Energy Analysis and Costs Estimation of An On-Shore Power Supply System in The Port of Gävle
Energy Analysis and Costs Estimation of An On-Shore Power Supply System in The Port of Gävle
ABSTRACT
The Port of Gävle is one of the most important harbours in Sweden as far as size and freight
capacity is concerned. Marine traffic is increasing greatly, thus environmental pollution as well as
noise and vibrations are of major concern in port cities. Shore to ship power supply systems might
be a feasible solution to curtail emissions because the Auxiliary Engines are instead shut down
while the ship stays alongside the quay. The literature review shows they are reliable and very
appealing in all respects, thereby contributing to sustainable development. Taking into account the
kind of vessels that call at the Port of Gävle, a High Voltage Shore Connection is recommendable,
in compliance with the International Standards. An own technical survey is developed to gather
all the information, as well as personal interviews to collect first-hand data. Technical issues such
as the synchronisation procedure and the ground system with regard to safety are briefly discussed.
Due to the lack of data, calculations consist of average values: peak and average demand, and fuel
consumption during a typical call. Considering updated energy prices for both electricity and fuel,
results show that an on-shore power supply system make energy costs decrease by 71% at berth in
comparison with burning marine fuel, which is saved by around 4 tonnes per call. Additionally,
up to 5126 tonnes of CO2 are avoided per year, among other pollutants. Shore-side power has
proven to be profitable and appealing to the Port of Gävle; however, vessels need to be retrofitted,
which implies relatively high investments. Collaboration agreements and shipping companies’
willingness to undergo changes are key issues that still need to be solved.
Keywords: On-shore Power Supply, Alternative Marine Power, High-Voltage Shore Connection,
Shore-side Power, Ship’s emissions, Marine fuel.
PREFACE
My special gratitude goes to Niklas, who has been overseeing my work during the development
of the thesis in the Port of Gävle. I am grateful to Linda and Pontus, who relied on me to set out
on the first steps of the project. It was fantastic to have the opportunity to work in your facilities
and in such a new environment for me.
I am also grateful to Arman, my thesis supervisor at the University of Gävle, for offering me the
possibility of working out my thesis in the Port of Gävle.
Finally, last but not least, also to my fellow students in Gävle, with whom I have had so much fun
during my Erasmus stay.
NOMENCLATURE
AE Auxiliary Engines
AMP Alternative Marine Power
CARB California Air Resources Board
CHE Cargo Handling Equipment
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
IMO International Maritime Organization
ISO International Organization for Standardization
EF Emission Factors
GT Gross Tonnage
HFO Heavy Fuel Oil
HVSC High-Voltage Shore Connection
LNGC Liquefied Natural Gas Carriers
LVSC Low-Voltage Shore Connection
MCR Maximum Continuous Rating
MDO Marine Diesel Oil
ME Main Engine
MEPA Marine Exchange/Port Authority
MGO Marine Gasoil
OGV Ocean-Going Vessel
OPS On-shore Power Supply
PIC Person in Charge
PMx Particulate Matter
PoLA Port of Los Angeles
PoLB Port of Long Beach
Ro/Ro Roll-on/Roll-off
RSZ Reduced Speed Zone
SECA Sulphur Oxide Emission Control Areas
SFOC Specific Fuel Oil Consumption
CONTENTS
1. INTRODUCTION 8
1.1. Background 8
1.2. Aim 8
2. METHOD 9
3. RESULTS AND DISCUSSION 10
3.1. Existing installations: a market review 10
3.1.1. Port of Gothenburg 10
3.1.2. Port of Stockholm 11
3.1.3. Port of Los Angeles 11
3.1.4. Port of Bergen 11
3.1.5. Other ports 12
3.2. Other matters of interests 12
3.2.1. Alternative Marine Power program 12
3.2.2. OPS Master Plan in Spanish Ports 12
3.3. Standards and regulations 13
3.3.1. Reference International Standards 13
3.3.2. Complementary regulations 13
3.3.3. Directives and recommendations 14
3.3.4. Discussion 15
3.4. Design configuration 16
3.4.1. Docking patterns 17
3.4.2. Possible shore-side configurations 17
3.5. Vessels register 19
3.5.1. Vessels activities in the Port of Gävle 19
3.5.2. Container terminal 21
3.5.3. Energy terminal 22
3.6. On-board power systems 23
3.6.1. On-board generation and distribution 23
3.6.2. Other ports statistics: a literature review 25
3.6.3. Power demand at the quay in the event of an OPS system 26
3.6.4. Synchronisation 27
3.7. Technical survey 28
3.7.1. Container terminal 28
3.7.2. Energy terminal 29
3.8. Energy prices 29
3.8.1. On-shore electricity prices 29
3.8.2. Fuel types and prices 30
3.9. Design parameters for an OPS system 31
3.10. Energy costs and savings 32
3.11. Emissions 33
3.11.1. Emission reduction estimation 33
3.11.2. Emission factors 34
4. CONCLUSIONS 36
5. REFERENCES 38
APPENDIX 44
1. INTRODUCTION
The current project has been carried out during the months of April and May of 2019, in the
offices of the Port of Gävle. This thesis is the front-end part of a broader project in collaboration
with the University of Gävle (HiG). The basis of the investigation has to be settled somehow on it
as there are many questions to be examined.
