0% found this document useful (0 votes)
105 views

Checklist For Stress Analysis: PEC-EN-FRM-Y-08927

This document is a checklist for stress analysis that contains 12 check points to ensure key information and design conditions are provided and the stress results are acceptable. The checklist must be filled out for each drawing with check marks or remarks explaining any missing check marks. It includes checks for basic input data, design conditions, line service information, applicable codes, stress results, loads on components like riser clamps, pig traps, and anchor blocks. Once completed, it requires a reviewer's signature and date.

Uploaded by

Yusri Fakhrizal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
105 views

Checklist For Stress Analysis: PEC-EN-FRM-Y-08927

This document is a checklist for stress analysis that contains 12 check points to ensure key information and design conditions are provided and the stress results are acceptable. The checklist must be filled out for each drawing with check marks or remarks explaining any missing check marks. It includes checks for basic input data, design conditions, line service information, applicable codes, stress results, loads on components like riser clamps, pig traps, and anchor blocks. Once completed, it requires a reviewer's signature and date.

Uploaded by

Yusri Fakhrizal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Checklist for

STRESS ANALYSIS
PEC-EN-FRM-Y-08927 Rev 0

PROJECT NAME :       PROJECT NO:      

DOCUMENT NO. :       CLIENT :      

DOCUMENT TITLE:       REV. :       DATE :      

Sr. No. Check Points Check Box Remarks

1. Stress Isometric is complete with all information


2. Correct basic input data provided
3. Correct Design Conditions provided
4. Correct Line service information provided
5. Correct applicable pipeline design codes are used
6. Stress result is acceptable

7. Riser clamp loadings checked and acceptable (for offshore)

Displacement and loading on pig trap support and Isolating joint checked
8.
and acceptable (for onshore).

9. Design of Anchor Flange and load on anchor block checked (for onshore)

Design of Anchor Flange and load on anchor block checked at shore


10.
approach (for offshore)

11. Loads on PLEM checked at Buoy Mooring Station (for offshore)

12. Standard cover sheet and index used

Note:
1. Check List must be filled up for each drawing. If    is not filled against each item,
please indicate the reason in Remarks.