Ayala Triangle Gardens: Roughing Installation (Drop-Off Landscape Lightings)
Ayala Triangle Gardens: Roughing Installation (Drop-Off Landscape Lightings)
Method Statement
For
Roughing Installation
(Drop-off Landscape Lightings)
Document Review
1 SCOPE OF WORK.........................................................................................................................3
2 REFERENCE DOCUMENTS.......................................................................................................3
3 WORK PROCEDURE...................................................................................................................3
3.1 Roughing Ins
3.2 Chipping Works
3.3 Pedestal Installation
5 SAFETY PRECAUTIONS.............................................................................................................5
7 QUALITY ASSURANCE/CONTROL..........................................................................................5
8 RESPONSIBILITIES......................................................................................................................5
9 APPENDICES.................................................................................................................................6
2 REFERENCE DOCUMENTS
Issued for Construction (IFC)
For Construction Drawing (FCD)
Reflected Ceiling Plan (RCP)
Approved Submittals
Shop Drawings
Method Statement
Inspection and Testing Plan (ITP)
Product Data
Materials
3 WORK METHODOLOGY
3.1 Conduit Roughing Ins
c. No conduits shall be used in any system smaller than 15mm (1/2 inch)
in diameter and shall have no more than four 90-degrees bend in any
one run wherein if necessary to provide pull boxes as directed.
d. All exposed pipes, conduits, boxes and flexible metal conduits shall be
pre-painted with primer paint prior to installation.
k. Pull boxes and other outlets inter- connections boxes shall conform to
the minimum size or dimensions suitable to receive the corresponding
number of wires by sizes, shall be painted epoxy-gray finish, mounted
and fastened in accordance with the standard hangers and supports.
l. All Metallic boxes (junction, square and pull boxes shall be fix-in-place
to the conduits by means of equal size locknut and bushing for
embedded and exposed conduits.
m. All hangers and support for the IMC shall be installed with a minimum
distance of 1.2m. Ensure that the deflection does not exceed 5mm mid
span of support when fully loaded
n. Anchor bolt shall be installed in a concrete slab 3/8 inch diameter full
threaded rod shall be installed to each anchor bolt. Ensure that the
deflection does not exceed 5mm mid span of support when fully
loaded.
p. Install Ga. 16 GI pull wires to all installed empty pipes and conduits
d. Remove all loose materials and thoroughly clean the surface of the
concrete to the pipe.
Power tools
Hilti drill
Hilti chipping gun
Makita grinder
Makita electric drill
Makita jigsaw
Lotus jigsaw
Hand tools
Hammer
Crew drivers
Dinder
Blow Torch
Saw
5 SAFETY PRECAUTIONS
See Attached Risk Assessment by Safety
7 QUALITY ASSURANCE/CONTROL
I. Inspections
The execution of work will strictly follow the project quality procedure.
II. Test
Physical/Visual Test
8 RESPONSIBILITIES
Identify key staff involved in the management / control of the work process and briefly
describe their responsibilities.
8.1 ECC. QAQC/PIC – Routes the Work Request (WAP) part to different trades and
ensure to complete the signatures of the related trade. To Conducts progress work
inspection and testing at project site (Refer on approved Inspection Test Plan (ITP)
and Ensure to comply Quality Control requirements).
8.2 ECC SO – To ensure that workers are equipped with complete PPE’s and with safe
working environment. To orient workers with safety precautions.
8.6 MDCBP PIC – To ensure all quality control requirements are complied and
approved the submitted Work Request (WR).
8.7 MDCBP QA/QC – To ensure PATOQ completed prior to start of any activity. Ensure
compliance of the work activity with regards to approved submittals, process and
controls. Review and verify compliance of work with regards to quality requirements.
To approved Work Request only if the activity complies with Quality Assurance &
Control requirements.
9 APPENDICES
Appendix A – MSDS report for pipe cement (solvent)