Al Moosa Hospital Project Schedule - Opt
Al Moosa Hospital Project Schedule - Opt
200,000 hrs
0%
WORK (HRS)
150,000 hrs
100,000 hrs
Remaining Work
50,000 hrs
0 hrs
217,566 hrs
9/6/20
9/20/20
10/4/20
10/18/20
11/1/20
11/15/20
11/29/20
12/13/20
12/27/20
1/10/21
1/24/21
2/7/21
2/21/21
3/7/21
3/21/21
4/4/21
4/18/21
5/2/21
5/16/21
5/30/21
6/13/21
6/27/21
7/11/21
7/25/21
8/8/21
8/22/21
9/5/21
9/19/21
10/3/21
10/17/21
10/31/21
11/14/21
11/28/21
12/12/21
12/26/21
1/9/22
1/23/22
2/6/22
2/20/22
Actual Work
Remaining Cumulative Work Remaining Cumulative Actual Work Baseline Remaining Cumulative Work
250,000 hrs
0 hrs
200,000 hrs
WORK OVERVIEW
WORK (HRS)
150,000 hrs
100,000 hrs
Al-Moosa Hospital
Sun 1/10/21 Tue 3/1/22 -
Schedule, 217,566 hrs
50,000 hrs
14000
12000
0 hrs
10000
Al-Moosa Hospital Schedule
8000 Group: PRISMA FACTORY
Actual Work Remaining Work Baseline Work 6000 Unit Availability
4000
Group: PRISMA FACTORY
2000
Work
WORK STATS 0
Shows work stats for all top level tasks.
Projects Manager
Project Team M
Project Team C
Project Team St
Project Team B 12000
Project Team A 10000
Procurement Manager
8000
Management Group: PRISMA SITE
6000
Commercial Unit Availability
4000
Factory Team
2000 Group: PRISMA SITE
Project Eng/For Work
Engineering Manager 0
100
92
87
Installation Manpower Strength
80
75
62
60
50
40
26
20 17
3 3
0
Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22
Month Apr-21 May-21 Jun-21 Jul-21 Aug-21 Sep-21 Oct-21 Nov-21 Dec-21 Jan-22 Feb-22 Mar-22 Apr-22
Total 3 50 75 87 92 107 107 107 107 62 17 26 3
AL-MOOSA SPECIALIST HOSPITAL
80,000 hrs 1%
70,000 hrs 1%
1%
60,000 hrs 1%
50,000 hrs 1%
40,000 hrs 1%
30,000 hrs 0%
0%
20,000 hrs 0%
10,000 hrs 0%
0 hrs 0%
RESOURCE STATUS
Remaing work for all work resources.
MANPOWER COST OVERVIEW Progress made versus the cost spent over time. If % Complete line below the cumulative cost
line,your project may be over budget.
Chart Title
SUN 1/10/21 - TUE 3/1/22
1% $3,000,000.00
$2,500,000.00
CUMULATIVE COST
1%
% COMPLETE
COST
$2,000,000.00
1%
$1,500,000.00
$2,637,520.00
0%
$1,000,000.00
0% $500,000.00
0% $0.00
8/8/21
9/6/20
10/18/20
11/29/20
1/10/21
2/21/21
4/4/21
5/16/21
6/27/21
9/19/21
10/31/21
12/12/21
1/23/22
REMAINING COST
% COMPLETE
COST STATUS
Chart Title
$3,000,000.00
COST STATUS $2,500,000.00
Cost status for top level tasks.
