REFERENCE - Pump Installation Procedure
REFERENCE - Pump Installation Procedure
CHTR
100 bar
Rolling Element Bearings
Installation/Operating Manual
Legal information/Copyright
Installation/Operating Manual CHTR
All rights reserved. The contents provided herein must neither be distributed, copied, reproduced, edited or
processed for any other purpose, nor otherwise transmitted, published or made available to a third party without
the manufacturer's express written consent.
Contents
1 General ..................................................................................................7
1.1 Principles ...........................................................................................................7
1.2 Installation of partly completed machinery .................................................... 7
1.3 Target group ..................................................................................................... 7
1.4 Other applicable documents ............................................................................ 7
1.5 Symbols .............................................................................................................8
2 Safety .....................................................................................................9
2.1 Key to safety symbols/markings ....................................................................... 9
2.2 General .............................................................................................................. 9
2.3 Intended use .....................................................................................................9
2.4 Personnel qualification and training ............................................................. 10
2.5 Consequences and risks caused by non-compliance with these operating
instructions ...................................................................................................... 10
2.6 Safety awareness ............................................................................................11
2.7 Safety information for the operator/user ..................................................... 11
2.8 Safety information for maintenance, inspection and installation work ..... 11
2.9 Unauthorised modes of operation ................................................................ 11
2.10 Explosion protection ...................................................................................... 12
CHTR 3 of 168
Contents
6 Commissioning/Start-up/Shutdown ...................................................51
6.1 User information ............................................................................................51
6.2 General information ....................................................................................... 51
6.3 Work to be carried out prior to commissioning/start-up ............................. 51
6.4 Commissioning/start-up ................................................................................. 61
6.5 Checklist for commissioning/start-up ............................................................ 65
6.6 Operation ........................................................................................................ 65
6.7 Operating limits .............................................................................................. 67
6.8 Measures to be taken for shutdown ............................................................. 69
6.9 Work after shutdown ..................................................................................... 71
6.10 Preservation for standstill .............................................................................. 73
6.11 Returning to service ...................................................................................... 74
7 Servicing/Maintenance .......................................................................75
7.1 User information ............................................................................................75
7.2 Supervision ...................................................................................................... 75
7.3 Maintenance ................................................................................................... 77
7.4 Dismantling the pump ...................................................................................80
7.5 Reassembling the pump ................................................................................. 95
7.6 Installing the pump into the system ............................................................ 113
7.7 Fastening the pump feet ............................................................................. 114
7.8 Fitting the piping and instruments ............................................................. 114
7.9 Fitting the contact guards ........................................................................... 114
7.10 Maintenance of the other pump set components ..................................... 114
7.11 Spare parts stock ........................................................................................... 115
4 of 168 CHTR
Contents
8 Trouble-shooting .............................................................................117
8.1 Trouble-shooting .......................................................................................... 117
CHTR 5 of 168
Glossary
Glossary
6 of 168 CHTR
1 General
1 General
1.1 Principles
This operating manual is supplied as an integral part of the type series and variants
indicated on the front cover. The manual describes the proper and safe use of this
equipment in all phases of operation.
The name plate indicates the type series and size, the main operating data, the order
number and the order item number. The order number and order item number
uniquely identify the pump (set) and serve as identification for all further business
processes.
KSB specialist personnel must be called in for installation, commissioning/start-up and
maintenance. KSB will only assume responsibility for faultless execution of the work
and for the safety of the personnel involved if dismantling/reassembly and
maintenance have been performed by KSB’s specialist team.
In the event of damage, immediately contact your nearest KSB service centre to
maintain the right to claim under warranty.
Noise characteristics (⇨ Section 9.2.1 Page 121)
CHTR 7 of 168
1 General
1.5 Symbols
Table 1: Symbols used in this manual
Symbol Description
✓ Conditions which need to be fulfilled before proceeding with the
step-by-step instructions
⊳ Safety instructions
⇨ Result of an action
⇨ Cross-references
1. Step-by-step instructions
2.
Note
Recommendations and important information on how to handle
the product
8 of 168 CHTR
2 Safety
2 Safety
All the information contained in this section refers to hazardous situations.
! DANGER
2.1 Key to safety symbols/markings
Table 2: Definition of safety symbols/markings
Symbol Description
! DANGER DANGER
This signal word indicates a high-risk hazard which, if not avoided,
will result in death or serious injury.
! WARNING WARNING
This signal word indicates a medium-risk hazard which, if not
avoided, could result in death or serious injury.
CAUTION CAUTION
This signal word indicates a hazard which, if not avoided, could
result in damage to the machine and its functions.
Explosion protection
This symbol identifies information about avoiding explosions in
potentially explosive atmospheres in accordance with EC Directive
94/9/EC (ATEX).
General hazard
In conjunction with one of the signal words this symbol indicates a
hazard which will or could result in death or serious injury.
Electrical hazard
In conjunction with one of the signal words this symbol indicates a
hazard involving electrical voltage and identifies information about
protection against electrical voltage.
Machine damage
In conjunction with the signal word CAUTION this symbol indicates
a hazard for the machine and its functions.
2.2 General
This manual contains general installation, operating and maintenance instructions
that must be observed to ensure safe pump operation and prevent personal injury
and damage to property.
The safety information in all sections of this manual must be complied with.
This manual must be read and completely understood by the specialist personnel/
operators responsible prior to installation and commissioning.
The contents of this manual must be available to the specialist personnel at the site
at all times.
Information attached directly to the pump must always be complied with and be
kept in a perfectly legible condition at all times. This applies to, for example:
▪ Arrow indicating the direction of rotation
▪ Markings for connections
▪ Name plate
The operator is responsible for ensuring compliance with all local regulations not
taken into account in this manual.
CHTR 9 of 168
2 Safety
▪ The pump must only be operated with the components selected by KSB.
▪ Never operate the pump without the fluid handled.
▪ Observe the minimum flow rates indicated in the data sheet or product literature
(to prevent overheating, bearing damage, etc).
▪ Observe the maximum flow rates indicated in the data sheet or product
literature (to prevent overheating, mechanical seal damage, cavitation damage,
bearing damage, etc).
▪ Do not throttle the flow rate on the suction side of the pump (to prevent
cavitation damage).
▪ Consult the manufacturer about any use or mode of operation not described in
the data sheet or product literature.
10 of 168 CHTR
2 Safety
CHTR 11 of 168
2 Safety
Sections of the manual marked by the Ex symbol apply to explosion-proof pump sets
also when temporarily operated outside potentially explosive atmospheres.
Only pumps/pump sets marked as explosion-proof and identified as such in the data
sheet must be used in potentially explosive atmospheres.
Special conditions apply to the operation of explosion-proof pump sets in accordance
with EC Directive 94/9/EC (ATEX).
Especially adhere to the sections in this manual marked with the Ex symbol.
The explosion-proof status of the pump set is only assured if the pump set is used in
accordance with its intended use.
Never operate the pump (set) outside the limits stated in the data sheet and on the
name plate.
Prevent impermissible modes of operation at all times.
2.10.1 Marking
Pump The marking on the pump refers to the pump part only.
Example of such marking: II 2 G c TX
Refer to the Temperature Limits table for the temperatures permitted for the
individual pump variants.
Shaft coupling An EC manufacturer's declaration is required for the shaft coupling; the shaft
coupling must be marked accordingly.
Motor The motor must be considered separately.
12 of 168 CHTR
2 Safety
2.10.5 Repair
Special regulations apply to repair work on explosion-proof pumps. Modifications or
alterations of the pump set may affect explosion protection and are only permitted
after consultation with the manufacturer.
CHTR 13 of 168
3 Transport/Temporary Storage/Disposal
3 Transport/Temporary Storage/Disposal
NOTE
The angle α depends on the lifting tackle; however it must never be wider than
120°.
14 of 168 CHTR
3 Transport/Temporary Storage/Disposal
3.4 Transport
DANGER
The pump or individual components could slip out of the suspension arrangement
Danger to life from falling parts!
▷ Always transport the pump or components in the specified position.
▷ Refer to the weights indicated for the individual components.
▷ Use suitable, permitted lifting accessories, e.g. self-tightening lifting tongs.
▷ Never attach the suspension arrangement to the free shaft end of the pump.
▷ Observe the applicable local accident prevention regulations.
▷ Use appropriate personal protective equipment.
DANGER
Improper transport
Risk of injury from lifting heavy components!
▷ Select lifting accessories which are suitable for the component weight.
▷ Always use the attachment points provided for the lifting accessories.
▷ Comply with the applicable health and safety regulations.
WARNING
Lack of stability
Serious injuries due to parts tipping over!
▷ Place the pump only on an area designed for this purpose.
▷ Comply with the requirements to be met by the load-bearing capacity of the
floor. Check the load-bearing capacity of the floor. Consult the building
drawing and general arrangement drawing.
▷ Give due attention to the position of the centre of gravity of the pump set.
▷ Refer to the table of weights for the weight of the pump (set) or packaging
unit.
CAUTION
Improper transport
Damage to the pump components!
▷ Always protect pump components from direct contact with chains or steel
ropes.
▷ Protect built-on accessories and pipes.
To determine the lifting capacity, give due consideration to the position of the centre
of gravity, the angle of spread and permissible bending radii of the lifting accessories
attached to the load to be lifted.
To transport the pump/pump set suspend it from the lifting tackle as shown below.
NOTE
The angle α depends on the lifting tackle; however it must never be wider than
120°.
CHTR 15 of 168
3 Transport/Temporary Storage/Disposal
a°
16 of 168 CHTR
3 Transport/Temporary Storage/Disposal
a°
CHTR 17 of 168
3 Transport/Temporary Storage/Disposal
DANGER
The pump rotor could slip out of the suspension arrangement.
Danger to life from falling parts!
▷ Never use steel ropes or chains for transport.
▷ Use manila ropes or plastic ropes.
▷ Transport the pump rotor in horizontal position.
Transport the pump rotor as shown.
CAUTION
Improper transport of strainers/filters
Damage to the strainer/filter through lifting tackle!
▷ Do not exert pressure on the strainer element and strainer meshes or damage
them.
▷ Transport pump set accessories by hand, if possible. If this is not an option
because of the weight, observe the transport options described in this manual.
18 of 168 CHTR
3 Transport/Temporary Storage/Disposal
Attach the lifting accessories as shown and/or in accordance with the relevant
manufacturer’s documentation.
α α
α
1 2 3
α α
α
4
6
Fig. 9: Transporting the pump set accessories
1 Conical strainer 2 Strainer housing
3 Basket strainer 4 Y-strainer
5 Cylindrical strainer 6 Minimum flow valve
WARNING
Lack of stability
Serious injuries due to parts tipping over!
▷ Place the cartrdige only on an area designed for this purpose.
▷ Comply with the requirements to be met by the load-bearing capacity of the
floor. Check the load-bearing capacity of the floor. Consult the building
drawing and general arrangement drawing.
▷ Give due attention to the position of the centre of gravity of the cartridge.
▷ Refer to the table of weights for the weight of the pump (set) or packaging
unit.
CHTR 19 of 168
3 Transport/Temporary Storage/Disposal
DANGER
The cartridge could slip out of the suspension arrangement
Danger to life from falling parts!
▷ Never use steel ropes or chains for transport.
▷ Always use hemp or plastic ropes.
▷ Transport the cartridge in a horizontal position.
<120°
3.5 Storage/preservation
If commissioning is to take place some time after delivery, we recommend that the
following measures be taken for storage:
CAUTION
Damage during storage by humidity, dirt, or vermin
Corrosion/contamination of the pump (set)!
▷ For outdoor storage cover the packed or unpacked pump (set) and accessories
with waterproof material.
CAUTION
Wet, contaminated or damaged openings and connections
Leakage or damage to the pump set!
▷ Only remove caps/covers from the openings of the pump set at the time of
installation.
CAUTION
Improper storage
Impairment of O-rings' sealing function!
▷ Do not store O-rings together with chemicals, solvents, fuels, acids, etc.
▷ Protect O-rings from light, in particular from direct sun exposure and strong
artificial light high in ultraviolet rays.
▷ Check the O-rings for damage before they are fitted.
Store the pump (set) in a dry, protected room where the atmospheric humidity is as
constant as possible.
20 of 168 CHTR
3 Transport/Temporary Storage/Disposal
Preservation
WARNING
Improper handling of materials and supplies
Risk of injury due to contact with hazardous substances!
▷ Observe the relevant safety instructions for the handling of hazardous
substances (wear safety goggles and protective gloves, for example).
Period of storage up to 12 The pump is supplied preserved for storage of up to 12 months. (Standard
months preservation)
Table 4: Measures taken for preservation
Type of preservation Preservative To be preserved
External preservation Tectyl 502-C made by All blank and uncoated
Valvoline GmbH, Hamburg parts (e.g. shaft ends,
couplings and flange faces)
Internal preservation Tectyl 502-C, made by All blank internal parts of
Valvoline GmbH, Hamburg the pump (e.g casing
(not applicable for pumps inside, shafts, impellers and
made of non-corroding diffusers)
materials)
Period of storage longer If the requisite preservation measures have not been performed by KSB (special
than 12 months preservation), they must be discussed with and approved by KSB prior to putting the
pump into storage.
Table 5: Measures to be taken for preservation
Type of preservation Preservative To be preserved
External preservation Tectyl 502-C made by All blank and uncoated
Valvoline GmbH, Hamburg parts (e.g. shaft ends,
couplings and flange faces)
Internal preservation Glycol/water mixture Fill pump interior
All blank internal parts of
the pump (e.g casing
inside, shafts, impellers and
diffusers)
WARNING
In the case of storage periods of more than 5 years, the sealing function of O-rings
may be impaired.
Rick of injury from leakage of hot, pressurised fluid handled!
▷ After a storage period of more than 5 years, the pump must be dismantled
before it is installed, and the O-rings must be replaced.
▷ Check the O-rings for damage before they are fitted.
CHTR 21 of 168
3 Transport/Temporary Storage/Disposal
NOTE
If required, a blank certificate of decontamination can be downloaded from the
KSB web site at: www.ksb.com/certificate_of_decontamination
3.7 Disposal
WARNING
Fluids, consumables and supplies which are hot or pose a health hazard
Hazard to persons and the environment!
▷ Collect and properly dispose of flushing fluid and any residues of the fluid
handled.
▷ Wear safety clothing and a protective mask, if required.
▷ Observe all legal regulations on the disposal of fluids posing a health hazard.
1. Dismantle the pump (set).
Collect greases and other lubricants during dismantling.
2. Separate and sort the pump materials, e.g. by:
- Metals
- Plastics
- Electronic waste
- Greases and other lubricants
3. Dispose of materials in accordance with local regulations or in another
controlled manner.
22 of 168 CHTR
4 Description of the Pump (Set)
4.3 Designation
Example: CHTR 5 / 6 or CHTR 5 / 1+5
Table 6: Key to the designation
Code Description
CHT Type series
R Additional code
5 Size
6 Number of stages (single-entry inlet)
1+5 Number of stages (double-entry inlet)
8
1
9
Ord.-No. Year 10
2
3 Ser.-No. Type 11
4 Item-No. Test pressure bar 12
5 Q m3/h H m 13
6 n 1/min t °C
7 ρ kg/dm3 14
MAWP bar MAWP @ °C
Bearings
ZN 3823 - E231
CHTR 23 of 168
4 Description of the Pump (Set)
▪ Single-entry or double-entry
▪ Multistage
▪ Sealing between the casings by means of O-rings or gaskets
▪ Nozzle positions
– Suction nozzle: radial, vertically to the top
– Discharge nozzle: radial, vertically to the top
– Tapping nozzle: Radial, possible in all stage casings, in various directions
Bearings Depending on pump size and design:
▪ Radial bearing
– Rolling element bearing, uncooled, oil ring lubrication
– Rolling element bearing, cooled, oil ring lubrication
– Rolling element bearing, oil mist lubrication
– Plain bearing, forced-feed lubrication
▪ Thrust bearing
– Rolling element bearing, cooled, oil ring lubrication
– Rolling element bearing, oil mist lubrication
– Plain bearing, forced-feed lubrication
Balancing device ▪ Axial thrust balancing by hydraulic balancing device on discharge side
▪ Balancing by drum or double drum
Shaft seal Depending on pump size and design:
▪ Mechanical seal, uncooled, mating ring cooling, injection or circulation
▪ Shaft equipped with a replaceable shaft sleeve in the shaft seal area
Flanges ▪ Mating dimensions to ASME
1 2 3 4 5
6 7 8 9 10 11 12 13 14 15 16
24 of 168 CHTR
4 Description of the Pump (Set)
CHTR 25 of 168
4 Description of the Pump (Set)
NOTE
Whenever dynamic rotor balancing has to be performed at site, this should be done
at 80 % of the critical speed, without fluid, by means of a balancing machine.
Table 9: Bearing
Pump end Size
Drive end NU 310 C3
Non-drive end 7310B-G
Table 10: Relevant drawings
Description Drawing number Comment
General arrangement drawing F30459B
Sectional drawing PR75525A
Piping & instrumentation drawings PR75593 C
Table 11: Illustrations for the removal/assembly of components
Description Drawing number Comment
Scaffolding UA3 37814 01 Cartridge removal
Puller & pusher kit Removal of throttle bush 542, rolling
UA3 37819 01
element bearings and balance drum
603.
As-built dimensions UA3 37818 01
Clamping kit UA3 37816 01
26 of 168 CHTR
5 Installation at Site
5 Installation at Site
DANGER
Improper installation in potentially explosive atmospheres
Explosion hazard!
Damage to the pump set!
▷ Comply with the applicable local explosion protection regulations.
▷ Observe the information in the data sheet and on the name plates of pump and
motor.
DANGER
Unprotected floor openings and/or foundations
Danger of death from falling!
▷ Secure the danger zone.
▷ Observe the applicable local occupational safety and accident prevention
regulations.
WARNING
Installation on mounting surface which is unsecured and cannot support the load
Personal injury and damage to property!
▷ Use a concrete of compressive strength class C12/15 which meets the
requirements of exposure class XC1 to EN 206-1.
▷ The mounting surface must have set and must be completely horizontal and
even.
▷ Observe the weights indicated.
DANGER
Insufficient stability of pump set as a result of incorrect dimensioning and fastening
of the baseplate (unless included in KSB's scope of supply)
Risk of pump tipping over!
▷ Prior to commissioning, provide proof that the baseplate is adequately
dimensioned to ensure the pump set’s stability, and proof of compliance with
the maximum permissible vibration level.
▷ Make sure that the vibrations do not exceed the specified limits.
✓ Proper illumination is available at the place of installation.
✓ Suitable alignment devices are available.
✓ In the area of the baseplate grouting and at the side walls of the holes for the
foundation bolts, the foundation has rough surfaces to allow for better bonding.
1. Check the structural requirements.
All structural work required must have been prepared in accordance with the
dimensions stated in the outline drawing/general arrangement drawing.
CHTR 27 of 168
5 Installation at Site
DANGER
Improper transport
Danger to life from falling parts!
▷ Use a stable mounting frame.
▷ Always coordinate all unpacking work with the responsible site management/
operator.
▷ Use personal protective equipment.
WARNING
Parts falling down during unpacking
Risk of crushing injuries!
▷ Secure loose parts (e.g. box lids) against falling down.
CAUTION
Open or closed connections and openings
Damage to the pump!
▷ During installation, do not open connections and openings earlier than
necessary. (All openings and connections are closed at the factory.)
▷ Prior to commissioning/start-up, check on the basis of the information given in
(⇨ Section 6 Page 51) whether the openings and connections must be open or
closed.
▪ Do not unpack the pump set components until immediately before the
installation work starts. Take care not to damage the cable.
▪ The consignee of the components supplied is responsible for disposal of the
packaging.
▪ Completely cover the unpacked pump set components on site to protect them
against dirt, moisture, spark discharge, grinding dust and other harmful ambient
influences. Take special care to adequately protect instruments, electric cables
and wiring ducts.
▪ Spare parts and parts which are not immediately needed must be stored.
NOTE
If components of the pump set became damaged, wet or dirty, inform KSB.
NOTE
If the pump has been specially preserved for storage of more than 12 months or sea
transport, the necessary measures for removal of preservation prior to installation
must be carried out. (⇨ Section 6.3.1 Page 51)
28 of 168 CHTR
5 Installation at Site
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
CHTR 29 of 168
5 Installation at Site
WARNING
Risk of hot oil escaping as a result of an improperly mounted/dismantled coupling
cover
Risk of burns!
Damage to the coupling!
▷ Do not damage the seal elements and sealing surfaces.
▷ Never operate the coupling without a lubricant.
▷ Prior to putting the coupling into service, check the coupling cover for correct
installation and sealing.
1. Remove all pipe connections on the cover.
2. Remove the taper pins and screws of the cover split joints.
3. Unscrew the screws in the upper part of the coupling cover.
4. Remove the upper half of the coupling cover.
5. Remove the internal injection lines.
6. Disconnect the lower half of the coupling cover from the flange and remove
this half.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
CAUTION
Improper dismantling
Damage to bearings and coupling parts!
▷ Remove coupling hubs using a puller.
▷ Never strike the coupling hubs.
WARNING
Falling coupling parts
Risk of crushing from falling parts!
▷ Secure coupling parts against falling down.
▷ Wear safety shoes.
CAUTION
Improper mounting of elastomers
Elastomers' sealing function reduced!
▷ Never use elastomeric parts again which have been heated.
▷ As a general rule, always use new elastomeric parts.
30 of 168 CHTR
5 Installation at Site
NOTE
Observe the marking between coupling hub and shaft. (⇨ Section 7.4.4 Page 83)
1. Permissible tolerance at the pump shaft ≤ 0.03 mm/ 0.0012 inch. If this value is
exceeded, inform KSB.
2. After every 90° turn, read measured values again.
3. Permissible tolerance at the motor shaft, see the data provided by the
manufacturer.
WARNING
Hot surfaces due to heating of components for assembly/dismantling
Risk of burns!
▷ Wear heat-resistant protective gloves.
▷ Remove flammable substances from the danger zone.
4. To facilitate fitting, the coupling hubs may be heated uniformly to a
temperature of 80 °C max. Elastomeric parts must be removed before heating.
Elastomeric parts which have been heated must not be used any more.
CHTR 31 of 168
5 Installation at Site
32 of 168 CHTR
5 Installation at Site
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
CHTR 33 of 168
5 Installation at Site
from the foundation side through the special foundation bolt holes into the
baseplate holes and screw on the nuts until the bolt thread projects by about 10
mm.
3. Place the baseplate onto the levelling screws and align the baseplate using the
screws. Check the alignment in relation to the foot supporting surfaces both
parallel to and 90° to the foundation centreline using a spirit level (accuracy <
0.3 mm/m). The foundation bolts must hang freely in the foundation holes.
4. Set the pump set components which are not mounted on the baseplate in place
on the baseplate as described in the manufacturer’s product literature. If
coupling hubs are mounted on the pump set components, the markings on the
coupling parts to be connected must be identical.
5. Check the baseplate alignment once again in relation to the foot supporting
surfaces both parallel to and 90° to the foundation centreline using a spirit level
(accuracy < 0.3 mm/m). Correct any deviations which might have occurred under
the load of the components using the levelling screws.
6. Fasten the plates and nuts of the special foundation bolts at the bottom side of
the foundation to the special foundation bolts.
The plates for the special foundation bolts must rest evenly on the foundation.
7. Tighten the nut of the special foundation bolts. Refer to the general
arrangement drawing for bolt tightening torque.
DANGER
Impermissible temperatures at the coupling or bearings caused by misalignment of
the coupling
Explosion hazard!
▷ Make sure that the coupling is correctly aligned at all times.
WARNING
Improper coupling alignment
Overloading or destruction of coupling!
Risk of injury from parts flying off!
▷ Align the coupling properly.
▷ When performing alignment, take into account any thermal expansion of the
machines to be coupled.
CAUTION
Misalignment of pump and motor shafts
Damage to pump, motor and coupling!
▷ Always check the coupling after the pump has been installed and connected to
the piping.
▷ Also check the coupling of pump sets supplied with pump and motor mounted
on the same baseplate.
CAUTION
Increased wear due to dry running
Damage to the pump set!
▷ Never operate the pump set without liquid fill.
▪ Align the pump set components in accordance with the manufacturer’s product
literature.
▪ Coupling alignment starts with the drive which is the reference point for aligning
all other pump set components.
The pump is the last component to be aligned.
Exception:
34 of 168 CHTR
5 Installation at Site
Pumps equipped with feet underneath the pump body which are already fitted
and pinned to the baseplate cannot be aligned laterally. In this case the pump is
the reference point for alignment of the other pump set components; the drive is
the last component to be aligned.
▪ In the case of motors with axial tolerance, their rotors must be placed in the
magnetic centre as described in the manufacturer’s documentation. This rotor
position must not be altered during the full duration of alignment work.
DANGER
Impermissible temperatures at the coupling or bearings caused by misalignment of
the coupling
Explosion hazard!
▷ Make sure that the coupling is correctly aligned at all times.
CAUTION
Incorrect measurement results and damage to the alignment device
Coupling misalignment!
Damage to the pump set!
▷ Never turn the coupling by means of the alignment device.
CHTR 35 of 168
5 Installation at Site
36 of 168 CHTR
5 Installation at Site
A B
Fig. 23: Checking the alignment of a coupling without spacer (example)
A Coupling hub used as a reference B Coupling hub to be aligned
point for alignment
Va
VR
CHTR 37 of 168
5 Installation at Site
VR
SMin.
38 of 168 CHTR
5 Installation at Site
1 2 3
CHTR 39 of 168
5 Installation at Site
40 of 168 CHTR
5 Installation at Site
- Fill at least 1/3 of each field of the baseplate with non-shrinking grouting
compound (e.g. Pagel concrete grout), minimum compressive strength class C
25/30, grain size ≤ 8 mm. The remaining 2/3 of the fields may be filled with
standard concrete of this quality. KSB recommends that all fields be completely
grouted with non-shrinking concrete grout. Produce flowability with the help
of a solvent. Complete grouting without major interruptions.
- In order to avoid cavities, the grouting compound must be compacted.
4. When the grouting compound has set, check the nuts of the special foundation
bolts for tightness once again using a torque wrench. Observe the tightening
torque!
5. Check coupling alignment and re-align, if necessary.
5.16 Piping
DANGER
Improper connection of auxiliary lines
Explosion hazard from escaping leakage or fluid!
▷ Correctly install the auxiliary lines.
▷ Observe the maintenance and monitoring schedules.
5.16.1 Prerequisites
▪ The pump set has been earthed.
▪ The pipelines have been anchored in close proximity to the pump and connected
without transmitting any stresses or strains.
▪ With short pipelines, the nominal diameters should be at least equal to the
nominal diameters of the pump nozzles. For long pipelines, the most economical
nominal diameter has to be determined from case to case.
▪ Adapters to larger diameters should have a diffuser angle of approximately 8° in
order to avoid any pressure losses caused by the formation of air pockets.
▪ The nominal diameters of the pipelines are at least equal to the nominal
diameters of the pump nozzles.
▪ The general arrangement drawing shows which pipes, valves and instruments are
included in our scope of supply and how they are arranged.
▪ All pipes in the baseplate area have been completely mounted at the factory.
▪ Make and adapt any possibly required connecting pipes in accordance with the
general arrangement drawing (offset at flange connections and pipe unions is
not permitted.).
▪ Pipes supplied by KSB have been cleaned and closed. Nevertheless their interior
must be checked for impurities which might have been caused afterwards and be
cleaned, if required.
▪ As a general rule, pipes made on site must be cleaned prior to final mounting.
▪ Do not remove blind flanges or covers on pump nozzles and pipe connections
including any packaging with desiccants possibly attached to them until
immediately before the relevant pipes are connected.
CHTR 41 of 168
5 Installation at Site
CAUTION
Solids inside the pump or in the pipelines.
Increased wear or blockages!
▷ When flushing the piping, the pump must as a rule be protected against
welding beads, scale and other impurities.
▷ Use pipe bypasses or filters to prevent solids from entering the pump.
CAUTION
Cleaning with a high-pressure steam-jet air ejector
Destruction of plastic parts through high-pressure steam-jet air ejector.
▷ Never clean the cooling circuit with a high-pressure steam-jet air ejector.
Permissible cleaning methods:
▪ The pipes may be blown through with compressed air.
▪ If the pipes have been welded with forming gas, they may be cleaned using a
high-pressure steam-jet air ejector at a steam temperature of at least 110 °C.
WARNING
Fluids posing a health hazard
Hazard to persons and the environment!
▷ Observe all legal regulations on the disposal of fluids posing a health hazard.
▷ Observe the relevant safety instructions for the handling of hazardous
substances (wear protective clothing and mask, if required).
CAUTION
Caustic damage to auxiliary systems
Leaks on flexible pipe parts!
▷ Never pickle flexible pipe parts.
Pickle oil pipes with dilute hydrochloric acid.
Neutralise oil pipes with a 0.5 % soda solution (500 g of soda/100 l of water).
Composition of the pickling solution for 100 litres:
▪ 30 l of concentrated hydrochloric acid (37% concentration)
▪ 70 l of water
▪ Temperature: Ambient temperature
1. Screw off the oil pipes and close one side.
2. Fill the pipes with the pickling solution and allow it to react until the inside pipe
surfaces are cleaned to bright metal, however 4 hours as a maximum.
