Annex A Report of The Project EngineerCPAF NOV 16 2020

Uploaded by

Ariel Dela Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views1 page

Annex A Report of The Project EngineerCPAF NOV 16 2020

Uploaded by

Ariel Dela Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Report of the Project Engineer as of: November 16, 2020

Target Accomplishment 18%


Percent of Work Accomplished 13.7178%
Slippage 4.2822%
Contract Time 150 CD
Time Elapsed 26 Days

Manpower 9 - Workers
1 - Foreman
4 -Skilled
4 - Laborers

Previous Activities:

- Installation of temporary Facilities


- Safe demolition of proposed fire exit location
- Dismantling of existing cubicles, dry wall partition, ceiling, vinyl tiles, ceramic tiles
- Removal of lighting fixtures, ceiling fans, plumbing fixtures and ACU steel platforms
- Chipping of concrete floor
- Hauling of construction debris

On-going Activities:

- Tile works
- Electrical roughing-ins

Projected Activities:

- Installation of ACU
- Installation of dry wall partition

Submitted by:

Engr. Christian B. Canlas


Project Engineer