UPS Battery Testing
UPS Battery Testing
Sometimes it seems hard to justify spending extra time and money troubleshooting your new
battery plant before testing (“Hey, won’t the load test itself will reveal any problems?”). Any
number of “real-world” factors can pressure you to cut corners in order to recover lost time:
• Batteries are long-lead items, and were among the last major components delivered to
the site.
• Contractor delays kept you from finishing the battery installation until just yesterday.
• The UPS and switchgear are already in place and have passed preliminary functional
testing.
• The IS manager is anxious to get conditioned power to his new data center.
• The project is already behind schedule and all the vendors want to get paid.
The pressures may be severe, but stand firm in your commitment to pre-testing and inspection.
Your new room full of batteries is a complex electrochemical system with hundreds of jars and
interconnects mounted on custom-assembled racks. Anything can go wrong. On a more positive
note, proper inspection and testing will give you useful information that can be applied
immediately and which will serve as a baseline for testing throughout the service life of the
batteries.
• Interconnection integrity
• State of charge
If basic information is not collected, analyzed and understood before initial charging and dynamic
testing, the results are unpredictable. There is a very real possibility that the battery could suffer
damage if a major problem is not diagnosed in advance. Some possible consequences are:
A properly performed certification inspection, therefore, is very important, whether or not the
specification requires it.
Battery system installation certification inspections can be performed by the installing contractor,
by a third-party battery service provider or by the battery manufacturer’s authorized
representatives. The completed inspection report should be available to those responsible for the
battery and thoroughly reviewed. Any necessary corrective action as a result of the inspection
should be carried out before the battery receives its initial charge.
• Mechanical inspection
Mechanical Inspection
These steps should be carried out prior to initial charging.
1. Check all rack hardware for tightness. This is best accomplished before racks are loaded
with cells. Missing hardware should be replaced before racks are loaded. Never loosen
hardware on a loaded rack -- it may collapse.
2. Inspect the battery for general cleanliness. The battery should be free of spilled
electrolyte, construction debris, heavy dirt and excessive dust. Heavily soiled battery
systems should be cleaned before being placed in service.
3. Inspect the rack rails and jar undersides for chemical residue. The author has observed
increasing numbers of installing contractors using various compounds to lubricate the
tops of the rails. This practice makes it easier to slide jars along the rails. Unfortunately,
not all compounds react benignly with jar materials. Most oil-based products -- even
those as mild as cooking spray -- react with jar materials. In one well-publicized case, a
contractor used cable-pulling grease on the frame rails; within weeks, virtually all the jars
were leaking. The first sign of such a reaction is the cracking and crazing of the plastic jar
material. Generally, once a reaction is observed, the cell must be replaced. To avoid this
situation, installers must be familiar with the battery makers’ recommendations and use
only compounds approved or recommended by them. To be on the safe side, many
manufacturers recommend using plain water; it provides some amount of lubrication and
evaporates afterward without leaving an oily residue.
4. All jars and covers should be examined for cracks and leaks. Leaking cells should be
replaced at the earliest possible time. Leaking cells quickly contaminate racks. This can
cause ground fault alarms to trip and present a safety hazard to service personnel.
5. All flame arrestors should be intact and installed securely. Batteries should never be
charged unless all flame arrestors are properly installed. VRLA battery pressure relief
valves should be in place and secure as well. The perimeter of the vent well and flame
arrestor seal ring should be clean and dry before flame arrestors are installed. This will
prevent electrolyte migration from inside the cell to outside the gasket area.
6. Check all inter-tier, inter-rack and inter-aisle connecting cables for excessive stress on
terminals, as evidenced by twisting and “leaning” of posts and terminals. Cable must not
cause stress to these components. Corrective action is necessary when stress is
observed.
1. Verify that all cells are arranged in the proper series connection. A common installation
error is interconnecting cells with like polarities.
2. Check all bolted interconnections for tightness to the proper value per manufacturer
specifications. Errors we have observed include; (a) an incorrect torque setting and (b) a
wrench graduated in foot pounds instead of the more common inch-pounds unit
ofmeasure.
