Development of A Delay Analysis System For A Railway Construction Project
Development of A Delay Analysis System For A Railway Construction Project
Abstract
Construction delays are one of the biggest issues facing the construction industry. The characteristics of
delay factors and their level of impact vary from project to project, ranging from a few days to years.
They have significant financial, environmental and social impact in construction projects; therefore, it is
vital to investigate the causes of delay and analyse their impact. In this context, the paper was initiated to
develop a model for analysing and quantifying the impacts of delay factors on railway construction
projects. The system was evaluated using a case study of track doubling project between Chengannur and
Mavelikkara. The analysis of case study using Delay Analysis System found that the doubling project
might be delayed by 135 months. Also the most sensitive delay factors were identified from the
sensitivity report.
Keywords: Critical Path Method, Delay Analysis system, Delay Factors, Frequency Index, Importance
Weight, Influence Value, Monte Carlo Simulation, Sensitivity Analysis, Severity Index, Questionnaire
Survey.
1. INTRODUCTION
Construction delay is a foremost problem facing the construction industry in almost all countries in the
world. Delays occur in almost every construction project and their magnitudes vary considerably from
project to project, ranging from a few days to years. It is generally understood that construction delay is
the most critical factor affecting the delivery of construction projects in terms of time, budget and the
required quality [17]. However, it is very important to identify the exact causes and their significance in
order to minimise and avoid the impact of delays in construction projects. Construction projects
completed on time were a signal of project efficiency [18]; however, construction processes depend on a
number of unpredictable factors that occur from various sources. These sources include the performance
of construction stakeholders, availability of resources, site conditions, contract types, weather conditions
and the contractual relations between stakeholders. However, it rarely happens that a project is completed
2. LITERATURE REVIEW
To identify the causes of construction delays, a detailed literature review was carried out. Previous
literature has shown that there are few research studies related to delay analysis methods in the
construction industry.
The major causes of time overrun in Hong Kong construction projects were identified in [10]. First
they identified the principal causes of delays in both building and civil engineering projects in Hong
Kong, and then investigated the relative importance weight of these causes. Secondly, they studied the
differences in the perceptions of the three major industry participants – clients, consultants and
contractors – to analyses the factors causing project delays.
The major causes of delays, effects of delays, and methods of minimising delays in construction
projects in Aceh, Indonesia were identified in [1]. A total of fifty-seven factors that caused delays were
identified. These factors were grouped into eight groups of causes of delays: contractor-related delays;
equipment-related delays; client-related delays; material-related delays; finance-related delays;
consultant-related delays; external-related delays; and manpower-related delays. These delay factors were
considered during the design of a questionnaire that aimed to rank the delay factors using the responses
collected from construction industry representatives, including consultants, contractors and owners. The
possible delay factors in construction projects are also categorised into internal and external delay factors
as follow:
However, the involvement of government, particularly in a developing country, where contracts are
awarded to the lowest bidders without analysing the technical capability of contractors, is one of the main
external factors delaying a project. Malaysia, Nigeria and Saudi Arabia have all reported this type of
problem as an external factor.
The paper [5] studied the effects of delays in project delivery in the Nigerian construction industry and
investigated how the effects of delays on project delivery and the total construction cost of building
projects can be minimised.
The paper [7] identified the causes of delays in construction in the Eastern Province of Saudi Arabia, and
tested the importance of the causes of delay between each of two groups of parties. They also studied the
differences in perceptions of the three major parties in involved, namely owners, contractors and
consultants.
The major causes of delay in construction projects in Malaysia and the perceptions of the different parties
regarding the causes and types of those delays were studied in [17].
From the review of literature it can be noticed that construction delay is a global phenomena and that
causes and effects of the delays in the construction industry can vary from country to country due to
differences in the geographical locations, environmental constraints, and techniques applied in the
3. RESEARCH METHODOLOGY
The methodology begins with the field study, which is the study on the doubling project at railway
construction department, Kayamkulam. For the study one of the recently completed project carried out by
the railway construction department Kayamkulam, which is the railway track doubling work is been
considered. The railway construction department no more does any construction works themselves, instead
they are all sub-contracted. The entire works involved are sub-contracted to various engineers on open
tendering. The methodology to carry out the project is given by a flow diagram shown in Figure 1.
The study began with a field study which was carried out at railway construction department,
Kayamkulam. In the study one of the recently commissioned doubling work, which is Chengannur-
Mavelikkara doubling work was studied. From the study it was found that almost all the associated works
in that project were delayed, and also the budget also overrun. This background study paved path for
literature survey to identify the delay factors responsible for construction delays.
