Chapter 37 Interchanges
Chapter 37 Interchanges
INTERCHANGES
Chapter Thirty-seven
INTERCHANGES
Table of Contents
Section Page
37-i
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Table of Contents
(Continued)
Section Page
37-ii
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Table of Contents
(Continued)
Section Page
37-iii
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Table of Contents
(Continued)
Section Page
37-iv
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
Chapter Thirty-seven
INTERCHANGES
AASHTO defines an interchange as a system of interconnecting roadways in conjunction with
one or more grade separations that provide for the movement of traffic between two or more
roadways on different levels. The operational efficiency, capacity, safety, and cost of the
highway facility are largely dependent upon its design. Chapter 37 provides guidance in the
design of interchanges including interchange types, selection, layout, operations, spacing,
freeway ramp terminals, ramps, and ramp/crossroad terminals. Information that is also
applicable to interchanges is included in the following chapters:
Chapter 15 discusses the procedures and content for interchange type and design
studies.
Chapter 44 discusses freeway new construction and reconstruction design criteria, lane
drops, frontage roads, grade separations, and access control along the freeway.
37-1 GENERAL
37-1.01 Responsibilities
The district is responsible for determining the need for, location of, type of, and design of
interchanges. For interchange types other than the conventional diamond and parclo Type C,
BDE involvement in type studies is recommended because of the larger number of alternatives
requiring analysis and the typically higher costs; see Chapter 15.
37-1.02 Guidelines
The need for an interchange will vary based on site-specific conditions. Consider the following
guidelines when determining the need for an interchange:
37-1.1
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
Where signals are warranted within 10 to 20 years, plan for the future
development of an interchange. Purchase the access rights for
approximately 1000 ft to 1200 ft (300 m to 350 m) along each leg of the
major crossroad.
37-1.2
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
5. Road-User Benefits. If an analysis reveals that road-user benefits over the service life of
the interchange will exceed costs, then an interchange may be considered. The
designer must consider all costs including right-of-way, construction, maintenance, and
user costs in the analysis. For additional guidance, the designer may refer to the
AASHTO publication A Manual on User Benefit Analysis of Highway and Bus-Transit
Improvements.
6. Access. An interchange may be required in an area where access availability from other
sources is not practical, and the freeway is the only facility that serves the area.
7. Traffic Volumes. Although there are no specific traffic volumes that warrant an
interchange, consider providing an interchange where the traffic volumes at an
intersection are at or near capacity and where other improvements are not practical.
Section 111 of Title 23, United States Code (23 USC 111) identifies that all agreements
between FHWA and IDOT for the construction of projects on the Interstate System must contain
a clause that IDOT will not add any points of access to, or exit from, the project in addition to
those approved by FHWA in the plans for the project, without the prior approval of FHWA. 23
CFR 625 designates those criteria and policies that are acceptable to FHWA for the geometric
and structural design of highways, including Interstate facilities.
The original FHWA policy regarding new or revised access points to existing Interstate facilities
was first published in the Federal Register on October 22, 1990, revised in the February 11,
1998 Federal Register, and then revised again in the August 27, 2009 Federal Register. The
February 1998 revision incorporates the planning requirements of the 1991 Intermodal Surface
Transportation and Efficiency Act, clarifies the coordination between the access request and
environmental procedures, and updates the policy language at various locations. The August
2009 revisions were made to reflect the direction provided in the Safe, Accountable, Flexible,
Efficient Transportation Equity Act: A Legacy for Users (SAFETEA–LU), to clarify the
operational and safety analysis and assessment of impacts that provides the basis for proposed
changes in access to the Interstate System, and to update language at various locations to
reference Federal laws, regulations, and FHWA policies. Additional guidance from FHWA
Headquarters office was established in 1996 and 1997. This guidance allowed FHWA Division
Offices to approve more Interstate revisions in access and established a two-step process for
approving these changes.
New or revised access points to the existing Interstate System will be reviewed against the
criteria in Section 37-1.03(b). Sections 37-1.03(d) and 37-1.03(e) define the information
required to be included in final submittals to FHWA when requesting approval for revisions in
Interstate access. Section 37-1.03(c) provides the procedures obtaining approvals from IDOT
and/or FHWA.
37-1.3
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
37-1.03(b) Applicability
In general, all new and/or revised access points should be minimized on existing fully access-
controlled facilities. Each entrance and exit point on the mainline, including “locked gate” access
(e.g., utility opening), is defined as an access point. For example, a diamond interchange
configuration has four access points. Revised access is considered to be a change in the
existing interchange configuration although the number of access points may not change. For
example, replacing one of the direct ramps of a diamond interchange with a loop or changing a
cloverleaf interchange into a fully directional interchange is considered to be a revised access.
The criteria in Section 37-1.03 is applicable to new or revised access points to existing fully
access-controlled facilities (Interstate and non-Interstate facilities) regardless of the funding
source. Consequently, it applies to private developers, and any changes to an access-
controlled facility, which may be required of the private developer by IDOT or a local agency.
Each access revision will need to be analyzed on a case-by-case basis. Consider the following:
new partial interchange or new ramps to-from continuous frontage road that
create a partial interchange (e.g., slip ramps);
locked gate access (e.g., access via locked gates by privately employed
personnel); and
2. Revisions not Requiring FHWA Access Approval. The following revisions to access-
controlled facilities are not considered a change in access and, therefore, do not require
FHWA access approval, but still may require BDE approval:
37-1.4
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
d. Auxiliary Lanes. This includes the addition of a single auxiliary lane between two
adjacent interchange ramps. The single auxiliary lane should not function as a
mainline travel lane.
iii. Design Exceptions. If the design criteria cannot be met, obtain a design
exception for the improvement. See Section 31-7 for the procedures for
obtaining a design exception.
37-1.5
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
f. Addition of On-Ramp Lanes. This consists of adding a lane to a single lane on-
ramp, resulting in a two-lane on-ramp. Although an individual access justification
approval is not required, the district will be responsible for conducting an
operational analysis (e.g., weaving, capacity, signing).
h. Signing and Pavement Markings. This includes new signing, striping, and/or
resurfacing of an on-ramp or off-ramp where geometric features are not changed.
BDE and FHWA must approve all proposed changes in interchange configurations on the
Interstate System, even if the number of access points does not change. For proposed changes
on non-Interstate freeways, BDE or the Bureau of Operations will review and approve any access
changes (i.e., FHWA will not be regularly involved for these facilities).
The following procedures are applicable where 1) the highway is on the State highway system
and Federal funds were used for right-of-way and/or construction costs of the roadway segment;
and 2) the highway is access controlled and the proposed access revisions will modify previous
commitments made in environmental documents:
2. Secondary Impacts. Determine the secondary impacts associated with the proposed
access revisions based on traffic-induced impacts on the State highway facility and on
the potential environmental impacts on the surrounding area. Because the area of
influence on the highway facilities and surrounding land use will vary, describe the limits
of influence for each case prior to determining impacts.
37-1.6
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
3. Outside Agency Proposals. The district will recommend whether IDOT or the agency
requesting the revision will conduct the studies. BDE will review and approve Phase I
reports.
4. FHWA Coordination. BDE usually will review and approve the interchange type and
interchange design studies (IDS) using the Department’s Certification Acceptance
procedures except where the action is proposed on the Interstate system. For
Interstates, FHWA must also agree on the type and the design details, see Section 37-
1.03(d). IDOT must discuss with FHWA any proposed access control revisions on the
NHS at scheduled district coordination meetings.
5. Central Office Processing. Access control revisions along a freeway will be processed
by the Central Office in the following manner:
b. BDE. Where design studies and/or construction funds are used in the proposed
action requiring access control revisions, BDE will review and process the
proposed action.
f. FHWA Approval. Submit the Access Justification Report (AJR) to the FHWA
Division Office for approval. This submission will be a “stand-alone” document
that will show reasonable care has been performed and confirm future safety and
traffic operations along the Interstate corridor will not be adversely affected by
37-1.7
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
g. Filing. BDE will retain on file the approved revision in access submittal.
FHWA approval is only required where there are new or revised access points to the Interstate
System. For non-Interstate routes, BDE or the Bureau of Operations will review and approve
any access changes. The following will apply to Interstate routes:
1. Design Criteria. All FHWA approvals for new, added or revised access is conditioned
upon IDOT complying with all applicable Federal rules and regulations. For Illinois, this
design criteria is contained in the BDE Manual and the Illinois Highway Standards which
meet or exceed the criteria presented in the AASHTO publications A Policy on
Geometric Design of Highways and Streets and A Policy on Design Standards -
Interstate System.
2. FHWA Concept Approval. Concept approval is the first step in the FHWA approval
process and involves a determination of safety engineering, and operational
acceptability. Ideally, it should be done as soon as possible and when the Department
has a good understanding of the scope of the improvement. The FHWA Division Office
and IDOT will develop a consensus on proposed access concepts at the coordination
meetings. FHWA concept approval will need to be received from either the FHWA
Headquarters Office (Washington, D.C.) or from the FHWA Illinois Division Office
(Springfield, IL). The following identifies the FHWA office that will submit the approval:
37-1.8
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
b. FHWA Illinois Division Office Concept Approval. The FHWA Division Office and
the Department will develop a consensus on proposed access concepts at
coordination meetings, which are documented in the Access Justification Report
(AJR); see Section 37-1.03(e). FHWA Division Office concept approval will be
given by the FHWA Division Administrator. Send the AJR to the FHWA Division
Office with signature lines for the FHWA Division Office Field Engineering
Manager (FEM) (recommend approval) and for the FHWA Division Office
Division Administrator (for approval). The signed AJR will document FHWA
concept approval. Once signed, the AJR will be sent to IDOT. The FHWA
Division Office gives concept approval for the following types of Interstate revised
access:
3. FHWA Final Approval. The FHWA Division Administrator gives final approval for all
types of Interstate access changes. Concept Approval and completion of the NEPA
process are needed for the Final Approval of Access Revision. No additional information
is required for the final approval request unless any conditions previously noted in the
AJR have changed substantially.
37-1.9
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
2. Purpose. Describe the purpose and need for the new or revised access point (i.e., why
it is needed).
5. Concerns. List any known areas of concern (e.g., environmental, safety). Always
include a crash analysis summary for all new or revised access requests. Identify all
presently known “Five Percent Report Locations” within or adjacent to the project limits,
and proposed mitigation measures to improve safety in the future. FHWA must be
assured that there will be steps taken so that either no impact or only minimal adverse
impact on safety and operation of the Interstate facility itself will occur.
6. Communities. Note the distances to and size of communities or facilities directly served.
8. Design Exceptions. Clearly identify any necessary design exceptions from currently
adopted BDE design criteria; see Section 31-7.
9. Traffic Signals/Signing. For each request, include a conceptual plan of the type and
location of the signs proposed to support each design alternative. Identify any additional
proposed traffic signalization, if applicable.
10. Lane Balance. Describe how the interchange will provide lane balance and the basic
number of lanes.
11. Existing Facilities. FHWA policy states: “The need being addressed by the request
cannot be adequately satisfied by existing interchanges to the Interstate, and/or local
roads and streets in the corridor can neither provide the desired access, nor can they be
reasonably improved (such as access control along surface streets, improving traffic
control, modifying ramp terminals and intersections, adding turn bays or lengthening
storage) to satisfactorily accommodate the design-year traffic demands(23 CFR
625.2(a)).” The intent of this requirement is to demonstrate that an access point is
needed for regional traffic needs and not to solve local system needs or problems. The
37-1.10
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
facility should not be allowed to become part of the local circulation system, but be
maintained as the main regional and interstate highway it was intended to be.
In the case of adding a new interchange or new ramp(s), evaluate or consider whether
existing or possible future roads or streets generally parallel to the Interstate facility that
could be used as a connection to existing adjacent interchange ramps in lieu of adding a
new interchange or ramps.
12. Transportation System Management. FHWA policy states: “The need being addressed
by the request cannot be adequately satisfied by reasonable transportation system
management type improvements (such as ramp metering, mass transit, and HOV
facilities), geometric design, and alternative improvements to the Interstate without the
proposed change(s) in access (23 CFR 625.2(a)).” The intent of this requirement is to
ensure that all reasonable alternatives, including improvements to the existing local
roads and streets in lieu of new access, have been fully considered.
13. Access Connections and Design. FHWA policy states: “The proposed access connects
to a public road only and will provide for all traffic movements. Less than “full
interchanges” may be considered on a case-by-case basis for applications requiring
special access for managed lanes (e.g., transit, HOVs, HOT lanes) or park and ride lots.
The proposed access will be designed to meet or exceed current standards(23 CFR
625.2(a), 625.4(a)(2), and 655.603(d)).” The intent of this requirement is that, except in
the most extreme circumstances, all interchanges should provide for all basic
movements. Partial interchanges usually have undesirable operational characteristics.
If circumstances exist where a partial interchange is considered appropriate, then
commitments to the FHWA, possibly even purchase of necessary right-of-way during the
initial project stage for future completion, must be made by IDOT. Special purpose
access for HOV’s, for transit vehicles, or for park and ride lots should be treated as
special cases and the movements to be provided decided on a case-by-case basis.
14. Transportation Land Use Plans. FHWA policy states: “The proposal considers and is
consistent with local and regional land use and transportation plans. Prior to receiving
final approval, all requests for new or revised access must be included in an adopted
Metropolitan Transportation Plan, in the adopted Statewide or Metropolitan
Transportation Plan (STIP or TIP) and the Congestion Management Process within
transportation management areas, as appropriate, and as specified in 23 CFR part 450,
and transportation conformity requirements of 40 CFR parts 51 and 93.” The intent of
this requirement is to cause sufficient review and coordination so as not to have piece-
meal consideration of added access and to avoid as much as practical future conflict
with other, possibly more needed, access. The request should include a discussion as
to how the current proposal fits into the overall plans for the area and, if it is an addition
to the current plans for the area, how it fits in and affects the current plans. Added
access requests do not have to be included in official transportation plans or approved
by MPOs or similar organizations prior to submittal. All coordination may be completed
after access approval and as part of the normal project development process. The
expectation here is that any proposal is considered in view of currently known plans for
37-1.11
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
transportation facilities and/or land use planning. This is especially important where
several new interchanges are anticipated.
15. Comprehensive Interstate Network Study. FHWA policy states: “In corridors where the
potential exists for future multiple interchange additions, a comprehensive corridor or
network study must accompany all requests for new or revised access with
recommendations that address all of the proposed and desired access changes within
the context of a longer-range system or network plan (23 U.S.C. 109(d), 23 CFR
625.2(a), 655.603(d), and 771.111).” The intent of this requirement is to analyze and
consider all proposed changes in access for an area at the same time. See Section 37-
1.03(d) for guidance regarding adjacent interchange spacing that trigger the need for
FHWA approval. If a new or revised interchange is being proposed and another new or
revised adjacent interchange is being planned and programmed by IDOT then analyze
both changes together.