1.1. Background
Freight traffic is strongly rising worldwide despite the economic stagnation. Globalization together
with the growing trade and economic relations have led to an increase in the number of ships,
namely cargo ships and large ferry vessels [1] [2] [3]. This implies greater air pollution and
becomes of paramount importance for the port cities, as far as ship’s mooring is concerned. Local
air and water pollution as long as noise and vibrations pose a threat for persons, plants and the
environment [4] [5] [6]. Shore-to-ship power supply systems have the potential to limit all that
negative impact, by means of connecting the vessels to the on-land electricity grid, which
electricity is expected to be generated in a sustainable manner [7]. An On-shore Power Supply
(OPS) system may contribute to sustainable development as long as overall emissions are
reduced [8]. Energy efficiency increases because primary energy sources are not mainly based on
fossil fuels and also the power demand is reduced as a result. However, there are many aspects to
be examined because each case involves specific aspects. General concerns have still to be deeply
studied as well.
1.2. Aim
As this project is barely a preliminary study, all sort of information may be useful for it or for
further studies. A potential On-shore Power Supply system in the Port of Gävle is determined by
the energy costs and fuel savings, which obviously depend on the ship’s parameters and type of
activity. That OPS system is intended to be installed only and for the moment in the Container
terminal and in the Energy terminal [9]. Consequently, results shown in this report are related to
these two terminals and the vessels that ever stay alongside their quays. The purpose of this thesis
requires several tasks to be undertaken, and they are described in the following bullet points.
a. Literature review about other existing OPS systems that have been carried out in relevant
ports, including a review of regulations and international standards to be applied in the Port
of Gävle.
b. Statistics of vessels calling at the Port of Gävle: number of calls and time at berth.
c. Review of on-board power systems, fuel consumption and emissions of container ships
and tankers calling at the Port of Gävle.
d. Brief review of main technical issues and factors that must be taken into account.
e. Brief review of energy prices: shore-side electricity and fuels.
f. Estimation of energy costs, fuel saving and emission reduction based on the above tasks.
g. Recommendation of a shore-ship connection configuration.
2. METHOD
In this section, how each of the tasks shortlisted in the previous chapter and carried out is described.
Although the time dedicated to collect information takes longer than calculations, final
estimations are paramount and the key purpose of this thesis. On-shore power supply systems
have not been widely investigated, therefore to support recommendations and a design
configuration for the Port of Gävle is not easy. Not a lot of papers on this matter have been
published; hence, this report cannot be based on a pure literature study. Peer-reviewed papers
comprise not only general issues about on-shore power supply systems, but also technical
problems approaching fuel consumption and emissions calculation, or ship-to-shore power
synchronisation. In fact, International Standards relied upon some of these papers. Conversely,
reports, personal interviews and practical and real installations are instead even more
meaningful for this project [10] [11] [12] [13] [14] [15] [16]. To receive first-hand information
boosts the accuracy of calculations and supports any further suggestions strongly.
Literature review has been conducted through interviews and conversations with port managers
and authorities, who also provided additional information consisting of internal studies and reports.
Most of them were relevant for the project, and so have they been included in the current report;
however, some were discarded. At the same time, an own questionnaire surveying several ships
that called at the Port of Gävle is used to reinforce the input data (so-called Technical Survey); it
is based on [17]. This survey is key for the calculations and estimations, since they consist of direct
values and opinions from on-board engineers that are closely familiarised with operational issues
(APPENDIX).
In order to carry out estimations, average data are considered to be accurate enough. For instance,
average time at berth and average power demand at berth for vessels are significant values and
core elements in the report. The timeframe taken ranges from January 2017 to March 2019.
However, there are many vessels calling at the Port of Gävle, and to gather all the information for
each one of them is neither easy nor quick. Other sources of information, consisting of case studies,
technical equivalencies between vessels and the results found in the literature, are thereby used to
support the calculations and to allow the project to be finished within the scheduled time.
The economic analysis is quite simple due to a lack of detailed data. Shore-side electricity prices
and fuel cost for vessels are considered constant. Looking over the past, it makes no sense to
discuss future prices because trends do not have a clear correlation. Hence, costs are estimated
using average data.
from 1,5 MVA for Ro/Ro ships to 15 MVA for cruise ships. Every ship call among 2010 and
forecasted berthing for 2011, organised by terminal, is taken into account to justify the
calculations. Costs included are the following: running costs for electricity generation on-board
and on-shore, investment costs for OPS, environmental costs (air pollution and CO2), and costs of
retrofitting. There is not any OPS for the container, cruise, or tanker segments
Provided the estimations, results delivered show that only a couple of terminals seem profitable if
an OPS is installed (partially and fully). Namely, the Ro/Ro- and the Car transport ships terminal.
These results may not be appealing for the Port of Gävle, considering the primary OPS system
would be installed in the Energy terminal (tankers) and the Container terminal (container ships).
However, an analysis needs to be undertaken with calculations for a practical case. Existing
installations have arisen due to single co-operation between ports and shipping companies. If a
broader OPS installation takes place, how the costs are to be distributed (between ports and
shipping companies) needs to be clarified. Moreover, flexible equipment to supply at both 50 Hz
and 60 Hz has not been considered in the study, which can open up the range of vessels using the
OPS.
studies in order to identify existing barriers and outline solutions [37]. In its database, many
relevant references are accessible for the general public, including technical and real life solutions.
IEC 62613 addresses the needs in terms of plugs, socket-outlets and ship couplers (ship connectors
and inlets), of the IEC/ISO/IEEE 80005-1:2016, therein referred to as “accessories”. This standard
specifies requirements that allow compliant ships to connect to compliant high voltage power
systems through a compatible shore-to-ship connection.