After this procedure there must be no rust or scale particles left; remove
tenacious scale residues, if any, using a bottle brush.
3. Drain the pipes and flush them thoroughly with cold water.
4. Neutralise any possibly existing acid residues by filling the pipes with a soda
solution in a 0.5 % concentration.
5. After about 1 or 2 hours drain the pipes and flush them thoroughly with cold
water.
6. Immediately blow hot air through the pipes and dry them.
7. Immediately afterwards coat the pipes with the oil intended for this purpose,
for example by spray-coating, or filling and subsequent draining.
42 of 168 CHTR
5 Installation at Site
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
NOTE
The strainer in the inlet line is destined to stop welding beads, scale and other
impurities (that come off the piping with time) from entering the pump. It is not
destined to remove any inadmissible particles entrained in the fluid handled due to
an excessive solids content.
For installing the strainer refer to the manufacturer's product literature.
CAUTION
Improper transport of strainers/filters
Damage to the strainer/filter through lifting tackle!
▷ Do not exert pressure on the strainer element and strainer meshes or damage
them.
▷ Transport pump set accessories by hand, if possible. If this is not an option
because of the weight, observe the transport options described in this manual.
1. Prior to installation, perform a visual inspection of the inlet pipe between
strainer and pump. Clean it, if required.
2. Install the strainer in the inlet line as close to the pump nozzle as possible.
3. For differential pressure monitoring a drilled hole is provided upstream and
downstream of the strainer insert or at the strainer housing.
CHTR 43 of 168
5 Installation at Site
DANGER
Impermissible loads acting on the pump nozzles
Danger to life from leakage of hot, toxic, corrosive or flammable fluids!
▷ Do not use the pump as an anchorage point for the piping.
▷ The pipelines have been anchored in close proximity to the pump and
connected without transmitting any stresses or strains.
▷ Observe permissible forces and moments at the pump nozzles.
▷ Take appropriate measures to compensate thermal expansion of the piping.
CAUTION
Incorrect earthing during welding work at the piping
Destruction of rolling element bearings (pitting effect)!
▷ Never earth the electric welding equipment on the pump or baseplate.
▷ Prevent current flowing through the rolling element bearings.
NOTE
It is recommended to install check and shut-off elements in the system, depending
on the type of plant and pump. However, such elements must not obstruct proper
drainage or hinder disassembly of the pump.
1. Thoroughly clean, flush and blow through all vessels, pipelines and connections
(especially of new installations).
2. Before installing the pump in the piping, remove the flange covers on the
suction and discharge nozzles of the pump.
CAUTION
Welding beads, scale and other impurities in the piping
Damage to the pump!
▷ Free the piping from any impurities.
▷ If necessary, install a filter.
▷ Comply with the instructions set out in (⇨ Section 5.16.4 Page 43) .
44 of 168 CHTR
5 Installation at Site
CAUTION
Inadmissible forces at the flange connections
Overloaded pump nozzles and leakage!
▷ It must be possible to insert all bolts of the flange into their respective holes
and to remove them without becoming bolt bound (off-set holes).
▷ It must be possible to bring the pipes into their mounting position with one
hand.
▷ It must be possible to prise apart the pump nozzle flanges by approx. 300 mm.
(Fitting the flange seal)
▷ Never use flange bolts to tighten the flanges.
3. If the flange seal has not yet been fitted, insert flange seal. For this purpose, use
an appropriate tool to prise apart the flanges in order to fit the flange seal.
4. Connect the pump nozzles with the piping.
CAUTION
Aggressive flushing and pickling agents
Damage to the pump!
▷ Match the cleaning operation mode and duration for flushing and pickling
service to the casing and seal materials used.
NOTE
Where fluid has to be pumped out of a vessel under vacuum, it is recommended to
install a vacuum balance line.
CHTR 45 of 168
5 Installation at Site
1 2 3 4
5 6
Fig. 30: Vacuum balance system
1 Vessel under vacuum 2 Vacuum balance line
3 Shut-off element 4 Swing check valve
5 Main shut-off element 6 Vacuum-tight shut-off element
NOTE
An additional line (from the pump discharge nozzle to the balance line) fitted with
a shut-off element facilitates venting of the pump before start-up.
CAUTION
Impermissible piping layout
Damage to the balancing system
▷ When installing the bypass line and the balancing line, the minimum flow
diagram and/or P + I diagram must be observed.
▷ Install an orifice immediately ahead of the inlet vessel to avoid vaporisation.
DANGER
Incorrect electrical installation
Explosion hazard!
▷ For electrical installation, also observe the requirements of IEC 60079-14.
▷ Always connect explosion-proof motors via a motor protection switch.
DANGER
Work on the pump set by unqualified personnel
Danger of death from electric shock!
▷ Always have the electrical connections installed by a trained and qualified
electrician.
▷ Observe regulations IEC 60364 and, for explosion-proof models, EN 60079.
46 of 168 CHTR
5 Installation at Site
WARNING
Incorrect connection to the mains
Damage to the mains network, short circuit!
▷ Observe the technical specifications of the local energy supply companies.
1. Check the available mains voltage against the data on the motor name plate.
2. Select an appropriate start-up method.
NOTE
A motor protection device is recommended.
5.17.1 Earthing
DANGER
Electrostatic charging
Explosion hazard!
Fire hazard!
Damage to the pump set!
▷ Connect the PE conductor to the earthing terminal provided.
NOTE
In compliance with IEC 60034-8, three-phase motors are always wired for clockwise
rotation (looking at the motor shaft stub).
The pump's direction of rotation is indicated by an arrow on the pump.
1. Match the motor's direction of rotation to that of the pump.
2. Observe the manufacturer's product literature supplied with the motor.
CHTR 47 of 168
5 Installation at Site
DANGER
Lack of necessary monitoring and alarm equipment
Failure of pressurised components!
Explosion hazard
Risk of injury in the event that the hot, pressurised fluid handled escapes!
▷ Mount the monitoring and alarm equipment necessary to ensure operating
reliability.
General
▪ Choose a pressure gauge with an adequate measuring range!
▪ Do not remove the screwed plugs of the connection points until immediately
before mounting.
Pressure gauges
▪ Insert the sealing washer and screw the pressure gauge into place with a
clamping nut.
Thermometer (bearing)
▪ Insert the seal element. Screw in the thermometer.
Oil sight gauge or constant-level oiler
▪ Screw in the oil sight gauge or constant-level oiler including sealing tape or
liquid seal. Lengthening pieces, if required, are included in the delivery.
Resistance thermometer or thermocouple
▪ When installing standard resistance thermometers observe the assembly
instructions. (⇨ Section 9 Page 121)
▪ For the feeler length and the threaded connection required for the respective
measuring point, please refer to the list of measuring points and check the
length at the place of installation.
▪ Insert the seal element. Screw in the resistance thermometer or thermocouple.
48 of 168 CHTR
5 Installation at Site
▪ Run the electric connecting cables in cable conduits until just before reaching the
measuring point and have them connected by authorised personnel.
Differential pressure monitoring
1. Fasten the differential pressure monitoring equipment to the holder provided
on the baseplate.
2. Fasten the instrument leads at the intended connection points and install them
according to the constraints on site.
3. Run the electric connecting cables in cable conduits until just before reaching
the measuring point and have them connected by authorised personnel.
Vibration sensors and shaft trajectory measurement
1. For information on the sensor for the respective measuring point, please refer
to the list of measuring points and check at the place of installation.
2. Install in accordance with the manufacturer’s instructions.
3. Run the electric connecting cables in cable conduits until just before reaching
the measuring point and have them connected by authorised personnel.
CHTR 49 of 168
5 Installation at Site
NOTE
The manufacturer’s product literature is binding for all work performed on the
pump/set
NOTE
Items on this check list that are not found in the instruction manual do not apply.
50 of 168 CHTR
6 Commissioning/Start-up/Shutdown
6 Commissioning/Start-up/Shutdown
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
DANGER
Work on the pump set by unqualified personnel
Danger of death from electric shock!
▷ Always have the electrical connections installed by a trained electrician.
▷ Observe regulations IEC 30364 (DIN VDE 0100) and, for explosion-proof models,
EN 60079.
▷ The pump set's electrical equipment must comply with the general
requirements of the EN 60204-1 standard.
WARNING
Fluids, consumables and supplies which are hot or pose a health hazard
Hazard to persons and the environment!
▷ Collect and properly dispose of flushing fluid and any residues of the fluid
handled.
▷ Wear safety clothing and a protective mask, if required.
▷ Observe all legal regulations on the disposal of fluids posing a health hazard.
CHTR 51 of 168
6 Commissioning/Start-up/Shutdown
NOTE
Observe the manufacturer's instructions for application/removal of the preservative.
6.3.2 Work to be carried out prior to restart after standstill > 12 months
1. Dismantle the pump-end coupling hub.
2. Dismantle the bearings.
3. Remove the mechanical seal and check it in accordance with the manufacturer’s
product literature.
If the mechanical seal is clean and undamaged, it may be re-installed. Otherwise
a new mechanical seal must be installed.
4. Re-mount the bearings and lift the pump rotor if the pump is equipped with
plain bearings.
5. Re-mount the pump-end coupling hub.
6.3.4 Flushing the lube oil circuit with oil (if applicable)
DANGER
Ignition of lubricant leakage on hot pump surfaces
Explosion hazard!
▷ The ignition temperature of the lubricant should exceed the maximum surface
temperature of the pump by at least 50 K.
Oil quality When operating the pumps in potentially explosive atmospheres, lubricants have to
be selected whose ignition temperature / flash point exceeds the maximum surface
temperature of the pump by at least 50 K. Recommended oil quality (⇨ Section 9
Page 121)
52 of 168 CHTR
6 Commissioning/Start-up/Shutdown
CAUTION
Incorrect commissioning/start-up
Damage to the bearings!
▷ Do not perform oil flushing until immediately before commissioning/start-up.
▷ If commissioning/start-up is delayed by more than one month, repeat the oil
flushing.
1. Dismantle the pump-end coupling hub.
2. Dismantle the bearings.
3. For oil flushing, mount the bearing housings including existing labyrinth rings
and the thrower, but without internal bearing parts (bearing shell, bearing
segment carriers, thrust bearing plate, etc.).
4. Check whether all connections on the bearing housings and covers are closed
with plugs.
5. Mount the coupling cover, if applicable.
6. Check all the connection points of the oil circuit; connect and seal if required.
7. Close the oil supply ports of the coupling cover, if applicable.
8. Fully open all throttle valves in the oil supply pipes.
9. Switch on the oil supply unit or auxiliary oil pump and check for leakage.
10. Check the oil flow at the oil sight gauge in the oil return lines.
11. Check the oil level of the oil reservoir and top up, if required.
When the cooling circuits and pipes are filled and vented, the oil level shall be
in the middle between the minimum and maximum mark of the oil sight
gauges.
12. Change over and clean the filters of the oil circuits frequently, see the
manufacturer’s catalogue.
13. Switch off the oil supply unit or auxiliary oil pump when the oil filters are free
from dirt for at least eight hours.
14. Check the oil quality. If required, clean or replace the oil.
15. Re-install the pump bearings and lift the pump rotor.
16. Re-mount the pump end coupling hub.
DANGER
Ignition of lubricant leakage on hot pump surfaces
Explosion hazard!
▷ The ignition temperature of the lubricant should exceed the maximum surface
temperature of the pump by at least 50 K.
CAUTION
Incorrect oil level in bearing housing
Damage to the pump!
▷ Check the oil level only during standstill of the pump!
CHTR 53 of 168
6 Commissioning/Start-up/Shutdown
CAUTION
Unsuitable time for flushing with oil
Damage to the bearings!
▷ Do not perform oil flushing of the oil lines until immediately before
commissioning/start-up.
▷ If commissioning/start-up is delayed by more than one month, repeat the oil
flushing.
General information
▪ During operation, the oil level in the bearing housing drops.
▪ An excessive oil level leads to a temperature rise and to leakage of the fluid
handled or oil.
▪ An inadequate oil level results in insufficient lubrication and bearing damage.
▪ Refer to the technical specifications section for the oil quantity/quality.
▪ Filter the oil prior to filling it in; filter mesh size 30 µm.
▪ After a standstill of more than 12 months, check the quality of the oil. Clean or
replace the oil if necessary.
▪ Fill the pump set components with lubricant in accordance with the
manufacturer’s product literature.
▪ Observe the permissible ambient temperatures. (⇨ Section 6.7.2 Page 68)
For recommended oil quality, oil quantity and oil change intervals refer to: (⇨ Section
9.2.8 Page 128)
54 of 168 CHTR
6 Commissioning/Start-up/Shutdown
3. Fill the reservoir of constant-level oiler 638 with oil and return it to its operating
position.
4. Re-insert vent plug 913 with gasket 400.05.
5. After a short time check whether the oil level in the reservoir has dropped.
It is important to keep at least one third of the reservoir filled at all times. If the
oil level is too low, top it up with oil.
DANGER
Temperature increase resulting from contact between rotating and stationary
components
Explosion hazard!
Damage to the pump set!
▷ Never check the direction of rotation by starting up the unfilled pump set.
▷ Separate the pump from the motor to check the direction of rotation.
CAUTION
Pump and motor running in the wrong direction of rotation
Damage to the bearing and shaft seal!
▷ Pay attention to the rotation arrow on the drive end bearing housing.
▷ The direction of rotation of the drive must correspond to the direction
indicated in the general arrangement drawing.
If the pump set is driven by an electric motor, the direction of rotation of the motor
must be checked prior to commissioning/start-up.
Prerequisites
▪ Check the direction of rotation prior to the final assembly of the coupling (motor
alone is running).
▪ Observe the manufacturer’s documentation.
▪ The electric motor is provided with a lubricant.
DANGER
Mistake in the electrical connections
Danger of death from electric shock!
Short circuit, motor damage or pump is running in the wrong direction!
▷ Mark the connections in the terminal box.
WARNING
Starting of the motor for checking the direction of rotation
Risk of injury due to contact with unprotected or rotating parts or parts flying off!
▷ Remove or fasten any movable parts on the motor shaft.
▷ Never touch any unprotected, rotating parts.
CHTR 55 of 168
6 Commissioning/Start-up/Shutdown
CAUTION
Incorrect axial clearance
Damage to the bearings!
▷ In the case of electric motors with axial tolerance, re-align the motor shaft
coupling hub in line with the actual magnetic centre, if required. If the coupling
has a spacer, it must be possible to mount and remove it.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
5. Secure the drive against unintentional start-up.
56 of 168 CHTR
6 Commissioning/Start-up/Shutdown
▪ It must be possible to rotate the pump rotor by hand, and it may only be rotated
in the direction of rotation of the pump. If necessary, attach an appropriate tool
at the coupling hub.
▪ If the pump is fitted with a balance disc without lift-off device, move the pump
rotor towards the non-drive end by approx. 1 mm before you turn it by hand.
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
WARNING
Unprotected rotating coupling
Risk of injury by rotating shafts!
▷ Always operate the pump set with a coupling guard.
If the customer specifically requests not to include a coupling guard in KSB's
delivery, then the operator must supply one!
▷ Observe all relevant regulations for selecting a coupling guard.
At the end of all preparatory work to be carried out for start-up, mount all protective
equipment (e.g. coupling guard, contact guard, etc.) and check for correct
functioning.
Operate the pump (set) only after all protective equipment has been fitted.
CHTR 57 of 168
6 Commissioning/Start-up/Shutdown
WARNING
Risk of hot oil escaping as a result of an improperly mounted/dismantled coupling
cover
Risk of burns!
Damage to the coupling!
▷ Do not damage the seal elements and sealing surfaces.
▷ Never operate the coupling without a lubricant.
▷ Prior to putting the coupling into service, check the coupling cover for correct
installation and sealing.
58 of 168 CHTR
6 Commissioning/Start-up/Shutdown
DANGER
Overload due to incorrectly set monitoring and alarm equipment
Seal failure!
Explosion hazard
Rick of injury resulting from leakage of hot or pressurised fluid.
▷ Connect and activate all monitoring and alarm equipment installed.
▷ Check all instruments in accordance with the manufacturer's product literature
for correct measuring data and adjust the instruments, if required.
▷ Set the warning and shutdown values in cooperation with control engineering
specialists.
DANGER
Improper connection of auxiliary lines
Explosion hazard from escaping leakage or fluid!
▷ Correctly install the auxiliary lines.
▷ Observe the maintenance and monitoring schedules.
CHTR 59 of 168
6 Commissioning/Start-up/Shutdown
CAUTION
Improper maintenance
Damage to the pump set!
Insufficient lubrication!
▷ Only make adjustments when oil operating temperature has been reached.
▷ No oil is allowed to escape between labyrinth ring (423) and shaft (210)!
1. Set the switching points of the pressure switches for switching the auxiliary oil
pump on and off as well as for enabling and switching off the drive.
2. Adapt the pre-drilled orifice plates on the lube oil outlets to the gear or
variable speed coupling and operate in accordance with the relevant
manufacturer's documentation.
3. Check the oil level and top up, if required.
4. Switch on the oil supply unit or auxiliary oil pump and check the oil pressure.
5. Adjust the throttle valves in the supply lines of the thrust and radial bearings of
the pump with the help of auxiliary pressure gauges.
6. Screw the auxiliary pressure gauges in the throttle valves.
7. Secure the adjustment of the throttle valves with locking screws.
8. Switch off the oil supply unit or auxiliary oil pump, remove the auxiliary
pressure gauges and close the connection carefully.
DANGER
Risk of potentially explosive atmosphere inside the pump
Explosion hazard!
▷ The pump internals in contact with the fluid to be handled, including the seal
chamber and auxiliary systems must be filled with the fluid to be handled at all
times.
▷ Provide sufficient inlet pressure.
▷ Provide an appropriate monitoring system.
CAUTION
Increased wear due to dry running
Damage to the pump (set)/bearings!
▷ Never operate the pump set without liquid fill.
▷ Never operate the pump set in incompletely primed or incompletely vented
condition.
▷ Never close the shut-off element in the suction line and/or supply line during
pump operation.
60 of 168 CHTR
6 Commissioning/Start-up/Shutdown
NOTE
Do not cool down cooling chambers and heat exchangers with aggressive raw
water.
6. If fitted, check the filter in the barrier fluid system of the mechanical seal. Clean
it, if required.
7. Open the valves in the minimum flow system.
8. Check the oil levels and top up with oil, if required.
9. Fully open the valve in the inlet pipe.
10. Fill the inlet pipe, pump and discharge pipe with the fluid handled. If the
discharge pipe is equipped with a check valve, the shut-off element in the
discharge pipe may remain open as long as there is some back pressure.
11. Vent all pressure gauge lines until there is no more air to escape.
12. Fully open the shut-off element in the inlet pipe.
13. Check whether inlet pressure is available.
NOTE
For design-inherent reasons, the existence of some spaces not filled with liquid after
the pump has been filled prior to commissioning cannot be excluded. However,
once the drive is started up the pumping effect will immediately fill these spaces
with the fluid handled.
6.4 Commissioning/start-up
CHTR 61 of 168
6 Commissioning/Start-up/Shutdown
WARNING
Leakage caused by improper fitting of pipes and/or flanges
Risk of injury resulting from leakage of hot or pressurised fluid or vapour!
▷ Check all screws/bolts, screw/bolt and pipe connections as well as pipes and
flanges for leakage or damage prior to and during commissioning/start-up.
▷ Close all unused connections.
▪ Prior to and during starting of the pump check all connections, pipes, flanges,
screw/bolt connections and pipe unions for leakage and damage.
▪ All unused connections must be closed.
▪ The inlet vessel is in operational condition.
▪ The inlet line, pump and discharge line have been primed and vented.
▪ The shut-off element in the inlet line is fully open.
▪ The shut-off element in the discharge line is closed. If the discharge line is
equipped with a check valve, the shut-off element in the discharge line may
remain open as long as there is some back pressure.
▪ The connection for tapping, if applicable, is closed.
▪ The shut-off elements in the bypass line are open.
▪ The cooling water system is ON.
▪ The cooling liquid pressure at the inlet must not exceed 6 bar.
▪ The cooling liquid temperature at the outlet must not exceed 55 °C.
▪ All temperatures indicated are below the limit values.
▪ In the case of a pump set with variable speed coupling, check the scoop tube
position for compliance with the manufacturer’s product literature and re-adjust,
if required.
▪ Check all guards for correct fastening.
▪ Monitor the bearing oil temperature. Make sure that the limits are not exceeded.
(⇨ Section 6.7.2 Page 68)
DANGER
Non-compliance with operating limits for pressure, temperature, fluid handled and
speed
Hot or toxic fluid could escape!
Explosion hazard!
▷ Comply with the operating data indicated in the data sheet.
▷ Avoid prolonged operation against a closed shut-off element.
▷ Never operate the pump at temperatures exceeding those specified in the data
sheet or on the name plate unless the written consent of the manufacturer has
been obtained.
WARNING
Sound pressure level above 85 dB(A) when starting up the pump set
Injury to or impairment of hearing!
▷ Wear ear protection.
▷ Access to the pump set is permitted to authorised specialist personnel only.
▷ Observe the applicable local occupational health and safety regulations.
62 of 168 CHTR
6 Commissioning/Start-up/Shutdown
WARNING
Failure of seal elements on suction and discharge nozzles and other pressurised
parts
Risk of personal injury in the event that hot, pressurised fluid handled escapes!
▷ Wear safety goggles.
▷ Check seal elements regularly.
▷ Access to the pump is permitted to authorised specialist personnel only.
WARNING
Hot surfaces - Pump and piping take on the temperature of the fluid handled.
Risk of burns!
▷ Do not touch hot surfaces.
CAUTION
Abnormal noises, vibrations, temperatures or leakage
Damage to the pump!
▷ Switch off the pump (set) immediately.
▷ Eliminate the causes before returning the pump set to service.
CAUTION
Off-design operating data
Damage to the pump set by cavitation!
▷ The minimum discharge head of 150 m must not be underrun, except in the
start-up and stopping phase.
▷ The minimum speed of n = 1000 min-1 may only be underrun in the start-up and
stopping phase.
▷ The minimum speed (< 5 s) must be reached quickly.
NOTE
Should warning signals or problems occur during starting or trial run, proceed as
described in the chapter "Trouble-shooting"
CHTR 63 of 168
6 Commissioning/Start-up/Shutdown
CAUTION
Blocking of rotor
Damage to the rotor!
▷ In the event of a turning gear failure and pump standstill (n = 0 rpm), the pump
has to cool down until the pump casing temperature is ≤ 60 ℃ before it is
returned to service.
1. If a pump is primed with a fluid which has a temperature greater than 60° C, let
the pump casing cool down to 60° C.
2. Switch on the turning gear, if any, and observe the turbine manufacturer’s
instructions on starting of the pump set.
3. If pre-warming is provided, open the valve in the pre-warming line.
4. Switch on the cooling water (if applicable).
5. Check the temperature and smooth running of the bearings. Observe the
information given in "Interlock criteria for rolling element and plain bearings
and permissible vibrations at the bearing housings".
6. Check the pump pressures and differential pressures.
7. Monitor the minimum flow valve to make sure it works (hydrodynamic noise).
8. Check the mechanical seal. Mechanical seals must not drip.
9. Increase the pump speed until the operating speed is reached.
10. Slowly open the shut-off valve of the discharge line until it is completely open.
When starting against an open shut-off valve in the discharge line, consider the
higher power input required.
11. Continuously monitor the pump set’s operating behaviour.
64 of 168 CHTR
6 Commissioning/Start-up/Shutdown
NOTE
The manufacturer’s product literature is binding for all work performed on the
pump/set
6.6 Operation
DANGER
Non-compliance with the permissible pressure and temperature limits if the pump is
operated with the suction and/or discharge line closed.
Explosion hazard!
Leakage of hot or toxic fluids!
▷ Never operate the pump with the shut-off elements in the suction line and/or
discharge line closed.
▷ Only start up the pump set with the discharge-side shut-off element slightly or
fully open.
CHTR 65 of 168
6 Commissioning/Start-up/Shutdown
DANGER
Excessive temperatures due to dry running or excessive gas content in the fluid
handled
Explosion hazard!
Damage to the pump set!
▷ Never operate the pump set without liquid fill.
▷ Prime the pump as specified.
▷ Always operate the pump within the permissible operating range.
DANGER
Improper or no earthing
Risk of personal injury from electric shock!
Damage to the pump set!
▷ Ensure proper earthing of the pump set and check regularly.
WARNING
Excessive temperatures as a result of bearings running hot or defective bearing seals
Fire hazard!
Damage to the pump set!
▷ Regularly check the oil level and tightness of the bearings.
▷ Regularly check the temperature and smooth running of the bearings.
WARNING
Unprotected, rotating parts
Risk of injury from parts flying off!
Risk of injury by rotating shafts!
▷ Operate the pump set only after all protective equipment has been fitted.
▷ Never remove any guards while the pump is running.
▷ Regularly check all guards for correct fastening.
WARNING
Sound pressure level above 85 dB(A) when starting up the pump set
Injury to or impairment of hearing!
▷ Wear ear protection.
▷ Access to the pump set is permitted to authorised specialist personnel only.
▷ Observe the applicable local occupational health and safety regulations.
WARNING
Failure of seal elements on suction and discharge nozzles and other pressurised
parts
Risk of personal injury in the event that hot, pressurised fluid handled escapes!
▷ Wear safety goggles.
▷ Check seal elements regularly.
▷ Access to the pump is permitted to authorised specialist personnel only.
WARNING
Hot surfaces - Pump and piping take on the temperature of the fluid handled.
Risk of burns!
▷ Do not touch hot surfaces.
66 of 168 CHTR
6 Commissioning/Start-up/Shutdown
CAUTION
Excessive density of the fluid handled
Motor overload!
▷ Observe the information on fluid density in the data sheet.
▷ Make sure the motor has sufficient power reserves.
DANGER
Non-compliance with operating limits for pressure, temperature, fluid handled and
speed
Explosion hazard!
Hot or toxic fluid could escape!
▷ Comply with the operating data indicated in the data sheet.
▷ Never use the pump for handling fluids it is not designed for.
▷ Avoid prolonged operation against a closed shut-off element.
▷ Never operate the pump at temperatures, pressures or rotational speeds
exceeding those specified in the data sheet or on the name plate unless the
written consent of the manufacturer has been obtained.
DANGER
Excessive surface temperature of the motor
Explosion hazard!
Damage to the motor!
▷ In case of explosion-proof motors, observe the frequency of starts specified in
the manufacturer's product literature.
CAUTION
Excessive frequency of starts
Damage to the balancing device!
▷ Do not exceed the values for the frequency of starts.
CAUTION
Re-starting while motor is still running down
Damage to the pump (set)!
▷ Do not re-start the pump set before the pump rotor has come to a standstill.
NOTE
The values indicated for the frequency of starts apply to the pump only.
The frequency of starts is usually determined by the maximum temperature increase
of the motor. This largely depends on the power reserves of the motor in steady-
state operation and on the starting conditions (DOL, star-delta, moments of inertia,
etc). Observe the manufacturer’s instructions. (⇨ Section 9 Page 121)
CHTR 67 of 168
6 Commissioning/Start-up/Shutdown
CAUTION
Operation outside the permissible ambient temperature
Damage to the pump (set)!
▷ Observe the specified limits for permissible ambient temperatures.
Observe the following parameters and values during operation:
Table 14: Permissible ambient temperatures
Permissible ambient temperature Value
Maximum 50 °C
Minimum - 20 °C
For operation at temperatures outside the permissible limits, contact KSB.
Bearing oil temperature The minimum permissible bearing oil temperature when starting the pump depends
upon the quality of oil used:
DANGER
Temperature increase due to insufficient lubrication
Explosion hazard!
Damage to the pump set!
▷ Always observe the minimum permissible bearing oil temperature when
starting the pump.
To = Tf + ΔT
gxH
ΔT = c x η x (1 - η)
68 of 168 CHTR
6 Commissioning/Start-up/Shutdown
CAUTION
Impermissibly high density of the fluid handled
Motor overload!
▷ Observe the information on fluid density indicated in the data sheet.
▷ Make sure the motor has sufficient power reserves.
CAUTION
Off-design operating data
Damage to the pump set by cavitation!
▷ The minimum discharge head of 150 m must not be underrun, except in the
start-up and stopping phase!
▷ The minimum speed of n = 1000 rpm may only be underrun in the start-up and
stopping phase.
▷ The minimum speed (< 5 s) must be reached quickly.
WARNING
Hot surfaces - Pump and piping take on the temperature of the fluid handled.
Risk of burns!
▷ Do not touch hot surfaces.
6.8.1 Shutdown with the pump set remaining ready for operation
CHTR 69 of 168
6 Commissioning/Start-up/Shutdown
NOTE
The cooling water system remains ON!
CAUTION
Blocking of rotor
Damage to the rotor!
▷ In the event of a turning gear failure and pump standstill (n = 0 rpm), the pump
has to cool down until the pump casing temperature is ≤ 60 ℃ before it is
returned to service.
▪ If the speed of the pump set drops to the speed of the turning gear, the turning
gear takes over rotating of the rotor.
▪ The pre-warming unit (if any) remains in operation.
