Indent of Materials - Unit 2.
Indent of Materials - Unit 2.
Direct Cost
• Direct cost is a price that can be completely attributed to the
product of specific goods or work or service.
Indirect Cost
Indirect cost is made up of the following:
• Architect’s and Engineer’s professional charges including R.C.C.
specialist’s fees
• Supervisor’s salary
• Municipal tax of the land where work is going on during the
period of construction
Overhead costs
Overhead cost include general office expenses, rent, taxes and
supervision and other cost which are indirect expenses and not
productive expenses on job.
General overheads
• Establishment (office staff),
• Stationary, printing, postages etc.
• Travelling expenses
• Telephone
• Rate and taxes
Overhead costs
Job overheads
• Supervision (salary of engineers, overseers supervision)
• Handling of Materials
• Reprise
• Carriage and depreciation of T. and P.
• Amenities of labour
• Workmen compensations, insurance etc
• Interest on investment
• Losses on advance
Overhead costs
• The contractor may be allowed a net profit of 6-8%, and the
misc. overhead expenses may come to about 5-10%.
Unit rate
• “Unit rate” is a comparison of any two separate but related
measurements when the second of these measurements is
reduced to a value of one. Calculating the unit rate in any set of
circumstances will require the use of division.
• A unit rate is the cost per unit to build an asset or to perform
some action. Unit rates can be used to calculate the value of an
individual asset, to estimate the cost of planned works, or to
perform a complete valuation or revaluation of a network of
assets.
Unit rate
• The execution of the works can also be carried out by any
of the following arrangement depending upon nature of
work and other factors:
1. Day work
2. Piece work
3. Task work
Day work
• This method of execution of the work is adopted for all small
item of the work which cannot either to be measured or valued,
• The payment made to the contractor consist of net cost of
material and labour to complete the work and usually about 20
to25 present on the same which will cover the contractor’s
profit, establishment charges, and the rentals for plants, if any.
• It required the proper check on the material and the labour
employed.
• It is duty of architect and engineer to sanction those extra works
in written which cannot be measured valued properly to be paid
day work prices.
Day work
Day work
1. The work should not be the commenced till the necessary
sanction has been obtained from the architect.
2. Due notice of its commencement should be given to the
architect or the engineer.
3. Day work statement should be certified weekly by the architect
or the engineer. If the contractor is found irregular in the same, it is
likely that the architect or the engineer may not certify the
payment of the same later on.
• The day work method of execution should be avoided as far as
possible as it forms an expensive method. A close supervision is
necessary as the contractor will try to increase the cost, so as to
get more profit.
Piece work
• If the work is of an urgent nature and where day work is not
possible, it is divided into the parts and each part is given to the
contractor known as piece work.
• The items of the work and their rate are agreed upon prior to its
commencement. It cannot be called contract in the strict sense
as there is no time limit, no security deposit or no penalty.
• PWD and other Government agencies usually carry out the work
up to Rs.2000 by this system and when the work is likely to cost
more up to a limit of Rs.75000, special sanction is required for
the executive engineer to that effect.
Piece work
• The rate quote by the various contractor must be within the
limit of sanction rates.
• The measurements in this case of recorded in the measurement
book and are checked by the executive engineer to see that the
payment made tells with the work executed.
Task work
• The quantity of work that can be done by a labour in one day is
termed as the task work or the outturn of the labour. Here, a
day means working for 8 hours.
Indent of material
• A document that is prepared by the contactor/engineer ,
internally that authorize the purchasing of products and material
needed for the project
• These are documents that are used to track the movement of
materials and stock before it is brought on the site
• Different item are listed and the required materials are given in
the tabular format and filled as per quantity of material required
for each item
• All the quantities of different items for one particular material are
added with addition of 2% wastage to get the total requirement
of particular material for construction
THANKYOU
REFERANCE: Notes (SCOA/18-19/Compiled by Prof. Nalini Naiknimbalkar, Prof. T.B. Shinde and Er. Dakshayani Shete)