Project Title: Location: Subject: Proposed Variation Order No. 1

This document outlines proposed variations to improve a CISC office, including: 1. Removing and replacing walls between rooms. 2. Modifying office cubicles as requested by end-users. 3. Relocating doors and walls for electrical, toilet and exit areas. The variations include demolishing and rebuilding walls, installing new doors and partitions, painting, and fabricating and installing new cubicles. Cost estimates are provided for added and deducted work items.

Uploaded by

Ariel Dela Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views5 pages

Project Title: Location: Subject: Proposed Variation Order No. 1

This document outlines proposed variations to improve a CISC office, including: 1. Removing and replacing walls between rooms. 2. Modifying office cubicles as requested by end-users. 3. Relocating doors and walls for electrical, toilet and exit areas. The variations include demolishing and rebuilding walls, installing new doors and partitions, painting, and fabricating and installing new cubicles. Cost estimates are provided for added and deducted work items.

Uploaded by

Ariel Dela Cruz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

PROJECT TITLE : IMPROVEMENT OF CISC OFFICE

LOCATION : CPAf COMPOUND, DOMINGO LATICAN AVENUE UPLB, COLLEGE, UPLB

SUBJECT : PROPOSED VARIATION ORDER NO. 1

JUNCAN ENTERPRISES
ITEM MATERIALS LABOR/EQPT. RENTAL TOTAL
DESCRIPTION OF WORK
NO UNIT QTY. PER UNIT TOTAL PER UNIT TOTAL COST
(P) (P) (P) (P) (P)
(1) (2) (3) (4) (5) (6) (7) (8) (9)

I EXTRA WORK ORDER

ARCHITECTURAL WORKS

REMOVAL OF CEMENT PARTITION WALL BETWEEN READING ROOM


AND STAFF ROOM
A. MASONRY WORKS
1. 100mm thk. CHB (350 psi, NLB) with mortar for filler and laying
(1:3 mortar mix) sq.m
2. Plastering, smooth finish (1:3 mortar mix) sq.m
3. Preparatory Works (Demolition of existing CHB partition wall, drilling
of rebars to walls and column, and application of structural grout, etc.) lot 1.00
B. PAINTING WORKS
1. Masonry wall (Semi-gloss acrylic based latex paint finish, UPLB Beige
color)
a. New painting sq.m 350.00 35.00

MODIFICATIONS ON OFFICE CUBICLE AS REQUESTED BY THE


END-USER
C. FABRICATION, SUPPLY, DELIVERY & INSTALLATION
1. OFFICE CUBICLE
a. 45mm thk. modular wall partition with fabric finish panel sidings,
powder coated aluminum alloy frames. Provide 6mm thk. clear float
glass top partition panel, punch out holes for utilities, 25mm thk.
HPL pre-laminated modular table with PVC edging. Provide plastic
grommet for computer cables (size of holes as per manufacturer's
recommendation), complete with standard parts and accessories,
pre-fabricated/pre-assembled with mobile pedestal,
per construction bulletin plan lot 1.00

REMOVAL OF DOOR TO BE RAPLACED WITH FIBER CEMENT DRY WALL


AT THE PROPOSED RESEARCH ROOM
D. WALL FINISHES
1. PW-2A; 6mm thk fiber cement board on galvanized metal framing
drywall partition, as per plan sq. m. 1,900.00 190.00
E. PAINTING WORKS
1. Drywall (Semi-gloss acrylic based latex paint finish) sq.m 250.00 25.00

RELOCATION OF TOILET DOOR TO THE ADJACENT WALL


F. PREPARATORY WORKS
1. Demolition of portion of the adjacent CHB Wall lot 1.00

G. MASONRY WORKS
1. 100mm thk. CHB (350 psi, NLB) with mortar for filler and laying
(1:3 mortar mix) sq.m
2. Plastering, smooth finish (1:3 mortar mix) sq.m
3. Preparatory Works (Chipping of surface, drilling of rebars to walls and
column, and application of structural grout, etc.) lot 1.00
H. PAINTING WORKS
1. Masonry wall (Semi-gloss acrylic based latex paint finish, UPLB Beige
color)
a. New painting sq.m 350.00 35.00

RELOCATION OF ELECTRICAL ROOM DOOR


I. MASONRY WORKS
1. 100mm thk. CHB (350 psi, NLB) with mortar for filler and laying
(1:3 mortar mix) sq.m
2. Plastering, smooth finish (1:3 mortar mix) sq.m
3. Preparatory Works (Chipping of surface, drilling of rebars to walls and
column, and application of structural grout, etc.) lot 1.00
J. PAINTING WORKS
1. Masonry wall (Semi-gloss acrylic based latex paint finish, UPLB Beige
color)
a. New painting sq.m 350.00 35.00

