Win
Win
7 414400
Name of Project: CONCRETING OF CORE LOCAL ACCESS ROAD
Location: SITIO BINATON, PM. SOBRECAREY, CARAGA, DAVAO ORIENTAL
Bid Amoun 4,140,399.32
DETAILED ESTIMATES
QTY. = 2 each
Equipment Cos= -
Total = 1,573.44
Output/hr. As S= 1.00
Direct Unit Cos= 1,573.44
Materials: Unit Unit Cost Amount
30 Post 6 - 2x3x10' coco bd.ft. 16.00 = 480.00
16 Extended Nailer 6- 2x2x8' coco bd.ft. 16.00 = 256.00
20 Diagonal bracing 4- 2x3x10' coco bd.ft. 16.00 = 320.00
13.33 Cross Bracing 4- 2x2x10' coco bd.ft. 16.00 = 213.28
3.33 Staking 1- 2x2x10' bd.ft. 16.00 = 53.28
3 1/2" thk. 4x8 Marine Plywood sht. 590.00 = 1,770.00
1 Assorted C.W. Nails kgs. 73.00 = 73.00
1 Tarpaulin print (1-4'x8' & 1-8'x8') lot 1,455.00 = 1,455.00
QTY. = 1 l.s
QTY. = 2 mos.
QTY. = 1 l.s.
Labor Cost = -
Equipment: No. of Hour/s Rental Rate Amount
Materials Cost=
QTY. = 22 each
Materials Cost= -
Materials Cost= -
Materials Cost= -
LABOR UTILIZATION
EQUIPMENT UTILIZATION
SUMMARY SHEET
Materials: Unit
13 pcs. - 2x2x8' Coco Lumber (Plus 5%) 34.00 bd.ft.
Paint 0.00 gals
Field Books 2.00 pcs.
Paint Brush 2.00 pcs.
Assorted Wire Nails 0.00 kgs.
Post 6 - 2x3x10' coco 30.00 bd.ft.
Extended Nailer 6- 2x2x8' coco 16.00 bd.ft.
Diagonal bracing 4- 2x3x10' coco 20.00 bd.ft.
Cross Bracing 4- 2x2x10' coco 13.33 bd.ft.
Staking 1- 2x2x10' 3.33 bd.ft.
1/2" thk. 4x8 Marine Plywood 3.00 sht.
Assorted C.W. Nails 1.00 kgs.
Tarpaulin print (1-4'x8' & 1-8'x8') 1.00 lot
Safety Helmet 59.00 man-day
Safety Shoes 9.00 man-day
Safety Vest 59.00 man-day
Working Gloves 9.00 man-day
Rubber Boots 50.00 man-day
Raincoat 3.00 man-day
Medical Kit 3.00 man-day
Speed Restriction (R4-1) 4.00 each
Roadwork Ahead (T1-1) 4.00 each
End Roadwork (T2-16) 4.00 each
End Speed Restriction (R4-2) 4.00 each
Workmen Ahead (T1-5) 4.00 each
Prepare to Stop (T1-18) 2.00 each
Roadwork Machinery Ahead (T1-3) 2.00 each
Temporary Hazard Marker (Chevron, T5-5) 1.00 each
Plastic Safety Barriers 22.00 each
Temporary Bollards (@ 5m apart) 48.94 each
Safety Vest 2.00 man-day
Hard Hat 2.00 man-day
Safety Shoes 2.00 man-day
Rope, 1" dia. - 5 uses 50.00 m
Common Borrow (w/ 25% Shrinkage Factor) 1.25 cu.m.
Aggregate Subbase Course (w/ 15% Shrinkage Factor) 1.15 cu.m.
Uncrushed Aggregate Surface Course (w/ 15% Shrinkage Fa 1.15 cu.m.
Refinforcing Steel Bar 0.39 kg.
Curing Compound 0.29 lit.
Asphalt Sealant 0.12 lit.
Steel Forms, (Rental) 0.46 l.m.
Sand 0.11 cu.m.
Gravel, G2 0.20 cu.m.
Cement 1.90 bag
Concrete Saw (Diamond Blade 14") 0.00 pc
Pipe Sleeve, 2" dia. 0.01 l.m.
Grease/Tar 0.01 lit.
Cement 3.00 bag
Sand 0.25 cu.m.
Gravel Fill (Natural) 0.02 cu.m.
Weep Holes (PVC) 0.30 l.m.
