Analysis of Rock-Lining Interaction For Circular Tunnels Using The Finite Element Simulation
Analysis of Rock-Lining Interaction For Circular Tunnels Using The Finite Element Simulation
net/publication/315783464
Analysis of rock-lining interaction for circular tunnels using the finite element
simulation.
CITATIONS READS
0 165
3 authors, including:
3 PUBLICATIONS 1 CITATION
Ain Shams University
69 PUBLICATIONS 265 CITATIONS
SEE PROFILE
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Fathalla M. El-Nahhas on 05 April 2017.
1/9
2. FINITE ELEMENT SIMULATION
Idealized ground profile at the Whitemud-Creek Tunnel is shown in Fig. 1. Analysis of
displacements and stresses around the tunnel was carried out using a 2-D plane strain finite
element package ANSYS version 5.6 taking into consideration the linear-elastic behavior of the
lining and the ground materials. The finite element mesh used to carry out the simulation for the
excavation phase is shown in Fig. 2 with 2836 nodes and 5270 2-D elements representing ground
layers. The mesh used for the interaction simulation phase is shown in Fig. 3 with 1057 nodes
and 1739 2-D elements representing the ground and the lining material.
3/9
The values of radial displacements on the tunnel perimeter are shown in Fig. 6. The average
radial displacement ahead the tunnel face is estimated as 6.4mm along the perimeter of excavated
tunnel which resulted from the releasing of stresses after excavation process. This value on the
Ground Reaction Curve is estimated as 6mm. The values of vertical, horizontal and radial
displacements at the tunnel crown, spring line and invert of the tunnel are listed in Table 1.
Table 1: Values of displacements due to excavation
Vertical Horizontal Radial
Location
displacement displacement displacement
Crown 10mm 0 10mm
Spring line 1mm 4mm 4.1mm
Invert 6.8mm 0 6.8mm
The vertical in-situ stresses around the tunnel are changed due to excavation process. These
changes are shown in Fig. 7. It is obvious that the changes of stresses at the crown and the invert
are tension due to the inward movement of the ground in the vertical direction. It is downward at
the crown and upward at the invert. But, at spring line the increase of stresses is compression
because of stress arching.
The increase of horizontal stresses at the crown and the invert is compression due to stress
arching and at the spring line, the change of horizontal stresses is tension due to the inward
ground movement in the horizontal direction. The values of change in horizontal stresses are
shown in Fig. 8 and the values of vertical, horizontal and radial stresses at the crown, spring line
and invert of the tunnel are summarized in Table 2.
Table 2 Values of change in stresses due to excavation
Vertical Horizontal Radial
Location
stresses stresses stresses
Crown 586.5kPa -121kPa 598.9kPa
Fig.11 and Fig.12 illustrate the change in vertical and horizontal stresses in rock mass after
steel ribs lining activation. The values of the change in vertical, horizontal and radial stresses at
the tunnel crown, spring line and invert are summarized in Table 4.
4/9
Table 3 Values of displacements in rock mass due to lining activation
Vertical Horizontal Radial
Location
displacement displacement displacement
Crown 0.7mm 0 0.7mm
The final equilibrium stresses of the ground profile are estimated as the sum of the in-situ
stresses as compression and the induced stresses at the excavation and lining phases.
σ final = -σ º + σ excavation phase + σ lining phase (1)
Fig.13 and Fig.14 illustrate the final vertical and horizontal stresses of the ground profile at
equilibrium position. The values of the final vertical, horizontal and radial stresses in rock mass
at the tunnel crown, spring line and invert are listed in Table 5.
For the tunnel perimeter the radial displacement after steel ribs lining activation is shown in
Fig.15.
Table (5) Values of Final Stresses in Rock Mass
Vertical Horizontal Radial
Location
stresses stresses stresses
Crown -187.4kPa -660.1kPa -686.2kPa
Spring line -1718.7kPa -131.34kPa -1723.7kPa
Invert -219kPa -815.1kPa -844kPa
The total average radial displacement is equal to the sum of the average radial displacement
of the excavation and interaction phases, which are equal to 6.4 mm and 0.6 mm respectively.
