DETAILED ESTIMATE
GRANT : MGNREGS
CIRCLE : NELLORE
DIVISION :NELLORE
SUB DIVISION :NELLORE
MANDAL : T.P.GUDUR
SPECIFICATION REPORT
Specification Report to accompanying the Detailed Estimate prepared for the work
Construction of CC Side drains in T P GUDUR GP of T.P.GUDUR Mandal
It has been decided by the Government of Andhra pradesh to Utilize MGNREGS funds for
Liquid waste management works of Open CC Drains with convergence of CSR funds in the Ratio
of 70:30 (MGNREGS: CSR)
This Project is intended for proper disposal of household grey water and Rainfall discharge from
road surface and house areas for maintaining proper sanitation facilities around household
premisis of rural households. This estimate is prepared for providing open CC drains at Valluru
Grampanchayat in Muthukur Mandal.
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other
1 deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305
MORD / 304 MORTH, including (As per RSSR 2019-20) by manually
Supply and filling of sand in trenches, sides of foundations with intial lead in layers not
exceeding 10cm thick, comnsolidated each deposited layer by watering and ramming as per
2
drawing and technical specification Excluding GST and all operational charges etc complete
finished item of work
Vibrated Cement Concrete Nominal Mix (1:3:6) 40 mm down graded HBG Metal including cost
of all materials and labour charges etc,,complete -1 cum with Machine mixing for CC Bed
3
including conveyance, seigonarage of materials of sand &metal and excluding cost of steel and its
fabrication charges etc .
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm HBG graded metal
including cost of all materials and labour charges etc,,complete -1 cum with Machine mixing for
4
side walls of drains including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
Supply ,Cost of steel including fabrication charges including all operational and incidental
5
charges etc
Plastering with CM (1:5)mix, 12 mm including cost of all materials and labour charges
6 etc,,complete -for 10 Sqm but including conveyance and serignorage charges of materials of sand
etc Completed
Cutting of Open CC Road surface with Concrete saw Cutter and Removel with Breaker and
7
disposal @ 0.50 km away etc completed
Necessary Provisions for Q.C charges at 0.5% , Seignorage Charges, Name Board and Other
8 unforseen items are also provided in the estimate.
The Estimate is prepared as per the Revised Current Schedule of rates of 2019-2020 and RSSR
and the work will be carried out as per APDSS.
This Project is intended for proper disposal of household grey water and Rainfall discharge from
road surface and house areas for maintaining proper sanitation facilities around household
premisis of rural households. This estimate is prepared for CONSTRUCTION OF CC OPEN
DRAIN IN bit 1 KODUR GP OF TP Gudur MANDAL.
2 Cement Concrete Nominal Mix (1:3:6) 40 mm down graded HBG Metal with Machine mixing
for CC Bed to a width of 0.85M and to a thickness of 100mm
3 Vibrated Cement Concrete Nominal mix (1:2:4) using 20mm HBG graded metal with Machine
mixing for side walls of drains to a width of 150mm at top and 230mm at bottom and to a
height of 0.45M for both side walls (Clear vent 0.30M)
4 Fitting and placing HYSD bar reinforcement in slab over drain complete
5 VRCC M-20 Nominal mix using 20 mm to 12 mm Graded size crushed hard granite
metal - for Drain Cover Slab
6 Plastering with CM (1:5) 12 mm thick for vent portion
The Estimate is prepared as per the Revised Current Schedule of rates of 2020-21 and CSOR
and the work will be carried out as per APDSS.
Necessary L.S Provision are show for Q.C charges at 0.5% , GST at 12% on total amount
except on cost of cement and unskilled labour charges
Inamadugu Dharmaiah(H) to
1 X 1 5.00 0.85 0.32 1.36
Inamadugu Sarasamma (H)
Balla vijaykumar(H) to
1 X 1 20.00 0.85 0.52 8.84
Inamadugu pedda seenaiah(H)
Netrambaku Eswaraiah(H)to
1 X 1 124.00 0.85 0.60 63.24
opposite to Water Tank
Kaduru Paramdhamaiah(H)
to Netrambaku
Venkataramanaiah(H), 1 X 1 115.00 0.85 0.60 58.65
Pathan khalesha House
Krpalem
Inamadugu Dharmaiah(H) to
1 X 1 28.20 0.85 0.10 2.40
Inamadugu Sarasamma (H)
Vinayaka swamy temple to
1 X 1 31.10 0.85 0.10 2.64
kavali Ramu (H)
Balla vijaykumar(H) to
1 X 1 75.00 0.85 0.10 6.38
Inamadugu pedda seenaiah(H)
Main Viiage Water Tank to
1 X 1 116.50 0.85 0.10 9.90
School
SI. Meausurements Amount
Descritption of item Qty Rate Per
No
No L B D (Rs.)