A detailed literature survey was then carried out, from which some of the major delay factors in
construction industry could be found. With these factors identified through literature and the factors
identified through direct field study and interview a questionnaire was designed. This questionnaire was
then tested for reliability, validity and practicality through a pilot study (among civil engineering
students) and expert opinion. Then the actual survey was carried out among 10 railway engineers and 10
The equations to calculate the frequency index (FI), severity index (SI), importance weight (IW),
importance index (II), average weight (AW), influence value and activity duration are as below.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Random = random numbers generated by MCS for the selected type of risk distribution
The Railway Construction Department deals with various construction works like Track doubling,
Gauge works, Platform works, new track construction etc. Track Doubling is the work where a new track
is constructed in parallel with the existing track in order to control the rail traffic. Chengannur-
Mavelikkara track is 12km long. The work was commenced in 2005 and commissioned in 2012. The
various activities involved in the project are shown in Table 1.
Land
A 2 18 16
Acquisition
Rail Barricading
B 4 23 19
EW Ch93000-
C 9 48 39
95770
EW Ch95770-101450
D 8 39 31
EW Ch101450-
E 6 36 30
105600
Br.
F 128,129,130,13 6 22 16
3,136,141
Br.
G 116,125,126, ROB, RUB 6 32 26
H Br. 124 9 15 6
Collection &
I Stacking of Ballast 6 20 14
Collection &
J Stacking of Ballast 6 25 19
Collection &
K Stacking of Ballast 6 26 20
Signal &
L Telecommunication acm 6 14 8
FOB &
M 5 36 31
platform shelter
N Track linking 6 16 10
O Commissioning 2 2 0
The Critical path method (CPM) is a planning technique, which is normally used for activities and
resource planning. The CPM helps to identify the possible critical activities in a construction project that
are affected by critical resources. If some of the activities require other activities to finish before they can
start, then the project becomes a complex task to identify critical activities.
Path Duration(month)
A-B-C-I-L-N-O 35
A-B-D-I-L-N-O 34
A-B-E-I-L-N-O 32
A-B-F-I-L-N-O 32
A-B-G-I-L-N-O 32
A-B-H-I-L-N-O 35
A-B-C-I-M-N-O 34
A-B-D-I-M-N-O 33
A-B-E-I-M-N-O 31
A-B-F-I-M-N-O 31
A-B-G-I-M-N-O 31
A-B-H-I-M-N-O 34
Critical path is defined as the path with the longest duration. All activities lying on the critical path
are called critical activities. It can be observed from the table that there are only two paths with the
highest duration which are A-B-C-I-L-N-O and A-B-H-I-L-N-O. So, the critical activities are A, B, C,
H, I, J, K, L, N and O. The total duration is 35 months.
Table 4 gives the importance index values of the sub-category delay factors. Here the importance
index value is higher for the contractor/project management category. Ranking on the basis of importance
index is considered superior than ranking based on average weight. And hence the project management
category is the most critical category. Table 3 shows the importance index values of the main categories.
Among the main categories contractor has the highest importance weight, the value is 1.221 which is
higher as compared to all other categories.
Averag Importan
Catego Modul e ce Ran
ry us k
Weight Index
CON 0.534 2.288 1.221 1
OTHER
S 0.224 2.229 0.499 2
Avera Importan
Modulu ge ce
Category s Weig Rank
ht Index
0.03
C/MP 4 2.431 0.082 8
0.08
C/EQ 6 2.057 0.176 5
0.06
C/MT 8 2.513 0.170 6
0.34
C/PM 4 2.286 0.786 1
0.17
EF 2 2.363 0.406 2
From Figure 2 and 3, it is very clear that contractor is the main party responsible for the delay in the main
category and among sub-categories the project management issue stands first.
A. Simulation Results
The DAS was developed to assist construction managers and stakeholders to analyse and quantify the
possible impact of delay factors on construction projects. Project managers can take appropriate decision
and necessary measures to reduce the impact of delay factors before starting a construction project or
during the implementation stage to avoid further delay.
The evaluation of the simulation model of the DAS is done using the case study, Chengannur-
Mavelikkara track doubling project. In this case study, the doubling project was analyzed to quantify the
project duration, taking into account the impact of delay factors. Using the information discussed in the
sections above (such as critical activities, influence values, random numbers and equations), the possible
duration of the building project was quantified through the simulation model of the DAS.
The simulation was run with 1,000 iterations to determine the durations of the project activities, and
the results are presented in Figure 4. The figure shows that the project duration was predicted at around
42 months after considering a total of 58 delay factors. However, the project was originally estimated at
35 months. Comparing these values, it was found that the project might be delayed by 7 months when
taking into account the delay factors.
B. Sensitivity Analysis
Sensitivity analysis is used to identify sensitivity in project duration due to the variation in the influence
value of each delay factor affecting the project. Because the influence values are assigned an uncertainty
by integrating random numbers, its values varies in every trial of the simulation.
