Protection Automation Application Guide v1 - Compressed (301 400)
Protection Automation Application Guide v1 - Compressed (301 400)
IS2 I1 + I 2
I bias =
2
(b) Biased differential operating characteristic
Figure 17.5: Typical generator biased differential protection
17-4
Chapter 17 ⋅ Generator and Generator Transformer Protection
17-5
Protection & Automation Application Guide
17.6 DIFFERENTIAL PROTECTION OF usually applied to balance the generator differential protection
GENERATOR-TRANSFORMERS and prevent the unit transformer through current being seen
as differential current. An exception might be where the unit
A common connection arrangement for large generators is to
transformer rating is extremely low in relation to the generator
operate the generator and associated step-up transformer as a
rating, e.g. for some hydro applications. The location of the
unit without any intervening circuit breaker. The unit
third set of current transformers is normally on the primary
transformer supplying the generator auxiliaries is tapped off
side of the unit transformer. If located on secondary side of
the connection between generator and step-up transformer.
the unit transformer, they would have to be of an exceptionally
Differential protection can be arranged as follows.
high ratio, or exceptionally high ratio interposing CTs would
have to be used. Thus, the use of secondary side CTs is not to
17.6.1 Generator/Step-up Transformer Differential
be recommended. One advantage is that Unit Transformer
Protection faults would be within the zone of protection of the generator.
The generator stator and step-up transformer can be protected However, the sensitivity of the generator protection to unit
by a single zone of overall differential protection (Figure 17.8). transformer phase faults would be considered inadequate, due
This will be in addition to differential protection applied to the to the relatively low rating of the transformer in relation to that
generator only. The current transformers should be located in of the generator. Thus, the unit transformer should have its
the generator neutral connections and in the transformer HV own differential protection scheme. Protection for the Unit
connections. Alternatively, CTs within the HV switchyard may Transformer is covered in Chapter 16, including methods for
be employed if the distance is not technically prohibitive. Even stabilising the protection against magnetising inrush
where there is a generator circuit breaker, overall differential conditions.
protection can still be provided if desired.
Generator Main transformer 17.7 OVERCURRENT PROTECTION
17-6
Chapter 17 ⋅ Generator and Generator Transformer Protection
performance of the excitation system and its field-forcing are discussed in the following sections. The choice depends
capability. Without the provision of fault current compounding upon the power system characteristics and level of protection
from generator CTs, an excitation system that is powered from to be provided. Voltage-dependent overcurrent relays are
an excitation transformer at the generator terminals will often found applied to generators used on industrial systems,
exhibit a pronounced fault current decrement for a terminal as an alternative to full differential protection.
fault. With failure to consider this effect, the potential exists
for the initial high fault current to decay to a value below the 17.7.2.1 Voltage Controlled Overcurrent Protection
overcurrent protection pick-up setting before a relay element Voltage controlled overcurrent protection has two time/current
can operate, unless a low current setting and/or time setting is characteristics which are selected according to the status of a
applied. The protection would then fail to trip the generator. generator terminal voltage measuring element. The voltage
The settings chosen must be the best compromise between threshold setting for the switching element is chosen
assured operation in the foregoing circumstances and according to the following criteria.
discrimination with the system protection and passage of
normal load current, but this can be impossible with plain • during overloads, when the system voltage is sustained
overcurrent protection. near normal, the overcurrent protection should have a
current setting above full load current and an operating
In the more usual case of a generator that operates in parallel time characteristic that will prevent the generating
with others and which forms part of an extensive plant from passing current to a remote external fault for
interconnected system, back-up phase fault protection for a a period in excess of the plant short-time withstand
generator and its transformer will be provided by HV limits
overcurrent protection. This will respond to the higher-level
• under close-up fault conditions, the busbar voltage
backfeed from the power system to a unit fault. Other
must fall below the voltage threshold so that the second
generators in parallel would supply this current and, being
protection characteristic will be selected. This
stabilised by the system impedance, it will not suffer a major
characteristic should be set to allow relay operation
decrement. This protection is usually a requirement of the
with fault current decrement for a close-up fault at the
power system operator. Settings must be chosen to prevent
generator terminals or at the HV busbars. The
operation for external faults fed by the generator. It is
protection should also time-grade with external circuit
common for the HV overcurrent protection relay to provide
protection. There may be additional infeeds to an
both time-delayed and instantaneous high-set elements. The
external circuit fault that will assist with grading
time-delayed elements should be set to ensure that the
protected items of plant cannot pass levels of through fault Typical characteristics are shown in Figure 17.9.
current in excess of their short-time withstand limits. The
Current
instantaneous elements should be set above the maximum
pick-up
possible fault current that the generator can supply, but less level
than the system-supplied fault current in the event of a
generator winding fault. This back-up protection will minimise
plant damage in the event of main protection failure for a I>
generating plant fault and instantaneous tripping for an HV-
side fault will aid the recovery of the power system and parallel
generation. KI>
17-7
Protection & Automation Application Guide
17-8
Chapter 17 ⋅ Generator and Generator Transformer Protection
Open ∼
Re Re
2
* Optional interlocked
Vph-n earth-fault protection
Minimum earth fault level = IF = if grading problems exist
Re
3 1
Figure 17.11: Comprehensive earth-fault protection scheme for direct-
connected generators operating in parallel Va
Vb
For cases (b) and (c) above, it is not necessary to use a Vc
directional facility. Care must be taken to use the correct RCA Vn
setting – for instance if the earthing impedance is mainly 1 Derived from phase neutral voltages
resistive, this should be 0o. On insulated or very high 2 Measured from earth impedance
impedance earthed systems, an RCA of –90o would be used, 3 Measured from broken delta VT
as the earth fault current is predominately capacitive. Figure 17.12: Neutral voltage displacement protection
Directional sensitive earth-fault protection can also be used for
detecting winding earth faults. In this case, the relay element
17.8.2 Indirectly-Connected Generators
is applied to the terminals of the generator and is set to As noted in Section 17.2, a directly-earthed generator-
respond to faults only within the machine windings. Hence transformer unit cannot interchange zero-sequence current
earth faults on the external system do not result in relay with the remainder of the network, and hence an earth fault
operation. However, current flowing from the system into a protection grading problem does not exist. The following
winding earth-fault causes relay operation. It will not operate sections detail the protection methods for the various forms of
on the earthed machine, so that other types of earth-fault impedance earthing of generators.
protection must also be applied. All generators must be so
fitted, since any can be operated as the earthed machine. 17.8.2.1 High Resistance Earthing – Neutral Overcurrent
Protection
17.8.1.3 Neutral Voltage Displacement Protection A current transformer mounted on the neutral-earth conductor
In a balanced network, the addition of the three phase-earth can drive an instantaneous and/or time delayed overcurrent
voltages produces a nominally zero residual voltage, since relay element, as shown in Figure 17.13. It is impossible to
there would be little zero sequence voltage present. Any earth provide protection for the whole of the winding, and Figure
fault will set up a zero sequence system voltage, which will 17.13 also details how the percentage of winding covered can
give rise to a non-zero residual voltage. This can be measured be calculated. For a relay element with an instantaneous
by a suitable relay element. The voltage signal must be derived setting, protection is typically limited to 90% of the winding.
from a VT that is suitable – i.e. it must be capable of This is to ensure that the protection will not maloperate with
transforming zero-sequence voltage, so 3-limb types and those zero sequence current during operation of a primary fuse for a
without a primary earth connection are not suitable. This VT earth fault or with any transient surge currents that could
unbalance voltage provides a means of detecting earth faults. flow through the interwinding capacitance of the step-up
17-9
Protection & Automation Application Guide
a
If Loading
V>
Is resistor
aV
R If =
R
IsR
a min = (b) Protection using a voltage element
V
% covered = (1 − a min) × 100% Figure 17.14: Generator winding earth-fault protection - distribution
transformer earthing
Figure 17.13: Earth fault protection of high-resistance earthed As discussed in Section 17.8.2.1, the protection should be time
generator stator winding using a current element delayed when a sensitive setting is applied, in order to prevent
maloperation under transient conditions. It also must grade
17.8.2.2 Distribution Transformer Earthing Using a with generator VT primary protection (for a VT primary earth
Current Element fault). An operation time in the range 0.5s-3s is usual. Less
In this arrangement, shown in Figure 17.14(a), the generator sensitive instantaneous protection can also be applied to
is earthed via the primary winding of a distribution provide fast tripping for a heavier earth fault condition.
transformer. The secondary winding is fitted with a loading
resistor to limit the earth fault current. An overcurrent relay 17.8.2.3 Distribution Transformer Earthing Using a
element energised from a current transformer connected in the Voltage Element
resistor circuit is used to measure secondary earth fault Earth fault protection can also be provided using a voltage-
current. The relay should have an effective setting equivalent measuring element in the secondary circuit instead. The
to 5% of the maximum earth fault current at rated generator setting considerations would be similar to those for the current
voltage, in order to protect 95% of the stator winding. The operated protection, but transposed to voltage. The circuit
relay element response to third harmonic current should be diagram is shown in Figure 17.14(b).
limited to prevent incorrect operation when a sensitive setting
is applied. Application of both voltage and current operated elements to a
generator with distribution transformer earthing provides some
advantages. The current operated function will continue to
operate in the event of a short-circuited loading resistor and
the voltage protection still functions in the event of an open-
circuited resistor. However, neither scheme will operate in the
event of a flashover on the primary terminals of the
transformer or of the neutral cable between the generator and
17-10
Chapter 17 ⋅ Generator and Generator Transformer Protection
the transformer during an earth fault. A CT could be added in The initial bias slope is commonly set to 0% to provide
the neutral connection close to the generator, to energise a maximum sensitivity, and applied up to the rated current of
high-set overcurrent element to detect such a fault, but the the generator. It may be increased to counter the effects of CT
fault current would probably be high enough to operate the mismatch. The bias slope above generator rated current is
phase differential protection. typically set to 150% of rated value. The initial current setting
is typically 5% of the minimum earth fault current for a fault at
17.8.2.4 Neutral Voltage Displacement Protection the machine terminals.
This can be applied in the same manner as for direct-
connected generators (Section 17.8.1.3). The only difference 17.8.3.2 High Impedance REF Protection
is that the are no grading problems as the protection is The principle of high impedance differential protection is given
inherently restricted. A sensitive setting can therefore be used, in Chapter 10 and also described further in Section 17.5.2.
enabling cover of up to 95% of the stator winding to be The same technique can be used for earth-fault protection of a
achieved. generator, using three residually connected phase CTs
balanced against a similar single CT in the neutral connection.
17.8.3 Restricted Earth Fault Protection Settings of the order of 5% of maximum earth fault current at
This technique can be used on small generators not fitted with the generator terminals are typical. The usual requirements in
differential protection to provide fast acting earth fault respect of stabilising resistor and non-linear resistor to guard
protection within a defined zone that encompasses the against excessive voltage across the relay must be taken,
generator. It is cheaper than full differential protection but where necessary.
only provides protection against earth faults. The principle is
that used for transformer REF protection, as detailed in 17.8.4 Earth Fault Protection for the Entire Stator
Section 16.7. However, in contrast to transformer REF Winding
protection, both biased low-impedance and high-impedance All of the methods for earth fault protection detailed so far
techniques can be used. leave part of the winding unprotected. In most cases, this is of
no consequence as the probability of a fault occurring in the 5%
17.8.3.1 Low-Impedance Biased REF Protection of the winding nearest the neutral connection is very low, due
This is shown in Figure 17.15. The main advantage is that the to the reduced phase to earth voltage. However, a fault can
neutral CT can also be used in a modern relay to provide occur anywhere along the stator windings in the event of
conventional earth-fault protection and no external resistors insulation failure due to localised heating from a core fault. In
are used. Relay bias is required, as described in Section cases where protection for the entire winding is required,
10.4.2, but the formula for calculating the bias is slightly perhaps for alarm only, there are various methods available.
different and also shown in Figure 17.15.
17.8.4.1 Measurement of Third Harmonic Voltage
Phase CT ratio 1000/1
One method is to measure the internally generated third
∼
Phase A
Phase B
Phase C
harmonic voltage that appears across the earthing impedance
due to the flow of third harmonic currents through the shunt
Neutral CT ratio capacitance of the stator windings etc. When a fault occurs in
200/1
the part of the stator winding nearest the neutral end, the third
harmonic voltage drops to near zero, and hence a relay
element that responds to third harmonic voltage can be used
IA to detect the condition. As the fault location moves
IB progressively away from the neutral end, the drop in third
IC
harmonic voltage from healthy conditions becomes less, so
IN that at around 20-30% of the winding distance, it no longer
becomes possible to discriminate between a healthy and a
I BIAS =
(highest of I A , I B , I C ) + (IN × scaling factor ) faulty winding. Hence, a conventional earth-fault scheme
2
neutral CTratio 200
should be used in conjunction with a third harmonic scheme,
where scaling factor = = = 0.2
phase CTratio 1000 to provide overlapping cover of the entire stator winding. The
IDIFF = I A + I B + I C + ( scaling factor × IN ) measurement of third harmonic voltage can be taken either
Figure 17.15: Low impedance biased REF protection of a generator from a star-point VT or the generator line VT. In the latter
17-11
Protection & Automation Application Guide
case, the VT must be capable of carrying residual flux, and this may cause a sudden rise in terminal voltage due to the
prevents the use of 3-limb types. If the third harmonic voltage trapped field flux and/or overspeed
is measured at the generator star point, an undervoltage
Sudden loss of load should only cause a transient overvoltage
characteristic is used. An overvoltage characteristic is used if
while the voltage regulator and governor act to correct the
the measurement is taken from the generator line VT. For
situation. A maladjusted voltage regulator may trip to manual,
effective application of this form of protection, there should be
maintaining excitation at the value prior to load loss while the
at least 1% third harmonic voltage across the generator neutral
generator supplies little or no load. The terminal voltage will
earthing impedance under all operating conditions.
increase substantially, and in severe cases it would be limited
A problem encountered is that the level of third harmonic only by the saturation characteristic of the generator. A rise in
voltage generated is related to the output of the generator. speed simply compounds the problem. If load that is sensitive
The voltage is low when generator output is low. In order to to overvoltages remains connected, the consequences in terms
avoid maloperation when operating at low power output, the of equipment damage and lost revenue can be severe.
relay element can be inhibited using an overcurrent or power Prolonged overvoltages may also occur on isolated networks,
elements (kW, kVAr or kVA) and internal programmable logic. or ones with weak interconnections, due to the fault conditions
listed earlier.
17.8.4.2 Use of Low-Frequency Voltage Injection
For these reasons, it is prudent to provide power frequency
Another method for protecting the entire stator winding of a overvoltage protection, in the form of a time-delayed element,
generator is to deploy signal injection equipment to inject a low either IDMT or definite time. The time delay should be long
frequency voltage between the stator star point and earth. An enough to prevent operation during normal regulator action,
earth fault at any winding location will result in the flow of a and therefore should take account of the type of AVR fitted and
measurable injection current to cause protection operation. its transient response. Sometimes a high-set element is
This form of protection can provide earth fault protection when provided as well, with a very short definite-time delay or
the generator is at standstill, prior to run-up. It is also an instantaneous setting to provide a rapid trip in extreme
appropriate method to apply to variable speed synchronous circumstances. The usefulness of this is questionable for
machines. Such machines may be employed for variable generators fitted with an excitation system other than a static
speed motoring in pumped-storage generation schemes or for type, because the excitation will decay in accordance with the
starting a large gas turbine prime mover. open-circuit time constant of the field winding. This decay can
last several seconds. The relay element is arranged to trip both
17.9 OVERVOLTAGE PROTECTION the main circuit breaker (if not already open) and the
Overvoltages on a generator may occur due to transient surges excitation; tripping the main circuit breaker alone is not
on the network, or prolonged power frequency overvoltages sufficient.
may arise from a variety of conditions. Surge arrestors may be
required to protect against transient overvoltages, but relay 17.10 UNDERVOLTAGE PROTECTION
protection may be used to protect against power frequency Undervoltage protection was historically rarely fitted to
overvoltages. generators. It is sometimes used as an interlock element for
A sustained overvoltage condition should not occur for a another protection function or scheme, such as field failure
machine with a healthy voltage regulator, but it may be caused protection or inadvertent energisation protection, where the
by the following contingencies: abnormality to be detected leads directly or indirectly to an
undervoltage condition. A transmission system undervoltage
• defective operation of the automatic voltage regulator condition may arise when there is insufficient reactive power
when the machine is in isolated operation generation to maintain the system voltage profile and the
• operation under manual control with the voltage condition must be addressed to avoid the possible
regulator out of service. A sudden variation of the load, phenomenon of system voltage collapse. However, it should
in particular the reactive power component, will give be addressed by the deployment of ’system protection’
rise to a substantial change in voltage because of the schemes. The generation should not be tripped. The greatest
large voltage regulation inherent in a typical alternator case for undervoltage protection being required would be for a
• sudden loss of load (due to tripping of outgoing feeders, generator supplying an isolated power system or to meet the
leaving the set isolated or feeding a very small load) public Utility demands for connection of embedded generation
(see Section 17.21).
17-12
Chapter 17 ⋅ Generator and Generator Transformer Protection
In the case of generators feeding an isolated system, sensitivity of better than 3% is required, a metering class CT
undervoltage may occur for several reasons, typically
Motoring Power Protection
overloading or failure of the AVR. In some cases, the Prime Mover Possible Damage
Setting
(% of rated)
performance of generator auxiliary plant fed via a unit
Fire/explosion due to
transformer from the generator terminals could be adversely unburnt fuel
affected by prolonged undervoltage. Diesel Engine 5-25
Mechanical damage to
Where undervoltage protection is required, it should comprise gearbox/shafts
17.11.1 Low Forward Power Protection The reverse power protection should be provided with a
definite time delay on operation to prevent spurious operation
Low forward power protection is often used as an interlocking
with transient power swings that may arise following
function to enable opening of the main circuit breaker for non-
synchronisation or in the event of a power transmission system
urgent trips – e.g. for a stator earth fault on a high-impedance
disturbance.
earthed generator, or when a normal shutdown of a set is
taking place. This is to minimise the risk of plant overspeeding
17.12 UNBALANCED LOADING
when the electrical load is removed from a high-speed
cylindrical rotor generator. The rotor of this type of generator A three-phase balanced load produces a reaction field that, to
is highly stressed mechanically and cannot tolerate much a first approximation, is constant and rotates synchronously
overspeed. While the governor should control overspeed with the rotor field system. Any unbalanced condition can be
conditions, it is not good practice to open the main circuit resolved into positive, negative and zero sequence
breaker simultaneously with tripping of the prime mover for components. The positive sequence component is similar to
non-urgent trips. For a steam turbine, for example, there is a the normal balanced load. The zero sequence component
risk of overspeeding due to energy storage in the trapped produces no main armature reaction.
steam, after steam valve tripping, or in the event that the
steam valve(s) do not fully close for some reason. For urgent 17.12.1 Effect of Negative Sequence Current
trip conditions, such as stator differential protection operation, The negative sequence component is similar to the positive
the risk involved in simultaneous prime mover and generator sequence system, except that the resulting reaction field
breaker tripping must be accepted. rotates in the opposite direction to the d.c. field system.