▪ The cooling unit (if applicable) remains in operation.
CAUTION
Blocking of rotor
Damage to the rotor!
▷ If the turning gear does not begin operation after a period of 10 seconds, the
pump has to cool down until the pump casing temperature is ≤ 60 ℃ before it is
returned to service.
▪ If it cannot be ensured that the turning gear turns the rotor within a period of 10
seconds after standstill of the pump set (n = 0 rpm), solenoid valves for example
have to be installed for the jacket cooling.
▪ If the pump set reaches a speed of n = 500 rpm, the solenoid valves, for example,
stop the jacket cooling.
▪ One minute after putting into service of the turning gear, the jacket cooling has
to be activated by means of solenoid valves, for example.
▪ The pre-warming unit (if any) remains in operation.
▪ Close the shut-off element in the discharge line. If the discharge line is equipped
with a check valve, the shut-off element in the discharge line may remain open
as long as there is some back pressure.
▪ Monitor the minimum flow valve to make sure it works.
NOTE
The cooling water system remains ON!
70 of 168 CHTR
6 Commissioning/Start-up/Shutdown
CAUTION
Unintentional starting of pump set
Damage to the shaft!
▷ Secure the drive against unintentional start-up, e. g. by disconnecting the
motor.
6. Close the shut-off valve in the minimum flow line.
7. Close the shut-off element in the inlet line.
8. Turn off the cooling water supply when the casing temperature (measured at
the pump nozzles) is lower than 50 °C.
9. Close all other pipes.
CAUTION
Pump set started up inadvertently
Damage to the pump!
▷ Secure drive against unintentional start-up, e. g. by disconnecting the motor.
5. Close the shut-off valve in the minimum flow pipe.
6. Close the shut-off element in the inlet pipe.
7. Turn off the cooling water when the casing temperature (measured at the
pump nozzles) is lower than 50 °C.
8. Close all other pipes.
6.9.1 Work after shutdown with the pump set remaining ready for operation
General Information
If the period of standstill during readiness for instant start-up is longer than 2 weeks,
the pump set components such as gear or motor must be protected against water
ingress and humidity as described in the manufacturer’s preservation instructions.
Every 4 to 6 weeks
▪ Start up the pump set. (⇨ Section 6.4 Page 61)
▪ After approximately 10 minutes shut down the pump set. (⇨ Section 6.8 Page 69)
▪ Check whether the pump rotor runs down smoothly to a standstill.
Every two months (in the case of pump set with variable speed coupling)
▪ If the scoop tube actuator was used during stand-by operation, re-lubricate the
guide bush. Comply with the manufacturer’s product literature.
CHTR 71 of 168
6 Commissioning/Start-up/Shutdown
6.9.2 Work after shutdown for standstill - Pump not ready for operation
CAUTION
Danger of frost/freezing
Damage to the pump!
▷ If there is any risk of freezing or in the event of prolonged standstill, drain and
preserve the pump.
In the case of danger of frost and standstill > 2 weeks, drain and preserve the pump.
General information
▪ Make sure that the drive cannot be switched on.
▪ Secure all valves against opening.
▪ Close all openings and supply lines.
If the period of standstill is longer than 2 weeks, the pump set components such as
gear or variable speed coupling must be protected against water ingress and
humidity as described in the manufacturer’s preservation instructions.
WARNING
Fluids posing a health hazard
Hazard to persons and the environment!
▷ Collect and properly dispose of flushing liquid and any residues of the fluid
handled.
▷ Wear safety clothing and a protective mask, if required.
▷ Observe all legal regulations on the disposal of substances posing a health
hazard.
DANGER
Insufficient preparation of work on the pump (set)
Risk of injury!
▷ Properly shut down the pump set.
▷ Close the shut-off elements in suction and discharge line.
▷ Drain the pump and release the pump pressure.
▷ Close any auxiliary connections.
▷ Allow the pump set to cool down to ambient temperature.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
General information
▪ Make sure that the drive cannot be switched on.
▪ Secure all valves against opening.
▪ Open all drains and/or drain pipes.
▪ Collect the fill in an appropriate container and dispose of according to the local
anti-pollution regulations.
If the period of standstill is longer than 2 weeks, the pump set components such as
gear or variable speed coupling must be protected against water ingress and
humidity as described in the manufacturer’s preservation instructions.
72 of 168 CHTR
6 Commissioning/Start-up/Shutdown
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
WARNING
Pump parts falling down during dismantling and reassembly.
Risk of injury from falling parts!
▷ Use appropriate means to secure the parts, if possible.
▷ Wear safety shoes.
▷ Observe the applicable local accident prevention regulations.
Preservation for standstill is required if:
▪ The pump set is not commissioned immediately after its installation
▪ The standstill time of the pump set exceeds two weeks
▪ There is any risk of freezing
Preservative Use a preservative which fulfils the following criteria:
▪ Mixture of glycol and water, ratio 1:1
NOTE
This mixture ensures protection against freezing down to approximately - 42 °C.
✓ The pump set has been shut down. (⇨ Section 6.8 Page 69)
✓ All necessary work after shutdown has been performed. (⇨ Section 6.9.3 Page 72)
✓ The drive has been secured against start-up.
✓ The pump has been drained, if required.
✓ A container for collecting the fluid is on hand.
✓ Sufficient preservative is available.
1. Secure all shut-off elements against opening.
2. Place suitable containers under the drain holes.
3. Open all drains and/or drain lines.
4. Collect and properly dispose of the fluid.
5. Close all drains and drain lines.
6. Fill the pump with preservative.
7. Dismantle and store the coupling guard.
8. Dismantle and store the spacer of the coupling as described in the
manufacturer’s documentation.
9. If required, fill the bearing housing with oil.
10. Rotate the pump rotor once or twice a month to prevent a separation of the
preservation fill.
11. Check the fill level of the preservative once or twice a month; top it up, if
required.
CHTR 73 of 168
6 Commissioning/Start-up/Shutdown
WARNING
In the case of storage periods of more than 5 years, the sealing function of O-rings
may be impaired.
Rick of injury from leakage of hot, pressurised fluid handled!
▷ After a storage period of more than 5 years, the pump must be dismantled
before it is installed, and the O-rings must be replaced.
▷ Check the O-rings for damage before they are fitted.
For returning the pump to service, observe the items on commissioning/start-up
(⇨ Section 6.4 Page 61) .
In addition, carry out all servicing/maintenance operations before returning the
pump (set) to service. (⇨ Section 7 Page 75)
74 of 168 CHTR
7 Servicing/Maintenance
7 Servicing/Maintenance
7.2 Supervision
DANGER
Improperly serviced pump set
Explosion hazard!
Damage to the pump set!
▷ Service the pump set regularly.
▷ Prepare a maintenance schedule with special emphasis on lubricants, shaft seal
and coupling.
NOTE
During the warranty term, pumps/pump sets must only be dismantled or
reassembled by KSB personnel!
The operator ensures that all maintenance, inspection and installation work is
performed by authorised, qualified specialist personnel who are thoroughly familiar
with the manual.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
WARNING
Fluids posing a health hazard and/or hot fluids
Risk of personal injury!
▷ Observe all relevant laws.
▷ When draining the fluid take appropriate measures to protect persons and the
environment.
▷ Decontaminate pumps which handle fluids posing a health hazard.
A regular maintenance schedule will help avoid expensive repairs and contribute to
trouble-free, reliable operation of the pump (set) with a minimum of maintenance
expenditure and work.
NOTE
All maintenance, service and installation work can be carried out by KSB Service or
authorised workshops. Find your contact in the attached "Addresses" booklet or on
the Internet at "www.ksb.com/contact".
Never use force when dismantling and reassembling the pump set.
CHTR 75 of 168
7 Servicing/Maintenance
76 of 168 CHTR
7 Servicing/Maintenance
7.3 Maintenance
DANGER
Excessive temperatures as a result of bearings running hot or defective bearing seals
Explosion hazard!
Fire hazard!
Damage to the pump set!
▷ Regularly check the lubricant level.
▷ Regularly check the rolling element bearings for running noises.
CAUTION
Increased wear due to dry running
Damage to the pump set!
▷ Never operate the pump set without liquid fill.
▷ Never close the shut-off element in the suction line and/or supply line during
pump operation.
CAUTION
Impermissibly high temperature of fluid handled
Damage to the pump!
▷ Prolonged operation against a closed shut-off element is not permitted
(heating up of the fluid).
▷ Observe the temperature limits in the data sheet and in the section on
operating limits. (⇨ Section 6.7 Page 67)
CHTR 77 of 168
7 Servicing/Maintenance
NOTE
Perform a visual inspection of the pump set — as far as accessible — about 500
operating hours after commissioning/start-up.
78 of 168 CHTR
7 Servicing/Maintenance
Constant-level oiler
CHTR 79 of 168
7 Servicing/Maintenance
✓ The constant-level oiler is fitted in the bearing housing on the relevant side (see
figure Constant-level oiler).
1. Remove vent plug 913 with gasket 400.05.
2. Press together clamp on constant-level oiler 638 and pull the reservoir of the
constant-level oiler upwards.
3. Fill the reservoir of constant-level oiler 638 with oil and return it to its operating
position.
4. Re-insert vent plug 913 with gasket 400.05.
5. After a short time check whether the oil level in the reservoir has dropped.
It is important to keep at least one third of the reservoir filled at all times. If the
oil level is too low, top it up with oil.
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
DANGER
Unprotected floor openings and/or foundations
Danger of death from falling!
▷ Secure the danger zone.
▷ Observe the applicable local occupational safety and accident prevention
regulations.
WARNING
Improper lifting/moving of heavy assemblies or components
Personal injury and damage to property!
▷ Use suitable transport devices, lifting equipment and lifting tackle to move
heavy assemblies or components.
80 of 168 CHTR
7 Servicing/Maintenance
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
▷ Make sure that the pump set cannot be started up unintentionally.
▷ Always make sure the electrical connections are disconnected before carrying
out work on the pump set.
WARNING
Unqualified personnel performing work on the pump (set)
Risk of injury!
▷ Always have repair and maintenance work performed by specially trained,
qualified personnel.
WARNING
Pump parts falling down during dismantling and reassembly.
Risk of injury from falling parts!
▷ Use appropriate means to secure the parts, if possible.
▷ Wear safety shoes.
▷ Observe the applicable local accident prevention regulations.
WARNING
Hot surface
Risk of injury!
▷ Allow the pump set to cool down to ambient temperature.
Observe the general safety instructions and information.
For any work on the motor, observe the instructions of the relevant motor
manufacturer.
For dismantling and reassembly observe the exploded views and the general
assembly drawing.
DANGER
Insufficient preparation of work on the pump (set)
Risk of injury!
▷ Properly shut down the pump set.
▷ Close the shut-off elements in suction and discharge line.
▷ Drain the pump and release the pump pressure.
▷ Close any auxiliary connections.
▷ Allow the pump set to cool down to ambient temperature.
NOTE
All maintenance, service and installation work can be carried out by KSB Service or
authorised workshops. Find your contact in the attached "Addresses" booklet or on
the Internet at "www.ksb.com/contact".
NOTE
After a prolonged period of operation the individual components may be hard to
pull off the shaft. If this is the case, use a brand name penetrating agent and/or - if
possible - an appropriate puller.
CHTR 81 of 168
7 Servicing/Maintenance
NOTE
This type of pump design allows the cartridge to be removed from the barrel casing
with minimum dismantling (Removal of pump cartridge: (⇨ Section 7.4.9 Page 92) ).
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
82 of 168 CHTR
7 Servicing/Maintenance
2
3
WARNING
Falling coupling parts
Risk of crushing from falling parts!
▷ Secure coupling parts against falling down.
▷ Wear safety shoes.
WARNING
Coupling hub coming off suddenly
Risk of crushing fingers/hands at the puller
▷ Never put fingers/hands in the spaces between coupling hub and tool during
dismantling.
▷ Use appropriate personal protective equipment.
CAUTION
Improper dismantling
Damage to bearings and coupling parts!
▷ Remove coupling hubs using a puller.
▷ Never strike the coupling hubs.
CAUTION
Improper mounting of elastomers
Elastomers' sealing function reduced!
▷ Never use elastomeric parts again which have been heated.
▷ As a general rule, always use new elastomeric parts.
1. Dismantle the retaining rings, if applicable, from the coupling hub.
CHTR 83 of 168
7 Servicing/Maintenance
1 2
WARNING
Hot surfaces due to heating of components for assembly/dismantling
Risk of burns!
▷ Wear heat-resistant protective gloves.
▷ Remove flammable substances from the danger zone.
4. To facilitate removal, the coupling hubs may be heated uniformly to a
temperature of 80 °C max. Elastomeric parts must be removed before heating.
Elastomeric parts which have been heated must not be used any more.
84 of 168 CHTR
7 Servicing/Maintenance
NOTE
Observe the marking between coupling hub and shaft. (⇨ Section 7.4.4 Page 83)
1. Permissible tolerance at the pump shaft ≤ 0.03 mm. If this value is exceeded,
contact KSB.
2. Permissible tolerance of the motor shaft, see the data provided by the
manufacturer.
CHTR 85 of 168
7 Servicing/Maintenance
8 9 10
4 5 6 7
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
CAUTION
Improper dismantling/installation
Damage to the shaft and bearings!
▷ When the bearings are dismantled ensure that the shaft never rests on the
bearing housings or labyrinth rings or is rotated.
▷ Mark the bearings to ensure their correct assignment to the bearing housings.
86 of 168 CHTR
7 Servicing/Maintenance
CAUTION
Installation of defective or damaged bearings
Damage to the pump!
▷ Re-use only bearings which are in perfect condition.
▷ In the case of slight discolourations or any damage, the bearings must be
replaced.
▷ After washing the bearings out, immediately spray them with oil.
CHTR 87 of 168
7 Servicing/Maintenance
7.4.6.4 Dismantling the INPRO labyrinth seal from the non-drive end bearing
housing (if applicable)
CHTR 2-3
✓ Observe the disassembly sketches of the INPRO labyrinth seal in work instruction
UA1 37858 02.
1. Loosen hexagon nuts 920.05 including discs 550.05 to remove bearing housing
350.02 from cooling chamber cover 165.01.
2. Remove bearing housing 350.02 including bearings 320/324 and labyrinth seal
423.01 using forcing screws 901.73 as shown in the work instruction
UA3 37819 01.
3. Continue the removal of the bearing housing until labyrinth seal 423.01
separates from the bearing housing by striking against segmental ring 501.04.
4. Pull spacer ring 504.01, segmental ring 501.04 from shaft 210. Gently remove
INPRO labyrinth seal 423.01 from the shaft by pushing it or using a mallet.
CHTR 4-5
✓ Observe the disassembly sketches of the INPRO labyrinth seal in work instruction
UA1 37858 02.
1. Loosen hexagon nuts 920.05 including discs 550.05 to remove bearing housing
350.02 from cooling chamber cover 165.01.
2. Remove bearing housing including bearings using forcing screws 901.73 as
shown in the work instruction UA3 37819 01.
88 of 168 CHTR
7 Servicing/Maintenance
3. Continue the removal of the bearing housing until it can be pulled from the
shaft along with INPRO labyrinth seal 423.01, bearings 320/324 and spacer ring
504.01.
7.4.7.1 Preparations
Disconnect all cooling liquid, barrier fluid, circulation or injection pipes as far as
necessary.
WARNING
Damaged shaft sleeve and mechanical seals
Risk of personal injury in the event that hot, pressurised fluid handled escapes!
▷ Replace damaged shaft sleeves and mechanical seals by new components.
CAUTION
Incorrect handling of locking screws
Damage to the shaft seal!
▷ Never loosen locking screws in diagonally opposite sequence.
▷ Never screw out the individual locking screws completely in a single go.
5. Loosen the locking screws of the locking sleeve (A) uniformly and one after the
other by a quarter turn, see figure Locking sleeve.
6. Loosen the locking screws further in a second run or any further run, however,
do not screw them out.
7. Remove dirt from shaft sleeve.
8. Remove locking sleeve (A) from shaft sleeve (D).
CHTR 89 of 168
7 Servicing/Maintenance
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
CHTR 2-3
1. Undo and remove shaft nut 921.
2. Use an appropriate device as described in the work instruction UA3 37819 01 to
remove balance drum 603.01 with spacer ring 504.02 and O-ring 412.02 or joint
ring 411.02 from shaft 210.
3. Undo socket head cap screws 914.14 and push throttle bush 542.01 with screws
out of cover 160.01. Also remove O-ring 412.05 or joint ring 411.05 and O-ring
412.04.
4. Check balance drum 603.01 and throttle bush 542.01 for damage.
90 of 168 CHTR
7 Servicing/Maintenance
CHTR 4-5
1. Undo socket head cap screws 914.10 and pull off loose collar 505.01.
2. Remove segmental ring 501.01 from shaft groove and spacer ring 504.02 from
shaft 210.
3. Use an appropriate device as described in the work instruction UA3 37819 01 to
remove balance drum 603.01 with O-ring 412.02 or joint ring 411.02 from shaft
210.
4. Undo socket head cap screws 914.14 and push throttle bush 542.01 with screws
out of cover 160.01. Also remove O-ring 412.05 or joint ring 411.05 and O-ring
412.04.
5. Check balance drum 603.01 and throttle bush 542.01 for damage.
NOTE
An exact measurement of the rotor clearances is only possible with the pump set
dismantled!
If the pump body is not dismantled, only an approximate radial clearance can be
measured.
CHTR 91 of 168
7 Servicing/Maintenance
NOTE
The pump cartridge may only be dismantled by trained specialist personnel.
In case of maintenance, the pump cartridge must be clamped together axially in
accordance with the assembly instruction UA3 37816 01 or UA3 37817 01, and, if
necessary, sent to KSB Service Center or KSB with dismantled components.
7.4.9.2 Prerequisites
▪ All pipes, add-on parts and measuring instruments which have to be dismantled
for pump cartridge removal are dismantled.
▪ Only use the special tools (tool cradle) included in the scope of supply as shown
in the assembly sketch (CHTR 2:UA3 37814 01; CHTR 3-5: UA3 37815 01).
▪ Prior to dismantling, mark the exact positions of component parts and
connection holes to one another.
7.4.9.3 Preparations
CHTR 2
1. Dismantle the drive end bearing housing (⇨ Section 7.4.6 Page 86) and the shaft
seal (⇨ Section 7.4.7 Page 89) .
2. Fit the dummy bearing housing 350.81 along with ring 500.81 and secure in
position using four discs 550.05 and four hexagon nuts 920.05, if applicable.
3. Loosen hexagon head bolts 901.06 and remove guide piece 897.
CHTR 3-5
1. Dismantle drive end bearing cover 360.02 or labyrinth ring 423.01. (⇨ Section
7.4.6 Page 86)
2. If applicable, loosen hexagon nut 920.07 and remove cooling insert 442.01
including O-ring 412.19, discs 550.07 and stud 902.07 or 902.08.
3. Loosen hexagon head bolts 901.06 and remove guide piece 897.
CHTR 4-5 with double suction impellers (i.e. pump types CHTR N /1+X)
1. Dismantle drive end bearing cover 360.02 or labyrinth ring 423.01. (⇨ Section
7.4.6 Page 86)
2. If applicable, loosen hexagon nut 920.07 and remove cooling insert 442.01
including O-ring 412.19, discs 550.07 and stud 902.07 or 902.08.
3. Remove hexagon nuts 920.15 and 920.19 with discs 550.15 and 550.19 including
studs 902.15 and 902.19 from barrel casing 10-3 and inlet ring 131.02 and
remove the two-piece ring (500).
92 of 168 CHTR
7 Servicing/Maintenance
CHTR 93 of 168
7 Servicing/Maintenance
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
1. Screw eyebolt 59-47.2 into cover 160.01/160.02 or casing insert 13-6.
2. Loosen and remove the remaining four hexagon nuts 920.01, if applicable.
3. Fasten strips 575.84 to barrel casing 10-3 using hexagon head bolts 901.91 and
sleeve 520.81, if applicable. Screw in hexagon head bolts 901.86.
4. Uniformly force pump cartridge out of barrel casing 10-3 by tightening hexagon
head bolts 901.86.
5. Remove pump cartridge from barrel casing 10-3. If necessary, lift the pump
cartridge using hexagon nuts 920.81 and hexagon head bolts 901.82 on the
non-drive end, or hexagon head bolts 901.88 on the drive end so that the pump
cartridge can be withdrawn from the barrel casing without knocking against it.
NOTE
It must be possible to easily withdraw the pump cartridge from the barrel casing
without tilting. If this is not possible, contact KSB.
6. Attach transport rope as shown in the assembly sketch UA3 37814 01 or UA3
37815 01.
7. If there is enough clearance for removal, transport the complete pump
cartridge including lengthening pipes to the place of dismantling and place
down on assembly supports.
If space is not sufficiently available, disconnect pipes 710.82, 710.83 and 710.84,
if applicable, from pipe 710.81 using tommy bar 969.75 and remove them.
8. Lift the pump cartridge off the tool cradle.
9. Transport the pump cartridge to the place of dismantling (⇨ Section 3 Page 14)
and place it down on assembly supports.
10. Remove gasket 400.03, O-ring 412.01 or joint ring 411.01 and gaskets 400.08
and spacer discs 551.01, if fitted.
94 of 168 CHTR
7 Servicing/Maintenance
1. Slide first gasket 400.81 and then disc 550.84 over inlet ring 131.03.
2. Fasten inlet ring 131.03 (with gasket 400.81 and disc 550.84) to cover 160.01
using tie bolts 905.81, discs 550.86 and 550.87 and hexagon nuts 920.86.
3. Axially clamp together the pump cartridge using nut 920.86, taking into
account reference dimension A as specified in the assembly instructions
UA3 37818 01.
WARNING
Pump parts falling down during dismantling and reassembly.
Risk of injury from falling parts!
▷ Use appropriate means to secure the parts, if possible.
▷ Wear safety shoes.
▷ Observe the applicable local accident prevention regulations.
WARNING
Improper lifting/moving of heavy assemblies or components
Personal injury and damage to property!
▷ Use suitable transport devices, lifting equipment and lifting tackle to move
heavy assemblies or components.
WARNING
O-rings in contact with oil or grease
Risk of injury in the event that the hot, pressurised fluid handled escapes!
▷ Do not take the O-rings out of their original packagings until immediately
before they are fitted and protect them from mineral oil and grease.
▷ Do not fit the O-rings in dry condition: Observe the specifications on auxiliary
materials for assembly outlined by KSB and the manufacturer of the mechanical
seal.
▷ Check the O-rings for damage before they are fitted.
CHTR 95 of 168
7 Servicing/Maintenance
WARNING
Damage to locating and sealing surfaces through improper reassembly or
dismantling.
Risk of injury in the event that the hot, pressurised fluid handled escapes!
▷ Do not damage the locating and sealing surfaces.
CAUTION
Improper reassembly
Damage to the pump!
▷ Reassemble the pump (set) in accordance with the general rules of sound
engineering practice.
▷ Use original spare parts only.
NOTE
Check dismantled parts for damage. The installation of damaged parts leads to
increased wear or to failure of the balancing device, which results in damage to the
pump rotor.
▪ Reassembly must be performed in accordance with the rules of sound mechanical
engineering practice.
▪ Meticulously clean all dismantled parts, in particular the locating and sealing
surface areas.
▪ If required, remove any lime and incrustation from the cooling chambers.
▪ Check all dismantled parts for damage.
▪ Prior to reassembly coat the screw/bolt connections and pipe unions as well as
the fits of the individual components using the respective specified lubricating
agent as described in the work instruction UA4 28699 01.
Sequence Always reassemble the pump in accordance with the corresponding general assembly
drawing.
Seal elements ▪ Gaskets
– Always use new gaskets, making sure that they are of the same thickness and
material as the old ones.
▪ O-rings
– Always use new O-rings, making sure that they are of the same thickness and
material as the old ones.
– Never use O-rings that have been glued together from material sold by the
metre.
Tightening torques For reassembly, tighten all screws and bolts as specified in this manual.
7.5.2 Prerequisites
▪ Mounting of the pump cartridge may only be performed with the special tools
included in the supply (tool cradle) as shown in the assembly sketch
UA3 37814 01 or UA3 37815 01.
▪ The spare cartridge (if any) has been clamped together with assembly tools at the
factory as described in the assembly instruction UA3 37816 01 or UA3 37817 01.
▪ Refer to the outline drawingUA3 37818 01 for the dimensions of the spare
cartridge, see chapter 9.
▪ The sealing and locating surfaces of the barrel casing and the components to be
mounted must not exhibit any damage.
96 of 168 CHTR
7 Servicing/Maintenance
7.5.3.1 Preparations
1. Measure dimension ‘L2’ as shown on the dimensional record UA3 37818 01 and
calculate the actual dimension ‘A’.
2. Fit the tool cradle, if required. (⇨ Section 7.4.9.5 Page 93)
DANGER
Pump cartridge tipping over
Risk of crushing hands and feet!
▷ Secure pump cartridge against tipping over.
4. Attach transport rope as shown in the assembly sketch UA3 37814 01 or UA3
37815 01.
5. Lift the pump cartridge from the assembly supports and transport it to the
barrel casing.
Observe the assembly sketch UA3 37814 01 or UA3 37815 01.
6. If pipes 710.82, 710.83, and 710.84, if applicable, have not been mounted
during the dismantling of the original pump cartridge, screw pipes 710.82,
710.83 and 710.84 together with pipe 710.81 using tool 969.75.
7. Introduce pump cartridge into barrel casing 10-3 as far as the point where rolls
59-30.81 rest on support feet 183.81, and pipe 710.83 or 710.84 rests on rolls
59-30.81 mounted on trestle 895.81.
8. Remove the transport ropes from the pump cartridge.
CAUTION
Incorrect installation
Damage to the sealing faces!
▷ It must be possible to easily insert the pump cartridge into the barrel casing
without tilting.
▷ The O-ring joints must not be damaged.
▷ Should problems arise, contact KSB.
CHTR 97 of 168
7 Servicing/Maintenance
NOTE
The orientation of the opening in the inlet ring 131, 131.01, 131.02, 131.03, if
applicable, must coincide with that of the suction nozzle.
10. If applicable, the slot in the inlet ring 131 or 131.02 or 131.03 should
accommodate guide piece 897. If a hole is provided instead of a slot, then the
hole in the inlet ring 131 or 131.02 or 131.03 should engage the cylindrical pin
562.12 and also engage the hexagon bolt 901.06.
11. Remove the pipes 710.82 to 710.84 one after the other depending on the
position of the cartridge from shaft 210.
12. Remove lifting lug 59-47.2 from cover 160.01 or 160.02.
13. Dismantle strips 575.81 including pins 564.81 and rolls 59-30.81 from cover
160.01 or 160.02 or casing insert 13-6.
14. For CHTR 5 (250 bar) only:Fit original cover 160.02 and socket head cap screws
914.19.
15. Fit four of the twelve/sixteen discs 550.01 and hexagon nuts 920.01 at
equispaced locations and tighten.
16. Completely dismantle the tool cradle on the drive end.
17. Fit and tighten the remaining discs 550.01 and hexagon nuts 920.01 as
described in the relevant work instruction UA3 37821 01 or UA3 37821 02. For
tightening sequence, follow the usual good engineering practices.
CHTR 2
1. Remove dummy bearing housing 350.81 from shaft 210.
2. Fit bearing and bearing housing.
CHTR 2-5
1. Fasten the guide piece 897 to barrel casing 10-3 with hexagon head bolt 901.06
applying the tightening torque given in the relevant work instruction UA3
37821 01.
CHTR 4-5 with double suction impellers (i.e. type series CHTR N /1+X)
1. Fit studs 902.15 and 902.19 to barrel casing 10-3 and inlet ring 131.02 or 131.03.
2. Fit ring 500 to barrel casing 10-3 and inlet ring 131.02 or 131.03 using parallel
pins 562.12 and 562.22.
3. Fit discs 550.15 and 550.19 and hexagon nuts 920.15 and 920.19 on studs 902.15
and 902.19 applying the tightening torque given in the relevant work
instruction UA3 37821 01.
98 of 168 CHTR
7 Servicing/Maintenance
2. Fit balancing device (⇨ Section 7.5.5 Page 106) on the non-drive end and on the
drive and non-drive ends of both shaft seal (⇨ Section 7.5.6 Page 107) and
bearings (⇨ Section 7.5.7 Page 109) .
WARNING
Pump parts falling down during dismantling and reassembly.
Risk of injury from falling parts!
▷ Use appropriate means to secure the parts, if possible.
▷ Wear safety shoes.
▷ Observe the applicable local accident prevention regulations.
NOTE
The work described below is only necessary if throttle bush 542.01 or balance drum
603.01 require reworking or replacement.
Carry out this work with special care in order not to damage the internal pump parts.
CHTR 2-5
1. Refer to figure "Adapting the balance drum". Measure the distance “d” for the
total length of throttle bush 542.01. Measure distance "b" for total length, and
distance "c" of balance drum 603.01.
2. Determine distance "a": a=d-b. (Note: "a” can be either positive or zero.)
CHTR 99 of 168
7 Servicing/Maintenance
6. Refer to figure "Adjusting the pump rotor position". Move the pump rotor
towards the discharge side until it abuts and then move it back to the suction
side by a distance = SL1. (For SL1 refer to Table of Clearances ). (⇨ Section 9.2.3
Page 122) ).