$2,000,000.00
Name Actual Cost Remaining Baseline Cost Cost Variance $1,500,000.00
Cost Cost
$1,000,000.00
Al-Moosa Hospital $0.00 $2,637,520.00 $0.00 $2,637,520.0 $2,637,520.00
Schedule 0 $500,000.00
$0.00
Al-Moosa Hospital Schedule
Cost
Remaining Cost Actual Cost Baseline Cost
$250,000.00
$200,000.00
$150,000.00
$100,000.00
$50,000.00
$0.00
Cost
AL-MOOSA SPECIALIST HOSPITAL
ID Task Name Duration Start Finish Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
4 a. Design and Submittal - CW, ACP, Screen and Catwalk 40 days Sun 1/10/21 Mon 3/1/21 Engineering Manager[300%]
5 b. Approval of Submittal 10 days Mon 3/1/21 Sun 3/14/21
6 d. Design and Submittal - Miscellaneous 14 days Mon 3/1/21 Thu 3/18/21 Engineering Manager[300%]
7 e. Approval of Miscellaneous Item Submittal 10 days Sat 3/20/21 Wed 3/31/21
8 f. Material and Glass Requisition 11 days Sun 3/14/21 Sun 3/28/21 Engineering Manager
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
10 Material Procurement 46 days Sun 3/28/21 Tue 5/25/21 Procurement Manager
11 Glass Stock Order 23 days Tue 3/23/21 Tue 4/20/21 Procurement Manager
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
13 Cutting List and Material Requisition 1 day Tue 2/2/21 Tue 2/2/21 Project Eng/For,Engineering Manager
14 Material Procurement 4 days Wed 2/3/21 Mon 2/8/21 Procurement Manager
15 Fabrication - Aluminum 0.2 days Tue 2/9/21 Tue 2/9/21 Factory Team[500%]
16 Installation - Aluminum 1 day Wed 2/10/21 Wed 2/10/21 Project Eng/For
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
18 Procurement (Aluminum and Steel) 48 days Sun 3/28/21 Thu 5/27/21 Procurement Manager
19 Site Measurements and Cutting List 25 days Mon 3/1/21 Wed 3/31/21 Project Eng/For,Engineering Manager
20 Glass Fabrication 46 days Wed 4/21/21 Sat 6/19/21 Procurement Manager
21 Internal Aluminum Curtain Wall (7,738.06 m²) 93 days Mon 4/26/21 Sun 8/22/21
22 Aluminum Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[3,000%]
23 Aluminum Installation 60 days Mon 5/10/21 Sun 7/25/21 Project Team A[2,400%]
24 Glass/Cladding Installation 60 days Mon 5/24/21 Sun 8/8/21 Project Team B[2,400%]
25 Handing over 11 days Mon 8/9/21 Sun 8/22/21 Project Eng/For,Project Team M[500%]
26 External Steel Truss and Aluminum (Louver + Catwalk) 127 days Mon 4/26/21 Mon 10/4/21
27 Steel Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[2,000%]
28 Aluminum Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[1,000%]
29 Steel Installation 60 days Tue 6/22/21 Mon 9/6/21 Project Team St[2,400%]
30 Aluminum Installation 60 days Tue 7/6/21 Mon 9/20/21 Project Team C[1,200%]
31 Handing over 11 days Tue 9/21/21 Mon 10/4/21 Project Eng/For,Project Team M[500%]
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
33 Procurement (Aluminum and Steel) 48 days Tue 4/27/21 Sun 6/27/21 Procurement Manager
34 Site Measurements and Cutting List 5.5 days Wed 6/9/21 Tue 6/15/21 Project Eng/For
35 Glass Fabrication 46 days Wed 6/16/21 Sat 8/14/21 Procurement Manager
36 Internal Aluminum Curtain Wall (7,738.06 m²) 113 days Wed 6/16/21 Sun 11/7/21
37 Aluminum Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[3,000%]
ID Task Name Duration Start Finish Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
38 Aluminum Installation 60 days Mon 7/26/21 Sun 10/10/21 Project Team A[2,400%]
39 Glass/Cladding Installation 60 days Mon 8/9/21 Sun 10/24/21 Project Team B[2,400%]
40 Handing over 11 days Sun 10/24/21 Sun 11/7/21 Project Eng/For,Project Team M[500%]
41 External Steel Truss and Aluminum (Louver + Catwalk) 147 days Wed 6/16/21 Mon 12/20/21
42 Steel Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[2,000%]
43 Aluminum Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[1,000%]
44 Steel Installation 60 days Tue 9/7/21 Mon 11/22/21 Project Team St[2,400%]
45 Aluminum Installation 60 days Tue 9/21/21 Mon 12/6/21 Project Team C[1,200%]
46 Handing over 11 days Mon 12/6/21 Mon 12/20/21 Project Eng/For,Project Team M[500%]
