Deswik Module Summary UGM 1
Deswik Module Summary UGM 1
METALS
MODULE
SUMMARY
VERSION 1.8
CONTENTS Click on the product you would like to view
Deswik.SO Deswik.UGDB
Stope Optimizer Underground
Drill & Blast
Deswik.GeoTools
Deswik.IS Deswik.LHS UG Deswik.AdvUGM Operational Geology
Interactive Scheduler Underground Advanced
Landform & Haulage Underground Metals
deswik.com
CONTENTS
Deswik.CAD
DESIGN & SOLIDS MODELING
Deswik.CAD has been designed by mining professionals for mining »» Incorporate a broad variety of data sources:
professionals. Effectively a spatial database, Deswik.CAD combines -- Global constants and parameter tables
the visual power of a modern CAD engine with the efficient data
-- Curve and value surface interpolation
management of a fully featured database, giving you the ability to
-- Interactive and rules-based filtering from attribute values.
display, analyze and report your data however you need to.
Deliberately designed to provide generic engineering tools with COMPREHENSIVE MINING DESIGN TOOLS
flexible applications, Deswik.CAD is used and sought after across »» Advanced design and editing tools within a simple, modern,
all mining sectors; underground and open pit mines, both coal and intuitive interface.
and metal, throughout the world. »» Universal applications handle all mining sectors, open cut or
underground, coal or metals.
FULLY FEATURED CAD ENGINE »» Rules-based mine design engine for designs, allowing for
»» Modern Graphics engine designed to handle large mining scenario and what-if analysis.
datasets with excellent graphics performance.
»» Generate solids and surfaces using a multitude of methods:
»» Generate, slice and Boolean without errors. Arguably the best
-- Projection – strip or pit (open cut reserving)
solids and polygon Boolean tools on the market.
-- X-Section along polyline (tunnels)
»» Support for all standard CAD objects as well as mining specific
-- Manual or batch linking (stopes)
objects including:
-- Tessellation (LIDAR data processing or DTM creation).
-- Irregular stopes and tunnels
-- Drill holes
AUDITABILITY AND CONSISTENCY
-- Gridded seam and block models.
»» Information manipulation using a powerful formula builder,
»» Superior graphic performance taking advantage of modern instead of scripting.
graphics card technologies. »» Add structure to the planning process using graphical process
»» Generate solids / polygons using a robust Boolean engine. maps tied into the entire Deswik.CAD toolset.
Where other mining technologies fail, our solids will be valid. »» Wizard and rules-based tools provides data manipulation
»» Import invalid solids from other mining systems and repair transparency.
them automatically. »» Customizable process map macro builder:
-- Repeatable design and data transformations
INTEGRATED DATA MANAGEMENT
-- Standardized planning process mapped to internal processes
»» Superior attribute and metadata handling, bringing GIS-style
-- Remove confusion for unfamiliar users.
capabilities to 3D mining data.
»» Brings advanced spreadsheet style calculations into the design
environment, offering superior analysis and insights:
-- 3D spatial lookup formulae
-- Interrogate against solids for volume, area and intersections.
2
CONTENTS
Deswik.CAD
DESIGN & SOLIDS MODELING
3
CONTENTS
Deswik.Sched
GANTT CHART SCHEDULER
From interactive Gantt charts to PERT network diagrams, Deswik. TIME MANAGEMENT
Sched is tailored for the needs of mine planners. Encompassing »» Detailed work calendars for scheduling and reporting from a
both rate and duration based scheduling, it easily handles the shift basis through to a 100yr+ Life Of Mine.
massive data sets that modern detailed planning requires;
»» Flexible combination of manual scheduling tools for short
integrating production, ancillary and project activities with
term and automated long term scheduling.
ease. Built around a powerful resource leveling engine; you’ll
»» Scheduled task duration is calculated in seconds, allowing for
understand your resourcing better than ever, setting priorities,
infinitely customizable period reporting.
constraints and objectives designed to reflect the real world
requirements of actual mining activities. »» Construct detailed time usage models using:
-- Detailed rules based resource calendars
Unrestricted by timescales, long-term and short-term planning
-- Grid based time usage data
horizons sit seamlessly together in a single schedule. By
-- Comprehensive time based reporting fields.
accessing the comprehensive suite of flexible reporting options,
you’ll generate more accurate output data in more meaningful »» Integrate long, medium and short-term plans in one schedule,
ways, including detailed Critical and Point to Point path analysis. set specified planning horizons.