Hence, a flux is produced which cuts the rotor at twice the
17.11.2 Reverse Power Protection rotational velocity, thereby inducing double frequency currents
Reverse power protection is applied to prevent damage to in the field system and in the rotor body. The resulting eddy-
mechanical plant items in the event of failure of the prime currents are very large and cause severe heating of the rotor.
mover. Table 17.1 gives details of the potential problems for So severe is this effect that a single-phase load equal to the
various prime mover types and the typical settings for reverse normal three-phase rated current can quickly heat the rotor
power protection. For applications where a protection slot wedges to the softening point. They may then be extruded
under centrifugal force until they stand above the rotor surface,
17-13
Protection & Automation Application Guide
when it is possible that they may strike the stator core. 10000
Time (sec)
and it is usual in determining the generator negative sequence
withstand capability to assume that the heat dissipation during
such periods is negligible. Using this approximation it is 1
I 22t = K 0.1
where:
I2 = negative sequence component (per unit of machine rated 0.01
17-14
Chapter 17 ⋅ Generator and Generator Transformer Protection
17-15
Protection & Automation Application Guide
17.15 ROTOR FAULTS Figure 17.17: Flux distribution on rotor with partial winding short
circuit
The field circuit of a generator, comprising the field winding of
the generator and the armature of the exciter, together with
17.15.1 Rotor Earth-Fault Protection
any associated field circuit breaker if it exists, is an isolated d.c.
circuit which is not normally earthed. If an earth fault occurs, Two methods are available to detect this type of fault. The first
there will be no steady-state fault current and the need for method is suitable for generators that incorporate brushes in
action will not be evident. the main generator field winding. The second method requires
at least a slip-ring connection to the field circuit:
Danger arises if a second earth fault occurs at a separate point
in the field system, to cause the high field current to be • Potentiometer method
diverted, in part at least, from the intervening turns. Serious • A.C. injection method
damage to the conductors and possibly the rotor can occur
very rapidly under these conditions. 17.15.1.1 Potentiometer Method
More damage may be caused mechanically. If a large portion This is a scheme that was fitted to older generators, and it is
of the winding is short-circuited, the flux may adopt a pattern illustrated in Figure 17.18. An earth fault on the field winding
such as that shown in Figure 17.17. The attracting force at would produce a voltage across the relay, the maximum
the surface of the rotor is given by: voltage occurring for faults at the ends of the winding.
A ‘blind spot' would exist at the centre of the field winding. To
avoid a fault at this location remaining undetected, the tapping
17-16
Chapter 17 ⋅ Generator and Generator Transformer Protection
Field
winding I > Exciter L.F. injection
supply ∼
∼
∼ V>
17-17
Protection & Automation Application Guide
potentially damaging rotor vibration. Detection of such an instantaneously as it flows in a highly inductive circuit.
electrical fault is possible using a probe consisting of a coil Consequently, the flux energy must be dissipated to prevent an
placed in the airgap. The flux pattern of the positive and excessive inductive voltage rise in the field circuit. For
negative poles is measured and any significant difference in machines of moderate size, it is satisfactory to open the field
flux pattern between the poles is indicative of a shorted turn or circuit with an air-break circuit breaker without arc blow-out
turns. Automated waveform comparison techniques can be coils. Such a breaker permits only a moderate arc voltage,
used to provide a protection scheme, or the waveform can be which is nevertheless high enough to suppress the field current
inspected visually at regular intervals. An immediate fairly rapidly. The inductive energy is dissipated partly in the
shutdown is not normally required unless the effects of the arc and partly in eddy-currents in the rotor core and damper
fault are severe. The fault can be kept under observation until windings.
a suitable shutdown for repair can be arranged. Repair will
With generators above about 5MVA rating, it is better to
take some time, since it means unthreading the rotor and
provide a more definite means of absorbing the energy without
dismantling the winding.
incurring damage. Connecting a ‘field discharge resistor’ in
Since short-circuited turns on the rotor may cause damaging parallel with the rotor winding before opening the field circuit
vibration and the detection of field faults for all degrees of breaker will achieve this objective. The resistor, which may
abnormality is difficult, the provision of a vibration a detection have a resistance value of approximately five times the rotor
scheme is desirable – this forms part of the mechanical winding resistance, is connected by an auxiliary contact on the
protection of the generator. field circuit breaker. The breaker duty is thereby reduced to
that of opening a circuit with a low L/R ratio. After the breaker
17.15.4 Protection Against Diode Failure has opened, the field current flows through the discharge
A short-circuited diode will produce an a.c. ripple in the exciter resistance and dies down harmlessly. The use of a fairly high
field circuit. This can be detected by a relay monitoring the value of discharge resistance reduces the field time constant to
current in the exciter field circuit, however such systems have an acceptably low value, though it may still be more than one
proved to be unreliable. The relay would need to be time second. Alternatively, generators fitted with static excitation
delayed to prevent an alarm being issued with normal field systems may temporarily invert the applied field voltage to
forcing during a power system fault. A delay of 5-10 seconds reduce excitation current rapidly to zero before the excitation
may be necessary. system is tripped.
Fuses to disconnect the faulty diode after failure may be fitted. 17.16 LOSS OF EXCITATION PROTECTION
The fuses are of the indicating type, and an inspection window
Loss of excitation may occur for a variety of reasons. If the
can be fitted over the diode wheel to enable diode health to be
generator was initially operating at only 20%-30% of rated
monitored manually.
power, it may settle to run super-synchronously as an
A diode that fails open-circuit occurs less often. If there is induction generator, at a low level of slip. In doing so, it will
more than one diode in parallel for each arm of the diode draw reactive current from the power system for rotor
bridge, the only impact is to restrict the maximum continuous excitation. This form of response is particularly true of salient
excitation possible. If only a single diode per bridge arm is pole generators. In these circumstances, the generator may be
fitted, some ripple will be present on the main field supply but able to run for several minutes without requiring to be tripped.
the inductance of the circuit will smooth this to a degree and There may be sufficient time for remedial action to restore the
again the main effect is to restrict the maximum continuous excitation, but the reactive power demand of the machine
excitation. The set can be kept running until a convenient during the failure may severely depress the power system
shutdown can be arranged. voltage to an unacceptable level. For operation at high initial
power output, the rotor speed may rise to approximately 105%
17.15.5 Field Suppression of rated speed, where there would be low power output and
The need to rapidly suppress the field of a machine in which a where a high reactive current of up to 2.0p.u. may be drawn
fault has developed should be obvious, because as long as the from the supply. Rapid automatic disconnection is then
excitation is maintained, the machine will feed its own fault required to protect the stator windings from excessive current
even though isolated from the power system. Any delay in the and to protect the rotor from damage caused by induced slip
decay of rotor flux will extend the fault damage. Braking the frequency currents.
rotor is no solution, because of its large kinetic energy.
The field winding current cannot be interrupted
17-18
Chapter 17 ⋅ Generator and Generator Transformer Protection
+jX
17.16.1.1 Small Generators ( ≤ 5MVA) D
j cot θ
(X G + X T + Z S )1 −
2 −X
ZR = G
2
The general case can be represented by a system of circles
with centres on the line CD; see Figure 17.21. Also shown is a
typical machine terminal impedance locus during loss of
excitation conditions.
17-19
Protection & Automation Application Guide
+jX EG the direct-axis value, the ratio of Xd/XG being known as the
=15
.
ES saliency factor. This factor varies with the slip speed. The
1.8
effect of this factor during asynchronous operation is to cause
2.0 XG to vary at slip speed. In consequence, the loss of excitation
Load point impedance locus does not settle at a single point, but it
2.5
continues to describe a small orbit about a mean point.
Loss of field
5.0
locus A protection scheme for loss of excitation must operate
D
decisively for this condition, but its characteristic must not
inhibit stable operation of the generator. One limit of operation
corresponds to the maximum practicable rotor angle, taken to
-R +R
be 120°. The locus of operation can be represented as a circle
EG
=1 on the impedance plane, as shown in Figure 17.22, stable
ES
C operation conditions lying outside the circle.
Locus of
+jX constant MVA
0.5
ZS
0.6
0.7 -R XT +R
0.75X'd
-jX
2X'd
Figure 17.21: Swing curves and loss of synchronism locus
Limiting
When excitation is removed from a generator operating generation
synchronously the flux dies away slowly, during which period point
phase position, the locus bends round as the internal e.m.f. -jX
collapses, condensing on an impedance value equal to the Figure 17.22: Locus of limiting operating conditions of synchronous
machine reactance. The locus is illustrated in Figure 17.21. machine
The relay location is displaced from point C by the generator On the same diagram the full load impedance locus for one per
reactance XG. One problem in determining the position of these unit power can be drawn. Part of this circle represents a
loci relative to the relay location is that the value of machine condition that is not feasible, but the point of intersection with
the maximum rotor angle curve can be taken as a limiting
impedance varies with the rate of slip. At zero slip XG is equal
operating condition for setting impedance-based loss of
to Xd, the synchronous reactance, and at 100% slip XG is equal
excitation protection.
to X’’d, the sub-transient reactance. The impedance in a
typical case has been shown to be equal to X’d, the transient
17.16.2 Impedance-Based Protection Characteristics
reactance, at 50% slip, and to 2X’d with a slip of 0.33%. The
slip likely to be experienced with asynchronous running is low, Figure 17.21 alludes to the possibility that a protection scheme
perhaps 1%, so that for the purpose of assessing the power for loss of excitation could be based on impedance
measurement. The impedance characteristic must be
swing locus it is sufficient to take the value XG=2Xd’.
appropriately set or shaped to ensure decisive operation for
This consideration has assumed a single value for XG. loss of excitation whilst permitting stable generator operation
However, the reactance Xq on the quadrature axis differs from within allowable limits. One or two offset mho under
17-20
Chapter 17 ⋅ Generator and Generator Transformer Protection
impedance elements (see Chapter 11 for the principles of • time delay on drop-off, tdo1 = 0s
operation) are ideally suited for providing loss of excitation
If a fast excitation system is employed, allowing load angles of
protection as long as a generator operating at low power
up to 120o to be used, the impedance diameter must be
output (20-30%Pn) does not settle down to operate as an
reduced to take account of the reduced generator impedance
induction generator. The characteristics of a typical two-stage
seen under such conditions. The offset also needs revising. In
loss of excitation protection scheme are illustrated in Figure
these circumstances, typical settings would be:
17.23. The first stage, consisting of settings Xa1 and Xb1 can
be applied to provide detection of loss of excitation even where • impedance element diameter Xb1 = 0.5Xd
a generator initially operating at low power output (20-30%Pn) • impedance element offset Xa1 = -0.75X’d
might settle down to operate as an induction generator.
• time delay on pick-up, td1 = 0.5s – 10s
X • time delay on drop-off, tdo1 = 0s
Normal machine
operating impedance The typical impedance settings for the second element, if used,
R are:
-Xa2 -Xa1 Alarm
angle kV 2
X b2 =
MVA
Xb2 Xb1 kV 2
X a 2 = −0.5 X d'
MVA
The time delay settings td2 and tdo2 are set to zero to give
instantaneous operation and reset.
17-21
Protection & Automation Application Guide
forward power part of the cycle unless either a very short pick- 17.17.3.1 Pole Slipping Protection by Impedance
up time delay and/or a suitable drop-off time delay is used to Measurement
eliminate resetting. Although a mho type element for detecting the change in
The main advantage of this method is that a reverse power impedance during pole-slipping can be used in some
element is often already present, so no additional relay applications, but with performance limits, a straight line ‘ohm’
elements are required. The main disadvantages are the time characteristic is more suitable. The protection principle is that
taken for tripping and the inability to control the system angle of detecting the passage of the generator impedance through a
at which the generator breaker trip command would be issued, zone defined by two such impedance characteristics, as shown
if it is a requirement to limit the breaker current interruption in Figure 17.24. The characteristic is divided into three zones,
duty. There is also the difficulty of determining suitable A, B, and C. Normal operation of the generator lies in zone A.
settings. Determination of settings in the field, from a When a pole-slip occurs, the impedance traverses zones B and
deliberate pole-slipping test is not possible and analytical C, and tripping occurs when the impedance characteristic
studies may not discover all conditions under which pole- enters zone C.
slipping will occur.
+jX
rapid tripping is required during the first slip cycle and where Ohm relay 1
some control is required for the system angle at which the Figure 17.24: Pole slipping detection by ohm relays
generator circuit breaker trip command is given. Where Tripping only occurs if all zones are traversed sequentially.
protection against pole-slipping must be guaranteed, a more Power system faults should result in the zones not being fully
sophisticated method of protection should be used. A typical traversed so that tripping will not be initiated. The security of
reset timer delay for pole-slipping protection might be 0.6s. this type of protection scheme is normally enhanced by the
For generator transformer units, the additional impedance in addition of a plain under impedance control element (circle
front of the relaying point may take the system impedance about the origin of the impedance diagram) that is set to
outside the under impedance relay characteristic required for prevent tripping for impedance trajectories for remote power
loss of excitation protection. Therefore, the acceptability of this system faults. Setting of the ohm elements is such that they
pole-slipping protection scheme will be dependent on the lie parallel to the total system impedance vector, and enclose
application. it, as shown in Figure 17.24.
17-22
Chapter 17 ⋅ Generator and Generator Transformer Protection
P Characteristic
ZB
P' Blinder
α θ
R
Figure 17.26: Definition of zones for lenticular characteristic
If the impedance locus lies above line PP’, the swing lies far
Lens out in the power system – i.e. one part of the power system,
including the protected generator, is swinging against the rest
ZB of the network. Tripping may still occur, but only if swinging is
prolonged – meaning that the power system is in danger of
complete break-up. Further confidence checks are introduced
Figure 17.25: Pole-slipping protection using lenticular characteristic
by requiring that the impedance locus spends a minimum time
and blinder within each zone for the pole-slipping condition to be valid.
The trip signal may also be delayed for a number of slip cycles
The width of the lens is set by the angle α and the line PP’,
even if a generator pole-slip occurs – this is to both provide
perpendicular to the axis of the lens, is used to determine if the
confirmation of a pole-slipping condition and allow time for
centre of the impedance swing during a transient is located in
other relays to operate if the cause of the pole slip lies
the generator or power system.
somewhere in the power system. Should the impedance locus
Operation in the case of a generator is as follows. The traverse the zones in any other sequence, tripping is blocked.
characteristic is divided into 4 zones and 2 regions, as shown in
Figure 17.26. Normal operation is with the measured 17.18 STATOR OVERHEATING
impedance in zone R1. If a pole slip develops, the impedance Overheating of the stator may result from:
locus will traverse though zones R2, R3, and R4. When entering
zone R4, a trip signal is issued, provided the impedance lies • overload
below reactance line PP’ and hence the locus of swing lies • failure of the cooling system
within or close to the generator – i.e. the generator is pole • overfluxing
slipping with respect to the rest of the system.
• core faults
Accidental overloading might occur through the combination
of full active load current component, governed by the prime
mover output and an abnormally high reactive current
component, governed by the level of rotor excitation and/or
step-up transformer tap. With a modern protection relay, it is
relatively simple to provide a current-operated thermal replica
protection element to estimate the thermal state of the stator
windings and to issue an alarm or trip to prevent damage.
Although current-operated thermal replica protection cannot
take into account the effects of ambient temperature or
17-23
Protection & Automation Application Guide
uneven heat distribution, it is often applied as a back-up to To minimise overspeed on load rejection and hence the
direct stator temperature measuring devices to prevent mechanical stresses on the rotor, the following sequence is
overheating due to high stator current. With some relays, the used whenever electrical tripping is not urgently required:
thermal replica temperature estimate can be made more
• trip prime mover or gradually reduce power input to zero
accurate through the integration of direct measuring resistance
temperature devices. • allow generated power to decay towards zero
• trip generator circuit breaker only when generated
Irrespective of whether current-operated thermal replica
power is close to zero or when the power flow starts to
protection is applied or not, it is a requirement to monitor the
reverse, to drive the idle turbine
stator temperature of a large generator in order to detect
overheating from whatever cause.
17.19.3 Loss of Vacuum
Temperature sensitive elements, usually of the resistance type, A failure of the condenser vacuum in a steam turbine driven
are embedded in the stator winding at hot-spot locations generator results in heating of the tubes. This then produces
envisaged by the manufacturer, the number used being strain in the tubes, and a rise in temperature of the low-
sufficient to cover all variations. The elements are connected to pressure end of the turbine. Vacuum pressure devices initiate
a temperature sensing relay element arranged to provide alarm progressive unloading of the set and, if eventually necessary,
and trip outputs. The settings will depend on the type of stator tripping of the turbine valves followed by the high voltage
winding insulation and on its permitted temperature rise. circuit breaker. The set must not be allowed to motor in the
event of loss of vacuum, as this would cause rapid overheating
17.19 MECHANICAL FAULTS of the low-pressure turbine blades.
Various faults may occur on the mechanical side of a
generating set. The following sections detail the more 17.20 COMPLETE GENERATOR PROTECTION
important ones from an electrical point of view. SCHEMES
From the preceding sections, it is obvious that the protection
17.19.1 Failure of the Prime Mover
scheme for a generator has to take account of many possible
When a generator operating in parallel with others loses its faults and plant design variations. Determination of the types
power input, it remains in synchronism with the system and of protection used for a particular generator will depend on the
continues to run as a synchronous motor, drawing sufficient nature of the plant and upon economic considerations, which
power to drive the prime mover. This condition may not appear in turn is affected by set size. Fortunately, modern, multi-
to be dangerous and in some circumstances will not be so. function, numerical relays are sufficiently versatile to include all
However, there is a danger of further damage being caused. of the commonly required protection functions in a single
Table 17.1 lists some typical problems that may occur. package, thus simplifying the decisions to be made. The
Protection is provided by a low forward power/reverse power following sections provide illustrations of typical protection
relay, as detailed in Section 17.11. schemes for generators connected to a grid network, but not
all possibilities are illustrated, due to the wide variation in
17.19.2 Overspeed generator sizes and types.
The speed of a turbo-generator set rises when the steam input
is in excess of that required to drive the load at nominal
17.20.1 Direct-Connected Generator
frequency. The speed governor can normally control the A typical protection scheme for a direct-connected generator is
speed, and, in any case, a set running in parallel with others in shown in Figure 17.27. It comprises the following protection
an interconnected system cannot accelerate much functions:
independently even if synchronism is lost. However, if load is • stator differential protection
suddenly lost when the HV circuit breaker is tripped, the set
• overcurrent protection – conventional or voltage
will begin to accelerate rapidly. The speed governor is
dependent
designed to prevent a dangerous speed rise even with a 100%
load rejection, but nevertheless an additional centrifugal • stator earth fault protection
overspeed trip device is provided to initiate an emergency • overvoltage protection
mechanical shutdown if the overspeed exceeds 10%. • undervoltage protection
17-24
Chapter 17 ⋅ Generator and Generator Transformer Protection
• overload/low forward power/reverse power protection differential protection) may utilise a separate relay. Figure
(according to prime mover type) 17.28 shows a typical overall scheme.
• unbalanced loading Electrical trip of governor Governor
trip
• overheating
Emergency push button
• pole slipping
Stator differential (biased/high
• loss of excitation impedance)
Stator E/F (or neutral voltage
• underfrequency displacement)
Back-up overcurrent (or voltage
dependent O/C)
• inadvertent energisation Lubricating oil failure
Mechanical faults (urgent)
17-25
Protection & Automation Application Guide
the Utility distribution system or not, since there may exist fault In addition, particular circumstances may require additional
conditions when this occurs irrespective of the design intent. protection functions:
If plant operation when disconnected from the Utility supply is • neutral voltage displacement
required, underfrequency protection (Section 17.14.2) will • reverse power
become an important feature of the in-plant power system.
• directional overcurrent
During isolated operation, it may be relatively easy to overload
the available generation, such that some form of load In practice, it can be difficult to meet the protection settings or
management system may be required. Similarly, when performance demanded by the Utility without a high risk of
running in parallel with the Utility, consideration needs to be nuisance tripping caused by lack of co-ordination with normal
given to the mode of generator operation if reactive power power system faults and disturbances that do not necessitate
import is to be controlled. The impact on the control scheme tripping of the embedded generation. This is especially true
of a sudden break in the Utility connection to the plant main when applying protection specifically to detect loss of the
busbar also requires analysis. Where the in-plant generation is Utility supply (also called ‘loss of mains’) to cater for operating
run using constant power factor or constant reactive power conditions where there would be no immediate excursion in
control, automatic reversion to voltage control when the Utility voltage or frequency to cause operation of conventional
connection is lost is essential to prevent plant loads being protection functions.
subjected to a voltage outside acceptable limits.