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
48 Procurement 35.25 days Wed 5/26/21 Sun 7/11/21 Procurement Manager
49 Site Measurements and Cutting List 5.5 days Tue 8/24/21 Tue 8/31/21 Project Eng/For
50 Glass Fabrication 46 days Tue 8/31/21 Thu 10/28/21 Procurement Manager
51 Internal Aluminum Curtain Wall (2,210.88 m²) 64.75 days Tue 8/31/21 Mon 11/22/21
52 Aluminum Fabrication 11.5 days Tue 8/31/21 Tue 9/14/21 Factory Team[3,000%]
53 Aluminum Installation 17.25 days Sun 10/10/21 Mon 11/1/21 Project Team A[2,400%]
54 Glass/Cladding Installation 17.25 days Sun 10/24/21 Mon 11/15/21 Project Team B[2,400%]
55 Handing over 5.5 days Mon 11/15/21 Mon 11/22/21 Project Eng/For,Project Team M[500%]
56 External Steel Truss and Aluminum (Louver + Catwalk) 122 days Tue 8/31/21 Wed 2/2/22
57 Steel Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[3,000%]
58 Aluminum Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[1,000%]
59 Steel Installation 35 days Mon 11/22/21 Wed 1/5/22 Project Team St[2,400%]
60 Aluminum Installation 35 days Mon 12/6/21 Wed 1/19/22 Project Team C[1,200%]
61 Handing over 11 days Wed 1/19/22 Wed 2/2/22 Project Eng/For,Project Team
62 Spider Glass (1,443.00 m²) 93.25 days Tue 8/31/21 Tue 12/28/21
63 Procurement and Fabrication 16.5 days Tue 8/31/21 Tue 9/21/21 Procurement Manager
64 Spider Glass Installation 23 days Mon 11/15/21 Tue 12/14/21 Project Team B[1,200%]
65 Handing over 11 days Tue 12/14/21 Tue 12/28/21 Project Eng/For,Project Team M[300%
66 Sandtrap Louver with Steel support (2,456.83 m²) 115.5 days Tue 8/31/21 Tue 1/25/22
67 Procurement and Fabrication 37.5 days Tue 8/31/21 Mon 10/18/21 Procurement Manager,Factory Team[1,000%]
68 Louver Installation 56.25 days Mon 11/1/21 Tue 1/11/22 Project Team A[1,200%]
69 Handing over 11 days Tue 1/11/22 Tue 1/25/22 Project Eng/For,Project Team M
70 ACP on Wall (3,210 m²) 105.25 days Tue 8/31/21 Wed 1/12/22
71 Aluminum Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[1,000%]
72 Aluminum Installation 35 days Mon 11/22/21 Wed 1/5/22 Project Team A[1,200%]
73 Handing over 5.5 days Wed 1/5/22 Wed 1/12/22 Project Eng/For,Project Team M[3
74 ACP on Column (1,141.0 m²) 82.25 days Thu 9/30/21 Wed 1/12/22
ID Task Name Duration Start Finish Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021 Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
75 Aluminum Fabrication 12 days Thu 9/30/21 Sat 10/16/21 Factory Team[1,000%]
76 Aluminum Installation 18 days Tue 12/14/21 Wed 1/5/22 Project Team B[1,200%]
77 Handing over 5.5 days Wed 1/5/22 Wed 1/12/22 Project Eng/For,Project Team M[3
78 Miscellaneous Works 96.5 days Tue 8/31/21 Sat 1/1/22
79 Doors and Windows (D-38 & W-59) 39.5 days Tue 8/31/21 Wed 10/20/21
80 Aluminum Fabrication 11.5 days Tue 8/31/21 Tue 9/14/21 Factory Team[1,200%]
81 Aluminum Installation 23 days Tue 9/14/21 Wed 10/13/21 Project Team M[1,200%]
82 Handing over 5.5 days Wed 10/13/21 Wed 10/20/21 Project Eng/For,Project Team M[300%]
83 Glass Handrail (1,096 m) 39.5 days Wed 10/13/21 Thu 12/2/21
84 Procurement and Fabrication 23 days Wed 10/13/21 Thu 11/11/21 Factory Team[1,200%],Procurement Manager
85 Aluminum Installation 23 days Wed 10/27/21 Thu 11/25/21 Project Team M[1,200%]
86 Handing over 5.5 days Sat 11/27/21 Thu 12/2/21 Project Eng/For,Project Team M[300%]
87 Glass Partition (389 m²) 62.5 days Wed 10/13/21 Sat 1/1/22
88 Procurement 23 days Wed 10/13/21 Thu 11/11/21 Procurement Manager
89 Aluminum Installation 23 days Sat 11/27/21 Sat 12/25/21 Project Team M[600%]
90 Handing over 5.5 days Sun 12/26/21 Sat 1/1/22 Project Eng/For,Project Team M[300
91 Canopy (23 m²) 96.5 days Tue 8/31/21 Sat 1/1/22
92 Aluminum Fabrication 11 days Tue 8/31/21 Tue 9/14/21 Factory Team[1,200%]
93 Aluminum Installation 23 days Sat 11/27/21 Sat 12/25/21 Project Team M[600%]
94 Handing over 5.5 days Sun 12/26/21 Sat 1/1/22 Project Eng/For,Project Team M[300
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,Projec
E. LEVEL-1 ACTIVITIES
PRISMA Metal Industry L.L.C.
