.00 145,904.50 145,904.50 145,904.50
Filling Cabinet
Filling Cabinet 1.00 pc 1.00 10,000.00 10,000.00 10,000.00
Environmental Mitigating Measure
10 - 2" x 2" Tarpuline Printing 40.00 sq.ft 1.00 30.00 1,200.00 1,200.00
Caution Tape 1.00 roll 1.00 1,020.00 1,020.00 1,020.00
TOTAL INDIRECT COST 422,426.25 390,897.50
Page 12
Page 13
1,000.00
4,000.00
1,800.00
12,000.00
7,475.00
5,253.75
12,728.75 18,800.00
ARCILY D. AGRAVANTE
Barangay Chairperson
URSULA G. OCAO
BSPMC
Page 14
ADMINISTRATIVE COST DERIVATION
Fare/
No of
Sub-project Activities Destination/Description Allowance Qty. Unit Amount
transactions
/Unit Price
Sub-Total 1,360.00
2. TE for procurement
transactions of CVs
BSPMC office to any point of
Serving of Canvass Siquijor Province (vice versa) 100.00 x 3 persons x 2 times = 600.00
meals 80.00 x 3 persons x 2 times = 480.00
BSPMC office to any point of
Serving of PO & Payments Siquijor Province (vice versa)
100.00 x 2 persons x 2 times = 400.00
meals 80.00 x 2 persons x 2 times = 320.00
Sub-Total 1,800.00
3. Project Meetings
Supplies 50.00 x 8 meetings = 400.00
Snacks 20.00 x 8 persons x 8 times = 1,280.00
Sub-Total 1,680.00
4. MCT-Initiated Meetings
BSPMC office to MCT Office
(vice versa)
150.00 x 5 persons x 5 times = 3,750.00
Meals 80.00 x 5 persons x 5 times = 2,000.00
Sub-Total 5,750.00
5. Treasurer Payroll/Bill
Payment Processing
BSPMC office to any point of
Siquijor Province (vice versa)
150.00 x 1 persons x 8 times = 1,200.00
Meals 80.00 x 1 persons x 8 times = 640.00
Sub-Total 1,840.00
6. Forms/Supplies and
Reproduction
Bondpaper long 300.00 x 2 reams = 600.00
Ballpens 5.00 x 5 pcs = 25.00
Reproduction 2.00 x 1000 sheets = 2,000.00
Petty cash box w/ padlock 800.00 x 1 set = 800.00
Rubber Stamp 50.00 x 1 pc = 50.00
Stampad 50.00 x 1 pc = 50.00
Stamping Ink 50.00 x 1 pc = 50.00
Stapler 100.00 x 1 pc = 100.00
Stapler Remover 15.00 x 1 pc = 15.00
Staple Wire 30.00 x 4 boxes = 120.00
Calculator 400.00 x 1 pc = 400.00
Columnar Book 50.00 x 4 pcs = 200.00
Liquid Eraser 35.00 x 1 ps = 35.00
Paste/Glue 20.00 x 1 pc = 20.00
Folder long 5.00 x 40 pcs = 200.00
Paper clip 20.00 x 1 box = 20.00
Pentil pen 30.00 x 1 pc = 30.00
Log book 80.00 x 4 pcs = 320.00
Fastener 50.00 x 1 box = 50.00
Sub-Total 5,085.00
7. Notarial Fees and Permits
Sub-project Aggreement 300.00 x 1 lot x 1 times = 300.00
Resolution to open Account 300.00 x 1 lot x 1 times = 300.00
Sub-Total 600.00
TOTAL FOR ADMIN COST 18,115.00
Concurred by:
Checked and Reviewed by:
URSULA G. OCAO
ENGR. HALDOR JAY A. DATOY BSPMC
ACT TF
W5 W6 W7 W8 W9
3.60
`
75,397.50
13.90 13.90 13.90 13.90
Date Prepared : Name of proposed community project: Concreting of 0.400 km Barangay Panlautan Access Road
Barangay : Panlautan
Municipality : Siquijor Total Estimated Cost: 2,568,000.00
Province : Siquijor Community Project Duration: 45 CALENDAR DAYS
LCC In-Kind: 39,403.75
Estimated Cost: 1st Tranche: 31,523.00 `
2nd Tranche: 3,415.00
3rd Tranche: 3,415.00
Mode of Implementation By Contract
QUANTITY
REMARKS
RATE PER DAY/
Procurement
ITEM DESCRIPTION UNIT Total 3rd
UNIT COST Method 1st TRANCHE 2nd Tranche MONTHS
TRANCHE TOTAL
In Kind In Kind In Kind 1 2 3
DIRECT COST
1) Skilled - - - - -
2) Unskilled 1.00 lot 7,875.00 7,875.00 6,300.00 787.50 787.50 7,875.00
TOTAL DIRECT COST 6,300.00 787.50 787.50 7,875.00
INDIRECT COST
Pre-Engineering 1.00 PD 1,000.00 1,000.00 800.00 100.00 100.00 1,000.00
Pow Preparation 1.00 PD 5,800.00 5,800.00 4,640.00 580.00 580.00 5,800.00
TA in Project Implementation 1.00 PD 12,000.00 12,000.00 9,600.00 1,200.00 1,200.00 12,000.00
Project Supervision 30.00 days 250.00 7,475.00 5,980.00 747.50 747.50 7,475.00
Project Billboard 1.00 lot - - -
Material Testing 1.00 lot - - -
Administrative/Operating Cost 1.00 lot - - -
Hand Tools/PPE 1.00 lot - - -
Treasurer's Bond 1.00 ls 5,253.75 5,253.75 4,203.00 525.38 525.38 5,253.75
Over Head Cost 60.00 days
Contractors Profit 1.00 ls
Tax 1.00 ls
Environmental Mitigating Measure
1.00 lot
Filling Cabinet 1.00 lot
TOTAL INDIRECT COST 25,223.00 2,627.50 2,627.50 31,528.75
GRAND TOTAL 31,523.00 3,415.00 3,415.00 39,403.75
MICHELLE SUMALPONG ENGR. HALDOR JAY A. DATOY ARCILY D. AGRAVANTE ENGR. ERIZA R.EMADIN
BAC Secretary MCT-TF Barangay Chairperson CPO