-- Linked reporting and 3D solid animation viewers. »» Manual or rules-based resource assignment for individual or
pooled resources.
»» Generate complex scheduling data through powerful »» Resource specific priorities and proximity de-rating for gear
spreadsheet-style formula tools, referencing data from a working close together.
variety of sources, including lookup tables, range lookups,
»» Incorporate resource specific maintenance requirements
curves and global constants.
including:
»» Innovative task and dependency options including:
-- Maintenance events based on equipment hours
-- Hammock tasks
-- Retire and replace equipment based on a defined lifespan.
-- Percentage overlap dependencies.
4
CONTENTS
Deswik.Sched
GANTT CHART SCHEDULER
INTEGRATED REPORTING
»» User-defined pivot-style reports can be quickly customized to
drill into the details of a schedule.
»» Unlimited options for pivot based reporting layout includes:
-- Task and resource filtering
-- Report based formulas
-- Incorporated graphing options
5
CONTENTS
Deswik.IS
INTERACTIVE SCHEDULER
6
CONTENTS
Deswik.IS
INTERACTIVE SCHEDULER
-- Automatically merges small polygons created at the edge -- Updates face positions for underground development
of a pit shell with larger adjacent blocks, to create more against survey pickups updating the schedule as required.
practical mining shapes. »» Automatic and on demand batch update functions transfers
»» Create polygons and solids to represent an ore drive, using information from your design to your schedule and back again
centerlines and polygons defining the ore limit outline. within the software – no need to save out files to load into
»» Innovative graphical interface with a flexible, rules-based »» Project merge facilitates multi-user planning of different mine
approach delivers repeatable and auditable creation of areas or timeframes for true integration across a project.
complex mining sequences. »» Set a mining direction for your overall design; define specific
»» Graphically set resource paths for greater control of dates and then cut the task solids to indicate the face
equipment sequencing. positions.
»» Graphical dependency tool provides visual representation of »» Create stage plans that represent snapshots of the surface of
every single task dependency in the linked schedule. your mining and dump faces at different times throughout the
»» Intuitive manual linking between design graphics based on life of your mine.
polygon, centroid or solid selection. »» Cut tunnels and outlines based on the meters scheduled to
»» Build comprehensive sets of automatic dependency rules that be mined across a range of periods that you define.
can be re-run for new or updated designs as required: »» Manage different files related to the one mine plan by
-- Link directly on task metadata (attributes) merging multiple base projects into one master project:
-- Spatial linking based on solid centroid -- Build the master schedule from all tasks contained in the
original base schedules.
-- Vertical overlap and face angle.
-- Vary master schedule as required and then write changes
»» Dependencies are automatically updated to the schedule in
back to the base projects to keep them updated.
real time as they are created.
-- Dependent tasks in the master schedule are incorporated
»» Access animation mode while creating dependencies to
into the base schedule as non-editable external tasks.
immediately visualize changes to the mining sequence.
»» Option to assign schedule resources to tasks graphically as
part of the dependency creation process.
7
CONTENTS
Deswik.LHS Underground
LANDFORM & HAULAGE
Deswik.LHS for Underground lets you quickly and easily calculate FAST
the haulage metrics of your schedule and present the results in »» Entire life of asset schedules can be run in a matter of
the form of 3D animations and combined reports from Deswik. minutes, using detailed rimpull calculations for haulage.
Sched. The entire process is presented in a compact, process-
driven user interface to guide you through generating the SIMPLE SOLUTION
input data, including creating and validating a haulage network, »» Easy-to-use software requiring no expert knowledge of
configuring source to destination rules, and configuring haulage haulage modeling or setup.
assumptions.
SIMPLE SOLUTION
»» Easy-to-use software requiring no expert knowledge of
haulage modeling or setup.
INTEGRATED DECISIONS
»» Integrate haulage modeling results with your schedule to
determine trucking requirements.