AL-MOOSA SPECIALIST HOSPITAL Location: Al-Hasa
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
SUMMARY
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
4 a. Design and Submittal - CW, ACP, Screen and Catwalk 40 days Sun 1/10/21 Mon 3/1/21 Engineering Manager[300%]
5 b. Approval of Submittal 10 days Mon 3/1/21 Sun 3/14/21
6 d. Design and Submittal - Miscellaneous 14 days Mon 3/1/21 Thu 3/18/21 Engineering Manager[300%]
7 e. Approval of Miscellaneous Item Submittal 10 days Sat 3/20/21 Wed 3/31/21
8 f. Material and Glass Requisition 11 days Sun 3/14/21 Sun 3/28/21 Engineering Manager
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
ENGINEERING
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
10 Material Procurement 46 days Sun 3/28/21 Tue 5/25/21 Procurement Manager
11 Glass Stock Order 23 days Tue 3/23/21 Tue 4/20/21 Procurement Manager
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
PROCUREMENT
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
13 Cutting List and Material Requisition 1 day Tue 2/2/21 Tue 2/2/21 Project Eng/For,Engineering Manager
14 Material Procurement 4 days Wed 2/3/21 Mon 2/8/21 Procurement Manager
15 Fabrication - Aluminum 0.2 days Tue 2/9/21 Tue 2/9/21 Factory Team[500%]
16 Installation - Aluminum 1 day Wed 2/10/21 Wed 2/10/21 Project Eng/For
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
MOCK UP
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
18 Procurement (Aluminum and Steel) 48 days Sun 3/28/21 Thu 5/27/21 Procurement Manager
19 Site Measurements and Cutting List 25 days Mon 3/1/21 Wed 3/31/21 Project Eng/For,Engineering Manager
20 Glass Fabrication 46 days Wed 4/21/21 Sat 6/19/21 Procurement Manager
21 Internal Aluminum Curtain Wall (7,738.06 m²) 93 days Mon 4/26/21 Sun 8/22/21
22 Aluminum Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[3,000%]
23 Aluminum Installation 60 days Mon 5/10/21 Sun 7/25/21 Project Team A[2,400%]
24 Glass/Cladding Installation 60 days Mon 5/24/21 Sun 8/8/21 Project Team B[2,400%]
25 Handing over 11 days Mon 8/9/21 Sun 8/22/21 Project Eng/For,Project Team M[500%]
26 External Steel Truss and Aluminum (Louver + Catwalk) 127 days Mon 4/26/21 Mon 10/4/21
27 Steel Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[2,000%]
28 Aluminum Fabrication 48.5 days Mon 4/26/21 Sun 6/27/21 Factory Team[1,000%]
29 Steel Installation 60 days Tue 6/22/21 Mon 9/6/21 Project Team St[2,400%]
30 Aluminum Installation 60 days Tue 7/6/21 Mon 9/20/21 Project Team C[1,200%]
31 Handing over 11 days Tue 9/21/21 Mon 10/4/21 Project Eng/For,Project Team M[500%]
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
PHASE-1 (Floor 1 to 7)
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
33 Procurement (Aluminum and Steel) 48 days Tue 4/27/21 Sun 6/27/21 Procurement Manager