16. Coordination with Transportation System Improvements. FHWA policy states: “When a
new or revised access point is due to a new, expanded, or substantial change in current
or planned future development or land use, requests must demonstrate appropriate
coordination has occurred between the development and any proposed transportation
system improvements (23 CFR 625.2(a) and 655.603(d)). The request must describe
the commitments agreed upon to assure adequate collection and dispersion of the traffic
resulting from the development with the adjoining local street network and Interstate
access point (23 CFR 625.2(a) and 655.603(d)).” It is recognized that more and more
private involvement in transportation improvements will be happening in the future. The
intent of this requirement is not to try to control developers and their plans through IDOT,
which has no such direct powers. It is incumbent upon IDOT, however, to ensure that
the highway facilities are developed in an orderly and coordinated manner to serve the
public. Therefore, when private development is clearly the driving force behind the need
for access, it is only reasonable that the IDOT and the developer work closely together in
order to develop the access to achieve mutual benefits with minimal adverse impact on
travelers. Stage construction could be used where extensive private development is not
expected to be completed for several years. The developer might be required to have
certain parts of the local circulation system ready before ramps can be constructed or
opened to traffic. In some heavily congested areas, the developer might be required to
provide ride-sharing incentives or even assist in providing transit facilities. The intent is
therefore to accomplish any coordination that might be possible, even if it is only to know
what each is doing and when.
This coordination and cooperation is appropriate where a developer has agreed to fund
or perhaps even construct access at the same time the IDOT is planning or is already in
the process of improving that particular section of the route. It is only reasonable that
these activities be coordinated to ensure compatibility.
17. Status of Planning and NEPA. FHWA policy states: “The request for new or revised
access contains information relative to the planning requirements and the status of the
environmental processing of the proposal.” The intent of this requirement is to confirm
37-1.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
and report information relative to the status of the planning and NEPA processes, with
regard to the access request (e.g., anticipated schedule dates, public hearing dates,
public support or opposition, recent activities, future activities).
18. Operational Analysis. FHWA policy states: “An operational and safety analysis has
concluded that the proposed change in access does not have a significant adverse
impact on the safety and operation of the Interstate facility (which includes mainline
lanes, existing, new, or modified ramps, ramp intersections with crossroad) or on the
local street network based both the current and the planned future traffic projections.
The analysis shall, particularly in urbanized areas, include at least the first adjacent
existing or proposed interchange on each side of the proposed change in access (23
CFR 625.2(a), 655.603(d) and 771.111(f)). The crossroads and other roads and the
local street network, to at least the first major intersection on either side of the proposed
change in access, shall be included in this analysis to the extent necessary to fully
evaluate the safety and operational impacts that the proposed change in access and
other transportation improvements may have on the local street network (23 CFR
625.2(a) and 655.603(d)). Requests for a proposed change in access must include a
description and assessment of the impacts and ability of the proposed changes to safely
and efficiently collect, distribute and accommodate traffic on the Interstate facility, ramps,
intersection of ramps with crossroad, and local street network (23 CFR 625.2(a) and
655.603(d)). Each request must also include a conceptual plan of the type and location
of the signs proposed to support each design alternative (23 U.S.C. 109(d) and 23 CFR
655.603(d)).” The intent of this requirement is to ensure that sufficient operational
analyses are made to determine the impact of the revised or new access on the
Interstate operation. For consistency, it is anticipated that the current Highway Capacity
Manual analysis procedures will be used.
The operational analysis of the proposed change will need to be designed to a design
year that is 20 years after the date when the construction of the project is scheduled to
be complete, and open to the traveling public.
The following additional items are required by the current FHWA Illinois Division
Administrator for any Access Justification Report (AJR) to even be considered for
approval:
37-1.13
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
The operational analysis should typically include some or all of the information in Items
19 and 20.
19. Interchange Location Map. Include a dimensioned, detailed drawing of the design
elements of the existing and proposed change conditions, including, as applicable:
project limits,
adjacent interchange(s),
ramp to be added,
ramp to be removed,
relocation of ramp gore,
configuration,
travel lanes and shoulder widths,
ramp radii,
ramp grades,
acceleration lane lengths,
deceleration lane lengths,
taper lengths,
auxiliary lane lengths,
taper or parallel type exit ramps,
truck climbing lane(s),
37-1.14
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
The drawing, and/or report wording, should identify all presently known pertinent
engineering design details of the proposed change. Clearly identify any design
exceptions, and compare them with the latest BDE and AASHTO criteria.
Include another drawing showing the traffic volumes for all turning movements as well as
mainline, ramp, and local road traffic volumes. Identify current and design year ADT and
DHV.
20. Highway Capacity Analysis. Use the current Highway Capacity Manual (HCM), or
current version of the Highway Capacity Software (HCS), for the needed engineering
analyses. An acceptable engineering analysis for determining engineering acceptability
and feasibility will need to be determined jointly by FHWA and IDOT. Include all the
following engineering analysis, unless otherwise agreed to by BDE and FHWA:
a. Existing Peak Hour Volumes. Provide a plan view map, with ramps and mainline
through lanes labeled with Existing “AM Peak Hour” and “PM Peak Hour”
volumes.
b. Design Year No-Build Peak Hour Volumes. Provide a plan view map, with ramps
and mainline through lanes labeled with the Design Year No-Build “AM Peak
Hour” and “PM Peak Hour” volumes.
c. Design Year Build Peak Hour Volumes. Provide a plan view map, with ramps
and mainline through lanes labeled with the Design Year Build “AM Peak Hour”
and “PM Peak Hour” volumes.
e. Existing Peak Hour Levels of Service. Provide a plan view map, with ramps,
mainline through lanes, and crossroads labeled with calculated Existing “AM
Peak Hour Level of Service” values and “PM Peak Hour Level of Service” values.
f. Design Year No-Build Peak Hour Levels of Service. Provide a plan view map,
with ramps, mainline through lanes, and crossroads labeled with calculated
Design Year No-Build “AM Peak Hour Level of Service” values and “PM Peak
Hour Level of Service” values.
g. Design Year Build Peak Hour Levels of Service. Provide a plan view map, with
ramps, mainline through lanes, and crossroads labeled with calculated Design
Year Build “AM Peak Hour Level of Service” values and “PM Peak Hour Level of
Service” values.
37-1.15
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES March 2016
p. Weave Area Analyses of the Design Year “Build” Conditions. Preferably, provide
program outputs from the latest release of the HCS for all weaving areas.
37-1.16
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Where interchanges are spaced farther apart, freeway operations, level of service, and safety
between connecting facilities are improved. Desirably, the spacing between interchanges on
the average should not be less than 2 miles (3 km) in urban areas, 4 miles (6 km) in suburban
areas, and 7.5 miles (12 km) in rural areas. These values allow adequate distances for an
entering driver to adjust to the freeway environment, for proper weaving maneuvers between
entrance and exit ramps, and for adequate signing distances. However, considering the effects
of existing streets and highways, traffic operations, and social considerations, the spacing
between adjacent interchanges may vary considerably. Therefore, the minimum distance
between adjacent interchanges should not be less than 1 mile (1.5 km) in urban areas, 2 miles
(3 km) in suburban areas, and 3 miles (5 km) in rural areas. In urban areas, a spacing of less
than 1 mile (1.5 km) may be developed by using collector-distributor roads.
The basic number of lanes is the minimum number of lanes designated and maintained over a
significant length of a route based on the overall operational needs of that section. The number
of lanes should remain constant over short distances. For example, do not drop a lane at the
exit of a diamond interchange and then add it at the downstream entrance simply because the
traffic volume decreases between the exit and entrance ramps. Likewise, do not drop a basic
lane between closely spaced interchanges simply because the estimated traffic volume does
not warrant the higher number of lanes. Lane drops should only occur where there is general
lowering of the traffic volumes on the freeway route as a whole.
Lane balance refers to certain principles that apply at freeway exits and entrances:
1. Exits. The number of approach lanes on the highway should equal the sum of the
number of mainline lanes beyond the exit plus the number of exiting lanes minus one;
see Figure 37-2.A. An exception to this principle would be at cloverleaf loop ramp exits
that follow a loop ramp entrance or at exits between closely spaced interchanges (e.g.,
interchanges where the distance between the taper end of the entrance terminal (1 ft
(300 mm) stub) and the beginning taper (1 ft (300 mm) stub) of the exit terminal is less
than 1500 ft (450 m) and a continuous auxiliary lane is used between the terminals). In
these cases, the auxiliary lane may be dropped at a single-lane exit with the number of
lanes on the approach roadway being equal to the number of through lanes beyond the
exit plus the lane on the exit.
2. Entrances. At entrances, the number of lanes beyond the merging of the two traffic
streams should be not less than the sum of the approaching lanes minus one; see Figure
37-2.A.
37-2.1
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-2.A
37-2.2
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
3. Travel Lanes. Reduce the number of travel lanes on the freeway only one lane at a time.
For example, dropping two mainline lanes at a two-lane exit ramp would violate the principle of
lane balance. One lane should provide the option of remaining on the freeway. Lane balance
would also prohibit immediately merging both lanes of a two-lane entrance ramp into a highway
mainline without the addition of at least one additional lane beyond the entrance ramp. Figure
37-2.A illustrates how to coordinate lane balance and the basic number of lanes at an
interchange. Figure 37-2.A also illustrates how to achieve lane balance at the merging and
diverging points of branch connections.
The capacity of an interchange will depend upon the operation of its individual elements that
include:
The basic capacity reference is the Highway Capacity Manual (HCM). The HCM and the
Highway Capacity Software (HCS) provide the analytical tools required to analyze the level of
service for each element listed above. Other capacity analysis programs and techniques may
be used provided they are approved by BDE. To be eligible for approval, the output results of
other programs and techniques must compare closely with the HCS.
Level of service values presented in Chapter 44 for freeways will also apply to interchanges.
Desirably, the level of service of each interchange element should be equal to the level of
service provided on the basic freeway section. Individual elements should not operate at more
than one level of service below that of the basic freeway section. In addition, the operation of
the ramp/crossroad intersection in urban areas should not impair the operation of the mainline.
This will likely involve a consideration of the operational characteristics on the minor road for
some distance in either direction from the interchange. For most projects, the district
geometrics engineer will be responsible for conducting or reviewing the capacity analysis at
interchanges.
As applied to interchange design, auxiliary lanes are most often used to comply with the
principle of lane balance, to increase capacity, to accommodate weaving, or to accommodate
entering and exiting vehicles. Operational efficiency of the freeway may be improved if a
continuous auxiliary lane is provided between entrance and exit terminals where interchanges
37-2.3
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
are closely spaced. An auxiliary lane may be dropped at an exit if properly signed and
designed. The following statements apply to the use of an auxiliary lane within or between
interchanges:
1. Within Interchange. Figure 37-2.B provides the basic schematics of alternative designs
for adding and dropping auxiliary lanes within interchanges. The selected design will
depend upon traffic volumes for the exiting, entering, and through movements.
2. Between Interchanges. Where interchanges are closely spaced, the designer should
provide an auxiliary lane where the distance between the taper end of the entrance
terminal and beginning taper of the exit taper is less than 1500 ft (450 m). Figure 37-2.C
illustrates where an auxiliary lane is used between two closely spaced interchanges.
Auxiliary lane drops beyond the interchange may be merged approximately 2500 ft (750 m)
beyond the influence of the last interchange. Design details for auxiliary lane drops beyond an
interchange are provided in Chapter 44. Design details for dropping auxiliary lanes at exits or
adding them at entrances are provided in Section 37-6. If the auxiliary lane is dropped at a
single lane exit, a recovery area beyond the gore should be provided as shown in Figure 37-2.B.
Where certain sight distance restrictions are unavoidable (e.g., on structures), the recovery area
should be extended 500 ft to 1000 ft (150 m to 300 m) downstream from the exit. This distance
should be increased to 1500 ft (450 m) or more with complex designs.
The major route should flow continuously through an interchange. For freeway and expressway
routes that change direction, the driver should not be required to change lanes or exit to remain
on the major route. Route continuity without a change in the basic number of lanes is consistent
with driver expectancy, simplifies signing, and reduces the decision demands on the driver.
Interchange configurations should not necessarily favor the heavier traffic movement. Other
marked routes that turn or exit at an interchange can be accomplished by a single-lane ramp if
capacity is adequate. If these ramps are longer than ½ mile (800 m), consider providing a two-
lane ramp for better traffic operations.
37-2.07 Uniformity
Interchange configurations should be uniform from one interchange to another. All ramps
should exit and enter on the right except under highly unusual conditions. Dissimilar
arrangements between interchanges can cause confusion resulting in undesirable lane
switches, reduced speeds, etc., especially in urban areas where interchanges are closely
spaced.
37-2.4
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-2.B
37-2.5
HARD COPIES UNCONTROLLED
Illinois
37-2.6
Notes:
INTERCHANGES
1. If the distance between the theoretical 1 ft (300 mm) stubs is less than or equal to 1500 ft (450 m), provide an auxiliary lane
connecting the entrance terminal to the exit terminal even if the auxiliary lane would not be required by a weaving analysis.
2. See Figure 37-6.L for Entrance Ramp Terminal with auxiliary lane.
Figure 37-2.C
September 2010
Illinois INTERCHANGES September 2010
Avoid the use of left-hand exit and entrance ramps. They are less efficient operationally than
right-hand ramps and may present a serious crash potential. They also introduce an
undesirable element of non-uniformity into the design of a freeway system that leads to
confusion and, in some cases, hazardous behavior by drivers. The disadvantages of left-hand
ramps greatly outweigh the potential for directional turning movements and the increased
flexibility of design. Therefore, where a left-hand ramp is being considered, approval of the
design and analysis must be obtained from BDE for the Interchange Design Study (IDS).
Proper interchange operations depend partially on the compatibility between its geometric
design and the traffic control devices at the interchange. The proper application of signs and
pavement markings will increase the clarity of paths to be followed, safety, and operational
efficiency. The logistics of signing along a highway segment will also impact the minimum
acceptable spacing between adjacent interchanges. The Bureau of Operations’ Policies and
Procedures Manual provides guidelines and criteria for the placement of traffic control devices
at interchanges. For complex interchanges and location/design studies involving closely spaced
interchanges, include a preliminary signing plan with the IDS.
Ramp metering may be used to improve freeway operations. Ramp metering consists of traffic
signals installed on entrance ramps before the entrance terminal to control the number of
vehicles entering the freeway. The Bureau of Operations will determine the need for ramp
metering. If ramp metering is used, the designer will need to coordinate with the Bureau of
Operations to determine the placement of the ramp signal to ensure that there is sufficient
storage area before the ramp signal and that sufficient acceleration distance is available beyond
the signal to allow a vehicle to reach the freeway operating speed.
Weaving sections are highway segments where the pattern of traffic entering and exiting at
contiguous points of access results in vehicular paths crossing each other. The turbulent effect
of weaving operations can result in reduced operating speeds and levels of service for the
through traffic. Weaving sections may be eliminated at an interchange between two major
highways by using directional or semi-directional connections or by using collector-distributor
roadways.