7. This rotor adjustment must not be changed during the entire process of
measuring the balancing device!
8. Slide balance drum 603.01 onto shaft 210 until it abuts with the last stage
impeller hub.
9. Refer to figure "Adapting the balance drum". Adapt balance drum 603.01.
CAUTION
Incorrect measurement values due to improperly installed temperature measuring
instrument.
Damage to the pump (set)!
▷ When mounting the bearings, the holes for measuring the temperature in the
bearing segments and the associated temperature measuring instrument
connections in the bearing housings and/or bearing covers must be in
alignment.
CAUTION
Incorrect adjustment of rotor position
Damage to the pump (set)!
▷ Never change the rotor position when measuring the balancing device.
n 504.01
350.02
m
501.04
184.73
OIM_CHTR 012
Fig. 51: Adjusting the thrust bearings CHTR 2-3 (angular contact ball bearings)
Z Unmachined
b Machined
6. Fit segmental ring 501.04 and spacer ring 504.01 along with the shaft. Ensure
proper engagement of spacer ring and segmental ring using clamping ring
184.73, stud 902.72 and nut 920.72 as shown in the figure. Measure the distance
"m" on the clamping ring and the distance "n" from the outer face of the
bearing housing to the face of the clamping ring (see figure: Adjusting the
thrust bearings CHTR 2-3).
NOTE
Machine the contact face of spacer ring 504.01 abutting against clamping ring
184.73.
7. Shorten spacer ring 504.01 to the dimension "b" , where b = Z-[(n + d)-m].
"Z" is the unmachined length of spacer ring 504.01.
The maximum permissible deviation from plane parallelism for spacer ring
504.01 is 0.02 mm/0.0008 in.
902.71 504.01
n d
350.02
m
Z 504.01
b
920.71 184.74
320
Fig. 52: Adjusting the thrust bearings CHTR 4-5 (angular contact ball bearings)
Z Unmachined
b Machined
6. Slide spacer ring 504.01 over shaft until it abuts against the shaft collar.
7. Ensure proper abutment of spacer ring against shaft collar using clamping ring
184.74, stud 902.71 and nut 920.71 as shown in the figure. Measure the distance
"m" on the clamping ring and the distance "n" from the outer face of the
bearing housing to the face of the clamping ring as shown in the figure:
Adjusting the thrust bearing CHTR 4-5 (angular contact ball bearing)).
8. Shorten spacer ring 504.01 to the dimension "b" , where b = Z-[(n + d)-m].
The maximum permissible deviation from plane parallelism is 0.02 mm/0.0008
in.
2. Fit non-drive end shaft seal housing 441.02 and cooling chamber cover 165.01
to cover 160.01, without O-rings.
3. Position rotor. (⇨ Section 7.5.4.1 Page 99)
4. Measure distances L1, L2, l1, l2 and X (as shown in the figure: Bearing
dimensions).
L1 X L2
l1 l2
c
OIM_CHTR 018
n 504.01
350.02
m
Z c
b
501.04
184.73
324
OIM_CHTR 019
CHTR 2-3
Fig. 54: Adjusting the thrust bearings CHTR 2-3 (tapered roller bearings)
12. Ensure proper engagement of spacer ring and segmental ring using clamping
ring 184.73, stud 902.72 and nut 920.72 as shown in the figure: Adjusting the
thrust bearing CHTR 2-3 (tapered roller bearing)). Measure the distance "m" on
the clamping ring and the distance "n" from the outer face of the bearing
housing to the face of the clamping ring as shown in the figure. Shorten spacer
ring 504.01 to the dimension "b", where b = Z-[(n + d)-m]+c.
"Z" is the unmachined length of spacer ring 504.01. The maximum permissible
deviation from plane parallelism for spacer ring 504.01 is 0.02 mm/0.0008 in.
902.71 504.01
n d 350.02
m
c
Z 504.01
b
920.71 184.74
324
OIM_CHTR 020
CHTR 4-5
Fig. 55: Adjusting the thrust bearings CHTR 4-5 (tapered roller bearings)
11. Slide spacer ring 504.01 over shaft until it abuts against the shaft collar.
12. Ensure proper abutment of spacer ring against shaft collar using clamping ring
184.74, stud 902.78 and nut 920.78 as shown in the figure: Adjusting the thrust
bearing CHTR 4-5 (tapered roller bearing). Measure the distance "m" on the
clamping ring and the distance "n" from the outer face of the bearing housing
to the face of the clamping ring as shown in the figure: Adjusting the thrust
bearing CHTR 4-5 (tapered roller bearing).
13. Shorten spacer ring 504.01 to the dimension "b", where b = Z-[(n + d)-m] + c.
"Z" is the unmachined length of spacer ring 504.01. The maximum permissible
deviation from plane parallelism is 0.02 mm/0.0008 in.
CAUTION
Insufficient face contact
Damage to the pump (set)!
▷ If throttle bush 542.01 or balance drum 603.01 have been remachined or
replaced, check the dimensions and adapt the size of the components, if
required. (⇨ Section 7.5.4 Page 99)
CHTR 2-5
1. Insert parallel pin 562.03 into cover 160.01, if applicable.
2. Fit throttle bush 542.01 including O-ring 412.05 or joint ring 411.05 and/or O-
ring 412.04. Parallel pin 562.03, if applicable, must engage in the groove of
throttle bush 542.01. Fasten with socket head cap screws 914.14. (Tightening
torque as per work instruction UA3 37821 01)
CAUTION
Incorrect installation
Damage to the pump rotor through incorrect tightening torques!
▷ Apply tightening torque as per work instruction UA3 37821 01.
3. For the adjustment of the rotor position refer to figure Adjusting the pump
rotor position.
4. Move the pump rotor towards the discharge side until it abuts and then move it
back to the suction side by a distance = SL1. (For SL1 refer to Table of Clearances
(⇨ Section 9.2.3 Page 122) ).
5. Fit O-ring 412.02 or joint ring 411.02 into groove of balance drum 603.01. Slide
balance drum 603.01 onto shaft 210 until key 940.04 snaps into place.
6. Slide spacer ring 504.02 onto shaft 210.
7. Place key 940.04 on shaft 210.
CHTR 2-3
1. Tighten shaft nut 921 on shaft 210 using an appropriate tool as described in the
work instruction UA3 37819 01.
CHTR 4-5
1. Insert segmental ring 501.01 into shaft groove. Slide loose collar 505.01 over
them and fasten to balance drum 603.01 using socket head cap screws 914.10;
for tightening torque refer to the relevant work instruction UA3 37821 01.
DANGER
Improper connection of auxiliary lines
Explosion hazard from escaping leakage or fluid!
▷ Correctly install the auxiliary lines.
▷ Observe the maintenance and monitoring schedules.
WARNING
Damaged shaft sleeve and mechanical seals
Risk of personal injury in the event that hot, pressurised fluid handled escapes!
▷ Replace damaged shaft sleeves and mechanical seals by new components.
▪ Observe the tightening torques.
▪ Observe the direction of rotation of the seal components.
▪ Observe the general drawings of the mechanical seal and the manufacturer’s
product literature.
WARNING
Damaged shaft sleeve and mechanical seals
Risk of personal injury in the event that hot, pressurised fluid handled escapes!
▷ Replace damaged shaft sleeves and mechanical seals by new components.
▪ Observe the tightening torques.
▪ Observe the direction of rotation of the seal components.
▪ Observe the general drawings of the mechanical seal and the manufacturer’s
product literature.
2. Fit the hexagon nuts 920.10 and tighten; for tightening torque see the relevant
work instruction.
3. Lock the mechanical seal shaft sleeve on the shaft 210 with the grub screws.
NOTE
Do not tighten the locking screws prior to sliding on the locking sleeve, otherwise
the locking sleeve or shaft sleeve cannot be mounted.
4. Slide the locking sleeve (A) over the shaft sleeve (D) and join with the locking
screw as shown in the figure: Locking sleeve (example)).
5. In the area of the locking sleeve seat, the outer surface of the shaft sleeve may
be greased.
CAUTION
Improper reassembly
Destruction of the locking screws or insufficient preload!
▷ Do not tighten the locking screws in diagonally opposite sequence.
6. Tighten the locking screws uniformly and one after the other in anti-clockwise
direction. The tightening torque for the locking screws is stamped on the
locking sleeve.
7. At the end of the mounting process, the faces of locking sleeve and shrink disc
must be in alignment.
CAUTION
Improper dismantling/installation
Damage to the shaft and bearings!
▷ When the bearings are dismantled ensure that the shaft never rests on the
bearing housings or labyrinth rings or is rotated.
▷ Mark the bearings to ensure their correct assignment to the bearing housings.
CAUTION
Installation of defective or damaged bearings
Damage to the pump!
▷ Re-use only bearings which are in perfect condition.
▷ In the case of slight discolourations or any damage, the bearings must be
replaced.
▷ After washing the bearings out, immediately spray them with oil.
CAUTION
Improper reassembly
Damage to the rotor parts!
▷ Adjustment work may only be effected by trained specialist personnel!
▷ Carry out the work with special care.
For mounting the bearings observe the relevant assembly drawing UA3 37819 01.
3. If cooling chamber cover 165.01 and O-rings 412.03 and 412.11 have been
removed, place them back in position on the drive and non-drive ends.
4. Fit bearing housing 350.01 and/or 350.02 including labyrinth seal 423.01 and
parallel pin 562.10, if applicable. If applicable, observe the information on the
installation of INPRO labyrinth seal 423.01. (⇨ Section 7.5.7.1.2 Page 110) (⇨
Section 7.5.7.1.1 Page 110)
5. Fit discs 550.05 and hexagon nuts 920.05. Tighten hexagon nuts applying the
tightening torque indicated in the relevant work instruction.
6. Fit bearing guard 680.03 with discs 550.14 and hexagon head bolt 901.05 to
bearing housing 350.01.
7. Water cooling design: Insert cooling chamber cover 165.03 and/or 165.04
including O-ring 412.19 and/or 412.27 and cooling insert 442.01 and/or 442.02
including O-ring 412.19 into bearing housing 350.01 and/or 350.02.
Air cooling design: Insert cooling chamber cover 165.03 and/or 165.04 including
O-ring 412.19 and/or 412.27 and cooling insert 442.01 and/or 442.02 including
O-ring 412.19 into bearing housing 350.01 and/or 350.02.
8. Fit nuts 920.07 with discs 550.07 on studs 902.07 or 902.08 and tighten.
7.5.7.1.1 Fitting INPRO labyrinth seal into non-drive end bearing housing (if
applicable)
WARNING
Incorrect installation
Damage to the mechanical seal!
▷ Do not remove the assembly fixtures of mechanical seal before the assembly of
pump is completed.
✓ Observe work instruction UA1 37858 01 for the installation of the INPRO
labyrinth seal.
1. Fit labyrinth seal 423.01, spacer ring 504.01 and segmental ring 501.04 on shaft
210.
2. Slide bearing housing 350.02 over spacer ring 504.01 and segmental ring 501.04
to fit it into cooling chamber cover 165.01.
3. Position the bearing housing on studs 902.05. Engage the outer diameter of
labyrinth seal 423.02 into the inner diameter of bearing housing 350.02.
Tighten nuts 920.05 on studs 902.05 until bearing housing 350.02 along with
labyrinth seal 423.02 moves close enough to the face of mechanical seal 433.02
so that segmental ring 501.20 can be inserted tightly into the gap between the
face of labyrinth seal 423.02 and the face of mechanical seal 433.02.
4. Continue tightening hexagon nuts 920.05 to fasten bearing housing 350.02 to
cooling chamber cover 165.01 until the outer diameter of labyrinth seal 423.02
engages completely into the inner diameter of bearing housing 350.02.
5. Loosen hexagon nuts 920.05 and remove bearing housing 350.02 until
segmental ring 501.20 is loosened and can be removed.
6. Again tighten hexagon nuts 920.05 to fasten bearing housing 350.02 to cooling
chamber cover 165.02.
7.5.7.1.2 Fitting INPRO labyrinth seal into drive end bearing housing (if applicable)
CAUTION
1. Fit labyrinth seal 423.01, spacer ring 504.03 and circlip 932.01 on shaft 210.
2. Slide bearing housing 350.01 over spacer ring 504.03 to fit it into cooling
chamber cover 165.01.
3. Position the bearing housing on studs 902.01. Engage the outer diameter of
labyrinth seal 423.01 into inner diameter of bearing housing 350.01. Tighten
nuts 920.05 on studs 902.01 until bearing housing 350.01 along with labyrinth
seal 423.01 moves close enough to the face of mechanical seal 433.01 so that
segmental ring 501.20 can be inserted tightly into the gap between the face of
labyrinth seal 423.01 and the face of mechanical seal 433.01.
4. Continue tightening hexagon nuts 920.05 to fasten bearing housing 350.01 to
cooling chamber cover 165.01 until the outer diameter of labyrinth seal 423.01
engages completely into the inner diameter of bearing housing 350.01.
5. Loosen hexagon nuts 920.05 and remove bearing housing 350.01 until
segmental ring 501.20 is loosened and can be removed.
6. Again tighten hexagon nuts 920.05 to fasten bearing housing 350.01 to cooling
chamber cover 165.02.
CAUTION
Incorrect measurement values due to improperly installed temperature measuring
instrument.
Damage to the pump (set)!
▷ When mounting the bearings, the holes for measuring the temperature in the
bearing segments and the associated temperature measuring instrument
connections in the bearing housings and/or bearing covers must be in
alignment.
1. Fasten thrust bearing housing 350.02 to the crane by means of eyebolt and
rope.
2. Position rotor. (⇨ Section 7.5.5 Page 106)
3. For CHTR 2-3, insert segmental ring 501.04. Slide appropriately machined spacer
ring 504.01 onto shaft 210. (⇨ Section 7.5.4 Page 99)
As a general rule, always use a new spacer ring 504.01! This will ensure correct
positioning of the thrust bearing.
WARNING
Hot surfaces due to heating of components for assembly/dismantling
Risk of burns!
▷ Wear heat-resistant protective gloves.
▷ Remove flammable substances from the danger zone.
4. To facilitate fitting, the inner rings of the two angular contact ball bearings or
the two tapered roller bearings respectively may be heated uniformly to a
temperature of 110-120°C/230-248°F.
5. Use an appropriate device as described in assembly sketch UA3 37819 03 E to
slide the angular contact ball bearings 320 or tapered roller bearings 324 in
pairs onto shaft 210 and insert them into bearing housing 350.02.
6. Slide spacer sleeve 525.05 onto shaft 210.
7. Place slotted nut 920.12 onto the shaft. Tighten with normal hammer
tightening. Fit disc 550.06 and hexagon socket head cap screw 914.06 and
tighten with the tightening torque indicated in the relevant work instruction.
8. If applicable, insert oil ring 644.02 into the designated groove of spacer sleeve
525.05.
NOTE
If a tapered roller bearing is used, ensure parallel pin 562.04 is fitted between the
bearing housing and the non-drive end bearing cover.
9. Fit bearing cover 360.01 including labyrinth seal 423.02 and O-ring 412.09 along
with fan hood part 832.02. If a tapered roller bearing is used, parallel pin 562.10
must engage in the corresponding groove of bearing cover 602.01. Tighten
hexagon head bolts 901.03 uniformly; for tightening torque, see the relevant
work instruction.
10. Fit key 940.06 into the keyway of shaft 210.
11. Fit adapter 82-5 with assembled fan impeller 831 on the shaft, engaging key
940.06.
12. Place circlip 932.02 in its designated groove on shaft 210.
13. Fit fan hood 832.01 and secure in place using hexagon head bolts 901.02 and
discs 550.02.
NOTE
The bearing cover and the bearing housing have cast-on markings. Ensure during
assembly of the angular contact ball bearings that both markings coincide. They
need not coincide for the assembly of the tapered roller bearings.
NOTE
Zero axial clearance is required between bearing cover and bearing housing face!
Refer to work instructions (UA4 37827 01 and UA4 37828 01) (⇨ Section 9.4 Page
137)
WARNING
Hot surfaces due to heating of components for assembly/dismantling
Risk of burns!
▷ Wear heat-resistant protective gloves.
▷ Remove flammable substances from the danger zone.
3. To facilitate fitting, the inner ring of the cylindrical roller bearing 322 may be
heated uniformly to a temperature of 110-120°C/230-248°F.
4. Insert the outer ring of cylindrical roller bearing 322 including rollers and cage
in bearing housing 350.01.
5. Slide spacer sleeve 525.01 over the shaft 210. Tighten grub screws 904.16, secure
them with Loctite 221, and place oil ring 644.01 in the designated groove of
bearing sleeve 525.01.
6. Fit bearing cover 360.02 including O-ring 412.09 and labyrinth seal 423.01.
Tighten hexagon head bolts 901.01 uniformly; for tightening torque, see the
relevant work instruction.
NOTE
The bearing cover and the bearing housing have cast-on markings. Ensure during
assembly that both markings coincide.
NOTE
An axial clearance of about 0.5 to 1 mm/0.0197 to 0.0394 in is required between
bearing cover and bearing housing.
DANGER
Improper transport
Danger to life from falling parts!
▷ Observe the safety regulations for transport work. (⇨ Section 2 Page 9)
(⇨ Section 3 Page 14)
▷ Observe the applicable local occupational safety and accident prevention
regulations.
2
3
Drive
▪ See manufacturer's product literature
7.11.2 Recommended spare parts stock for 2 years' operation to DIN 24296
Table 19: Quantity of spare parts for recommended spare parts stock
Part No. Description Number of pumps (including stand-by pumps)
2 3 4 5 6 and 7 8 and 9 10 and
more
210.01/.02 Shaft (complete with small 1 1 1 2 2 2 20 %
parts)
230 Impeller (set) 1 1 1 2 2 2 20 %
314 Thrust bearing5) 1 1 2 2 3 4 50 %
320 Rolling element bearing (set)5) 1 1 2 2 2 3 25 %
322 Radial roller bearing5) 1 1 2 2 2 3 25 %
324 Thrust roller bearing5) 1 1 2 2 2 3 25 %
370 Bearing shell5) 1 1 2 2 3 4 50 %
384 Thrust bearing plate 1 1 2 2 3 4 50 %
388 Counter thrust bearing plate5) 1 1 2 2 3 4 50 %
400 Gasket (set) 4 6 8 8 9 10 100 %
411 Joint ring 4 6 8 8 9 10 100 %
412 O-ring (set) 4 6 8 8 9 10 100 %
420.01 Shaft seal ring 4 6 8 8 9 10 100 %
423.01 Labyrinth ring 4 6 8 8 9 10 100 %
433 Mechanical seal5) 1 1 2 2 2 3 25 %
456 Neck bush5) 1 1 2 2 2 3 30 %
501.01 Segmental ring 1 1 2 2 3 4 50 %
502.01/.02 Casing wear ring 2 2 2 3 3 4 50 %
503.01/.02 Impeller wear ring5) 1 1 2 2 3 4 50 %
/.04
8 Trouble-shooting
This section forms a part of the installation / operating manual and is not complete
by itself. The installation / operating manual must be read and understood in its
entirety.
8.1 Trouble-shooting
If problems occur that are not described in the following table, consultation with
KSB’s customer service is required.
Table 20: Trouble-shooting
Fault/malfunction Possible cause Remedy
Pump flow rate < specified Pump delivers against an Keep opening the shut-off element in the discharge
value excessively high pressure line until the duty point is reached.
Excessive back pressure Mount larger impeller(s).
Contact KSB’s service centre.
Increase the speed of the turbine or the combustion
engine.
Check system for impurities.
Pump and/or piping not Vent and/or prime.
completely vented and/or
primed
Inlet pipe or impeller(s) clogged. Remove deposits in the pump and/or piping.
Formation of air pockets in the Alter piping layout.
piping Fit a vent valve.
NPSHavailable (positive suction Check/alter the fluid level.
head) is too low Fully open the shut-off element in the inlet pipe.
Change inlet pipe if the friction losses in the inlet
pipe are too high.
Check any strainers installed.
Excessive speed of pressure fall Observe permissible speed of pressure fall.
Suction head too high Clean the strainer element and inlet pipe.
Correct/alter the fluid level.
Change the inlet pipe.
Check any strainers installed.
Wrong direction of rotation Interchange 2 phases of the power supply.
Speed is too low Increase the speed.
Increase the voltage.
Contact KSB’s service centre.
Internal parts worn Replace defective parts.
Contact KSB’s service centre.
Motor is running on two phases Replace defective fuses.
only. Check the power cable connections.
Pump discharge pressure pd Speed is too high Alter the impeller diameter.
> specified value Contact KSB’s service centre.
Inlet pressure ps < specified Damaged measuring instrument Replace the measuring instrument.
value Differential pressure in strainer Dismantle and clean the strainer element.
element too high
Shut-off element in the inlet Open the shut-off element.
pipe not fully open
Pressure in the inlet vessel too Check the inlet vessel and/or increase the pressure.
low
Pump discharge pressure pd Damaged measuring instrument Replace the measuring instrument.
< specified value Speed is too low Check the drive.
Inlet pressure too low Check the inlet pressure and inlet vessel.
Temperature of the medium Increase/reduce the temperature.
pumped is too low or too high.
Defective minimum flow system Check the minimum flow system.
Leakage at the shaft seal Defective shaft seal Check; replace, if required.
Score marks or roughness on Check shaft sleeve 523; replace, if required.
shaft sleeve 523
Seal cover tightened incorrectly Check.
9 Related Documents
NOTE
The specified noise characteristics are based on proper installation of the pump (set)
in accordance with this manual. Improper isolation of pump (set) and building/plant
or an inappropriate piping layout may increase noise emission and/or the vibration
level.
100
LpA
90
80
70
60
2900 rpm
50
1 10 100 1000 10000 PN
Fig. 61: Noise characteristics
LpA6) Surface sound pressure level
PN Rated power input
6) Measured at a distance of 1 m from the pump outline (as per DIN 45635 Parts 1 and 24)
9.2.3 Clearances
9.2.3.1 Clearance
Fig. 64: Clearance between double balance drum, balance disc seat and throttle bush
CHTR sizes 3 to 5 (250 bar) Sizes CHTR 5 (100 bar), CHTR 2 (250 bar),
Table 25: Tilting-pad thrust bearing clearances
Size Pressure Bearing clearance SLG 2 (diametral
[bar] clearance)
[mm] [inch]
2, 3, 4, 5 250 0.40 - 0.60 0.0157 - 0.0236
5 100 0.30 - 0.50 0.0118 - 0.0196
9.2.5 Interlock criterion for rolling element and plain bearings (only applicable if
resistance thermometers or thermocouples are used)
NOTE
Do not open bearing temperature measuring connections 4M.7 and 4M.8 while the
pump is running. All values indicated are based on normal ambient temperatures.
9.2.6 Permissible vibrations at the bearing housings (pump variants with plain or
rolling element bearings and grouted baseplates)
NOTE
The specified vibration values are based on proper installation of the pump (set) in
accordance with this manual. Improper isolation of pump (set) and building/plant or
an inappropriate piping layout may increase noise emission and/or the vibration
level.
Limits7) for unfiltered vibrations (vibration level) in the preferred operating range:
Q = 0.5 X Qopt to 1.25 X Qopt
Table 31: Vibration velocity RMS
Standard Alarm Tripping
Measuring mm/s inch/s mm/s inch/s mm/s inch/s
point
At the 3 0.12 ≥ 7.1 ≥ 0.28 ≥ 10.92 ≥ 0.43
bearing
housing
NOTE
An increase in vibration is allowed at flows outside the preferred operating range
but within the allowable operating range of 30 % of the values specified.
7) As per API 610/10, values Table 7; these values do not apply to minimum flow operation.
8) The values correspond to the limit value stipulated for zone B in part III of DIN ISO 10816-1 (August 1997 edition).
Admixtures
For concrete and cement mortar - also for fixing any anchoring parts in position -
only admixtures as per item 2 and exhibiting a valid test symbol must be used, and
only under the conditions stated in the test certificate. Chlorides, chloride-containing
or other substances expediting the corrosion of steel must not be added to
reinforced concrete as well as concrete and mortar coming into contact with
reinforced concrete.
Consistency of concrete
Concrete of consistency class F2, propagation value 35 to 41 cm (14 to 16 in) shall be
used.
9.2.9 Weights
NOTE
The weights indicated in the tables below are for orientation. The actual pump set
weight is indicated on the plate at the barrel casing.
500 Ring - - - - ✘ ✘ - - - - ✘ ✘
550.01 Disc ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘
550.15 Disc - - - - ✘ ✘ - - - - ✘ ✘
550.19 Disc - - - - - - - - - - ✘ ✘
902.02 Stud ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘
902.15 Stud - - - - ✘ ✘ - - - - ✘ ✘
902.19 Stud - - - - - - - - - - ✘ ✘
920.01 Nut ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘ ✘
920.15 Nut - - - ✘ ✘ - - - - - ✘ ✘
920.19 Nut - - - - - - - - - - ✘ ✘
NOTE
Always observe all signs at the pump (set).
Keep signs, plates and labels in a perfectly legible condition at all times.
Immediately replace any damaged or illegible signs, plates or labels by new ones.
! ! ! !
DE Betriebshandbuch beachten.
ES
Obsérvense el manual de
instrucciones.
PT
Observar instrucões do Manual de
Servico.
IT Osservare il manuale di istruzioni.
NL Bedrijfshandleiding opvolgen.
DK Vær opmærksom på driftshånbag.
SV Observera instruktionshandboken.
FI Käsikirjan ohjeita on noudatettava.
146 of 168
Record
CHTR
CHECKED / VERIFIED DIMENSIONS SIZE
t1 = L1-L3 = Dimension with 2 gaskets and1 Spacer
NOMINAL DIM. CHTR2=8.6 mm±0.1 disc of 2 mm thickness
9 Related Documents
1 2 3 4
NENNMASS ABMASS 1. WERK-NR.
NOMINAL SIZE TOLERANCE 1. WORK NUMBER
US
1:1
AS PER PART LIST
ALT. IND./ALT. No.
DATED/PRP. BY CHTR 2-5 100 bar ANG. CONT. B RG.
WORK INSTRUCTION
PROTO SCALE 1 : 2
312
F BRG. END COVER MACHINING
H&LP; KSBTECH
UA4 37827 01 1
2010 2
1 2 3 4
NENNMASS ABMASS 1. Works No.
NOMINAL SIZE TOLERANCE 1. WORK NUMBER
US
Note:
1:1
AS PER PART LIST
Old
CHTR 2-5 100bar Antifrict.
IND./ALT. No.
DATED/PRP. BY CO NT. B RG.
WORK INSTRUCTION
PROTO SCALE 1 : 2
312
F BRG. END COVER MACHINING
H&LP; KSBTECH
UA4 37827 01 2
2010 2
1 2 3 4
NENNMASS ABMASS 1. WERK-NR.
NOMINAL SIZE TOLERANCE 1. WORK NUMBER
US
1:1
AS PER PART LIST
ALT. IND./ALT. No.
DATED/PRP. BY CHTR 2-5 100 bar TAPER ROLL BRG.
WORK INSTRUCTION
PROTO SCALE 1 : 2
312
F BRG. END COVER MACHINING
H&LP; KSBTECH
UA4 37828 01 1
2010 2
1 2 3 4
NENNMASS ABMASS 1. WERK-NR.
NOMINAL SIZE TOLERANCE 1. WORK NUMBER
US
Note:
B
1:1
AS PER PART LIST
ALT. IND./ALT. No.
DATED/PRP. BY CHTR 2-5 100 bar TAPER ROLL BRG.
WORK INSTRUCTION
PROTO SCALE 1 : 2
312
F BRG. END COVER MACHINING
H&LP; KSBTECH
UA4 37828 01 2
2010 2
10 EC Declaration of Conformity
CHTR
▪ is in conformity with the provisions of the following Directives as amended from time to time:
– Pump (set): Machinery Directive 2006/42/EC
The manufacturer also declares that
▪ the following harmonised international standards have been applied:
– ISO 12100
– EN 809
Person authorised to compile the technical file:
Detlef Prokasky
Head of Product Development
High-pressure Ring-section Pumps from 64 bar
KSB Aktiengesellschaft
Johann-Klein-Straße 9
67227 Frankenthal
The EC Declaration of Conformity was issued in/on:
Place, date
..............................9).............................
Name
Function
Company
Address
11 Certificate of Decontamination
Type: ................................................................................................................................
Order number/
Order item number10): ................................................................................................................................
⃞ ⃞ ⃞ ⃞
Radioactive Explosive Corrosive Toxic
⃞ ⃞ ⃞ ⃞
Harmful Bio-hazardous Highly flammable Safe
Comments: ................................................................................................................................
................................................................................................................................
The product/accessories have been carefully drained, cleaned and decontaminated inside and outside prior to dispatch/
placing at your disposal.
We herewith declare that this product is free from hazardous chemicals, biological and radioactive substances.
On seal-less pumps, the rotor has been removed from the pump for cleaning.
...............................................................................................................................................................
...............................................................................................................................................................
We confirm that the above data and information are correct and complete and that dispatch is effected in accordance with
the relevant legal provisions.