34 Site Measurements and Cutting List 5.5 days Wed 6/9/21 Tue 6/15/21 Project Eng/For
35 Glass Fabrication 46 days Wed 6/16/21 Sat 8/14/21 Procurement Manager
36 Internal Aluminum Curtain Wall (7,738.06 m²) 113 days Wed 6/16/21 Sun 11/7/21
37 Aluminum Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[3,000%]
38 Aluminum Installation 60 days Mon 7/26/21 Sun 10/10/21 Project Team A[2,400%]
39 Glass/Cladding Installation 60 days Mon 8/9/21 Sun 10/24/21 Project Team B[2,400%]
40 Handing over 11 days Sun 10/24/21 Sun 11/7/21 Project Eng/For,Project Team M[500%]
41 External Steel Truss and Aluminum (Louver + Catwalk) 147 days Wed 6/16/21 Mon 12/20/21
42 Steel Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[2,000%]
43 Aluminum Fabrication 48.5 days Wed 6/16/21 Mon 8/16/21 Factory Team[1,000%]
44 Steel Installation 60 days Tue 9/7/21 Mon 11/22/21 Project Team St[2,400%]
45 Aluminum Installation 60 days Tue 9/21/21 Mon 12/6/21 Project Team C[1,200%]
46 Handing over 11 days Mon 12/6/21 Mon 12/20/21 Project Eng/For,Project Team M[500
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
1 Al-Moosa Hospital Schedule 327 days Sun 1/10/21 Tue 3/1/22
2 Approved Contract and PO 0 days Sun 1/10/21 Sun 1/10/21 1/10
3 Engineering Design - Shop drawing and approval 64 days Sun 1/10/21 Wed 3/31/21 3/31
9 Procurement 50 days Tue 3/23/21 Tue 5/25/21
12 PHASE Zero (Mockup) 7.5 days Tue 2/2/21 Wed 2/10/21 2/10
17 PHASE ONE (FLR - 1 TO 7) 171.5 days Mon 3/1/21 Mon 10/4/21
32 PHASE TWO (FLR - 8 TO 14) 186.5 days Tue 4/27/21 Mon 12/20/21
47 PHASE THREE (FLR - 15 & 16, RF, GF, BASEMENT) 198 days Wed 5/26/21 Wed 2/2/22
48 Procurement 35.25 days Wed 5/26/21 Sun 7/11/21 Procurement Manager
49 Site Measurements and Cutting List 5.5 days Tue 8/24/21 Tue 8/31/21 Project Eng/For
50 Glass Fabrication 46 days Tue 8/31/21 Thu 10/28/21 Procurement Manager
51 Internal Aluminum Curtain Wall (2,210.88 m²) 64.75 days Tue 8/31/21 Mon 11/22/21
52 Aluminum Fabrication 11.5 days Tue 8/31/21 Tue 9/14/21 Factory Team[3,000%]
53 Aluminum Installation 17.25 days Sun 10/10/21 Mon 11/1/21 Project Team A[2,400%]
54 Glass/Cladding Installation 17.25 days Sun 10/24/21 Mon 11/15/21 Project Team B[2,400%]
55 Handing over 5.5 days Mon 11/15/21 Mon 11/22/21 Project Eng/For,Project Team M[500%]
56 External Steel Truss and Aluminum (Louver + Catwalk) 122 days Tue 8/31/21 Wed 2/2/22
57 Steel Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[3,000%]
58 Aluminum Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[1,000%]
59 Steel Installation 35 days Mon 11/22/21 Wed 1/5/22 Project Team St[2,400%]
60 Aluminum Installation 35 days Mon 12/6/21 Wed 1/19/22 Project Team C[1,200%]
61 Handing over 11 days Wed 1/19/22 Wed 2/2/22 Project Eng/For,Project T
62 Spider Glass (1,443.00 m²) 93.25 days Tue 8/31/21 Tue 12/28/21
