Tasnee HDPE - LDPE Plant Project: Method Statement For Earthworks: Excavation and Backfilling
Tasnee HDPE - LDPE Plant Project: Method Statement For Earthworks: Excavation and Backfilling
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 SAFETY
8.0 GENERAL
11.0 INSPECTION
12.0 ATTACHMENT
1.0 PURPOSE
2.0 SCOPE
This procedure applies to:
Excavation and Backfilling for Basins, Structures and Foundation
Excavation and Backfilling for U/G Pressure Pipes and Sewer Line
Excavation and Backfilling for Electrical and Instrument Cables and
Ductbanks
3.0 REFERENCES
3.1 TECNIMONT ARABIA LIMITED
L3 PC AC1 Site Coordination Procedure
L3 PQ AQ1 Site Inspection Procedure
3276-AX-SG-PO1 Civil Works Site Inspection Plan
TM 930.2/05E Civil Works Charges and Liability
3.2 INTERNATIONAL STANDARD
ASTM D 422 Standard Test Method for Practice Analysis of Soils
ASTM D 698 Standard Test Method for Laboratory Compaction
Characteristics of Soil
ASTM D 1556 Standard Test Method for Density of Soils in Place by
Sand Cone Method
Doc. No:GT-QAQC-002 TASNEE HDPE-LDPE PLANT PROJECT
METHOD STATEMENT FOR EARTHWORKS: Page 4/11
Rev.3
EXCAVATION AND BACKFILLING
4.0 DEFINITIONS
Excavation - removing of in-situ material up to the level of requested sub-
grade elevation.
Embankment - means any earthwork executed above the ground level, by
transporting material, but not limited thereto:
1. Any embankment for roads and yards
2. Any embankment for tank pads, without perimeter r.c. and/or
masonry ring wall
3. Any embankment for retaining earth dikes, dam, etc.
4. Any general embankment for improving and leveling of large areas.
Backfilling - means filling up any single or general excavation for
foundations, trenches, pits, etc. also in the presence of any
construction works and/or piping systems, cable routing, etc.
Subgrade - the ground supporting the road foundation, as well as the
embankment.
Doc. No:GT-QAQC-002 TASNEE HDPE-LDPE PLANT PROJECT
METHOD STATEMENT FOR EARTHWORKS: Page 5/11
Rev.3
EXCAVATION AND BACKFILLING
5.0 RESPONSIBILITIES
Foreman – Coordinate day to day activities of direct labor and sub-
contractors and responsible for the on-going quality and
production at the work face.
QC Inspector – Witness all tests performed in his designated area and carry
out detailed inspection prior to raising an AFI from
Integrated Management Team (IMT). All such tests should
be signed and certified by the individual performing the
test. Perform daily surveillance inspection of workmanship
and documentation activities.
Site Engineer – Provide technical information and oversees the day-to-day
activities of field supervision.
Site Manager – Manages and directs project construction activities
performed by the project team composed of personnel
assigned by the various functional departments.
6.0 SAFETY
6.1 Protection and safety shall be in accordance with approved TAL / OWNER
HSE Plan.
6.2 GAMA shall provide barricades, lights and any other preventive measures
according to the approved HSE Plan for personal safety during construction
to include fall prevention/protection when the depth of the excavation
exceeds two (2) m.
6.3 When the excavation has a depth of more than 1.2 m, a suitable shoring shall
be installed, sides shall be sloped back to a safe angle or benched,
excavated materials shall be kept as a minimum one (1) m from the edge of
the excavation and excess materials shall be moved to a spoil heap.
6.4 Access/egress shall be in accordance with approved TAL/GAMA safety
procedures.
6.5 Worker shall use ear protection/ear plug in using compaction
machine/equipment.
Doc. No:GT-QAQC-002 TASNEE HDPE-LDPE PLANT PROJECT
METHOD STATEMENT FOR EARTHWORKS: Page 6/11
Rev.3
EXCAVATION AND BACKFILLING
6.6 Fire control/protection (fire extinguisher) will be on stand-by for any fire
occurrence.
6.7 Compaction machine/equipment with inspection pass/ color code shall be
use at the site. Any damage / oil leaking (environmental spill) shall be
reported immediately to GAMA HSE Department.
6.8 All necessary Safety pre start-up form (STARRT) must be filed and
discussed to all workers concern.
8.0 GENERAL
8.1 As a general rule all excavated material may be used for backfilling. If no
otherwise specified in document, the material for back-filling shall be free of
all-organic matter, dirt, loose, foreign materials and debris.
8.2 This work is applied to any kind and depth of excavation by means of any
kind of machine or by hand.
8.3 Ground adjacent to all excavation shall be graded to prevent water from
running in.
9.1.7 When several close excavations are needed, the entire interested area may
be excavated together.
9.1.8 Adequate access for vehicles to the bottom, if needed, shall be foreseen.
9.1.9 Adequate drainage, such as temporary ditches shall be provided, if
necessary to avoid an accumulation of water inside the excavation.
9.1.10 Ground adjacent to all excavations shall be graded to prevent water
running in.
9.1.11 Permanent trench excavation shall not be used as temporary drainage
ditches.
9.2 BACKFILLING
9.2.1 Backfilling activities can be started only after approval from TAL/IMT.
9.2.2 Within 300 mm of pipe top, back-filling shall be hand tamped or board
shall be used to protect the pipe from damage caused by plate compactor
vibration.
9.2.3 For sewer and U/G piping the excavation bottom shall be free of rock and
coarse material.
9.2.4 Backfill to be in layers of 30 cm loose thickness.
9.2.5 Backfilling in presence of water inside the excavation is strictly prohibited.
9.2.6 Backfilling of item to be backfilled shall be executed in a uniform way and
the relevant materials that have not reached a sufficient strengthening
grade is prohibited.
Doc. No:GT-QAQC-002 TASNEE HDPE-LDPE PLANT PROJECT
METHOD STATEMENT FOR EARTHWORKS: Page 8/11
Rev.3
EXCAVATION AND BACKFILLING
9.2.7 Using for transportation proper trucks, covering etc. in order to avoid any
mudding on the traveled roads and to remove promptly any fortuitous
mudding due to this activity.
9.2.8 In case of backfilling of pipes and thin walls, the works shall be executed
simultaneously on both sides.
9.3 COMPACTION
9.3.1 Compaction in each layer shall be done by a suitable compaction
equipment or by hand operated equipment for restricted area in order to
reach not less than 95% of the maximum dry density as determined by
Modified Proctor Test (ASTM D 1557) as specified in technical
documentation.
12.0 ATTACHMENT
See attached Job Safety Analysis.