Cost Estimate - Electrical

This document provides a cost estimate for electrical materials for upgrading the storage tanks drainage system at an oil movement terminal. It lists 7 items being estimated, including MCCs, power supply, heat tracing cables, grounding systems, and lighting for an evaporation pond. The total estimated cost is $1,294,859.72 including a 10% contingency amount. Key materials listed are circuit breakers, cables, junction boxes, poles, and control stations.

Uploaded by

mel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views2 pages

Cost Estimate - Electrical

This document provides a cost estimate for electrical materials for upgrading the storage tanks drainage system at an oil movement terminal. It lists 7 items being estimated, including MCCs, power supply, heat tracing cables, grounding systems, and lighting for an evaporation pond. The total estimated cost is $1,294,859.72 including a 10% contingency amount. Key materials listed are circuit breakers, cables, junction boxes, poles, and control stations.

Uploaded by

mel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 2

STORAGE TANKS DRAINAGE SYSTEM UPGRADE AT OIL MOVEMENT TERMINAL

COST ESTIMATE - ELECTRICAL MATERIALS

ITEM UNIT MAT'L UNIT INST.


DESCRIPTION UNIT QTY TOTAL, USD
NO. COST, USD COST, USD

1 480 V MCC 12 - 20 MOVs


480V/277V DB, 42 ckts, 400A Set 2 1,100.00 440.00 3,080.00
Circuit breakers, 30A, 3-pole set 28 100.00 40.00 3,920.00

480 V MCC 13 - 16 MOVs


480V/277V DB, 42 ckts, 400A Set 2 1,100.00 440.00 3,080.00
Circuit breakers, 30A, 3-pole set 28 100.00 40.00 3,920.00

480 V MCC 14 - 12 MOVs


480V/277V DB, 42 ckts, 400A Set 1 1,100.00 440.00 1,540.00
Circuit breakers, 30A, 3-pole set 14 100.00 40.00 1,960.00

Sub-total 17,500.00
2 POWER SUPPLY FOR MOV ACTUATORS / EVAPORATION POND
2c x 35 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 250 30 12.00 10,500.00
2c x 16 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 300 18 7.20 7,560.00
3c x 4 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 3600 15 6.00 75,600.00
7c x 2.5 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 1000 25 10.00 35,000.00
Local Control Station EA 48 1,000 400.00 67,200.00
Junction box, explosion-proof EA 16 2000 800.00 44,800.00
Tiles, concrete, red EA 2000 5 2.00 14,000.00
Cable terminator EA 150 20 8.00 4,200.00
Terminal lugs (assorted) EA 300 6.0 2.40 2,520.00

Sub-total 261,380.00
3 HEAT TRACING CABLES
2c x 2.5 mm2, tinned copper, self-regulating heating cable, 277V M 1500 35 14.00 73,500.00
2c x 4.0 mm2, tinned copper, self-regulating heating cable, 277V M 1500 45 18.00 94,500.00
Junction boxes, heat trace, explosion proof EA 30 2,000 800.00 84,000.00

Sub-total 252,000.00
4 GROUNDING SYSTEM
1 x 70 mm2 bare copper, stranded M 1500 15 6.00 31,500.00
1 x 35 mm2 bare copper, stranded M 200 40 16.00 11,200.00
1 x 70 mm2 copper, stranded, with yellow/green PVC insulation M 200 30.0 12.00 8,400.00
1 x 35 mm2 copper, stranded, with yellow/green PVC insulation M 300 15.0 6.00 6,300.00
Ground rod, 20 mm x 3000mm, copperweld EA 20 34.0 13.60 952.00
Ground rod clamps EA 20 15.0 6.00 420.00
Terminal lugs (assorted) EA 100 4.0 1.60 560.00

Sub-total 59,332.00
5 EVAPORATION POND
Lighting Pole Ea 8 1,250 500.00 14,000.00
Floodlight Ea 16 800 320.00 17,920.00
4c x 150 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 1500 150 60.00 315,000.00
4c x 4 mm2, 0.6/1kV, Cu/SWA/XLPE/PVC M 200 15 6.00 4,200.00
480V/277V DB, corrosion-resistant EA 4 20,000 8,000.00 112,000.00
Local Control Station EA 8 1,500 600.00 16,800.00

Sub-total 479,920.00

SUB- TOTAL (1 + 2 + 3 + 4 + 5) 1,070,132.00


STORAGE TANKS DRAINAGE SYSTEM UPGRADE AT OIL MOVEMENT TERMINAL
COST ESTIMATE - ELECTRICAL MATERIALS

ITEM UNIT MAT'L UNIT INST.


DESCRIPTION UNIT QTY TOTAL, USD
NO. COST, USD COST, USD

6 TECHNICAL ASSISTANCE 107,013 107,013.20


SUB- TOTAL (1 + 2 + 3 + 4 + 5 + 6) 1,177,145.20

7 CONTINGENCY & P&TS Services 10% 117,714.52


GRAND TOTAL (1 + 2 + 3 + 4 + 5 + 6 + 7), USD 1,294,859.72

GRAND TOTAL, IN LD (1 USD = 4.48 LD) 5,800,971.55