Manual ABT SYSTEM
Manual ABT SYSTEM
The following is an example of a Statement of Work. The Statement of Work outlines the general
activities that must be conducted in order to complete the installation and commissioning tasks for a
Ripwave Base Station.
Example:
Statement of Work for Standard Installation Services
The following statement of work will be used to outline the areas of responsibilities for the Navini
Networks antenna (known as the RFS) and Base Station (known as the BTS) installations to be
completed with Navini Networks Client (referred to as Client in this document). Client may choose
to hire a contractor or tower crew to assist with its activities. Navini Networks has no formal
contract relationship with the contractor, who will be managed by Client. The following work items
are suggested content only - - final scope and terms to be negotiated directly with Client. Navini
Networks support personnel will be on site for the entire installation and commissioning process,
and will provide technical expertise, information, and recommendations with respect to site design
and installation.
It is recommended that contractor have a Non-Disclosure Agreement (NDA) in place with Client and
Navini Networks prior to execution of work. Contractor shall not publicly disclose any information
concerning this deployment or trial with any other parties, unless approved in writing in advance by
Client and Navini Networks.
Navini Networks
1. Provide Field Engineer to consult with Client and Contractor for planning efforts. Review
Site design sketches and BOM prepared by others.
2. Review network architecture information (connection diagram and logical addresses) prior to
start of installation.
3. Review Sweep results with Client and contractor. Sweep to be provided of RFS after
shipment, of coax cables and RF path on tower, and of cables and RFS after installation,
before power up.
4. Review AC and DC power system installation. Review DC power system test with Client
and contractor.
5. Review backhaul circuit installation test results with Client.
6. Review GPS antenna and cable installations.
7. Review and Verify Cable and Antenna System Installation Work
8. Site walk with contractor and Client for Punchlist.
9. Load EMS software on Client supplied workstation, and verify connectivity to BTS.
antenna to BTS.
20. Site walk at completion with Client and Navini, create Punchlist; clear applicable punchlist
items.
21. Arrange disposal of trash
22. Provide RF coverage analysis plots before start of installation. Provide model tuning, if
required.
23. Provide architecture document before start of installation, including connection diagram and
logical network element assignments (IP addresses, PVCs, etc.).
24. Set Up and Verify all network equipment and backhaul circuits.
25. Set Up and Verify Operation and connectivity of EMS computer.
26. Provide one resource to assist with drive testing and location data rate testing.
27. Provide all end user / CPE provisioning in EMS after initial testing.
28. Provide all end user interface and troubleshooting.
29. Monitor EMS / alarms. Forward trouble issues to Navini call center.
30. Contractor and Client to provide own tools, computers, and test equipment.
The following is an example of a Responsibility Assignment Matrix (RAM). The RAM is a tool for
capturing who will do what to get systems deployed and turned up. It provides an easy-to-read and
follow tabular format. Each of the activities in the list must be addressed in order to complete the
installation and commissioning tasks for a Ripwave Base Station.
1 Network Requirements 2 1
2 Network Architecture 2 1
3 Provisioning Guidelines 1
8 Order Circuits 1
SITE ACQUISITION
SITE DESIGN
3 Prepare BOM 2 1
CONSTRUCTION / INSTALLATION
5 Ground Kits S, I
10 Batteries / UPS S, I
12 Electrical Circuits S, I
15 Environmental Equipment S, I
16 Miscellaneous Hardware S
18 Network Router S, I
24 CPE S
CONSTRUCTION
2 Pull Cables 1
7 Install Racks 2 1
9 Backhaul to rack 1
11 Quality Assurance 2 1
3 Test DC System 2 1
6 Boot BTS 1
8 Test Operation 1
9 Integrate Backhaul 2 1
10 Verify Operation 2 1
TESTING
7 Issue reports 1
2 Monitor Network 2 1
5 Performance Reporting 2 1
5 Material Procurement
5.1 Bill Of Materials From Approved Construction Drawings
5.2 Vendor Selection
5.3 Bids / Quotes
5.4 Requisitions / Purchase Orders
5.5 Tower, Mounts, Lightning Protection, Lighting, Cable Ladder, Safety Climb,.
5.6 BTS - with Rack (IBTS), with Enclosure (OBTS)
5.7 RFS - Active, Passive
5.8 Cables, Connectors, Mounting Hardware, Surge Protection
5.9 AC Power Equipment
5.10 DC Power Equipment
5.11 Telco Equipment
5.12 Grounding Equipment and Materials
5.13 Delivery Coordination / Warehousing / Logistics
6 Facilities Orders
6.1 Electric Power Service Order Site Walk / Engineering
6.2 Electric Power Service / Equipment Order
6.3 Telephone Service Order Site Walk / Engineering
6.4 Telco Service / Equipment Order
NAVINI NETWORKS
SITE EVALUATION FORM
PN - 40-00091-00
Site Name
Date
FSE
SITE INFORMATION
COMPANY NAME
ADDRESS
SITE OWNER
SITE CONTACT NO.