IEC 60092-101:2018 – Electrical installations in ships. Part 101: Definitions and general
requirements. [43]
IEC 60092-503:2007 – Electrical installations in ships - Part 503: Special features - AC supply
systems with voltages in the range of above 1 kV up to and including 15 kV. [44]
3.3.4. Discussion
Taking into account the new LVSC standards [41], it is not recommendable to have more than 5
cables and sockets in LVSC, and that poses a problem when supplying high power is required. As
a result, a solution suggested by environmental managers and electricity technicians in the ports
contacted consists of having the power station on board the vessels. That would be theoretically
easy to apply in container vessels, as the installation would be integrated in a single container and
the two HV socket-outlets would be accessible at the lar- or starboard of the vessel. Container
vessels seldom carry their maximum capacity, thereby this solution is likely to be implemented.
Standards push forward HVSC, and having an on-board power station seems the most
reasonable solution to turn a LVSC into a HVSC. Most current vessels are not equipped with any
socket-outlet for shore connection, thus leading inevitably to some kind of retrofitting. It seems
easier to develop a standardised solution for the mentioned integrated power station on board
container ships, than trying to plug them in LV. Once a vessel carries its own power station, the
connection procedure is quicker and safer [54].
With regard to tankers, an analogous procedure is often hindered by problems of space, i.e. the
vessels need to be retrofitted case by case. Moreover, the standards suggest specific requirements
for tankers and Liquefied Natural Gas Carriers (LNGC) due to security issues. The control
and monitoring cable management system must be separated from the plug (shore-side) and
socket-outlet (on-board), which means separated cable arrangements are needed for each vessel.
Three cables are to be plugged in tankers, but only one in LNGC [39]. If an area contains electrical
equipment that is not of safe type, certified or approved by a competent authority for the gases or
combustible dust encountered, the such equipment may have to be isolated by the time the tanker
is at the quay [39] [41].
One aspect of major concern for the standard is the issue of human safety. Both port authorities
and ship-owners are concerned with the possibility of injuries or deaths related to power
connection. Strict shore connections and technical solutions must allow smooth dockside
operations and safe cable handling. The standard requires the use of a mechanical securing device
that locks the connection in the engaged position. This plug and socket-outlet is sometimes called
as a Kirk key interlock device, and the power plug/socket contacts sequence shall be as specified
in [55]. To comply with the regulations, each port must have its own written procedures and
training for operators undertaking safe cold-ironing operation. For instance, PoLA unveiled its
connection procedures in 2014 [21].
Figure 3. Docking patterns in the current Container terminal in the Port of Gävle.
by the International Standards for each type of vessel; however, the docking patterns may be
particularly unlikely to affect in the Port of Gävle. According to the European Commission
Recommendation, voltage level ranges are limited [50]; however, the final configuration is open
to distribute the cables either in AC or DC and the place to install the power converter is also
flexible (Figure 4).
Three main possible topologies are widely discussed in the study carried out by I. Fazlagic and P.
Ericsson [18], and the summary of advantages and disadvantages is shown in Table 1. In that
report, the Configuration 2 is recommended to be implemented in a whole big port. However, the
Port of Gävle has only a few berths and the project will start out in the Container terminal and the
Energy terminal. Therefore, the Configuration 1 seems more likely in this case.
Table 1. Summary of advantages and disadvantages for different configurations [18].
Every vessel calling at the Port of Gävle is recorded. In this report, vessels berthing in the
Container terminal and in the Energy terminal from January 2017 to March 2019 are
considered. Ships often change their names, which means the same vessel is visiting the same port
but is not clearly registered. This has been considered and the following results are proper. Every
vessel has associated a unique IMO number that allow them to be tracked. The number of
container ships and time they are berthed varies significantly from year to year, as Figure 6
illustrates.
5811 1800
Time at berth until 31st March (h)
6000
1539
4891 1600
5000 1307
Total time at berth (h)
1400
4000 1200 1077
1000
3000
800
2000 600
1000 400
200
0 0
2017 2018 2017 2018 2019
Year Year
Figure 6. Total time at berth, left. Time at berth until March 31st, right (Container terminal).
In short, only 12 vessels are berthed alongside the port during more than 90% of the time, with an
average time at berth of 30,9 h. Data dispersion throughout time berthed for each vessel is narrow,
as most of calls range from 20 to 40 hours. For instance, the following figures illustrate the time
at berth per call for the vessels ANNABA, OOCL RAUMA and VERA RAMBOW (Figure 7,
Figure 8, Figure 9).
100
90 90,7
80
70
Time at berth (h)
60
50
40
30
20
6,9
10
0
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55
Calls
Figure 7. Time at berth per call for ANNABA vessel.
100
93,6
90
80
70
Time at berth (h)
60
50
40
30 22,1
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Calls
Figure 8. Time at berth per call for OOCL RAUMA vessel.
110 102,0
100
90
80
Time at berth (h)
70
60
50
40
30 19,0
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Calls
Figure 9. Time at berth per call for VERA RAMBOW vessel.
However, the total time at berth for these vessels does not represent a significant percentage, as
illustrated in Figure 10 and Figure 11.
225
200
175
Total time at berth (h)
150
125
100
75
50
25
0
5
33
61
89
117
1
9
13
17
21
25
29
37
41
45
49
53
57
65
69
73
77
81
85
93
97
101
105
109
113
Tankers
Figure 10. Total time at berth per vessel in Energy terminal.
100
90 186,3
80
Average time at berth (h)
70
60
50
40
30
20
10
0
9
93
1
5
13
17
21
25
29
33
37
41
45
49
53
57
61
65
69
73
77
81
85
89
97
101
105
109
113
117
Tankers
Figure 11. Average time at berth per vessel in Energy terminal.