1. Weave Length. Weaving sections on freeways other than cloverleafs should be at least
1000 ft (300 m) or the length determined using the Highway Capacity Manual (HCM),
whichever is greater. Section 37-3.06(b) discusses the minimum design criteria for one-
sided weaving sections at cloverleaf interchanges.
37-2.7
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
2. Level of Service. The level of service of a weaving section should be the same as the
adjacent mainline; however, at a minimum, it can be one level lower. A higher volume in
weaving sections may be accommodated and their adverse impact on through traffic
minimized by providing the weaving section on collector-distributor roadways. Section
37-4.02 discusses the use and design of collector-distributor roadways.
Consider the grading around an interchange early in the design process. Alignment, fill and cut
sections, median widths, lane widths, drainage, structural design, and infield contour grading, all
affect the aesthetics of the interchange. Properly graded interchanges allow the overpassing
structure to blend naturally into the terrain. In addition, ensure that the crossroad and ramp
slopes are not too steep to compromise safety and that they can support plantings that prevent
erosion and enhance the appearance of the area. Flatter slopes also allow easier maintenance.
Transitional grading between cut and fill slopes should be long and natural in appearance. The
designer must ensure that plantings will not affect the sight distance within the interchange and
that larger plantings are a significant distance from the traveled way. See Chapter 59 for
additional guidelines.
Review the proposed design from the driver’s perspective. Examine all possible movements
that a motorist might encounter. Several computer programs are available that allow a designer
to test drive the design. Review the plans for areas of possible confusion, sufficient weaving
and sight distances, proper signing, and ease of operation.
Design all roadways through an interchange with the same criteria as used for the approaches
including design speed, sight distance, horizontal and vertical alignment, cross section, and
roadside safety elements. The applicable chapters in Parts IV, Roadway Design Elements, and
V, Design of Highway Types, present the geometric design criteria that apply to the roadways
through interchanges. In addition, consider the following:
2. Design Year. Typically, use a 20-year design period based on the anticipated opening
date of the facility.
3. Design Speed. The crossroad design speed will be based on its functional classification
and its urban or rural classification; see the geometric design tables in Part V, Design of
Highway Types. For rural crossroads (e.g., county highways, township roads), the
minimum design speed of the crossroad through the interchange should be 55 mph (90
km/hr).
37-2.8
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
4. Horizontal Alignment. In general, lay out the alignment of the freeway/expressway and
crossroad through the interchange on a tangent. Where this is not practical, consider
the following:
b. Freeway Ramp Terminals. Lay out the freeway alignment so that only one exit
terminal departs from the mainline curving to the right, or design the mainline
curve to lie entirely within the limits of the interchange and away from the exit and
entrance terminals.
5. Vertical Alignment. Vertical profiles for both roadways through the interchange should
be as flat as practical. Where compromises are necessary, use the flatter grade on the
major facility. In addition, the designer should consider the following:
a. Sight Distance. To improve the sight distance to exit gores, locate exit ramp
terminals and major divergences where the mainline is on an upgrade.
b. Ramps. Avoid creating a hidden ramp roadway in the vertical plane. Also,
provide flat approach grades adjacent to the crossroad. For additional
information on storage platforms at the ramp/crossroad intersection, see
Sections 36-1.06 and 37-5.01.
d. Turning Trucks. Large trucks may become unstable when executing a nonstop,
left turn from a crossroad on a downgrade. The combination of a downgrade,
sharp turning maneuvers into a ramp, and reverse superelevation may produce
instability in large trucks. Therefore, the maximum grade for all crossroads
associated with these conditions is desirably 2% through the ramp/crossroad
terminal. For existing crossroads to remain in place, limit the downgrade to 3%.
At a maximum, limit the up and downgrades to 4%.
37-2.9
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
6. Cross Sections. When designing the crossroad through the interchange, consider the
following:
a. Widths. In general, carry the approach cross section of the major facility through
the interchange. See Sections 37-5.01 and 37-5.02 for typical cross sections of
a crossroad through an interchange.
c. Side Slopes. Side slopes on the crossroad through the interchange area should
be 1V:4H or flatter. Chapter 34 and Part V further discuss roadway side slopes.
b. Access Control. To determine the required length of access control along the
crossroad at the interchange, see Chapter 35.
c. Left-Turn Lanes. Select the appropriate left-turn lane lengths based on the
design speed of the crossroad and/or the required storage lengths; see Section
37-2.10
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
10. Structures. Chapter 39 provides the geometric design criteria for structures designed in
conjunction with interchanges.
11. Trucks. Check truck merging speeds at entrance terminals. This typically is only critical
where the:
Operations and safety are important considerations in interchange design. The following
summarizes several major considerations:
Provide decision sight distance, where practical, to the freeway exit; see Chapter
31. Desirably, use the pavement surface for the height of object (i.e., 0.0 inches
(0.0 mm)).
Ramps should depart from the mainline where there will be no vertical curvature
to restrict visibility along the ramp. Avoid ramp designs that drop out of sight.
Avoid locating exit terminals where the mainline curves to the left.
Provide sufficient distance to allow safe deceleration from the freeway design
speed to the design speed of the first governing geometric feature on the ramp,
typically a horizontal curve.
37-2.11
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
3. Driver Expectancy. Ensure that the interchange is designed to conform to the principles
of driver expectation. These may include the following:
Avoid left-hand exit or entrance terminals. Drivers expect single-lane exit and
entrance terminals to be located on the right side of the freeway.
Do not locate exit ramps so that it gives the appearance of a continuing mainline
tangent as the mainline curves to the left.
4. Fixed Objects. Because of traffic operations at interchanges, many fixed objects may be
located within interchanges (e.g., signs at exit gores, bridge piers, rails). Avoid locating
these objects near decision points, make them breakaway, or shield them with barriers
or impact attenuators. Make any concrete footings flush with the ground line. See
Chapter 38 for additional guidance on roadside safety.
7. Weaving. Areas of vehicular weaving may create a high demand on driver skills and
attentiveness. Where practical, design interchanges without weaving areas by changing
the sequence of ramps, increasing the spacing between ramps, or removing the weaving
areas from the highway mainline by using collector-distributor roads.
8. Pedestrians and Bicyclists. Use signing and lane markings to increase awareness of
pedestrians and bicyclists. Signing, crosswalks, barriers, over and underpasses, bridge
sidewalks, and other traffic control devices may be required to manage traffic
movements and to control pedestrian and bicycle movements.
37-2.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Successive freeway ramp terminals may be placed relatively close to each other especially in
urban areas. The distance between the terminals should provide for vehicular maneuvering,
signing, and capacity. Figure 37-2.D provides recommended guidelines for spacing distances
of various freeway ramp terminals. The criteria in Figure 37-2.D should be considered for the
initial planning stages of interchange location. The final decision on the spacing between
freeway ramp terminals must satisfy the level-of-service criteria. This will be determined by
conducting a detailed capacity analysis using the Highway Capacity Manual. Where the
distance between the tapers of successive entrance and exit terminals is less than 1500 ft (450
m), connect the two terminals with an auxiliary lane and provide a recovery area beyond the exit
terminal as illustrated in Figure 37-6.B.
37-2.13
HARD COPIES UNCONTROLLED
Illinois
37-2.14
INTERCHANGES
Notes:
1. Distance is measured from the end of taper (1 ft (300 mm) stub) to the gore nose and desirably should be 400 ft (120 m) or more; see Figure 37-6.K.
Figure 37-2.D
Illinois INTERCHANGES September 2015
37-3.01 General
In Illinois, there are six basic interchange types the diamond, the cloverleaf, the partial
cloverleaf, the trumpet, the directional, and the semi-directional. These interchange types, and
variations within each type, permit adaptation to traffic needs, available right-of-way, terrain, and
cultural features. The following sections discuss these basic interchange types and the design
elements for laying out the interchange. The FHWA publication Alternative
Intersection/Interchange: Informational Report (AIIR) discusses alternative interchange designs
(e.g., diverging diamond interchange, displaced left-turn interchange). Each interchange must
be designed to fit the individual site considerations. The final design may be a minor or major
modification of one of the basic types or may be a combination of two or more basic types.
Sections 37-2, 37-4, 37-5, and 37-6 provide the general design criteria for the individual
elements of the interchange.
37-3.02(a) General
The conventional diamond is the simplest and most common interchange type. Diamonds
include one-way diagonal ramps in each quadrant and two intersections at the crossroad. With
proper treatments at the crossroad, the diamond interchange can accommodate a wide variety
of circumstances in suburban and urban areas where the crossroad operating speeds are
45 mph (70 km/hr) or less. The diamond is usually the best interchange choice where the
intersecting road is not access controlled. Figures 37-3.A and 37-3.B illustrate typical diamond
interchanges. Some of its advantages and disadvantages include:
Advantages
All exits from the mainline occur before reaching the crossroad structure and entrances
occur after the structure. This conforms to driver expectancy and therefore minimizes
confusion.
All traffic can enter and exit the mainline at relatively high speeds.
At the crossroad, adequate sight distance can usually be provided, and the operational
maneuvers are consistent with other intersections on the crossroad.
The diamond configuration easily allows modifications to provide greater ramp capacity,
if needed in the future.
37-3.1
HARD COPIES UNCONTROLLED
Illinois
37-3.2
INTERCHANGES
LEGEND
Figure 37-3.A
LEGEND
Illinois
37-3.3
September 2015
Figure 37-3.B
Illinois INTERCHANGES September 2015
Disadvantages
A diamond has a greater potential for wrong-way entry onto the ramps than, for
example, a full cloverleaf. Raised-curb channelization is used on the crossroad to
minimize the likelihood of driver confusion and wrong-way maneuvers.
The first step in laying out diamond interchange ramps is to determine the location of the
ramp/crossroad intersections. The length of the overlapping left-turn lanes generally will
determine the location of these intersections; see Figure 37-5.A. Section 36-3.02 provides the
criteria for determining the length for these separate left-turn lanes. Once the lengths are
determined and located away from the grade separation, set the left-turn control radii and
establish the baseline control; see Figures 37-5.D through 37-5.G.
Figures 37-5.D through 37-5.G illustrate typical diamond ramp/crossroad intersections. Figure
37-3.C provides guidelines for determining allowable ramp/crossroad intersection angles where
the crossroad is approximately perpendicular to the freeway. The preferred ramp/crossroad
intersection angle is 90, but if avoidance of agricultural property or other adjacent right-of-way
is desired, other angles are permitted according to Figure 37-3.C. The ramp angles in Figure
37-3.C are based on the volume of left-turning vehicles from either the crossroad or the ramp.
Note: This figure assumes the freeway and crossroad intersect at approximately 90.
Figure 37-3.C
37-3.4
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Although the angle of ramp intersection with the crossroad is important, the complete
development of ramp geometry may be influenced by a combination of other factors (e.g.,
conservation of agricultural land, avoiding existing development, angle of intersection of the
crossroad with the freeway). Because the angle of the crossroad with the freeway is a major
factor in determining the ramp alignment and length, the following design considerations are
provided:
b. Number of Curves. With a 60 intersection angle, only one curve is required on
the ramp; see Figure 37-3.A. For other angles of intersection, a second curve
adjacent to the crossroad will generally be required. For rural ramps with a 75
degree intersection angle with the crossroad, design the ramp curve nearest to
the crossroad with a minimum 30 mph (50 km/hr) design speed and, desirably,
with a 40 mph (60 km/hr) design speed. In urban areas, the design speed should
be at least 25 mph (40 km/hr) unless available right-of-way is highly restricted by
existing development; see Figure 37-3.B.
c. Minimum Tangent Length. The minimum tangent length between two reverse
curves should be (2/3T1 + 2/3T2). T1 and T2 are the individual superelevation
runoff lengths for each curve. See Figure 37-4.F for the applicable runoff
lengths.
d. Curve Locations. Where two curves are designed on an exit ramp, the curve
nearest the freeway ramp terminal may be located by computing the center-to-
center distance of the two curves. This center-to-center distance, “L,” passes
through a point of intersection with a line drawn parallel to the edge of the
freeway and passing through the center of the curve located next to the freeway.
This procedure is illustrated in Figure 37-3.D.
2. Freeway and Crossroad Skewed. If the crossroad is skewed, in either direction, strict
adherence to the guidelines for perpendicular intersections in Item 1 can result in
unacceptable design features (e.g., excessive ramp lengths, short curve lengths, steep
grades, indirect alignment). Therefore, design modifications are generally necessary.
Under these conditions, give primary consideration to the ramp alignment rather than the
intersection angle as determined from Figure 37-3.C. With skewed crossroads, the
ramp alignment should be, in order of preference, one of the following:
37-3.5
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Example:
Proposed Mainline Design Speed = 75 mph
Figure 37-3.D
37-3.6
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
reverse curves with radii connected by a tangent length greater than the
minimum required for superelevation runoff lengths, see Item 1c above; or
In the design of the preferred alignment, the designer must also control the overall ramp
length. Normally, the gore nose of a ramp should be located about 1250 ft (375 m) from
the crossroad structure. If the first preference alignment cannot be developed with a
gore within 1250 ft to 1400 ft (375 m to 425 m) of the structure, the second preference
should be investigated and the third, if necessary, until an acceptable ramp length is
achieved for both grade and directness.
The modified diamond interchange is a combination of the diamond interchange and partial
cloverleaf. Figure 37-3.E illustrates typical schematics of a modified diamond interchange. This
design type is typically used where subdivisions, extensive commercial or industrial
development, lakes, ponds, or other adverse topography and/or soil conditions are located in
one of the interchange quadrants, making right-of-way acquisition, design, or construction
unusually expensive. Some of the advantages and disadvantages of the modified diamond
include:
Advantages
Depending upon site conditions, modified diamonds may offer the opportunity to
increase weaving distances.
It allows access where one of the quadrants presents adverse right-of-way, topography,
or environmental constraints.
Disadvantages
The loop results in a longer travel distance for the turning vehicle than for a conventional
diamond, and the operating speeds on the loop ramp are generally slower.
The exit or entrance terminal is located before or after the crossroad structure that may
require additional signing to guide the motorist.
37-3.7
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-3.E
37-3.8
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
37-3.04(a) General
A compressed diamond, also called a tight diamond interchange, is similar to the conventional
diamond except that the ramp termini on the crossroad are located near the structure. Figure
37-3.F presents a schematic of a compressed diamond interchange without frontage roads.
This design type is generally only used in urban areas where a diamond interchange is
appropriate, but right-of-way or other environmental features preclude the use of the
conventional diamond. Although operationally a compressed diamond is similar to a single-
point diamond discussed in Section 37-3.05, they have significant differences. Some of the
advantages and disadvantages of the compressed diamond include:
Advantages
The open pavement area at the intersection is significantly less than that for a single
point diamond.
The grade separation structure is significantly smaller than that for a single-point
diamond, retaining walls and/or embankments are less expensive, and construction
costs are lower.
Slip ramps for one-way frontage roads can be easily incorporated into the design.
Figure 37-3.F
37-3.9
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Disadvantages
Left-turn lanes between the ramp termini usually need to be overlapped (i.e., side-by-
side opposing left-turn lanes). Consequently, the cross section of the crossroad is
generally wider than a conventional diamond.