17.21.1 Protection Against Loss of Utility Supply
Limits may be placed by the Utility on the amount of
power/reactive power import/export. These may demand the If the normal power infeed to a distribution system, or to the
use of an in-plant Power Management System to control the part of it containing embedded generation is lost, the effects
embedded generation and plant loads accordingly. Some may be as follows:
Utilities may insist on automatic tripping of the interconnecting a. embedded generation may be overloaded, leading to
circuit breakers if there is a significant departure outside generator undervoltage/ underfrequency
permissible levels of frequency and voltage, or for other reasons.
b. embedded generation may be underloaded, leading
From a Utility standpoint, the connection of embedded to overvoltage/overfrequency
generation may cause problems with voltage control and c. little change to the absolute levels of voltage or
increased fault levels. The settings for protection relays in the frequency if there is little resulting change to the
vicinity of the plant may require adjustment with the load flow through the PCC
emergence of embedded generation. It must also be ensured
The first two effects are covered by conventional voltage and
that the safety, security and quality of supply of the Utility
frequency protection. However, if condition (c) occurs,
distribution system is not compromised. The embedded
conventional protection may not detect the loss of Utility
generation must not be permitted to supply any Utility
supply condition or it may be too slow to do so within the
customers in isolation, since the Utility supply is normally the
shortest possible auto-reclose dead-times that may be applied
means of regulating the system voltage and frequency within
in association with Utility overhead line protection. Detection
the permitted limits. It also normally provides the only system
of condition (c) must be achieved if the requirements of the
earth connection(s), to ensure the correct performance of
Utility are to be met. Many possible methods have been
system protection in response to earth faults. If the Utility
suggested, but the one most often used is the Rate of Change
power infeed fails, it is also important to disconnect the
of Frequency (ROCOF) relay. Its application is based on the
embedded generation before there is any risk of the Utility
fact that the rate of change of small changes in absolute
power supply returning on to unsynchronised machines. In
frequency, in response to inevitable small load changes, will be
practice this generally requires the following protection
faster with the generation isolated than when the generation is
functions to be applied at the ‘Point of Common Coupling’
in parallel with the public, interconnected power system.
(PCC) to trip the coupling circuit breaker:
However, problems with nuisance tripping in response to
• overvoltage national power system events, where the system is subject to
• undervoltage significant frequency excursions following the loss of a large
generator or a major power interconnector, have occurred.
• overfrequency
This is particularly true for geographically islanded power
• underfrequency systems, such as those of the British Isles. An alternative to
• loss of Utility supply ROCOF protection is a technique sometimes referred to as
17-26
Chapter 17 ⋅ Generator and Generator Transformer Protection
‘voltage vector shift’ protection. In this technique the rate of ROCOF relay for a set time, or once the voltage phase angle
phase change between the directly measured generator bus drift exceeds the set angle, tripping occurs to open the
voltage is compared with a memorised a.c. bus voltage connection between the in-plant and Utility networks.
reference.
While it is possible to estimate the rate of change of frequency
Sources of embedded generation are not normally earthed, from knowledge of the generator set inertia and MVA rating,
which presents a potential safety hazard. In the event of an this is not an accurate method for setting a ROCOF relay
Utility system earth fault, the Utility protection should operate because the rotational inertia of the complete network being
to remove the Utility power infeed. In theory, this should also fed by the embedded generation is required. For example,
result in removal of the embedded generation, through the there may be other embedded generators to consider. As a
action of the stipulated voltage/frequency protection and result, it is invariably the case that the relay settings are
dependable ‘loss of mains’ protection. However, in view of determined at site during commissioning. This is to ensure
safety considerations (e.g. fallen overhead line conductors in that the Utility requirements are met while reducing the
public areas), an additional form of earth fault protection may possibility of a spurious trip under the various operating
also be demanded to prevent the backfeed of an earth fault by scenarios envisaged. However, it is very difficult to determine
embedded generation. The only way of detecting an earth whether a given rate of change of frequency will be due to a
fault under these conditions is to use neutral voltage ‘loss of mains’ incident or a load/frequency change on the
displacement protection. The additional requirement is only public power network, and hence spurious trips are impossible
likely to arise for embedded generation rated above 150kVA, to eliminate. Thus the provision of Loss of Utility Supply
since the risk of small embedded generators not being cleared protection to meet power distribution Utility interface
by other means is negligible. protection requirements, may actually conflict with the
interests of the national power system operator. With the
17.21.2 ROCOF Relay Description growing contribution of non-dispatched embedded generation
A ROCOF relay detects the rate of change of frequency in to the aggregate national power demand, the loss of the
excess of a defined setpoint. The signal is obtained from a embedded generation following a transmission system incident
voltage transformer connected close to the Point of Common that may already challenge the security of the system can only
Coupling (PCC). The principal method used is to measure the aggravate the problem. There have been claims that voltage
time period between successive zero-crossings to determine vector shift protection might offer better security, but it will
the average frequency for each half-cycle and hence the rate of have operation times that vary with the rate of change of
change of frequency. The result is usually averaged over a frequency. As a result, depending on the settings used,
number of cycles. operation times might not comply with Utility requirements
under all circumstances. [Reference 17.1] provides further
17.21.3 Voltage Vector Shift Relay Description details of the operation of ROCOF relays and the problems that
may be encountered.
A voltage vector shift relay detects the drift in voltage phase
angle beyond a defined setpoint as long as it takes place within Nevertheless, because such protection is a common
a set period. Again, the voltage signal is obtained from a requirement of some Utilities, the ‘loss of mains’ protection
voltage transformer connected close to the Point of Common may have to be provided and the possibility of spurious trips
Coupling (PCC). The principal method used is to measure the will have to be accepted in those cases. Site measurements
time period between successive zero-crossings to determine over a period of time of the typical rates of frequency change
the duration of each half-cycle, and then to compare the occurring may assist in negotiations of the settings with the
durations with the memorised average duration of earlier half- Utility, and with the fine-tuning of the protection that may
cycles in order to determine the phase angle drift. already be commissioned.
17-27
Protection & Automation Application Guide
17.22.1 Protection Settings of a Small Industrial offset magnetising inrush or motor starting current waveforms
Generator with an r.m.s level close to rated current, and where there is a
high L/R time constant for the offset, the use of a 0% bias slope
Salient details of the generator, network and protection required
may give rise to maloperation. Such waveforms can be
are given in Table 17.2. The example calculations are based on
encountered when plant of similar rating to the generator is
a MiCOM P343 relay in respect of setting ranges, etc.
being energised or started. Differences between CT designs or
differing remanent flux levels can lead to asymmetric
Generator Data
saturation and the production of a differential spill current.
Rated Rated
Rated
Rated
Prime Therefore, it is appropriate to select a non-zero setting for K1,
KVA KW PF Freque Mover and a value of 5% is usual in these circumstances.
Voltage Current Speed
ncy Type
17-28
Chapter 17 ⋅ Generator and Generator Transformer Protection
short-time current limits. A curve should be provided by the generator). It must therefore have a setting that grades with
manufacturer, but IEC 60034-1 demands that an AC the downstream protection. The protection is driven from the
generator should be able to pass 1.5 times rated current for at generator star-connected VT, while the downstream protection
least 30 seconds. The operating time of the downstream is current operated.
protection for a three-phase fault current of 850A is 0.682s, so
It is therefore necessary to translate the current setting of the
the voltage controlled relay element should have a minimum
downstream setting of the current-operated earth-fault
operating time of 1.09s (0.4s grading margin used as the relay
protection into the equivalent voltage for the NVD protection.
technology used for the downstream relay is not stated – see
The equivalent voltage is found from the formula:
Table 9.2). With a current setting of 87.5A, the operating time
of the voltage controlled relay element at a TMS of 1.0 is: (I pe × Z e )× 3
Veff =
VTratio
0.14
= 3.01s
850
0.02 48 × 31.7 × 3
−1 =
87.5 100
= 45.6V
Therefore a TMS of:
where:
1.09
= 0.362 Veff = effective voltage setting
3.01
is required. Use 0.375, nearest available setting. Ipe = downstream earth fault current setting
Ze = earthing resistance
17.22.1.3 Stator Earth Fault Protection
Hence a setting of 48V is acceptable. Time grading is
The maximum earth fault current, from Table 17.2, is 200A. required, with a minimum operating time of the NVD
Protection for 95% of the winding can be provided if the relay is protection of 1.13s at an earth fault current of 200A. Using
set to detect a primary earth fault current of 16.4A, and this the expression for the operation time of the NVD element:
equates to a CT secondary current of 0.033A. The nearest
relay setting is 0.04A, providing protection for 90% of the K
t= s
winding. (M − 1)
The protection must grade with the downstream earth fault where:
protection, the settings of which are also given in Table 17.2.
At an earth fault current of 200A, the downstream protection V
M =
has an operation time of 0.73s. The generator earth fault
Vsnvd
protection must therefore have an operation time of not less
than 1.13s. At a TMS of 1.0, the generator protection relay and
operating time will be: V = voltage seen by relay
Vsnvd = relay setting voltage
0.14 s the value of K can be calculated as 3.34. The nearest settable
200 0.02 value is 3.5, giving an operation time of 1.18s.
− 1
20 17.22.1.5 Loss of Excitation Protection
= 2.97s, so the required TMS is Loss of excitation is detected by a mho impedance relay
1.13 element, as detailed in Section 17.16.2. The standard settings
= 0.38 for the P340 series relay are:
2.97
Use a setting of 0.4, nearest available setting.
17-29
Protection & Automation Application Guide
17-30
Chapter 17 ⋅ Generator and Generator Transformer Protection
0.05 × 5 × 10 6
K2 150%
= Ise 0.04
500 × 100 Stator earth fault
TMS 0.4
= 5W Vsnvd 48V
Neutral Voltage Displacement
This value can be set in the relay. A time delay is required to K 3.5
guard against power swings while generating at low power Xa -14.5Ω
levels, so use a time delay of 5s. No reset time delay is Xb 227Ω
required. Loss of excitation
td1 3s
td01 0.5s
Ivcset 0.73
Vs 33
Voltage controlled overcurrent
K 0.6
TMS 0.375
I2>> 0.05
K 8.6s
Negative phase sequence Kreset 8.6s
tmin 1.5s
tmax 600s
V> meas mode three-phase
V> operate mode any
V>1 setting 107%
V>1 function DT
Overvoltage
V>1 time delay 10s
V>2 setting 120%
V>2 function DT
V>2 time delay 0sec
F<1 setting 49Hz
F<1 time delay 20s
Underfrequency
F<2 setting 48Hz
F<2 time delay 0.5s
P1 function reverse power
P1 setting 5W
Reverse Power
P1 time delay 5s
P1 DO time 0s
Table 17.3: Small generator protection example – relay settings
17-31
Protection & Automation Application Guide
throughout. VN
I flt =
(nR ) + (X )
2
Parameter Value Unit 2
f d + X t + nX f
Generator MVA rating 187.65 MVA
Generator MW rating 160 MW Where
Generator voltage 18 kV Iflt = minimum generator primary current for a multi-phase
Synchronous reactance 1.93 pu feeder-end fault
Direct-axis transient reactance 0.189 pu
VN = no load phase-neutral generator voltage
Minimum operating voltage 0.8 pu
Generator negative sequence capability 0.08 pu Xd = generator d-axis synchronous reactance
Generator negative sequence factor, Kg 10 Xt = generator transformer reactance
Generator third harmonic voltage under load 0.02 pu
Rf = feeder resistance
Generator motoring power 0.02 pu
alarm 1.1 Xf = feeder reactance
Generator overvoltage time delay 5 n = number of parallel generators
trip 1.3
Hence,
Generator undervoltage not required
Max pole slipping frequency 10 Hz I flt = 2893 A = 0.361I n
Generator transformer rating 360 MVA
and
Generator transformer leakage reactance 0.244 pu
Generator transformer overflux alarm 1.1 pu
V flt =
(
VN 3 (nR f ) + X t + nX f
2
( )) 2
(nR ) + (X + nX )
Generator transformer overflux alarm 1.2 pu
2 2
Network resistance (referred to 18kV) 0.56 mΩ f d + Xt f
17-32
Chapter 17 ⋅ Generator and Generator Transformer Protection
17.22.2.4 Negative Phase Sequence Protection The third harmonic undervoltage protection setting must be
The generator has a maximum steady-state capability of 8% of below this value, a factor of 80% is acceptable. Use a value of
rating, and a value of Kg of 10. Settings of I2cmr = 0.06 166.3V and a time delay of 0.5s. Inhibition of the element at
(=480A) and Kg = 10 are therefore used. Minimum and low generator output must be determined during
maximum time delays of 1s and 1300s are used to co-ordinate commissioning.
with external protection and ensure tripping at low levels of
negative sequence current are used.
17.22.2.7 Loss of Excitation Protection
The client requires a two-stage loss of excitation protection
17.22.2.5 Overfluxing Protection function. The first is alarm only, while the second provides
The generator-transformer manufacturer supplied the tripping under high load conditions. To achieve this, the first
following characteristics: impedance element of the P343 loss of excitation protection can
be set in accordance with the guidelines of Section 17.16.3 for a
V generator operating at rotor angles up to 120o, as follows:
Alarm > 1.1
f
X b1 = 0.5 X d = 1.666Ω
V
Trip > 1.2 inverse time characteristic X a1 = −0.75 X d' = −0.245Ω
f
Use nearest settable values of 1.669Ω and 0.253Ω. A time
Hence the alarm setting is
delay of 5s is used to prevent alarms under transient
1.05 conditions. For the trip stage, settings for high load are used,
18000 × = 315 V as given in Section 17.16.3:
60 Hz
A time delay of 5s is used to avoid alarms due to transient kV 2 18 2
X b2 = = = 1.727Ω
conditions. The trip setting is: MVA 187.65
1.2 X a2 = −0.75 X d' = −0.1406Ω
18000 × = 360 V
60 Hz The nearest settable value for Xb2 is 1.725Ω. A time delay of
A TMS value of 10 is selected, to match the withstand curve 0.5s is used.
supplied by the manufacturer.
17.22.2.8 Reverse Power Protection
17.22.2.6 100% Stator Earth Fault Protection The manufacturer-supplied value for motoring power is 2% of
This is provided by a combination of neutral voltage rated power. The recommended setting is therefore 1.6MW.
displacement and third harmonic undervoltage protection. For An instrumentation class CT is used in conjunction with the
the neutral voltage displacement protection to cover 90% of the relay for this protection, to ensure accuracy of measurement.
stator winding, the minimum voltage allowing for generator A time delay of 0.5s is used. The settings should be checked at
operation at a minimum of 92% of rated voltage is: the commissioning stage.
17-33
Protection & Automation Application Guide
The lens angle setting, α, is found from the equation: V>1 setting 19800V F<3 time delay 1s
V>1 function DT
1.54 − Rt min Overvoltage
a min = 180 − 2 tan
A −1
V>1 time
5s
Z A + ZB delay
V>2 setting 23400V
and, substituting values,
V>2 function DT
α min = 62.5
V>2 time
0.1s
delay
Use the minimum settable value of 90o. The blinder angle, θ,
Table 17.5: Relay settings for large generator protection example
is estimated to be 80o, and requires checking during
commissioning. Timers T1 and T2 are set to 15ms as 17.23 REFERENCE
experience has shown that these settings are satisfactory to
[17.1] Survey of Rate of Change of Frequency Relays and
detect pole slipping frequencies up to 10Hz.
Voltage Phase Shift Relays for Loss of Mains
This completes the settings required for the generator, and the Protection. ERA Report 95-0712R, 1995. ERA
relay settings are given in Table 17.5. Of course, additional Technology Ltd.
protection is required for the generator transformer, according
17-34
Chapter 17 ⋅ Generator and Generator Transformer Protection
17-35
INDUSTRIAL AND
COMMERCIAL POWER
SYSTEM PROTECTION
Chapter 18
INDUSTRIAL AND COMMERCIAL
POWER SYSTEM PROTECTION
GEGridSolutions.com 18-1
Protection & Automation Application Guide
different switchboards. ∼
NO
HV supply HV supply
1 2
* NC
A B C
0.4kV
NO
NO
A B
6kV
Transformer Transformer *
1 2
2 out of 3 NO
mechanical or electrical
interlock * NC
A B C
0.4kV
NO
NO
* NC
0.4kV
A NO B C
Figure 18.2: Typical switchboard configuration for an industrial plant
Bus section C - Essential supplies
The main power system design criterion is that single outages EDG - Emergency generator
on the electrical network within the plant will not cause loss of * - Two out of three interlock
both the main and standby drives simultaneously. Considering Figure 18.3: Typical industrial power system
a medium sized industrial supply system, shown in Figure The Essential Services Boards are used to feed equipment that
18.3, in more detail, it will be seen that not only are duplicate is essential for the safe shut down, limited operation or
supplies and transformers used, but also certain important preservation of the plant and for the safety of personnel. This
loads are segregated and fed from ‘Essential Services Board(s)’ will cover process drives essential for safe shutdown, venting
(also known as ‘Emergency’ boards), distributed throughout systems, UPS loads feeding emergency lighting, process
the plant. This enables maximum utilisation of the standby control computers, etc. The emergency generator may range
generator facility. A standby generator is usually of the turbo- in size from a single unit rated 20-30kW in a small plant up to
charged diesel-driven type. On detection of loss of incoming several units of 2-10MW rating in a large oil refinery or similar
supply at any switchboard with an emergency section, the plant. Large financial trading institutions may also have
generator is automatically started. The appropriate circuit standby power requirements of several MW to maintain
breakers will close once the generating set is up to speed and computer services.
rated voltage to restore supply to the Essential Services
sections of the switchboards affected, provided that the normal 18.3 DISCRIMINATION
incoming supply is absent - for a typical diesel generator set,
Protection equipment works in conjunction with switchgear.
the emergency supply would be available within 10-20
For a typical industrial system, feeders and plant will be
seconds from the start sequence command being issued.
protected mainly by circuit breakers of various types and by
fused contactors. Circuit breakers will have their associated
overcurrent and earth fault relays. A contactor may also be
18-2
Chapter 18 ⋅ Industrial and Commercial Power System Protection
equipped with a protection device (e.g. motor protection), but Curve of asymmetrical
associated fuses are provided to break fault currents in excess prospective short-circuit
of the contactor interrupting capability. The rating of fuses and current
selection of relay settings is carried out to ensure that Current trace
discrimination is achieved – i.e. the ability to select and isolate Ip
only the faulty part of the system.
Time
18.4 HRC FUSES Start of
The protection device nearest to the actual point of power Short-circuit
utilisation is most likely to be a fuse or a system of fuses and it Arcing
Pre-arcing
is important that consideration is given to the correct time
time
application of this important device.
