Quiz - CPM and Pert
Quiz - CPM and Pert
2) Given the following data of software development. Times are given in weeks. (200
points)
ACTIVITY PRECEDING OPTIMISTIC PROBABLE PESSIMISTIC
TIME TIME TIME
A - 7 9 14
B A 2 2 8
C A 8 12 16
D A 3 5 10
E B 4 6 8
F B 6 8 10
G C, F 2 3 4
H D 2 2 8
I H 6 8 16
J G, I 4 6 14
K E, J 2 2 5
A. Draw the network diagram and determine the ES, EF, LS, LF, and Slack time.
B. Which activities form the critical path?
C. What is the estimated time of the critical path?
D. What are the project variance and a project standard deviation?
E. What is the probability of completion of the project after week 40?