CEP#a Maintenance Report
CEP#a Maintenance Report
Table of Contents
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 2 of 16
Background
On 26th November, CEP#A encountered motor high vibration (DE > 4 mm/s) as well as the sibilating
sound raised from pump bearing housing. In addition, during pump lift check it’s been observed that
the shaft is not lifted enough. Inducer got stuck with suction bell inner periphery.
Total running hours recorded 12738 where it is common that overhaul interval period is subject to
16000 working hours. It must take into account the physical state (vibration, noise, stress), pump
switching frequency, equipment failure, demand availability and so on. Abnormal working condition
requirements the immediate pump corrective maintenance to prevent mechanical withstand of
undesirable vibration, noise and stress.
Scope of Work
It has been decided that MMD will overhaul the pump and scope of the work to be followed-
Disintegrate the pump sequentially Find out actual problem & resolution
Check the accuracy of the dismantled parts Do correct leveling & alignment (if needed)
Check wearing parts & data recording Minimize pump vibration & noise as well
Spare to be used if any rejection occurred Carry out test run & Consequence Analysis
Technical Specification
Suction
Type 16NLT-215 - 0.60 Bar Product Index 427-H75N/100-E2
Press.
Carbon Graphite
Speed 1480 rpm pH Level 8.8 - 9.3 Face Material Antimony Impregnated
NPSHr & Head 3.5 m & 176 m Conductivity < 10 μS/cm Seat Material Silicon Carbide
Coupling Bearing
Power 412 KW
(Shanghai Apollo) (SKF)
Flexible /
Weight 6000 KG C#1, Type Identity 7326 BCBM
Rubber Bush
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 3 of 16
Preparation of Work
It’s a massive task, so prepared pump overhaul plan to conduct one by one in accordance. Hence some
following preparation needed to be executed.
Work Permit :
Issued work permit no. PTW20201201001 and date of initiation 1st December, 2020.
Warehouse Stock :
Checked warehouse availability for consumable items and pump spares if there any possibility of
replacing. PR generated against deficiency of required items.
Lifting Gear :
Functional load test of lifting hoist has been carried out earlier. All lifting gears i.e. slings, shackles,
chain blocks are inspected by the certified company. Necessary items shifted to the workplace.
Material & Tool Management :
Arranged all kinds of essential hand tools, power tools and measuring tools along with an organizer.
Several ply boards and wood padding blocks have been set in the workplace to keep small, loose &
bulky items as well as disintegrated parts.
Resource Utilization
A maintenance requires a lot to be performed. In this regard, various hand tools, power tools, precision
tools, marking tools, consumable items, non-consumable items, borrowed items, documents, manuals
and so on have been used and it is not logical to include all names & history. Some important items are
categorized shortly as following tables -
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 4 of 16
Consumable Item
1 Silicon Grease & Sealant Anabond 662, Threebond 1212 Tube 1 Each
2 Rag Cotton, White Color KG 10
3 Rust Remover & Molykote WD40 & 1000 Paste Can 5&1
4 Emery Paper (Grit) Diff. Size Pcs 16
5 Cup Brush, Cutting / Grinding Disc 4 Inch Pcs 2 Each
6 Masking Tape & Caution Tape 2 Inch & 3 Inch Reel 1 Each
7 Lube Oil L-TSA 46 / ISO VG 46 Liters 10
8 LP Gas 12.5 Kg Cylinder 1
Planning, drafting and vendor recommendations has followed to the document titled Condensate
Pump, document no. SP311-OM-ST-04-0015 and Sectional Drawing refer 16NLT-215-000 (Apollo).
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 5 of 16
Maintenance Activities
Pump Disassembling
All electrical power connections have been disconnected and instruments have been taken out by I&C.
Before decoupling all data have been recorded. Removed all auxiliaries such as motor cooling water
line, seal & bearing cooling water line, flushing water line, suction & delivery flange as well.
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 6 of 16
Loosened impeller nut M22x1.5, dismantled first stage impeller and first stage impeller locating shaft
sleeve in sequence. According to the sequence of guide vane shell, secondary impeller, inter-stage shaft
sleeve, guide vane shell to step by step. Dismantled the second stage to the fifth stage in sequence and
lifted all the parts by using ST crane. Parts kept according to serial no to prevent interchanging (ref.
photo#16). In the process of dismantling, added wood padding block under the rotor and the stationary
part and kept relatively parallel to avoid components abrading of pump shaft (ref. photo#18).
Actually pump inducer and two shafts were targeted to do DPT as they encountered & raised some
abnormalities while lifting. DPT has been done and maintained with basic procedure which has given
below –
Finally There were no severe mark or finding during penetration test. (ref. photo#10 & #11).