The HRC fuse is a key fault clearance device for protection in Total clearance 1 Cycle
industrial and commercial installations, whether mounted in a time
distribution fuseboard or as part of a contactor or fuse-switch. Figure 18.4: HRC fuse cut-off feature
The latter is regarded as a vital part of LV circuit protection, Since the electromagnetic forces on busbars and connections
combining safe circuit making and breaking with an isolating carrying short circuit current are related to the square of the
capability achieved in conjunction with the reliable short- current, it will be appreciated that ‘cut-off’ significantly
circuit protection of the HRC fuse. Fuses combine the reduces the mechanical forces produced by the fault current
characteristics of economy and reliability; factors that are most and which may distort the busbars and connections if not
important in industrial applications. correctly rated. A typical example of ‘cut-off’ current
HRC fuses remain consistent and stable in their breaking characteristics is shown in Figure 18.5. It is possible to use
characteristics in service without calibration and maintenance. this characteristic during the design stage of a project to utilise
This is one of the most significant factors for maintaining fault equipment with a lower fault withstand rating downstream of
clearance discrimination. Lack of discrimination through the fuse, than would be the case if ‘cut-off’ was ignored. This
incorrect fuse grading will result in unnecessary disconnection may save on costs, but appropriate documentation and
of supplies, but if both the major and minor fuses are HRC maintenance controls are required to ensure that only
devices of proper design and manufacture, this need not replacement fuses of very similar characteristics are used
endanger personnel or cables associated with the plant. throughout the lifetime of the plant concerned – otherwise a
safety hazard may arise.
18.4.1 Fuse Characteristics 1000
The time required for melting the fusible element depends on
the magnitude of current. This time is known as the ‘pre-
arcing’ time of the fuse. Vaporisation of the element occurs on
melting and there is fusion between the vapour and the filling 100 1250A
710A 800A
powder leading to rapid arc extinction.
Cut off current (peak kA)
500A 630A
400A
Fuses have a valuable characteristic known as ‘cut-off’, shown 200A 315A
125A
in Figure 18.4. When an unprotected circuit is subjected to a 80A
short circuit fault, the r.m.s. current rises towards a 10
50A
‘prospective’ (or maximum) value. The fuse usually interrupts 35A
25A
the short circuit current before it can reach the prospective 16A
value, in the first quarter to half cycle of the short circuit. The
6A
rising current is interrupted by the melting of the fusible 1.0
2A
element, subsequently dying away dying away to zero during
the arcing period.
0.1
0.1 1.0 10 100 500
Figure 18.5: Typical fuse cut-off current characteristics
18-3
Protection & Automation Application Guide
18-4
Chapter 18 ⋅ Industrial and Commercial Power System Protection
Single-pole units may be coupled mechanically in groups to • because of their higher ratings, MCCBs are usually
form 2, 3 or 4 pole units, when required, by assembly on to a positioned in the power distribution system nearer to
rail in a distribution board. The available ratings make MCBs the power source than the MCBs
suitable for industrial, commercial or domestic applications, for • the appropriate European specification is EN 60947-2
protecting equipment such as cables, lighting and heating
circuits, and also for the control and protection of low power Care must be taken in the short-circuit ratings of MCCBs.
motor circuits. They may be used instead of fuses on MCCBs are given two breaking capacities, the higher of which
individual circuits, and they are usually ‘backed-up’ by a device is its ultimate breaking capacity. The significance of this is that
of higher fault interrupting capacity. after breaking such a current, the MCCB may not be fit for
continued use. The lower, or service, short circuit breaking
Various accessory units, such as isolators, timers, and capacity permits continued use without further detailed
undervoltage or shunt trip release units may be combined with examination of the device. The standard permits a service
an MCB to suit the particular circuit to be controlled and breaking capacity of as little as 25% of the ultimate breaking
protected. When personnel or fire protection is required, a capacity. While there is no objection to use of MCCBs to break
residual current device (RCD) may be combined with the short-circuit currents between the service and ultimate values,
MCB. The RCD contains a miniature core balance current the inspection required after such a trip reduces the usefulness
transformer that embraces all of the phase and neutral of the device in such circumstances. It is also clearly difficult
conductors to provide sensitivity to earth faults within a typical to determine if the magnitude of the fault current was in
range of 0.05% to 1.5% of rated current, dependent on the RCD excess of the service rating.
selected. The core balance CT energises a common magnetic
trip actuator for the MCB assembly. The time-delay characteristics of the magnetic or thermal
timed trip, together with the necessity for, or size of, a back-up
It is also possible to obtain current-limiting MCBs. These types device varies with make and size of breaker. Some MCCBs are
open prior to the prospective fault current being reached, and fitted with microprocessor-controlled programmable trip
therefore have similar properties to HRC fuses. It is claimed characteristics offering a wide range of such characteristics.
that the extra initial cost is outweighed by lifetime savings in Time–delayed overcurrent characteristics may not be the same
replacement costs after a fault has occurred, plus the as the standard characteristics for dependent-time protection
advantage of providing improved protection against electric stated in IEC 60255-3. Hence, discrimination with other
shock if an RCD is used. As a result of the increased safety protection must be considered carefully. There can be
provided by MCBs fitted with an RCD device, they are tending problems where two or more MCBs or MCCBs are electrically
to replace fuses, especially in new installations. in series, as obtaining selectivity between them may be
difficult. There may be a requirement that the major device
18.5.2 Moulded Case Circuit Breakers (MCCBs) should have a rating of k times the minor device to allow
These circuit breakers are broadly similar to MCBs but have discrimination, in a similar manner to fuses – the
the following important differences: manufacturer should be consulted as to value of k. Careful
examination of manufacturers’ literature is always required at
• the maximum ratings are higher, with voltage ratings
the design stage to determine any such limitations that may be
up to 1000V a.c./1200V d.c. Current ratings of 2.5kA
imposed by particular makes and types of MCCBs. An
continuous/180kA r.m.s break are possible, dependent
example of co-ordination between MCCBs, fuses and relays is
upon power factor
given in Section 18.12.2.
• the breakers are larger, commensurate with the level of
ratings. Although available as single, double or triple 18.5.3 Air Circuit Breakers (ACBs)
pole units, the multiple pole units have a common
Air circuit breakers are frequently encountered on industrial
housing for all the poles. Where fitted, the switch for
systems rated at 3.3kV and below. Modern LV ACBs are
the neutral circuit is usually a separate device, coupled
available in current ratings of up to 6.3kA with maximum
to the multi-pole MCCB
breaking capacities in the range of 85kA-120kA r.m.s.,
• the operating levels of the magnetic and thermal depending on system voltage.
protection elements may be adjustable, particularly in
the larger MCCBs This type of breaker operates on the principle that the arc
produced when the main contacts open is controlled by
directing it into an arc chute. Here, the arc resistance is
increased and hence the current reduced to the point where
18-5
Protection & Automation Application Guide
the circuit voltage cannot maintain the arc and the current 18.5.4 Oil Circuit Breakers (OCBs)
reduces to zero. To assist in the quenching of low current arcs, Oil circuit breakers have been very popular for many years for
an air cylinder may be fitted to each pole to direct a blast of air industrial supply systems at voltages of 3.3kV and above. They
across the contact faces as the breaker opens, so reducing are found in both ‘bulk oil’ and ‘minimum oil’ types, the only
contact erosion. significant difference being the volume of oil in the tank.
Air circuit breakers for industrial use are usually withdrawable In this type of breaker, the main contacts are housed in an oil-
and are constructed with a flush front plate making them ideal filled tank, with the oil acting as the both the insulation and
for inclusion together with fuse switches and MCBs/MCCBs in the arc-quenching medium. The arc produced during contact
modular multi-tier distribution switchboards, so maximising separation under fault conditions causes dissociation of the
the number of circuits within a given floor area. hydrocarbon insulating oil into hydrogen and carbon. The
Older types using a manual or dependent manual closing hydrogen extinguishes the arc. The carbon produced mixes
mechanism are regarded as being a safety hazard. This arises with the oil. As the carbon is conductive, the oil must be
under conditions of closing the CB when a fault exists on the changed after a prescribed number of fault clearances, when
circuit being controlled. During the close-trip operation, there the degree of contamination reaches an unacceptable level.
is a danger of egress of the arc from the casing of the CB, with Because of the fire risk involved with oil, precautions such as
a consequent risk of injury to the operator. Such types may be the construction of fire/blast walls may have to be taken when
required to be replaced with modern equivalents. OCBs are installed.
ACBs are normally fitted with integral overcurrent protection,
thus avoiding the need for separate protection devices. 18.5.5 Vacuum Circuit Breakers (VCBs)
However, the operating time characteristics of the integral In recent years, this type of circuit breaker, along with CBs
protection are often designed to make discrimination with using SF6, has replaced OCBs for new installations in
MCBs/MCCBs/fuses easier and so they may not be in industrial/commercial systems at voltages of 3.3kV and above.
accordance with the standard dependent time characteristics
Compared with oil circuit breakers, vacuum breakers have no
given in IEC 60255-3. Therefore, problems in co-ordination
fire risk and they have high reliability with long maintenance
with discrete protection relays may still arise, but modern
free periods. A variation is the vacuum contactor with HRC
numerical relays have more flexible characteristics to alleviate
fuses, used in HV motor starter applications.
such difficulties. ACBs will also have facilities for accepting an
external trip signal, and this can be used in conjunction with
an external relay if desired. Figure 18.6 shows the typical
18.5.6 SF6 Circuit Breakers
tripping characteristics available. In some countries, circuit breakers using SF6 gas as the arc-
quenching medium are preferred to VCBs as the replacement
1000 for air- and oil-insulated CBs. Some modern types of
Inverse
switchgear cubicles enable the use of either VCBs or SF6-
Very Inverse insulated CBs according to customer requirements. Ratings of
100
Ultra Inverse up to 31.5kA r.m.s. fault break at 36kV and 40kA at 24kV are
Short Circuit typical. SF6-insulated CBs also have advantages of reliability
10 and maintenance intervals compared to air- or oil-insulated
Time (s)
CBs and are of similar size to VCBs for the same rating.
1
18.6 PROTECTION RELAYS
When the circuit breaker itself does not have integral
0.1
protection, then a suitable external relay will have to be
provided. For an industrial system, the most common
0.01 protection relays are time-delayed overcurrent and earth fault
1 10 20 relays. Chapter 9 provides details of the application of
Current (multiple of setting) overcurrent relays.
Figure 18.6: Typical tripping characteristics of an ACB
18-6
Chapter 18 ⋅ Industrial and Commercial Power System Protection
Residual
CT Phase current System Type of
connections elements Notes
elements fault
A B C
A B C
(i) Ph.-Ph.
(b) 3Ph. 3w
(ii) Ph.–E* * Earth fault protection only if
earth fault current is not less
(i) Ph. - Ph. than twice primary operating
(ii) Ph. – E current
(c) 3Ph. 4w
(iii) Ph. - N
A B C
A B C
(i) Ph. - Ph. Earth fault settings may
(e) 3Ph. 3w
(ii) Ph. – E be less than full load
A B C N
A B C N
18-7
Protection & Automation Application Guide
Traditionally, for three wire systems, overcurrent relays have core balance type CT generally enables more sensitive settings
often been applied to two phases only for relay element to be obtained without the risk of nuisance tripping with
economy. Even up until the last generation of static relays, residually connected phase CTs. When this method is applied
economy was still a consideration in terms of the number of to a four-wire system, it is essential that both the phase and
analogue current inputs that were provided. Two overcurrent neutral conductors are passed through the core balance CT
elements can be used to detect any interphase fault, so it was aperture. For a 3-wire system, care must be taken with the
conventional to apply two elements on the same phases at all arrangement of the cable sheath, otherwise cable faults
relay locations. The phase CT residual current connections for involving the sheath may not result in relay operation (Figure
an earth fault relay element are unaffected by such a 18.8).
convention. Figure 18.7 shows the possible relay connections
Cable gland
and limitations on settings.
Cable box
18.7 CO-ORDINATION PROBLEMS
There are a number of problems that commonly occur in
industrial and commercial networks that are covered in the Cable gland /sheath I >
ground connection
following sections.
When an earth fault relay is driven from residually connected 18.7.2 Four-Wire Dual-Fed Substations
CTs, the relay current and time settings must be such that that
The co-ordination of earth fault relays protecting four-wire
the protection will be stable during the passage of transient CT
systems requires special consideration in the case of low
spill current through the relay. Such spill current can flow in
voltage, dual-fed installations. Horcher [18.1] has suggested
the event of transient, asymmetric CT saturation during the
various methods of achieving optimum co-ordination.
passage of offset fault current, inrush current or motor starting
Problems in achieving optimum protection for common
current. The risk of such nuisance tripping is greater with the
configurations are described below.
deployment of low impedance electronic relays rather than
electromechanical earth fault relays which presented
significant relay circuit impedance. Energising a relay from a
18-8
Chapter 18 ⋅ Industrial and Commercial Power System Protection
18.7.2.1 Use of 3-pole CBs substation with both incoming supply breakers and bus section
When both neutrals are earthed at the transformers and all breaker closed.
circuit breakers are of the 3-pole type, the neutral busbar in
the switchgear creates a double neutral to earth connection, as
shown in Figure 18.9. In the event of an uncleared feeder
earth fault or busbar earth fault, with both the incoming supply
breakers closed and the bus section breaker open, the earth
fault current will divide between the two earth connections.
I > I >
Earth fault relay RE2 may operate, tripping the supply to the
RS1 RS2
healthy section of the switchboard as well as relay RE1 tripping
the supply to the faulted section. I >
Supply 1 Supply 2
RE
F1
IF/2 IF/2
RE1 RE2
IF I >
IF/2 F2
RF
Supply 1 Supply 2
IF/2 Neutral busbar Figure 18.10: Dual fed four-wire systems: use of single point neutral
earthing
Bus section CB When the substation is operated with the bus section switch
closed and either one or both of the incoming supply breakers
closed, it is possible for unbalanced neutral busbar load current
IF caused by single phase loading to operate relay RS1 and/or RS2
and inadvertently trip the incoming breaker. Interlocking the
Figure 18.9: Dual fed four-wire systems: use of 3-pole CBs trip circuit of each RS relay with normally closed auxiliary
contacts on the bus section breaker can prevent this.
If only one incoming supply breaker is closed, the earth fault
relay on the energised side will see only a proportion of the However, should an earth fault occur on one side of the busbar
fault current flowing in the neutral busbar. This not only when relays RS are already operated, it is possible for a contact
significantly increases the relay operating time but also reduces race to occur. When the bus section breaker opens, its break
its sensitivity to low-level earth faults. contact may close before the RS relay trip contact on the
healthy side can open (reset). Raising the pick-up level of
The solution to this problem is to utilise 4-pole CBs that switch
relays RS1 and RS2 above the maximum unbalanced neutral
the neutral as well as the three phases. Then there is only a
current may prevent the tripping of both supply breakers in this
single earth fault path and relay operation is not compromised.
case. However, the best solution is to use 4-pole circuit
18.7.2.2 Use of single earth electrode breakers, and independently earth both sides of the busbar.
A configuration sometimes adopted with four-wire dual-fed If, during a busbar earth fault or uncleared feeder earth fault,
substations where only a 3-pole bus section CB is used is to the bus section breaker fails to open when required, the
use a single earth electrode connected to the mid-point of the interlocking break auxiliary contact will also be inoperative.
neutral busbar in the switchgear, as shown in Figure 18.10. This will prevent relays RS1 and RS2 from operating and
When operating with both incoming main circuit breakers and providing back-up protection, with the result that the fault
the bus section breaker closed, the bus section breaker must must be cleared eventually by slower phase overcurrent relays.
be opened first should an earth fault occur, in order to achieve An alternative method of obtaining back-up protection could
discrimination. The co-ordination time between the earth fault be to connect a second relay RE, in series with relay RE, having
relays RF and RE should be established at fault level F2 for a an operation time set longer than that of relays RS1 and RS2.
But since the additional relay must be arranged to trip both of
18-9
Protection & Automation Application Guide
the incoming supply breakers, back-up protection would be rare cases, it may have to be taken into consideration for
obtained but busbar selectivity would be lost. correct time grading for through-fault protection
considerations, and in the calculation of peak voltage for high-
An example of protection of a typical dual-fed switchboard is
impedance differential protection schemes.
given in Section 18.12.3.
It is more important to take motor contribution into account
18.8 FAULT CURRENT CONTRIBUTION FROM when considering the fault rating of equipment (busbars,
INDUCTION MOTORS cables, switchgear, etc.). In general, the initial a.c. component
of current from a motor at the instant of fault is of similar
When an industrial system contains motor loads, the motors
magnitude to the direct-on-line starting current of the motor.
will contribute fault current for a short time. They contribute
For LV motors, 5xFLC is often assumed as the typical fault
to the total fault current via the following mechanism.
current contribution (after taking into account the effect of
When an induction motor is running, a flux, generated by the motor cable impedance), with 5.5xFLC for HV motors, unless
stator winding, rotates at synchronous speed and interacts it is known that low starting current HV motors are used. It is
with the rotor. If a large reduction in the stator voltage occurs also accepted that similar motors connected to a busbar can
for any reason, the flux in the motor cannot change be lumped together as one equivalent motor. In doing so,
instantaneously and the mechanical inertia of the machine will motor rated speed may need to be taken into consideration, as
tend to inhibit speed reduction over the first few cycles of fault 2 or 4 pole motors have a longer fault current decay than
duration. The trapped flux in the rotor generates a stator motors with a greater number of poles. The kVA rating of the
voltage equal initially to the back e.m.f. induced in the stator single equivalent motor is taken as the sum of the kVA ratings
before the fault and decaying according to the X/R ratio of the of the individual motors considered. It is still possible for
associated flux and current paths. The induction motor motor contribution to be neglected in cases where the motor
therefore acts as a generator resulting in a contribution of load on a busbar is small in comparison to the total load
current having both a.c. and d.c. components decaying (again IEC 60909 provides guidance in this respect).
exponentially. Typical 50Hz motor a.c. time constants lie in However, large LV motor loads and all HV motors should be
the range 10ms-60ms for LV motors and 60-200ms for HV considered when calculating fault levels.
motors. This motor contribution has often been neglected in
the calculation of fault levels. 18.9 AUTOMATIC CHANGEOVER SYSTEMS
Industrial systems usually contain a large component of motor Induction motors are often used to drive critical loads. In
load, so this approach is incorrect. The contribution from some industrial applications, such as those involving the
motors to the total fault current may well be a significant pumping of fluids and gases, this has led to the need for a
fraction of the total in systems having a large component of power supply control scheme in which motor and other loads
motor load. Standards relating to fault level calculations, such are transferred automatically on loss of the normal supply to
as IEC 60909, require the effect of motor contribution to be an alternative supply. A quick changeover, enabling the motor
included where appropriate. They detail the conditions under load to be re-accelerated, reduces the possibility of a process
which this should be done, and the calculation method to be trip occurring. Such schemes are commonly applied for large
used. Guidance is provided on typical motor fault current generating units to transfer unit loads from the unit
contribution for both HV and LV motors if the required data is transformer to the station supply/start-up transformer.
not known. Therefore, it is now relatively easy, using
When the normal supply fails, induction motors that remain
appropriate calculation software, to determine the magnitude
connected to the busbar slow down and the trapped rotor flux
and duration of the motor contribution, so enabling a more
generates a residual voltage that decays exponentially. All
accurate assessment of the fault level for:
motors connected to a busbar will tend to decelerate at the
• discrimination in relay co-ordination same rate when the supply is lost if they remain connected to
• determination of the required switchgear/busbar fault the busbar. This is because the motors will exchange energy
rating between themselves, so that they tend to stay ‘synchronised’
to each other. As a result, the residual voltages of all the
For protection calculations, motor fault level contribution is not motors decay at nearly the same rate. The magnitude of this
an issue that is generally important. In industrial networks, voltage and its phase displacement with respect to the healthy
fault clearance time is often assumed to occur at 5 cycles after alternative supply voltage is a function of time and the speed
fault occurrence, and at this time, the motor fault level of the motors. The angular displacement between the residual
contribution is much less than just after fault occurrence. In motor voltage and the incoming voltage will be 180° at some
18-10
Chapter 18 ⋅ Industrial and Commercial Power System Protection
instant. If the healthy alternative supply is switched on to Figure 18.11(b) shows the residual voltage method, which is
motors which are running down under these conditions, very more common, especially in the petrochemical industry.
high inrush currents may result, producing stresses which
Two feeders are used, supplying two busbar sections
could be of sufficient magnitude to cause mechanical damage,
connected by a normally open bus section breaker. Each
as well as a severe dip in the alternative supply voltage.
feeder is capable of carrying the total busbar load. Each bus
Two methods of automatic transfer are used: section voltage is monitored and loss of supply on either
section causes the relevant incomer CB to open. Provided
• in-phase transfer system
there are no protection operations to indicate the presence of a
• residual voltage system busbar fault, the bus section breaker is closed automatically to
The in-phase transfer method is shown in Figure 18.11(a). restore the supply to the unpowered section of busbar after the
Normal and standby feeders from the same power source are residual voltage generated by the motors running down on
used. that section has fallen to a an acceptable level. This is
between 25% and 40%, of nominal voltage, dependent on the
Phase angle measurement is used to sense the relative phase characteristics of the power system. The choice of residual
angle between the standby feeder voltage and the motor voltage setting will influence the re-acceleration current after
busbar voltage. When the voltages are approximately in the bus section breaker closes. For example, a setting of 25%
phase, or just prior to this condition through prediction, a high- may be expected to result in an inrush current of around 125%
speed circuit breaker is used to complete the transfer. This of the starting current at full voltage. Alternatively, a time
method is restricted to large high inertia drives where the delay could be used as a substitute for residual voltage
gradual run down characteristic upon loss of normal feeder measurement, which would be set with knowledge of the plant
supply can be predicted accurately. to ensure that the residual voltage would have decayed
Preferred Standby sufficiently before transfer is initiated.
feeder feeder
The protection relay settings for the switchboard must take
account of the total load current and the voltage dip during the
re-acceleration period in order to avoid spurious tripping
during this time. This time can be several seconds where large
Phase inertia HV drives are involved.