Figure 12. On-board power systems for conventional propulsion vessels [58].
Figure 13. On-board power systems for Diesel-electric propulsion vessels [58].
In view of the changes of the market (bigger ships and development of power electronics), new
vessels are increasingly using diesel-electric propulsion systems [7] [34] [59]. The vessels calling
at the Port of Gävle are expected to include conventional electric-drive power systems. In any case,
issues concerning an OPS and the socket-outlet on board are only practical, i.e. the OPS associated
switchgear only has to supply electricity to the Service Loads of the AE while the ships are berthed
alongside the quay.
System frequency in the vessels is mainly 60 Hz, but the amount of vessels using 50 Hz is not
negligible. The idea of creating an OPS exclusive on-land power plant to supply electricity at a
different frequency from the one that the existing in-land grid has, has not been reported yet.
Therefore, supplying electricity to vessels at both frequencies implies the use of a power
electronics converter.
3.6.4. Synchronisation
The shore-to-ship connection must be controlled at every time. According to the International
Standards, the transition from ship-side to shore-side supply must be smooth, which means that
power tripping, voltage dips, surges and overloads should be avoided [39] [40] [41]. If any of these
events occurs, the threat of a blackout might happen [60]. The ground system becomes therefore
a critical part of the design, as discussed below.
a. The blackout problem
A blackout is an unexpected power disconnection that may damage some electronic devices,
which would need to be replace, taking up time and money. This situation may be due to a
malfunctioning of protection relays, transient overcurrent and short-circuits, unpredictable
transient surges, or failure in shore-to-ship power synchronisation. On-board chief engineers are
very concerned about this problem, and the best way to solve it consists of the development of a
plug-and-play solution [11] [12]. When the power required in LV is high (greater than 750 kVA),
up to 5 single cables are needed according to [41]. A limit of 5 cables is recommended for
supplying LV power, 2 cables for HV containers, 3 cables for HV LNGC and 1 cable for HV
tankers [39] [41]. Cables have standardised cross section and their current rating depend on the
type of cable, its operating conditions and its working environment. Aluminium or copper cables
can be used, being aluminium cables more suitable in this case because they are lighter and
expected to be winded and unwinded quite often [61].
b. Ground system and other issues of concern
In order to avoid a blackout, several considerations must be addressed. In LVSC, phase-ground
faults are limited by using a neutral grounding resistor, which is continuously monitored and the
protection relays automatically trip shore-side supply in case the monitoring is lost.
High-resistance grounded (HRG) systems prevent high fault currents and the neutral resistor may
be sized as a 5 A continuous, as it is recommended in [41] and discussed in [60]. Although an
ungrounded power system is not recommended (IT configuration), the International Standards
allow it. In [60], a sized 2 A continuous neutral resistor is recommended. Furthermore, Port
Authorities may require vessels to equip on-board isolation transformers instead of a neutral
disconnect switch. In HVSC, ungrounded power system is not allowed. In any case, a
phase-ground fault can create a touch voltage exceeding 25 V in LVSC and 30 V in HVSC [39]
[41]. Finally, safety loop controls must be tested in order to assure the safety of the operators
during the shore-to-ship connection procedure [62].
According to the International Standards, the HVSC system design should also consider harmonic
distortion and line voltage drops, among others. Magnitudes of these issues are evaluated and
discussed in [61]. On the one hand, voltage drops increase with the power demand and the length
of cables. Likewise, voltage drops decrease when the power factor (cos phi) and the cable cross
section are increased, as it is expected looking over the theory. Results included in this paper
provide candidates of power cables for HVSC systems that comply with the International
Standards, depending on the cable length requirements.
The operating life and the load cycle of the engines make a little difference, although these data
are acceptable in this case [63]. Average data within surveyed sister vessels have been used to
extend results to their non-surveyed sister vessels. Blanks for those vessels whose data are not
available have been inferred by calculating the average values from the rest of vessels. As it has
been mentioned before, the average power at the quay in the case of a potential OPS system has
been calculated by multiplying the average power at the quay for each vessel by a 0,60 coefficient.
1
OOCL RAUMA, BALTIC PETREL and VERA RAMBOW: chartered by Unifeeder.
ESSENCE and AMERDIJK: chartered by MSC.
The peak power at the quay depends mostly on the reefers carried, and the peak power in a
potential OPS system would not be so high, due to the same arguments stated. However, this drop
would not be so significant in that event and, therefore, any reduction coefficient has been
considered. Parameters and power demand are shown in Table 4 and Table 5.
Table 5. Container ships fuel consumption and power demand at the quay.
2
Shipping Company based in Gothenburg.
fixed charges. For the calculations made in this report, an electricity price of 0,70 SEK/kWh is
considered.
0,90
Average electricity price
0,80
0,70
0,60
(SEK/kWh)
0,50
0,40
0,30
0,20
0,10
0,00
terms of the GT value. Table 6 provides the IVL report values and those obtained through the
Technical Survey, which match reasonably well.
Table 6. Fuel consumption in comparison to IVL report values.