Signal timing and interconnection are necessary in order to eliminate left-turn queues
from overlapping each other and causing gridlock.
Due to the close proximity of the two intersections, the compressed diamond typically
will need to operate as a six-phase overlap signal system. Consequently, longer
clearance times are required.
Length of access control on the crossroad may be more extensive than that for a
conventional diamond.
Section 37-5 presents the criteria for ramp/crossroad intersections, which is also applicable to
compressed diamonds. However, the minimum length for left-turn lanes is based on the
storage length and not on the deceleration distance. See Section 36-3.02 to determine the
minimum storage length. If there is insignificant space for storage, the designer will need to
consider optimizing the traffic signals.
Figure 37-3.F illustrates a schematic of a compressed diamond without frontage roads. Figure
37-5.M presents the criteria for a compressed diamond with one-way frontage roads and slip
ramps. Where there are one-way frontage roads and where there is significant U-turn traffic to
the opposite frontage road, the designer may want to consider using a turnaround design.
Figure 37-3.G illustrates the general layout and cross section for a turnaround design.
Depending upon specific site conditions, this arrangement may significantly improve traffic
operations at the interchange. The major operational feature of the turnaround is to provide
access for traffic on the freeway to the one-way frontage road in the opposite direction without
passing through the two intersections on the crossroad. If U-turn movements are considered to
be significant, prepare an origin and destination study to determine the need for a turnaround prior
to the development of IDS.
Advantages
It preserves and enhances the accessibility to property abutting one-way frontage roads.
U-turning vehicles do not have to pass through the two intersections on the crossroad.
37-3.10
HARD COPIES UNCONTROLLED
Illinois
INTERCHANGES
Notes:
37-3.11
September 2015
Figure 37-3.G
Illinois INTERCHANGES September 2015
Disadvantages
It is more costly than a typical compressed diamond due to the longer structure.
Longer distances are required between the slip ramp frontage road merge point and the
crossroad.
37-3.05(a) General
The single-point urban diamond interchange (SPUI) offers improved traffic-carrying capabilities,
safer operations, and reduced right-of-way needs under certain conditions when compared with
other interchange configurations. The distinguishing feature of this interchange is the
convergence of all through and left-turning movements into a single, large signalized
intersection area. Figure 37-3.H illustrates a schematic of a SPUI. Some of its advantages and
disadvantages include:
Advantages
It can increase interchange capacity and alleviate storage problems from two closely
spaced intersections on the crossroad.
Figure 37-3.H
37-3.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Opposing left turns operate to the left of each other so that their paths do not cross each
other.
At the intersection of the ramps with the crossroad, the design typically includes flatter
curves for turning radii, which allows left turns to be completed at higher speeds.
Disadvantages
Special pavement markings and a centrally located diamond-shaped island are required
to guide the left-turning drivers through the intersection.
There is a significantly wider pavement area for pedestrians to cross and may create
greater delays in traffic when compared to the conventional diamond.
It has a higher cost than the conventional or compressed diamond because of the need
for a long, single-span structure and the need for retaining walls or reinforced earth walls
along the mainline.
In the case of the mainline over a crossroad, lighting is required under the structure.
The interrelationship of the design elements is extremely important in the design of single-point
diamond interchanges (SPUI). Therefore, make every effort to use the desirable values for all
design features of the interchange. See NCHRP 345 Single-Point Urban Interchange Design
and Operational Analysis for complete design details. Figures 37-3.I and 37-3.J illustrate the
typical layout for a SPUI. In addition, consider the following:
1. Over versus Under. One of the first things the designer must address is whether to
place the freeway or expressway over or under the crossroad. The overpass SPUI,
illustrated in Figure 37-3.I, typically includes a conventional, single-span structure 220 ft
(67 m) in length with a depth of 8 ft to 9 ft (2.4 m to 2.7 m). The underpass design
(freeway over) typically includes two spans of approximately 65 ft (20 m) in length and a
depth of 3 ft to 4 ft (1.0 m to 1.2 m). The underpass design tends to provide a more
open and less restrictive feeling as the driver approaches the intersection area. For both
designs, the crossroad profile should be as flat as practical. Section 44-4.02 discusses
additional considerations when determining whether to place the crossroad over or
under the freeway.
37-3.13
HARD COPIES UNCONTROLLED
Illinois
37-3.14
INTERCHANGES
Figure 37-3.I
September 2015
Illinois INTERCHANGES September 2015
Figure 37-3.J
37-3.15
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
2. Sight Distance. Sight distance along the exit ramp to the crossroad intersection is
especially critical with the SPUI because the decision point to turn left or right generally
will occur sooner at a SPUI than at other diamond type interchanges. The point of initial
driver perception of the large triangular intersection island and the point for the left- or
right-turn decision should occur at or just beyond the gore nose of the off ramp. At a
minimum, provide the stopping sight distance as discussed in Section 31-3.01 and,
desirably, decision sight distance wherever practical (Section 31-3.02). The designer
must also check the horizontal sight distance to ensure that the structure abutments or
parapet walls do not block the sight distance.
4. Design Speed. Desirably, the design speed for the turns should be 30 mph to 40 mph
(50 km/hr to 60 km/hr). In highly restricted ROW areas, the left-turning roadway from the
exit ramp onto the crossroad may be designed with a 25 mph (40 km/hr) design speed.
6. Number of Lanes. A capacity analysis is required to determine the number of turn lanes
for the overall intersection design. At a minimum, provide sufficient space to allow two
through lanes for each direction on the crossroad, one left-turn lane on the crossroad,
dual-turn lanes on the exit ramp for left-turning movements, and one right-turn lane from
the exit ramp onto the crossroad.
9. Central Island. Figure 37-3.K illustrates the central island that should be used on the
crossroad.
10. Offset Turning Movements. To allow ease of movements for left-turns, the separation
between opposing left-turning vehicles on the crossroad should be at least 10 ft (3.0 m).
11. Right-Turn Lanes. Ensure the right-turn lanes on the exit ramps are of sufficient length
to allow right-turning vehicles to bypass the queue of left-turning vehicles on the ramp.
37-3.16
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-3.K
12. Traffic Control Devices. To eliminate confusion at the SPUI, proper exit ramp guide
signing, pavement markings, and lane-use signing must be included to provide the
necessary positive guidance through the intersection. Contact the Bureau of Operations
for the applicable signing and pavement marking criteria.
13. Traffic Signal Placement. When determining signal locations, consider the following:
Due to possible lane confusion, mount signal heads directly over the travel lanes.
For overpass SPUI’s, mount vertical signal heads outside the structure; see
Figure 37-3.J.
The visibility of the signal heads controlling the exit-ramp left-turning movements
is critical. An additional signal for advance notice may be required within the
large triangular island.
Contact the Bureau of Operations for the design of all signal installations.
37-3.17
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
37-3.06(a) General
Cloverleaf interchanges are used at four-leg intersections and employ loop ramps to
accommodate left-turn movements. Full cloverleaf interchanges are those with loops in all four
quadrants; all others are partial cloverleafs and are discussed in Section 37-3.07.
Where two access-controlled highways intersect, a full cloverleaf is the minimum type of
interchange design that will suffice. In addition, they also may be used at the intersection of
other multilane arterials to accommodate large volumes of traffic.
The operation of a cloverleaf with high weaving volumes is greatly improved through the
addition of collector-distributor (C-D) roadways; see Section 37-4.02. The C-D roadways may
be advantageous in suburban areas because of the need for smaller loops. This may reduce
the amount of right-of-way acquisition necessary for the development of the interchange.
Although right-of-way requirements may be reduced, overall costs usually increase due to
longer and wider structures and additional pavement costs.
Figure 37-3.L provides typical examples of full cloverleafs with and without C-D roads.
Advantages
Full cloverleafs eliminate all vehicular stops through the use of free-flow terminals and
they provide continuous free-flow operation on both intersecting highways.
Full cloverleafs eliminate all at-grade intersections, eliminate left turns across traffic and,
therefore, eliminate the need for traffic signals.
Disadvantages
Because of the geometric design of loops, full cloverleafs require large amounts of right-
of-way.
They are typically more expensive than diamond interchanges due to considerably more
lengths of ramps, wider structures, and the desirability of providing C-D roads.
The loops in cloverleafs result in a greater travel distance for left-turning vehicles than do
diamonds and the speeds on the ramps are generally slower.
Exit and entrance terminals are located before and after the crossroad structure, which
require additional signing to guide motorists.
Weaving sections between loop ramps must be made long enough to provide for
satisfactory traffic operations.
37-3.18
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
CLOVERLEAF INTERCHANGES
Figure 37-3.L
37-3.19
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-3.M illustrates the design and layout of a typical cloverleaf interchange. In developing
the cloverleaf interchange, consider the following steps:
1. Exit Gore. The first step is to locate the physical nose of the exit gore of the weaving
section a minimum of three seconds of travel time at the design speed beyond the
structure on each of the four interchange legs; see Figures 37-3.N.
2. Weaving Section. The second step is to determine the minimum lengths required for the
weaving sections. The following will apply:
a. Length. Figure 37-3.N illustrates various weaving lengths based on the design
speed of the highway and ramp curvature of the preceding entrance ramp and
the following exit ramp. The length of the weaving section also must be
determined using the Highway Capacity Manual (HCM) and the appropriate level
of service; see Item 2b below. The minimum weaving section length will be
based on the greater value from the HCM or Figure 37-3.N.
b. Capacity. At a minimum, the level of service of the weaving sections may be one
level lower than the adjacent freeway. Desirably, the level of service should be
the same as the adjacent mainline. When the total volume on the two
successive ramps reaches approximately 1000 vph, interference increases
rapidly with a resulting reduction of the through traffic speed. At these weaving
volume levels, consider using a collector-distributor road. Section 37-4.02
discusses the use and design of collector-distributor roadways. Expected design
capacities for single-lane loops range from 800 to 1200 vph. The higher figures
are generally only achievable where the design speed is 30 mph (50 km/hr) or
higher and few trucks use the loop.
37-3.20
HARD COPIES UNCONTROLLED
Illinois
LEGEND
INTERCHANGES
Figure 37-3.M
37-3.21
September 2015
Illinois
37-3.22
INTERCHANGES
Figure 37-3.N
Illinois INTERCHANGES September 2015
CLOVERLEAF INTERCHANGE
(Weaving Section) (Metric)
Figure 37-3.N
37-3.23
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
3. Entrance Gore. The location of the entrance gore is determined by adding the minimum
weaving length to the exit gore nose location determined in Step 1. At a minimum, place
the entrance gore 100 ft (30 m) before the structure and, desirably, 200 ft (60 m) before
the structure; see Figure 37-3.N.
4. Inner Loops. Once the physical noses of the exit and entrance gores have been
determined, the horizontal alignment between the corresponding exit and entrance gores
must be determined. Circular curve loop ramps are the most desirable geometrically
because speeds and travel paths tend to be more uniform. However, this is often
impractical and compound curvature is generally required. The initial and final arcs of
the loops may preclude using the specified radii for the design speed of the respective
highways and length of the weaving sections. A third intermediate arc is then
compounded with initial and final arcs. If necessary, in obtuse quadrants, two arcs may
be compounded between the initial and final curves. If the intermediate arc cannot be
compounded with the minimum arc lengths provided in Section 37-4.07, one or both of
the adjacent weaving sections containing the loop terminals must be adjusted and the
process repeated.
5. Outer Connections. Once a satisfactory inner loop design has been developed, the
designer must select the appropriate outer connection design. Desirably, this will be a
tangent section connected by radii at the exit and entrance terminals. In place of the
tangent section, compound curves having a radius greater than the radius preceding the
exit terminal may be used. In urbanized areas where right-of-way may be restricted, a
“wrap around” design may be used. In this situation, the central curve of the outer
connector is normally made concentric to the arc at the center of the inner loop and the
selected radius should provide a minimum design speed of 40 mph (60 km/hr). Set the
outer connector to provide a common drainage section between the inner loop and the
outer connection. Figure 37-3.O illustrates a typical layout with a wrap around design.
37-3.07(a) General
Partial cloverleaf (parclo) interchanges are those with loops in one, two, or three quadrants.
Several of the disadvantages listed for full cloverleafs also apply to partial cloverleafs (e.g.,
geometric restriction of loops). However, some specific advantages of partial cloverleafs
include:
Partial cloverleafs provide access where one or more quadrants present adverse right-
of-way and/or topographic problems that preclude a typical diamond interchange.
Partial cloverleafs may accommodate heavy left-turn traffic by means of a loop and
thereby improve capacity, operations, and safety.
Depending upon site conditions, partial cloverleafs may offer the opportunity to increase
weaving distances.
37-3.24
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Note: Where the two ramps parallel each other, the elevations of the left edge of the outer
ramp should approximately match the elevation of the inner loop ramp.
Figure 37-3.O
37-3.25
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Partial cloverleaf designs can be segregated into the two-quadrant and four-quadrant partial
cloverleaf. These are further explained as follows:
a. Type A. Both the exit and entrance terminals are located in advance of the
structure and two channelized “T” intersections are formed on the crossroad.
This arrangement reduces the probability of wrong-way movements. However,
all turning movements from the crossroad must undergo a “reverse” operation;
i.e., drivers traveling to the right must turn left and those traveling to the left must
turn right.
b. Type B. Because the “T” intersections allow normal operations for turning
movements from the crossroad, the probability of wrong-way movements are
greatly reduced. The exit terminals are located beyond the structure and, due to
the lower design speed on the loop ramp, drivers tend to decelerate more on the
mainline through lanes in advance of the exit.
2. Four-Quadrant Partial Cloverleaf Interchange. Figures 37-3.S and 37-3.T illustrate the
Type A and Type B four-quadrant parclo interchanges, respectively. The four-quadrant
parclo interchange is used to provide for higher traffic volumes than the conventional
diamond through the elimination of left-turning traffic at the crossroad ramp terminals.
37-3.26
HARD COPIES UNCONTROLLED
Illinois
LEGEND
37-3.27
September 2015
Figure 37-3.P
Illinois
37-3.28
LEGEND
Figure 37-3.Q
Illinois
LEGEND
D - Radius return.
E - See Section 37-4.04 for radii
requirements and Section 32-2.05 for
INTERCHANGES
Figure 37-3.R
37-3.29
September 2015
LEGEND
A - Standard exit ramp terminal.
Illinois
37-3.30
C - Left-turn lane length based on design speed of crossroad.
D - Radius return.
E - See Section 37-4.04 for radii requirements and
Section 32-2.05 for minimum length of curve
requirements.
.F - Directional corner island.
G - Typically 90.
H - Minimum tangent distance between curves.
nose.
N - Ditch section width, minimum 50 ft
(15 m).
O - Ramp radii compounded at 2:1.
P - Minimum 3 seconds travel time at
design speed of mainline to physical
nose. Note: Where the two ramps parallel each
Q - Minimum distance between structure other, the elevations of the left edge of
and exit ramp based on intersection the outer ramp should approximately
Figure 37-3.S
LEGEND
A - Standard exit ramp terminal.