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
TOWER PICTURE
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
Comments
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
NORTH VIEW
Comments
NORTHEAST VIEW
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
EAST VIEW
Comments
SOUTHEAST VIEW
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
SOUTH VIEW
Comments
SOUTHWEST VIEW
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
WEST VIEW
Comments
NORTHWEST VIEW
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
Comments
GROUNDING
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
INGRESS
Comments
EGRESS
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
POWER
Comments
TELCO
Comments
NAVINI NETWORKS
SITE EVALUATION FORM
Site Name 0
SHELTER PICTURE
Comments
Comments
Required Equipment
You will need the following equipment to perform the Interference Sweep:
?? HP4404B Spectrum Analyzer or equivalent. An equivalent analyzer must have the following:
- Screen Save abilities
- Max-hold function
- Peak search
- Ability to operate in the required frequency range
?? Omni or Directional Antenna for the given frequency range
The directional antenna should have a gain of > 9 dBi.
?? Cavity Filter
Pass band should cover the frequency range. It must have good out-of-band rejection so the
LNA is not jammed by high power AMP, PCS, or TV signals.
?? LNA Module
Gain > 21dB, NF < 7dB, for frequency range
?? Various SMA and N-Type adapters
?? Various RF cables to connect to Antenna and to test equipment
Initial Configuration
The set-up shown in Figure E1 and the information below are for the initial configuration. It gives
you a starting point for this procedure. During the later steps, this configuration will change.
Antenna
DC
Powered
Step 2. Program the initial Spectrum Analyzer settings, per the following:
When using a directional antenna to pick up the interference, try to change the angle or downtilt to
face a potential interference source such as a tower or a more populated area. A directional antenna
is used to determine the location of the source that is generating the interference. The beamwidth of
the directional antenna determines the number of directions that you need to sweep.
For example, if the beamwidth of the directional antenna is 90 degrees, then four passes of the
procedure are necessary. Whereas, an antenna with a 30-degree beamwidth requires 12 sets of
sweeps to cover the same 360 degree area. The smaller beamwidth requires more sweeps but gives
you greater accuracy in determining the source of the interfering signal. On each pass the directional
antenna is moved per the beamwidth. Refer to Figure E2.
With both types of antennas, try to determine the polarization of the interfering signals during each
sweep. To do this, flip the antenna 90 degrees. All measurements that are captured are with the
antenna in the vertical polarization position.
The frequency band to be investigated is determined by the range of the BTS and RFS that is
purchased by a customer. The 2.6GHz MMDS band is a licensed band, and the customer purchasing
the equipment will have a license for a given 6MHz channel. The 2.4GHz band is an unlicensed
frequency range that is open for many applications. The objective for the 2.4GHz sweeps is to find a
5MHz range that is the clearest of any interference.
TEST
ANTENNA
POSITION 1
90
DEGREES
TEST
ANTENNA
POSITION 4
DEGREES
DEGREES
90
90
TEST
ANTENNA
POSITION 2
90
DEGREES
TEST
ANTENNA
POSITION 3
The 2.6GHz sweeps are done to verify that there is not another carrier infringing on the given
licensed channel. If you are performing the sweeps for a licensed 2.6GHz channel, it will greatly
reduce the number of steps that you will need to perform. For a 2.6GHz system you only need to
look at three channels for the spectrum. You will sweep the licensed channel as well as the channels
above and below the licensed band.
For example: If you have an E3 license (2.620GHz – 2.626GHz), you will sweep E3 plus F2
(2.614GHz-2.620GHz) and F3 (2.626GHz – 2.632GHz).
You will only need the Max-hold portion of the procedure for 2.6GHz systems.
Max-hold
The Max-hold portion of the procedure is to be used for both unlicensed and licensed systems.
Step 1. If using a directional antenna, check the direction of the antenna with a compass.
Record the results.
Step 2. Set the Start Frequency to 2.390GHz for a 2.4GHz system and to 2.595GHz for a
2.6GHz system.
Step 3. Set the Stop Frequency to 2.5GHz for a 2.4GHz system and to 2.645GHz for a
2.6GHz system.
Step 4. Replace the antenna with a terminator to get a noise floor level. Save a screen capture.
Step 5. Turn on the Max-hold feature and acquire the signal for two minutes. Save a screen
capture.
Step 6. Run Single Sweep two times, saving the screen captures for both sweeps. This gives a
reference for the worst case that is shown with the Max-hold in Step 5. Time can be
saved on this step if the Spectrum Analyzer is equipped with a dual trace option. Turn
Trace 2 on constant sweep and Trace 1 on Max-hold. After the Max-hold has
acquired a signal for two minutes, press the single sweep. Save the screen capture.
Refer to Figure E3, Max-hold Screen Capture.
Step 7. Repeat steps 5 and 6 with the following Start and Stop frequencies.
Time Domain
The Time Domain portion of the procedure is for unlicensed systems only.
Step 1. Set the Center Frequency to 2.4025GHz. Set the Resolution Bandwidth to 5 MHz.
Step 5. Replace the antenna with a terminator to get a noise floor level. Save a screen capture.
Step 6. Set the display line to the noise floor level. The display line needs to stay on for all of
the following sweeps. This display line is used for a reference point and should be set
with the LNA powered on.