8
CONTENTS
Deswik.AdvUGM
ADVANCED UNDERGROUND METALS
Developed in direct response to the needs of our customers, »» Report out dilution, overbreak and underbreak from hanging
Deswik.AdvUGM adds functionality across the Deswik software wall, footwall, sides, crowns and toes.
suite. Continually updated with the latest releases from our
development pipeline, this module enables your mine planners BACKFILL PLANNING AND RECONCILIATION
to do more effective, more detailed and more value driven »» Generate staged backfill solids based on material
planning. Unlocking advanced design and scheduling features for characteristics and fill volumes from nominated fill points on a
both long and short term planning, the module includes: 3D stope void solid.
»» Reconcile actual fill amounts against required fill and
»» Underground Tabular Design Toolbox and Auto Development
determine void locations.
Designer for rapid development layouts
»» Easy development and stope reconciliation tools for ADVANCED RESOURCE LEVELING
compliance auditing »» Access to features such as backwards pass leveling, multi-field
or sink rate targeting and time usage models.
»» Backfill design and reconciliation including slump calculations
»» Short-term manual scheduling via interactive resource paths
»» Advanced scheduling functions including backwards pass
or import resource paths from other packages.
resource leveling, objective targeting and resource path
importing.
CALCULATE STEREONETS
Deswik.AdvUGM can be used with either Deswik.CAD or Deswik. »» Import strike azimuth and dip data to generate geotechnical
Sched or a combination of both. stereonets directly in the Deswik.CAD design space.
»» Supports Schmidtt, Wulff, Rose and observation diagrams.
AUTO DEVELOPMENT DESIGNER
»» Uses rule-based processing to rapidly layout development INCLUDES DESWIK.SVIZ (SCHEDULER
and panels for underground mining operations. VISUALIZER)
»» Automates standard polyline manipulation tools and formula »» Embedded 3D visualizer for Deswik.Sched.
based attribute assignment. »» Utilizing a dockable interface, it provides interactive viewing
and animation of mine designs, sitting side-by-side with the
UNDERGROUND TABULAR DESIGN TOOLBOX schedule tasks.
»» Design toolbox developed specifically for repetitive
underground designs in tabular-style deposits. TUNNELS BY VARIABLE SECTION
»» Generates development layouts relative to defined geological »» Tunnel creation tool that uses chainage based rules to allow a
models. tunnel to have variable profiles
»» The tool has 3 different rule sets available:
PROCESS CMS
-- Primary X-section rule – this allows the user to change the
»» Import CMS polylines or triangles and stich them together to
profile of the tunnel as required
create a closed solid.
-- Secondary X-section rule – allows the user to insert repetitive
»» Rapidly generate shells around CMS point cloud data.
changes to tunnel profil ie. safety bays, Fresh Air bases,
electrical cut outs etc
AS-BUILT RECONCILIATION
»» Detailed reconciliation between as-built and design solids -- Excavation Rules – allows the user to dice up any tunnel
from a 3D perspective for development or stopes. profile into excavation segments that will be excavated, ie,
top bench, bottom bench, wall stripping etc.
9
CONTENTS
Deswik.OPS
OPERATIONS PLANNING & CONTROL
Collaborative short-term
planning and shift execution
tool for monitoring and
managing compliance to plan
Deswik.OPS is a web-based, operations scheduling, production to allow for Short Interval Control (SIC) during a shift while
data management and collaboration tool. Integrating with the monitoring any deviations from the longer term goals of the
organization’s longer-term schedules, it enables production organization.
planners to rapidly create detailed, activity-based shift plans »» Monitor progress against the plan: the shift view provides a
directly from the short-term schedule. clear picture of what is happening throughout a shift for the
control room operator.
Deswik.OPS manages the progress of mining activities within the
site and meets the daily requirements of short-term engineers, »» Dynamically change a plan at the shift level and add new
production engineers, shift bosses, control room personnel and activities as required during the shift.
site superintendents. »» Maintain a direct link between longer term schedule tasks and
the operations plan.