Illinois
F -
Directional corner island.
G -
Typically 90.
INTERCHANGES
H -
Minimum tangent distance between curves.
K -
100 ft (30 m) minimum to physical nose.
N -
Ditch section width, minimum 50 ft (15 m).
O -
Ramp radii compounded at 2:1.
P -
Minimum 3 seconds travel time at design
speed of mainline to physical nose.
Q - Minimum distance between structure and exit
Note: Where the two ramps parallel each
ramp based on intersection sight distance.
other, the elevations of the left
V - Curve not less than 10 mph (20 km/hr) below
edge of the outer ramp
37-3.31
September 2015
Figure 37-3.T
Illinois INTERCHANGES September 2015
Figures 37-3.P, 37-3.Q, and 37-3.R provide the general design and layout criteria for Type A,
Type B, and Type C parclo cloverleafs, respectively. During the layout and design of the two-
quadrant partial cloverleaf, consider the following steps:
a. Type A. Place the physical nose of the standard entrance terminal a minimum of
100 ft (30 m) upstream from the structure. Design the smallest loop radius with a
30 mph or 40 mph (50 km/hr or 60 km/hr) design speed in rural areas and 25
mph or 30 mph (40 km/hr or 50 km/hr) design speed in urban areas. Project a
tangent line from the loop radius to intersect with the crossroad at approximately
90. This procedure sets the location of both ramps and the location for the
beginning of the left-turn lane on the crossroad. Check the intersection sight
distance at the intersection of the exit ramp with the crossroad back to the left
along the crossroad; see Section 36-6.
b. Type B. Place the physical nose of the exit terminal three seconds of travel time
beyond the structure. Design the smallest loop radius with a 30 mph to 40 mph
(50 km/hr or 60 km/hr) design speed in rural areas and 25 mph or 30 mph
(40 km/hr or 50 km/hr) design speed in urban areas. Project a tangent line from
the loop radius to intersect with the crossroad at approximately 90. Layout the
location of the left-turn lane on the crossroad to fit into the intersection of the
entrance ramp. Check the intersection sight distance at the intersection of the
exit ramp with the crossroad back to the right along the crossroad; see Section
36-6.
c. Type C. The ramp/crossroad intersections for a Type C parclo are located in the
same manner as the respective terminals for Types A and B.
2. Loop Ramps. For Type A parclos, the radii of succeeding arcs should increase in the
direction of travel so that the traffic may enter the mainline highway at a reasonably high
operating speed. For Type B parclos, the radii of succeeding arcs should decrease at a
ratio of 2:1, with the arc of the sharpest curve being located immediately before the
tangent section of the ramp.
3. Outer Connections. The tangent portions of the outer connectors are set parallel to the
tangent portions of the loop ramps and are separated by a 50 ft (15 m) median. This
width provides for a suitable common drainage section and minimizes headlight glare
from opposing traffic. The remaining portion of the outer connection is developed
concentric with the loop ramp and then follows a line approximately 45 in relationship to
the mainline. The intervening tangent length between the reverse curves should be no
less than the sum of 67% of the two superelevation runoff lengths.
37-3.32
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figures 37-3.S and 37-3.T illustrate the typical design and layout criteria for four-quadrant
partial cloverleaf interchange Types A and B. The design procedures for the four-quadrant
parclo are similar to those for the cloverleaf and the corresponding two-quadrant parclo. The
loop ramps are designed in the same manner as those of the cloverleaf. However, because
they use the standard entrance and exit terminals rather than the weaving section terminals, the
loops are smaller than the conventional cloverleaf loops. The outer connectors are designed in
the same manner as those of the two-quadrant parclo interchange.
Provide a common drainage section between the outer connectors and the free-flow loops and
set the tangent approach to the crossroad to intersect the crossroad at approximately 90. The
right-turn free-flow directional ramps located in opposite quadrants consist of compound circular
arcs where the adjacent radii should not exceed a ratio of 2:1. The standard exit and entrance
terminals of the directional ramps are located a certain minimum distance from the intersection
of the outer connections with the crossroad. These features are illustrated in Figures 37-5.K
and 37-5.L.
37-3.08(a) General
The trumpet type interchanges, illustrated in Figures 37-3.U and 37-3.V, are examples of three-
leg interchanges where three of the turning movements are accommodated with directional or
semi-directional ramps and one movement by a loop ramp.
at intersections with non-freeway spur connections or routes which are terminated at the
freeway,
at intersections with other highways which are contiguous with the freeway for a short
distance and then diverge on their own alignment, or
They are typically limited to intermediate traffic volumes that can be accommodated by single-
lane ramps.
The “bell” of the trumpet is normally oriented to favor the predominant turning movements.
Where the volume of traffic exiting from the freeway exceeds the volume entering from the
minor highway, use the trumpet Type A. Where the volume entering from the minor highway
exceeds the volume exiting from the freeway, use the trumpet Type B. Where the entering and
exiting volumes are comparable, the trumpet Type A is preferred due to its better operational
characteristics.
37-3.33
HARD COPIES UNCONTROLLED
LEGEND
Illinois
37-3.34
B - Standard entrance ramp terminal.
E - See Section 37-4.04 for radii requirements
and Section 32-2.05 for minimum length of
curve requirements.
F - Directional corner island.
G - Typically 90.
(Type A)
Figure 37-3.U
Illinois
LEGEND
A - Standard exit ramp terminal.
B - Standard entrance ramp terminal.
E - See Section 37-4.04 for radii requirements
and Section 32-2.05 for minimum length of
curve requirements.
H - Minimum tangent distance between curves.
O - Ramp radii compounded at 2:1.
M - Minimum median width 22 ft (7.0 m) with
INTERCHANGES
C&G.
P - Minimum 3 seconds travel time at design
speed of mainline to physical nose.
R - Minor convergence.
S - Minor divergence.
T - See Section 37-4.04 for radii requirements.
U - Locate end of horizontal curve so that no
superelevation runoff is located on the bridge
approach slab.
V - Curve not less than 5 mph (10 km/hr) below
37-3.35
September 2015
Figure 37-3.V
Illinois INTERCHANGES September 2015
Figures 37-3.U and 37-3.V illustrate the design and layout criteria for Type A and Type B
trumpet interchanges. Use Type A configuration where the predominate movement is left-turns
from the freeway to the minor road. Use Type B configuration where the predominate
movement is right turns from the freeway to the minor road.
In designing the trumpet interchange, first develop the location of the loop ramp and structure.
This requires a certain amount of trial and error because the loop is a continuation of the minor
highway rather than a connection to a standard entrance and exit terminal. The loop and the
outer connection are placed on curved alignment as they pass over the major highway.
Reverse curvature is used before the structure for operational purposes. Because the minor
highway is typically carried over, full superelevation should be attained before the structure
approach slab so that the structure and approach slabs may be designed with a constant
superelevation rate.
The outer connector is located adjacent and parallel to the roadway of the loop ramp and the
rest of the ramp is located based on the selected design speed. These directional ramps
provide turning movements to and from the minor highway through the use of standard entrance
and exit terminals on the freeway and minor convergence and divergence terminals on the
minor highway. Design the directional ramps for right turns to and from the minor highway using
compound curves and a minimum design speed of 50 mph (80 km/hr).
As shown in Figures 37-3.U and 37-3.V, the loop ramps or outer connectors do not exit from the
minor highway with the standard terminals, but are a continuation of the single-lane roadways
formed by the minor divergence and convergence terminals; see Figures 37-6.R and 37-6.T.
Because of sight distance restrictions, due to the presence of the structure or piers and higher
possible speeds on the stem approach, motorists may be confronted with an abrupt transition in
speed and alignment immediately beyond the structure. To minimize these operational
difficulties, place the ramps on curved alignment before passing over or under the freeway with
larger radii.
Directional or semi-directional ramps are used for heavy left-turn movements, to reduce travel
distance, to increase speed and capacity, and to eliminate weaving. These types of
connections allow an interchange to operate at a better level of service than is possible with
loops. Figures 37-3.W and 37-3.X illustrate common directional and semi-directional ramps
and/or roadways. Left-hand exits and entrances should be avoided.
Directional or semi-directional interchanges are most often provided in urban or suburban areas
at freeway-to-freeway or freeway-to-arterial intersections. In rural areas, there is generally an
insufficient traffic volume to justify the use of directional or semi-directional ramps in all
quadrants. A directional interchange provides the highest possible capacity and level of service,
but it is often costly to construct due to the number of structures required and amount of
embankment.
37-3.36
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
DIRECTIONAL INTERCHANGES
Figure 37-3.W
37-3.37
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
SEMI-DIRECTIONAL INTERCHANGES
Figure 37-3.X
37-3.38
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
37-3.11 Selection
Typically, several interchange types will be evaluated for potential application considering the
following:
compatibility with the highway system and functional classification of the intersecting
highway;
level of service for each interchange element (e.g., freeway ramp terminal, ramp proper,
ramp/crossroad terminal);
driver expectancy;
right-of-way impacts and availability, construction and maintenance costs, and potential
for stage construction;
37-3.39
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
In addition, consider the following, which will influence the selection of an interchange type:
1. Basic Types. A freeway interchange will be one of two basic types. A “systems”
interchange will connect a freeway to a freeway; a “service” interchange will connect a
freeway to a lesser facility.
2. Urban/Rural. In rural areas where interchanges occur relatively infrequently, the type
selected is normally influenced by existing topography and environmental factors. In
urban areas where restricted right-of-way and close spacing of interchanges are
common, the type selection and design of the interchange may become more complex.
The operational characteristics of the crossroad and proximity of nearby interchanges
must be considered when selecting and designing an urban interchange.
3. Capacity. The need for loop ramps or other free-flowing ramps may depend upon the
capacity of the ramp termini to adequately accommodate the turning traffic. Conduct a
capacity analysis to determine if the ramp termini will be adequate and to determine the
appropriate number of approach lanes on the crossroad and ramps.
4. Movements. All interchanges should provide for all movements, even when the
anticipated turning volume is low.
37-3.40
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
The components of a ramp include the freeway ramp terminal, the ramp proper, and a free-flow
or controlled ramp terminal at the crossroad. Although ramps have varying shapes, each can
be classified into one or more of the types illustrated in Figure 37-4.A and discussed in the
following sections.
1. Free-Flow. The free-flow loop, Figure 37-4.A(a), consists of compounded circular arcs
which turn through approximately 270. The initial and final curves of the loop are
tangent to the standard exit or entrance terminal or to a weaving section, depending
upon the interchange type. The free-flow loop is a standard component of the cloverleaf
interchange, the four-quadrant partial cloverleaf interchange, and the trumpet
interchange. Free-flow loops are designed so that the central arc is a sharper radius
than that of either the initial or final arcs, or the central arc is intermediate between the
two. Motorists decelerate from the speed of the through highway over the initial portion
of the ramp and accelerate uniformly over the final portion of the ramp.
Avoid flatback loops or loop ramps where the central arc has a greater radius than either
the initial or final arcs.
Diagonal ramps, Figure 37-4.A(c), are a component of the diamond interchange. Standard
entrance and exit terminals are used on the major road, and controlled terminals are provided
on the crossroad. The angle of intersection with the crossroad varies between 60 and 90; see
Section 37-3.02(d).
Outer-connector ramps are in the same quadrant and to the outside of loop ramps; see Figure
37-4.A(d). They may have free-flow operation (e.g., at cloverleaf or trumpet interchanges) or
have controlled operations (e.g., at partial cloverleaf interchanges).
37-4.1
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
RAMP TYPES
Figure 37-4.A
37-4.2
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Semi-directional ramps are indirect in alignment, yet more direct than a loop ramp. These
ramps are illustrated in Figure 37-4.A(e). Motorists making a left turn normally exit to the right
and initially turn to the right, reversing direction before entering the intersecting highway. The
outer connection of the trumpet interchange is also a semi-directional ramp.
Directional ramps do not deviate greatly from the intended direction of travel. These are
illustrated in Figure 37-4.A(f) as an element of a trumpet interchange. They are also used to
accommodate single lane, right-turning traffic on four-quadrant partial cloverleafs, semi-
directional, and directional interchanges.
37-4.02(a) Usage
A collector-distributor (C-D) roadway is an auxiliary roadway parallel to and separated from the
main traveled way which serves to collect and distribute traffic from several access points. It
provides greater capacity and permits higher operating speeds to be maintained on the main
traveled way. C-D roadways may be provided at single interchanges, through two adjacent
interchanges or, in urban areas, continuously through several interchanges. Figure 37-3.L
illustrates a schematic of a C-D roadway within a full cloverleaf interchange.
Usually, interchanges designed with single exits are superior to those with two exits, especially
if one exit is a loop ramp or the second exit is a loop ramp preceded by a loop entrance ramp.
Whether used in conjunction with a full cloverleaf or with a partial cloverleaf interchange, the
single-exit design may improve the operational efficiency of the entire interchange. C-D
roadways use the single exit approach to improve the interchange operational characteristics.
C-D roadways will:
remove weaving maneuvers from the mainline and transfer them to the slower speed
C-D roadways,
provide high-speed single exits and entrances from and onto the mainline,
satisfy driver expectancy by placing the exit before the grade separation structure,
C-D roadways are most often warranted when traffic volumes (especially in weaving sections)
are so high that the interchange cannot operate at an acceptable level of service. They also
may be warranted where the speed relationship between weaving and non-weaving vehicles is
significant.
37-4.3
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
37-4.02(b) Design
1. Design Speed. The design speed of a C-D roadway usually ranges from 40 to 55 mph
(60 to 90 km/hr). Typically, use a design speed within 20 mph (30 km/hr) of the mainline
design speed, but not exceeding 55 mph.
2. Lane Balance. Maintain lane balance at the exit and entrance points of the C-D
roadways; see Section 37-2.03.
3. Width. C-D roadways may be one or two lanes, depending upon the traffic volumes and
weaving conditions. C-D roadways are designed similar to ramps with traveled way
widths of either 16 ft or 24 ft (4.9 m or 7.2 m).
4. Separations. The separation between the C-D roadway and mainline should be as wide
as practical. Figure 37-4.B provides the minimum separation that should be provided
with and without a median barrier.
5. Terminal Designs. Figure 37-4.C illustrates typical entrance terminal designs for C-D
roadways. Figure 37-4.D illustrates typical exit terminal designs.
1. Directional Roadways. The design speed of directional roadways, in rural areas may be
60 mph or 70 mph (100 km/hr or 110 km/hr). In urban areas, directional roadways may
be designed for 50 mph, 55 mph, or 60 mph (80 km/hr, 90 km/hr, or 100 km/hr)
depending on traffic volumes, right-of-way, motorist expectations, and importance of
route. In all cases, the maximum superelevation rate is 6%. Shoulder widths are the
same as the mainline roadway.