Step 7. Run the Single Sweep approximately 50 times and determine how often the
interference occurs. Save a screen capture of one worst case and one typical. See
Figure E4, Time Domain Screen Capture.
Step 8. Set the Sweep Time to 400 ms, and repeat Step 7.
Step 9. Repeat Steps 7 and 8 for an offset of 5MHz up to 24875MHz for 2.4 systems.
2.4GHz Band
Center Frequency
2.4075GHz
2.4125GHz
2.4175GHz
2.4225GHz
2.4275GHz
2.4325GHz
Up to 2.4875GHz
Step 10. If a directional antenna is used, repeat the Max-hold and Time Domain steps for each
direction.
Overview
The Navini 2.4 GHz frequency Interference Sweep Test tool is used by an Installation &
Commissioning Technician or Field Engineer to sweep and collect data concerning RF conditions at
a specific site. The location is typically a site that has been identified as a potentially good candidate
for a Base Station installation.
The test tool manages the RF sweep and interference level conditions, with post-analysis performed
by RF Engineering personnel using simulation models. The results of the analysis are not a
guarantee of optimal operating conditions for the Ripwave system. The objective is to identify and
eliminate sites that might pose high potential problems in order to prioritize a given list of sites for
Base Station deployment.
Installation
Equipment
Figure F1 is a block diagram showing the requirements to install the equipment. Figure F2 provides
an example of the laptop and cable configuration.
Control Cable
Ethernet Cable
Laptop Computer
AC outlet
Mounting
The Navini Test Box should be installed in the location where the RFS will be installed, or as close
as possible. This will give the most accurate representation of the interference at the site. On the
upper portion of the test box there are three labels indicating 0, 120, and 240 degrees (Figure F3).
These are the antennas that are inside the test box. The label indicating 0 degrees should be pointed
as close to north as possible. Connect the Control Cable from the Navini Test Box to the Control
Box. The Control Box has a power connector, a circular control cable connector, and a blue
Ethernet cable on it. The Ethernet cable will be connected to your laptop.
Control Box
s
ree
eg
0d
12
0d
s
ree
eg
eg
ree
0d
s
24
1. Interval Setting
Provided by Navini Networks RF planning group
2. Frequency Selection
2.400 to 2.476 GHz approved ISM operating frequency
Procedure
Step 1. Open the application by selecting the Data Logger icon. Figure F5 shows the icon in the
background.
Step 3. Starting in the upper left corner of the program screen, set the date and time for the
application to start its measurement interval. If the date and time set are earlier than the
current time, logging will begin immediately.
Step 4. If the measurement needs to be repetitive, determine the interval between measurements
by selecting the repeat box and entering the time interval (Figure F6).
a. There are 3 frequency band selections. By default two are not available until selected
by clicking on the white checkboxes to the right of each.
b. If you select more than one band, it is best if you put in some delay between each
band’s measurements, as mentioned in Step 6 below.
Step 6. If more than one frequency band has been selected, choose the delay to be used between
each band’s measurements. You can use the scroll bar or just type in the interval.
Step 7. Select the number of frames for Gain Adjust. This allows the system to calculate the
Modem’s receiver sensitivity.
Step 8. Select the number of frames to be stored for analysis. The same number will be captured
for each frequency band if more than one is selected.
Step 9. Ensure antenna orientation is selected properly. It takes about 1 second to log one frame
of data. Therefore:
Where n is the number of gain adjustment loops. Up to 10 are possible if the received
signal varies to a great extent in amplitude from frame to frame.
Step 11. Enter in the desired Site Name in the pop-up window, and press Enter to start the
measurements.
Step 13. PC and Test operation should be validated every 3-4 hours for working order.
Analysis of Data
Not available on this release.
FTP Instructions
Step 1. Launch FTP Pro.
Step 2. Select the file, “Rfsweep”.
Step 3. The FTP Password is provided by Navini in a separate document.
Step 4. To transfer the file, locate the Navinidatalog folder on the “C” drive of the laptop.
Step 5. Select all files in the data folder via FTP browser, then, send the files.
Step 6. Once the file transfer is complete, delete the data folder and rename the “gain.adj” file for
the next test sequence. Create a new “gain_adj” folder under the NaviniDataLog folder.