Provided the information obtained from previous sections, it is possible to estimate fuel costs for
an average container ship calling at the Port of Gävle and the electricity costs for a potential
shore-side supply. As Table 9 shows, these values only comprise operational costs for the
Container terminal. Results are expressed in per call, which make overall calculations easier, due
to the fact that the number of vessels and time they are berthed varies significantly from year to
year. Using the OPS system, energy costs decrease by 71% at berth (from 19919 SEK to
4022 SEK). Additionally, 3984 kg of MGO are saved per call on average, thereby eliminating
associated noise and emissions, which are estimated further on. Vessels navigate different routes,
but they usually call at the same ports during a few years. This implies a different number of calls
and average time at the quay for each vessel. There is no doubt that profitability is higher for ships
if they use the OPS system as many times as possible, and also energy prices are different in each
port. Consequently, this report does not carry out any payback calculations for the vessels.
Table 9. Fuel consumption and electricity costs for an OPS system in the Container terminal.
3.11. Emissions
In this final section, ship’s emissions are addressed.
Table 11. Summary of the total estimated emissions in the Port of Gävle in 2017.
Data obtained from the Technical Survey are not comprehensive enough to carry out an accurate
calculation on emissions. As it has been described before, most container ships are quite similar.
As long as all the vessels considered above (90% of the time at the quay) undertake the necessary
retrofitting, a significant reduction in the associated emissions is expected. To multiply 90% by
the % of emissions above the total at the quay, an acceptable estimation on emissions is obtained.
Results included above in Table 11 are used and compared in Table 12 below. To summarise, a
potential OPS installed in the Container terminal and connected to 90% of container ships at the
quay avoids emissions that are estimated in: 5126 tonnes of CO2, 72 tonnes of NOx, 0,36 tonnes
of PMx and 2,7 tonnes of SOx each year.
Table 12. Estimated emissions on an OPS system in the Container terminal.
4. CONCLUSIONS
Looking back to the tasks that were intended to be carried out at the beginning of the project, most
of them have been addressed with satisfaction. As the project goes on, the tasks and the schedule
may undergo changes. Due to a lack of information but namely time, a design configuration has
not been recommended. It is expected that further studies within the project undertake an in-depth
analysis on the shore-side configurations.
The current thesis has analysed input data with regard to vessels calling at the Port of Gävle: power
systems, fuel consumption and emissions, among others. According to available input data, the
OPS system and the estimations have only been considered in the Container terminal, putting the
Energy terminal on the back burner. 12 container ships stay alongside the quay during 90,1%
of the time; therefore, a reasonable decision for a potential OPS system would be to retrofit only
these vessels. A typical call lasts 30,9 h on average, seldom less than 20 h, which means that the
time required to carry out the connection procedure is negligible. The Energy terminal is an
EX-classified area and handles large amounts of liquid bulk with fire hazards that require to be
carefully addressed in further projects. Furthermore, the International Standards do not include
very detailed procedures for HazLocs in ports, that need to be further developed.
Existing HVSC in other ports have proven to be useful, mainly those that have been installed
recently and according to the International Standards. Most LVSC were carried out as pilot
projects, thereby evincing LVSC cannot become very widespread due to practical issues.
Moreover, HVSC have been studied deeper than LVSC, in line with the needs of the market. In
the Port of Gävle, container ships’ power demand is such that a HVSC is highly recommended.
This is a big decision because it affects both technical and practical issues of the shore-side
installation. A connection point on the quay in the Container terminal shall supply 1250 kVA at
a voltage level of 6600 V, which means the vessels shall carry their own power transformer. The
electricity shall be supplied at either 50 Hz or 60 Hz, according to the vessels’ electrical systems.
Therefore, the installation of a power converter somewhere is mandatory (obviously shore-side).
A few configurations have been discussed but none of them is suggested as the design
configuration because of the need of a more comprehensive analysis of the shore-side installation.
With regard to the Technical Survey, the own questionnaire was expected to be filled out by more
vessels. Estimations of power demand and fuel consumption at the quay have been carried out
taking data from sister vessels and other studies conducted by other port authorities. As a result,
calculations cannot be more accurate and average data have been used instead. An interesting
result of an OPS system is the reduction of the power demand at berth due to the AE shut down,
which has been estimated in a 40%. The problem of a blackout, of big concern for the on-board
Chief Engineers, is yet sorted out as long as the installations are built in compliance with the
International Standards.
3984 kg of MGO (<0,1% S) are saved per call on average, which implies that energy costs
decrease by 71% at berth (from 19919 SEK to 4022 SEK) in an OPS system. MGO and electricity
prices are constant for those calculations: 500 $/ton and 0,70 SEK/kWh, respectively; a trend for
future prices could not be found due to high variations during the past years. Looking over the
investment costs, yearly costs result in 620.000 SEK/year for a typical container ship calling at
the Port of Gävle (1500 kVA), considering an interest rate of 6% and a depreciation of 10 years.
The OPS system likeability depends on energy prices and investments, but namely on the vessels’
willingness to undergo changes. There are two complementary arguments that stand for and
against in that regard. On the one hand, the Port of Gävle requires a minimum number of vessels
to be willing to be plugged at berth to carry out any investments on a shore-side installation. On
the other hand, vessels require to be connected to shore power in as many ports as possible. Therein
lies the main hindrance to the project. Port Authorities and shipping companies need to strive and
work hand in hand to make steps forward. Moreover, governments and competent authorities
should encourage all the parties involved to boost OPS systems, by means of collaboration
agreements or new regulations on the field.
Finally, a potential OPS system installed in the Container terminal and connected 90% of the time
at the quay avoids emissions that are estimated in: 5126 tonnes of CO2, 72 tonnes of NOx,
0,36 tonnes of PMx and 2,7 tonnes of SOx each year. Noise and vibrations are also directly
reduced, although they have not been quantitative identified. The emission reduction estimation is
significant, which encourages other ships, i.e. tankers and cargo ships, to be shore-side supplied.