Filter Cloth 0.02 sq.m.
Boulders (15-25 kg.) 1.05 cu.m.
Manpower:
Instrumentman 743.84 / day
Surveyman 537.76 / day
Laborer 414.80 / day
Skilled Labor 92.98 / hour
Unskilled Labor 51.85 / hour
Safety Officer (Full Time) 743.84 / day
Health Personnel 414.80 / day
Traffic Controller (Flagmen) 51.85 / hour
Construction Foreman 92.98 / hour
Equipment:
Surveying Equipment (Rental) 2500.00 / day
Two Way Radio 2.60 / hour
Barricade Flasher Light 0.65 / hour
Stake Cargo 1215.00 / day
Dumptruck (12 cu.yd.) 1420.00 / day
Water Truck (16000 liter) 2450.00 / day
Transit Mixer (5 cu.yd.) 1320.00 / day
Chainsaw 75.36 / day
Bulldozer, D6H SERIES II PSDS/DD 3375.00 / day
Payloader (1.50 cu.m.) 1733.00 / day
Payloader (1.50 cu.m.) - at disposal area 1733.00 / day
Dumptruck (12 cu.yd) 1420.00 / day
Backhoe (0.80 cu.m.) 1537.00 / day
Motorized Road Grader (140hp), G710A 2173.00 / day
Vibratory Roller (10m.t.), SD100DC 1846.00 / day
Water Truck (16000 L) 2450.00 / day
Transit Mixer (5 1320.00 / day
Concrete Vibrator 91.25 / day
Batching Plant (30 cu.m.) 1759.50 / day
Payloader (1.50 cu.m.), LX80-2C 1733.00 / day
Concrete Screeder (5.5 Hp) 545.00 / day
Water Truck (16000 L) 2450.00 / day
Concrete Saw, Blade 14" dia. (7.5 Hp) 32.63 / day
Bar Cutter, Single Phase 219.75 / day
Joint Sealer (gas or Diesel Driven w/ Hot & Cold Spray nozzle 56.38 / day
Name of Project: CONCRETING OF CORE LOCAL ACCESS ROAD
Location: SITIO BINATON, PM. SOBRECAREY, CARAGA, DAVAO ORIENTAL
BILL OF QUANTITIES
Item No. Description Qty. Unit Unit Cost Adjusted Total Cost
CASHFLOW
CONSTRUCTION METHOD
Upon receipt of the Notice to Proceed the following steps must be observed:
• Coordinate with the procuring entity and the office concerned.
•
A joint site investigation between the procuring entity and the contractor must be do
•
Prepare an as-stake investigation of the proposed project site which includes the pr
contract variation (extra worksand change order) and as-stake plan.
• After the above-mentioned activities has been done, construction work for the projec
started.
• All construction materials and construction activities must be in accordance with th
specification and should pass the quality control standard.
• No activity must be done without the presence and concurrence of the project engin
inspector.
• Mobilize manpower, equipment, install billboard, build temporary facilities and deliv
materials.
• Clearing the proposed site, layout, established horizontal control.
•
Start the construction activities of the project accordingly based on the approved co
schedule submitted and on the approved plans and specifications.
• Install warning signs on the construction site as safety precautionary measure to pr
accident, provide field office, equipment and supplies and other temporary facilities
during the construction period.
• All materials to be used should pass the quality control and must be in conformity w
specification but not limited to aggregates, reinforcing bars but all materials intend
installed for the said project.
• Documentary requirements such as, pouring permits and other related paper pertain
prosecution of the project must be made possible.
• Daily monitoring on the progress work will be conducted to thresh out problems tha
occure and periodic coordinative meeting and consultation with key staff will be ma
resolve any problem and remedial measures will be employed and the project shall
within the specified contract duration
• Clearing of construction debris, request for final inspection, prepare as-built plan, tu
one.
reparation of
ct will be
he standard
neer and
very
onstruction
revent
needed
with the
ed to be
ning to the
at may
ade to
be complete
rn-over and
Project Title: CONCRETING OF CORE LOCAL ACCESS ROAD
Location: SITIO BINATON, PM. SOBRECAREY, CARAGA, DAVAO ORIENTAL
PERT/CPM
0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60
START OF
P ROJECT
G G
0 1 2 3 8
A , B, D, E, F
4 5 6 END OF
7 P ROJECT
H, J I K L, M,N
LEGEND :