0.00 53.4"
-5.00
-10.00
-15.00 Vertical
Horizontal
-20.00
Scale
DESCRIPTION
GALVANIZED
ANTENNA
Frequency Range 2.3GHz low band range = 2.305GHz Through 2.320GHz MOUNTING
PIPE
Polarization Vertical
Antenna Gain 17-17.5 dBi for 120 Degree Sectored
Horizontal HPBW 130 Degrees
Vertical HPBW 6 Degrees
Connector Type's 9 Female "N" Type
1 - 12 Pin Female Circular
Lateral Thrust at 100 MPH (161 KM/HR) w/o ice 220 LB. Lateral Load
Mounting Configurations To Pipe Mount - 2 3/4" TO 3" OD 2"
53.4"
0.00
-5.00
-10.00
-15.00 Vertical
Horizontal
-20.00
Scale
4.5 OD pipe
sch 40 pipe
12.6"
5"
DESCRIPTION
Frequency Range 2.4GHz range = 2.4GHz through 2.483GHz GALVANIZED
ANTENNA
MOUNTING
PIPE
54.5"
57.5"
Polarization Vertical
Antenna Gain 17-17.5 dBi for 120 Degree Sectored
Horizontal HPBW 130 Degrees
Vertical HPBW 6 Degrees
Connector Type's 9 Female "N" Type
DC Power Dissipation 80 Watts
Lateral Thrust at 100 MPH (161 KM/HR) w/o ice 220 LB. Lateral Load
Mounting Configurations To Pipe Mount - 2 3/4" TO 3" OD
Electrical Downtilt 6 Degrees 2"
0.00
-5.00
-10.00
-15.00 Vertical
Horizontal
-20.00
Scale
8.9"
NAVINI PART NUMBERS: 2.3GHz- low band with LNAs 95-23008-02*
note: * 02 or 12 are for degree of 2.3GHz- high band with LNAs 95-23008-12*
downtilt also available are 04 and 2.3GHz- low band without LNAs 95-23108-02*
14 2.3GHz- high band without LNAs 95-23108-12*
** xx is the degree of downtilt 2.4GHz- with LNAs 95-24008-xx**
02 or 04. 2.4GHz- without LNAs 95-24108-xx**
2.5GHz- with LNAs 95-25008-xx**
2.5GHz- without LNAs 95-25108-xx**
2.6GHz- EFGH with LNAs 95-26008-xx**
2.6GHz- EFGH without LNAs 95-26108-xx**
DESCRIPTION 13.057"
Frequency Range 2.3GHz low band range = 2.305GHz Through 2.320GHz
2.3GHz high band = 2.345GHz through 2.360GHz 73.5"
0.00
-5.00
-10.00
-15.00 Vertical
Horizontal
-20.00
Scale
NAVINI PART NUMBERS: 2.4GHz TTA RFS, 2 degree downtilt 95-24018-02 8.9"
DESCRIPTION 13.057"
General
Navini Networks does not manufacture external cabinets for the Ripwave BTS. The following lists
two manufacturers who are positioned to provide external cabinets for the Navini system. Inclusion
of the manufacturers on this list does not represent an endorsement of the manufacturer or its
products by Navini Networks.
Manufacturers List
Purcell Systems
22924 E. Appleway Avenue
Liberty Lake, WA 99019
509 755-0341
Steve Busby
Http://www.purcellsystems.com/
General
This section includes contact information for two rectifier/BBU suppliers. Inclusion of a supplier on
this list does not represent an endorsement of the supplier or its products.
Suppliers List
Argus DC Power
Argus Regional Sales Manager
Addison, IL
630 530-5006
Richard Meyer
http://www.argusdcpower.com/
Regulatory
RF CABLES
PSX-ME
SURGE
GROUND PROTECTOR
BAR
CABLE RUN / CABLE LADDER
OPTION 3
PANEL LOCATION
OPTION 6
CORE TO INSIDE
PANEL OF TOWER
ANTENNA
BTS Opt 2
Indoor
PSX-ME
SURGE RF CABLES
PROTECTOR
SHELTER / HUT
GPS CABLE
OPTION 1
ENTRY
INDOOR BTS
OPTION 2
INDOOR BTS CABLE OVERHEAD CABLE LADDER
LADDER
GROUND
BAR PSX
24VDC PSX 24VDC GROUND BAR
@ 60A GROUND BAR @ 60A
ETHERNET NAVINI
ETHERNET NAVINI / TELCO BTS
/ TELCO BTS
CABINET CABINET
GND GND
NOTE
1.CABLE BUNDLE CONSIST OF 9 RF CABLES AND 1 POWER/DATA CABLE
2.RF CABLE TYPE TO BE DETERMINED BASED ON RUN LENGTH AND DB
LOSS/FT
3.CABLE HANGERS TO BE SPECIFIED/RECOMMENDED BY TOWER CREW
4.ANTENNA BRACKET TO BE SUPPLIED BY CUSTOMER AS RECOMMENDED BY
TOWER CREW
5.BTS REQUIRES 24VDC @ 60A.
6.PSX-ME SURGE PROTECTORS TO BE INSTALLED IN-LINE BETWEEN RF
CABLE AND ANTENNA
7.PSX SURGE PROTECTOR TO BE MOUNTED ON GROUND BAR CLOSE TO BTS
CABINET/CHASSIS
8.ETHERNET/TELCO BACKHAUL TO BE PROVIDED BY CUSTOMER
9.ALL INSTALLED EQUIPMENT/MATERIALS MUST BE PROPERLY GROUNDED
10.OPTION 1 IS FOR AN INDOOR BTS INSTALL, OPTION 2 IS FOR
OUTDOOR BTS
CUSTOMER
SITE NAME
LOCATION
5 ANTENNA HEIGHT
17 GPS MOUNT
28 INDOOR RACK/CABINET
Overview
This section provides formulas and data that are necessary inputs for determining the right cable to be
measured, cut, and installed. There are 3 types of cables that are part of the Base Station installation: antenna
cables, calibration (cal) cable, and data/power cable.
