Acm UNIT 1
Acm UNIT 1
Construction Industry is one of the cannonading industries of today that has a great
impact on the economy of any nation. Any piece of infrastructure or real estate
erected around us is undertaken by segments under Construction Industry. The
scope of Construction Industry is too broad.
2. The concrete bonds to the tendons as it cures, and when the tension is
transported to the construction site, which may limit their size. Pre-tensioned
elements may be incorporated into beams, balconies, lintels, floor
slabs or piles.
A set of tendons are fished through the duct and the concrete is poured. Once the
concrete has hardened, the tendons are tensioned byhydraulic jacks that react
(push) against the concrete member itself.
This method is commonly used to create monolithic slabs for house construction in
locations where expansive soils (sometimes called adobe clay) create problems for
the typical perimeter foundation. All stresses from seasonal expansion and
contraction of the underlying soil are taken into the entire tensioned slab, which
supports the building without significant flexure.
Circular slabs are more commonly used in the design of circular water tank
containers with flat bottom and raft foundations
• Normally, near the Centre of the slab, reinforcement is provided in the form
of mutually right angle mesh; and near the edge of the slab, in the form of
radial and circumferential bars.
Uses of Circular Slabs:
1.Roof of a room or hall circular in plan
2.Floor of circular water tanks or towers
3.Roof of pump houses constructed above tube wells
4.Roof of a traffic control post at the intersection of roads.
Uses:
reuse it.
posts, electric poles, block fence, etc. because moulds can be released
quickly.
• It is used for cold weather concreting because rapid evolution of heat during
distant places for placement in structural elements. Sometimes the distance can be
in many kilometers or miles. So, the effect of this transit times can reduce the
quality of concrete. Following are the various effects of transit times on Ready Mix
Concrete:
1. Loss of workability:
The concrete should always be laid in position without loss of time to avoid setting
and stiffening of concrete to reduce its workability. When the transit time is high, it
will have effect on workability of concrete. This happens due to hydration reaction
taking place when cement mixes with water, evaporation of mixed water in
While the workability of concrete depends on many factors such as the constituent
concrete. Thus, while planning for use of Ready Mixed Concrete, the aspect of loss
of workability in the likely transit time involved should be taken into account.
RMC plant and after transit time, loss of workability may be estimated.
Excessive dose may lead to segregation. In addition, there may be retardation also.
in IS: 4926-2003, are met with. Uniformity requirement specify variation limits for
properties like air content, slump, compressive strength & density etc. At site, there
concrete. Thus, it is advised that re-tempering i.e. addition of water after mixing,
should not be permitted at all either during transit or at the site of construction.
2. Setting of concrete:
When the transit time of ready mix concrete is high, the initial setting of concrete
may take place. To avoid setting of concrete, retarding admixtures can be used to
ensured that the suitability and dose of retarder is decided after conducting
conducting trials. Large quantity of admixture/ retarder may delay the setting of
admixture should be mixed at delivery site only. Addition of admixture should not
In order to control loss of workability and setting of concrete, the concrete should
be delivered completely to the site of work within one and half hours (when the
atmospheric temperature is above 200C) and within two hours ( when the
atmospheric temperature is at or below 200C)of adding the mixing water to the dry
mix of cement and aggregate or adding the cement to the aggregate whichever is
earlier.
Adequacy of the time period, required for delivery of concrete, should be checked.
In case, location of site of construction is such that this time period is inadequate,
delivery time period should be increased and specified clearly duly keeping some
margin for hurdles in the way (i.e. level crossing/ check post/heavy traffic
As explained earlier, generally admixture like water reducing agents/ retarders are
used in Ready Mixed Concrete for retention of workability and to avoid setting of
concrete. IS: 9103 “Specification for admixtures for Concrete” may be referred to
According to it, the concrete mix should be prepared both with and without
admixture using the same raw materials as proposed to be used for the work. The
(c)
Foamed concrete has a surprisingly long history and was first patented in
1923, mainly for use as an insulation material.
(f)
Lightweight and free flowing, it is a material suitable for a wide range of
purposes such as, but not limited to,
wall casting,
floating homes,
void infills,
slope protection,
outdoor furniture and many more applications.
In the light weight concrete this is done by introducing air through the
proprietary foam process which enables one to control density and
strength precisely
Normal concrete has a density of 2,400 kg/m3 while densities range from
1,800, 1,700, 1,600 down to 300 kg/m3.