Deswik.OPS is highly configurable and integrates with third-party
»» Display multiple baselines or future plans to ensure the active
production data capture systems and the Deswik suite of mine
operations schedule follows the longer term plans.
planning tools.
SCHEDULE INTEGRATION
OPERATIONS PLANNING »» Direct integration with the short-term planners’ schedule
»» Quickly build detailed, activity-based weekly and shift plans lets you rapidly build your operations schedule. For example,
directly from the short-term plan. you can import the first 1-4 weeks of the 12-week plan from
»» Convert longer term tasks into detailed activity cycles using Deswik.Sched or a third-party system.
user configurable rules. »» Use process and site-specific activity cycles along with
»» Create additional activities and cycles representing detailed business rules to automatically expand your short-term
work not considered in the short term plan, e.g. services schedule into an operations schedule.
activities. »» Deswik.OPS builds on the strong foundations provided by the
»» Assign equipment and operator resources to activities. powerful Deswik.Sched engine to manage dependencies and
»» Prioritize activities to ensure operations focus on critical tasks. OPS and the Deswik.Sched tasks in the short-term schedule,
allowing production data in Deswik.OPS to quickly update the
»» Record in-shift movements and better understand the
short-term schedule.
constraints within the mine for the shift being managed.
»» All data captured in Deswik.OPS is available for reporting using
»» Record baselines of the agreed plans to help drive compliance
third party reporting tools through a SQL Server database.
to plan.
»» Monitor equipment availability and utilization, and dynamically TRACK AND MONITOR ACTIVITY PROGRESS
adjust the shift plan based on the impact of delays upon your »» As production data is directly matched against the planned
schedule. activities, data analytics can reveal more meaningful insights.
»» Track and manage resource and material assignment, »» Analyse the repository of historic planning and production
movements and delays. data to predict ways to improve your operations’ efficiency.
»» Check the progress of the previous or current shift activities
10
CONTENTS
Deswik.OPS
OPERATIONS PLANNING & CONTROL
»» Reconcile planning Baselines against production data to help »» The data underlying the operations schedule is kept
manage the compliance to plan. synchronized between the multiple views and is available for
»» Throughout a shift, capture real-time data regarding shift reporting and analysis through the Reporting Database.
operations, or enter it at shift completion.
»» Automatically record production data for each activity from
a third-party system, or manually enter it for equipment not
managed by a Fleet Management System.Activity specific KPI’s
can be configured to ensure all important production data is
captured.
»» All collected production data is mapped to planned activities
to display progress against the plan and allow reporting of
planned vs actual.
»» Process specific tracker views clearly indicate how production
is performing against the agreed plan, allowing corrective
action to be taken.
»» Superintendents and managers can view outstanding
workflow items across departments and re-allocate tasks to
balance workloads.
»» All planning and production data is available through the
Reporting Database for analysis and reporting using 3rd party
tools.
COLLABORATION
»» Deswik.OPS supports collaboration between multiple
departments through the multi-user web interface.
»» It improves communication across shifts between all site
personnel.
»» Users can add structured comments about locations,
activities, resources, or a shift, and add attachments to
increase meaning.
»» A range of configurable input views enables planning and
production data input from different teams.
»» Different views of the same data are available for different
stakeholders:
-- Location tracker and whiteboard for the shift supervisors
-- Gantt chart for the scheduling engineers and control room
operators
-- Agreed weekly or daily planned activities recorded as
baselines can be compared against current activity
progress to check for deviations to the plan and allow
corrective action to be taken.
11
CONTENTS
Deswik.MDM
MINING DATA MANAGEMENT
PROCESS WORKFLOWS
»» Process workflows can be built into the MDM, defining or
enhancing current organizational planning processes.
»» Workflows provide formalized, repeatable processes that
ensure data validity and auditability.
DATA SECURITY
»» Users are assigned rights to only allow read or write access to
specific categories of data.
»» Users can be grouped to allow multiple people to work on
common tasks as available.
12
CONTENTS
Deswik.FM
FILE MANAGER
Deswik.FM is a centralized, collaborative and auditable document DIRECT INTEGRATION WITH DESWIK SUITE
management system. Operating from an integrated user »» Intuitive user interface docks directly within Deswik.CAD or
interface within the Deswik suite, users add or remove files Deswik.Sched.
and control file versioning via an intuitive check in/check out
»» Familiar tree structure representation of files includes status
mechanism.
and history for selected files.