The antenna cables are the eight cables that carry amplified RF signals. They run between the RF/PA cards
and the 8 antenna elements. The calibration (cal) cable is a single RF coaxial cable that provides an RF
feedback path for calibrating the system. It runs between the backplane of the digital shelf and the RFS. The
data/power cable may or may not be a separate cable from the cal cable. It is possible to use different types of
cable with different loss factors for the antenna cables and cal cable. The formulas presented in this section
call for either an antenna cable loss or a cal cable loss. Most applications deploy the same cable type for both
the antenna and cal cables.
To determine the type of cable and acceptable loss of that cable for a site, the operating transmit and receive
range must be known. This is commonly referred to as the maximum transmit output power and the receiver
sensitivity range. The operating transmit power and receive range should have been identified during the site
survey, or they may be based on regulatory compliance.
Determining the cable type and acceptable loss for a site are typically driven by two goals: (1) Which is the
least expensive cable; and (2) Which has the higher (normally) loss. Whether or not the goals are achieved is
determined by the output power. For example, the maximum transmit output power for a 2.6 Base Station
might be given as +30dBm, or 1 Watt, to the antenna. An example of receiver sensitivity for a 2.6 system
would be given as – 80 to –90 dBm.
In addition to cable power loss, other types of loss have to be factored - for example, the calibration board.
The calibration board is part of the RFS that samples the energy being transmitted from or received by the 8
antenna elements and combines that energy which is used when performing a calibration on the Base Station.
This loss, plus cable loss and other types of loss in the equipment are called out in the following procedure.
Procedure
Read and follow the 7 steps/formulas below, in the order shown, to determine the resulting PA/RFS output
power and desired transmit and receive calibration range for the type of Base Station you will be installing.
Refer to Tables L1 and L2 to complete the steps. Table L1 provides Base Station operating parameters based
on system type (2.3, 2.4, etc.), as well as other variables. Table L2 provides cable attenuation data. Before you
begin, read through the steps/formulas, notes, and Table L1 in detail. Refer to the column letters at the top of
Table L1 to locate the appropriate values requested in some of the formulas. Note that step/formula 1 contains
a sub-procedure for determining antenna cable loss using Table L2.
Step/Formula 1 Determine the maximum capable BTS output power to the antenna.
= [(PA Output to Meet FCC) or (to Meet SNR)] – BTS Loss – RFS Loss – BTS Antenna Cable Loss*
[Column A or B]1 – [Column E] 2 – [Column F or G] – [Calculated* or Measured]
Step/Formula 2
Determine the maximum BTS output power that can be calibrated.
= Max Synth Input + Cal Cable Loss + Min Cal Board Loss3 + Backplane Loss4
[Column K] + [Calculated or Measured] + [Note 3 ] + [Default of 5.0 in EMS or Measured]
Step/Formula 3
Determine the actual** max BTS output power available to the antenna.
= The lesser of the two values of Step/Formula 1 and Step/Formula 2 (aka, the “floor”)
Step/Formula 4
Determine the minimum BTS output power that can be calibrated .
= Min Synth Input + Cal Cable Loss + Max Cal Board Loss3 + Backplane Loss4
[Column J] + [Calculated or Measured] + [Note 3 ] + [Default of 5.0 in EMS or Measured]
Cal
Determine the actual** maximum EIRP. Cable
Step/Formula 5 Selection
= Step/Formula 3 + Antenna Gain. The antenna gain is affected by the type of antenna (omni, panel, 2.3,
2.4, etc.) and refers to the values in the RFS Configuration Script that accompanied the antenna from
Manufacturing.
Step/Formula 6
Determine the minimum BTS RX input power that can be calibrated.
= Min Synth Output - Cal Cable Loss - Min Cal Board Loss3 - Backplane Loss4
[Column H] - [Calculated or Measured] - [Note 3 ] - [Default of 5.0 in EMS or Measured]
Step/Formula 7
Determine the maximum BTS RX input power that can be calibrated.
= Max Synth Output - Cal Cable Loss -Max Cal Board Loss3 - Backplane Loss4
[Column I] - [Calculated or Measured] - [Note 3 ] - [Default of 5.0 in EMS or Measured]
NOTES
1
This note pertains to Step/Formula 1: For PA_Output_Powe r, if in the U.S. use Column A. If outside the U.S., as a
precaution contact Navini Technical Support (Engineering) for sign-off. The value input cannot be more than the
value shown in Column B.
2
This note pertains to Step/Formula 1: BTS_Loss is either (a) loss with a filter - i.e., if operating in the U.S. or other
market that requires a filter, or (b) loss with a bypass cable. The first number (+1) is the correct value if a standard
filter is used. The second number (0.4) is the correct value if a bypass cable is used. In Column D, for a 2.3 GHz
system the values are the same for both the 8-carrier and the 10-carrier systems.
3
Min loss in Cal Board is 27 dB. Max loss in Cal Board is 31 dB.
4
In the EMS the backplane loss will show 5.0 as default. Actual measured loss will be indicated on the back of the
chassis.
* The lowest value at which 2.3, 2.5, and 2.6 EFGH PAs will shut down automatically. There is no auto shutdown for 2.4 and 2.6 EF combo systems.