High speed
angle ϕ<
relay CB
18.10 VOLTAGE AND PHASE REVERSAL
PROTECTION
Voltage relays have been widely used in industrial power
supply systems. The principle purposes are to detect
M
(a) In phase transfer method undervoltage and/or overvoltage conditions at switchboards to
disconnect supplies before damage can be caused from these
conditions or to provide interlocking checks. Prolonged
Feeder Feeder
No.1 No.2 overvoltage may cause damage to voltage-sensitive equipment
(e.g. electronics), while undervoltage may cause excessive
current to be drawn by motor loads. Motors are provided with
thermal overload protection to prevent damage with excessive
current, but undervoltage protection is commonly applied to
disconnect motors after a prolonged voltage dip. With a
Ursd < Ursd <
voltage dip caused by a source system fault, a group of motors
could decelerate to such a degree that their aggregate re-
acceleration currents might keep the recovery voltage
depressed to a level where the machines might stall. Modern
M M M M numerical motor protection relays typically incorporate voltage
protection functions, thus removing the need for discrete
(b) Residual voltage method undervoltage relays for this purpose (see Chapter 19). Older
Figure 18.11: Auto-transfer systems installations may still utilise discrete undervoltage relays, but
the setting criteria remain the same.
18-11
Protection & Automation Application Guide
Capacitor kVAr
rotation in the opposite direction to that intended. Incorrect
rotation due to reverse phase sequence might be set up
following some error after power system maintenance or
repairs, e.g. to a supply cable. Older motor control boards
might have been fitted with discrete relays to detect this
condition. Modern motor protection relays may incorporate kW V
this function. If reverse phase sequence is detected, motor ϕ2
ϕ1
starting can be blocked. If reverse phase sequence voltage kVA2 lo
a
with co d current
protection is not provided, the high-set negative phase kV mpens
A ation
Magnetising kVAr
1 l
sequence current protection in the relay would quickly detect o
Compensating kVAr
co ad
m cu
the condition once the starting device is closed – but initial pe rr
ns en
at t w
reverse rotation of the motor could not be prevented. ion ith
ou
t
Shunt capacitors are often used to improve power factor. The A spreadsheet can easily be constructed to calculate the
basis for compensation is shown in Figure 18.12, where <φ1 required amount of compensation to achieve a desired power
represents the uncorrected power factor angle and <φ2 the factor.
angle relating to the desired power factor, after correction.
18.11.1 Capacitor Control
Where the plant load or the plant power factor varies
considerably, it is necessary to control the power factor
correction, since over-correction will result in excessive system
voltage and unnecessary losses. In a few industrial systems,
capacitors are switched in manually when required, but
automatic controllers are standard practice. A controller
provides automatic power factor correction, by comparing the
running power factor with the target value. Based on the
available groupings, an appropriate amount of capacitance is
switched in or out to maintain an optimum average power
factor. The controller is fitted with a ‘loss of voltage’ relay
element to ensure that all selected capacitors are disconnected
18-12
Chapter 18 ⋅ Industrial and Commercial Power System Protection
instantaneously if there is a supply voltage interruption. When Protection equipment is required to prevent rupture of the
the supply voltage is restored, the capacitors are reconnected capacitor due to an internal fault and also to protect the cables
progressively as the plant starts up. To ensure that capacitor and associated equipment from damage in case of a capacitor
groups degrade at roughly the same rate, the controller usually failure. If fuse protection is contemplated for a three-phase
rotates selection or randomly selects groups of the same size in capacitor, HRC fuses should be employed with a current rating
order to even out the connected time. The provision of of not less than 1.5 times the rated capacitor current.
overvoltage protection to trip the capacitor bank is also
Medium voltage capacitor banks can be protected by the
desirable in some applications. This would be to prevent a
scheme shown in Figure 18.14. Since harmonics increase
severe system overvoltage if the power factor correction (PFC)
capacitor current, the relay will respond more correctly if it
controller fails to take fast corrective action.
does not have in-built tuning for harmonic rejection.
The design of PFC installations must recognise that many
Double star capacitor banks are employed at medium voltage.
industrial loads generate harmonic voltages, with the result
As shown in Figure 18.13, a current transformer in the inter
that the PFC capacitors may sink significant harmonic
star-point connection can be used to drive a protection relay to
currents. A harmonic study may be necessary to determine
detect the out-of-balance currents that will flow when
the capacitor thermal ratings or whether series filters are
capacitor elements become short-circuited or open-circuited.
required.
The relay will have adjustable current settings, and it might
contain a bias circuit, fed from an external voltage transformer,
18.11.2 Motor P.F. Correction
that can be adjusted to compensate for steady-state spill
When dealing with power factor correction of motor loads, current in the inter star-point connection.
group correction is not always the most economical method.
A
Some industrial consumers apply capacitors to selected motor
substations rather than applying all of the correction at the B
18.11.3 Capacitor Protection Another high voltage capacitor configuration is the ‘split phase’
arrangement where the elements making up each phase of the
When considering protection for capacitors, allowance should
capacitor are split into two parallel paths. Figure 18.15 shows
be made for the transient inrush current occurring on switch-
two possible connection methods for the relay. A differential
on, since this can reach peak values of around 20 times
relay can be applied with a current transformer for each
normal current. Switchgear for use with capacitors is usually
parallel branch. The relay compares the current in the split
de-rated considerably to allow for this. Inrush currents may be
phases, using sensitive current settings but also adjustable
limited by a resistor in series with each capacitor or bank of
compensation for the unbalance currents arising from initial
capacitors.
capacitor mismatch.
18-13
Protection & Automation Application Guide
18-14
Chapter 18 ⋅ Industrial and Commercial Power System Protection
18.12 EXAMPLES
A
In this section, examples of the topics dealt with in this
Chapter are considered.
I>
18.12.1 Fuse Co-ordination
An example of the application of fuses is based on the
arrangement in Figure 18.16(a). This shows an unsatisfactory
B
scheme with commonly encountered shortcomings. It can be
seen that fuses B, C and D will discriminate with fuse A, but
the 400A sub-circuit fuse E may not discriminate, with the
I> 500A sub-circuit fuse D at higher levels of fault current.
Rating
1000A A
C
Rating
Rating
Alarm Trip 400A
E 30A
each
(a)
Rating
1000A A
I>
I> Rating
30A
C F
(b) Correct layout and discrimination
Figure 18.16: Fuse protection: effect of layout on discrimination
I> The solution, shown in Figure 18.16(b), is to feed the 400A
circuit E direct from the busbars. The sub-circuit fuse D may
now have its rating reduced from 500A to a value, of say
100A, appropriate to the remaining sub-circuit. This
Alarm Trip arrangement now provides a discriminating fuse distribution
scheme satisfactory for an industrial system.
(b)
Figure 18.15: Differential protection of split phase capacitor banks However, there are industrial applications where
18-15
Protection & Automation Application Guide
kVA
Auxiliary FLC =
Circuits kV × 3
Figure 18.17: Example of back-up protection 1000
=
The major fuse of 800A is chosen, as the minimum rating that 0.4 × 3
is greater than the total load current on the switchboard. = 1443 A
Discrimination between the two fuses is not obtained, as the
pre-arcing I2t of the 800A fuse is less than the total I2t of the With the CT ratio of 2000/1A and a relay reset ratio of 95% of
the nominal current setting, a current setting of at least 80%
630A fuse. Therefore, the major fuse will blow as well as the
would be satisfactory, to avoid tripping and/or failure to reset
minor one, for most faults so that all other loads fed from the
with the transformer carrying full load current. However, choice
switchboard will be lost. This may be acceptable in some
of a value at the lower end of this current setting range would
cases. In most cases, however, loss of the complete
move the relay characteristic towards that of the MCCB and
switchboard for a fault on a single outgoing circuit will not be
discrimination may be lost at low fault currents. It is therefore
acceptable, and the design will have to be revised.
prudent to select initially a relay current setting of 100%.
18.12.2 Grading of Fuses/MCCBs/Overcurrent Relays
18.12.2.2 Relay characteristic and time multiplier selection
An example of an application involving a moulded case circuit
An EI characteristic is selected for the relay to ensure
breaker, fuse and a protection relay is shown in Figure 18.18.
discrimination with the fuse (see Chapter 9 for details). From
A 1MVA 3.3kV/400V transformer feeds the LV board via a
Figure 18.19, it may be seen that at the fault level of 40kA the
circuit breaker, which is equipped with an Alstom MiCOM
fuse will operate in less than 0.01s and the MCCB operates in
P14x numerical relay having a setting range of 8-400% of
approximately 0.014s. Using a fixed grading margin of 0.4s,
rated current and fed from 2000/1A CTs.
the required relay operating time becomes 0.4 + 0.014 =
0.414s. With a CT ratio of 2000/1A, a relay current setting of
100%, and a relay TMS setting of 1.0, the extremely inverse
curve gives a relay operating time of 0.2s at a fault current of
40kA. This is too fast to give adequate discrimination and
indicates that the EI curve is too severe for this application.
Turning to the VI relay characteristic, the relay operation time
is found to be 0.71s at a TMS of 1.0. To obtain the required
relay operating time of 0.414s:
18-16
Chapter 18 ⋅ Industrial and Commercial Power System Protection
operate in 8.1s, which does not give discrimination with the Trip Trip
2500/1 NO
MCCB. A relay operation time of 8.3s is required. To A1 A2 0.4kV
50kA rms
overcome this, the relay characteristic needs to be moved
away from the MCCB characteristic, a change that may be I>> Trip
I>
achieved by using a TMS of 0.625. The revised relay
characteristic is also shown in Figure 18.19. Relay B
I>>
300/1 Relay A
10.0
Motor cable
M
160kW
Characteristic for relay
Figure 18.20: Relay grading example for dual-fed switchboard
18-17
Protection & Automation Application Guide
18.12.3.2 Motor protection relay settings acceleration did not need to be considered.
From the motor characteristics given, the overcurrent relay The high-set setting needs to be above the full load current
settings (Relay A) can be found using the guidelines set out in and motor starting/re-acceleration transient current, but less
Chapter 19 as: than the fault current by a suitable margin. A setting of
Thermal element: 12.5kA is initially selected. A time delay of 0.3s has to used to
ensure grading with relay A at high fault current levels; both
• current setting: 300A relays A and B may see a current in excess of 25kA for faults
• time constant: 20 mins on the cable side of the CB feeding the 160kW motor. The
relay curves are shown in Figure 18.21.
Instantaneous element:
Relay A
• current setting: 2.32kA
Relay B
These are the only settings relevant to the upstream relays. Re-acceleration
Relay A setting
Relay B setting
18.12.3.3 Relay B settings 1000
Relay B settings are derived from consideration of the loading
and fault levels with the bus-section breaker between busbars 100
A1 and A2 closed. No information is given about the load split
between the two busbars, but it can be assumed in the 10
starting/re-acceleration currents. If the entire load on the 100 1000 10000 100000
busbar was motor load, an aggregate starting current in excess Current (A) referred to 0.4kV
of 13kA would occur, but a current setting of this order would Figure 18.21: Grading of relays A and B
be excessively high and lead to grading problems further
upstream. It is unlikely that the entire load is motor load 18.12.3.4 Relays C settings
(though this does occur, especially where a supply voltage of
The setting of the IDMT element of relays C1 and C2 has to be
690V is chosen for motors – an increasingly common practice)
suitable for protecting the busbar while grading with relay B.
or that all motors are started simultaneously (but simultaneous
The limiting condition is grading with relay B, as this gives the
re-acceleration may well occur). What is essential is that relay
longest operation time for relays C.
B does not issue a trip command under these circumstances –
i.e. the relay current/time characteristic is in excess of the The current setting has to be above that for relay B to achieve
current/time characteristic of the worst-case starting/re- full co-ordination, and a value of 3250A is suitable. The TMS
acceleration condition. It is therefore assumed that 50% of the setting using the SI characteristic is chosen to grade with that
total bus load is motor load, with an average starting current of relay B at a current of 12.5kA (relay B instantaneous
of 600% of full load current (= 6930A), and that re-acceleration setting), and is found to be 0.45. The high-set element must
takes 3s. A current setting of 3000A is therefore initially used. grade with that of relay B, so a time delay of 0.62sec is
The SI characteristic is used for grading the relay, as co- required. The current setting must be higher than that of relay
ordination with fuses is not required. The TMS is required to B, so use a value of 15kA. The final relay grading curves and
be set to grade with the thermal protection of relay A under settings are shown in Figure 18.22.
‘cold’ conditions, as this gives the longest operation time of
Relay A, and the re-acceleration conditions. A TMS value of
0.41 is found to provide satisfactory grading, being dictated by
the motor starting/re-acceleration transient. Adjustment of
both current and TMS settings may be required depending on
the exact re-acceleration conditions. Note that lower current
and TMS settings could be used if motor starting/re-
18-18
Chapter 18 ⋅ Industrial and Commercial Power System Protection
1000
100
10
Time (s)
18-19
AC MOTOR PROTECTION
Chapter 19
AC MOTOR PROTECTION
GEGridSolutions.com 19-1
Protection & Automation Application Guide
The variety of motor designs, diverse applications, variety of K = negative sequence rotor resistance / positive sequence
possible abnormal operating conditions and resulting modes of rotor resistance at rated speed.
failure result in a complex thermal relationship. A generic A typical value of K is 3.
mathematical model that is accurate is therefore impossible to
Finally, the thermal replica model needs to take into account
create. However, it is possible to develop an approximate
the fact that the motor will tend to cool down during periods of
model if it is assumed that the motor is a homogeneous body,
light load, and the initial state of the motor. The motor will
creating and dissipating heat at a rate proportional to
have a cooling time constant, τ r , that defines the rate of
temperature rise. This is the principle behind the ‘thermal
replica’ model of a motor used for overload protection. cooling. Hence, the final thermal model can be expressed as:
19-2
Chapter 19 ⋅ AC Motor Protection
t = Te1 log e
(K − A )
2 2 100 000
(K − 1)
2
Equation 19.1
10 000
where: Te1 = Te2 = 60min
motor windings carry full line current, while in the ‘run’ Thermal equivalent current Ieq in terms of the
condition, they carry only 57% of the current seen by the relay. current thermal threshold Iq>
Similarly, when the motor is disconnected from the supply, the Figure 19.1: Thermal overload characteristic curves from cold – initial
heating time constant Te1 is set equal to the cooling time thermal state 0%
19-3
Protection & Automation Application Guide
the stall withstand time can be less than the starting time. In 100
Time (s)
• mechanical problems
• low supply voltage
• excessive load torque
1
A large current will be drawn from the supply, and cause
extremely high temperatures to be generated within the motor.
This is made worse by the fact that the motor is not rotating,
and hence no cooling due to rotation is available. Winding
damage will occur very quickly – either to the stator or rotor
windings depending on the thermal limitations of the 0.1
particular design (motors are said to be stator or rotor limited 0.1 1 10
Current (p.u.)
in this respect). The method of protection varies depending on
whether the starting time is less than or greater than the safe Figure 19.2: Relay setting for successful start: start time<stall time
stall time. In both cases, initiation of the start may be sensed
19.4.1.2 Start time ≥ safe stall time
by detection of the closure of the switch in the motor feeder
(contactor or CB) and optionally current rising above a starting For this condition, a definite time overcurrent characteristic by
current threshold value – typically 200% of motor rated itself is not sufficient, since the time delay required is longer
current. For the case of both conditions being sensed, they than the maximum time that the motor can be allowed to
may have to occur within a narrow aperture of time for a start carry starting current safely. An additional means of detection
to be recognised. of rotor movement, indicating a safe start, is required. A
speed-sensing switch usually provides this function. Detection
Special requirements may exist for certain types of motors of a successful start is used to select the relay timer used for
installed in hazardous areas (e.g. motors with type of the safe run-up time of the motor. This time can be longer
protection EEx ‘e’) and the setting of the relay must take these than the safe stall time, as there is both a (small) decrease in
into account. Sometimes a permissive interlock for machine current drawn by the motor during the start and the rotor fans
pressurisation (on EEx ‘p’ machines) may be required, and this begin to improve cooling of the machine as it accelerates. If a
can be conveniently achieved by use of a relay digital input and start is sensed by the relay through monitoring current and/or
the in-built logic capabilities. start device closure, but the speed switch does not operate, the
relay element uses the safe stall time setting to trip the motor
19.4.1.1 Start time < safe stall time before damage can occur. Figure 19.3(a) illustrates the
Protection is achieved by use of a definite time overcurrent principle of operation for a successful start, and Figure 19.3(b)
characteristic, the current setting being greater than full load for an unsuccessful start.
current but less than the starting current of the machine. The
time setting should be a little longer than the start time, but
less than the permitted safe starting time of the motor. Figure
19.2 illustrates the principle of operation for a successful start.
19-4
Chapter 19 ⋅ AC Motor Protection
19-5
Protection & Automation Application Guide
In this example, the maximum number of starts within the phase, etc.) or the cause (cyclic overheating, etc.), the
Supervising Time has been reached, therefore the Inhibit Start presence of the surrounding metallic frame and casing will
Time is initiated. The remaining time is greater than the ensure that it rapidly develops into a fault involving earth.