REMOVAL OF WALL EXTENSION OF DIRECTOR'S OFFICE AND CONSTRUCTION


OF PARTITION TO ENCLOSE THE ELECTRICAL AND COMFORT ROOMS
K. PREPARATORY WORKS
1. Demolition of CHB wall extension

L. WALL FINISHES
1. PW-2A; 6mm thk fiber cement board on galvanized metal framing
drywall partition, as per plan sq.m. 1,900.00 190.00
2. Installation of Refurbished Wooden Lattice with Wooden Frame lot

M. PAINTING WORKS
1. Drywall (Semi-gloss acrylic based latex paint finish) sq. m. 250.00 25.00
2. Refurbished wooden latice (Oil wood stain finish) lot 1.00

INSTALLATION OF ALUMINUM FRAMED GLASS DOOR AT THE EXIT DOOR


AT THE CORRIDOR
N. WALL FINISHES
1. PW-2A; 6mm thk fiber cement board on galvanized metal framing
drywall partition, as per plan sq.m 1,900.00 190.00

O. PAINTING WORKS
1. Drywall (Semi-gloss acrylic based latex paint finish) sq. m. 250.00 25.00

P. FABRICATION, SUPPLY, DELIVERY & INSTALLATION


1. DOORS
a. PD-1A; Proposed aluminum framed glass door with fixed side panel
6mm thk bronze tinted float glass on standard analok finish
aluminum door frame, ( Aluminum door frame component shall be
1.5mm thk minimum) 1.5mm thk x 40mm x 100mm close tube
analok finish aluminum jamb, provide fr 25mm thk x 150mm KD
narra wood push/pull plates on both sides, painted with oil wood
stain primer coat and semi-gloss lacquer top coat heavy duty door
closer, key hole lock set, complete with weather stripping
(Mohawk Hair) and standard parts and accessories, provide
architectural grade sealant brown color along perimeter frame
(both sides), as per plan (H=2.1m, W=1.8m) set 1.00

EXTRA WORK ORDER - TOTAL ADDITIVE COST -

II DEDUCTIVE ITEMS OF WORK

ARCHITECTURAL WORKS

REMOVAL OF CEMENT PARTITION WALL BETWEEN READING ROOM


AND STAFF ROOM
A. FABRICATION, SUPPLY, DELIVERY & INSTALLATION
1. DOORS
a. ED-4*; Proposed 1 3/4" hollow core flush door on existing door
jamb with 1/4" thk marine plywood skins and single rabbeted stop
door jamb, complete 3 - 3" x 3" loose pin hinges and cylindrical
lockset. Door leaf and jamb to be painted with Quick dry enamel
paint finish (same color as existing), as per plan.
(H=2.1m, W=0.8m) set 1 15,000.00 15,000.00 1,500.00 1,500.00 16,500.00

B. PAINTING WORKS
For the existing door and jamb to be re-used
a. Door (Oil wood stain) lot 1
b. Jamb (Quick dry enamel based paint) lot 1

MODIFICATIONS ON OFFICE CUBICLE AS REQUESTED BY THE


END-USER
C. FABRICATION, SUPPLY, DELIVERY & INSTALLATION
1. OFFICE CUBICLE
a. 45mm thk. modular wall partition with fabric finish panel sidings,
powder coated aluminum alloy frames. Provide 6mm thk. clear float
glass top partition panel, punch out holes for utilities, 25mm thk.
HPL pre-laminated modular table with PVC edging. Provide plastic
grommet for computer cables (size of holes as per manufacturer's
recommendation), complete with standard parts and accessories,
pre-fabricated/pre-assembled, per plan lot 1.00 500,000.00 500,000.00 50,000.00 50,000.00 550,000.00

REMOVAL OF DOOR TO BE RAPLACED WITH FIBER CEMENT DRY WALL


AT THE PROPOSED RESEARCH ROOM
D. PREPARATORY WORKS
1. Re-installation of existing door ED-5

E. PAINTING WORKS
1. For the existing door and jamb to be re-used
a. Door (Oil wood stain) lot 1.00
b. Jamb (Quick dry enamel based paint) lot 1.00

REMOVAL OF WALL EXTENSION OF DIRECTOR'S OFFICE AND CONSTRUCTION


OF PARTITION TO ENCLOSE THE ELECTRICAL AND COMFORT ROOMS
F. PAINTING WORKS
1. Masonry wall (Semi-gloss acrylic based latex paint finish, UPLB Beige
color)
a. Repainting sq.m 350.00 35.00

TOTAL CHANGE ORDER - TOTAL DEDUCTIVE COST

TOTAL NET ADDITIVE COST

Conforme: Prepared/Estimated by:


JUNCAN ENTERPRISES

CHRISTIAN B. CANLAS RONALD P. BELIZARIO MARY MAE R. DUNGCA


PROJECT ENGINEER Architectural Works Inspector/ Architectural Works Inspector/