4. After a resistance benchmark has been established, measure and record all
interconnection resistances. Reference the readings to the benchmark standards and
make note of any connections requiring corrective action based on the acceptance
criteria from line 3 above.
5. Measure and record total battery voltage at the open circuit potential. Divide that reading
by number of cells in the string. The resulting per-cell value should be close to the
calculated open circuit voltage. Refer to Table 1 in Appendix A.
If the tasks above have been completed and meet the acceptance criteria, initial charging of the
battery may then begin. Items that do not conform to the battery manufacturer or IEEE standards
must be noted on the inspection report and corrected. Corrective action should be taken as soon
as practical. The amount of time a battery requires to reach a fully charged state for testing is a
function of several conditions:
• Ambient temperature
Electro-Chemical Pre-Testing
In Pre-Test, the following tasks should always be completed prior to load testing the battery
system:
1. Before load tests can take place, the battery must be fully charged. and the state of
charge must verified. This cannot be overemphasized. Generally, a battery is considered
to be fully charged when the voltage of lowest cell in the string stops rising over three
consecutive hourly readings while on equalize charge and the lowest specific gravity
measurement is within the nominal rating by a window of +/- 10 (.010) gravity points. This
can be used as a guideline during charging. Refer to the battery manufacturer’s specific
instructions for more detail.
2. Find the lowest cell and verify the state of charge as described above. If the cell voltage
continues to rise with the next hourly reading, continue the equalize charge until it stops
rising. When that cell voltage stops rising, the battery should then be returned to normal
float status. Monitor cell temperature while on charge. Do not exceed the maximum
allowable temperature or cells may be damaged.
3. IEEE 450-1995 states a battery should receive an equalize charge and be returned to
normal float potential for no less than 3 days, but not longer than 30 days prior to testing.
This three-day period will allow time for all the hydrogen gas bubbles (formed on the
plates during equalize charging) to be released from the surface of the plates. Until all the
bubbles are released, the full surface area of the plates is not available for chemical
interaction with the electrolyte, and the battery could appear to have diminished capacity.
4. When Items 2 and 3 are satisfied, measure and record the specific gravity of each cell in
the battery just prior to the load test. If the gravity readings are within the manufacturer’s
recommended window, (usually +/- 10 points), they are considered acceptable. For
specific details regarding allowable gravity values, refer to the battery manufacturer
installation and operating instructions.
5. Measure and record the electrolyte temperature of every sixth cell, with not less than
10% of the total number of cells in the battery. Battery performance data is referenced to
77 degrees, F. (25 C). Cooler temperatures will cause diminished battery capacity.
Higher temperatures will cause increased capacity, but reduce service life. Temperature
considerations are a frequently neglected factor in the load testing equation.
Correction factors are listed in Table 2 in Appendix A. To illustrate their use, let’s take a sample
UPS system rated at 750 kVA and 600 kW (Rated kW), and assume the cell electrolyte
temperature was measured at 67°F. Table 2 shows a temperature correction factor (Tc) of 1.064.
Load bank setting (AC kW) can be expressed by the formula:
AC kW = (Rated kW)/Tc
AC kW = (600 kW)/1.064
AC kW = 564 kW
The original 77 degree AC KW would have been 600 KW. The corrected load bank setting
indicates a difference of 36 KW (6% of rated capacity). Had the battery been tested at the full 600
kW load, the battery would have provided less than rated backup time.
Summary
It’s critical to ensure battery system integrity before it is load tested. It must be fully charged,
properly installed and its condition verified in order to minimize the likelihood of retests and
equipment damage. When compared with downtime cost, delays, retests and hardware failures,
the cost of battery certification is a bargain, well worth the expense and time added to a project.
About Liebert
Liebert, an Emerson Network Power company, is the world leader in mission-critical power and
cooling technology. Liebert delivers unparalleled protection of critical systems through an
adaptive platform of power cooling and monitoring technologies that deliver high availability and
low cost of ownership. Liebert solutions are tailored to application requirements by a network of
local representatives that average better than 16 years of experience in the industry. Liebert
Global Services is the world`s largest service team dedicated to the maintenance and on-site
repair of critical computer support systems. For more information on Liebert, visit
www.liebert.com.