63 Procurement and Fabrication 16.5 days Tue 8/31/21 Tue 9/21/21 Procurement Manager
64 Spider Glass Installation 23 days Mon 11/15/21 Tue 12/14/21 Project Team B[1,200%]
65 Handing over 11 days Tue 12/14/21 Tue 12/28/21 Project Eng/For,Project Team M[3
66 Sandtrap Louver with Steel support (2,456.83 m²) 115.5 days Tue 8/31/21 Tue 1/25/22
67 Procurement and Fabrication 37.5 days Tue 8/31/21 Mon 10/18/21 Procurement Manager,Factory Team[1,000%]
68 Louver Installation 56.25 days Mon 11/1/21 Tue 1/11/22 Project Team A[1,200%]
69 Handing over 11 days Tue 1/11/22 Tue 1/25/22 Project Eng/For,Project Te
70 ACP on Wall (3,210 m²) 105.25 days Tue 8/31/21 Wed 1/12/22
71 Aluminum Fabrication 23.5 days Tue 8/31/21 Wed 9/29/21 Factory Team[1,000%]
72 Aluminum Installation 35 days Mon 11/22/21 Wed 1/5/22 Project Team A[1,200%]
73 Handing over 5.5 days Wed 1/5/22 Wed 1/12/22 Project Eng/For,Project Team
74 ACP on Column (1,141.0 m²) 82.25 days Thu 9/30/21 Wed 1/12/22
75 Aluminum Fabrication 12 days Thu 9/30/21 Sat 10/16/21 Factory Team[1,000%]
76 Aluminum Installation 18 days Tue 12/14/21 Wed 1/5/22 Project Team B[1,200%]
ID Task Name Duration Start Finish Dec 27, '20 Jan 31, '21 Mar 7, '21 Apr 11, '21 May 16, '21 Jun 20, '21 Jul 25, '21 Aug 29, '21 Oct 3, '21 Nov 7, '21 Dec 12, '21 Jan 16, '22 Feb 20, '22 Mar 27, '22
1 16 31 15 2 17 1 16 1 16 31 15 30 15 30 14 29 13 28 13 28 12 27 12 27 11 26 10 25 12 27 11
77 Handing over 5.5 days Wed 1/5/22 Wed 1/12/22 Project Eng/For,Project Team
78 Miscellaneous Works 96.5 days Tue 8/31/21 Sat 1/1/22
79 Doors and Windows (D-38 & W-59) 39.5 days Tue 8/31/21 Wed 10/20/21
80 Aluminum Fabrication 11.5 days Tue 8/31/21 Tue 9/14/21 Factory Team[1,200%]
81 Aluminum Installation 23 days Tue 9/14/21 Wed 10/13/21 Project Team M[1,200%]
82 Handing over 5.5 days Wed 10/13/21 Wed 10/20/21 Project Eng/For,Project Team M[300%]
83 Glass Handrail (1,096 m) 39.5 days Wed 10/13/21 Thu 12/2/21
84 Procurement and Fabrication 23 days Wed 10/13/21 Thu 11/11/21 Factory Team[1,200%],Procurement Manager
85 Aluminum Installation 23 days Wed 10/27/21 Thu 11/25/21 Project Team M[1,200%]
86 Handing over 5.5 days Sat 11/27/21 Thu 12/2/21 Project Eng/For,Project Team M[300%]
87 Glass Partition (389 m²) 62.5 days Wed 10/13/21 Sat 1/1/22
88 Procurement 23 days Wed 10/13/21 Thu 11/11/21 Procurement Manager
89 Aluminum Installation 23 days Sat 11/27/21 Sat 12/25/21 Project Team M[600%]
90 Handing over 5.5 days Sun 12/26/21 Sat 1/1/22 Project Eng/For,Project Team M[
91 Canopy (23 m²) 96.5 days Tue 8/31/21 Sat 1/1/22
92 Aluminum Fabrication 11 days Tue 8/31/21 Tue 9/14/21 Factory Team[1,200%]
93 Aluminum Installation 23 days Sat 11/27/21 Sat 12/25/21 Project Team M[600%]
94 Handing over 5.5 days Sun 12/26/21 Sat 1/1/22 Project Eng/For,Project Team M[
95 Snag List 21 days Wed 2/2/22 Tue 3/1/22 Project Eng/For,P