** The value at which the bypass does not meet FCC limits.
***Passive configurations of BTS affect system Noise figure. For passive systems other than 2.4, consult SYSTEMS ENGINEERING.
½?
1 ¼? 7/8? 5/8? ½? Super 3/8?
2 ¼? 1 5/8 ?
LMR LDF LMR LDF LMR LDF LDF LMR flex LMR LDF LMR
Cable Type LDF LDF 7-
1700 6- 1200 5- 900 4.5- 4- 600 FSJ 500 2- 400
12-50 50A
50A 50A 50A 50A 4- 50A
50B
Frequency/Size 2.350 1.980 1.670 1.550 1.200 1.090 0.870 0.865 0.630 0.590 0.520 0.500 0.440 0.405
2000 MHz 0.994 1.11 1.5 1.42 1.99 1.82 2.64 2.27 3.25 3.9 5.09 4.84 5.17 6
2400 MHz N/A 1.24 1.7 1.5 2.2 2.02 2.9 2.52 3.63 4.3 5.67 5.4 5.67 6.6
2500 MHz N/A 1.27 1.71 1.53 2.26 2.07 3 2.58 3.70 4.42 5.8 5.48 5.79 6.8
2600 MHz N/A 1.3 1.8 1.57 2.3 2.12 3.1 2.64 3.78 4.5 5.94 5.6 5.91 6.9
Weight lbs/ft 1.22 0.82 0.74 0.63 0.45 0.33 0.27 0.15 0.15 0.13 0.14 0.1 0.08 0.07
Table L3: 2.4 GHz TTA BTA Max Power and Frequency Range Supported
Table L4: 2.4 GHz TTA BTA Cable Loss and Corresponding Cable Length
Calculated
Cable
Length of RG6 Engineering Notes
Loss
Bundled Cable
For a cable loss of more than 15 dB,
Min 5 dB 40 ft (12 m) Adjacent Channel Power degradation
US
will occur.
(Omni & Sector)
Max(1) 20 dB 180 ft (55 m) At 20 dB of cable loss a minimum
ACP degradation of 3dB will occur
Min 5 dB 40 ft (12 m)
Omni For a cable loss of more than 15 dB,
(2)
Max 20 dB 180 ft (55 m) Adjacent Channel Power degradation
ETSI will be dominated by RFC.
Min 5 dB 40 ft (12 m) At 20 dB of cable loss RFC SNR will
Sector be approaching 30 dB
Max(1) 20 dB 180 ft (55 m)
Table L5: 3.5 GHz TTA BTA Max Power and Frequency Range Supported
ETSI
30 dBm 3.410 to 3.700 GHz
(Omni & Sector)
Table L6: 3.5 GHz TTA BTA Cable Loss and Corresponding Cable Length
1/13/2003 1:58:54 PM
Part
13-00034-00 : CONN, COAX, CRIMP, N STRAIGHT PLUG, EZ PIN (LMR600) . Quantity: 36
Part
13-00194-00 A CONN, COAX, CRIMP, N STRAIGHT PLUG, EZ PIN, MALE (LMR400). Quantity: 8
Part
Connectors, NType
13-00218-00 A CONN, LUG, ONE-HOLE #6. Quantity: 10
Connectors
13-00219-00 : CONN, LUG, TWO-HOLE #6. Quantity: 10
Connectors
13-00220-00 : CONN, LUG, TWO-HOLE #2. Quantity: 10
Part
18-00001-00 : CABLE, COAX, OUTDOOR RF, LMR600. Quantity: 1350
Part
18-00035-00 A WIRE, GROUND, GREEN, STRANDED, #2. Quantity: 50
Part
18-00036-00 : CABLE, COAX, OUTDOOR RF, LMR400. Quantity: 200
Cables, Coax
18-00049-00 : WIRE, STRANDED, GREEN, #6 AWG 50. Quantity: 13
Part
24-00045-00 : NUT, REG. HEX, CRES, 1/4-20UNC. Quantity: 8
Part
24-00117-00 : BUSS BAR, GROUND, TOWER, 1/4IN X 2-1/2IN X 12-1/2IN. Quantity: 1
Part
24-00118-00 : BUSS BAR, GROUND, SHELTER, 1/4IN X 4IN, DRILLED TO 5/8IN. Quantity: 1
Part
24-00119-00 : GRIP, HOISTING, PRE-LACED, FOR 1/2IN COAX CABLE. Quantity: 10
Part
24-00120-00 : HANGERS, ASSY, CUSHION, 5H, 1/2IN CORREGATED COAX. Quantity: 4
Mechanical Hardware
24-00121-00 : MOUNT, HANGER, CROSS CUSHION, KIT OF 5. Quantity: 2
Part
24-00122-00 : BLOCK, SUPPORT, MINI COAX. Quantity: 2
Part
24-00134-00 A BREAKER, OUTPUT DISTRIBUTION, 60 AMP, BTS INSTALLATION. Quantity: 1
Mechanical Hardware
24-00156-00 : CLAMP, PIPE TO PIPE, KIT OF 2. Quantity: 1
Mechanical Hardware
24-00170-00 : NUT, REG. HEX, CRES, #10-24. Quantity: 3
Part
24-00171-00 : WASH, STAR, #10. Quantity: 3
Part
24-00172-00 : WASH, STAR, ¼. Quantity: 16
Part
24-00250-10 : BOLT, HEX, 1/4-20 X 1.000 LG, SSPA. Quantity: 8
Mechanical Hardware
24-06156-43 : WASH, FLAT, CRES, #6 T-B-REGULAR, .156 X .438 X .040. Quantity: 16
Part
24-06250-14 : WASH, LOCK, SPLIT, CRES 1/4, Reg, .252X.487X.062. Quantity: 16
Part
32-00031-00 : ARRESTOR, LIGHTNING, RF 1.2 - 2.8GHz, N TYPE FEMALE, DC BLOCK, PSX. Quantity: 9
Part