Index
A Monitoring equipment 13
Abrasive fluids 69
Aligning the coupling 36 O
Applications 9 Oil lubrication
Assembly drawing 137, 138, 139 Oil quantity 128
Assembly Instructions 141, 142, 143, 144 Oil pipes 42
Oil quality 128
C Oil ring lubrication 128
Operating limits 62, 67
Certificate of decontamination 166 Order number 7
Clearance 122, 123, 124 Ordering spare parts 115
Plain bearing 124
Tilting-pad thrust bearing 125
Total theoretical axial clearances 125 P
Concrete quality 127 Partly completed machinery 7
Pickling solution 42
D Preservation for standstill 73
Designation 23
Dismantling 81 R
Disposal 22 Reassembly 81
Return to supplier 21
E Returning to service 74
Running noises 77
Explosion protection 12, 27, 34, 35, 46, 47, 48, 55, 59,
60, 65, 66, 67, 75, 77
S
F Safety 9
Safety awareness 11
Fluid handled Spare parts stock 115
Density 69 strainer/filter 43
Frequency of starts 67
T
I Temperature limits 12
Installation at site 27 Thrust bearing 101
Intended use 9 Tightening torques 125, 150, 151, 152
M W
Maintenance 75 Weights 128
Mechanical seal 60 Work Instructions 147, 148, 149, 159, 160, 161, 162,
Misuse 10 163, 164
--
www.weg.net
Português 2
English 58
Español 115
58 Motores Elétricos
www.weg.net
JIEC 60034-1 (2010): Rotating Electrical Machines - Part 1: Rating and Performance
JEN / IEC 60079-0 (2007): Explosive Atmospheres – Part 0: Equipment - General Requirements
JEN / IEC 60079-1 (2007): Explosive Atmospheres – Part 1: Equipment protection by flameproof enclosures “d”
JNBR IEC 60079-1 (2009): Proteção de Equipamento por Invólucro à Prova de Explosão “d”
JEN / IEC 60079-7 (2006): Explosive Atmospheres – Part 7: Equipment protection by increased safety “e”
JNBR IEC 60079-7 (2008): Proteção de Equipamentos por Segurança Aumentada “e”
JEN / IEC 60079-15 (2010): ): Explosive Atmospheres – Part 15: Equipment protection by type of protection “n”
JNBR IEC 60079-15 (2007): Construção, Ensaio e Marcação de Equipamentos Elétricos com Tipo de Proteção “n”
JEN / IEC 60079-31 (2008): Explosive Atmospheres – Part 31: Equipment dust ignition protection by enclosure “t”
JIEC 61241-0 (2004): Electrical apparatus for use in the presence of combustible dust - Part 0: General requirements
JNBR IEC 61241-0 (2006): Equipamentos Elétricos para Utilização em Presença de Poeira Combustível - Parte 0:
Requisitos Gerais
JNBR IEC 61241-1 (2007): Equipamentos Elétricos para Utilização em Presença de Poeira Combustível - Parte 1:
JCSA C22.2 N°145 (1986) – Motors and Generators for Use in Hazardous Locations
JCSA C22.2 N°30 (1986) - Explosion-Proof Enclosures for Use in Class I Hazardous Locations
JCSA C22.2 N°213 (1987) - Non-Incendive Electrical Equipment for Use in Class I, Division 2 Hazardous Locations
Information about classification of areas and safety requirements to be considered during equipment repair, overhaul
and reclamation, when applicable, can be found in the following standards:
JEN / IEC 60079-10-1 (2008): Classification of areas - Explosive gas atmospheres
JABNT NBR IEC 60079-10-1 (2009): Classificação de áreas - Atmosferas explosivas de gás
JEN/ IEC 60079-10-2 (2009): Classification of areas - Combustible dust atmospheres
JEN / IEC 60079-14 (2007): Electrical installations design, selection and erection
If you have any questions regarding this manual, please contact WEG branch.
TABLE OF CONTENTS
1. TERMINOLOGY 62
2. INITIAL RECOMMENDATIONS 66
3. SAFETY INSTRUCTIONS 71
4.1. LIFTING................................................................................................................................................. 72
4.1.1. Horizontal motors with one eyebolt ......................................................................................... 72
4.1.2. Horizontal motor with two eyebolts ........................................................................................ 73
4.1.3. Vertical Motors .......................................................................................................................... 74
4.1.3.1. Procedures to place W22 motors in the vertical position .................................................. 74
4.1.3.2. Procedures to place HGF motors in the vertical position ................................................. 75
4.2 PROCEDURES TO PLACE W22 VERTICAL MOUNT MOTORS IN HORIZONTAL POSITION ....... 76
5. STORAGE 78
5.2. STORAGE............................................................................................................................................. 78
5.3 BEARINGS ............................................................................................................................................ 79
5.3.1 Grease lubricated bearings ....................................................................................................... 79
5.3.2 Oil Lubricated bearings ............................................................................................................. 79
5.3.3 Oil Mist lubricated bearings ...................................................................................................... 80
5.3.4 Sleeve Bearing ............................................................................................................................ 80
5.4. INSULATION RESISTANCE ................................................................................................................ 80
5.4.1. Insulation resistance measurement ........................................................................................ 80
6. INSTALLATION 83
7. COMMISSIONING 101
8. MAINTENANCE 105
ENGLISH
8.2.2. Oil lubricated bearings ........................................................................................................... 109
8.2.3. Oil mist lubricated bearings................................................................................................... 109
8.2.4. Sleeve bearings ....................................................................................................................... 109
8.3. MOTOR ASSEMBLY AND DISASSEMBLY ...................................................................................... 110
8.3.1. Terminal box ..............................................................................................................................111
8.4. DRYING THE STATOR WINDING INSULATION .............................................................................. 112
8.5. SPARE PARTS ................................................................................................................................... 112
1. TERMINOLOGY
Balancing: the procedure by which the mass distribution of a rotor is checked and, if necessary, adjusted to
ensure that the residual unbalance or the vibration of the journals and/or forces on the bearings at a frequency
corresponding to service speed are within specified limits in International Standards.
Balance quality grade: indicates the peak velocity amplitude of vibration, given in mm/s, of a rotor running
free-in-space and it is the product of a specific unbalance and the angular velocity of the rotor at maximum
operating speed.
Hazardous area: area in which an explosive atmosphere is present, or may be expected to be present, in
quantities such as to require special precautions for the construction, installation and use of electrical
apparatus.
Non-hazardous area: area in which an explosive atmosphere is not expected to be present in quantities such
as to require special precautions for the construction, installation and use of electrical apparatus.
Explosive atmosphere: mixture with air, under atmospheric conditions, of flammable substances in the form
of gas, vapour, dust, fibres, or flyings which, after ignition, permits self-sustaining propagation.
Temperature class: maximum surface temperature of the equipment. Following temperature classes are
defined:
Temperature Class
Maximum surface temperature (°C)
IEC NEC
T1 T1 450
T2 T2 300
- T2A 280
- T2B 260
- T2C 230
- T2D 215
T3 T3 200
- T3A 180
- T3B 165
- T3C 160
T4 T4 135
- T4A 120
- T5 100
- T6 85
Simple apparatus: electrical component or combination of components of simple construction with well-
defined electrical parameters which is compatible with the intrinsic safety of the circuit in which it is used.
Flameproof enclosure "d" (Ex d): type of protection in which the parts capable of igniting an explosive gas
atmosphere are provided with an enclosure which can withstand the pressure developed during an internal
explosion of an explosive mixture, and which prevents the transmission of the explosion to the explosive gas
atmosphere surrounding the enclosure
Increased safety "e" (Ex e): type of protection applied to electrical apparatus in which additional measures
are applied so as to give increased security against the possibility of excessive temperatures and of the
occurrence of arcs and sparks in normal service or under specified abnormal conditions.
Type of protection "n" (Ex n): type of protection applied to electrical apparatus such that, in normal operation
and in certain specified abnormal conditions, it is not capable of igniting a surrounding explosive gas
atmosphere.
Dust ignition protection by enclosure “t” (Ex t): type of protection for explosive dust atmosphere where
electrical equipment is provided with an enclosure providing dust ingress protection and a means to limit
surface temperatures.
Gas groups: are subdivided according to the nature of the explosive atmosphere for which they are intended:
JGroup I: coal mines susceptible to firedamp (methane).
JGroup II: areas not susceptible to firedamp. This group is subdivided into:
JGroup IIA (IEC) / D (NEC): propane, acetone, butane, combustible gas, gasoline, ethyl alcohol, methyl
ENGLISH
Dust groups: are subdivided into (excepting mines susceptible to firedamp (methane)):
JGroup IIIA (IEC): combustible fibers / combustible flyings – solid particles, including fibers larger than 500 μm
JGroup IIIB (IEC): electrically nonconductive dusts – solid particles smaller than 500 μm, with electrical
10³ Ω.m
JGroup E (NEC): combustible metallic powders, for example: aluminum, magnesium and their commercial
alloys.
JGroup F (NEC): combustible carbonaceous dusts that have more than 8% total entrapped volatiles.
JGroup G (NEC):atmospheres containing dusts not included in Group E and F, including flour, grain wood ,
Flameproof joint: place where the corresponding surfaces of two parts of an enclosure, or the conjunction of
enclosures, come together, and which prevents the transmission of an internal explosion to the explosive gas
atmosphere surrounding the enclosure.
Symbol “X”: symbol used to denote special conditions for safe use.
Equipment Protection Level - EPL: level of protection assigned to equipment based on its likelihood of
becoming a source of ignition and distinguishing the differences between explosive gas atmospheres, explosive
dust atmospheres, and the explosive atmospheres in mines susceptible to firedamp. These EPLs are classified
into:
JEPL Ga: equipment for explosive gas atmospheres, having a “very high” level of protection, which is not a
source of ignition in normal operation, during expected malfunctions ou during rare malfunctions.
EPL Gb: equipment for explosive gas atmospheres, having a “high” level of protection, which is not a source
J
EPL Gc: equipment for explosive gas atmosphere, having a “enhanced” level of protection, which is not a
J
source of ignition in normal operation and which may have some additional protection to ensure that it
remains inactive as an ignition source in case of regular expected occurrences (for example failure of a lamp).
Manual of Electric Motors 63
www.weg.net
EPL Da: equipment for explosive dust atmospheres, having a “very high” level of protection, which is not a
J
source of ignition in normal operation, during expected malfunctions, or during rare malfunctions.
EPL Db: equipment for explosive dust atmospheres, having a “high” level of protection, which is not a source
J
EPL Dc: equipment for explosive dust atmospheres, having a “enhanced” level of protection, which is not a
J
source of ignition in normal operation and which may have some additional protection to ensure that it
remains inactive as an ignition source in the case of regular expected occurrences ( for example failure of a
lamp).
EPL Ma: equipment for installation in a mine susceptible to firedamp, having a “very high” level of protection,
J
which has sufficient security that it is unlikely to become an ignition source in normal operation, during
expected malfunctions or during rare malfunctions, even when left energized in the presence of an outbreak
of gas.
EPL Mb: equipment for installation in a mine susceptible to firedamp, having a “high” level of protection, which
J
has sufficient security that it is unlikely to become an source of ignition in normal operation or during expected
malfunctions in the time span between there being an outbreak of gas and the equipment being de-
energized.
Time “tE”: time taken for an a.c. rotor or stator winding, when carrying the initial starting current IA, to be heated
up to the limiting temperature from the temperature reached in rated service at the maximum ambient
temperature. See Figure 1-1.
ENGLISH
Symbols
T - temperature
A – maximum allowed ambient temperature
B – service temperature
C – limiting temperature
t - time
1 – temperature rise in rated service
2 – Temperature rise during locked rotor test
Type of protection: set of specific measures applied to electrical apparatus to avoid ignition of a surrounding
explosive atmosphere by such apparatus.
Zones: hazardous areas are classified in terms of zones on the basis of the frequency and duration of the
occurrence of an explosive atmosphere.
Zone 0 (IEC) / Class I Div 1 (NEC): area in which an explosive gas atmosphere is present continuously, or for
long periods or frequently.
Zone 1 (IEC) / Class, I Div 1 (NEC): area in which an explosive gas atmosphere is likely to occur in normal
operation occasionally.
Zone 2 (IEC) / Class I, Div 2 (NEC): area in which an explosive gas atmosphere is not likely to occur in normal
operation, but if it does occur, will persist for a short period only.
Zone 20 (IEC) / Class II, Div 1 (NEC): area in which an explosive atmosphere in the form of a cloud of
combustible dust in air is present continuously, or for long periods or frequently.
ENGLISH
[IEC 60050 IEV number 426-03-23]
Zone 21 (IEC) / Class II, Div 1 (NEC): area in which an explosive atmosphere in the form of a cloud of
combustible dust in air is likely to occur, occasionally, in normal operation.
Zone 22 (IEC) / Class II, Div 2 (NEC): area in which an explosive atmosphere in the form of a cloud of
combustible dust in air is not likely to occur in normal operation but, if it does occur, will persist for a short
period only.
Live Part: Conductor or conductive part intended to be energized in normal operation, including a neutral
conductor.
Note: The qualification is only valid for the company that trained the employee in the conditions set out by the authorized and qualified
professional responsible for training.
2. INITIAL RECOMMENDATIONS
Motors for hazardous areas are specially designed to meet the government regulations regarding the
environment in which they are installed. Misapplication, incorrect connection or other changes although
small, may jeopardize product reliability.
Electric motors have energized circuits, exposed rotating parts and hot surfaces that may cause serious injury
to people during normal operation. Therefore, it is recommended that transportation, storage, installation,
operation and maintenance services are always performed by qualified personnel.
Also the applicable procedures and relevant standards of the country where the machine will be installed must
be considered.
Noncompliance with the recommended procedures in this manual may cause severe personal injuries and/or
substantial property damage and may void the product warranty.
For practical reasons, it is not possible to include in this Manual detailed information that covers all construction
variables nor covering all possible assembly, operation or maintenance alternatives.
This Manual contains only the required information that allows qualified and trained personnel to carry out their
services. The product images are shown for illustrative purpose only and the type of protection is not represented.
The type of protection and the Equipment Protection Level (EPL) indicated on the motor nameplate must be
respected considering the explosive atmosphere where the motor will be installed.
Components added to the motor by the user, such as cable-glands, threaded plugs, encoder, etc. must meet the
type of protection, the Equipment Protection Level (EPL) in accordance with the standards indicated on the
product certificate.
The symbol “X” added to the certificate number, informed on the motor nameplate, denotes that motor requires
special conditions for installation, use and/or maintenance, as described in the certificate.
ENGLISH
Failure to follow these requirements may affect the product and installation safety.
For Smoke Extraction Motors, please refer to the additional instruction manual 50026367 available on the website
www.weg.net.
For brake motors, please refer to the information contained in WEG 50006742 / 50021973 brake motor manual
available on the website www.weg.net.
For information about permissible radial and axial shaft loads, please check the product technical catalogue.
The user is responsible for the correct classification of the area for the motor installation, for the definition
of environment conditions and application characteristics.
During the warranty period, all repair, overhaul and reclamation services must be carried out by WEG
authorized Service Centers for explosive atmospheres to maintain validity of the warranty.
Special attention should be given to the type of protection and/or to the Equipment Protection Level.
J Remove the shaft locking device (if any) and rotate the shaft by hand to ensure that it rotates freely.
J Check that the motor has not been exposed to excessive dust and moisture during the transportation.
Do not remove the protective grease from the shaft, or the plugs from the cable entries. These protections must
remain in place until the installation has been completed.
2.3. NAMEPLATES
The nameplate contains information that describes the construction characteristics and the performance of the
motor. Figure 2-1, Figure 2-2, Figure 2-3 and Figure 2-4 show nameplate layout examples.
ENGLISH
ENGLISH
14 F.P / P.F Power factor
15 AMB. Ambient Temperature (°C)
16 F.S. / S.F. Service factor
17 ALT. Altitude (m.a.s.l.)
18 kg / lb / WEIGHT Weight (kg / lb)
19 DE bearing specification and amount of grease
20 NDE bearing specification and amount of grease
21 Grease type used for bearing lubrication
22 Lubrication interval (h)
23 Connection diagram
24 Hazardous areas / Type of protection / Certificate1)
25 I A / IN / IP / IN Starting current / rated current relationship
26 CAT. / DES. Design
27 I.F.S. / S.F.A. Service factor amps (A)
28 Serial number
The product certificates can be obtained from WEG. Please contact WEG nearest Office.
Motor marking intended for use in hazardous areas: the marking system is indicated according to the standards
applicable for each type of protection:
3. SAFETY INSTRUCTIONS
The motor must be disconnected from the power supply and be completely stopped before conducting
any installation or maintenance procedures. Additional measures should be taken to avoid accidental
motor starting.
Professionals working with electrical installations, either in the assembly, operation or maintenance,
should use proper tools and be instructed on the application of standards and safety requirements,
including the use of Personal Protective Equipment (PPE) that must be carefully observed in order to
reduce risk of personal injury during these services.
Electric motors have energized circuits, exposed rotating parts and hot surfaces that may cause serious
injury to people during normal operation. It is recommended that transportation, storage, installation,
operation and maintenance services are always performed by qualified personnel.
Always follow the safety, installation, maintenance and inspection instructions in accordance with the applicable
standards in each country.
ENGLISH
Eyebolts provided on the frame are designed for lifting the machine only. Do not use these eyebolts for
lifting the motor with coupled equipment such as bases, pulleys, pumps, reducers, etc.
Never use damaged, bent or cracked eyebolts. Always check the eyebolt condition before lifting the motor.
Eyebolts mounted on components, such as on end shields, forced ventilation kits, etc. must be used for lifting
these components only. Do not use them for lifting the complete machine set.
Handle the motor carefully without sudden impacts to avoid bearing damage and prevent excessive mechanical
stresses on the eyebolts resulting in its rupture.
To move or transport motors with cylindrical roller bearings or angular contact ball bearings, use always
the shaft locking device provided with the motor.
All HGF motors, regardless of bearing type, must be transported with shaft locking device fitted.
4.1. LIFTING
Before lifting the motor ensure that all eyebolts are tightened properly and the eyebolt shoulders are in
contact with the base to be lifted, as shown in Figure 4.1. Figure 4.2 shows an incorrect tightening of the
eyebolt.
ENGLISH
Ensure that lifting machine has the required lifting capacity for the weight indicated on the motor nameplate.
Figure 4.1 – Correct tightening of the eyebolt Figure 4.2 – Incorrect tightening of
the eyebolt.
The center-of-gravity may change depending on motor design and accessories. During the lifting
procedures the maximum allowed angle of inclination should never be exceeded as specified below.
Figure 4.3 – Maximum allowed angle-of-inclination for motor with one eyebolt.
There are two possible eyebolt arrangements (vertical and inclined), as shown below:
J For motors with vertical lifting eyebolts, as shown in Figure 4.4, the maximum allowed lifting angle should not
exceed 45° in relation to the vertical axis. We recommend to use a spreader beam for maintaining the lifting
elements (chain or rope) in vertical position and thus preventing damage to the motor surface.
45° Max.
Figure 4.4 – Maximum resulting angle for motors with two or more lifting eyebolts.
J For HGF motors, as shown in Figure 4.5, the maximum resulting angle should not exceed 30° in relation to the
vertical axis.
ENGLISH
30° Max.
J For motors fitted with inclined eyebolts, as shown in Figure 4.6, the use of a spreader beam is required for
maintaining the lifting elements (chain or rope) in vertical position and thus preventing damage to the motor
surface.
Always use the eyebolts mounted on the top side of the motor, diametrically opposite, considering the
mounting position. See Figure 4.8.
ENGLISH
4. Reduce the load on the first pair of eyebolts to start the motor rotation, as shown in Figure 4.11. This
procedure must be carried out slowly and carefully.
ENGLISH
Figure 4.11 – End result: motor placed in vertical position.
These procedures will help you to move motors designed for vertical mounting. These procedures are also
used to place the motor from the horizontal position into the vertical position and vertical to horizontal.
2. Lower the hoist fixed to motor drive end while lifting the hoist fixed to motor non-drive end until the motor
reaches its equilibrium, see Figure 4.13.
3. Remove the hoist hooks from the drive end eyebolts and rotate the motor 180° to fix the removed hooks into
the two eyebolts at the motor non-drive end, see Figure 4.14.
ENGLISH
Figure 4.14 – Lifting HGF motors by the eyebolts at the non-drive end.
4. Fix the removed hoist hooks in the other two eyebolts at the non-drive end and lift the motor until the vertical
position is reached, see Figure 4.15.
These procedures will help you to move motors designed for vertical mounting. These procedures are also
used to place the motor from the horizontal position into the vertical position and vertical to horizontal.
1. Ensure that all eyebolts are tightened properly, as shown in Figure 4.1;
2. Install the first pair of eyebolts and lift the motor as shown in Figure 4.16;
ENGLISH
Figure 4.17 – Install the second pair of eyebolts
4. Reduce the load on the first pair of eyebolts for rotating the motor, as shown in Figure 4.18. This procedure
must be carried out slowly and carefully.
5. STORAGE
If the motor is not installed immediately, it must be stored in a dry and clean environment, with relative humidity
not exceeding 60%, with an ambient temperature between 5 ºC and 40 ºC, without sudden temperature
changes, free of dust, vibrations, gases or corrosive agents. The motor must be stored in horizontal position,
unless specifically designed for vertical operation, without placing objects on it. Do not remove the protection
grease from shaft end to prevent rust.
If the motor are fitted with space heaters, they must always be turned on during the storage period or when the
installed motor is out of operation. Space heaters will prevent water condensation inside the motor and keep
the winding insulation resistance within acceptable levels. Store the motor in such position that the condensed
water can be easily drained. If fitted, remove pulleys or couplings from the shaft end (more information are given
on item 6).
The space heaters should never be energized when the motor is in operation.
For the use of space heaters in motors that are stored in hazardous area, adopt the same cable inlet and
connection requirements described in item 6.
Notes:
1) Never stack larger packaging onto smaller packaging.
2) Align the packaging correctly (see Figure 5.1 and Figure 5.2).
3) The feet of the crates above should always be supported by suitable wood battens (Figure 5.3) and never
stand on the steel tape or without support (Figure 5.4).
4) When stacking smaller crates onto longer crates, always ensure that suitable wooden supports are provided
to withstand the weight (see Figure 5.5). This condition usually occurs with motor packaging above IEC 225S/M
(NEMA 364/5T) frame sizes.
ENGLISH
Figure 5.5 – Use of additional battens for stacking
5.3 BEARINGS
5.3.1 Grease lubricated bearings
We recommend rotating the motor shaft at least once a month (by hand, at least five revolutions, stopping the
shaft at a different position from the original one). If the motor is fitted with shaft locking device, remove it before
rotating the shaft and install it again before performing any handling procedure. Vertical motors may be stored
in the vertical or in horizontal position. If motors with open bearings are stored longer than six months, the
bearings must be relubricated according to Item 8.2 before commissioning of the motor.
If the motor is stored for longer than 2 years, the bearings must be replaced or removed, washed, inspected
and relubricated according to Item 8.2.
The oil must always be removed when the motor has to be handled. If the oil mist system is not operating after
installation, fill the bearings with oil to prevent bearing rusting. During the storage period, rotate the shaft by
hand, at least five revolutions, stopping it at a different position from the original one. Before starting the motor,
all bearing protection oil must be drained from the bearing and the oil mist system must be switched ON.
The insulation resistance must be measured with a megohmmeter. The machine must be in cold state and
disconnected from the power supply.
To prevent the risk of an electrical shock, ground the terminals before and after each measurement.
Ground the capacitor (if any) to ensure that it is fully discharged before the measurement is taken.
It is recommended to insulate and test each phase separately. This procedure allows the comparison of the
insulation resistance between each phase. During the test of one phase, the other phases must be grounded.
The test of all phases simultaneously evaluates the insulation resistance to ground only but does not evaluate
the insulation resistance between the phases.
The power supply cables, switches, capacitors and other external devices connected to the motor may
considerably influence the insulation resistance measurement. Thus all external devices must be disconnected
and grounded during the insulation resistance measurement.
Measure the insulation resistance one minute after the voltage has been applied to the winding. The applied
voltage should be as shown in Table 5.3.
Table 5.3 – Voltage for the insulation resistance
Winding rated voltage (V) Testing voltage for measuring the insulation resistance (V)
< 1000V 500
1000 - 2500 500 - 1000
2501 - 5000 1000 - 2500
5001 - 12000 2500 - 5000
> 12000 5000 - 10000
The reading of the insulation resistance must be corrected to 40 °C as shown in the Table 5.4.
ENGLISH
Measuring temperature Correction factor of the Measuring temperature of Correction factor of the
of the insulation insulation resistance the insulation resistance insulation resistance
resistance (°C) corrected to 40 °C (°C) corrected to 40 °C
10 0.125 30 0.500
11 0.134 31 0.536
12 0.144 32 0.574
13 0.154 33 0.616
14 0.165 34 0.660
15 0.177 35 0.707
16 0.189 36 0.758
17 0.203 37 0.812
18 0.218 38 0.871
19 0.233 39 0.933
20 0.250 40 1.000
21 0.268 41 1.072
22 0.287 42 1.149
23 0.308 43 1.231
24 0.330 44 1.320
25 0.354 45 1.414
26 0.379 46 1.516
27 0.406 47 1.625
28 0.435 48 1.741
29 0.467 49 1.866
30 0.500 50 2.000
The motor insulation condition must be evaluated by comparing the measured value with the values
indicated in Table 5.5 (corrected to 40 °C):
Table 5.5 – Evaluation of the insulation system
Limit value for rated voltage Limit value for rated voltage
Situation
up to 1.1 kV (MΩ) above 1.1 kV (MΩ)
Dangerous. The motor can not
Up to 5 Up to 100
be operated in this condition
5 to 100 100 to 500 Regular
100 to 500 Higher than 500 Good
Higher than 500 Higher than 1000 Excellent
The values indicated in the table should be considered only as reference values. It is advisable to log all
measured values to provide a quick and easy overview on the machine insulation resistance.
If the insulation resistance is low, moisture may be present in the stator windings. In this case the motor
should be removed and transported to a WEG authorized Service Center for proper evaluation and repair
(This service is not covered by the warranty). To improve the insulation resistance through the drying
process, see section 8.4.
ENGLISH
6. INSTALLATION
The installation of electric motors in hazardous areas must be always performed by qualified personnel
with knowledge on relevant standards and safety rules.
1. Insulation resistance: must be within the acceptable limits. See item 5.4.
2. Bearings:
If the electric motor is installed without running immediately, proceed as described in item 5.3.
3. Operating conditions of the start capacitors: If single-phase motors are stored for a period of over two years,
it is recommended to change the start capacitors before motor starting since they lose their operating
characteristics.
4. Terminal box:
a. the inside of the terminal box must be clean and dry.
b. the contacts must be correctly connected and corrosion free. See 6.9 and 6.10.
c. the cable entries must be correctly sealed and the terminal box cover properly mounted in order to ensure
the degree of protection indicated on the motor nameplate.
5. Cooling: the cooling fins, air inlet and outlet openings must be clean and unobstructed. The distance
between the air inlet openings and the wall should not be shorter than ¼ (one quarter) of the diameter of the
air inlet. Ensure sufficient space to perform the cleaning services. See item 7.
6. Coupling: remove the shaft locking device (where fitted) and the corrosion protection grease from the shaft
end and flange just before installing the motor. See item 6.4.
7. Drain hole: the motor must always be positioned so the drain hole is at the lowest position (If there is any
indication arrow on the drain, the drain must be so installed that the arrow points downwards).
Motors supplied with rubber drain plugs leave the factory in the closed position and must be opened
periodically to allow the exit of condensed water. For environments with high water condensation levels and
ENGLISH
motor with degree of protection IP55, the drain plugs can be mounted in open position (see Figure 6.1).
For motors with degree of protection IP56, IP65 or IP66, the drain plugs must remain at closed position (see
Figure 6.1), being opened only during the motor maintenance procedures.
The drain system of motors with Oil Mist lubrication system must be connected to a specific collection
system (see Figure 6.12).
Figure 6.1 – Detail of the rubber drain plug mounted in closed and open position.
8.Additional recommendations:
a. Check the direction of motor rotation, starting the motor at no-load before coupling it to the load.
b. Vertical mounted motors with shaft end down must be fitted with drip cover to protect them from liquids
or solids that may drop onto the motors.
c. Vertical mounted motors with shaft end up should be fitted with water slinger ring to prevent water
ingress inside the motor.
6.1. FOUNDATIONS
The foundation is the structure, structural element, natural or prepared base, designed to withstand the
stresses produced by the installed equipment, ensuring safe and stable performance during operation. The
foundation design should consider the adjacent structures to avoid the influences of other installed equipment
and no vibration is transferred through the structure.
The foundation must be flat and its selection and design must consider the following characteristics:
a) The features of the machine to be installed on the foundation, the driven loads, application, maximum
allowed deformations and vibration levels (for instance, motors with reduced vibration levels, foot flatness,
flange concentricity, axial and radial loads, etc. lower than the values specified for standard motors).
b) Adjacent buildings, conservation status, maximum applied load estimation, type of foundation and fixation
and vibrations transmitted by theses constructions.
If the motor is supplied with leveling/alignment bolts, this must be considered in the base design.