They are expected to be more difficult to retrofit, though, and also the shore-side facility. The
highest emissions occur at the quay due to the time the ships are berthed; however, emissions while
manoeuvring and sailing through the fairway are not negligible and need to be addressed.
In conclusion, an OPS system in the Port of Gävle has proven to be committed to sustainable
development and inclusive growth, due to a more efficient use of resources and energy. The Port
of Gävle expect to carry on with the project in order to start out their first OPS system in the near
future. Hopefully, this thesis can serve to undertake that further project as soon as possible.
Future outlook
Several research projects may be addressed to follow up, since this report is a first approach to the
installation of a potential OPS system in the Port of Gävle. One interesting starting point is to strike
up conversations with shipping companies and ship owners in order to come up to agreements
with regard to their willingness to carry out the vessels’ required retrofit. Likewise, other Port
Authorities may be looking forward to know about OPS systems as well and they might study the
shore-to-ship power supply feasibility in their berths. The Baltic Sea is indeed an intensive
shipping area and ships usually sail routes within Baltic ports. On account of that, collaboration
agreements seem reasonably easy to reach. Focusing on the Port of Gävle, a more comprehensive
study on fuel savings at berth might be useful in relevant ships, as part of the collaboration, leading
to case studies. Not only container ships, but also tankers and cargo ships, which have not been
examined in this thesis. Moreover, challenges related to the Energy terminal need to be discussed,
since this area is EX-classified because it handles large amounts of liquid bulk with fire hazards.
5. REFERENCES
[1] Danish Ship Finance, «Shipping Market Review,» DSF Publications, Copenhagen,
Denmark, 2018.
[2] B. Dragovic et al., “Ship emissions and their externalities in cruise ports,”
Transportation Research, vol. D, no. 61, pp. 289-300, 2018.
[4] J. J. Corbett et al., «Mortality from ship emissions: a global assessment,» Environmental
Science and Technology, vol. 41, nº 24, pp. 8512-8518, 2007.
[5] Y. Zhang et al., “Shipping emissions and their impacts on air quality in China,” Science
of the Total Environment, no. 581-582, pp. 186-198, 2017.
[6] M. Viana et al., “Impact of maritime transport emissions on coastal air quality in
Europe,” Atmospheric Environment, vol. 90, pp. 96-105, 2014.
[7] T. Borkowski and D. Tarnapowicz, “Shore to ship system: An alternative electric power
supply in port,” Journal of KONES Powertrain and Transport, vol. 19, no. 3, pp. 49-58,
2012.
[8] X. Yang et al., “Shore to ship converter system for energy saving and emission
reduction,” in 8th International Conference on Power Electronics - ECCE Asia, The
Shilla Jeju, South Korea, 2011.
[10] BALTIC PETREL Chief Engineer, Interviewee, On-board visit. [Interview]. 11th April
2019.
[11] ESSENCE Chief Engineer, Interviewee, On-board visit. [Interview]. 17th April 2019.
[12] OOCL RAUMA Chief Engineer, Interviewee, On-board visit. [Interview]. 4th April
2019.
[13] VERA RAMBOW Chief Engineer, Interviewee, Conversation via email. [Interview].
April 2019.
[14] TERNSUND Chief Engineer, Interviewee, Conversation via email. [Interview]. April
2019.
[15] C. Solerud, Interviewee, Conversation via telephone. [Interview]. 29th April 2019.
[16] S. Yanes (Facilities Manager), Interviewee, Conversation via email. [Interview]. May
2019.
[17] California Air Resources Board, «Ocean-going ship survey - Summary of results,»
CARB Publications, California, 2007.
[18] I. Fazlagic and P. Ericsson, “Shore-side power supply: a feasibility study and a technical
solution for an on-shore electrical infrastructure to supply vessels with electric power
while in port,” MSc Electric Power Engineering, Chalmers University of Technology,
Göteborg, Sweden, 2008.
[19] Port of Gothenburg and ABB, “Preconditions for connecting ships to Onshore Power
Supply in the Port of Gothenburg,” Port of Gothenburg Publications, Gothenburg,
Sweden, 2012.
[20] S. Doves, “AMP in the port of Rotterdam: a feasibility study into the use of shore-side
electricity for containerships,” Port of Rotterdam Authority, Rotterdam, 2006.
[21] Port of Los Angeles: Construction and Maintenance Division, General High Voltage
Shore Connection Procedures, Los Angeles: PoLA, 2014.
[22] Schneider Electric, “Schneider Electric ShoreBox,” 11th December 2017. [Online].
Available: https://download.schneider-
electric.com/files?p_enDocType=Brochure&p_File_Name=COM-SHORE-
REF1EN_Berguen_web.pdf&p_Doc_Ref=COM-SHORE-REF1EN. [Accessed April
2019].
[24] Siemens AG, “Shore connection system for berthed ships SIHARBOR,” 2017. [Online].
Available:
https://w3.siemens.com/powerdistribution/global/SiteCollectionDocuments/en/mv/pow
er-supply-solutions/onshore-power-supply/brochure%20SIHARBOR_en.pdf.
[Accessed April 2019].
[25] ABB, “Shore-to-ship power and Smart ports,” 19th April 2017. [Online]. Available:
https://search-
ext.abb.com/library/Download.aspx?DocumentID=9AKK10103A1196&LanguageCod
e=en&DocumentPartId=&Action=Launch. [Accessed April 2019].
[26] Port of Los Angeles, “Alternative Marine Power in the Port of Los Angeles,” [Online].
