The document provides an estimate for proposed construction of an RCC building including excavation, filling, masonry work, RCC work, plastering, flooring, doors, windows and other items. It includes a detailed bill of quantities and costs for 24 line items and provides a total estimate of Rs. 939,000.

Uploaded by

Sangram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views4 pages

Estimating and Costing Project Plan

The document provides an estimate for proposed construction of an RCC building including excavation, filling, masonry work, RCC work, plastering, flooring, doors, windows and other items. It includes a detailed bill of quantities and costs for 24 line items and provides a total estimate of Rs. 939,000.

Uploaded by

Sangram
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Est.

No - 59
Date – 22/8/2020

Estimate of the Proposed R.C.C. Building


At Post - Kake Tal - Panhala Dist - Kolhapur
On C.S. NO.:-202 PLOT NO :-

GROUND FLOOR

sr.no qty. item. rate per amount


1 job. clearing the site of all rubbish the LUMP 1000 1000
structure etc, lining out structure
with chack dust and provinding
semiperment marks for checking
etc. complete

2 40.5 excavation in soil and murum to 157 cum. 6358


cum requared depth inciuding dewatenng
if necessary back filling after construction
disposing of the excess stuff within 100 ft.
lead as directed etc. complete.

3 56.5 filling the plinth with soil and murum from 85 cum 2041
cum excation laying in 150 mm layers, watering
raming etc.complete.

4 25.3 filling the plinth with murum, brougth from 584.35 cum 14784
cum outside laying in 150 mm layers watering
ramming etc.complete.

5 18.2 providing and constructing u.c,r, masonary 3176 cum 57,803.00


cum 0.45m thk, Including c,m1.6 and using
header at 1m, filling the joints with morter
curing etc. complete.

6 5.3 providing and casting c.c. 1.2.4 for R.C.C 4050 cum 21465
cum footings as per desing shuttering, ;placing
curing etc. complete

7 9.65 providing and casting c.c. 1.2.4 for R.C.C 4411 cum 42566
cum column as per desing shuttering, ;placing
curing etc. complete

8 12.5 providing and casting c.c. 1.2.4 for R.C.C 4411 cum 55137
cum beam as per desing shuttering, ;placing
curing etc. complete

9 7.52 providing and casting c.c.1.2.4 for R.C.C 3225 rnm 24,252.00
rnm lintel as per desing shuttering, ;placing
curing etc. complete

10 30.42 providing and casting C.C 1:2:4 for R.C.C 807 sqm 12629
sqm chajjah aevrage 75 mm thk Shuttering
placing, curing, etc, complete.

11 35.2 providing and casting C.C.1:2:4 for R.C.C 275 sqm 9680
spm parapets walls, fins, louvers 37.5mm to 50mm
Thk Shuttering, placing, curing, etc.complete

12 0.95 providing cutting bending, and binding 65000 mt 61750


mt M.Sreinforcement for all R.C.C work
etc,complete. (wastage and binding wire
will not paid for)

13 1.75 providing cutting, bending and binding high 70445 mt 123278


tensile renforcement (tor steel or gripsteel)
for all R.C.C work etc, complete.
(wastage and binding wire will not paid for)

14 25.35 providing and constructing 230 mm thk 4500 cum 114075


cum brick burnt masonary in C.M 1:8/1:6
for super structure scafolding, watering
curing, etc, complete.

15 52 providing and constructing 100mm thk 900 sqm 46,800.00


sqm burn brick partitions with R.C.C 100 mm
thk. Band at 3 feet level interval, scafolding
watering etc, complete.

16 322 providing and applying plastering with first 375 sqm 120750
sqm coat in C;M1:5/1:4 finished smooth with
neeru, scaffolding, watering etc,complete.

17 350 providing and applying one coat of primer 30 sqm 10500


sqm and two coat of dry distemper including
rubbing the surface with polish paper
scafolding etc.complete.

18 350 providing and applying three coat of cement 45 sqm 15750


sqm paint including watering preparing the
surface scafolding etc. complete

19 95.26 providing and fixing marble mosaic tile 185 sqm 17623
sqm floring of dark or grey shade and appeoved
make set on lime mortor 1:3 and cement
grout pointing curing polishing etc
complete

20 42.82 provinding and fixing marble mosaic tile 914 sqm 39137
sqm floring of light shade (on white cement
base) and approved make set on lime
mortor 1:3 and cement grout pointing
curing, polishing etc.complete

21 49.52 providing and fixing polished shahabad 332 sqm 16440


sqm treds and risers with rounded nosing set
on cement mortor & cement pointing
curing etc. complete.

22 18.47 providing and fixing 1st class quality 650 sqm 12005
sqm white/colored glazed tile for floring and
dado on neat cement with filling the joints
in white cement, pointing curing etc.
complete.

23 16.56 providing and fixing doors (with glased 1665 sqm 27572
sqm ventilators) teack frame 125 mm 60mm
and solid core block board 3705 mm
plywood shuters with teak wood facing on
one/both sides and commertial on other
with copper oxidised steel hinges nickel
plated / c.o.brass fixtures, applying three
coats of frentch polish on decorative face &
three coats of enamel paint on the other
face etc.complete.

24 19.52 provinding and fixing windows with teack 1465 sqm 28596
sqm wood frame 125 mm *60mm and teack
woodstilels 30 mm *80mm glased (4 mm
glass) with copper steel ;hinges nickel
plated / c.o. brass fixturee, applying three
coats of enamel paint with m.s. greel,
bars as per design etc. complete.

Total Rs. 881991


Electrification 2% 17638
Plumbing 2% 17638
Arch/.Engg.Consultancy Fees 2.5% 22047
Grand Total 939314
Say Rs. 939,000

* Amount in Words - NINE LAKHS THIRTY NINE THOUSAND RS


ONLY