The resulted value is equal 7 mm while the value estimated using the Convergence-Confinement
approach varies between 7.5 to 9 mm as shown in Fig.16. It is clear that the resulted values of the
two analysis procedures are compatible. The final acting pressure on the steel ribs lining at the
tunnel crown, spring line and invert are summarized in Table 6 and Fig.17. The average acting
pressure on steel ribs lining is equal to 215 kPa while the average estimated value from the
Convergence-Confinement approach is equal to 228 kPa as shown in Fig.16. It is clear that the
resulted values of the two analysis procedures are compatible.
5/9
Table (6) Final acting pressure on steel ribs lining
Location Final acting pressure on lining
(kPa)
Crown 144.3
Spring line 339.2
Invert 162
6.3 Evaluation of the Ground Movements and Stresses Associated with Shotcrete and Steel
Ribs Lining
The radial displacement along tunnel perimeter after shotcrete with steel ribs lining
activation is shown in Fig.18. The total average radial displacement is equal to the sum of the
average radial displacement of the excavation and interaction phases, which are equal to 6.6 and
0.4 mm respectively. The resulted value is equal 7 mm, while the average estimated value from
the Convergence-Confinement approach is equal to 11.4 mm as shown in Fig.19. The values of
final radial displacements and radial stresses in rock mass at tunnel crown, spring line and invert
are summarized in Table 7. The final acting pressure on the shotcrete with steel ribs lining at the
tunnel crown, spring line and invert are summarized in Table 8.
Table 7 Values of final radial displacement and final radial stresses in rock mass
Final radial Final radial
Location
displacements stresses
Crown 11mm 709.7kPa
The average acting pressure on shotcrete with steel ribs lining is equal to 94 kPa while the
average estimated value from the Convergence-Confinement approach is equal to 115 kPa as
shown in Fig.19. It is clear that the resulted values of the two analysis procedure are similar.
The final acting pressure on shotcrete with steel ribs lining are shown in Fig.20.
It should be noted that the value of released stresses in excavation phase is equal to 75% of the
total in-situ stresses because the activation of the two lining systems (steel ribs and shotcrete)
take more time than the activation of steel ribs only. Therefore, the value of average radial
displacement is greater than the corresponding value in case of steel ribs lining system but the
efficiency of this system is better because its load capacity is higher.
6/9
Finally, after calibration of Whitemud-Creek Tunnel by the finite element analysis with the
Convergence-Confinement approach which was guided by field measurements, the results proved
that the utilized finite element procedure is a good procedure for the ground-lining interaction.
Hence, the finite element analysis was used for a parametric study to evaluate the effect of
different parameters on rock-lining interaction.
7. PARAMETRIC STUDY
One of the main objectives of this study is to investigate the effect of different parameters
on the behavior of excavated tunnel before and after lining activation. The analysis followed the
same procedure which had been applied in the analysis of the case of Whitemud-Creek Tunnel
taking into consideration the different values of the tunnel radius and the depth of excavated
tunnel through different qualities of rock ranging between very poor rock and poor rock.
The parametric study has been conducted for circular tunnel as follows:
Circular tunnel
R1 = 3m R2 = 4.5m R3 = 6m
d1 = 30m d2 = 40m d3 = 50m d
R
The depth of the tunnel (d) is measured from ground surface to the center line of tunnel.
Table 9 contains the geotechnical properties of different rock mass qualities which are used for
the parametric study.The purpose of this study is to display the effect of the different parameters (
such as, the dimensions of the tunnel Young's modulus (E), depth of the overburden above the
tunnel center line (d), shear modulus (G) and unconfined compressive strength (σci)) on the
displacement of the ground and the lining and the final load of the lining.