Please consider for the foundation dimensioning all stresses that are generated during the operation
ENGLISH
The foundation stresses can be calculated by using the following equations (see Figure 6.2):
F1 = 0,5 * g * m – (4 * Tb / A)
F2 = 0,5 * g * m + (4 * Tb / A)
Where:
J Metallic bases: are generally used for small-size motors (see Figure 6.3).
F1 F1
A
F2 F2
Figure 6.2 – Motor installed on concrete base Figure 6.3 – Motor installed on metallic base
The metallic and concrete bases may be fitted with sliding system. These types of foundations are generally
used where the power transmission is achieved by belts and pulleys. This power transmission system is easier
to assemble/disassemble and allows the belt tension adjustment. Other important aspect of this foundation
type is the location of the base locking screws that must be diagonally opposite. The rail nearest the drive
pulley is placed in such a way that the positioning bolt is between the motor and the driven machine. The other
rail must be placed with the bolt on the opposite side (diagonally opposite), as shown in Figure 6.4 .
J leveling screws;
J positioning screws;
ENGLISH
Figure 6.4 – Motor installed on sliding base
After completing the installation, it is recommended that all exposed machined surfaces are coated with
suitable rust inhibitor.
Footless motors supplied with transportation devices, according to Figure 6.5, must have their devices
removed before starting the motor installation.
L = 1.5 x D
D
Figure 6.6 – Mounting system of a foot mounted motor
The drawings of the flange mounting dimensions, IEC and NEMA flanges, can be checked in the technical
catalogue.
The coupling of the driven equipment to the motor flange must be properly dimensioned to ensure the required
concentricity of the assembly.
Depending on the flange type, the mounting can be performed from the motor to the driven equipment flange
(flange FF (IEC) or D (NEMA)) or from the driven equipment flange to the motor (flange C (DIN or NEMA)).
For the mounting process from the driven equipment flange to the motor, you must consider the bolt length,
flange thickness and the thread depth of the motor flange.
If the motor flange has tapped through-holes, the length of the mounting bolts must not exceed the
tapped through-hole length of the motor flange, thus preventing damage to the winding head.
For flange mounting the thread engagement length of the mounting bolt should be at least 1.5 times the bolt
diameter. In severe applications, longer thread engagement length may be required.
In severe applications or if large motors are flange mounted, a foot or pad mounting may be required in addition
to the flange mounting (Figure 6.7). The motor must never be supported on its cooling fins.
Figure 6.7 - Mounting method of flange mounted motors with frame base support
Note:
When liquid (for example oil) is likely to come into contact with the shaft seal, please contact your local WEG representative.
6.3. BALANCING
Unbalanced machines generate vibration which can result in damage to the motor. WEG motors are
dynamically balanced with “half key” and without load (uncoupled). Special balancing quality level must be
stated in the Purchase Order.
The transmission elements, such as pulleys, couplings, etc., must balanced with “half key” before they
are mounted on the motor shaft.
The balance quality grade meets the applicable standards for each product line.
ENGLISH
The maximum balancing deviation must be recorded in the installation report
6.4. COUPLINGS
Couplings are used to transmit the torque from the motor shaft to the shaft of the driven machine. The
following aspects must be considered when couplings are installed:
J Use proper tools for coupling assembly & disassembly to avoid damages to the motor and bearings.
J Whenever possible, use flexible couplings, since they can absorb eventual residual misalignments during the
machine operation.
J The maximum loads and speed limits informed in the coupling and motor manufacturer catalogues cannot
be exceeded.
J Level and align the motor as specified in sections 6.5 and 6.6, respectively.
Remove or fix the shaft key firmly when the motor is operated without coupling in order to prevent
accidents.
Do not use roller bearings for direct coupling unless sufficient radial load is expected.
Excessive belt tension will damage the bearings and cause unexpected accidents such as breakage of
the motor shaft.
To prevent the buildup of static electricity in the belt drive system, use only properly grounded belts in
conductive construction.
Motors designed with sleeve bearings must be operated with direct coupling to the driven machine or a
gearbox. Pulley and belts can not be applied for sleeve bearing motors.
Motors designed with sleeve bearings have 3 (three) marks on the shaft end. The center mark is the indication
of the magnetic center and the 2 (two) outside marks indicate the allowed limits of the rotor axial movement, as
shown in Figure 6.9.
The motor must be so coupled that during operation the arrow on the frame is placed over the central mark
indicating the rotor magnetic center. During start-up, or even during operation, the rotor may freely move
between the two outside marks when the driven machine exerts an axial load on the motor shaft. However,
under no circumstance, the motor can operate continuously with axial forces on the bearing.
Axial Clearance
ENGLISH
For coupling evaluation consider the maximum axial bearing clearance as shown in Table 6.1.
The axial clearance of the driven machine and coupling influence the maximum bearing clearance.
* For Motors in accordance with API 541, the total axial clearance is 12.7 mm
The sleeve bearings used by WEG were not designed to support axial load continuously.
Under no circumstance must the motor be operated continuously at its axial clearance limits.
6.5. LEVELING
The motor must be leveled to correct any deviations in flatness arising from the manufacturing process and the
material structure rearrangement. The leveling can be carried out by a leveling screw fixed on the motor foot or
on the flange or by means of thin compensation shims. After the leveling process, the leveling height between
the motor mounting base and the motor cannot exceed 0.1 mm.
If a metallic base is used to level the height of the motor shaft end and the shaft end of the driven machine, level
only the metallic base relating to the concrete base.
Record the maximum leveling deviations in the installation report.
6.6. ALIGNMENT
The correct alignment between the motor and the driven machine is one of the most important variables that
extends the useful service life of the motor. Incorrect coupling alignment generates high loads and vibrations
reducing the useful life of the bearings and even resulting in shaft breakages. Figure 6.10 illustrates the
misalignment between the motor and the driven machine.
Motor shaft Driven machine shaft
Max.
misalignment
Driven machine
offset (mm)
Motor
offset (mm)
ENGLISH
Figure 6.10 – Typical misalignment condition
Alignment procedures must be carried out using suitable tools and devices, such as dial gauge, laser alignment
instruments, etc. The motor shaft must be aligned axially and radially with the driven machine shaft.
The maximum allowed eccentricity for a complete shaft turn should not exceed 0.03 mm, when alignment is
made with dial gauges, as shown in Figure 6.11. Ensure a gap between couplings to compensate the thermal
expansion between the shafts as specified by the coupling manufacturer.
Dial gauge
Reference
Line
GAP
If alignment is made by a laser instrument, please consider the instructions and recommendations provided by
the laser instrument manufacturer.
The alignment should be checked at ambient temperature with machine at operating temperature.
Pulley and belt couplings must be so aligned that the driver pulley center lies in the same plane of the driven
pulley center and the motor shaft and the shaft of the driven machine are perfectly parallel.
After completing the alignment procedures, ensure that mounting devices do not change the motor and
machine alignment and leveling resulting into machine damage during operation.
It is recommended to record the maximum alignment deviation in the Installation Report.
Inlet
Drain
Outlet
Figure 6.12 – Oil supply and drain system of oil lubricated or oil mist lubricated motors
cooling. According to item 7.2, ensure correct cooling water flow rate and water temperature in the motor
cooling system.
Before connecting the motor, check if the power supply voltage and the frequency comply with the
motor nameplate data. All wiring must be made according to the connection diagram on the motor
nameplate. Please consider the connection diagrams in the Table 6.2 as reference value.
To prevent accidents, check if motor has been solidly grounded in accordance with the applicable standards.
6 4 5 6 4 5
6 '-Y 1 2 3 1 2 3
L1 L2 L3 L1 L2 L3
4 5 6 4 5 6
7 8 9 7 8 9
YY - Y 1 2 3 1 2 3
L1 L2 L3 L1 L2 L3
9
4 5 6 4 5 6
7 8 9 7 8 9
Single Speed ''-' 1 2 3 1 2 3
L1 L2 L3 L1 L2 L3
11 12 10 11 12 10 11 12 10 11 12 10
5 6 4 5 6 4 5 6 4 5 6 4
8 9 7 8 9 7 8 9 7 8 9 7
'' - YY - ' - Y 2 3 1 2 3 1 2 3 1 2 3 1
L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3 L1
12 PART-WINDING WYE-DELTA
START RUN START RUN
' - PWS 12 10 11 12 10 11 12 10 11 12 10 11
Part-winding start 7 8 9 7 8 9 6 4 5 6 4 5
6 4 5 6 4 5 7 8 9 7 8 9
1 2 3 1 2 3 1 2 3 1 2 3
L1 L2 L3 L1 L2 L3 L1 L2 L3 L1 L2 L3
4 5 6 4 5 6
YY - Y 1 2 3 1 2 3
Variable Torque L1 L2 L3 L1 L2 L3
ENGLISH
LOW SPEED HIGH SPEED
4 5 6 4 5 6
' - YY 1 2 3 1 2 3
6
Constant Torque L1 L2 L3 L1 L2 L3
LOW SPEED HIGH SPEED
Double Speed
Dahlander 4 5 6 4 5 6
YY - ' 1 2 3 1 2 3
Constant Output L1 L2 L3 L1 L2 L3
LOW SPEED HIGH SPEED
7 8 9 7 8 9 7 8 9
1 2 3 1 2 3 1 2 3
4 5 6 4 5 6 4 5 6
9 ' - Y - YY
L1 L2 L3 L1 L2 L3 L1 L2 L3
ONLY FOR
LOW SPEED HIGH SPEED STARTING
1 2 3 6 4 5
Double Speed
6 -
Double Winding L1 L2 L3 L1 L2 L3
LOW SPEED HIGH SPEED
Connect the motor properly to the power supply by means of safe and permanent contacts.
The grounding connectors are provided inside the terminal box and on the motor frame. Upon request,
grounding terminals may be also provided on the motor feet. According to IEC 60079-0, the grounding cable
must have a cross-section area of at least 4 mm².
When connectors are used, all wires of the stranded cable must be properly inserted and fixed inside
the connector.
If motors are supplied without terminal blocks, insulate the cable terminals with suitable insulation material that
meets the power supply voltage and the insulation class indicated on the motor nameplate. The connection
must be made outside the hazardous area or protected by a standardized type of protection.
Ensure correct tightening torque for the power cable and grounding connections as specified in Table 8-8.
The clearance distance (see Figure 6.13) between non-insulated live parts with each other and between
grounded parts must be as indicated in Table 6.3.
Clearance distance
Clearance distance
ENGLISH
Even when the motor is off, dangerous voltages may be present inside the terminal box used for the
space heater supply or winding energization when the winding is used as heating element.
Motor capacitors will hold a charge even after the power has been cut off. Do not touch the capacitors
and/or motor terminals, before discharging the capacitors completely.
After the motor connection has been completed, ensure that no tool or foreign body has been left inside
the terminal box.
The thread types and sizes for cable inlet are specified in Table 6.4 and Table 6.5.
Tabela 6.4 - Thread dimensions for inlet power cables.
ENGLISH
560 6800
630 7000
8000
8800
9600
Note: explosion-proof motors are supplied with Metric or NPT threads only.
Note: explosion-proof motors are supplied with Metric or NPT threads only.
Unused cable entry holes in the terminal box must be properly closed to ensure the type of protection,
the degree of protection and the Equipment Protection Level (EPL) indicated on the motor nameplate.
Cable entry holes used by the user for the motor and accessory connection must be fitted with
components (such as, cable glands and conduits) that meet the applicable standards and regulations in each
country. For “Ex d” motors, conduit entries are permitted only for electrical equipment of group II.
All terminal box holes must be properly closed/protected to ensure the degree of protection, the Equipment
Protection Level (EPL) and the type of protection of the enclosure indicated on the motor nameplate.
If the motor is fitted with accessories, such as brakes and forced cooling systems, these devices must
be connected to the power supply according to the information provided on their nameplates and with
special care as indicated above.
All protection devices, including overcurrent protection, must be set according to the rated machine conditions.
These protection devices must protect the machine against short circuit, phase fault or locked rotor condition.
The motor protection devices intended for use in hazardous areas must be set according to the applicable
standards.
Delta connected motors must be protected against phase fault. To do that, connect the overload relay in series
to the winding phases and set it to 0.58 times the rated current.
Check the direction of rotation of the motor shaft. If there is no limitation for the use of unidirectional fans, the
shaft rotation direction can be changed by reversing any two of the phase connections. For single-phase motor,
check the connection diagram indicated on the motor nameplate.
All thermal protections (RTDs, bimetal thermal protectors and thermistors for stator protection) used in the
motor protection circuit must be connected as a simple equipment in and intrinsically safe circuit.
Motors driven by frequency inverters must have their winding thermal protections connected.
For other starting methods, the use of the thermal protections is optional.
Do not apply test voltage above 2.5 V on thermistors and current above 1 mA on RTDs (Pt-100)
ENGLISH
Figure 6.14 and Figure 6.15 show the connection diagram of the bimetal thermal protector (thermostats) and
thermistors, respectively.
In applications with protection by increased safety “Ex e”, the protection device, in case of overload or locked
rotor, must trip with time delay based on the current along with monitoring the three external leads. The time-
“tE” indicated on the motor nameplate should not be exceeded.
If motors with protection by increased safety “Ex e” are submitted to acceleration time > 1.7x time-“tE”, they
must be protected by protection devices against overcurrent.
94 Manual of Electric Motors
www.weg.net
Notes:
1) The number and type of the installed protection devices are stated on the accessory nameplate of the motor.
2) If the motor is supplied with calibrated resistance, (for example, Pt-100), the motor monitoring system must be set according to the
operating temperatures indicated in Table 6.6
The non-isolated part of the accessory cables should not exceed 1 mm up to the connector as shown in Figure
6.16.
ENGLISH
ºC Ω ºC Ω ºC Ω ºC Ω ºC Ω
-29 88.617 17 106.627 63 124.390 109 141.908 155 159.180
-28 89.011 18 107.016 64 124.774 110 142.286 156 159.553
-27 89.405 19 107.404 65 125.157 111 142.664 157 159.926
-26 89.799 20 107.793 66 125.540 112 143.042 158 160.298
-25 90.193 21 108.181 67 125.923 113 143.420 159 160.671
-24 90.587 22 108.570 68 126.306 114 143.797 160 161.043
-23 90.980 23 108.958 69 126.689 115 144.175 161 161.415
-22 91.374 24 109.346 70 127.072 116 144.552 162 161.787
-21 91.767 25 109.734 71 127.454 117 144.930 163 162.159
-20 92.160 26 110.122 72 127.837 118 145.307 164 162.531
-19 92.553 27 110.509 73 128.219 119 145.684 165 162.903
-18 92.946 28 110.897 74 128.602 120 146.061 166 163.274
-17 93.339 29 111.284 75 128.984 121 146.438 167 163.646
ENGLISH
ENGLISH
Figura 6.18 - Dual voltage space heater connection.
The space heaters should never be energized when the motor is in operation.
Table 6.9 shows examples of possible indirect starting methods to be used according to the voltage indicated
on the motor nameplate and the power supply voltage.
Table 6.9 – Starting methods x voltage
Starting by
Operating Autotransformer Part Winding Starting by
Nameplate voltage Star-delta series/parallel
voltage Starting Starting soft-starter
switch
220 V YES YES NO NO YES
220/380 V
380 V NO YES NO NO YES
220 V NO YES YES YES YES
220/440 V
440 V NO YES NO NO YES
230 V NO YES YES YES YES
230/460 V
460 V NO YES NO NO YES
380/660 V 380 V YES YES NO NO YES
220 V YES YES YES YES YES
ENGLISH
The W22 Quattro line motors must be started direct on-line (DOL) or driven by a frequency inverter in
scalar mode.
The starting by frequency inverter may be another starting method to avoid overloading the power supply line.
For more information about the motor control by frequency inverter, see item 6.14.
The operation with frequency inverter must be stated in the Purchase Order since this drive type may
require some changes of the motor design.
Motors driven by frequency inverters must have their winding thermal protections connected.
The frequency inverter used to drive motors up to 690 V must be fitted with Pulse With Modulation (PWM) with
vector control.
Motors driven by frequency inverters have an additional nameplate fixed on the motor frame indicating the
Service Factor, inverter type, frame size, and/or load type (constant or variable torque) as function of the speed
range and motor torque.
When a motor is driven by a frequency inverter at lower frequencies than the rated frequency, you must reduce
the motor torque to prevent motor overheating. The torque reduction (derating torque) can be found in the item
6.4 of the “Technical Guidelines for Induction Motors driven by PWM Frequency inverters” available on the site
www.weg.net.
J That the motor can supply max. 95% of its rated output;
The “Ex n” motor line driven by frequency inverter (used in Zone 2 – presence of gas) can be operated up to the
limit of the Temperature Class T3 (200 °C).
The “Ex t” motor line driven by frequency inverter (used in Zone 22 and Zone 21 - in the presence of
combustible dust) can be operated up to the temperature limit of 125 °C.
Information on the selection of the power cables between the frequency inverter and the motor can be found in
the item 6.8 of the “Technical Guidelines for Induction Motors driven by PWM Frequency inverters” available at
www.weg.net.
ENGLISH
≥ 0,1 μs ≥ 6 μs
575 < Vnom ≤ 690 V 4 ≤ 1600 V ≤ 5200 V/μs
575 < Vnom ≤ 690 V 5 ≤ 2200 V ≤ 7800 V/μs
Notes:
1. For the application of motors with round enameled wires designed for 690 < Vnom ≤ 1100 V, please contact WEG.
2. For the application of dual voltage motors, example 380/660 V, consider the lower voltage (380 V).
3. Information supplied by the inverter manufacturer.
4. When not stated in the Purchase Order that the motor will be driven by frequency inverter.
5. When stated in the Purchase Order that the motor will be driven by frequency inverter.
Table 6.11 – Recommendation on the bearing insulation for inverter driven motors
Frame size Recommendation
IEC 315 and 355
NEMA L447/9, 504/5, 5006/7/8, 5009/10/11, 586/7, 5807/8/9, One bearing is isolated
5810/11/12 and 588/9
IEC 400 and higher
NDE-bearing is isolated
NEMA 680 and higher
The shaft grounding system for explosion-proof motors can be used only inside the enclosure. For other
types of protection the shaft grounding system is not allowed.
The non-compliance with the criteria and recommendations indicated in this manual may void the
product warranty.
The use of sparking components, such as grounding brushes, is not allowed in explosive atmospheres.
Note:
To select the maximum allowed motor speed, consider the motor torque derating curve.
For more information on the application of frequency inverters, contact WEG or check the “Technical Guidelines
for Induction Motors driven by PWM Frequency inverters” available at www.weg.net.
7. COMMISSIONING
7.1. INITIAL START-UP
After finishing the installation procedures and before starting the motor for the first time or after a long period
without operation, the following items must be checked:
J If the nameplate data (voltage, current, connection diagram, degree of protection, type of protection, cooling
J If the motor driving system ensures that the motor speed does not exceed the max. allowed speed indicated
in Table 6.12.
J Measure the winding insulation resistance, making sure it complies with the specified values in item 5.4.
J Inspect the motor terminal box for damage and ensure that it is clean and dry and all contacts are rust-free,
the seals are in perfect operating conditions and all unused threaded holes are properly closed thus ensuring
the degree of protection and the type of protection of the motor indicated on the motor nameplate.
J Check if the motor wiring connections, including grounding and auxiliary equipment connection, have been
carried out properly and are in accordance with the recommendations in item 6.9.
J Check the operating conditions of the installed auxiliary devices (brake, encoder, thermal protection device,
running, it is recommended to change the bearings, or to remove, wash, inspect and relubricate them before
the motor is started. If the motor is stored and/or installed according to the recommendations described in
item 5.3, lubricate the bearings as described in item 8.2. For the bearing condition evaluation, it is
recommended to use of the vibration analysis techniques: Envelope Analysis or Demodulation Analysis.
J When motors are fitted with sleeve bearings, ensure:
J correct oil level for the sleeve bearing. The oil level should be in the center of the sight glass (see Figure 6.8);
J that the motor is not started or operated with axial or radial loads;
ENGLISH
J that if the motor is stored for a period equal or longer than the oil change interval, the oil must be changed
never commissioned, it is recommended to change the start capacitors since they lose their operating
characteristics.
J Ensure that the air inlet and outlet opening are not blocked. The minimum clearance to the nearest wall (L)
should be at least ¼ of the fan cover diameter (D), see Figure 7.1. The intake air temperature must be at
ambient temperature.
Please consider the minimum distances shown in the Table 7.1 as reference value
Table 7.1 – Minimum distance between the fan cover and wall
Frame size Distance between the fan cover and the wall (L)
IEC NEMA mm inches
63 - 25 0.96
71 - 26 1.02
80 - 30 1.18
90 143/5 33 1.30
100 - 36 1.43
112 182/4 41 1.61
132 213/5 50 1.98
160 254/6 65 2.56
180 284/6 68 2.66
200 324/6 78 3.08
225 364/5
85 3.35
250 404/5
444/5
280 445/7 108 4.23
447/9
L447/9
504/5
315 122 4.80
5006/7/8
5009/10/11
586/7
588/9
355 136 5.35
5807/8/9
5810/11/12
6806/7/8
400
6809/10/11
147 5.79
450 7006/10 159 6.26
ENGLISH
J ensure correct water flow rate and water temperature when water cooled motors are used. See item 7.2.
J ensure that all rotating parts, such as pulleys, couplings, external fans, shaft, etc. are protected against
accidental contact.
Other tests and inspections not included in the manual may be required, depending on the specific installation,
application and/or motor characteristics.
After all previous inspections have been carried out, proceed as follows to start the motor:
J Start the motor on no-load (if possible) and check the motor direction of rotation. Check for the presence of
the assembly system and connections before the motor is started again.
J If excessive vibrations are noticed, check if the motor mounting bolts are well tightened or if the vibrations are
not generated and transmitted from adjacent installed equipment. Check the motor vibration periodically and
ensure that the vibration limits are as specified in item 7.2.1.
J Start the motor at rated load during a short time and compare the operating current with the rated current
As induction motors have high inrush currents during start-up, the acceleration of high inertia load requires an
extended starting time to reach full speed resulting in fast motor temperature rise. Successive starts within
short intervals will result in winding temperature increases and can lead to physical insulation damage reducing
the useful life of the insulation system. If the duty S1 is specified on the motor nameplate, this means that the
motor has been designed for:
J two successive starts: first start from cold condition, i. e., the motor windings are at room temperature and
The Troubleshooting Chart in section 10 provides a basic list of unusual cases that may occur during motor
operation with the respective corrective actions
For operating temperatures and altitudes differing from those above, the factors indicated in Table 7.2 must be
applied to the nominal motor power rating in order to determine the derated available output (Pmax = Pnom x
correction factor).
Table 7.2 - Correction factors for altitude and ambient temperature.
Altitude (m)
T (°C)
1000 1500 2000 2500 3000 3500 4000 4500 5000
10 0.97 0.92 0.88
15 0.98 0.94 0.90 0.86
20 1.00 0.95 0.91 0.87 0.83
25 1.00 0.95 0.93 0.89 0.85 0.81
30 1.00 0.96 0.92 0.90 0.86 0.82 0.78
35 1.00 0.95 0.93 0.90 0.88 0.84 0.80 0.75
40 1.00 0.97 0.94 0.90 0.86 0.82 0.80 0.76 0.71
45 0.95 0.92 0.90 0.88 0.85 0.81 0.78 0.74 0.69
50 0.92 0.90 0.87 0.85 0.82 0.80 0.77 0.72 0.67
55 0.88 0.85 0.83 0.81 0.78 0.76 0.73 0.70 0.65
60 0.83 0.82 0.80 0.77 0.75 0.73 0.70 0.67 0.62
65 0.79 0.76 0.74 0.72 0.70 0.68 0.66 0.62 0.58
70 0.74 0.71 0.69 0.67 0.66 0.64 0.62 0.58 0.53
75 0.70 0.68 0.66 0.64 0.62 0.60 0.58 0.53 0.49
80 0.65 0.64 0.62 0.60 0.58 0.56 0.55 0.48 0.44
Motors installed inside enclosures (cubicles) must be ensured an air renewal rate in the order of one cubic
meter per second for each 100 kW installed power or fraction of installed power. Totally Enclosed Air Over
ENGLISH
motors - TEAO (fan and exhaust / smoke extraction) are supplied without cooling fan and the manufacturer of
the driven machine is responsible for sufficient motor cooling. If no minimum required air speed between motor
fins is indicated on the motor nameplate, ensure the air speed indicated in the table 7.3 is provided. The values
shown in Table 7.3 are valid for 60 Hz motors. To obtain the minimum air speed for 50 Hz motors, multiply the
values in the table by 0.83.
Table 7.3 – Minimum required air speed between motor fins (metres/second).
Frame Poles
IEC NEMA 2 4 6 8
63 to 90 143/5 13 7 5 4
100 to 132 182/4 to 213/5 18 12 8 6
160 to 200 254/6 to 324/6 20 15 10 7
225 to 280 364/5 to 444/5 22 20 15 12
315 to 450 445/7 to 7008/9 25 25 20 15
The voltage and frequency variations may affect the performance characteristics and the electromagnetic
compatibility of the motor. The power supply variations should not exceed the values specified in the applicable
standards. Examples:
J ABNT NBR 17094 - Parts 1 and 2. The motor has been designed to supply the rated torque for a combined
J Zone B: ±10% of the rated voltage and +3% -5% of the rated frequency.
When operated continuously in Zone A or B, the motor may show performance variations and the operating
temperature may increase considerably. These performance variations will be higher in Zone B. Thus it is not
recommended to operate the motor in Zone B during extended periods.
J IEC 60034-1. The motor has been designed to supply the rated torque for combined variation in voltage and
frequency:
J Zone A: ±5% of the rated voltage and ±2% of the rated frequency.
J Zone B: ±10% of the rated voltage and +3% -5% of the rated frequency.
When operated continuously in Zone A or B, the motor may show performance variations and the operating
temperature may increase considerably. These performance variations will be higher in Zone B. Thus it is not
recommended to operate the motor in Zone B during extended periods. For multivoltage motors (example 380-
415/660 V), a ±5% voltage variation from the rated voltage is allowed.
Manual of Electric Motors 103
www.weg.net
J NEMA MG 1 Part 12. The motor has been designed to be operated in one of the following variations:
J ±10% of the rated voltage, with rated frequency;
J A combined variation in voltage and frequency of ±10%, provided the frequency variation does not exceed ±5%.
“Ex e“ motors are designed to be operated only in Zone A – voltage and frequency variation.
If the motor is cooled by ambient air, clean the air inlet and outlet openings and cooling fins at regular intervals to
ensure a free airflow over the frame surface. The hot air should never be returned to the motor. The cooling air must
be at room temperature limited to the temperature range indicated on the motor nameplate (if no room temperature
is specified, please consider a temperature range between -20 °C and +40 °C).
Table 7.4 shows the minimum required water flow for water cooled motors considering the different frame sizes and
the maximum allowed temperature rise of the cooling water after circulating through the motor. The inlet water
temperature should not exceed 40 °C.
Table 7.4 – Minimum required water flow and the maximum allowed
temperature rise of the cooling water after circulating through the motor
Frame size Flow rate Maximum allowed water
IEC NEMA (litres/minute) temperature rise (°C)
180 284/6 12 5
200 324/6 12 5
225 364/5 12 5
250 404/5 12 5
444/5
280 445/7 15 6
447/9
315 504/5 16 6
586/7
355 25 6
588/9
Motors fitted with oil mist lubrication systems can be operated continuously for a maximum of one hour after
ENGLISH
Considering the sun’s heat increases the operating temperature, externally mounted motors should always be
protected from direct sunlight exposure.
Each and every deviation from the normal operating condition (tripping of the thermal protection, noise and
vibration level increase, temperature and current rise) should be investigated and corrected by WEG Authorized
Service Centers for explosive atmospheres.
Motors fitted with cylindrical roller bearings require a minimum radial load to ensure a normal operation.
For information regarding the radial preload, please contact WEG.
7.2.1.Limits of vibration
The vibration severity is the maximum vibration value measured at all positions and in all directions as
recommended in the standard IEC 60034-14. Table 7.5 specifies the limits of the maximum vibrations
magnitudes according to standard IEC 60034-14 for shaft heights IEC 56 to 400, for vibrations grades A and B.
The vibration severity limits in Table 7.5 are given as RMS values (Root Mean Square values or effective values)
of the vibration speed in mm/s measured in free suspension condition.
Table 7.5 - Limits of maximum vibration magnitude according to standard IEC 60034-14
Shaft height [mm] 56 < H < 132 132 < H < 280 H > 280
Vibration Grade Vibration severity on elastic base [mm/s RMS]
A 1.6 2.2 2.8
B 0.7 1.1 1.8
Notes:
1 – The values in Table 7.5 are valid for measurements carried out with decoupled machines (without load) operated at rated voltage and
frequency.
2 - The values in Table 7.5 are valid regardless of the direction of rotation of the machine.
3 – The values in Table 7.5 are not applicable to single-phase motors, three-phase motors powered by a single-phase system or to
machines mounted in situ or coupled with inertia flywheels or to loads.
According to NEMA MG 1, the allowed vibration limit for standard motors is 0.15 in/s (peak vibration in in/s).
