Construction of Toilet Facilities at River State University, Port Harcourt, Rivers State
Construction of Toilet Facilities at River State University, Port Harcourt, Rivers State
1.1 Project Documentations /Approvals and Kickoff meeting: 7th April 2021.
1.7 Commenced and completed Roofing frames and roofing sheets installation.
BRC Fabric Mesh Re-enforcement 100% Completed in conformity to specifications & Standard.
Sawn formwork to vertical side of
100% Completed in conformity to specifications & Standard.
Column
Sawn formwork to sides of steps &
100% Completed in conformity to specifications & Standard.
ramps
Sawn formwork to edges of bed,
100% Completed in conformity to specifications & Standard.
beam
Spreading of Damp Proof 100% Completed in conformity to specifications & Standard.
Casting of DPC 100% Completed in conformity to specifications & Standard.
SUPER-STRUCTURE WORKS (Blocks works, including associated Concrete, Conduiting, Wiring and
Piping Works)
WEEK 3 BETAGOD INVESTMENT Doc. No. BGIL/TEPENG/003/21048
LIMITED
Construction of Toilet
Facilities at River State
University, Port Harcourt
Mechanical Installation & Fittings 50% Ongoing in conformity to specifications & Standard.
EQUIPMENT AND FURNITURE INSTALLATION (Delivery to Site and Installation of all equipments
St Furniture).
Delivery of Generators &
0%
Accessories/Installation
Delivery of Medical
0%
Equipment/Installation
Delivery of Office
0%
Equipment/Installation
Commissioning of site 0%
4.1 No delays
June 2021.
2021.
Block completed
Soakaway on going
Soak Away completed