32-00033-00 : ARRESTOR, LIGHTNING, GPS, PICKOR, DC PASS, MM50MNZ+6. Quantity: 2
Part
32-00052-00 : KIT, GROUNDING, LMR-600, 5FT X 1/2 IN, 2 HOLE LUG. Quantity: 9
Part
32-00053-00 : KIT, GROUNDING, LMR-400, 5FT X 3/8 IN, 2 HOLE LUG. Quantity: 2
Part
32-00077-00 : KIT, WEATHERPROOFING, GEL WRAP. Quantity: 1
Part
32-11004-00 : ARRESTOR, SURGE, EMP, DC BLOCK, RF COAX, In-line 2.4 GHz., PSX-ME. Quantity: 9
Part
92-00006-00 : SUBASSY, MOUNT UNIVERSAL FOR OMNI ANTENNA. Quantity: 1
Antennas
68-00006-00 : DWG, ASSY MOUNT UNIVERSAL FOR OMNI ANTENNA. Quantity: REF
Part
55-00079-00 : FLANGE C, ANTENNA MOUNT, OMNI. Quantity: 1
Part
55-00080-00 : GUSSET, ANTENNA MOUNT, OMNI . Quantity: 2
Part
55-00081-00 : PLATE, BASE, ANTENNA MOUNT, OMNI. Quantity: 1
Part
24-10000-00 : NUT, PEM, BLIND .250 1/4-20 BS-0420-2. Quantity: 8
Part Type
55-00088-00 : FLANGE, CLAMP, STANDARD MOUNT, GALVANIZED. Quantity: 2
Part
24-09000-00 : STUD, 7/16 X 14 LG ALL THREAD, GALVANIZED, ANTENNA MOUNT, OMNI. Quantity: 4
Mechanical Hardware
24-09001-00 : WASHER, SQ, ALUMINUM, ANTENNA MOUNT. Quantity: 4
Mechanical Hardware
24-09002-00 : WASHER, SQ, GALVANIZED, ANTENNA MOUNT. Quantity: 4
Mechanical Hardware
24-09003-00 : FLAT WASHER 7/16 REG GALVANIZED. Quantity: 12
Mechanical Hardware
24-09005-00 : LOCK WASHER, 7/16, GALVANIZED. Quantity: 12
Mechanical Hardware
24-09004-00 : HEX NUT 7/16 GALVANIZED. Quantity: 12
Mechanical Hardware
24-00124-00 : BOLT, HEX 1/4-20 X 1.250 LG SSPA. Quantity: 8
Part Type
24-06250-14 : WASH, LOCK, SPLIT, CRES 1/4, Reg, .252X.487X.062. Quantity: 8
Part
24-06250-28 : WASH, FLAT, CRES, 1/4 T-B-REGULAR, .281 X .734 X .063. Quantity: 8
The following article, written by Lou Caruso of Times Microwave Systems , appears in Volume 8
Issue 5, 2000 of Telecom Exchange.
“Among the keys to success in any wireless system are the quality and reliability of the connector
installations on the coaxial cable transmission lines. And it naturally follows that the more difficult
the connectors are to install, the lower the likelihood that they will be installed correctly thus
adversely affecting the quality and reliability of the entire system.
Traditional connectors require the pin contact to be soldered to the center conductor of the coax
cable. Unfortunately, when RF transmission lines are installed outdoors as is often the case, weather
conditions may not be conducive to using soldering equipment. Wind, rain and snow all can make
soldering difficult if not impossible. If electrical power isn’t available, gas or butane fired soldering
equipment may be the only recourse and these devices typically do not generate as much heat as
electrically powered devices. Consequently, they may not do as good of a job. The physical handling
of the cable, connector pin, butane torch and solder can also be tricky (not enough hands!),
especially if there’s only one person doing the installation.
For indoor installations, such as distributed antenna systems in buildings, the installer may be
working in cramped spaces, on a ladder and in low-light conditions. How can these issues be
overcome to ensure a reliable connector installation and proper system performance?
Simplicity is the key. The connector installation process can be simplified with the use of non-solder
connectors and the correct installation tools. We have designed non-solder connectors to work with
our LMR? low-loss flexible 50-Ohm coaxial cables. These connectors may be installed under all
field installation conditions, because they use either silver or gold plated copper-beryllium spring
finger contacts that make positive contact with the center conductor and do not require soldering.