Note:
For the load operation condition, the use of the standard ISO 10816-3 is recommended for evaluating the motor vibration limits. In the
load condition the motor vibration will be influenced by several factors, such as, type of the coupled load, condition of the motor fixation,
alignment condition under load, structure or base vibration due to other equipments, etc.
8. MAINTENANCE
The purpose of the maintenance is to extend the useful life of the equipment. The non-compliance with one of
these previous items can cause unexpected machine failures.
If motors with cylindrical roller or angular contact bearings are to be transported during the maintenance
procedures, the shaft locking device must always be fitted. All HGF motors, regardless of the bearing type,
must always be transported with the shaft locking device fitted.
All repairs, disassembly and assembly related services must be carried out only by qualified and well-trained
personnel by using proper tools and techniques. Make sure that the machine has stopped and it is
disconnected from the power supply, including the accessory devices (space heater, brake, etc.), before any
servicing is undertaken.
The company does not assume any responsibility or liability for repair services or maintenance operations to
motor for use in hazardous areas executed by non-authorized Service Centers or by non qualified service
personnel. The company shall have no obligation or liability whatsoever to the buyer for any indirect, special,
consequential or incidental loss or damage caused or arising from the company’s proven negligence.
Repairs to motor for use in hazardous areas must be executed in accordance with the applicable standards.
ENGLISH
Clean the motor enclosure. Remove oil spills and dust accumulation from the motor frame surface to
ensure a better heat transfer to the surrounding ambient. Motors with potential risk for electrostatic charge
accumulation, duly identified, must be cleaned carefully by using a damp cloth to prevent electrostatic
discharge during maintenance interventions.
J Check cooling fan condition and clean the air inlet & outlet openings to ensure a free air flow over the motor.
J Investigate the actual condition of the seals and replace them, if required.
J Drain the condensed water from inside the motor. After draining, reinstall the drain plugs to ensure the degree
of protection as indicated on the motor nameplate. The motor must always be positioned so the drain hole is
at the lowest position (see item 6).
J Check the connections of the power supply cables, ensuring the correct clearance distance between live and
grounded parts, as specified in Table 6-2.
J Check if the tightening torque of the bolted connections and mounting bolts meets the tightening torque
specified in Table 8 8.
J Check the status of the cable passages, the cable gland seals and the seals inside the terminal box and
replace them, if required.
J Check the bearing operating conditions. Check for the presence of any abnormal noise, vibration or other
abnormal operating conditions, like motor temperature rise. Check the oil level, the lube oil condition and
compare the workings hours with the informed life time.
J For explosion-proof motors check if the gap between the components is according to the Table 8-7. The
tolerance class of the metric threads for the cable inlet must be 6H or better.
J Record and file all changes performed on the motor.
Do not reuse damaged or worn parts. Damaged or worn parts must be replaced by parts supplied by
the manufacturer and must be installed as if they were the original parts.
8.2. LUBRICATION
Proper lubrication plays a vital role in the motor performance. Only use the grease or oil types, amounts and
lubrication intervals recommended for the bearings. This information is available on the motor nameplate and
the lubrication procedures must be carried out according to the type of lubricant (oil or grease).
When the motor is fitted with thermal protection devices for bearing temperature control, consider the operating
temperature limits shown in Table 6.3.
The maximum operating temperature of motors used in special applications may differ from those shown in
Table 6.3. The grease and oil disposal should be made in compliance with applicable laws in each country
Manual of Electric Motors 105
www.weg.net
Please contact WEG when motors are to be installed in special environments or used for special
applications.
The lubrication intervals specified in Table 8.1, Table 8.2, Table 8.3 and Table 8.4 consider an absolute
temperature on the bearing of 70 °C (up to frame size IEC 200 / NEMA 324/6) and 85 °C (for frame size IEC 225
/ NEMA 364/5 and above) the motor running at rated speed, a motor mounted in horizontal position, greased
with Mobil Polyrex EM grease. Any variation of the parameters listed above must be evaluated.
Table 8.1 - Lubrication intervals for deep groove ball bearings.
Lubrication intervals (hours)
W21 TEFC W22 TEFC
Frame Bearing Amount of
Poles (Totally Enclosed Fan (Totally Enclosed Fan
designation grease (g)
Cooled) Cooled)
IEC NEMA 50 Hz 60 Hz 50 Hz 60 Hz
2
4
90 143/5 6205 4 20000 20000 25000 25000
6
8
2
4
100 - 6206 5 20000 20000 25000 25000
6
8
2
4 6207/
112 182/4 9 20000 20000 25000 25000
6 6307
ENGLISH
8
2 20000 18400 25000 23200
4
132 213/5 6308 11
6 20000 20000 25000 25000
8
2 18100 15700 22000 20000
4
160 254/6 6309 13
6 20000 20000 25000 25000
8
2 13700 11500 17000 14000
4
180 284/6 6311 18
6 20000 20000 25000 25000
8
2 11900 9800 15000 12000
4
200 324/6 6312 21
6 20000 20000 25000 25000
8
2 4500 3600 5000 4000
4 11600 9700 14000 12000
6314 27
6 16400 14200 20000 17000
364/5 8 19700 17300 24000 20000
404/5 *Upon *Upon
2 3500 4000
444/5 request request
225 445/7 4 6316 34 10400 8500 13000 10000
250 447/9 6 14900 12800 18000 16000
280 L447/9 8 18700 15900 20000 20000
315 504/5 *Upon *Upon
2 2400 3000
355 5008 request request
5010/11 4 6319 45 9000 7000 11000 8000
586/7 6 13000 11000 16000 13000
588/9 8 17400 14000 20000 17000
4 7200 5100 9000 6000
6 6322 60 10800 9200 13000 11000
8 15100 11800 19000 14000
ENGLISH
Table 8.3 – Lubrication intervals for deep groove ball bearings – HGF line.
Frame Bearing Amount of Lubrication intervals (hours)
Poles
IEC NEMA designation grease (g) 50 Hz 60 Hz
2 6314 27 3100 2100
315L/A/B and 5006/7/8T and
6320 50 4500 4500
315C/D/E 5009/10/11T 4–8
6316 34 4500 4500
2 6314 27 3100 2100
355L/A/B and 5807/8/9T and
6322 60 4500 4500
355C/D/E 5810/11/12T 4–8
6319 45 4500 4500
2 6315 30 2700 1800
400L/A/B and 6806/7/8T and
6324 72 4500 4500
400 C/D/E 6809/10/11T 4–8
6319 45 4500 4500
2 6220 31 2500 1400
6328 93 4500 3300
4
450 7006/10 6322 60 4500 4500
6328 93 4500 4500
6–8
6322 60 4500 4500
6330 104 4200 2800
4
6324 72 4500 4500
500 8006/10
6330 104 4500 4500
6–8
6324 72 4500 4500
6330 104 4200 2800
4
6324 72 4500 4500
500 8006/10
6330 104 4500 4500
6–8
6324 72 4500 4500
560 8806/10 4-8
*Upon request
630 9606/10 4-8
Table 8.4 - Lubrication intervals for cylindrical roller bearings – HGF line
Frame Bearing Amount of Lubrication intervals (hours)
Poles
IEC NEMA designation grease (g) 50 Hz 60 Hz
315L/A/B and 5006/7/8 and 4 4300 2900
NU320 50
315C/D/E 5009/10/11 6-8 4500 4500
355L/A/B and 5807/8/9 and 4 3500 2200
NU322 60
355C/D/E 5810/11/12 6-8 4500 4500
400L/A/B and 6806/7/8 and 4 2900 1800
NU324 72
400C/D/E 6809/10/11 6-8 4500 4500
4 2000 1400
450 7006/10 6 NU328 93 4500 3200
8 4500 4500
4 1700 1000
500 8006/10 6 NU330 104 4100 2900
8 4500 4500
4 75 2600 1600
560 8806/10 NU228 + 6228
6-8 106 4500 4500
4 92 1800 1000
630 9606/10 6 NU232 + 6232 120 4300 3100
8 140 4500 4500
For each increment of 15 ºC above the room temperature, the relubrication intervals given in the Table must be
halved. The relubrication interval of motors designed by the manufacturer for mounting in horizontal position,
but installed in vertical position (with WEG authorization), must be halved.
For special applications, such as: high and low temperatures, aggressive environments, driven by frequency
inverter (VFD – frequency inverter), etc., please contact WEG about the required amount of grease and the
relubrication intervals.
Motors without grease fittings must be lubricated in accordance with the existing Maintenance Plan. Motor
disassembly must be carried out as specified in Item 8.3. If motors are fitted with shielded bearings (for
example, ZZ, DDU, 2RS, VV), these bearings must be replaced at the end of the grease service life.
8.2.1.2. Motor with grease fitting
To lubricate the bearings with the motor stopped, proceed as follows:
Motors with grease fittings must be stopped to be lubricated. Proceed as follows:
J Before lubricating, clean the grease nipple and immediate vicinity thoroughly;
J Pump in approximately half of the total grease indicated on the motor nameplate and run the motor for about
J Lower again the grease inlet protection and reinstall the grease outlet protection.
If Motors are provided with a spring device for grease removal, the grease excess must be removed by pulling
the rod and cleaning the spring until the spring does not remove more grease.
8.2.1.3. Compatibility of the Mobil Polyrex EM grease with other greases
The Mobil Polyrex EM grease has a polyurea thickener and a mineral oil thus being compatible with greases
that contain:
J Lithium based thickener, lithium-based complex thickener, polyurea thickener and refined mineral oil;
J The used grease must have in its formulation corrosion and oxidation inhibitors.
In general terms, greases with the same type of soap are compatible to each other. However, depending on the
proportion of the mixture there may be incompatibility. In such a case, it is not recommended to mix different
types of greases without contacting the supplier or WEG beforehand.
108 Manual of Electric Motors
www.weg.net
J fill-up with the type and amount of oil as specified on the nameplate;
J check oil level. The oil level is OK when the lubricant can be viewed approximately in the center of the sight
glass;
J reinstall oil inlet plug;
J check for oil leaks and ensure that all not used threaded plugs are closed with plugs.
The bearing lubricating oil must be replaced as specified on the nameplate or whenever changes in the oil
properties are noticed. The oil viscosity and pH must be checked periodically. The oil level must be checked
every day and must be kept in the center of the sight glass.
Please contact WEG, when oils with different viscosities should be used.
Note:
The HGF vertical mounted motors with high axial thrust are supplied with grease lubricated DE-bearings and with oil lubricated NDE-
bearings. The DE-bearings must be lubricated according to recommendations in item 8.2.1. Table 8.5 specifies the oil type and the
amount of oil required for this motor lubrication.
Table 8.5 – Oil properties for HGF vertical mounted motors with high axial thrust
ENGLISH
4-8 29320 26 mineral oil
355C/D/E 5810/11/12T Renolin
with antifoam
400L/A/B e 6806/7/8T e 8000 DTA 40 /
4-8 29320 37 and
400C/D/E 6809/10/11T SHC 629
antioxidant
additives
450 7006/10 4-8 29320 45
J Drain the oil through the drain hole located at the bottom of the bearing (see Figure 8.1);
J Fill the sleeve bearing with the specified oil and with the amount of oil specified in;
J Check the oil level and ensure it is kept close to the center of the sight glass;
Oil outlet
The lubricating oil must be replaced as specified on the nameplate or whenever changes on the oil properties
are noticed. The oil viscosity and pH must be checked periodically. The oil level must be checked every day
and kept in the center of the sight glass.
Please contact WEG, when oils with different viscosities are to be used.
All repair services on motors for use in hazardous areas should be always performed by qualified
personnel and in accordance with the applicable laws and regulations in each country. Always use
proper tools and devices for motor disassembly and assembly.
ENGLISH
Disassembly and assembly services can be carried out only after the motor has been disconnected
from the power supply and is completely stopped.
Dangerous voltages may be present at the motor terminals inside the terminal box since capacitors can
retain electrical charge for long periods of time even when they are not connected directly to a power source or
when space heaters are connected to the motor or when the motor windings are used as space heaters.
Dangerous voltages may be present at the motor terminals when they are driven by frequency inverter even
when they are completely stopped.
For explosion-proof motors and protection by enclosure motors, open the terminal box and/or
disassemble the motor only after the enclosure surface temperature has cooled down up to ambient
temperature.
Record the installation conditions such as terminal connection diagram, alignment / leveling conditions before
starting the disassembly procedures. These records should be considered for later assembly.
Disassemble the motor carefully without causing scratches on machined surfaces or damaging the threads.
Assemble the motor on a flat surface ensuring a good support base. Footless motors must be fixed/locked on
the base to prevent accidents.
Handle the motor carefully to not damage the insulated components such as windings, insulated rolling
bearings, power cables etc.
Seal elements, such as joint seals and bearing seals should always be replaced when wear or damage is
noticed.
Motors with degree of protection higher than IP55, the machined joints are protected at factory by a suitable
rust inhibitor. Thus all machined surfaces (for example, covers of the terminal boxes of explosion-proof motors)
must be carefully cleaned before assembly and provided again by a thin coat of rust inhibitor as shown in
Figure 8.2.
For explosion-proof motors, the joints can be coated only with the following products:
J
Lumomoly PT/4 (Lumobras);
J
Molykote DC 33 (Dow Corning).
For other types of protection, apply Loctite 5923 (Henkel) on the joints.
For explosion-proof motors special care should be taken with the machined surfaces of the flame path. These
surfaces must be free of burrs, scratches, etc. that reduce the flame path length and increase the gap.
The gaps between terminal boxes and the respective terminal box covers should not exceed the values
specified in Table 8.7.
Table 8.7 - Maximum gap between terminal box and terminal box cover for explosion-proof enclosures.
Flat joint Cylindrical joint
Frame size
W21 W22X W22X
IEC 71 to 355
0.05 mm 0.076 mm 0.158 mm
NEMA 143 to 586/7
ENGLISH
8.3.1. Terminal box
Proceed as follows to remove the terminal box cover and to disconnect/connect the power supply cables and
the cables of the accessory devices:
J Ensure that during the screw removal the terminal box cover does not damage the components installed
J If motors are supplied with terminal blocks, ensure the correct tightening torque on the motor terminals as
J Ensure that the original IP degree of protection is not changed and is maintained as indicate on the motor
nameplate. The power supply cables and the control cables must always be fitted with components (cable
glands, conduits) that meet the applicable standards and regulations of each country.
J Ensure that the pressure relief device is in perfect operating condition, if provided. The seals in the terminal
box must be in perfect condition for reuse and must be reinstalled correctly to ensure the specified degree of
protection.
J Ensure the correct tightening torque for the securing bolts of the terminal box cover as specified in Table 8.8.
To prevent electrical shock, discharge the motor terminals immediately before, and after each
measurement. If the motor is equipped with capacitors, these must be discharged before beginning any
repair.
Figure 8.3 - Exploded view of the components of a motor with type of protection “n”.
9. ENVIRONMENTAL INFORMATION
9.1. PACKAGING
WEG electric motors are supplied in cardboard, plastic or wooden packaging. These materials can be recycled
and must be disposed according to the applicable laws and regulations in each country. All wood used in the
packaging of WEG motors come from the company reforestation program and is not submitted to any chemical
conservation treatment.
9.2. PRODUCT
Electric motors consist mainly of ferrous metals (steel plates and cast iron), non ferrous metals (copper and
aluminum) and plastic materials.
In general, electric motors have relatively long service live. However when they must be discarded, WEG
recommends to dismantle the motor, sort the different materials and send them for recycling.
No-recyclable materials should be disposed of at industrial landfills according to the applicable environmental
laws and regulations in each country, or co-processed in cement kilns or incinerated.
The recycling service providers, the disposal in industrial landfills, the waste co-processing or the incineration
process must be properly authorized by the state environment agency to carry out these activities.
ENGLISH
Three-phase
IEC frames 63 to 630
Nema frames 42, 48, 56 and 143 to 9610
……………
Single-phase
IEC frames 63 to 132
Nema frames 42, 48, 56 and 143 to 215
……………
when installed, maintained and used in applications for which they were designed, and in compliance with the relevant
installation standards and manufacturer’s instructions, comply with the requirements of the following European Directives
and standards where applicable:
Directives:
Low Voltage Directive 2006/95/EC*
ENGLISH
Standards:
EN 60034-1:2010/ EN 60034-2-1:2007/EN 60034-5:2001/A1:2007/ EN 60034-6:1993/ EN 60034-7:1993/A1:2001/
EN 60034-8:2007/ EN 60034-9:2005/A1:2007/ EN 60034-11:2004/ EN 60034-12:2002/A1:2007/
EN 60034-14:2004/A1:2007/ EN 60034-30:2009, EN 60204-1:2006/AC:2010 and EN 60204-11:2000/AC:2010
Declaration of Incorporation:
The products above cannot be put into service until the machinery into which they have been incorporated has been
declared in conformity with the Machinery Directive.
A Technical Documentation for the products above is compiled in accordance with part B of annex VII of Machinery
Directive 2006/42/EC.
We undertake to transmit, in response to a reasoned request by the national authorities, relevant information on the partly
completed machinery identified above through WEG authorised representative established in the European Community.
The method of transmission shall be electronic or physical method and shall be without prejudice to the intellectual
property rights of the manufacturer.
These instructions are intended for the assembly, operating and supervising
personnel and should be kept at hand on site.
H75VA4-051-S7P0-DE001(2)A2
Table of contents
1 KEYWORDS..................................................................................................................................................... 4
3 TRANSPORT / STORAGE............................................................................................................................... 7
5 DESCRIPTION ............................................................................................................................................... 12
8 INSTALLATION .............................................................................................................................................. 18
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 3 / 28
9 OPERATION .................................................................................................................................................. 23
10 SERVICING.................................................................................................................................................... 24
10.5 Removal.................................................................................................................................................. 26
10.6 Required details for enquiries and orders of spare seals / parts ............................................................ 27
11 TROUBLESHOOTING ................................................................................................................................... 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 4 / 28
1 KEYWORDS
Please pay special attention to the following keywords:
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 5 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 6 / 28
Seal failure
WARNING
Hot medium to be sealed and/or supply medium may escape.
ü Preventive measures to protect persons and environment
a) Providing for splash protection and collecting device
b) Wearing of personal protective equipment
c) Care has to be taken by the user for disposal of the leakage, and he has to
control this measure
The user has to check what effects a failure of the mechanical seal might have
and what safety measures have to be taken to prevent personal injury or damage
to the environment.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 7 / 28
3 TRANSPORT / STORAGE
3.1 Transport
If not specified differently by contract the EagleBurgmann standard packaging is
used which is suitable for dry transport by truck, train or plane.
In addition seaworthy packaging may become necessary.
The following points have to be considered:
▪ graphical symbols for use on equipment
▪ weight specifications
▪ handling instructions
Notes for income inspection:
▪ Check packaging for visible damage.
▪ Open packaging carefully. Do not damage or lose parts supplied separately.
▪ Check if consignment is complete (delivery note). Inform the supplier imme-
diately in writing if parts are damaged or missing.
The seal has to be protected from damage during transport and storage. The
transport case in which the seal is supplied is well suited for this purpose.
Please keep it for a possible return transport.
If the machine as well as the seal installed into the machine are transported to-
gether, the shaft must be protected from deflection at all times, shocks and axial
displacement by means of a suitable machine support. Damage at the mechan-
ical seal resp. magnetic coupling caused by insufficient protection during trans-
port is excluded from the warranty.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 8 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 9 / 28
Due to longer erecting times of newly designed plant the period between delivery
of the mechanical seal and its installation and start-up in the machine may exceed
a period of 2-3 years.
After 3 years at the latest and in good time before the planned start-up of the
plant the seal has to be dismantled sent to the manufacturer or the nearest Eagle-
Burgmann service centre where it can be checked and reconditioned, if neces-
sary.
EagleBurgmann do not accept any warranty for damage caused by improper stor-
age.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 10 / 28
4.3 Materials
The materials of the mechanical seal depend on the application and are bound
to the customer order. They can be found on the drawing, and/or in the parts
lists attached to the documentation.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 11 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 12 / 28
5 DESCRIPTION
The horizontally arranged single M.S. has an integrated pumping device. At any
rate, the direction of rotation has to be taken from the drawing.
Together with the housing parts supplied the mechanical seal forms a premoun-
ted unit (seal cartridge), assembled at works, ready to be installed without any
adjustment.
Assembly fixtures are provided for holding the cartridge in one piece during
transport, storage, assembly and removal.
The seal face, preloaded by multiple springs, rotates with the shaft.
The seat is arranged stationary in the respective housing part.
A throttle ring at outboard prevents gushes of leakage.
The permitted axial displacement between shaft and housing is 1.5 mm in each
direction.
Torque transmission to the shaft by means of set screws with cup point.
Static pressure test before shipment.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 13 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 14 / 28
7 SUPPLY OF M.S.
If on the valid M.S. drawing differential pressures are stated, these must be ob-
NOTICE served at any rate.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 15 / 28
Sealing agents for threads (PTFE-tape, etc.) endanger the safe function of the
mechanical seal if they enter the seal chamber. When screwed connections are
opened take care by all means that sealing agents cannot enter the mechanical
seal.
Use DIN ISO 228 connecting threads only with encased gaskets or with self-seal-
ing pipe unions. Sealing agents for threads (e.g. PTFE-tape etc.) are not permit-
ted, because they may endanger the safe function of the seal if they enter the
sealing chamber.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 16 / 28
Quench medium to be selected by the user in accordance with the following cri-
NOTICE teria:
a) product compatibility
b) environmental compatibility
c) compatible with the used materials
d) no tendency to build deposits
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 17 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 18 / 28
8 INSTALLATION
Secondary sealing elements made of EP-rubber must never come into contact
NOTICE with mineral oil-based lubricants (swelling, possibly decomposition).
For applications free from silicone:
Lubricants must be free of silicones, fluorinated compounds which are able to mi-
grate, and tensides.
A wrong selection is not covered by EagleBurgmann's warranty.
For cleaning:
▪ ethyl alcohol
▪ cellulose-tissue (no rag, no cloth!)
For applications free from silicone:
▪ cotton-tissue (no rag, no cloth!)
▪ clean cotton gloves
For lubricating:
▪ suitable lubricants
▪ Lubricants must be compatible with all media (e.g. medium to be sealed, sup-
ply, flushing and/or cooling medium etc.), with those they get into contact with,
and they must not corrode the secondary sealing elements.
▪ Suitable synthetic lubricant for dynamic elastomeric secondary sealing ele-
ments, e.g. type "TURMOPOL GREASE SH 2 D" Fa. Lubricant Consult (LUB-
CON).
▪ Geeignetes Gleit-/Schmiermittel (FDA-Konform) z. B. Typ
"TURMSILON LMI 5000" make Lubricant Consult (LUBCON).
▪ Chloride-free surfactants (e.g. sodium dodecyl sulphate (SDS)) or low-tension
water for elastomeric bellows seals and static elastomeric secondary sealing
elements of seats
For installation:
▪ set of hexagon keys
▪ torque wrench
Additional for single seals:
▪ o-ring lifter
▪ cardboard discs to cover the sliding faces during installation
▪ hand screw press (compulsory for shaft diameter ≥80 mm)
▪ press-in tool (as usual for radial rotary shaft seals)
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 19 / 28
For sealing:
®
▪ sealing agents for threads for pipe connections, e.g. type "LOCTITE Nr. 266"
make: LOCTITE Corporation
For securing:
®
▪ for bolts, set screws etc. use liquid screw retention, e.g. type "LOCTITE
Nr. 243" make: LOCTITE Corporation
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 20 / 28
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 21 / 28
For the assembly of o-rings made of solid PTFE considerable assembly forces
are required to compress them. Yet, these forces may result in permanent de-
formations of seal components, in particular of the assembly fixtures. To com-
press o-rings made of PTFE little force over an extended period of time has to be
applied (force x time = constant). If necessary, the fastening screws have to be
retightened several times.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 22 / 28
Set screws with cup point must be used only once. Repeated fastening en-
NOTICE dangers the safety of force transmission.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 23 / 28
9 OPERATION
9.2 Start-up
Safety checks before start-up
▪ Seal assembly fixtures removed.
▪ Pipe connections tightened and pressure-sealed.
▪ Disposal connections installed environmentally safe.
▪ Direction of rotation has to comply with the drawing by all means, otherwise
contact EagleBurgmann!
▪ The machine must be earthed.
▪ Fill and vent the machine by all means in accordance with the instructions of
the machine manufacturer.
Now the seal is ready for operation.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 24 / 28
10 SERVICING
10.1 Maintenance
A correctly operated mechanical seal needs low maintenance. Wear parts, how-
ever, have to be replaced, if necessary.
A duly operation includes the regular check of the following parameters:
▪ Temperature
▪ Leakage (drainage) of the mechanical seal
An inspection of the mechanical seal should be carried out along with a revision
of the complete plant. We recommend having this inspection performed by
EagleBurgmann.
If the mechanical seal is removed during a revision of the plant the sliding parts
must be checked and the sliding faces be refinished or, if necessary, the sliding
parts must be replaced and all secondary sealing elements and springs must be
replaced.
The check should be carried out by EagleBurgmann personnel or qualified staff.
www.eagleburgmann.com.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 25 / 28
10.4 Reconditioning
If reconditioning is necessary, the complete seal should be sent to the manufac-
turer, as this is the best way to find out which components can be reconditioned
or which parts must be replaced in order to ensure an optimum tightness.
If, for compelling reasons, a reconditioning has to be carried out on site (e.g. no.
spare seal on stock, long transport, problems with customs) the seal may be re-
paired in a clean room by trained personnel of the user under the direction of
EagleBurgmann mechanics.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 26 / 28
10.5 Removal
a) Stop the machine as instructed, allow to cool, depressurise it and ensure that
WARNING pressure cannot build up again!
b) Work on the M.S. is only permitted when the machine is at a standstill and de-
pressurised.
c) Depressurise and shut off (or drain) the supply of the M.S.
d) There must be no product in the M.S. -> if necessary drain the machine and
rinse it out!
e) Isolate the machine to prevent it starting up unexpectedly!
f) Observe the safety notes (safety data sheets)!
If the medium to be sealed builds deposits or tends to solidify during cooling down
or standstill of the machine the stuffing box has to be flushed with suitable clean
liquid. The flow rate and the liquid should be determined by the user considering
the chemical resistance of the seal materials.
When removing, please observe by all means:
▪ current accident prevention regulations
▪ regulations for handling hazardous substances
Seals that have been used with hazardous substances must be properly cleaned
so that there is no possible danger to people or to the environment.
The packaging used to transport the seal must
▪ be identified with the relevant hazard symbol and
▪ include the safety data sheet for the product and/or supply medium.
The order of disassembly to remove the mechanical seal out of the machine de-
pends on the design of the machine and should be determined by the machine
manufacturer.
If the machine manufacturer specified auxiliaries (jigs and fixtures) they have to
be used in accordance with the specifications of the manufacturer.
▪ Remove the supply piping to the mechanical seal. Collect drained liquid and
dispose of properly.
▪ Drain the mechanical seal. Collect the drained liquid and dispose of properly.
▪ Install the assembly fixtures resp. assembly rings.
▪ Unscrew the set screws with cup point and dispose of.
Set screws with cup point must be used only once. Repeated fastening en-
NOTICE dangers the safety of force transmission.
▪ Loosen all screw connections between seal and the respective machine parts.
▪ Remove the mechanical seal in the reverse sequence as described for as-
sembly (set up).
– For an easier removal the mechanical seal is equipped with forcing
threads or any other disassembly devices (if available).
– In case of using sealing elements made of pure graphite (Statotherm)
and / or PTFE, these have to be used only once.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 27 / 28
Address of headquarters:
EagleBurgmann Germany GmbH & Co. KG
Postfach 1240
D - 82502 Wolfratshausen Germany
☎ +49 (0) 81 71-23 0
Fax +49 (0) 81 71-23 12 14
www.eagleburgmann.com
10.8 Copyright
EagleBurgmann Germany GmbH & Co. KG (Germany) holds the copyright to
this document. Customers and operators of mechanical seals are free to use
this document in the preparation of their own documentation. No claims of any
type or form can be derived in such instance.
Rev. 0 01/04/2016
Operating Manual / en
H75VA4-051-S7P0-DE001(2)A2 Page 28 / 28
11 TROUBLESHOOTING
Abnormal temperature distri- Open the valves and protect them against
bution at the circulation line. operating error.
Shut down the pump, if necessary, and
check the cooling water line for clogging.
Check the orifice for clogging.
Check the strainer for clogging.
In case of vertical pumps, eliminate gas ac-
cumulations in the seal chamber by thor-
oughly venting.
Clean the strainer.
Check the cyclone separator for clogging.
Remove obstacles (e.g. orifices) from the
lines.
Observe the specification of the cyclone
separator (solids content etc.).
Abnormal temperature in- Check the cooling water lines for clogging
crease in the cooling water. and clean the lines.
Rev. 0 01/04/2016
Metastream™ TSKS coupling I-TSKS ENG 0310
(PN 78257)
Fitting, & Maintenance Instructions. Page 1 of 10
1
2B
2 2A
6 8 7 5
3
A A
Foreword
These instructions are provided to familiarise the user with the coupling and its designated use. These
instructions must be read and applied whenever work is carried out on the coupling and must be kept
available for future reference.