Inhibit Start Time, so the start inhibition remains for a duration Therefore, provision of earth fault protection is very important.
equal to the supervising time minus the tn. The type and sensitivity of protection provided depends largely
on the system earthing, so the various types will be dealt with
19.5 SHORT-CIRCUIT PROTECTION in turn. It is common, however, to provide both instantaneous
Motor short-circuit protection is often provided to cater for and time-delayed relay elements to cater for major and slowly
major stator winding faults and terminal flashovers. Because developing faults.
of the relatively greater amount of insulation between phase
windings, faults between phases seldom occur. As the stator 19.6.1 Solidly-Earthed System
windings are completely enclosed in grounded metal the fault Most LV systems fall into this category, for reasons of
would very quickly involve earth, which would then operate the personnel safety. Two types of earth fault protection are
instantaneous earth fault protection. A single definite time commonly found – depending on the sensitivity required.
overcurrent relay element is all that is required for this
For applications where a sensitivity of > 20% of motor
purpose, set to about 125% of motor starting current. The time
continuous rated current is acceptable, conventional earth
delay is required to prevent spurious operation due to CT spill
fault protection using the residual CT connection of Figure
currents, and is typically set at 100ms. If the motor is fed from
19.5 can be used. A lower limit is imposed on the setting by
a fused contactor, co-ordination is required with the fuse, and
possible load unbalance and/or (for HV systems) system
this will probably involve use of a long time delay for the relay
capacitive currents.
element. Since the object of the protection is to provide rapid
fault clearance to minimise damage caused by the fault, the Upstream
application of differential protection, refer to Chapter 10. Figure 19.5: Residual CT connection for earth fault protection
However, non-directional earth fault overcurrent protection
Care must be taken to ensure that the relay does not operate
will normally be cheaper in cases where adequate sensitivity
from the spill current resulting from unequal CT saturation
can be provided.
during motor starting, where the high currents involved will
almost certainly saturate the motor CT’s. It is common to use
19.6 EARTH FAULT PROTECTION a stabilising resistor in series with the relay, with the value
One of the most common faults to occur on a motor is a stator being calculated using the formula:
winding fault. Whatever the initial form of the fault (phase-
19-6
Chapter 19 ⋅ AC Motor Protection
I st
Rstab = (Rct + kRl + Rr )
I0 Contact
breaking
Equation 19.2 capacity
Fuse
where:
Time
I st = starting current referred to CT secondary
19-7
Protection & Automation Application Guide
19-8
Chapter 19 ⋅ AC Motor Protection
S R F 0.5
E
R1 p + R2 p
2
( )
ZS ZL
2
N ∼ = + X 1 p + X 2' p
ZE
(2 − s )
A-G
S VA-G
S
R VA-G
S
R
[(
= R1 p + R2' p ) + (X
2
1p + X 2' p )]
2 0.5
19-9
Protection & Automation Application Guide
reactance at standstill. An alternative more meaningful way of 19.8 FAULTS IN ROTOR WINDINGS
expressing this is: On wound rotor machines, some degree of protection against
positive seq. impedance starting current faults in the rotor winding can be given by an instantaneous
= stator current overcurrent relay element. As the starting
negative seq. impedance rated current
current is normally limited by resistance to a maximum of
A typical LV motor starting current is 6 x full load current twice full load, the instantaneous unit can safely be set to
(FLC). Therefore, a 5% negative sequence voltage (due to, say, about three times full load if a slight time delay of
unbalanced loads on the system) would produce a 30% approximately 30 milliseconds is incorporated. It should be
negative sequence current in the machine, leading to excessive noted that faults occurring in the rotor winding would not be
heating. For the same motor, negative sequence voltages in detected by any differential protection applied to the stator.
excess of 17% will result in a negative sequence current larger
than rated full load current. 19.9 RTD TEMPERATURE DETECTION
Negative sequence current is at twice supply frequency. Skin RTDs are used to measure temperatures of motor windings or
effect in the rotor means that the heating effect in the rotor of shaft bearings. A rise in temperature may denote overloading
a given negative sequence current is larger than the same of the machine, or the beginning of a fault in the affected part.
positive sequence current. Thus, negative sequence current A motor protection relay will therefore usually have the
may result in rapid heating of the motor. Larger motors are capability of accepting a number of RTD inputs and internal
more susceptible in this respect, as the rotor resistance of such logic to initiate an alarm and/or trip when the temperature
machines tends to be higher. Protection against negative exceeds the appropriate setpoint(s). Occasionally, HV motors
sequence currents is therefore essential. are fed via a unit transformer, and in these circumstances,
some of the motor protection relay RTD inputs may be
Modern motor protection relays have a negative sequence assigned to the transformer winding temperature RTDs, thus
current measurement capability, in order to provide such providing overtemperature protection for the transformer
protection. The level of negative sequence unbalance depends without the use of a separate relay.
largely upon the type of fault. For loss of a single phase at
start, the negative sequence current will be 50% of the normal 19.10 BEARING FAILURES
starting current. It is more difficult to provide an estimate of
the negative sequence current if loss of a phase occurs while There are two types of bearings to be considered: the anti-
running. This is because the impact on the motor may vary friction bearing (ball or roller), used mainly on small motors
widely, from increased heating to stalling due to the reduced (up to around 350kW), and the sleeve bearing, used mainly on
torque available. large motors.
A typical setting for negative sequence current protection must The failure of ball or roller bearings usually occurs very quickly,
take into account the fact that the motor circuit protected by causing the motor to come to a standstill as pieces of the
the relay may not be the source of the negative sequence damaged roller get entangled with the others. There is
current. Time should be allowed for the appropriate protection therefore very little chance that any relay operating from the
to clear the source of the negative sequence current without input current can detect bearing failures of this type before the
introducing risk of overheating to the motor being considered. bearing is completely destroyed. Therefore, protection is
This indicates a two stage tripping characteristic, similar in limited to disconnecting the stalled motor rapidly to avoid
principle to overcurrent protection. A low-set definite time- consequential damage. Refer to Section 19.4 on stall
delay element can be used to provide an alarm, with an IDMT protection for details of suitable protection.
element used to trip the motor in the case of higher levels of Failure of a sleeve bearing can be detected by means of a rise
negative sequence current, such as loss-of-phase conditions at in bearing temperature. The normal thermal overload relays
start, occurring. Typical settings might be 20% of CT rated cannot give protection to the bearing itself but will operate to
primary current for the definite time element and 50% for the protect the motor from excessive damage. Use of RTD
IDMT element. The IDMT time delay has to be chosen to temperature detection, as noted in Section 19.9, can provide
protect the motor while, if possible, grading with other suitable protection, allowing investigation into the cause of the
negative sequence relays on the system. Some relays may not bearing running hot prior to complete failure.
incorporate two elements, in which case the single element
should be set to protect the motor, with grading being a 19.11 UNDERVOLTAGE PROTECTION
secondary consideration. Motors may stall when subjected to prolonged undervoltage
19-10
Chapter 19 ⋅ AC Motor Protection
conditions. Transient undervoltages will generally allow a motor torque occurs. Other conditions that may cause this
motor to recover when the voltage is restored, unless the condition are a fall in the applied voltage to stator or field
supply is weak. windings. Such a fall may not need to be prolonged, a voltage
dip of a few seconds may be all that is required. An out-of-
Motors fed by contactors have inherent undervoltage
step condition causes the motor to draw excessive current and
protection, unless a latched contactor is used. Where a
generate a pulsating torque. Even if the cause is removed
specific undervoltage trip is required, a definite time
promptly, the motor will probably not recover synchronism, but
undervoltage element is used. If two elements are provided,
eventually stall. Hence, it must be disconnected from the
alarm and trip settings can be used. An interlock with the
supply.
motor starter is required to block relay operation when the
starting device is open, otherwise a start will never be The current drawn during an out-of-step condition is at a very
permitted. The voltage and time delay settings will be system low power factor. Hence a relay element that responds to low
and motor dependent. They must allow for all voltage dips power factor can be used to provide protection. The element
likely to occur on the system during transient faults, starting of must be inhibited during starting, when a similar low power
motors, etc. to avoid spurious trips. As motor starting can factor condition occurs. This can conveniently be achieved by
result in a voltage depression to 80% of nominal, the voltage use of a definite time delay, set to a value slightly in excess of
setting is likely to be below this value. Re-acceleration is the motor start time.
normally possible for voltage dips lasting between 0.5-2
The power factor setting will vary depending on the rated
seconds, depending on system, motor and drive
power factor of the motor. It would typically be 0.1 less than
characteristics, and therefore the time delay will be set bearing
the motor rated power factor i.e. for a motor rated at 0.85
these factors in mind.
power factor, the setting would be 0.75.
19-11
Protection & Automation Application Guide
low-forward-power relay can detect this condition. A time multiple of τ 1 . With a cooling time constant of 75min,
delay will be required to prevent operation during system
τ R = 3 ×τ1 .
transients leading to momentary reverse power flow in the
motor.
19.14.1.2 Short circuit protection
19.14 MOTOR PROTECTION EXAMPLES Following the recommendations of Section 19.5, with a
starting current of 550% of full load current, the short-circuit
This section gives examples of the protection of HV and LV
element is set to 1.25 x 5.5 x 211A = 1450A.
induction motors.
In terms of the relay nominal current In, the setting value is
19.14.1 Protection of a HV Motor 1450
= 5.8 I n
Table 19.2 gives relevant parameters of a HV induction motor 250
to be protected. Using an Alstom MiCOM P241 motor
There is a minimum time delay of 100ms for currents up to
protection relay, the important protection settings are
120% of setting to allow for transient CT saturation during
calculated in the following sections.
starting and 40ms above this current value. These settings are
Quantity Value satisfactory.
Rated output 1000kW CMR
Rated Voltage 3.3kV
19.14.1.3 Earth-fault protection
Rated frequency 50Hz It is assumed that no CBCT is fitted. A typical setting of 30% of
Rated power factor/efficiency 0.9/0.92
motor rated current is used, leading to an earth fault relay
setting of
Stall withstand time cold/hot 20/7 sec
Starting current 550% DOL 211
0.3 × = 0.25I n
Permitted starts cold/hot 3/2 250
CT ratio 250/1
A stabilising resistor is required, calculated in accordance with
Start time at 100% voltage 4 sec
Equation 19.2 to prevent maloperation due to CT spill current
Start time at 80% voltage 5.5 sec
during starting as the CTs may saturate. With the stabilising
Heating/cooling time constant 25/75 mins resistor present, instantaneous tripping is permitted. The
System earthing Solid alternative is to omit the stabilising resistor and use a definite
Control device Circuit Breaker time delay in association with the earth-fault element.
Table 19.2: Example motor data However, the time delay must be found by trial and error
during commissioning.
19.14.1.1 Thermal protection
The current setting ITH is set equal to the motor full load 19.14.1.4 Locked rotor/Excessive start time protection
current, as it is a CMR rated (Continuous Maximum Rated) The current element must be set in excess of the rated current
motor. Motor full load current can be calculated as 211A, of the motor, but well below the starting current of the motor
therefore (in secondary quantities): to ensure that a start condition is recognised (this could also
be achieved by use of an auxiliary contact on the motor CB
211
I TH = = 0.844 wired to the relay). A setting of 500A (2In) is suitable. The
250 associated time delay needs to be set to longer than the start
Use a value of 0.85, nearest available setting. time, but less than the cold stall time. Use a value of 15s.
The relay has a parameter, K, to allow for the increased
19.14.1.5 Stall protection
heating effect of negative sequence currents. In the absence of
any specific information, use K=3. The same current setting as for locked rotor protection can be
used – 500A. The time delay has to be less than the hot stall
Two thermal heating time constants are provided, τ 1 and τ 2 . time of 7s but greater than the start time by a sufficient
τ 2 is used for starting methods other than DOL, otherwise it margin to avoid a spurious trip if the start time happens to be
a little longer than anticipated. Use a value of 6.5s.
is set equal to τ 1 . τ 1 is set to the heating time constant,
hence τ 1 = τ 2 .=25min. Cooling time constant τ R is set as a The protection characteristics for sections 19.14.1.1-5 are
shown in Figure 19.8.
19-12
Chapter 19 ⋅ AC Motor Protection
1 Cold Thermal
Hot Thermal
S/C
Parameter Symbol Value Unit
Locked Rotor
Stall (a) LV motor example
0.1 Start Current (100% V)
Start Current (80% V) Standard IEC 60034
Motor Voltage 400 V
0.01
0.01 1 10
Motor kW 75 kW
Ith/I (p.u.)
Figure 19.9: Protection characteristics for motor protection example Motor kVA 91.45 kVA
Motor FLC 132 A
19.14.1.6 Negative phase sequence protection Starting Current 670 %
Two protection elements are provided, the first is definite time- Starting Time 4.5 sec
delayed to provide an alarm. The second is an IDMT element Contactor rating 300 A
used to trip the motor on high levels of negative sequence Contactor breaking capacity 650 A
current, such as would occur on a loss of phase condition at Fuse rating 250 A
starting. In accordance with Section 19.7, use a setting of 20%
(b) Relay settings
with a time delay of 30s for the definite time element and 50%
Overcurrent Disabled -
with a TMS of 1.0 for the IDMT element. The resulting
Overload setting Ib 4.4 A
characteristic is shown in Figure 19.10. The motor thermal
protection, as it utilises a negative sequence component, is Overload time delay I>t 15 sec
19.14.2.1 CT ratio
Time (sec)
1
The relay is set in secondary quantities, and therefore a
suitable CT ratio has to be calculated. From the relay manual,
a CT with 5A secondary rating and a motor rated current in the
range of 4-6A when referred to the secondary of CT is required.
0.1 Use of a 150/5A CT gives a motor rated current of 4.4A when
10 Current (A) 10000 referred to the CT secondary, so use this CT ratio.
Figure 19.7: Motor protection example- negative sequence protection
characteristic 19.14.2.2 Overcurrent (short-circuit) protection
19.14.1.7 Other protection considerations The fuse provides the motor overcurrent protection, as the
protection relay cannot be allowed to trip the contactor on
If the relay can be supplied with a suitable voltage signal, stall
overcurrent in case the current to be broken exceeds the
protection can be inhibited during re-acceleration after a voltage
contactor breaking capacity. The facility for overcurrent
dip using the undervoltage element (set to 80-85% of rated
protection within the relay is therefore disabled.
voltage). Undervoltage protection (set to approximately 80%
voltage with a time delay of up to several seconds, dependent on
19.14.2.3 Thermal (overload) protection
system characteristics) and reverse phase protection can also be
implemented to provide extra protection. Unless the drive is The motor is an existing one, and no data exists for it except
critical to the process, it is not justifiable to provide a VT specially the standard data provided in the manufacturer's catalogue.
to enable these features to be implemented. This data does not include the thermal (heating) time constant
of the motor.
19-13
Protection & Automation Application Guide
In these circumstances, it is usual to set the thermal protection definite time relay element, a setting of 20% (from Section
so that it lies just above the motor starting current. 19.7) is appropriate, with a time delay of 25s to allow for short
high-level negative sequence transients arising from other
The current setting of the relay, I b , is found using the formula
causes.
In
Ib = 5 × 19.14.2.5 Loss of phase protection
Ip
The relay has a separate element for this protection. Loss of a
Where phase gives rise to large negative sequence currents, and
therefore a much shorter time delay is required. A definite time
I n = motor rated primary current delay of 5s is considered appropriate.
I p = CT primary current The relay settings are summarised in Table 19.3(b).
Hence,
132
Ib = 5 × = 4.4 A
150
With a motor starting current of 670% of nominal, a setting of
the relay thermal time constant with motor initial thermal
state of 50% of 15s is found satisfactory, as shown in Figure
19.11.
250A
Contactor
CT
Relay
Cable
100
Time (sec)
10
Trip time
Start current
1
0 1 2 3 4 5 6 7 8
I/Ib
(b) Relay trip characteristic
Figure 19.81: Motor protection example – contactor-fed motor
19-14
Chapter 19 ⋅ AC Motor Protection
19-15
SYSTEM INTEGRITY
PROTECTION SCHEMES
Chapter 20
SYSTEM INTEGRITY PROTECTION
SCHEMES
20.2 BLACKOUTS
In 1965, 25 million people in parts of the United States and
Canada lost their electricity supply for about 12 hours. The
failure was attributed to a maintenance error and carries the
reputable distinction of being the first large scale blackout. It
is not an isolated event. Leaving aside ‘planned’ disruptions
caused by, for example civil unrest such as the miners’ strike in
the UK in 1974, there are many such events that have caused
disruption that is, at the least inconvenient, generally commer-
cially damaging, and at worst, life-threatening.
In 1978, 80 percent of France was affected by a blackout caused
by the breakdown of a transmission line.
In 1989, a geomagnetic storm caused an outage that left 6
million people in Québec, Canada without power for nine
GEGridSolutions.com 20-1
Protection & Automation Application Guide
In 1999 a major blackout was triggered in Brazil following a include energy management system technology and system
lightning strike. Over 90 million people were affected. integrity protection schemes also known as special protection
schemes, remedial action schemes, or wide area schemes.
In August 2003, a wide-area power collapse in the north of the
United States of America and central Canada affected 50 million Electrical power systems are designed and operated to
people. It is estimated to have cost billions of dollars, and at withstand contingencies that are likely to occur as a result of a
least eleven fatalities were attributed to the loss of power. single event. Such events are sometimes referred to as class 1,
or N-1 type contingencies. For these contingencies protection is
During the miners' strike of 1974, energy and electrical power
likely to be afforded by relays applied to individual items of plant.
systems had been at the forefront of the political agenda in the
UK. The devastation caused by the North American blackout A combination of simultaneous events could be classified as a
put electrical power systems onto the world political agenda. class 2, or N-2 type contingency, and a cascading event as a
Supply of electrical energy had become, to many, no longer a class 3, or N-3 contingency.
luxury, but a basic human need.
For N-2 and N-3 contingencies, system level action is
Large-scale blackouts have continued since that time in required. This could involve generator tripping (possibly on a
countries including Australia, Japan, Peru, Greece, Russia and massive scale), load shedding or, ultimately, coordinated
Italy, but technology is being developed and deployed to help system separation, to preserve system stability and/or prevent
prevent future occurrences. serious damage to transmission and generation equipment.
Scenarios of major blackouts are hardly ever the same. The As well as the N- contingencies, another way of looking at the
starting event may be a generation-load imbalance, a short system operation is by means of the state diagram introduced
circuit, human actions (or inaction), unexpected grid topology by Fink and Carlsen [20.1] as shown in Figure 20.1.
changes, lack of voltage support, or natural causes such as
lightning storms or untrimmed trees. What they all share is a Normal
resulting failure process that cascades.
oscillations and cascading failure, which spreads to wider parts In this model, conventional protection and control is likely to
of the network and, in some cases, the entire grid. be effective in the ‘alert’ and ‘emergency’ states where the
load capacity and generating capacity remain matched. In the
20.1.2 Preserving Supply ‘extreme’ state, they are no longer matched and system
Although rare, these widespread blackouts and their collection integrity protection schemes are required.
of critical consequences on business, public safety (lighting), Remedial actions performed by system integrity protection
public comfort (heating/air conditioning), telecommunications, schemes are the second and third lines in the plan to protect
etc., have driven the industry to develop automatic control the system.
systems to mitigate the occurrence of such large-scale failures
caused by unexpected events. Modern power systems are 20.1.3 Enabling Technologies
designed and equipped to be resistant to this sort of cascading System integrity protection schemes have advanced thanks to
failure. Facilities and tools, which embed such resistance, technological developments, which have been widely adopted
20-2
Chapter 20 ⋅ System Integrity Protection Schemes
by the industry. Three technological developments in be catastrophic and so system integrity protection schemes
particular that have brought great benefit and advances in the must be carefully designed. Four main design criteria
field of measurement, protection, control and automation of applicable to system integrity protection schemes are [20.2]:
electrical power systems are:
• Dependability:– The certainty that the system integrity
• advances in embedded computing protection scheme operates when required, that is, in
all cases where emergency controls are required to
• wide-area communications and
avoid a collapse.
• accurate time synchronisation
• Security:– The certainty that the system integrity
This chapter explores at how these enabling technologies can protection scheme will not operate when not required,
enhance the measurement of power system quantities, i.e. does not apply emergency controls unless they are
enabling wide-area monitoring and control, and ‘bigger necessary to avoid a collapse.
picture’ protection solutions. • Selectivity:– The ability to select the correct and
minimum action to perform the intended function.