Table 9 Geotechnical properties of different rock mass qualities
σci Erm G γ
Type of rock RMR GSI υ
MPa MPa MPa kN/m3
Very poor rock 5 15 10 0.3 500 192.3 22.1
Poor rock 10 30 25 0.25 1000 400 24
Where
σci unconfined compressive strength.
RMR Rock Mass Rating.
GSI Geotechnical Strength Index.
υ Poisson’s ratio.
Erm Young’s modulus of rock mass.
G Shear modulus.
γ Unit weight.
Fig.21 shows the finite element mesh used to carry out the simulation of the circular tunnel
shape for the parametric study using the material properties given in Table 9. Due to the quality
of rock mass, the total value of each force is divided into two ratios depending on the excavation
and interaction phases as follows:
80% of each force will be applied in the excavation phase to simulate the stress
releases after excavation.
7/9
20% of each force will be applied in the interaction phase to simulate the ground-
lining interaction to achieve the state of equilibrium between rock and shotcrete
with steel ribs lining.
The changes of average radial displacement and radial stresses are the major aim of the
obtained results for each model analysis. The analysis consists of 18 models for circular tunnel
before lining activation for very poor rock and poor rock. Also, the analysis consists of 2 models
for circular shape with diameter D=12 m at depth equal to 50 m excavated through very poor
rock as the worst case of study and poor rock to be lined with shotcrete with steel ribs lining
system. This lining system was chosen because the very poor rock in some region of the tunnel
section may contain small fragments or huge separated blocks which would probably fall down.
Therefore, we need a fast installation and safe lining system. The results for different circular
tunnel cases before and after lining activation is shown in Tables 10, 11 and 12. Figures 22 to 25
show the average radial displacement for different circular tunnel cases due to tunnel excavation.
Table 10 The conclusion of results for different circular tunnel cases due to tunnel
excavation
Average radial
Tunnel condition R (m) d (m)
displacement (mm)
Very poor rock 3 30 3.8
Very poor rock 3 40 5
Very poor rock 3 50 6.3
Very poor rock 4.5 30 5.7
Very poor rock 4.5 40 7.5
Very poor rock 4.5 50 9.6
Very poor rock 6 30 7.6
Very poor rock 6 40 10.4
Very poor rock 6 50 13.2
Poor rock 3 30 2
Poor rock 3 40 2.7
Poor rock 3 50 3.4
Poor rock 4.5 30 2.8
Poor rock 4.5 40 3.8
Poor rock 4.5 50 5
Poor rock 6 30 4
Poor rock 6 40 5.5
Poor rock 6 50 6.7
8/9
Table 11 The conclusion of results for circular tunnel (D=12m, d=50m) excavated through
very poor rock
Average radial pressure
Average radial
Tunnel condition due to lining activation
displacement (mm)
(kPa)
Before lining activation 13.2 Not applicable
After lining activation 1 85.8
Final 14.2 85.8
Table 12 The conclusion of results for circular tunnel (D=12m, d=50m) excavated through
poor rock
Average radial pressure
Average radial
Tunnel condition due to lining activation
displacement (mm)
(kPa)
Before lining activation 6.7 Not applicable
After lining activation 0.7 44.8
Final 7.4 44.8
REFRENCES
[1] Carranza-Torres , C. and Fairhurst , C. (2000), “Application of The Convergence-
Confinement Method of Tunnel Design to Rock Masses that Satisfy The Hoek-Brown
Failure Criterion.” Journal of Tunnelling and Underground Space Technology, Vol. 15,
No. 2, Published by Elsevier Science Ltd. pp. 187-213.
[2] El-Nahhas , F. (1977), “Field Measurements in two Tunnels in the City of Edmonton” ,
MSc. Thesis , University of Alberta , Edmonton , Alberta , Canada ,85 p.
[3] Bell , F. G. “Engineering Properties of Soil and Rock Mechanics”, pp 268-310.
[4] Thomson , S. and EL-Nahhas , F. (1980), “ Field Measurements in Two Tunnels in
Edmonton, Alberta” , Canadian Geotechincal Journal, Vol. 17, No. 1 , pp 20-33.
9/9