37-4.4
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-4.B
37-4.5
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-4.B
37-4.6
HARD COPIES UNCONTROLLED
Illinois
INTERCHANGES
37-4.7
September 2015
Figure 37-4.C
(1 of 2)
Illinois
37-4.8
Notes:
INTERCHANGES
Figure 37-4.C
(2 of 2)
September 2015
Illinois INTERCHANGES September 2015
Figure 37-4.D
(1 of 2)
37-4.9
HARD COPIES UNCONTROLLED
Illinois
37-4.10
Notes:
Figure 37-4.D
(2 of 2)
September 2015
Illinois INTERCHANGES September 2015
Figure 37-4.E provides the AASHTO recommended ranges of ramp design speeds based on
the design speed of the mainline. IDOT targets the middle range and the values apply to the
entire ramp (i.e., ramp terminal and ramp proper). In addition to Figure 37-4.E, consider the
following when selecting the ramp design speed:
1. Loop Ramps. Design speeds in the middle and high range are generally not attainable
for loop ramps. The following apply to loop ramps:
Where the truck ADT is greater than 15%, use a minimum design speed of 30
mph (50 km/hr) for the initial curve after the exit curve; see Figure 37-3.N.
For rural loop ramps, a 30 mph (50 km/hr) design speed is preferred.
Use a design speed of 35 mph (60 km/hr) for cloverleaf interchange loop ramps
between freeways.
Figure 37-4.E
37-4.11
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
2. Outer Connector Ramps. The design speed for the outer connector ramp of a rural
cloverleaf interchange should be in the middle range however, where a wrap-around
type ramp is used, a design speed 5 mph (10 km/hr) less than the middle range may be
used for the center curve.
3. Semi-Directional Ramps. Use design speeds in the middle range for semi-directional
ramps. In restricted urban conditions do not use a design speed less than 40 mph (60
km/hr).
4. Directional Ramps. These include both diagonal ramps at a diamond interchange and
ramps at a directional interchange. The design speed shall be in the middle range.
7. Variable Speeds. The ramp design speed may vary based on the two design speeds of
the intersecting roadways. Use a higher design speed on the portion of the ramp near
the higher speed facility and a lower design speed near the lower speed facility. When
using variable design speeds, the maximum speed differential between controlling
design elements (e.g., horizontal curves, vertical curves) should not be greater than
10 mph (20 km/hr). The designer must ensure that sufficient deceleration distance is
available between design elements with varying design speeds (e.g., two horizontal
curves).
Figure 37-4.F presents geometric design criteria for interchange ramps based on the selected
design speed (e.g., sight distance, horizontal alignment and vertical alignment). These are
discussed in detail in the following sections.
The designer should review the ramp cross-section, horizontal alignment, and vertical alignment
to ensure that stopping sight distance is continuously provided along the interchange ramp.
Because ramps are composed of curves of various radii and design speeds, sight distance
requirements may vary over the length of the ramp. Figure 37-4.F provides a summary of the
geometric criteria for ramps, including stopping sight distance.
37-4.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
GEOMETRIC REQUIREMENTS
GENERAL NOTES:
Where radii greater than R1 are used, determine the ramp superelevation rate
according to Section 32-3.
emax = 6% values are applicable to areas with snow and ice conditions and/or
highly congested traffic operations.
Figure 37-4.F
37-4.13
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
GEOMETRIC REQUIREMENTS
GENERAL NOTES:
Where radii greater than R1 are used, determine the ramp superelevation rate
according to Section 32-3.
emax = 6% values are applicable to areas with snow and ice conditions and/or
highly congested traffic operations.
Figure 37-4.F
37-4.14
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-4.G
37-4.15
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Figure 37-4.G presents the typical cross section criteria for tangent and superelevated portions
of ramps. The following also applies to the ramp cross section:
1. Width. The minimum width of a one-way, one-lane ramp is 30 ft (9.1 m). The 30 ft (9.1
m) width includes a 6 ft (1.8 m) left shoulder (4 ft (1.2 m) paved), an 8 ft (2.4 m) right
shoulder (6 ft (1.8 m) paved), and a 16 ft (4.9 m) paved traveled way. This arrangement
is illustrated in the ramp cross sections in Figure 37-4.G. For multilane directional
roadways, the cross sectional width is the same as the freeway design (e.g., 24-ft (7.2-
m) traveled way width plus shoulders); see Chapter 44.
2. Pavement Design. For pavement design information that is also applicable to ramps,
see Chapter 54.
3. Cross Slope. For tangent sections, the 16 ft (4.9 m) traveled way is sloped
unidirectionally at 3/16/ft (1.5%) towards the right shoulder. Shoulder cross slopes, for
both the paved and unpaved portions, are typically 1/2/ft (4%). The left shoulder is
typically sloped away from the traveled way. For all superelevated ramps, the ramp
traveled way and shoulders are sloped as discussed for open roadways conditions in
Section 32-3.
4. Curbs. If curb and gutter is required, place it on the outside edge of the full-width paved
shoulders. See Chapters 34 and 38 for information on the use of curbs.
5. Bridges and Underpasses. Carry the full paved width of the ramp, including the paved
shoulders over a bridge. See Chapters 38 and 39 when determining the clear ramp
width for an underpass.
6. Side Slopes/Ditches. For the ramp proper, use a side slope of 1V:4H or flatter.
Chapters 34 and 38 provide the applicable design information for side slopes and
ditches.
7. Clear Zones. Measure the clear zone from the edge of the traveled way on both sides of
the ramp using the criteria in Section 38-3.
8. Right-of-Way. The right-of-way adjacent to the ramp is fully access controlled and the
right-of-way is fenced.
37-4.16
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Establishing horizontal alignment criteria for any highway element requires a determination of
the theoretical basis for the various alignment factors. These include the side-friction factor (f),
the distribution method between side friction and superelevation, the relative longitudinal
gradients, and the distribution of the superelevation runoff length between the tangent and
horizontal curve. For horizontal alignment on the ramp proper, the theoretical basis will be
open-roadway conditions as discussed in Chapter 32. In summary, this includes:
relatively low side-friction factors (i.e., a relatively small level of driver discomfort);
distributing 67% of the superelevation runoff length on the tangent and the remainder on
the horizontal curve.
The following sections discuss the specific horizontal alignment criteria for ramps.
1. Minimum Curve Radii. Figure 37-4.F provides the minimum curve radii based on ramp
design speed, open-roadway conditions, and emax.
2. Superelevation Rates. For most areas, the maximum superelevation rate on the ramp is
emax = 8%. For areas with snow and ice conditions and/or areas with high congestion,
the maximum superelevation rate is emax = 6%. For two-lane directional roadways within
an interchange, use an emax = 6% throughout the State.
Because of the typically restricted site conditions for interchanges (e.g., the need to
minimize right-of-way), the majority of horizontal curves on ramps will be superelevated
at emax. Where practical, use curves flatter than Rmin. For these curves, the design
superelevation rate will be determined from the applicable emax figure in Section 32-3 for
open roadways.
3. Trucks. Where there are a significant number of trucks on loop ramps, the designer may
need to consider how the design may increase the rollover potential for large trucks. To
reduce this potential, consider using flatter curve radii on the second curve. Modified
radii can be obtained by reducing the superelevation rates and/or lowering the side-
friction factors. For additional guidance on modified truck friction factors, see the article
in Transportation Research Record No. 1385 entitled “Interchange Ramp Geometrics
Alignment and Superelevation Design.”
37-4.17
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
5. Ramp Baseline. Typically, the right edge of the ramp traveled way is used for horizontal
and vertical control, and the control point for the axis of rotation.
6. Shoulder Superelevation. The criteria presented in Section 32-3 for superelevating the
high and low side of shoulders for open roadways will apply to superelevated curves on
ramps.
Design the reverse curves with a minimum tangent section consisting of a continuously
rotating plane between the curves. This continuously rotating plane will determine the
necessary distance between the PT and the succeeding PC and is based on the 67%
superelevation runoff lengths for each curve. See Section 32-3 for more information on
superelevating reverse curves.
8. Sight Distance. Section 32-4 presents the criteria for sight distance around horizontal
curves based on the curve radii and design speed. These criteria also apply to curves
on ramps.
9. Controlled Ramp Termini. Exit ramps may end at a controlled intersection stop
control or signal control. If horizontal curves on the ramps are near the intersection, a
design speed for the curve should be selected which is appropriate for expected
operations at the curve. See Section 36-1.05(b) for more information.
Where compound arcs of decreasing radius are used on exit ramps, the arcs should have
sufficient length to enable motorists to decelerate at a reasonable rate over the range of design
speeds; see Figure 37-4.H. The radii of the flatter arc compared to the radii of the sharper arc
should not exceed a ratio of 2:1 to prevent abruptness in operation and appearance.
Comparable radii and length controls may be used on entrance ramps with compound arcs of
increasing radii. However, for entrance ramps, the 2:1 ratio of compound curves is not critical
because the vehicle is accelerating into a curve with a larger radius or into a tangent section.
37-4.18
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
US Customary
Radius (ft) 100 150 200 250 300 400 500 or more
Minimum (ft) 40 50 60 80 100 120 140
Desirable (ft) 60 70 90 120 140 180 200
Metric
Radius (m) 30 50 60 75 100 125 150 or more
Minimum (m) 12 15 20 25 30 35 45
Desirable (m) 20 20 30 35 45 55 60
Note: These lengths are applicable where the ramp curve is followed by a curve 1/2 the radius or
preceded by a curve of double radius.
Figure 37-4.H
37-4.08(a) Grades
Values of limiting gradients are +4% to -6% regardless of the design speed but, for any one
ramp, the selected gradient is dependent upon several factors. These include:
Where steep grades are required, locate them within the center portion of the ramp.
Locate freeway ramp terminals and approach areas near intersections on as flat a grade
as practical; see Section 37-5 for grades near ramp/crossroad intersections and Section
37-6 for freeway ramp terminal grades.
Ramp grades may affect the location of ramp termini. This may be a concern where the
ramp intersects the crossroad at an angle of 70 or less. Section 37-5.01 further
discusses the location of ramp/crossroad intersections.
Design vertical curves on ramps to meet the stopping sight distance criteria based on the ramp
design as presented in Chapter 33. Figure 37-4.F provides the K-values for both crest and sag
vertical curves. The ramp profile often assumes the shape of the letter S with a sag vertical
curve at one end and a crest vertical curve at the other. In addition, design the vertical
curvature adjacent to the standard exit and entrance terminals using a design speed of 50 mph
(80 km/hr) or greater.
37-4.19
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2015
Where the horizontal alignment of a ramp is designed to be parallel to an adjacent ramp (e.g.,
parclo, cloverleaf, trumpet interchanges), first establish the profile of the loop ramp and then set
the profile of the outer ramp to be approximately parallel to the inner-loop ramp profile. This is
accomplished by calculating the left-edge elevations of the loop ramp and matching those
elevations for the left-edge elevations of the outer ramp. To ensure the median edges between
the two ramps are approximately level, develop a typical cross section during the preparation of
the IDS.
The criteria in Chapter 38 (e.g., clear zones, barrier warrants, length of need) will apply to the
roadside safety design of interchange ramps.
37-4.20
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
At diamond and partial cloverleaf interchanges, the ramp will terminate or begin at a controlled
intersection on the crossroad, either with a stop sign or traffic signal. In general, the intersection
should be designed as described in Chapter 36. Consider the following in the design of
ramp/crossroad intersections:
1. Length of Left-Turn Lanes. For diamond interchanges, typically the minimum distance
between ramp/crossroad intersections is set by the length of overlapping left-turn lanes.
Note that in rural areas, the minimum design speed for determining the length of left-turn
lanes on the crossroad is 55 mph (90 km/hr). Left-turn lanes are usually designed with
straight-line tapers when the crossroad goes over the freeway and with reverse curves
when the crossroad goes underneath the freeway; see Figure 37-5.A. For compressed
diamond interchanges, the length of the left-turn lanes will be determined based on left-
turn storage requirements, see Section 36-3.02 and Figure 37-5.B. The left-turn control
radii into the ramps are set at the ends of the left-turn lanes. This also determines the
location of the ramp baselines.
2. Turn Lanes on Ramps. Exclusive turn lanes are often required at the end of an exit
ramp. Chapter 36 provides information on the design of turn lanes at intersections,
which are also applicable for ramps.
4. Ramp Grades. Where the exit and entrance ramps intersect with the crossroad, design
the first 150 ft to 200 ft (45 m to 60 m) of the ramp with a profile grade of 1.5% to 2%.
5. Crossroad Grades. Design the crossroad grades for a maximum of 2% through the
ramp/ crossroad intersection.
6. Capacity. Ensure that sufficient capacity and storage for the ramp/crossroad
intersection is available. This may require adding lanes at the intersection or on the
ramp proper. The analysis must also consider the operational impacts of the traffic
characteristics in either direction on the crossroad.
7. Sight Distance. Section 36-6 discusses the criteria for intersection sight distance.
These criteria also apply to the ramp/crossroad intersection. Give special attention to
the location of the bridge piers, abutments, sidewalks, bridge railing, roadside barrier,
etc.; these elements may present major sight distance obstacles. The bridge obstruction
and the required intersection sight distance may result in the relocation of the
ramp/crossroad intersection further from the structure. In addition, the crest vertical
curve on the crossroad may need to be lengthened to provide adequate sight distance in
the vertical plane.
37-5.1
HARD COPIES UNCONTROLLED
Illinois
37-5.2
INTERCHANGES
Notes:
1. Determine the left-turn length on the crossroad using Section 36-3.02 and by assuming the distance needed for a stop condition.
2. Set the location of left-turn control radii to and from the crossroad at the same crossroad station.
3. See Figure 37-5.C for Section A-A.
Figure 37-5.A
September 2010
Illinois
INTERCHANGES
Notes:
1. Determine the left-turn length on the crossroad using Section 36-3.02. For this design, the storage requirements will govern.
2. Set the location of left-turn control radii to and from the crossroad at the same crossroad station.
3. For new construction, use a 30 ft (9.0 m) minimum median width on the crossroad.
37-5.3
September 2010
Figure 37-5.B
Illinois INTERCHANGES September 2010
9. Crossroad Cross Section. For safety and capacity, the crossroad through an
interchange should be as wide as practical. The minimum cross section is an 18 ft (5.5
m) raised-curb median separating two 14 ft (4.2 m) lanes and 8 ft (2.4 m) outside
shoulders. See Figure 37-5.C and Section 37-2.14 for additional information on the
crossroad dimensions.
10. Design Vehicle. Radius returns and left-turn control radii for ramp/crossroad
intersections should be designed using a WB-67 (WB-20) design vehicle; see Section
36-1.08.
The ramp/crossroad intersections with a two-quadrant partial cloverleaf interchange are similar
in design to a channelized “T” intersection; see Figure 37-5.I. To discourage wrong-way
movements into the exit ramp, use a maximum left-turn control radius of 80 ft (24 m) from the
crossroad into the entrance ramp and a 100 ft (30 m) left-turn control radius from the exit ramp
onto the crossroad.
Figure 37-5.J illustrates a typical median design on the crossroad for a parclo type interchange.