13
CONTENTS
Deswik.AdvSurvey
ADVANCED SURVEY
RECONCILIATION
»» Reconcile an existing stope or development design with an
as-built.
»» Use intensity values for visualization of structures and
comparison with surface scans.
USER-DEFINABLE SETTINGS
»» Allow users to control their results
INTEGRATED SYSTEMS
»» Integration with Deswik’s mine design, scheduling and data
management modules
14
CONTENTS
Deswik.ASD
AUTO STOPE DESIGNER
PRACTICAL RESULTS
»» Working from development layouts, Deswik.ASD slices against
block models to generate section lines representing individual
stopes.
»» Rapidly produces detailed stopes that are practical for narrow
vein, steeply dipping deposits.
DETAILED DESIGN
»» Consider geological constraints and incorporate design
parameters such as pillar restrictions, dilution factors and
cut-off grades.
»» Assign minimum footwall angles to automatically adjust design
and dilution to match.
SPECIALIZED FUNCTIONS
»» Constrain stopes to follow defined lenses in the orebody,
accounting for close-spaced multiple lenses.
»» Development matching for incremental cost analysis to the
extents of the ore body from a central access drive.
VARIABLE SCENARIOS
»» Supports multiple input data sources to generate variegated
stope designs in different ore zones or geological models.
»» Attributes are automatically assigned to be quickly used in the
generation of a schedule.
15
CONTENTS
Deswik.Caving
CAVE FLOW MODELING
PRODUCTION OPTIMIZATION
»» Models flow of rock within the cave Life-Of-Mine to give
recovery and dilution forecasts.
»» Optimizes production targets at draw points.
»» Schedules production for block, panel and sublevel caving.
CAPABILITIES
»» Automatic flow mechanics properties.
»» Recovery reports generated by level, phase, resource
classification, drawpoint and time.
»» Sublevel and block caving capability within the same model.
»» Allows for cave propagation within a simulation.
»» Allows for fine and alternate particle properties.
INTEGRATION
»» Ease of importing .DXF files for cave back propagation.
»» Integrates with the Deswik process.
16
CONTENTS
Deswik.Draft
DRAFTING AND PLOTTING
PROCESS MANAGEMENT
»» Add structure to the planning process using a customizable
process maps macro builder:
-- Repeatable design and data transformations.
-- Standardized planning process mapped to internal
processes.
-- Remove confusion for unfamiliar users.
17
CONTENTS
Deswik.UGDB
UNDERGROUND DRILL & BLAST
DYNAMIC UPDATING
»» Update holes layouts against survey and design changes,
change the drill rig or reverse the drill look direction.
»» Copy designs between rings – new design automatically
adjusts to the profile of the next ring slice.
BLAST DESIGN
»» Define charge holes and primer locations including
customizable decking layouts with multiple explosive
products.
»» Set blast timing for holes in various patterns and sequences
and animate the resultant blast.
18
CONTENTS
Deswik.SO
STOPE OPTIMIZER
A strategic mine planning tool, Deswik.SO automates stoping UNDERSTAND THE OPTIONS
design for a range of methods used in underground mines. Able »» Scenario Manager facilitates comparison of multiple design
to quickly analyze stoping methods and parameters for a defined scenarios with rapid adjustments.
geological block model, you’ll maximize the value of your ore »» Export and import scenario settings for rapid setup of new
body and develop a strategic plan assessed against a variety of projects and re-evaluate scenarios against new geological
approaches and constraints. data.
Built around the AMS Mineable Shape Optimizer, the tool allows INTEGRATED PLANNING SOLUTION
you to define numerous properties for the stopes including; »» Embedded in the Deswik.CAD graphics platform for effortless
general shape and orientation, cut-off grade, cost and revenue, generation of stope wireframes and solids.
pillar sizes, dilution, mining limits and waste ratios. The
»» Seamless flow into Deswik.Sched via Deswik.IS for rapid
scenario management tools allow multiple mining options to be analysis of scenario results.
considered and compared rapidly, generating output reports
that let you optimize for your best case.