Small cable sizes, LMR-400 (3/8”) and LMR-600 (1/2”), require a crimp-style contact attachment
ring. When the cable is larger, the LMR-900-DB (5/8”) for example, a larger clamp method of
attachment is needed. Interfaces available include 7-16DIN, N, TNC and reverse polarity TNC
connectors.
Even though using non-solder connectors is simpler, there are still certain techniques that must be
used if a proper connection is to be achieved. Additionally, you must use the proper tools to get the
job done, including stripping, prepping and deburring instruments. Poorly installed connectors are
the most common cause of voltage standing wave ratio problems. Likewise, a good connection will
achieve the best RF transmission performance with a minimum of signal loss. The following
techniques will ensure a good connection and long-term reliability.
The typical procedure for installing the connector on cable sizes LMR-400 and LMR-600 (also is the
same procedure on DB and FR) is:
The procedure for installing the connector on cable sizes LMR-400-LLPL and LMR-600-LLPL is
very similar with a couple of differences:
For installing the ‘EZ’ connectors on LMR-900-DB, FR and LLPL cables and larger, the process is
as follows:
Table N1: Reference Chart Showing ‘EZ’ Connectors For Use with LMR, DB & FR Cables
LMR? FR Interface Description Part Coupling Inner Outer
DB Number Nut Contact Contact
400 N Male Straight EZ-400- Hex Spring Crimp
Plug NMH Finger
400 N Female Straight EZ-400-NF NA Spring Crimp
Jack Finger
400 N Female Bulkhead EZ-400- NA Spring Crimp
Jack NF-Bh Finger
400 TNC Male Straight EZ-400- Knurl Spring Crimp
Plug TM Finger
400 TNC Male Reverse EZ-400- Knurl Spring Crimp
Polarity TM-RP Finger
400 TNC Reverse EZ-400- Knurl Spring Crimp
Female Polarity TM-RP Finger
400 UHF Male Straight EZ-400- Knurl Spring Crimp
Plug UM Finger
600 N Male Straight EZ-600- Hex Spring Crimp
Plug NMH Finger
600 N Male Right EZ-600- Hex Spring Crimp
Angle NMH-RA Finger
600 N Female Straight EZ-600-NF NA Spring Crimp
Jack Finger
600 N Female Bulkhead EZ-600- NA Spring Crimp
Jack NF-BH Finger
600 TNC Male Straight EZ-600- Knurl Spring Crimp
Plug TM Finger
600 TNC Male Reverse EZ-600- Knurl Spring Crimp
Polarity TM-RP Finger
600 TNC Reverse EZ-600- NA Spring Crimp
Table N2: Reference Chart Showing ‘EZ’ Connectors For Use with LMR LLPL Cables
LLPL Interface Description Part Coupling Inner Outer
Number Nut Contact Contact
400 N Male Straight EZ-400- Hex Spring Crimp
Plug NMH-PL Finger
600 N Male Straight EZ-600- Hex Spring Crimp
Plug NMH-PL Finger
900 N Male Straight EZ-900- Hex Press Fit Clamp
Table N3: Reference Chart Showing the Proper Tools for Use with ‘EZ’ Connectors
LMR? ‘EZ’ Strip/Prep Deburr Crimp Crimp Wrenches
LMR? -FR Connector Tool Tool Handle Dies
LMR? -DB Type
LMR? -LLPL
400 (3/8”) Crimp ST-400EZ DBT-01 HX-4 Y1719 N/A
CT- Included
400/300 w/Handle
600 (1/2”) Crimp ST-600EZ DBT-01 Hex-4 Y1720 N/A
900-DB Clamp ST- N/A N/A N/A WR-900 WR-900
(5/8”) 900/1200C
1200-DB Clamp ST- N/A N/A N/A WR-1200A WR-
(7/8”) 900/1200C 1200B
1700-DB Clamp ST-1700C N/A N/A N/A WR-1700 WR-1700
(1-1/4”)
All outdoor installations should be weatherproofed with either a standard weatherproofing kit such
as the Times WK-2 kit or a cold shrink kit, also available from Times. Times LMR? coax cables are
low loss, flexible and non-kinking, unlike corrugated coax cables, which are much less flexible and
prone to kinking. Times Microwave Systems offers a complete range of LMR? cables to suit every
possible type of installation and need:
?? LMR? – Low loss coax, flexible and non-kinking; suitable for general outdoor use such as
jumpers, rooftops and short tower runs.
?? LMR? DB – Watertight outdoor cable; designed for tower feeder runs, jumpers and rooftops
applications; uses the same connectors as LMR? cable.
?? LMR? FR – Riser rated (UL/CSA listed); fire retardant; employs a low smoke non-halogen
polyolefin jacket; for use in vertical riser/access shafts – unoccupied building spaces or anywhere
that fire retardance is needed; uses the same connectors as LMR? cable.
?? LMR? – LLPL – Plenum rated (UL/CSA listed); for in-building runs; can be used in open air
handling spaces such as above drop ceilings and air plenums; flame retardant and low smoke
generating design; uses special ‘EZ’ connectors.