The Figure 5 shows the sensitivity of different delay factors on the total project duration. The
sensitivity value of “delay in materials delivery” is the highest and its value is 0.581. The sensitivity
value shows the effect of these delay factors on the system output.
5. CONCLUSION
The research study has introduced a new methodology to analyse and quantify the impact of delay
factors by developing a delay analysis system (simulation model). A framework of the system was
developed using the findings from the literature review and industry survey in railway construction
projects.
The survey results showed that contractors, rather than consultants and owners, were the most
responsible party for the delays in construction projects. The identification of the responsible party will
assist owners and clients in the decision-making process during the procurement of a public and private
construction project
The findings of the case study show an indicative figure of the possible delay in terms of time when
considering the critical delay factors affecting a construction project. The key contribution of this study is
a methodology development for analysing and quantifying the impact of delay factors in construction
projects.
ACKNOWLEDGMENT
My sincere thanks to all the railway engineers at railway construction department, Kayamkulam for
having helped me throughout the work. I would like to express profound gratitude to my internal guide
Ciby Thomas, for all the support and guidance she has offered in successful completion of this work. My
heartfelt gratitude to Mr. Raghunathan Rajesh for immensely helping me in organizing my work.
I thank my parents for being my backbone, and finally I thank almighty for all the blessings he has
showered through many.
REFERENCES
[1] Abd. Majid, M.Z. and McCaffer, R. , “Factors of non-excusable delays that influence contractors’ performance”, Journal of Management
in Engineering, ASCE May/June, pp: 42-4, 1998.
[2] Abdulhamid Shebob . et al ., “Development of a methodology for analysing and quantifying the impact of delay factors affecting
construction projects” , KICEM Journal of Construction Engineering and Project Management , vol.2, No. 3, pp. 17-30, 2012.
[3] Abdul Razaque. et al ., “ Fostering project scheduling and controlling risk management”, International Journal of Business and Social
Science Vol. 3 No. 14 , pp. 118-128,2012.
[4] Abdelhak Challal and Mohamed Tkiouat , “Identification of the causes of deadline slippage in construction projects: state of the art and
application “, Journal of Service Science and Management, 2012, Vol 5, pp: 151-159, 2012.
[5] Aibinu, A. and Jagboro, G. , “Effects of construction delays on project delivery in nigerian construction industry”, International Journal of
Project Management, 20(8), 593–99, 2002.
[6] Andy K.W. Ng ,” Optimizing the time performance of subcontractors in the building projects” , Australasian Journal of Construction
Economics and Building, Vol 10 (1/2), pp: 90‐ 102, 2010.
[7] Assaf, A. and Al-Hejji, S. , “Causes of delays in large building construction projects”, ASCE Journal of Management in Engineering, 11(2),
45–50, 2006.
[8] A. Cunningham. et al., “Application of delay-time analysis via monte carlo simulation”, Journal of Marine Engineering and Technology Vol
10, No 3, pp. 57-72, 2011.
[9] A. De Marco,” Planning and Scheduling”, Project Management for Facility Constructions, pp 89-119, 2011.
[10] Chan, D. W. M. and Kumaraswamy, M. M. A., “Survey of time-cost relationships in Hong Kong construction projects”, Building
Technology and Management Journal, Vol 20,pp 54-72, 1994.
[11] ChangTaek . et al.,” The Development of Probabilistic Time and Cost Data: Focus on field conditions and labor productivity “KICEM
Journal of Construction Engineering and Project Management , vol 1, pp: 37- 44, 2011.
[12] Chidambaram Ramanathan and SP Narayanan , “Construction delays causing risks on time and cost – a critical review “, Australasian
Journal of Construction Economics and Building, Vol 12 (1), pp: 37-57, 2012.
[13] Dawood, N. , "Estimating project and activity duration: a risk management approach using network analysis", construction management and
economics, Vol.16, pp 41– 48, 1998.
[14] D. Grover,” Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts”, 2002.
[15] Dale.R.Labitzke, “Planning scheduling and Project control”
[16] Fouad Ghraizi and Fahad Al-Azzaz,” Planning & Scheduling Techniques Used By Elseif Engineering Contracting Company”,
Construction Planning And Scheduling pp 1-27, 2005.
[17] Hancher, D.E. and Rowings, I. E., “Setting highway construction contract duration”, Journal of Construction Engineering and Management,
ASCE 107 2, pp. 169-179, 1981.
[18] Mansfield N. K., Ugwu O. O. and Doran T. , “Causes of Delay and Cost Overruns in Nigerian Construction Projects”, Journal of Project
Management; 12; 254-260, 1994.
[19] Wa’el, A, Azizah, S, and Mohd, R. , “Housing shortage for low-income in Yemen: causes and suggestions”, Engineering, Construction and
Architectural Management, Volume 14 No 2007 pp. 192-206, 2007.