ATTENTION These instructions are for the fitting, operation and maintenance of the coupling as used in
rotating equipment and will help to avoid danger and increase reliability. The information
required may change with other types of equipment or installation arrangements. These
instructions must be read in conjunction with the instruction manuals for both the driver and
driven machinery.
If the coupling is to be used for an application other than that originally intended or outside the
recommended performance limits, John Crane must be contacted before its installation and use.
Any warranty may be affected by improper handling, installation, or use of this coupling. Contact the
company for information as to exclusive product warranty and limitations of liability
If questions or problems arise, contact your local John Crane sales/service engineer or the original
equipment manufacturer as appropriate.
ATTENTION John Crane couplings are precision products and must be handled appropriately. Take
particular care to avoid damage to spigots, mating faces, hub bores, keyways and
membranes. Do not excessively compress the coupling membranes during assembly. Refer
to Table 1 for compression limits. (X)
These instructions are written for standard catalogue products, generally designed in accordance with the
drawing shown.
Safety Instructions
The following designations are used in the installation instructions to highlight instructions of particular
importance.
IMPORTANT is used for items of particular concern when using the coupling.
A factory assembled transmission unit, comprising 2-off guard rings (5), 1 –off spacer (6), 2-off membrane
packs (7) plus fasteners and fixings(8)
Driver hub
Driven hub
2 sets of bolts (3) to assemble the transmission unit to the two hub flanges
IMPORTANT If a general arrangement drawing is supplied with the coupling then all data indicated
on that drawing takes precedence over information included in these instructions.
Storage
If the coupling is not to be used immediately, it should be stored away from direct heat in its original
packing.
All documentation supplied with the coupling should be retained for future reference.
Spares
When requesting spares always quote the full designation of the coupling
Set of hub bolts (4) (please specify standard or/and large hubs)
Hubs, bored to your requirement or unbored (2, 3)
Complete transmission unit, balanced or unbalanced(l)
Membrane pack including drive bolts and guard ring assemblies (5, 7, 8)
INSTALLATION
Remove coupling from packaging and carefully inspect for signs of damage. Pay particular attention to the
hub bores and the spigot/recess location features, which should be free from burrs and other damage.
INSTALLATION OF HUBS
! Prior to installing the coupling, ensure that the machinery is made safe. Hubs must be
adequately supported during installation to avoid accidental damage should they slip.
Fit and secure the axial ram or hydraulic nut BEFORE injecting oil between the
components.
5. Inject oil between the components until the required mounting pressure is reached, or it leaks out at the
ends of the mating surfaces.
6. By means of the mounting tools, position the hub in the correct axial position, injecting oil during this
operation.
Unbored Hubs
John Crane recommend a light interference fit for keyed
hubs and shafts [e.g. a K7/m6 fit]. The finished bore size
can be calculated from the measured shaft diameter.
FIGURE 3
When setting up the hub to machine the bore use the
hub location recess and face as datum surfaces, as RECESS
shown in Figure 3. TIR
The hub location recess should be set so the maximum run-out does not exceed 0.00008mm per mm of
recess diameter or 0.012 mm TIR, whichever is greater.
Adapters
For machines having an integral flanged shaft, the flange may be machined to suit the bolting configuration
of the coupling transmission unit. Alternatively, the coupling may be supplied with a customised flange
adapter. Refer to the specific general arrangement drawing for location and mounting details.
IMPORTANT DBSE should be measured between the inner face of the hubs and should not be
taken as the length of the transmission unit at its outer periphery. DBSE may not be equal to
the precise distance between shaft ends. In particularly, the faces of taper bored hubs may
not be flush with the shaft end. Refer to Figure 4.
4. Align the shaft centre lines both horizontally and vertically by aligning the hub flanges. JOHN CRANE
recommends the reverse periphery method for accurate alignment. This can be done using dial gauges
or with the John Crane "Lase-A-Lign" shaft alignment kit. Further details are available from John Crane
on request.
5. Recheck the DBSE after the shafts have been aligned.
6. Axial shims (together with a shim carrier in some cases) may be supplied on applications where it is
difficult to accurately set a predetermined shaft end separation [DBSE]. This is often the case where
one or both of the hubs are taper bored. Where this feature is supplied, the thickness of shims [plus
carrier if applicable] are added to the free length of the transmission unit so that the combined length is
equal to the measured distance between the hub flange faces, making any allowance for known shaft
movements. Note - it is best to measure the transmission unit when it is in a gagged condition.
IMPORTANT The misalignment tolerances quoted in literature and on drawings, allow for
dynamic conditions and variations. For the best service from the coupling, John Crane
recommend that installed misalignment is no more than 10% of the maximum allowable
misalignment, allowance being made for any anticipated movements which will occur
during operation (eg. Thermal movements on hot pumps).
3. Align the hub/transmission unit flanges if they have been match marked
4. Fit the hub bolts and tighten these evenly to locate the transmission unit, ensuring the spigots enter
their recesses squarely. Bolt-threads should be lubricated with oil and tightened in a "diametrically
opposite" sequence to the torque values shown in Table 1.
5. Measure dimension 'A (see Figure 1) on the transmission unit. Check against the minimum and
maximum value in Table 1.
6. Rotate the machinery two or three times slowly to ensure it moves freely.
TABLE 1
Coupling Hub bolt Hub bolt Min gap Coupling Dim’n Dim’n
Size Size Tightening X Max Axial 'A' (Min) 'A' (Max)
Torque mm Deflection mm mm
Nm +/- mm
0013 M6 13 7.1 1.0 7.7 7.8
0033 M8 25 7.2 1.25 8.2 8.4
0075 M8 25 7.6 1.5 8.8 9.0
0135 M8 25 8.1 2.0 9.6 9.9
0230 M10 50 8.3 2.5 10.2 10.4
0350 M8 25 11.6 2.75 13.6 13.9
0500 M10 50 11.8 3.25 14.4 14.7
0740 M10 50 12.3 3.75 15.2 15.5
0930 M12 86 12.5 4.25 15.9 16.2
1400 M12 86 13.4 5.0 17.4 17.8
Maximum angular misalignment = 0.5 degrees up to 3600rpm; 0.33 degrees up
to 7500rpm; 0.25 degrees above 7500rpm.
Routine examination should include a periodic check on the tightness of fasteners and visual inspection of
transmission components for signs of fatigue or wear.
If the coupled machinery is disturbed at any time, shaft alignment should be re checked. Alignment
checking is recommended if a deterioration of installation alignment during service is suspected.
Maintenance work must only be carried out by suitably qualified personnel when the
equipment is stationary and has been made safe.
Failures are rare and can generally be attributed to excessive misalignment or / and severe torsional
overload. In all cases of coupling failure, the cause should be identified and corrected before replacing the
coupling.
It is possible to repair the coupling by fitting replacement Membrane unit assemblies or replacing the entire
transmission unit.
To replace the transmission unit, remove the hub bolts and then withdraw the transmission unit using the
compression bolts feature in the spacer as appropriate.
Transmission unit must be adequately supported during removal to avoid accidental damage
should it slip.
ATTENTION When repairing John Crane MetastreamTM flexible membrane couplings, only John
Crane approved parts should be used.
NOTE: For balanced TSK spacer couplings, the transmission unit is usually supplied as a factory
assembled unit which should not be dismantled. However, when used at low or medium speeds, the
transmission unit can be reconditioned but will require rebalancing.
Membrane assemblies should be replaced in pairs, failure of one will usually result in damage to the other.
To replace the transmission unit, first remove the hub bolts (3) then
withdraw the transmission unit, using the lever slots in the hubs or
jacking holes in the spacer flanges. 8B 8S 8N
Identify the fasteners on the new membrane assembly which attach Spacer
to the spacer flanges. Remove the loosely assembled nuts (8N).
With the bolts (8B) in position, carefully press on the bolt heads to
push the new sleeves (8S) into the holes in the spacer flange. Take
care not to over-strain the flexible discs.
Place a small amount of threadlocking compound (e.g. Loctite 242)
on the protruding bolt threads and then assemble the nuts (8N).
Holding the bolts firmly, turn the spacer nuts evenly to the correct
tightening torque value given in Table 2.
This section refers to couplings which bear the CE and ATEX* required markings:
CE / ATEX marking
All couplings which comply with CE and ATEX legislation will be marked as shown. This will
be etched on the spacer element of the transmission unit.
- The hub electrical insulation. (if supplied option) - reinforced thermosetting plastic.
- Limited end float bearings. (if supplied option) – PTFE based plastic.
- Composite spacer tube. (if supplied option) – reinforced thermosetting plastic.
Metastream T series and L series couplings, using the disk type flexible elements, are
covered by type certificate Sira 02ATEX9403
Metastream M series couplings, using the diaphragm type flexible elements, are covered by
type certificate Sira 02ATEX9404
Where Metastream metal membrane couplings from John Crane are required for use in
higher ambient temperatures, John Crane Ltd certifies that the equipment complies with the
temperature classification range listed in table 1 and in all other respects complies with the
type certificates.
Table 1.
Max T Max. Surface
ambient Class temperature
o o
C # C
150 T3 200
90 T4 135
55 T5 100
40 T6 85
John Crane
31, Nash Road
Trafford Park
Manchester
M17 1SS
United Kingdom
T: +44 (0) 161 872 2484
F: +44 (0) 161 872 1654
www.johncrane.com
Declaration of Conformity
The technical Documentation is deposited with the designated Notified body in accordance
with article 8 1. (b) (ii) the Directive 94/9/EC:
John Crane
31, Nash Road
Trafford Park
Manchester
M17 1SS
United Kingdom
T: +44 (0) 161 872 2484
F: +44 (0) 161 872 1654
www.johncrane.com
Declaration of Incorporation
M, H, T, L Series
The machinery parts, covered by this declaration must not be put into
service until the machinery into which it is to be incorporated has been
declared in conformity with the provisions of the Directive.
These instructions are intended for the assembly, operating and monitoring personnel.
This manual must be kept available on site.
Read this manual diligently and follow all instructions.
We definitely recommend you contact EagleBurgmann should anything be unclear.
The product named on the title page will be called system in the following.
The designation non-EagleBurgmann equipment refers to all non-EagleBurgmann com-
ponents, see equipment list and drawing
Use this documentation only in conjunction with the documents stated in "System Infor-
mation" in order to avoid mistakes.
EBG_12.01.2016
EagleBurgmann Germany GmbH & Co. KG
Äußere Sauerlacher Straße 6-10 | D-82515 Wolfratshausen | Tel.: +49 (0)8171 23 0 | Fax: +49 (0)8171 23 12 14
[email protected] | www.eagleburgmann.com
Manufacturer and address
EagleBurgmann Germany GmbH & Co. KG
Stammhaus - Fachbereich Versorgungssysteme
Äußere Sauerlacher Straße 6-10
D - 82515 Wolfratshausen
Tel.: +49 (0) 81 71 - 23 0
Fax: +49 (0) 81 71 - 23 19 29
Dealer
http://www.eagleburgmann.com/en
EagleBurgmann International
Country (distribution locations and Service Center)
Service-Center
http://www.eagleburgmann.com/en
EagleBurgmann International
Country (distribution locations and Service Center)
Creation
Date: 12.04.2016
Supply Systems Department: F. Rößle
Documentation & Standardization Department: T. Eberl
2
Table of Contents
1. Safety ....................................................................................... 5
1.1. General safety notes ................................................................ 5
1.1.1. Operator-specific safety instructions and hazard analysis
results................................................................................ 5
1.1.2. Product-specific safety instructions .................................... 6
1.1.3. Operating-specific safety instructions ................................ 6
1.2. Personal, material, environmental damage and notes .............. 8
1.3. Standards and directives .......................................................... 9
1.4. Warranty and liability ................................................................ 9
2. System information..................................................................10
2.1. Intended use ...........................................................................10
2.2. Operating data and limits on use .............................................10
2.3. Materials .................................................................................10
2.4. Notes on explosion protection .................................................10
2.5. Findings from the general risk assessment..............................11
2.6. Other applicable documents and drawings ..............................12
3. Transportation .........................................................................13
3.1. Packaging ...............................................................................13
3.2. Delivery ...................................................................................13
4. Storage ...................................................................................14
5. Description and function ..........................................................15
5.1. Description of system ..............................................................15
5.2. Emission .................................................................................15
6. Assembly, and disassembly ....................................................16
6.1. Space required ........................................................................16
6.2. Accessories .............................................................................16
6.3. Assembly.................................................................................17
6.4. Disassembly ............................................................................18
7. Start up and shut down............................................................20
7.1. Requirements ..........................................................................20
7.2. Start-up ...................................................................................20
7.3. Shutdown ................................................................................20
12.04.2016 3
8. Operation ................................................................................21
8.1. Notes for the operator .............................................................21
9. Servicing .................................................................................23
9.1. Cleaning ..................................................................................23
9.2. Maintenance............................................................................23
9.3. Repair .....................................................................................24
10. Faults ......................................................................................25
11. Disposal ..................................................................................26
12. Customer service ....................................................................27
12.1. Spare parts..............................................................................27
12.2. Accessories .............................................................................27
12.3. Queries and orders..................................................................27
13. Copyright .................................................................................28
12.04.2016 4
WEF6100A4A001-D5 Safety
1. Safety
1.1. General safety notes
1.1.1. Operator-specific safety instructions and hazard analysis results
EagleBurgmann systems are manufactured to a high quality and
have high operational reliability. However, the system is a poten-
tial source of risk if it is not operated correctly or is used
improperly.
The regulations applicable at the location as well as the accident
prevention requirements must be complied with at all times.
Unauthorized modifications and changes that adversely affect the
safety of the system are not permitted.
The operator holds the responsibility for accident-free operation.
Within the scope of his safety concept the operator is requested
to check what effects failure or damage to the system would have
on the environment, and which additional prevention measures
are necessary to protect people or the environment.
The operator must prevent the system from being misused or op-
erated improperly.
To avoid the risk of burns and personal injuries due to contact
with hot surfaces, the operator must affix appropriate insulation
and/or warning signs to the system.
Safety and warning signs may not be removed and must be kept
in a legible condition.
The maximum permissible operating pressure of the system and
other components in a closed supply circuit must not be exceed-
ed, regardless if caused by incorrect handling or through
procedures. Appropriate measures must be taken which comply
with the regulations applicable at the location.
Work on the system is principally only permitted on a depressur-
ized machine during standstill and with disconnected supply
voltage. Secure the device to prevent unauthorized reactivation.
For the sake of clarity, the operator is recommended to incorpo-
rate this document into his generally applicable company
regulations.
The operating instructions of the operator must be observed and
complied with.
The system can be lifted by the points shown in the drawing.
The operator must ensure that the system is installed in the pre-
disposed installation point of the plant.
12.04.2016 5
WEF6100A4A001-D5 Safety
12.04.2016 6
WEF6100A4A001-D5 Safety
12.04.2016 7
WEF6100A4A001-D5 Safety
Situation resulting in
death or severe injuries Type and source of danger
if not avoided.
Possible consequences
DANGER - Action
- Action
WARNING - Action
- Action
CAUTION - Action
- Action
12.04.2016 8
WEF6100A4A001-D5 Safety
12.04.2016 9
WEF6100A4A001-D5 System information
2. System information
2.1. Intended use
The system is intended solely for use in the specified application. Any
other or more extensive usage will be regarded as incorrect usage and
the manufacturer shall not be liable for any damage caused. Any usage
not conforming to the conditions stipulated under “Operating limits and
Limits on use” below will be regarded as incorrect usage. The risk asso-
ciated with such improper usage shall be borne solely by the operator.
Operation under other conditions or in another location must be agreed
with EagleBurgmann and documented.
System:
Process medium: Process Condensate
Tubeside: 250°C /
Maximum operating temperature:
Shellside: 150°C
Tubeside: 68,11 kg/cm^2(g) /
Maximum operating pressure:
Shellside: 16,32 kg/cm^2(g)
Additional information:
Shell (content / pressure) 2,6 l / ---
Tube (content / pressure) 2,2 l / ---
Cooling medium: Water
2.3. Materials
The materials used to construct the system are varied to suit the applica-
tion and are specific to the order. They can be referred to from the
drawing and the documentation.
12.04.2016 10
WEF6100A4A001-D5 System information
When handling this system the customer must take the following into
account:
12.04.2016 11
WEF6100A4A001-D5 System information
12.04.2016 12
WEF6100A4A001-D5 Transportation
3. Transportation
3.1. Packaging
Unless otherwise contractually agreed, the packaging used conforms to
the "HPE" packaging guidelines issued by the "Bundesverband Holzmit-
tel, Paletten, Exportverpackung e.V." and "VDMA".
3.2. Delivery
EagleBurgmann supplies the system and all components
(e.g. measuring devices, if available) fully assembled, purged, unpres-
surized and tested for leaks and function.
12.04.2016 13
WEF6100A4A001-D5 Storage
4. Storage
If the unit will be stored for a few weeks or even months, it must be kept
indoors in a dry place protected against dust and from the weather. Even
when stored indoors, the system should be covered with a tarpaulin to
protect against dust. Long-term storage of the system is not permissible.
The storage location must be suitable for the weight of the sys-
tem.
There must be sufficient space available for maintenance and/or
repairs.
The storage location must be free of vibrations and other im-
pacts.
All equipment components must be stored upright on a flat sur-
face.
Electrical equipment should also be prepared for storage in ac-
cordance with the manufacturer’s instructions where applicable.
The system must be protected against freezing.
Adequate ventilation should be provided.
The temperature must be kept constant:
Relative humidity: < 65 %
Temperature: +25 °C to +45 °C
Protection must be provided against direct heat sources (sun and
heaters) and UV radiation (sun, halogen and fluorescent lamps
and arc welding).
The presence or creation of ozone (arc welding, mercury vapor
lamps, high voltage devices and electric motors) must be pre-
vented to avoid the risk of elastomer embrittlement.
12.04.2016 14
WEF6100A4A001-D5 Description and function
5.2. Emission
A seal is a dynamic system which cannot be leak-free for physical and
technical reasons. The leakage rate is influenced, among other things,
by the seal design, the production tolerances, the operating conditions,
and the running quality of the machine.
If the buffer pressure drops below the pressure in
the sealing chamber, the medium to be sealed
can access the sealing gap and contaminate the
flushing and buffer medium.
12.04.2016 15
WEF6100A4A001-D5 Assembly, and disassembly
6.2. Accessories
The following tools and accessories must be prepared for the assembly
and disassembly:
Allen key
Open-end or ring wrench
Torque wrench
Loctite (LOCTITE Corporation) or SWAK (Swagelok Company)
for thread locking
Cellulose cloths for cleaning
12.04.2016 16
WEF6100A4A001-D5 Assembly, and disassembly
6.3. Assembly
12.04.2016 17
WEF6100A4A001-D5 Assembly, and disassembly
6.4. Disassembly
Depressurize the system and drain the medium. For that pur-
pose, install a connecting pipe at the "DRAIN" (if available) outlet
to the collection tank. As soon as the system is depressurized
and the line is connected to the container the drain ball valve (if
available) can be opened. Next, the ball valve of the "VENT" ven-
tilation (if available) can be opened cautiously until the medium
has drained completely.
12.04.2016 18
WEF6100A4A001-D5 Assembly, and disassembly
WARNING death.
- Ensure the ventilation of rooms.
- Regularly check the nitrogen concentration.
- Wear personal protective equipment.
12.04.2016 19
WEF6100A4A001-D5 Start up and shut down
7.1. Requirements
Do not start up until:
7.2. Start-up
The system is ready for operation after it has been properly assembled
and connected.
7.3. Shutdown
After shutting down the plant for reasons of maintenance or operation
the pressure must be relieved, using the devices or fittings provided.
12.04.2016 20
WEF6100A4A001-D5 Operation
8. Operation
12.04.2016 21
WEF6100A4A001-D5 Operation
12.04.2016 22
WEF6100A4A001-D5 Servicing
9. Servicing
9.1. Cleaning
The cleaning intervals depend on the degree of contamination. After
maintenance and cleaning, we recommend purging the system to clean
the pipelines. In our experience, a large part of the impurities will have
drained out of the pipelines by this time.
9.2. Maintenance
If operated properly, the system is maintenance free. Wearing parts must
be replaced as necessary.
12.04.2016 23
WEF6100A4A001-D5 Servicing
9.3. Repair
12.04.2016 24
WEF6100A4A001-D5 Faults
10. Faults
12.04.2016 25
WEF6100A4A001-D5 Disposal
11. Disposal
12.04.2016 26
WEF6100A4A001-D5 Customer service
12.2. Accessories
Accessories can be obtained from the EagleBurgmann dealers, the
EagleBurgmann Service Center, or the EagleBurgmann Head Office.
Manufacturer-Commission number
Drawing no.
Diagram number
Equipment list / data sheets
Individual part-Item number
Material
Number of parts as per drawing
12.04.2016 27
WEF6100A4A001-D5 Copyright
13. Copyright
EagleBurgmann Germany GmbH & Co. KG has the copyright in this
manual and reserves the right to make technical modifications to im-
prove the system, even if such modifications are not included in this
manual.
12.04.2016 28
IWS-Monjé Ltd.
Heat Exchangers
Tel.: +49 (0)2932 890 188 -0
Fax: +49 (0)2932 890 188 -5
[email protected]
www.iws-monje.com
Installations-
Betriebs- &
Wartungsanleitung
Inhaltsverzeichnis
2. Montage
3.1. Aufstellungsbedingungen
3.2. Anschließen des Druckgerätes
3.3. Ausrüstung des Druckgerätes mit Begrenzungseinrichtungen
3. Inbetriebnahme
4. Benutzung
5.1. Allgemeine Hinweise
5.2. Anfahrbetrieb
5.3 Normalbetrieb
5.4. Außerbetriebnahme
5.5 Unsachgemäße Verwendung
Alle Öffnungen wie Stutzen, Flansche usw. sind mit geeigneten Mitteln zu
verschließen und dürfen nur durch fachkundiges Personal entfernt werden
(Achtung: Dichtflächen nicht beschädigen!)
Für Schäden an dem Druckgerät, die durch unsachgemässen Transport
entstehen, übernimmt der Hersteller keine Haftung.
2. Montage
2.1 Aufstellungsbedingungen
Die Montage darf nur durch fachkundiges Personal gemäss der jeweils
gültigen nationalen Rechtsvorschriften erfolgen. Druckgeräte sind so
aufzustellen, dass Beschäftigte oder Dritte nicht gefährdet werden.
Erforderliche Schutzabstände sind entsprechend den anwendbaren
nationalen gesetzlichen Bestimmungen des Aufstellungslandes
einzuhalten.
-Regeleinrichtungen
Geeignete, von Hand bediente oder automatisch arbeitende Regel-
und Steuereinrichtungen für die Einhaltung der Betriebsparameter, wie
z.B. Mess-, Steuer- und Regeleinrichtungen (MSR), Druck-,
Temperatur-, Standschalter, um die Betriebsbedingungen, während
des bestimmungsgemäßen Betriebes innerhalb der zulässigen
Minimal-/Maximalgrenzwerte zu halten.
- Überwachungseinrichtungen
Angemessene Überwachungseinrichtungen zur Überwachung der
Betriebsparameter, wie z.B. Mess-, Steuer- und Regeleinrichtungen
(MSR), Messwertanzeigen, Alarmeinrichtungen, Druck-, Temperatur- und
Standschalter, die angemessenes manuelles oder automatisches
Eingreifen ermöglichen. Korrekturmaßnahmen auslösen und/oder
Abfahren und Verriegeln sorgen, um das Druckgerät innerhalb der
Betriebsgrenzwerte zu halten.
- Sicherheitseinrichtungen
Angemessene Sicherheitseinrichtungen wie Sicherheitsventile,
Berstscheibensicherungen, Knickstabeinrichtungen usw. oder
sicherheitsrelevante MSR-Einrichtungen, die als letzte
Gefahrenabwehrmaßnahme sicherstellen, dass die zulässigen
Betriebsgrenzwerte nicht überschritten werden.
3. Inbetriebnahme
Die Prüfung vor Inbetriebnahme erfolgt durch die zugelassene
Überwachungsstelle.
Die Prüfung vor Inbetriebnahme ist nur durch fachkundiges Personal des
Betreibers der Anlage zu veranlassen und in Deutschland in
Übereinstimmung mit § 14 der Betriebssicherheitsverordnung
durchzuführen. In anderen Aufstellungsländern sind die entsprechenden
nationalen Vorschriften für die Prüfung vor Inbetriebnahme zu beachten.
Eine Überschreitung des maximal zulässigen Drucks und/oder maximal
zulässiger Temperatur ist durch geeignete Maßnahmen zu verhindern.
Für die Einhaltung der technischen Daten gemäß Abnahmeprotokoll und
Typenschild muss der Betreiber sorgen. Der Betreiber hat die
Lastwechsel zu dokumentieren, maximal 1’000 Lastwechsel.
4. Benutzung
4.2 Anfahrbetrieb
Das Druckgerät ist so anzufahren, dass sich aus dem Temperaturanstieg
bzw. Druckanstieg keine unzulässigen Spannungserhöhungen ergeben.
Im Anfahrbetrieb ist das Druckgerät ständig zu beobachten und auf
mögliche Leckagen hin zu überprüfen.
4.3. Normalbetrieb
Druckgeräte dürfen nur betrieben werden, wenn die sicherheitstechnisch
erforderlichen Ausrüstungsteile auf Dauer wirksam sind und während des
Betriebes nicht außer Funktion gesetzt werden oder in ihrer
bestimmungsgemäßen Wirkung geändert werden.
4.4. Außerbetriebnahme
Das Druckgerät ist so abzufahren, dass sich aus dem Temperaturabfall
bzw. Druckabfall keine unzulässigen Spannungserhöhungen ergeben.
Bei längeren Betriebspausen und/oder bei Frostgefahr muss die Anlage
entleert werden. Um Stillstandschäden zu vermeiden ist gegebenenfalls
eine Konservierung (z.B. Stickstoffbefüllung) vorzunehmen.
Eine besondere Prüfung des Druckgerätes ist erforderlich, wenn bei der
Betriebsstörung der zulässige Druck um mehr als 10 % überschritten
wurde oder die zulässige Betriebstemperatur erheblich überschritten bzw.
unterschritten wurde oder das Druckgerät bzw. seine Ausrüstungsteile
beschädigt worden sind.
5.4 Instandsetzung
Alle schadhaften Verschlusselemente z.B. abgenutzte, rissige und
verbogene Schrauben, ausgebrochene oder sonst beschädigte Muttern,
verbogene Klammern oder Bügel, beschädigte Dichtungen dürfen nicht
mehr verwendet werden und sind durch gleichartige zu ersetzen.
Die Firma IWS-Monjé Ltd. Arnsberg haftet nicht für Fehler die aus einem bestimmungswidrigen
Gebrauch des Produktes resultieren.
Wir behalten uns jederzeit das Recht vor ohne Ankündigung diese Bedienungsanleitung neueren
Erkenntnissen anzupassen.
Installation-
Operation- &
Maintenance Instruction
Contents
2. Assembly
3.1. Conditions of installation
3.2. Connection of the pressure device
3.3. Equipment of the pressure unit with limitation units
4. Use
5.1. General indication
5.2. Starting operation
5.3 Regular operation
5.4. Putting out of operation
5.5 Inappropriate use
2. Assembly
2.1 Conditions of Installation
The installation may only be handled by instructed personnel according
to the valid national conditions of law. Pressure devices are to be
installed the way that employed persons or third persons will not be
endangered. Requested security distances are to be obeyed according to
the usable national conditions of law of the country of installation.
The pressure devices are to be installed resp. assembled that way that
they are accessible for necessary viewings and inspections and can be
viewed at all sides,
the factory sign is visible well
the operation of the pressure device and its equipment is possible
from a secure position.
- Regulating Equipments
Suitable, manually operated or automatically working regulating- and
steering devices for the keeping of the operating parameter like e.g.
measuring-, steering- and regulating equipments (MSR), pressure-,
temperature-, standing position switch in order to hold the operating
conditions during the standardized operation within the permitted
minimal/maximum limits.
- Observation Equipments
Appropriate observation equipment for the observation of operating
parameter like measuring-, steering- and regulating equipments (MSR),
measurement indicators, alarm equipments, pressure-, temperature-
and standing position switches which facilitate an adequate manual or
automatical intervention. Release correcting measures and/or taking
care of depart and bolting in order to hold the pressure device within the
operating limits.
- Security Equipments
Appropriate security equipments like safety valves, burst disc protections,
kink stick equipments etc. or security relevant MSR-equipments which at
least make sure the danger measure, so that the permitted operating
3. Start of Operation
The check before putting into operation is being carried out by the
permitted place of observation. The putting into operation may only take
place when the pressure device
4. Use
5.4 Repair
All defective locking elements e.g. worn out, cracked and bent screws,
broken out or otherwise damaged screw nuts, bent clips or handles,
damaged seals may not be used any more and have to be replaced by
homogeneous ones.
Repairs which can impair the security of the pressure device like
measures which change the material properties e.g. by welding, cold- and
hot-formings, may be accomplished only in agreement with the national
regulations of the country of installation.
The company IWS Monj’e Ltd. Arnsberg is not responsible for errors, caused by use against the rules
of the product results.
We keep ourselves the right to adapt this operating instructions to newer findings without
announcement at any time.