CUSTOMIZABLE DESIGN
»» Wizard-based setup for easy definition of stope parameters
like strike and dip as well as stope and pillar widths.
»» Dilution offsets define planned dilution width on both footwall
and hangingwall sides of the stope.
ECONOMIC OPTIMIZATION
»» Use geological model fields as cut-off values or calculate a
value with grade, mining recovery, price, mining/processing
costs and royalties.
»» Alter the maximum waste proportion of the stopes to vary
resource recovery.
19
CONTENTS
Deswik.vCAD
CAD VIEWER
INCLUDED FUNCTIONALITY
»» Run animations published though Deswik.IS or simply load up
design files.
»» Select, pan, orbit, zoom, and display the animation in 3D.
»» Display the properties and attributes of a selected object.
»» Display or hide design layers through the normal layer
directory.
»» Apply previously defined:
-- Color legends.
-- Plane definition views.
-- Layer pre-sets.
»» Filter objects on a layer interactively.
20
CONTENTS
Deswik.vSched
SCHEDULER VIEWER
INCLUDED FUNCTIONALITY
»» Apply pre-configured layouts or create a new one as required
from:
-- Task grid setups
-- Gantt chart views
-- Reports
-- Timescales
-- Grouping.
»» View all of the file settings including:
-- Production fields
-- Custom fields
-- Filters
-- Calendars.
»» Adjust the view; collapse and expand groups.
»» Apply date range filters.
»» Print the schedule.
21
CONTENTS
Deswik.Blend
MATERIAL FLOW MODELING
COMPLEX SYSTEMS
»» Build a network of sources, stockpiles, dumps and plants to
model material flows and transformations to products and
waste through an intuitive graphic interface.
»» Materials can be modeled on either a raw or product basis
and incorporate unlimited variables.
22
CONTENTS
Deswik.SOT
SCHEDULE OPTIMIZATION TOOL
23
CONTENTS
Deswik.SViz
SCHEDULER VISUALIZER
SViz is an embedded 3D visualizer for Deswik.Sched. Using a IMPORTS SETTINGS AND DATA
dockable interface, it provides interactive viewing and animation »» Imports file settings such as legends, layer pre-sets and plane
of mine designs, sitting side-by-side with the schedule tasks. definitions for the Deswik.CAD design file.
Working from an initial design created through the Deswik
»» Display design layers through the layer directory and access
suite, SViz can enhance the scheduling process with real time
all the attributes and properties of the solids.
visualization of schedule changes.
SYNCHRONIZED
Full integration with Deswik.Sched lets you apply filters, color
»» See your changes to the schedule instantly reflected in the
blocks by schedule fields and assign resources, to view your their
animation in the viewer.
schedule data in a more meaningful way.
»» Apply schedule filters to see them instantly reflected in the
A low cost option designed to free up Deswik.CAD and Deswik. viewer.
IS licenses, SViz maintains the unique integration of design and
scheduling that sets Deswik apart.
STREAMLINED FUNCTIONALITY
»» Works with Deswik.Sched, independently of Deswik.CAD or
Deswik.IS.
»» One application and one interface for scheduling and
visualization.
SCHEDULE INTERACTION
»» Dependency view that clearly shows successor and
predecessor tasks in the 3D view.
»» Assign resources by dragging directly onto the 3D task solids.
24
CONTENTS
Deswik.GeoTools
OPERATIONAL GEOLOGY
from external lab systems. The system is fully configurable to 3D space ready for mapping. With the ability to use on-board
camera hardware, users can incorporate face photography,
an individual site and can be set up to accommodate whatever
which allows them to draw geological features on top of images
assays and geological observations are being collected. Once
with ease.
data is entered, it is immediately available in the Deswik 3D
model space and can be viewed and queried alongside other 3D All drawing features are entirely configurable. The app uses a
entities such as level surveys, block models, drillholes etc. template that can be controlled by geological supervisors to
ensure that the same styles, rock types, colors and symbols are
Data can be incrementally added to the system as required, used in all geological maps that are created.
25
deswik.com