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 7 of 16
Recommended clearance between shaft sleeve & sliding bearing is considered not more than 0.3 mm
and unilateral gap of impeller & pump casing ring is 0.5 mm. Physical measurements are following –
Suction Side Wear Ring ID Impeller Suction Side Impeller Eye OD Clearance
Guide Vane Shell # 1 251.05 mm Impeller # 1st Stage 250.67 mm 0.38 mm
Guide Vane Shell # 2 251.03 mm Impeller # 2nd Stage 250.65 mm 0.38 mm
Guide Vane Shell # 3 251.02 mm Impeller # 3rd Stage 250.65 mm 0.37 mm
Guide Vane Shell # 4 251.01 mm Impeller # 4th Stage 250.67 mm 0.34 mm
Guide Vane Shell # 5 251.02 mm Impeller # 5th Stage 250.66 mm 0.36 mm
Delivery Side Wear Ring ID Impeller Delivery Side Impeller Eye OD Clearance
Guide Vane Shell # 1 251.01 mm Impeller # 1st Stage 250.68 mm 0.33 mm
Guide Vane Shell # 2 251.01 mm Impeller # 2nd Stage 250.66 mm 0.35 mm
Guide Vane Shell # 3 251.08 mm Impeller # 3rd Stage 250.66 mm 0.42 mm
Guide Vane Shell # 4 251.00 mm Impeller # 4th Stage 250.66 mm 0.34 mm
Guide Vane Shell # 5 251.04 mm Impeller # 5th Stage 250.69 mm 0.35 mm
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 8 of 16
Shaft Run-out
Radial run-out involves distance inaccuracy from one point to another which will cause vibration. It
has been checked by dial indicator into some points by putting the shaft onto fabricated blocks.
Point A B C D
Top Shaft 0.04 0.01 0.01 0.02
Rotation Anti-clockwise Bottom Shaft 0.02 0.03 0.01 0.01
All dismantled parts have been cleaned properly. Rusty mating surface, ‘O’ ring groove cleaned by
power brush. Plain surfaces with light dirt cleaned by emery papers (320 grit), WD40 and rags. Bolts &
nuts were cleaned by using wire brushes.
Bearing housing and cooling chamber cleaned by pollen free rags. Finally service air blown away into
all the parts to prevent adhesion and decontamination in any precise parts.
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 9 of 16
Pump parts are checked thoroughly. The following table summarizes the state of each part –
According to the top table, some parts needed to be replaced. The following table represents details –
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 10 of 16
Pump Assembling
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 11 of 16
Pictorial
Photo#4: Stuck Inducer Photo#5: Damaged Rubber Bush Photo#6: Discarded Bearing Shim
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 12 of 16
Photo#7: Bearing Removal Tool Photo#8: Inducer Removal Tool Photo#9: Honing Operation
Photo#12: M.Seal Parting Photo#13: Inside Bearing Housing Photo#14: Safe Work Practice
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 13 of 16
Photo#15: Retainer / Spider Photo#16: Impeller & Guide Vane Photo#17: Coupling & Clasp
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 14 of 16
0.0 N 0.0 N
E E
W W
S + 0.03 S + 0.05
Alignment carried out by following rim & face method. Above figure representing final alignment data
and during alignment no shim is inserted. Measured the distance between the pump and the motor
coupling hub is 8.03 mm.
Before testing motor heater was kept on for dehumidifying. In 08.12.2020, Under SFT motor solo test
has been performed. It was running around 30 minutes and vibrations were recorded as below -
NDE DE
Before
Maintenance
Axial Horizontal Vertical Axial Horizontal Vertical
NDE DE
After
Maintenance
Axial Horizontal Vertical Axial Horizontal Vertical
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 15 of 16
During pump rolling, bearing & mechanical seal cooling water and flushing water was adjusted
according to the vendor recommendations. All operational & electrical parameters were within limits.
The pump noise level & vibration found normal and much less than before. Performance kept
monitoring while running, data has recorded by ACOEM OneProd Analyser. Overall vibration data &
velocity comparison chart is following –
Velocity (mm/s) 4.24 2.92 1.62 4.42 1.19 1.35 2.08 1.42 1.33
Acceleration (g) 1.54 1.28 1.27 2.75 0.868 0.799 1.58 1.51 1.44
Velocity (mm/s) 1.08 1.5 1.17 0.91 0.712 0.41 0.434 0.837 0.386
Acceleration (g) 0.2 0.144 0.128 0.703 0.259 0.289 0.153 0.11 0.115
4.5
4
3.5
3
2.5
2
1.5
1
0.5
0
Axial
Axial
Axial
Vertical
Vertical
Vertical
Horizontal
Horizontal
Horizontal
Go to Top
Summit Meghnaghat Power Company Limited
Condenser Extraction Pump # A Maintenance Report
1st Dec. to 8th Dec. 2020 Page 16 of 16
While maintenance, its been observed some difficulties to perform the work such as heating, jacking,
shaft leveling/straightening and so on. Some recommendations are given below-
Conclusion
Overhauling activities done successfully with no harms, no human injuries and no interruptions.
Involved persons have given their best efforts, sincerities and having good leadership. As a result
earlier vibration, noise and some operational issues are resolved technically.
The above report has briefly discussed on the various aspects of maintenance activities. The downtime
cost for such equipment overhauling or maintenance is expected to be very high. To meet these
challenges, it had to use plant available resources and maintenance skills in all spheres of activities to
perform its effective role in the profitability of the company.
The entire reel of work brought to pass successfully. However, the situation faced some difficulties
which need to be resolved. As a part of this it is desired that above mentioned items really needed in
the next overhauling. Therefore, annual planning & budgeting section should include the right
information about the advised special item. If it can be done, hopefully it will save a lot of time and
cost as well in any major maintenance in particular rotating equipments.
-------------------------------------
Go to Top