Available: https://www.portoflosangeles.org/environment/air-quality/alternative-
maritime-power-(amp). [Accessed April 2019].
[27] Stena Line Scandinavia AB, “Stena Line Freight,” [Online]. Available:
https://www.stenalinefreight.com/home. [Accessed April 2019].
[29] Sveriges Hamnar, “Anslutning av elektricitet till fartyg vid kaj,” Sveriges Hamnar,
Stockholm, Sweden, 2016.
[30] AECOM, “Shore power feasibility study Ogden Point,” Greater Victoria Harbour
Authority Publications, Victoria, Canada, 2013.
[31] E-Cubed Consultants Ltd and Cyan Engineering Ltd, “Feasibility Study: Into the
possibility of shore-side electrical supply for berthing vessels within Maltese harbours,”
Malta National Electromobility Platform Publications, Malta, 2014.
[32] ENVIRON International Corporation, “Shoreside power feasibility study for cruise ships
berthed at Port of San Francisco,” Port of San Francisco Publications, San Francisco,
USA, 2005.
[33] G. Liao et al., «Study on intelligen Low-Voltage shore power charging pile in inland
port,» de Proceedings of the 36th Chinese Control Conference, Dalian, China, 2017.
[34] D. Paul et al., «Shore-to-Ship Power Supply System for a Cruise ship,» de Annual
Meeting of the IEEE Industry Applications Society , Houston, USA, 2009.
[35] MariTerm AB, “Shore-side electricity for ships in ports,” MariTermAB Publications,
Gothenburg, 2004.
[36] California Air Resources Board, “Shore power for ocean-going vessels,” [Online].
Available: https://www.arb.ca.gov/ports/shorepower/shorepower.htm. [Accessed May
2019].
[37] Ministery of Industry, “OPS Master Plan in Spanish Ports,” [Online]. Available:
http://poweratberth.eu/?page_id=1219&lang=es. [Accessed April 2019].
[38] Juxiang HE et al., “Review and discussion on Standards for shore-to-ship power supply
system,” Advances in Engineering Research - ICMEA, vol. 146, pp. 22-26, 2017.
[45] E. Parliament, Directive 2005/33/EC of the European Parliament and of the Council,
Brussels, 2005.
[46] E. Parliament, Directive 2012/33/EC of the European Parliament and of the Council,
Brussels, 2012.
[47] E. Parliament, Directive 2016/802 of the European Parliament and of the Council,
Brussels, 2016.
[49] E. Parliament, Directive 2014/94/EU of the European Parliament and of the Council,
Brussels, 2014.
[54] S. Yan Qiong et al., “Technology of uninterruptable shore-side power supply for berthing
vessels and its application,” in 3rd International Conference on Advances in Energy and
Environmental Science, Zhuhai, China, 2015.
[56] K. Bailey and L. Browning, “Current methodologies and best practices for preparing port
emission inventories,” ICF Consulting, Washington D.C., 2006.
[57] UNCTAD, Review of Maritime Transport, New York and Geneva: United Nations
Publication, 2017.
[58] K. Valkeejärvi, “The ship's electrical network, engine control and automation,” Royal
Belgian Institute of Marine Engineers, Brussels, 2016.
[59] E. Skjong et al., “Past, present and future challenges of the marine vessel's electrical
power system,” IEEE Transactions on Transportation Electrification, p. 16, 2016.
[60] D. Paul et al., «Low-Voltage Shore Connection Power Systems: optional designs and a
safety loop circuit,» IEEE Industry Applications Magazine, pp. 62-68, 2018.
[61] M.-H. Chou et al., «Voltage-drop calculations and power cable designs for harbor
electrical distribution systems with High Voltage Shore Connection,» IEEE
Transactions on Industry Applications, vol. 53, nº 3, pp. 1807-1814, 2017.
[62] L. Pan et al., “Control research on electrical system of intelligent low voltage shore side
electric pile for river port,” in Proceedings of the 37th Chinese Control Conference,
Wuhan, China, 2018.
[63] F. Baldi et al., “Energy and exergy analysis of a cruise ship,” in Proceedings of the 28th
International Conference on Efficiency, Cost, Optimisation, Simulation and
Environmental Impact of Energy Systems, Pau, France, 2015.
[64] Invest in Gävleborg - Region Gävleborg, Data center brochure, Gävle: Region
Gävleborg Publications, 2019.
[65] Livebunkers, «What is the difference between MDO and MGO?,» [En línea]. Available:
http://livebunkers.com/what-difference-between-mdo-and-mgo. [Último acceso: April
2019].
[66] DNV-GL, «Det Norske Veritas group,» 29th October 2015. [En línea]. Available:
https://www.dnvgl.com/news/upcoming-environmental-regulations-for-emissions-to-
air-imo-nox-tier-iii-45479. [Último acceso: 3rd May 2019].
[68] IVL Swedish Environmental Research Institute, “Emissions from traffic to and from the
Port of Gävle in 2017,” IVL Publications, Stockholm, 2017.
[69] TrainMoS Global Project, On Shore Power Supply and LNG, Glasgow: On the MoS way
Publications, 2015.
[70] M. Simonsen et al., «Model for estimation of fuel consumption of cruise ships,»
Energies, vol. 11, nº 5, p. 1059, 2018.
[71] International Association of Ports and Harbors, “WPCI IAPH World Ports,” [Online].
Available: http://wpci.iaphworldports.org/onshore-power-supply/what-is-ops/.
[Accessed May 2019].