37-5.4
HARD COPIES UNCONTROLLED
Illinois
INTERCHANGES
Notes:
Figure 37-5.C
37-5.5
September 2010
Illinois INTERCHANGES September 2010
Figure 37-5.D
37-5.6
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.D
37-5.7
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.E
37-5.8
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.E
37-5.9
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.F
37-5.10
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.F
37-5.11
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.G
37-5.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.G
37-5.13
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.H
37-5.14
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.I
37-5.15
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.I
37-5.16
HARD COPIES UNCONTROLLED
Illinois
INTERCHANGES
Notes:
Figure 37-5.J
37-5.17
September 2010
Illinois INTERCHANGES September 2010
The controlled ramp terminals of a four-quadrant partial cloverleaf interchange are similar in
design to the ramp/crossroad intersections of a diamond interchange; however, they must be
located to minimize any adverse operational effects on the directional ramps in the opposite
quadrants. The left-turning path from the controlled ramp terminal of the four-quadrant partial
cloverleaf Type A must intersect the crossroad downstream from the gore of the exit terminal,
as illustrated in Figure 37-5.K. The minimum distance of 200 ft (60 m) discourages wrong-way
movements and allows for stored vehicles on the crossroad when signalized.
For the four-quadrant partial cloverleaf Type B, illustrated in Figure 37-5.L, terminate the left-
turn lane from the crossroad into the controlled entrance ramp in advance of the merging nose
of the entrance terminal. Providing this separation minimizes confusion between two decision
points on the crossroad and provides better traffic operations when signalized.
The designer must consider the impact of frontage roads, where present, on interchange
design. At some urban interchanges, separating the intersection of the ramp and frontage road
with the crossroad may be impractical. In these cases, the only alternative is to provide a slip
ramp to a one-way frontage road before the intersection with the crossroad. This can apply to
either an exit or entrance ramp. Sufficient distance must then be provided between the freeway
ramp terminal and the ramp/frontage road terminal to provide the necessary acceleration or
deceleration distance and weaving distance.
Figure 37-5.M provides the basic schematic for this design. The critical design element is the
distance “A” between the ramp/frontage road merge and the crossroad. This distance must be
sufficient to allow traffic weaving, vehicular deceleration and stopping, and vehicular storage to
avoid interference with the merge point. Figure 37-5.M presents general guidelines that may be
used to estimate this distance during the preliminary design phase. A number of assumptions
have been made including weaving volume, operating speeds, and intersection queue distance.
Therefore, a detailed analysis will be necessary to firmly establish the needed distance to
properly accommodate vehicular operations. Additional information can be found in a
Transportation Research Record 682 article entitled, “Distance Requirements for Frontage-
Road Ramps to Cross Streets: Urban Freeway Design” or in the Texas Transportation Institute
publication Procedures to Determine Frontage Road Level of Service and Ramp Spacing.
37-5.18
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.K
37-5.19
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.K
37-5.20
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.L
37-5.21
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Figure 37-5.L
37-5.22
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Frontage Road
“A”
Volume at Exit Ramp
Intersection Volume (vph) Typical Typical Special
(vph) Minimum Desirable Considerations
200 140 380 ft (115 m) 500 ft (150 m) 270 ft (80 m)
400 280 465 ft (140 m) 565 ft (170 m) 370 ft (110 m)
600 420 500 ft (150 m) 635 ft (190 m) 400 ft (120 m)
800 560 550 ft (165 m) 700 ft (210 m) 435 ft (130 m)
1000 700 600 ft (180 m) 765 ft (230 m) 465 ft (140 m)
1200 840 650 ft (195 m) 885 ft (265 m) 485 ft (145 m)
1400 980 700 ft (210 m) 985 ft (295 m) 500 ft (150 m)
1600 1120 785 ft (235 m) 1085 ft (325 m) 535 ft (160 m)
1800 1260 865 ft (260 m) 1200 ft (360 m) 565 ft (170 m)
2000 1400 985 ft (295 m) 1315 ft (395 m) 600 ft (180 m)
Assumes the total volume of traffic on the frontage road including the merged
exit-ramp volume.
Assumed to be 70% of total volume in first column.
Notes:
1. Table values are acceptable for planning purposes only. Final lengths will be based on a
detailed operational analysis. This design may be used only in restricted urban areas.
Figure 37-5.M
37-5.23
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES September 2010
Providing access control along the crossroad of an interchange is an important design feature
for both the safety and efficient operation of an interchange. The access control line is defined
as a line established by the Department that restricts direct access to property abutting a
highway. See Chapter 35 for additional details on access control limits.
37-5.24
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
37-6.01(a) Types
The exit ramp terminal is a speed-change lane that permits high-speed traffic to exit from the
through lane of the highway and enter the ramp proper. The exit terminal must be visible to the
approaching motorist and provide a clear indication for the point of departure from the traveled
way. When designing the interchange, consider the following exit ramp types:
1. Standard Exit Terminal. There are two basic types of exit freeway ramp terminals the
parallel design and the taper design. For all new and reconstructed ramps, use the
taper design. Figure 37-6.A and the Illinois Highway Standards illustrate the
Department’s standard exit ramp terminal design. Exit ramp terminals may carry a
marked route provided the marked route is not a freeway or expressway. Where a
freeway or expressway turns through an interchange, use the major divergence design
as discussed in Section 37-6.03.
2. Exit Terminal With an Auxiliary Lane. An auxiliary lane may be required prior to the exit
terminal:
where the exiting design traffic exceeds the appropriate service volume of a
standard exit terminal design but does not require a two-lane exit, and/or
proceeding a left-hand exit terminal. Note that interchange designs should not
use left-hand exit terminals. However, where necessary, left-hand exits must be
first approved by BDE before the interchange type approval.
Figure 37-6.B illustrates the design criteria for an exit terminal preceded by an auxiliary
lane. Extend the pavement markings on the left edge of the ramp to the right edge of
the mainline traveled way. Provide transverse pavement markings in the recovery area
to discourage the use of the auxiliary lane beyond the exit gore. Pavement markings in
the recovery area should be according to the Bureau of Operations’ Policies and
Procedures Manual.
3. Two-Lane Exits. These terminals are typically required where the traffic volumes on the
ramp exceed the capacity of a single-lane exit ramp. The following lists several
elements the designer should consider for two-lane exit terminals:
a. Lane Balance. For consistent freeway operations, maintain lane balance at the
freeway ramp terminal; see Section 37-2.03.
37-6.1
HARD COPIES UNCONTROLLED
Illinois
37-6.2
INTERCHANGES
Notes:
Figure 37-6.A
February 2014
Illinois
INTERCHANGES
Notes:
1. Where the mainline is superelevated to the left or right, the terminal elevations and grades must be adjusted.
37-6.3
Figure 37-6.B
Illinois INTERCHANGES February 2014
The sight distance approaching the gore nose should exceed the stopping sight distance for the
through traffic, desirably by 25% or more. Where there are unusual conditions, consider
providing decision sight distance to the exit terminal. Extra sight distance is particularly
important for exit loops immediately beyond a structure. When measuring for adequate sight
distance, ensure that the motorist can see the pavement surface at and beyond the gore nose.
Locating the exit terminal and gore nose where the mainline is on an upgrade provides the best
design condition. Do not locate exit terminals near mainline crest vertical curves where the
ramp pavement may disappear from the driver’s view.
37-6.01(c) Alignment
Figures 37-6.D through 37-6.F illustrate methods to determine the grades along sections of
typical exit ramp terminals where the mainline is on tangent, curving to the right, and curving to
the left. The Department’s preferred practice is to locate exit terminals on tangent sections or
on mainline curves to the right. However, this may not be practical in highly restricted areas.
Section 37-4.07 discusses the minimum alignment criteria for the ramp proper, including the
minimum radii for the initial ramp curve (R1).
37-6.4
HARD COPIES UNCONTROLLED
Illinois
INTERCHANGES
Notes:
Figure 37-6.C
February 2014
37-6.5
Illinois INTERCHANGES February 2014
Example 37-6.1
Problem: Find G1 and G2, where G1 and G2 are the actual design grades.
Figure 37-6.D(1)
(1 of 2)
37-6.6
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Solution:
1. Determine G1.
G1 = G + G1'
Use the profile equation for base conditions for the mainline:
Mainline profile = 0.0%
Mainline on tangent
⁄ ⁄
G1' = x 100
Determine actual G1
. ⁄ . ⁄
G1 = 2.00 + x 100
2. Determine G2.
G2 = G + G2'
Use the profile equation for base conditions for the ramp:
Mainline profile = 0.0%
R1 = 760 ft
⁄ .
G2' = x 100
Determine actual G2
. ⁄ .
G2 = 2.00 + x 100
Figure 37-6.D(1)
(2 of 2)
37-6.7
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Example 37-6.2
Problem: Find G1 and G2, where G1 and G2 are the actual design grades.
Figure 37-6.D(2)
(1 of 2)
37-6.8
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Solution:
1. Determine G1.
G1 = +1.922%
(See Example Problem 37-6.1 for G1 calculations.)
2. Determine G2.
G2 = G + G2'
Use the profile equation for base conditions for the ramp except for R1:
Mainline profile = 0.0%
R1 = 1560 ft
⁄ .
G2' = x 100
Determine actual G2
. ⁄ .
G2 = 2.00 + x 100
Figure 37-6.D(2)
(2 of 2)
37-6.9
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Example 37-6.3
Problem: Find G1 and G2, where G1 and G2 are the actual design grades.
37-6.10
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Solution:
1. Determine G1.
G1 = G + G1'
Use the profile equation for base conditions for the mainline except mainline is on curve:
Mainline profile = 0.0%
From Figure 32-3.C, the freeway superelevation, e = 5.0%.
5% is the maximum superelevation of the ramp terminal when the mainline is curved
to the right.
⁄ ⁄
G1' = x 100
Determine actual G1
. ⁄ . ⁄
G1 = 1.80 + x 100
2. Determine G2.
G2 = G + G2'
Use the profile equation for base conditions for the ramp.
Mainline profile = 0.0%
R1 = 760 ft
⁄ .
G2' = x 100
Determine actual G2
. ⁄ .
G2 = 1.80 + x 100
Figure 37-6.E(1)
(2 of 2)
37-6.11
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Example 37-6.4
37-6.12
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Solution:
1. Determine G1.
G1 = G + G1'
Use the profile equation for base conditions for the mainline except mainline is on curve:
Mainline profile = 0.0%
From Figure 32-3.C, the freeway superelevation, e = 3.0%.
5% is the maximum superelevation of the ramp terminal when the mainline is curved
to the right.
⁄ ⁄
G1' = x 100
Determine actual G1
. ⁄ . ⁄
G1 = +2.50 + x 100
2. Determine G2.
G2 = G + G2'
Use the profile equation for base conditions for the ramp.
Mainline profile = 0.0%
R1 = 760 ft
⁄ .
G2' = x 100
Determine actual G2
. ⁄ .
G2 = +2.50 + x 100
37-6.13
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Example 37-6.5
Figure 37-6.F(1)
(1 of 3)
37-6.14
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Solution:
1. Determine G1.
G1 = G + G1'
Use the profile equation for base conditions for the mainline except mainline is on curve:
Mainline profile = 0.0%
From Figure 32-3.C, the freeway superelevation, e = 3.2%.
4% is the maximum superelevation of the ramp terminal when the mainline is curved
to the left.
⁄ ⁄
G1' = x 100
. ⁄ . ⁄
G1 = +2.00 + x 100
2. Determine G2.
G2 = G + G2'
Use the profile equation for base conditions for the ramp.
Mainline profile = 0.0%
R1 = 760 ft
⁄ .
G2' = x 100
Determine actual G2
. ⁄ .
G2 = +2.00 + x 100
Figure 37-6.F(1)
(2 of 3)
37-6.15
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
3. Find the location and elevation of the VPI where the two design grades, G1 and G2,
intersect:
. . . ⁄
x=
⁄
. . . / .
x=
. . ⁄
x = 454.52 ft
.
Elev. of VPI3 = 454.52 30.03
Figure 37-6.F(1)
(3 of 3)
37-6.16
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Example 37-6.6
A high speed freeway with a mainline curve to the left may have certain situations where the
typical profile design shown in Example 37-6.5 does not provide the best fit for an exit terminal.
In these cases, extend the 140 ft tangent section of the standard exit terminal ahead on tangent
before an initial ramp curve to the right is designed into the ramp alignment. The cross slope of
the ramp at Section C-C and beyond should be set at 3/16/ft. Near the end of the tangent
section, the ramp is then rotated to transition into the superelevation runoff length.
Figure 37-6.F(2)
37-6.17
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Ramp cross slopes and superelevation rates for horizontal curves on ramps near the freeway
ramp terminal must be developed to properly transition the driver from the mainline to the first
curve on the exit ramp. The following will apply:
1. Cross Slope. The cross slope of the initial segment of the ramp departure from the
through lane, or an auxiliary lane preceding the exit ramp is usually sloped at the same
rate as the mainline. However, if the mainline has a flat longitudinal grade (i.e., less than
0.35%), consider increasing the cross slope rate on an auxiliary lane and the exit
terminal to 2%. Where the mainline is curving to the right, the maximum cross slope on
the exit terminal is 5%. Where the mainline is curving to the left, the maximum cross
slope on the terminal is 4%.
3. Radius/Superelevation Rate. Section 32-3 discusses the use of Method 5 for open
roadway conditions to distribute superelevation and side friction. This theoretical basis
also applies to the ramp portion of freeway exit terminals. Therefore, Figure 32-3.B (emax
= 8%) and Figure 32-3.C (emax = 6%) are used to determine the proper radius and
superelevation rate for horizontal curves on exit ramps. Also, see Figure 37-4.F. To
determine the applicable design speed to use, see Figure 37-6.G.
US Customary Metric
Figure 37-6.G
37-6.18
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
The gore area is normally considered both the paved triangular area between the through lane
and the exit ramp, plus the graded area that extends a significant distance downstream beyond
the gore nose; see Figure 37-6.H. The following definitions will apply:
1. Physical Nose. This is a point 100 ft (30 m) downstream of Section B-B from where the
16 ft (4.9 m) ramp width begins. As illustrated in Figure 37-6.H, the physical nose has a
dimensional width of 6 ft 4 in (1.94 m).
2. Gore Nose. This is the point where the paved shoulders separate from each other and
the sodded area begins as the ramp and mainline diverge. As illustrated in Figure
37-6.H, the gore nose has a dimensional width of 20 ft 2¾ in (6.3 m), which includes the
10 ft (3.0 m) right shoulder of the freeway and the 4 ft (1.2 m) paved left shoulder of the
ramp.
1. Roadside Obstacles. Desirably, the area beyond the gore nose should be free of all
obstacles (except the ramp exit sign) for at least 100 ft (30 m) or more beyond the gore
nose. Any obstacles within approximately 350 ft (100 m) of the gore nose should be
made breakaway or shielded by a barrier. See Chapter 38 for additional guidance for
the treatment of roadside obstacles.