20.2 SUMMARY OF SYSTEM INTEGRITY That is, to avoid using disruptive controls such as load
shedding if they are not necessary to avoid a collapse.
PROTECTION SCHEMES
• Robustness:– The ability of the system integrity
System integrity protection schemes (or 'special protection
protection scheme to provide dependability, security
schemes', 'remedial action schemes', and in some cases
and selectivity over the full range of dynamic and
'wide-area schemes'), are tools to protect the system. Unlike
steady state operating conditions that it will encounter.
conventional protection relays where the purpose is to isolate
faulted plant, system integrity protection schemes initiate Conformance to these criteria is critical to the deployment of
actions to correct the system. Typical system stress scenarios system integrity protection schemes.
that a system integrity protection scheme might be required to
Under normal system operation, the measures that a system
act upon include:
integrity protection scheme may initiate will be inactive. They
• transient instability are activated when some system disturbance or stress
• voltage degradation condition occurs.
• frequency degradation In terms of detection principles, system integrity protection
• thermal overloading schemes may be classified in two different categories: event-
• loss of synchronism based and response based. Event-based systems act to detect
• large power swings the cause(s) of a disturbance; Response-based systems
• cascade of overloads respond to the effects. Typically, event based systems will
automatically activate remedial actions and will operate
To implement effective, intelligent system integrity protection
quickly. Response based systems may activate the remedial
schemes appropriate for the prevailing power system condition,
actions either automatically or manually, and longer operating
it is essential that real time system data is made available.
times may apply.
Using this data, a system integrity protection scheme can
System integrity protection schemes may exist in stand-alone
initiate:
devices, using local quantities only to provide fast acting
• generator tripping decisions, or they may take quantities from a wider area of the
• load rejection system. The latter will have longer operating times as it relies
• controlled system separation on the communication of data between source of acquisition
and decision-maker. Additionally, system integrity protection
• voltage clamping
schemes may be made at the highest system level and be part
• modification to the operational state of FACTS devices
of the energy management suite as shown in Figure 20.2.
As with conventional protection the consequences of failing to
operate when required, or operating when not required could
20-3
Protection & Automation Application Guide
Centralised
Energy management
system integrity
protection scheme
20-4
Chapter 20 ⋅ System Integrity Protection Schemes
sometimes termed ‘wide-area protection’, or WAP. System 20.3.1.1 Synchrophasors for Oscillatory Stability
integrity protection schemes based on wide-area technology Synchrophasors can be used for oscillatory stability detection
are essentially control schemes. It is perhaps unwise to try to designed to detect slower inter-area system oscillations. These
differentiate the application of wide-area technology to the are characterised by power oscillations between two areas of
separate fields of monitoring, control, and protection, rather to generation, running at slightly different speeds and following
combine them into a single heading of ‘wide-area monitoring, small system perturbations such as load switching or tap
protection and control’, or WAMPAC. changes. If there is insufficient system damping, these
oscillations do not die away and can escalate leading to
20.3.1 Wide-area Monitoring, Protection and Control
potential out-of-step conditions if no pre-emptive action is
(WAMPAC) System Integrity Protection Schemes
taken. If the phasor measurement units feature frequency
A wide-area scheme to accommodate system integrity tracking that can accurately measure and track small changes
protection could consist of phasor measurement units to in signal frequencies, this can provide an accurate
generate the synchrophasor data signals. These signals need measurement for the fast detection of small signal oscillations
to be collected together before system level applications are to initiate damping actions.
exercised. Collection of synchrophasors is typically performed
by a phasor data concentrator (PDC) which prepares the
synchrophasor data for the application.
Portion of grid
de-energised? Adaptive
PMUs restoration
~minutes
3rd
Slow voltage
Figure 20.5: PMU data viewed in a simple visualisation tool
Voltage
decline?
PMUs
instability
prediction Synchronised measurements allow the comparison of the phase
~milliseconds
~10s of
seconds of the oscillatory modes to determine the parts of the system
Wide-Area State
1st Estimation 3rd that are oscillating with respect to each other, and enable
~ seconds
Angular
stabilising actions to be initiated as shown in Figure 20.6.
Substation instability
SE Abrupt frequency prediction
decline? ~milliseconds
2nd
Oscillatory
Inter-area and local instability Tune PSS, SVC, HVDC,
3rd
oscillations prediction taps, etc.
~minutes
Poorly damped Oscillatory
Substation oscillations? instability Key
SE
prediction
~milliseconds PSS: Power System Stabiliser
~minutes
SVC: Static Var Compensator
Immediate response to unexpected HVDC: High Voltage DC
1st events in the grid
Figure 20.6: Oscillatory instability prediction
Figure 20.4: WAMPAC opportunities
Figure 20.4 shows applications based on the use of 20.3.1.2 Synchrophasors for Voltage Stability
synchrophasors and state estimation (SE) for oscillatory Synchrophasors can be used to predict voltage instability. By
stability, voltage stability, transient stability (or angular comparing voltage and power transfers on the line against
instability prediction), and system restoration. specific stability margins, operators can be alerted to slow
The technology can also offer event triggering based on voltage declines and take remedial actions such as switching
overcurrent, under/overvoltage, under/over-frequency and in reactors as shown in Figure 20.7.
under/over-rate of change of frequency.
20-5
Protection & Automation Application Guide
The phase angles from the two parts of the system can be seen A synchrophasor is a phasor calculated from sampled values
diverging. A major blackout followed. This is the type of event that are referenced to a common timing signal. The timing
that the synchrophasor technology can help prevent. But what signal is global, meaning that a synchrophasor measured
exactly is a synchrophasor? anywhere in the world will be referenced to the same time
signal. This enables synchrophasors to be communicated for
20.3.2 Synchronised Phasor Measurements collation and comparison. This is the fundamental concept
A phasor is a representation of a sinusoidal quantity, behind wide-area special protection schemes.
representing the sinusoid as a vector rotating on the complex The IEEE 1344 standard for synchrophasors was published in
plane, defined in terms of amplitude and phase. As steady 1995. It was reaffirmed in 2001, but in 2005 it was
state power system quantities are sinusoids, it follows that superseded by IEEE C37.118. This recognised the
they can be represented by phasors. When augmented by an developments that would facilitate the effective application of
20-6
Chapter 20 ⋅ System Integrity Protection Schemes
synchrophasors to electrical power systems. IEEE C37.118 Figure 20.10: Time and frequency domain representation of
synchrophasors
describes the standards for measurement of synchrophasors,
the method of quantifying the measurements, as well as the The measured angle θ is valid in the range of –π to +π
testing and certification requirements for verifying accuracy. It radians.
also prescribes the data transmission format and protocol for A primary requirement for synchrophasors is the accuracy of
synchrophasor communication. The more recent 2011 edition the measured phasor. The IEEE C37.118 (2005) standard
of IEE C37.118 classifies phasor measurement units into M defines the total permitted vector error (TVE) for the static
Class (for very accurate measurements in steady-state) and P condition at nominal frequency as:
class (for tracking dynamic system conditions).
relative to the 1pps signal is further described in Figure 20.10, Table 20.1: Influencing quantities and allowable error limits for
compliance levels 0 – 1.
where X r (n) and X i (n) are the RMS real and imaginary
Devices offering compliance level 1 perform better in SIPS
filtered components at a particular instance and θ is the phase schemes, whereas level 0 devices are intended more for
angle as per the IEEE C37.118 standard definition. measurement purposes.
θ
Peak
This measurement accuracy will vary with the magnitude and
ms
frequency of the input signal and may be depicted graphically
Xi(n)
θ
as shown in Figure 20.11. The graph depicts a device with a
Xr(n) total vector error typically less than 0.4% (y-axis), consistent for
system frequency excursions off-nominal (z-axis), and
maintained for all except very low current magnitudes (x-axis).
1 PPS
20-7
Protection & Automation Application Guide
Total Vector Error across, say, an Ethernet network. An example of a typical data
frame is shown in Table 20.2.
TVE (%)
20-8
Chapter 20 ⋅ System Integrity Protection Schemes
The TCP or UDP mapped messages are written to and read frame rate is thus:
from using standard internet protocol (IP) input-output
• 1072 * 50 = 53.6kbps for a maximum frame rate of 50
functions. These functions apply a numerical identifier for the frames per second (TCP)
data structures of the terminals of the communications. The
• 1072 * 60 = 64.32kbps for a maximum frame rate of
terminal is referred to as a port and the numerical identifier is 60 frames per second (TCP)
called the port number. The port number should be set to
• 800 * 50 = 40kbps for a maximum frame rate of 50
align with the recipient phasor data concentrator (see section frames per second (UDP)
20.3.7). • 800 * 60 = 48kbps for a maximum frame rate of 60
Other settings that apply as the phasor message is mapped to frames per second (UDP)
the Ethernet layer are the IP address, subnet mask, and These figures are not absolute, but they can be of benefit in
gateway address. planning network requirements when installing and operating
phasor measurement units.
20.3.4.2 Communication Bandwidth Requirements
It can be useful to understand how much loading the addition 20.3.5 Phasor Measurement Units
of a phasor measurement unit can have on a communications Synchrophasors are generated in phasor measurement units.
system. A typical frame length of 72 bytes has already been A typical phasor measurement unit architecture is shown in
mentioned. For a typical application with a frame length of 72 Figure 20.12.
bytes and a repetition rate of 60 per second, the minimum
bandwidth requirement for these raw frames is, therefore,
4320 bytes per second.
20-9
Protection & Automation Application Guide
An IRIG-B signal from the time synchronisation unit allows the more conservative to apply dedicated time synchronisation
measurement processor to accurately time-stamp the devices into the substation using connections that are separate
synchrophasor values before passing them to the Ethernet to the LAN. A typical time synchronisation device might
processor. The Ethernet processor frames the synchrophasor provide a one-pulse-per-second (1pps) signal, derived from
values according to IEEE C37.118 before transmitting over the GPS signals, in order to provide precise alignment of the
either TCP/IP or UDP/IP. synchrophasors. To combat the effects of electrical interference
in the substation environment, the 1pps signal is generally
20.3.5.1 Physical Deployment of Phasor Measurement presented as a fibre-optic signal. The accuracy is typically
Units better than 0.1μs. Although the 1pps signal is very accurate
There is no need to install phasor measurement units at every (Figure 20.13), the pulse on it only signifies that another
busbar in the system as this will not necessarily contribute to second has passed (or is about to start). In order that the
more efficient system operation. Indeed, too many phasor phasor measurement unit can provide an accurate time stamp
measurement units could cause congestion on the for the synchrophasors, it is necessary to provide an additional
communications system, making data less manageable. ‘real’ time signal. This is achieved with an IRIG-B output,
which delivers coordinated universal time (UTC) for very
Phasor measurement units should be connected so that inter-
accurate time stamping. It is quite likely that the time
area oscillations and other critical dynamics will be correctly
synchronisation device will feature multiple outputs and be
monitored. They should be deployed on the network at critical
capable of synchronising multiple PMUs and merging units,
buses to ensure that a sufficient picture of the system
providing substation-wide timing information.
dynamics is available to the control centre to enable decisions
to be made. System visualisation using synchrophasors from
Seconds
various parts of the system can show, for example, the 1s
angular, frequency and voltage differences between groups of
<50ns
generators. To do this, synchrophasors from various locations
need to be brought together, and one method of achieving this Light <50ns
ON
is by means of phasor data concentrators, which is covered in 200ms ON
20-10
Chapter 20 ⋅ System Integrity Protection Schemes
From other
PDC substations
Antenna
Visualisation
15° mask angle Software
The antenna should be mounted so that it is above the roofline Figure 20.16: PMU and PDC architecture
of the building to which it is attached, ensuring that there is a The complete network requires rapid transfer of data within
360º horizontal view and a 150º vertical view of the sky (a the frequency of sampling of the synchrophasor data.
masking angle of 15º with respect to the horizon is the
The phasor data concentrator correlates the data, and controls
maximum that should be permitted). Ideally there should be
and monitors the phasor measurement units. It also serves to
no obstructions in view such as metal structures or buildings.
archive the data, which is essential in the event that post-
If the masking angle is greater than 15º with respect to the
disturbance analysis might be undertaken in order to
horizon (i.e. if is a large obstruction) the antenna must be re-
determine the root causes of cascade events. At the central
sited or mounted on a longer antenna pole.
control facility, the SCADA/EMS system presents system-wide
Due to the requirement for ensuring such a clear view of the data on all generators and substations in the system with
GPS constellation, the antenna is likely to be the highest frequent regular updates. These updates provide for a
component in the vicinity. As such it is exposed to lightning, visualisation of the system which facilitates response-based
and suitable protection is required. A lightning arrestor is schemes.
recommended for protection.
20.3.8 System Visualisation
20.3.7 Phasor Data Concentrators System visualisation enhances wide-area schemes. Figure
As shown in Figure 20.16, a phasor network consists of phasor 20.17, Figure 20.18, and Figure 20.19, show visualisations of
20-11
Protection & Automation Application Guide
electrical networks as presented on an advanced energy and the options available to them for remedial action.
management system.
System visualisation of real-time data realised thanks to wide-
area technology provides power system operators greater
awareness, and hence more precise control of the system.
Underpinning this wide-area technology is the capability to
accurately time synchronise the phasor measurement units.
20-12
Chapter 20 ⋅ System Integrity Protection Schemes
Energy management reactors, but these bring added complexity. Protection against
system integrity system disturbances may be provided to some extent by
protection scheme
frequency relays or voltage relays set to initiate actions such as
Centralised
Wide-area system
load-shedding on under-frequency conditions, but these may
integrity protection
scheme not be sufficient in themselves for all applications and
sophisticated system integrity protection schemes have been
Busbar
protection developed to complement them. Two particular examples that
do not require communications are described in sections
IED system integrity entitled 20.4.2 System Topology Changes and 20.4.3 System
Local
protection scheme
Synchronism Stability. The former describes an example of an
Communication requirements event-based system integrity protection scheme looking for
Figure 20.20: Communications requirements for system integrity changes in system topology. The latter describes an example of
protection schemes. a response-based system integrity protection scheme looking
This shows ‘local’ IED system integrity protection schemes for system instability.
that do not require any communications, and these form the
Both of these system integrity protection schemes are able to
subject of the rest of this chapter.
anticipate system-threatening conditions using local variables
only. They are based on Kalman filters and fuzzy-logic multi-
20.4.1 Single-point special protection
criteria algorithms. These system integrity protection schemes
In countries where large sources of power generation are
are applicable to large power systems prone to transient and
geographically far from the principal loads, so-called
dynamic instabilities.
transmission corridors of power provide the routes for the
transmission of that power. One example of this is the Hydro- 20.4.2 System Topology Changes
Québec network in Canada as shown in Figure 20.21.
Detecting topology changes such as open line conditions
allows timely initiation of system defence plans for severe
contingencies such as a loss of transmission corridor. In the
absence of communications, signalling an open line condition
from a remote terminal is not possible and so, detecting a loss
of corridor caused by a remote terminal action using only
locally available signals can enable system stabilising actions
to be initiated.
20-13
Protection & Automation Application Guide
the remote end, and line closing or opening with a shunt a better basis for open line detection. Observing the rate of
reactor connected. change of active and reactive power for various system events
produces interesting results. The rate of change of power
The typical speed required for open line detection operation is
(dP/dt, or DeltaP) can be studied for various system events
two cycles or less.
and two in particular are illustrated in Figure 20.23 and Figure
As with many other aspects of electrical power systems, open 20.24.
line operation can be characterised by both transient and
steady state conditions. Observation of the transient state
aspects and steady state aspects of open line conditions 60pu/min
DeltaP
opening, whilst steady state phenomena are more closely
linked to closed lines. 0.5pu/min
(consisting of the angle shift and the voltage ratio between its
ends) can be found so that, as seen from the sending end,
Time(s)
both active and reactive powers disappear.
Figure 20.23: Rate of change of power (DeltaP) filter response to power
flow reversal
1pu
0.5pu
DeltaP
0.01pu
Figure 20.22: Voltage ratio and angle trajectories vary with line length
for sending end active (Ps) and reactive (Qs) powers both at zero.
very sensitive: For short lines, say 30km, the typical Figure 20.24: Rate of change of power (DeltaP) at breaker opening
sensitivities are 45% MW per degree of angle shift and 25%
Figure 20.23 shows power transfer ramping from a positive
MVAr per unit of voltage ratio.
direction to a negative direction, thus passing through zero
It is therefore difficult to accurately detect this condition based without apparently any significant effect. As the power ramp
on power or current measurement alone, and thus it cannot crosses zero, however, it can be seen that DeltaP reaches a
form a reliable basis for detecting open lines. maximum value a few cycles later. Although the maximum
value of DeltaP varies according to the power slope, the
Studying the transient state aspects of opening a line provides
maximum is reached at nearly the same time.
20-14
Chapter 20 ⋅ System Integrity Protection Schemes
Anti-alias filter
Kalman filters
Output logic
Open Line
processor
Currents
steady-state value to its maximum value. Detection
Reactor Flag
It is apparent that observing DeltaP provides the capability for Currents
ICT1 ICT2
Kalman Filter is used since it can extract the fundamental
CT3
SHUNT REACTOR components and harmonic components. But unlike filters such
LINE
D
v as the Discrete Fourier Transform (DFT), a Kalman Filter can
IREACTOR
DISCONNECTOR
provide signal components at spectral frequencies other than
CVT LINE
the fundamental and its harmonics. Kalman Filters are well
suited to the application of protecting compensated lines, since
they can be used to detect, for example, the negative sequence
component at fundamental as well as resonances that may
Figure 20.25: Connections for open line detection. transiently appear when a line is opened at both ends while its
Figure 20.25 shows typical inputs used by an open line shunt reactors are connected. The outline of a Kalman filter is
detection algorithm. The inputs are taken from a capacitive shown in Figure 20.27, and the state diagram is shown in
voltage transformer (CVT) and three sets of current Figure 20.28.
transformers (CT1, CT2 associated with the circuit breakers X̂ klk
Vk +- Gk ++
and CT3 associated with the shunt reactor).
20-15
Protection & Automation Application Guide
Fuzzy logic to produce a conclusion as to the state of the line described by common language terms such as "Normal",
(open or closed). "Small", "Large", "Very Large", etc.
Probability μ
Probability μ
0.5 0.5
being in more than one state and where there may be overlap
Active Power
between states. Consider Figure 20.29, which shows a Delta P
0 0
θL θC θS θL θC θS
number of states for the active power.
Figure 20.30: Fuzzification of typical decision features
Membership Figure 20.30 illustrates this fuzzification process for two typical
variables: the Active Power and the DeltaP. The first feature is
defined as "SMALL" when its crisp value is below a given
1
Nil Low Normal threshold (θL) while the DeltaP feature is defined as "LARGE"
for crisp values higher than (θS).
Its membership of the “Nil” state is 0, its membership of the • Security: if (ActivePower is not SMALL) LINE is
CLOSED
“Normal” state is 1, and its membership of the “Low” state is
somewhere between 0 and 1. This process is known as • Reliability: if (DeltaP is LARGE) LINE is OPEN
“fuzzification”. Although called “fuzzy”, it is, in fact, a The fuzzy logic engine contains a number of these rules for
repeatable process to which rules can be applied. detecting the open-line status under various circumstances
A fuzzy logic approach can resolve conflicts that may arise in (reliability rules), and a number of rules for detecting the
doubtful cases such as during line energisation at no-load, or closed-line status (security rules). In each category, the rules
where capacitive voltage transformers induce electro-magnetic can be further classified in terms of transient and steady-state
transients suggesting that the active power is not zero (line rules. For instance, the reliability rule above is a transient one
closed) while the line is actually open. Fuzzy logic is ideally while the security rule is a steady state.
suited to resolving such conflicts since the decision is based on The last stage of the process is called defuzzification. This
several criteria with adaptable weighting factors. consists of converting the evaluation results of the criteria,
The fuzzy decision system consists of three main steps: which are applied by the rules, into a single decision. Each
criterion states that the line is open or closed with a given
• Fuzzification of the selected decisions features from the probability and defuzzification reconciles all partial decisions
pre-processor
using an aggregation procedure into a single decision.
