University of Technology, Jamaica: Faculty of The Built Environment
University of Technology, Jamaica: Faculty of The Built Environment
THEORY/PRACTICAL : THEORY
GROUP : CVE1
DURATION : 2 HOURS
________________________________________________________________
INSTRUCTIONS:
1. Answer all questions in Section A and one (1) question from Section B.
2. The answers for section A must be written on the question paper and
attached to the inside cover of the answer booklet.
3. The answer for section B must be numbered identical to the question being
answered.
5. The intended mark for each question is indicated at the end of the question
unless otherwise stated.
7. This paper is worth a total of 70 marks and represents 60% of the total mark
for this module.
Page 1 of 9
SECTION A PART 1 - 10 MARKS
Instruction:
Indicate the correct answer to each item below by circling for TRUE statements
and for FALSE statements.
5. T F A traverse that begins and ends on the same known point is known as
a closed loop traverse.
8. T F The stadia hairs can be read as a check on the readings of the main
crosshair.
10. T F Plane surveying computations are carried out on the assumption that
the surveyor is working on a flat surface.
Page 2 of 9
SECTION A PART 2 - 10 MARKS
INSTRUCTION:
Indicate the correct answer to each item below by circling the letter that indicates the
correct answer.
___________________________________________________________________________
Question # 11- 13
The readings obtained from a two peg test carried out on an automatic level with a single
level staff set up alternatively at two pegs A and B placed 60 m apart were as follows.
Question 11
(a) 0.740
(b) 1.491
(c) 2.143
(d) 0.423
Question 12
If the level is in good adjustment, what staff reading would be observed on point A
from the second set up?
(a) 1.642
(b) 2.380
(c) 2.079
(d) 2.502
Question 13
(a) 0.003
(b) 0.030
(c) 0.300
(d) 3.000
Question 14
Page 3 of 9
Benchmark Levelling is defined as:
Question 15
Question 16
Which of the following is/are Global Navigation Satellite System(s) operating worldwide?
i) China BEIDOU
ii) Russian GLONASS
iii) United States NAVSTAR
iv) European Union's GALILEO
Question 17
Which of the following would provide an independent check for observations and
measurement?
(a) Triangulation with two angles measured.
(b) Trilateration with two distances measured.
(c) An open traverse with angles and distances measured.
(d) A closed traverse with angles and distances measured.
Page 4 of 9
Question 18
Which one of the following explains why the staff is sometimes tilted slowly to and from the
instrument during a levelling exercise?
Question 19
Cumulative errors in surveying are more serious than compensating errors because:
Question 20
Which one of the following sources of error would be eliminated by making backsight
distances and foresight distances equal?
Question 21
The following observations were taken with the Total Station. Reduce the fieldbook to obtain
the mean horizontal and vertical angles. [6
marks]
Table # 1
Pointing Horizontal. Reading Vertical Reading Slope Dist.
F.R. A-B 200o 30′ 50″ 264o 59′ 40″
F.R A-C 240o 40′ 59″ 265o 34′ 20″
F.L .A-C 060o 40′ 50″ 094o 25′ 26″ 32.48m
o o
F.L. A-B 020 30′ 40″ 095 00′ 04″ 39.67m
Question 22
State the plans and drawings which are required from the beginning to the end of any
construction project. [4 marks]
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Question 23
List four (4) methods of controlling the vertical alignment of high rise structures. [2 marks]
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Page 6 of 9
Question 24
List three (3) methods for measuring vertical distances and determining the elevations of
points.
[3 marks]
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Question 25
Three points A,B, and C lie on a straight line with B between A and C. The distance BC =
211.000m. The coordinates of A and B in metres are
A 497.000m N, 610.000m E
B 350.000m N, 331.000m E
Question 26
What are the steps that would be taken if it was found that the proportional accuracy of a
traverse is not acceptable? [5 marks]
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Page 7 of 9
SECTION B - 25 MARKS
INSTRUCTION
Answer one (1) from this section in the answer booklet.
___________________________________________________________________________
Question 27
Table # 2 shows the readings taken to determine the clearance between the level of a river
and the soffit of a road bridge.
Table # 2
Intermediate Reduced
Back Sight Sight Fore Sight Level Remarks
0.872 21.460 OBM
0.665 3.980 TP1
2.920 River level at A
-1.332 Soffit of Bridge at A
-1.312 Soffit of Bridge at B
-1.294 Soffit of Bridge at C
-1.280 Soffit of Bridge at D
2.920 River level at D
4.216 0.597 TP2
1.155 OBM
(a) Reduce the levels and determine the clearance between the river level and the soffit of
the bridge using:
(a) Explain three (3) practical field procedures that should be adhered to in order to
avoid the errors that may arise when carrying out levelling work. [5 marks]
Question 28
(a) You are required to work on a small residential building site. Your supervisor tells
you that he has a topographic plan which shows a TBM but its elevation cannot be
read from the plan. There is a BM located 400 m down the road. He has asked you
to re-establish the elevation of the TBM on the site to within + 0.02 m.
(b) As the junior engineer in charge of surveying works on site, what suggestions would
you make to the surveying assistant to help ensure accurate work in levelling?
[10 marks]
Page 8 of 9
Question 29
Table # 3
(b) Compute the adjustments to be applied to all the lines in the network. [10
marks]
(c) Calculate the corrected latitudes and departures for all the lines in the network.
[10 marks]
(d) How would you check that the latitudes and departures were correctly adjusted? [1
mark]
Page 9 of 9