2. Curbing. Do not use curbing within the gore area of an exit terminal.
3. Side Slopes. Side slopes and ditches adjacent to the gore area should meet the same
criteria as the mainline. The graded area beyond the gore nose should be as flat as
practical, but still drain properly. The exit terminal should be located so there are no
major elevation differences in this area. For some reconstruction projects, the vertical
divergence of the ramp and mainline profiles may warrant protection for both roadways
beyond the gore nose (e.g., guardrail and/or impact attenuators).
4. Cross Slopes. The paved triangular gore area between the through lanes and exit ramp
should be flat and traversable. The cross slopes in the gore area from the physical nose
to the gore nose are 3/16/ft (1.5%). This design provides a drainage swale in the
neutral area of the terminal and is shown in Figure 37-6.H.
5. Traffic Control Devices. Signing in advance of the exit and at the divergence should be
according to the ILMUTCD and Bureau of Operations’ Policies and Procedures Manual.
37-6.19
HARD COPIES UNCONTROLLED
Illinois
37-6.20
INTERCHANGES
FIGURE 37-6.H
February 2014
Illinois INTERCHANGES February 2014
37-6.01(f) Structures
Exit ramp terminals on or near structures can create a split-bridge design which, because of
safety, economic, and maintenance considerations, should be avoided. A split-bridge deck
design may be required where the distance from the right edge of the mainline traveled way to
the left edge of the ramp exceeds 36 ft (11 m). This results in a fixed object on the structure
that must be shielded by an impact attenuator. The following, in order of preference, presents
options for addressing this problem:
1. Physical Nose Beyond Structure. Figure 37-6.I(a) illustrates the desirable position of the
exit ramp terminal on a structure. This position allows an appropriate perception and
reaction distance between the structure and ramp gore nose. It also permits the
placement of the 30 ft (9 m) bridge approach pavement to be coordinated with the
preferred terminal construction.
2. Gore Nose on Structure. Figure 37-6.I(b) illustrates a single structure design with the
exit ramp terminal positioned so that the distance between the mainline and ramp does
not exceed 36 ft (11 m). Preferably, the structure should be placed upstream of the 36 ft
(11 m) maximum offset.
3. Gore Nose on Split Structure. Figure 37-6.I(c) illustrates a split-bridge design which
cannot be avoided due to the length and location of a structure. The designer must
provide an impact attenuator for this special situation. For information on the required
minimum impact attenuator area, see Section 38-8.
Figure 37-6.J illustrates the minimum position for an exit ramp terminal near an overhead
structure. To achieve the optimized design and travel distance, locate the physical nose three
seconds of travel time from the edge of the structure.
37-6.02(a) Types
The entrance ramp terminal is a speed-change lane that permits ramp traffic to accelerate and
merge with the high-speed traffic on the mainline. When designing the interchange, consider
the following entrance ramp types:
1. Standard Entrance Terminal. There are two basic types of entrance freeway ramp
terminals the parallel design and the taper design. For all new and reconstructed
ramps, use the taper design, except as noted in Section 37-6.02(b). Figure 37-6.K and
the Illinois Highway Standards illustrate the standard entrance ramp terminal design
used by the Department. Use this ramp design for all single-lane entrances where the
level of service of the ramp terminal is equal to or greater than that of the mainline.
Entrance ramp terminals may carry a marked route provided the marked route is not a
freeway or expressway. Where a freeway or expressway merges at an interchange, use
the major convergence design as discussed in Section 37-6.04.
37-6.21
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Note: Where an exit terminal is placed on a structure, the minimum cross slope is 1/4/ft (2%). The
1/4/ft (2%) is measured perpendicular to the edge of the mainline pavement, which will require a
modification of the standard exit terminal profile.
Figure 37-6.I
37-6.22
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Figure 37-6.J
2. Entrance Terminal with an Auxiliary Lane. An auxiliary lane may be required after the
entrance terminal:
where the entering traffic exceeds the appropriate service volume of a standard
entrance terminal design but where a two-lane entrance ramp is not required.
Figure 37-6.L illustrates the design criteria for an entrance terminal with an auxiliary
lane. The final ramp radius typically is 760 ft (230 m), which requires a 200 ft (60 m)
tangent section preceding the physical nose. Typically, the auxiliary lane should be at
least 1000 ft (300 m). Where the final ramp radius is less than 760 ft (230 m), the length
of the auxiliary lane will be based on the necessary acceleration distance as discussed
in Section 37-6.02(b).
3. Two-Lane Entrances.. Where the entrance design traffic exceeds the service volume of
a single-lane entrance ramp terminal with an auxiliary lane, it may be necessary to
provide a two-lane entrance terminal as illustrated in Figure 37-6.M. Where a two-lane
entrance ramp is required, an additional lane on the freeway is necessary to
accommodate the additional traffic. This lane may be dropped 2500 ft (750 m)
downstream or at the next interchange.
37-6.23
HARD COPIES UNCONTROLLED
Illinois
37-6.24
INTERCHANGES
Notes:
1. For values in %, divide by 100 to obtain vertical offsets. Vertical differences are in inches(mm).
Figure 37-6.K
February 2014
Illinois
INTERCHANGES
Notes:
1. Include cross sections A-A, B-B, C-C, and D-D with the IDS.
2. See Figure 37-6.K for Standard Entrance Ramp Terminal.
Figure 37-6.L
February 2014
37-6.25
Illinois
37-6.26
INTERCHANGES
Note: Include cross sections A-A, B-B, C-C, and D-D with the IDS.
Figure 37-6.M
February 2014
Illinois INTERCHANGES February 2014
If the two-lane entrance is preceded by a two-lane exit ramp terminal, an increase in the
basic number of lanes will generally not be required. In this case, the added lane that
results from the two-lane entrance is considered an auxiliary lane. Note that this design
violates lane balance guidelines discussed in Section 37-2.03. Where the demand
volume of the entering traffic exceeds this design or where the entering roadway is a
freeway or expressway, use the major convergence design as discussed in Section
37-6.04.
37-6.02(b) Length
Consider the following when determining the appropriate length of an entrance terminal:
1. Capacity. Where the mainline and ramp will carry traffic volumes approaching the
design capacity of the merge area, consider using an auxiliary lane entrance ramp
design as discussed in Section 37-6.02(a).
Trucks. Where there are a significant number of trucks to impact the level of service on
the freeway and ramp, acceleration lanes may need to be treated as truck-climbing
lanes. The designer should reference the AASHTO publication A Policy on Geometric
Design of Highways and Streets for truck acceleration rates. Typical areas where trucks
might govern the ramp design include weigh stations, rest areas, truck stops, and
transfer staging terminals. Also consider using truck acceleration criteria where there is
substantial entering truck traffic and where the interchange crossroad has a high-skew
angle or there is a significant crash history involving trucks attributable to an inadequate
acceleration length.
2. Gradients. Where the gradient of the mainline and/or ramp exceeds +3%, the
acceleration length may need to be adjusted. These adjustments are discussed in
Section 36-2.03(e). For downgrades, use the standard entrance terminal design, and do
not reduce the acceleration distance.
3. Horizontal Curves. The application of the acceleration criteria regarding horizontal curves
preceding the entrance terminal are as follows:
a. Design Speed. The design speed of the horizontal curve adjacent to an entrance
terminal should be determined by open-roadway conditions. See Figure 37-4.F
and Chapter 32.
37-6.27
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
US Customary
75 70 60 50 40(2)(3)
Metric
Notes:
1. R1 is the radius of curve connecting to L1 of the standard entrance terminal. See Figure
37-6.K.
3. 100 ft (30 m) allowed for L1 at this mainline design speed. See figure 37-6.K.
Figure 37-6.N
37-6.28
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
37-6.29
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
c. Low-Volume Conditions. Where existing volumes on the mainline are low and
where the slower entering vehicles will not reduce the level of service on the
mainline, the use of the standard entrance terminal may be considered. The
speed profile of merging trucks onto the mainline must be investigated and
documented. However, provide sufficient right-of-way so that an auxiliary lane can
be added in the future.
d. Secondary Impacts. Before providing any additional acceleration lane length, the
designer must consider its impacts (e.g., additional construction costs, wider
structures, right-of-way impacts).
Decision sight distance desirably should be provided for drivers on the mainline approaching an
entrance terminal. They need sufficient distance to see the merging traffic and adjust their
speed or change lanes to allow the merging traffic to enter the freeway. Likewise, drivers on the
entrance ramp need to see a sufficient distance to locate gaps in the traffic stream for merging.
Section 31-3 discusses decision sight distance in more detail.
Standard entrance terminal designs have been developed to include appropriate superelevation
transitions and desirable crossover crown conditions where the terminal connects onto the
mainline; see Figure 37-6.K and the Highway Standards. When an IDS is prepared, develop
and show on the IDS the detailed cross section at A-A as indicated in Figure 37-6.K.
1. Physical Nose. This is a point located at Section C-C, as illustrated in Figure 37-6.K and
has a dimensional width of 4 ft (1.2 m).
2. Gore Nose. This is a point where the sodded area ends and the paved shoulders
connect. The gore nose, excluding the mainline right shoulder and ramp left shoulder, is
2 ft (600 mm) wide as shown in Figure 37-6.K.
37-6.30
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Where two freeways separate, provide a major divergence as shown in Figures 37-6.O, 37-6.P,
and 37-3.Q. The most important concept in the use of a major divergence is that if the route
turns at an interchange, the physical divergence of the roadways should also occur in the same
direction. To maintain lane balance, an additional interior lane will be required preceding the
divergence. The widening of the interior lane from 12 ft to 24 ft (3.6 m to 7.2 m) should occur in
a distance of 1000 ft (300 m). This provides a driver in the center lane the option of selecting
either direction of travel without having to change lanes.
Add additional lanes to the side of the lesser-preferred route. Check for lane balance. Pavement
joints should normally favor the freeway with the higher volume of traffic. An exception to this rule
is that in most cases, regardless of the traffic volume split, the Interstate is considered the preferred
route. Provide a minimum tangent length of 200 ft (60 m) beyond the 6 ft (1.8 m) physical nose to
facilitate a change of cross slope preceding the initial curve of any diverging roadway.
Where a major divergence is required but the preferred design of an equal split of the roadways
cannot be achieved due to the existing freeway alignment, a modified divergence design can be
used as shown in Figure 37-6.P. In addition, where a divergence design is required and
sufficient right-of-way is not available to build the one-sided divergence and where the diverging
traffic volume is not significant, a two-lane exit terminal design may be considered. However,
before using the two-lane exit design, coordination and approval must be received from BDE.
Consider a minor divergence for the following situations; see Figure 37-6.R:
where a highway terminates into separate single lane ramps (e.g., at a trumpet
interchange);
Where two freeways merge, provide a major convergence design as illustrated in Figure 37-6.S.
The number of lanes downstream from the convergence generally will be one less than the
combined total of the two approaching roadways. Under some circumstances, traffic demand
may require that the number of lanes departing the merge area be the same number as the two
approaching roadways.
37-6.31
HARD COPIES UNCONTROLLED
Illinois
37-6.32
INTERCHANGES
Notes:
1. Develop cross sections A-A, B-B, C-C, and D-D during the preparation of the IDS.
2. The divergence can be designed to divert traffic from either side of an existing roadway.
3. Full superelevation is attained at Section D-D.
Figure 37-6.O
February 2014
Illinois
INTERCHANGES
Notes:
1. Develop cross sections A-A, B-B, C-C, and D-D during the preparation of the IDS.
2. The divergence can be designed to divert traffic from either side of an existing roadway.
3. Full superelevation is attained at Section D-D.
37-6.33
Figure 37-6.P
Illinois
37-6.34
INTERCHANGES
Notes:
1. Develop cross sections A-A, B-B, C-C, and D-D during the preparation of the IDS.
2. The divergence can be designed to divert traffic from either side of an existing roadway.
3. Where a horizontal curve is provided downstream from the divergence, full superelevation is attained at Section D-D.
Figure 37-6.Q
February 2014
Illinois INTERCHANGES February 2014
Note: Develop cross sections A-A, B-B, C-C, and D-D during the preparation of IDS.
MINOR DIVERGENCES
Figure 37-6.R
37-6.35
HARD COPIES UNCONTROLLED
Illinois
37-6.36
INTERCHANGES
Notes:
1. If the right-hand lane is proposed to be dropped for capacity reasons, provide a minimum 1500 ft (450 m) auxiliary lane and a
550 ft (165 m) taper.
2. The convergence can be designed to merge from either side.
3. Develop cross sections A-A, B-B, C-C, and D-D during the preparation of IDS.
Figure 37-6.S
February 2014
Illinois INTERCHANGES February 2014
Typically, a lane drop will be required downstream from the convergence. The most desirable
and typical design will be to drop the right slow-speed lane versus the left high-speed lane.
However, it also may be desirable to drop the left lane of the merging roadway if it is serving the
lowest volume per lane. This design should be reviewed during the development of the IDS.
Consider a minor convergence for the following situations; see Figure 37-6.T:
where interchange ramps converge to form either a single or double lane roadway (e.g.,
trumpet interchanges) within complex interchanges; or
37-6.37
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
Notes:
1. Develop cross sections A-A, B-B, C-C, D-D, and E-E during the preparation of IDS.
2. Ramp cross slope should be determined by downstream horizontal alignment.
MINOR CONVERGENCES
Figure 37-6.T
37-6.38
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES February 2014
37-6.39
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES November 2011
37-7 REFERENCES
3. “Design Standards for Highways,” 23 CFR 625, Code of Federal Regulations, Title 23
(Highways), Part 625, April 1, 1997.
4. “Additional Interchanges to the Interstate System,” Federal Register, Vol. 55, No. 204,
October 22, 1990.
5. “Additional Interchanges to the Interstate System,” Federal Register, Vol. 63, No. 28,
February 11, 1998.
6. “Access to the Interstate System,” Federal Register, Vol. 67, No. 165, August 27, 2009.
10. NCHRP 345, Single Point Urban Interchange, Design and Operations Analysis,
Transportation Research Board, 1991.
11. “A Comparison of Two Diamond Interchange Forms in Urban Areas,” ITE Journal, May
1989.
13. Guidelines for Preliminary Selection of the Optimum Interchange Type for Specific
Location, FHWA/VTRC99-R15, FHWA, 1999.
16. “Distance Requirements for Frontage-Road Ramps to Cross Streets: Urban Freeway
Design,” TRR 682, Transportation Research Board, 1978.
17. NCHRP 3-55(5) Capacity and Quality of Service of Weaving Areas, Transportation
Research Board, 1996.
37-7.1
HARD COPIES UNCONTROLLED
Illinois INTERCHANGES November 2011
18. Manual on Uniform Traffic Control Devices, FHWA, ATSSA, AASHTO, and ITE, 2009.
19. Interchange Operations on the Local Street Side, Transportation Research Circular No.
430, Transportation Research Board, 1994.
21. “Interchange Ramp Geometrics Alignment and Superelevation Design,” TRR 1385,
Transportation Research Board, 1993.
37-7.2
HARD COPIES UNCONTROLLED