Attipati Malli(H) to Tandra
1 X 1 70.00 0.85 0.10 5.95
Chinnamma(H)
Netrambaku Eswaraiah(H)to
1 X 1 79.50 1.50 0.15 17.89
opposite to Water Tank
Kaduru Paramdhamaiah(H)
to Netrambaku 1 X 1 75.00 0.85 0.10 6.38
Venkataramanaiah(H),
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm
HBG graded metal including cost of all materials and labour charges
4 etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
Inamadugu Dharmaiah(H) to
1 X 2 5.00 0.23 0.32 0.74
Inamadugu Sarasamma (H)
Balla vijaykumar(H) to
1 X 2 20.00 0.22 0.52 4.58
Inamadugu pedda seenaiah(H)
Kaduru Paramdhamaiah(H)
to Netrambaku 1 X 2 20.00 0.21 0.61 5.12
Venkataramanaiah(H),
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm
HBG graded metal including cost of all materials and labour charges
5 etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
Steel 110 Kgs per cum(approx) for Top Slabs 0.00 47.14 Kg 0.00
Cutting of Open CC Road surface with Concrete saw Cutter and Removel
8
with Breaker and disposal @ 0.50 km away etc completed
SI. Meausurements Amount
Descritption of item Qty Rate Per
No
No L B D (Rs.)
CC Drain Side Walls 1 X 0 0.00 0.30 0.15 0.00 2424.00 Cum 0.00
9 Supply and fixing of name board of size 2'x3' with brick masonary 1.00 2500.00 1No 2500.00
Sub-Total 1553253.00
6 Seigniorage charges 25087.00
7 Provision towards QC Charges at 0.5% 7766.00
8 work wise file 100.00
9 Provision for GST Excluding cement and unskilled labour 154748.00
10 Provision of unforcien items LS 259046.00
Total 2000000.00
Supply and filling of sand in trenches, sides of foundations with intial lead
in layers not exceeding 10cm thick, comnsolidated each deposited layer by
1
watering and ramming as per drawing and technical specification Excluding
GST and all operational charges etc complete finished item of work
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm
HBG graded metal including cost of all materials and labour charges
3 etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
CC Drain Side Walls 1 X 2 -156.00 0.19 0.38 -22.23 8971.40 cum -199434.00
CC Drain Side Walls 1 X 1 -156.00 0.00 0.30 -46.80 237.60 Sqm -11119.00
Cutting of Open CC Road surface with Concrete saw Cutter and Removel
5
with Breaker and disposal @ 0.50 km away etc completed
CC Drain Side Walls 1 X 1 -7.80 1.00 0.15 -1.17 2424.00 Cum -2836.00
6 Supply and fixing of name board of size 2'x3' with brick masonary 1.00 2500.00 1No 2500.00
Sub-Total -272847.00
7 Seigniorage charges 21853.00
8 Provision towards QC Charges at 0.5% -1364.00
9 work wise file 100.00
10 Provision for GST Excluding cement and unskilled labour -58362.00
11 Provision of unforcien items LS 1360620.00
Total 1050000.00
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm
HBG graded metal including cost of all materials and labour charges
3 etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
CC Drain Side Walls 1 X 2 156.00 0.19 0.38 22.23 8971.40 cum 199434.00
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm
HBG graded metal including cost of all materials and labour charges
4 etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including all
charges etc Completed
Steel 110 Kgs per cum(approx) for Top Slabs 412.50 47.14 Kg 19443.00
CC Drain Side Walls 1 X 1 156.00 0.00 0.30 46.80 237.60 Sqm 11119.00
Cutting of Open CC Road surface with Concrete saw Cutter and Removel
7
with Breaker and disposal @ 0.50 km away etc completed
SI. Meausurements Amount
Descritption of item Qty Rate Per
No
No L B D (Rs.)
CC Drain Side Walls 1 X 1 7.80 1.00 0.15 1.17 2424.00 Cum 2836.00
Sub-Total 321109.00
8 Seigniorage charges 3234.00
9 Provision towards QC Charges at 0.5% 1606.00
10 Provision NAC @ 0.1% 321.00
11 Provision for GST Excluding cement and unskilled labour 32511.00
12 Provision of unforcien items LS 91219.00
Total 450000.00
Filling
Earth work excavartion
1 283.63 Cum 167.44 47491.00 1.00
(other materials)
Other material
Sand for
Sand for Cement in components (Skilled/ Unskilled labour charges
Amount mortar Amount Amount Amount Steel Amount
Kgs semiskilled ) etc
167.44 47491.00
0.00
25.59 0.00
27.88 22669.34
13510.20 64848.96
59613.30
61.19 49754.40
44873.40 215392.32
665472.23
0.00 0.00
0.00 0.00
0.00
0.00 0.00
0.00
524.88 2519.42
1.91 1737.76
24610.81
0.00
0.00
154748.00
0.00 1.91 1738.00 89.07 72424.00 58908.48 282761.00 0.00 0.00 904444.00 47491.00
100 100
191.36 8907.11 25087.00
1705501.00
25087.00
No.of Man days
In Put Data
Construction of CC Side drains in T P GUDUR GP of T.P.GUDUR Mandal
Length 590.80 rmt 20.00 Lakhs
Rate Per
S. No Task Name Unit Task Code Qty unit Amount (Rs.)
(in Rs.)