• Fuzzy logic inference on these features, using rules or
criteria The output from the open line detector is the flag that is
• Crisp decision sent to the output asserted when an open line is detected.
Fuzzification is a necessary step prior to a fuzzy-logic based 20.4.2.4 Open Line Detection Summary
reasoning system. It consists in transforming the crisp
In the context of interconnected and heavily loaded power
variables provided by the pre-processor into categories easily
20-16
Chapter 20 ⋅ System Integrity Protection Schemes
systems, fast detection of topology change is considered an 20.4.3.1 Conventional Out-of-Step Protection
efficient means to instigate remedial actions for the defence of
a power system against severe events. Open Line Detection, Blinder unit
20-17
Protection & Automation Application Guide
The RPS variables are used to track and anticipate the stable
or unstable evolution of power swings across the transmission
line. Three angular variables, one concavity index, two voltage
and six Vcosφ variables are derived and processed to prepare
them for the fuzzy-logic algorithm.
20-18
Chapter 20 ⋅ System Integrity Protection Schemes
20-19
RELAY TESTING
AND COMMISSIONING
Chapter 21
RELAY TESTING AND
COMMISSIONING
GEGridSolutions.com 21-1
Protection & Automation Application Guide
These are conducted to prove that relays are free from defects Directionality Forward/Reverse/Non-directional
during manufacture. Testing will take place at several stages RCA -95° to +95° 1°
Characteristic DT/IDMT
during manufacture, to ensure problems are discovered at the
Definite Time Delay 0 - 100s 0.01s
earliest possible time and hence minimise remedial work. The
IEC Standard Inverse
extent of testing will be determined by the complexity of the
IEC Very Inverse
relay and past manufacturing experience. IEC IDMT Time Delay
IEC Extremely Inverse
UK Long Time Inverse
21.1.3 Commissioning Tests Time Multiplier Setting (TMS) 0.025 - 1.2 0.005
These tests are designed to prove that a particular protection IEEE Moderately Inverse
IEEE Very Inverse
scheme has been installed correctly prior to setting to work.
IEEE IDMT Time Delay IEEE Extremely Inverse
All aspects of the scheme are thoroughly checked, from US-C08 Inverse
installation of the correct equipment through wiring checks US-C02 Short Time Inverse
and operation checks of the individual items of equipment, Time Dial (TD) 0.5 - 15 0.1
finishing with testing of the complete scheme. IEC Reset Time (DT only) 0 - 100s 0.01s
IEEE Reset Time IDMT/DT
21.1.4 Periodic Maintenance Checks IEEE DT Reset Time 0 - 100s 0.01s
These are required to identify equipment failures and IEEE Moderately Inverse
IEEE Very Inverse
degradation in service, so that corrective action can be taken.
IEEE IDMT Reset Time IEEE Extremely Inverse
Because a protection scheme only operates under fault US-C08 Inverse
conditions, defects may not be revealed for a significant period US-C02 Short Time Inverse
of time, until a fault occurs. Regular testing assists in Table 21.1: Overcurrent relay element specification
detecting faults that would otherwise remain undetected until Test no. Description
a fault occurs. Three phase non-directional pick up and drop off accuracy over complete current
Test 1
setting range for both stages
Element Range Step Size When a modern numerical relay with many functions is
I>1 0.08 - 4.00In 0.01In considered, each of which has to be type-tested, the functional
I>2 0.08 - 32In 0.01In type-testing involved is a major issue. In the case of a recent
21-2
Chapter 21 ⋅ Relay Testing and Commissioning
relay development project, it was calculated that if one person they comply with the product specification. Particular
had to do all the work, it would take 4 years to write the withstand and endurance type tests have to be carried out
functional type-test specifications, 30 years to perform the using d.c., since the normal supply is via a station battery.
tests and several years to write the test reports that result.
Automated techniques/ equipment are clearly required, and 21.2.7 Insulation Resistance
are covered in Section 21.7.2. The insulation resistance test is carried out according to IEC
60255-27, i.e. 500V d.c. ± 10%, for a minimum of 5 seconds.
21.2.2 Rating Tests This is carried out between all circuits and case earth, between
Rating type tests are conducted to ensure that components are all independent circuits and across normally open contacts.
used within their specified ratings and that there are no fire or The acceptance criterion for a product in new condition is a
electric shock hazards under a normal load or fault condition of minimum of 100MΩ. After a damp heat test the pass
the power system. This is in addition to checking that the criterion is a minimum of 10MΩ.
product complies with its technical specification. The following
are amongst the rating type tests conducted on protection 21.2.8 Auxiliary Supplies
relays, the specified parameters are normally to IEC 60255-1. Digital and numerical protection relays normally require an
auxiliary supply to provide power to the on-board
21.2.3 Thermal Withstand microprocessor circuitry and the interfacing opto-isolated input
The thermal withstand of VTs, CTs and output contact circuits circuits and output relays. The auxiliary supply can be either
is determined to ensure compliance with the specified a.c. or d.c., supplied from a number of sources or safe supplies
continuous and short-term overload conditions. In addition to - i.e. batteries, UPSs, etc., all of which may be subject to
functional verification, the pass criterion is that there is no voltage dips, short interruptions and voltage variations. Relays
detrimental effect on the relay assembly, or circuit are designed to ensure that operation is maintained and no
components, when the product is subjected to overload damage occurs during a disturbance of the auxiliary supply.
conditions that may be expected in service. Thermal withstand
Tests are carried out for both a.c. and d.c. auxiliary supplies
is assessed over a time period of 1s for CTs and 10s for VTs.
and include mains variation both above and below the nominal
21.2.4 Relay Burden rating, supply interruptions derived by open circuit and short
circuit, supply dips as a percentage of the nominal supply,
The burdens of the auxiliary supply, optically isolated inputs,
repetitive starts. The duration of the interruptions and supply
VTs and CTs are measured to check that the product complies
dips range from 2ms to 60s intervals. A short supply
with its specification. The burden of products with a high
interruption or dip up to 20ms, possibly longer, should not
number of input/output circuits is application specific i.e. it
cause any malfunction of the relay. Malfunctions include the
increases according to the number of optically isolated input
operation of output relays and watchdog contacts, the reset of
and output contact ports which are energised under normal
microprocessors, alarm or trip indication, acceptance of
power system load conditions. It is usually envisaged that not
corrupted data over the communication link and the corruption
more than 50% of such ports will be energised concurrently in
of stored data or settings. For a longer supply interruption, or
any application.
dip in excess of 50ms, the relay self recovers without the loss
of any function, data, settings or corruption of data. No
21.2.5 Relay Inputs
operator intervention is required to restore operation after an
Relay inputs are tested over the specified ranges. Inputs
interruption or dip in the supply.
include those for auxiliary voltage, VT, CT, frequency, optically
isolated digital inputs and communication circuits. In addition to the above, the relay is subjected a number of
repetitive starts or a sequence of supply interruptions. Again
21.2.6 Relay Output Contacts the relay is tested to ensure that no damage or data corruption
Protection relay output contacts are type tested to ensure that has occurred during the repetitive tests.
21-3
Protection & Automation Application Guide
Specific tests carried out on d.c. auxiliary supplies include • high frequency disturbance test
reverse polarity, a.c. waveform superimposed on the d.c. • fast transient test
supply and the effect of a rising and decaying auxiliary voltage. • surge immunity test
All tests are carried out at various levels of loading of the relay
• power frequency interference test
auxiliary supply.
• electrostatic discharge test
21-4
Chapter 21 ⋅ Relay Testing and Commissioning
60.00
50.00
40.00
Voltage (V)
Voltage
30.00 0
Time
20.00
10.00
0.00
1
88
175
262
349
436
523
610
697
784
871
958
1045
1132
1219
1306
1393
Figure 21.2: High Frequency Disturbance Test waveform
Time (ms)
Figure 21.1: A.C. ripple superimposed on d.c. supply test 21.3.5 Fast Transient Test
For auxiliary power supplies with a large operating range, the The Fast Transient Test simulates the HV interference caused
tests are performed at minimum, maximum, and other by disconnector operations in GIS substations or breakdown of
voltages across this range, to ensure compliance for the the SF6 insulation between conductors and the earthed
complete range. The interference is applied using a full wave enclosure. This interference can either be inductively coupled
rectifier network, connected in parallel with the battery supply. onto relay circuits or can be directly introduced via the CT or
The relay must continue to operate without malfunction during VT inputs. It consists of a series of 15ms duration bursts at
the test. 300ms intervals, each burst consisting of a train of 50ns wide
pulses with very fast (5ns typical) rise times (Figure 21.3),
21.3.3 D.C. Ramp Down/Ramp Up with a peak voltage magnitude of 4kV.
This test simulates a failed station battery charger, which
Burst period, 300 ms
would result in the auxiliary voltage to the relay slowly ramping
V Burst duration (1/15 ms)
down. The ramp up part simulates the battery being recharged
after discharging. The relay must power up cleanly when the
voltage is applied and not maloperate. t
21-5
Protection & Automation Application Guide
differential mode surges. The waveshape consists on open of the relay, with the cover both on and off. Two types of
circuit of a 1.2/50µs rise/fall time and a short circuit current of discharges are applied, air discharge and contact discharge. Air
8/20µs rise/fall time. The generator is capable of providing a discharges are used on surfaces that are normally insulators,
short circuit test current of up to 2kA, making this test and contact discharges are used on surfaces that are normally
potentially destructive. The surges are applied sequentially conducting. IEC 60255-22-2 is the relevant standard this test,
under software control via dedicated coupling networks in both for which the test parameters are:
differential and common modes with the product energised in
• cover on: Class 4, 8kV contact discharge, 15kV air
its normal (quiescent) state. The product shall not maloperate discharge
during the test, shall still operate within specification after the • cover off: Class 3, 6kV contact discharge, 8kV air
test sequence and shall not incur any permanent damage. discharge
21.3.7 Power Frequency Interference In both cases above, all the lower test levels are also tested.
This test simulates the type of interference that is caused when The discharge current waveform is shown in Figure 21.4.
there is a power system fault and very high levels of fault
100
current flow in the primary conductors or the earth grid. This 90
Rise Time = 0.7 to 1.0 ns.
causes 50 or 60Hz interference to be induced onto control and 80
Current specified for 30 ns and 60 ns
Current, % of Peak
70
communications circuits. 60
50
There is no international standard for this test, but one used by 40
Time, ns
applied to circuits for which power system inputs are not Figure 21.4: ESD Current Waveform
connected.
The test is performed with single discharges repeated on each
Tests are carried out on each circuit, with the relay in the test point 10 times with positive polarity and 10 times with
following modes of operation: negative polarity at each test level. The time interval between
successive discharges is greater than 1 second. Tests are
• current and voltage applied at 90% of setting, (relay not
tripped) carried out at each level, with the relay in the following modes
of operation:
• current and voltage applied at 110% of setting, (relay
tripped) • current and voltage applied at 90% of setting, (relay not
• main protection and communications functions are tripped)
tested to determine the effect of the interference • current and voltage applied at 110% of setting, (relay
tripped)
The relay shall not maloperate during the test, and shall still
• main protection and communications functions are
perform its main functions within the claimed tolerance.
tested to determine the effect of the discharge
21.3.8 Electrostatic Discharge Test To pass, the relay shall not maloperate, and shall still perform
This test simulates the type of high voltage interference that its main functions within the claimed tolerance.
occurs when an operator touches the relay’s front panel after
being charged to a high potential. This is exactly the same 21.3.9 Conducted and Radiated Emissions Tests
phenomenon as getting an electric shock when stepping out of These tests arise primarily from the essential protection
a car or after walking on a synthetic fibre carpet. requirements of the EU directive on EMC. These require
manufacturers to ensure that any equipment to be sold in the
In this case the discharge is only ever applied to the front panel
countries comprising the European Union must not interfere
21-6
Chapter 21 ⋅ Relay Testing and Commissioning
70
60
Figure 21.6: EMC test arrangements
50
When performing these two tests, the relay is in a quiescent
40
30 condition, that is not tripped, with currents and voltages
20
applied at 90% of the setting values. This is because for the
10
0 majority of its life, the relay will be in the quiescent state and
0.1 1 10 100
Frequency, MHz the emission of electromagnetic interference when the relay is
Figure 21.5: EMC Conducted Emissions test - example test plot tripped is considered to be of no significance. Tests are
The test arrangements for the conducted and radiated conducted in accordance with IEC 60255-25 and EN 55022,
emissions tests are shown in Figure 21.6. and are detailed in Table 21.3.
Table 21.3: Test criteria for Conducted and Radiated Emissions tests
21-7
Protection & Automation Application Guide
length of at least ¼ of the wavelength of the electromagnetic particular, the frequencies of mobile communications
wave it is required to conduct. equipment used by personnel working in the substation. This is
to ensure that when working in the vicinity of a relay, the
If a relay were to be subjected to radiated interference at
personnel should be able to operate their radios/mobile phones
150kHz, then a conductor length of at least
without fear of relay maloperation.
300 × 10 6
λ= = 500m IEC 60255-22-3 specifies the radiated immunity tests to be
(
150 × 10 3 × 4 ) conducted (ANSI/IEEE C37.90.2 is used for equipment
compliant with North American standards), with signal levels
of:
would be needed to conduct the interference. Even with all the
cabling attached and with the longest PCB track length taken • IEC: Class III, 10V/m, 80MHz -2700MHz
into account, it would be highly unlikely that the relay would • ANSI/IEEE: 35V/m 25MHz - 1000MHz with no
be able to conduct radiation of this frequency, and the test modulation, and again with 100% pulse modulation
therefore, would have no effect. The interference has to be IEC 60255-22-6 is used for the conducted immunity test, with
physically introduced by conduction, hence the conducted a test level of:
immunity test. However, at the radiated immunity lower
frequency limit of 80MHz, a conductor length of approximately • Class III, 10V r.m.s., 150kHz - 80MHz.
1.0m is required. At this frequency, radiated immunity tests
21.3.11 Power Frequency Magnetic Field Tests
can be performed with the confidence that the relay will
conduct this interference, through a combination of the These tests are designed to ensure that the equipment is
attached cabling and the PCB tracks. immune to magnetic interference. The three tests, steady
state, pulsed and damped oscillatory magnetic field, arise from
Although the test standards state that all 6 faces of the the fact that for different site conditions the level and
equipment should be subjected to the interference, in practice waveshape is altered.
this is not carried out. Applying interference to the sides and
top and bottom of the relay would have little effect as the 21.3.11.1 Steady state magnetic field tests
circuitry inside is effectively screened by the earthed metal These tests simulate the magnetic field that would be
case. However, the front and rear of the relay are not experienced by a device located within close proximity of the
completely enclosed by metal and are therefore not at all well power system. Testing is carried out by subjecting the relay to
screened, and can be regarded as an EMC hole. a magnetic field generated by two induction coils. The relay is
Electromagnetic interference when directed at the front and rotated such that in each axis it is subjected to the full
back of the relay can enter freely onto the PCBs inside. magnetic field strength. IEC 61000-4-8 is the relevant
When performing these two tests, the relay is in a quiescent standard, using a signal level of:
condition, that is not tripped, with currents and voltages
• Level 5: 300A/m continuous and 1000A/m short
applied at 90% of the setting values. This is because for the
duration
majority of its life, the relay will be in the quiescent state and
the coincidence of an electromagnetic disturbance and a fault The test arrangement is shown in Figure 21.7.
is considered to be unlikely.
21-8
Chapter 21 ⋅ Relay Testing and Commissioning
essential requirements are that the relay is safe and will not
cause an electric shock or fire hazard under normal conditions
Induction Coil and in the presence of a single fault. A number of specific tests
to prove this may be carried out, as follows.
21-9
Protection & Automation Application Guide
Voltage Impulse Withstand tests these should be carried out at 21.4.6 Other Regional or Industry Norms
75% of the specified level, in accordance with IEC 60255-27, Many products intended for application in North America will
to avoid overstressing insulation and components. additionally need certification to the requirements of UL
(Underwriter's Laboratory), or CUL for Canada. Products for
application in mining or explosive environments will often be
required to demonstrate an ATEX claim
• temperature
• humidity
• enclosure protection
• mechanical
5kV peak Duration (50 %) = 50µs These tests are described in the following sections.
Figure 21.8: Test generator characteristics for insulation withstand test
21.5.1 Temperature Test
21.4.3 Single Fault Condition Assessment
Temperature tests are performed to ensure that a product can
An assessment is made of whether a single fault condition withstand extremes in temperatures, both hot and cold, during
such as an overload, or an open or short circuit, applied to the transit, storage and operating conditions. Storage and transit
product may cause an electric shock or fire hazard. In the case conditions are defined as a temperature range of –25oC to
of doubt, type testing is carried out to ensure that the product +70oC and operating as –25oC to +55oC. Many products now
is safe. claim operating temperatures of +70°C or even higher.
21.4.4 Earth Bonding Impedance Dry heat withstand tests are performed at 70°C for 96 hours
Class 1 products that rely on a protective earth connection for with the relay de-energised. Cold withstand tests are
safety are subjected to an earth bonding impedance (EBI) type performed at –40°C for 96 hours with the relay de-energised.
test. This ensures that the earth path between the protective Operating range tests are carried out with the product
earth connection and any accessible earthed part is sufficiently energised, checking all main functions operate within tolerance
low to avoid damage in the event of a single fault occurring. over the specified working temperature range –25°C to +55°C.
The test is conducted using a test voltage of 12V maximum
21.5.2 Humidity Test
and a test current of twice the recommended maximum
protective fuse rating. After 1 minute with the current flowing The humidity test is performed to ensure that the product will
withstand and operate correctly when subjected to 93% relative
in the circuit under test, the EBI shall not exceed 0.1Ω.
humidity at a constant temperature of 40°C for 56 days. Tests
21.4.5 CE Marking are performed to ensure that the product functions correctly
within specification after 21 and 56 days. After the test, visual
A CE mark on the product, or its packaging, shows that
inspections are made for any signs of unacceptable corrosion
compliance is claimed against relevant EU directives e.g. Low
Voltage Directive 2006/95/EC and Electromagnetic and mould growth.
Compatibility (EMC) Directive 2004/108/EC.
21.5.3 Cyclic Temperature/Humidity Test
This is a short-term test that stresses the relay by subjecting it
to temperature cycling in conjunction with high humidity.
21-10
Chapter 21 ⋅ Relay Testing and Commissioning
The test does not replace the 56 day humidity test, but is used or growth, and photographs are usually taken of each PCB and
for testing extension to ranges or minor modifications to prove the case as a record of this.
that the design is unaffected.
21.5.4 Enclosure Protection Test
The applicable standard is IEC60068-2-30 and test conditions of:
Enclosure protection tests prove that the casing system and
• +25°C ±3°C and 95% relative humidity/+55°C ±2°C connectors on the product protect against the ingress of dust,
• 95% relative humidity moisture, water droplets (striking the case at pre-defined
are used, over the 24 hour cycle shown in Figure 21.9. angles) and other pollutants. An ‘acceptable’ level of dust or
water may penetrate the case during testing, but must not
100 96%
90 95% impair normal product operation, safety or cause tracking
Relative humidity %
95%
90%
80
70 15min
80% across insulated parts of connectors.
15min
15min Start of
temperature
fall 21.5.5 Mechanical Tests
End of temperature rise
21-11