[72] L. Johansson et al., “Global assessment of shipping emissions in 2015 on a high spatial
and temporal resolution,” Atmospheric Environment, vol. 167, pp. 403-415, 2017.
[73] International Maritime Organization, “Third IMO GHG Study,” IMO, Suffolk, United
Kingdom, 2014.
[75] CLEANSHIP EU, “Clean Baltic Sea Shipping,” Port of Trelleborg Publications,
Trelleborg, 2013.
[76] A. Ritchie, “Service contract on ship emissions: assignment, abatement and market-
based instruments,” Entec UK Limited Publications, Northwich, 2005.
[77] J. Moreno-Gutiérrez et al., “Methodologies for estimating shipping emissions and energy
consumption: A comparative analysis of current methods,” Energy, vol. 86, pp. 603-616,
2015.
APPENDIX
Table A 1. Container terminal vessel register (Jan 17’ – Mar 19’).
Division Name:
Email Address:
Type of Business: ☐ Auto Carrier/Ro-Ro ☐ Bulk Carrier/General Cargo ☐ Container Ship ☐ Motor Ship/Container
☐ Passenger ☐ Product Carrier ☐ Reefer ☐ Tanker
Signature: Date:
SHIP INFORMATION
Vessel Country Voltage
Lloyds/IMO #
Name Flag (V)
Vessel Date Ship Electrical Frequency
Type Built Power (kVA) (Hz)
Gross Net Deadweight (metric
Tonnage (GT) Tonnage (GT) Tonnage (GT) tons)
(metric
Average Daily Fuel Consumption at Normal Cruise Speed at Sea
tons)
(metric
Average Daily Fuel Consumption from ship berthed alongside the quay (hoteling)
tons)
Average Daily Fuel Costs from ship berthed alongside the quay (hoteling)
Direct Drive Main Engine/s (Note: for diesel-electric/generator-set engines on cruise ships, etc. pleas list under “auxiliary engines” below)
Number Engine If diesel engine,
☐ Diesel piston ☐ Gas turbine ☐ Steam turbine ☐ 2-stroke ☐ 4-stroke
of ME Type: type?
Date
Make
Built
Rated Power
Model ☐ kW ☐ hp RPM at MCR
at MCR
Fuel ______ % Fuel ______ %
☐ Residual ☐ Distillate ☐ Residual ☐ Distillate
Used #1 S Used #2 S
Average cruise power at Average cruise speed at
☐ kW ☐ hp (Knots)
sea sea
Please describe any engine modifications completed to either improve fuel efficiency or reduce emissions (e.g., slide valves, fuel injectors):
AUXILIARY ENGINES (and all diesel-electric engines, whether for ship propulsion or on-board power). Exclude emergency/standby engines.
Engine #1 Engine #2 Engine #3 Engine #4 Engine #5 Engine #6
Make
Model
Date Built
Rated Power at ☐ kW ☐ kW ☐ kW ☐ kW ☐ kW ☐ kW
MCR ☐ hp ☐ hp ☐ hp ☐ hp ☐ hp ☐ hp
☐ Turbine ☐ Turbine ☐ Turbine ☐ Turbine ☐ Turbine ☐ Turbine
☐ Diesel piston ☐ Diesel piston ☐ Diesel piston ☐ Diesel piston ☐ Diesel piston ☐ Diesel piston
Engine Type
☐ 2-stroke ☐ 4- ☐ 2-stroke ☐ 4- ☐ 2-stroke ☐ 4- ☐ 2-stroke ☐ 4- ☐ 2-stroke ☐ 4- ☐ 2-stroke ☐ 4-
stroke stroke stroke stroke stroke stroke
___ % ___ % ___ % ___ % ___ % ___ %
Fuel type used ☐ MGO S
☐ MGO
S
☐ MGO
S
☐ MGO
S
☐ MGO
S
☐ MGO
S
within Port of
___ % ___ % ___ % ___ % ___ % ___ %
Gävle SECA ☐ MDO ☐ MDO ☐ MDO ☐ MDO ☐ MDO ☐ MDO
S S S S S S
Average total ship power
☐ kW ☐ kW Ship alongside the ☐ kW
generated from engines #1-6 At sea Manoeuvring
above ☐ hp ☐ hp quay (hoteling) ☐ hp
Time the ship is berthed alongside Maximum power generated from engines #1-6 above, ☐ kW
hours
the quay (hoteling) alongside the quay (hoteling) ☐ hp
Cost of modifications
☐ Engine fuel pumps ☐ Engine fuel injectors ☐ Fuel piping and pumps
☐ Other, please explain other modifications that will be required and estimate the associated costs:
Would requiring low sulphur MGO use in main engines while operating within the SECA require modification of the vessel?
☐ Yes ☐ No If Yes, please comment below.
Check boxes for modifications required and estimate cost (if unable to provide individual cost estimates, please estimate total modification
cost):
☐ Fuel tank(s) ☐ Cylinder lube oil system ☐ Fuel valves
☐ Engine fuel pumps ☐ Engine fuel injectors ☐ Fuel piping and pumps
☐ Other, please explain other modifications that will be required and estimate the associated costs:
Manoeuvring
Ship alongside the quay
(hoteling)
* Please specify whether the information is expressed in other stated unit of measurement.
Has the company conducted any study on implementing a shore-side power supply system?
Is it possible/feasible to carry out any retrofit on board of existing vessels?
Is the company willing/reluctant to change to a shore-side power supply?
Hazardous areas (“HazLocs”): Which safety issues concern you most with regard to a shore-side power supply?