9 CW-G09.40 mm nominal HBG/HBT Graded Metal Cum 34824 55.27 1942.00 107332.00
1 Sand (unscreened) for concrete Pennar Cum 15 203.10 510.00 100.00 813.10
2 Sand for mortar (screened) Pennar Cum 15 203.10 605.00 100.00 908.10
3 Sand (unscreened) for filling Local Cum 1 28.30 375.00 100.00 503.30
1.Certified that the above leads are corrrect to the best of my knowledge
2. Rates of sand are as per incorporation of revised sand rates in the SOR 2019-20 vide Lr.No.ENC/IW/SE(P&M)/ EE.1/DEE.2/AEE(K)/ SOR 2019-20/ Vol-4
dt:25.10.2019 of the Engineer in Chief (Admin) (FAC) & Chairman, Board of Chief Engineers, Water Resources department.
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal
1
upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material
as per Technical Specification 305 MORD / 304 MORTH
Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 460.00 1674.40
Rate pr cum 167.44
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent of
labour cost. Assessment for dewatering shall be made as per site conditions.
Cement Concrete Nominal Mix(1:3:6) 40 mm down graded HBG Metal including cost of all materials and
3 labour charges etc,,complete -1 cum with Machine mixing for CC Bed including conveyance, seigonarage of
materials of sand &metal and excluding cost of steel and its fabrication charges etc . Inluding GST @ 12%.
Unit:1cum
A. Materials
Cement kg 220.00 3.67 807.84
Agreagate 40 mm nomial size cum 0.90 1942.00 1747.80
Sand cum 0.45 813.10 369.15
Water including for curing kl 1.20 83.00 99.60
sub total for material 3024.39
B. Labour
Mason 1st class nos 0.10 550.00 55.00
Man Mazdoor (semi skilled) nos 1.39 460.00 639.40
sub total for labour 694.40
C. Machinery
Vibrated Cement Concrete (1:2:4) using 60% of 20mm and 40% of 12mm HBG graded metal including cost
4 of all materials and labour charges etc,,complete -1 cum with Machine mixing for side walls of drains
including conveyance, seigonarage of materials of sand &metal including GST @12% on Rates
Sl. Rate (in Total
Description of item Reference Unit Qty
No. Rs.) Amount
1 2 3 4 5 6 7
Unit:1cum
A. Materials
Cement kg 330.00 3.67 1211.76
Aggregate 20 mm nomial size cum 0.54 2472.00 1334.88
Aggregate 12 mm nomial size cum 0.36 2202.00 792.72
Sand Cum 0.45 813.10 365.90
Water including for curing kl 1.20 83.00 99.60
sub total for material 3804.86
B. Labour
Mason 1st class nos 0.10 550.00 55.00
Man Mazdoor (semi skilled) nos 1.39 460.00 639.40
sub total for labour 694.40
C. Machinery
Centering charges for VCC vertical walls 1Cum 1.00 3959.20 3959.20
of plane surface (rate is for both sides
centering) including open drains SoR
2019-20 Sl.no 31 (b)- 4b (as per sub data)
Total for 1 Cum with centring charges 8971.40
Plastering with CM (1:5)mix, 12 mm including cost of all materials and labour charges etc,,complete -for 10
6
Sqm but including conveyance and serignorage charges of materials of sand including GST @12%
DATA for Conversion of Centering Charges from Sq.mt to Cum for sidewalls only
C.C(1:2:4) 0.075
C.C(1:3:6) 0.10
Drain Top Width 0.45 m
Sand Filling 0.10
0.85
Drain bottom width 0.30 m
Volume of drain for 1.00 RM length = 1.00 x (0.15+0.23)/2 x 0.45 0.0855 Cum
(Taking one side (inner side) centering only 1.00 x 0.457 0.457 Sqm
i.e., 0.0855 cum drain qty requires 0.457 sqm of centering area
Hence 1.00 cum volume of drain requires centering area = 0.457/0.0855 5.35 Sqm
Volume of drain for 1.00 RM length = 1.00 x (0.15+0.23)/2 x 0.3 0.057 Cum
(Taking one side (inner side) centering only 1.00 x 0.31 0.31 Sqm
i.e., 0.0855 cum drain qty requires 0.457 sqm of centering area
Hence 1.00 cum volume of drain requires centering area = 0.31/0.057 5.44 Sqm
5.35*.45+5.44*.3 4.04
0.0064
0.2025
0.2089 0.4570558
0.09
0.0064
0.0964 0.31