Project Execution Plan Piping
Project Execution Plan Piping
Document No.:
CONTRACTOR: SAO MAI BEN DINH PETROLEUM INVESTMENT JSC
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 2 of 22
Revision No.: 0
EXECUTION PLAN Page 3 of 22
CONTENTS
1. INSTRODUCTION ...................................................................................................................... 4
1.1. Objective of this document ..................................................................................................................................... 4
1.2. Definitions/ abbreviation ........................................................................................................................................ 4
2. SUBCONTRACTOR’S SCOPE OF WORKS ............................................................................. 5
3. PROJECT OBJECTIVES ............................................................................................................. 5
4. CONSTRUCTION MILESTONE ................................................................................................ 5
5. KEY RISK AND MANAGEMENT ............................................................................................. 6
6. PROJECT ORGANIZATION ...................................................................................................... 6
7. EXECUTION PLAN FOR NT3&4 COMBINED CYCLE POWER CHART ............................ 6
8. PROJECT MANAGEMENT SYSTEM AND PROCEDURES: ................................................. 7
9. CONSTRUCTION ENGINEERING EXECUTION .................................................................... 8
10. FABRICATION ............................................................................................................................ 8
10.1. FABRICATION PIPING: .................................................................................................................................. 8
10.1.1. General ........................................................................................................................................................... 8
10.1.2. Material Stock ................................................................................................................................................ 9
10.1.3. Fabrication ...................................................................................................................................................... 9
10.1.4. Preheating ..................................................................................................................................................... 11
10.1.5. Heat treatment .............................................................................................................................................. 11
10.1.6. NDE and Repair of defects ........................................................................................................................... 11
10.1.7. Painting:........................................................................................................................................................ 12
10.2. FABRICATION PIPE SUPPORT: .................................................................................................................. 12
10.2.1. Cutting: ......................................................................................................................................................... 12
10.2.2. Drillings holes .............................................................................................................................................. 12
10.2.3. End preparation fit-up and Alignment: ......................................................................................................... 12
10.2.4. Welding during fabrication of pipe support:................................................................................................. 13
10.3. FLOODING, CLEANING AND GAUGING: ................................................................................................. 13
10.3.1. Flooding, Cleaning ....................................................................................................................................... 13
10.3.2. Contingency Flooding .................................................................................................................................. 13
10.3.3. Gauging ........................................................................................................................................................ 14
10.4. HYDROSTATIC PRESSURE TESTING :...................................................................................................... 14
10.4.1. Thermal Stabilisation .................................................................................................................................... 14
10.4.2. Pressurisation ................................................................................................................................................ 14
10.4.3. Test Pressure ................................................................................................................................................. 15
10.4.4. Test Hold Period ........................................................................................................................................... 15
10.4.5. Depressurisation ........................................................................................................................................... 15
10.4.6. Leak Identification and Rectification ........................................................................................................... 16
10.5. BLASTING AND PAINTING : ....................................................................................................................... 16
10.5.1. Surface preparation:...................................................................................................................................... 16
10.5.2. Application conditions :................................................................................................................................ 18
10.5.3. Inspection ..................................................................................................................................................... 20
11. EQUIPMENT ERECTION ......................................................................................................... 21
11.1. Equipment Unloading, Preservation ................................................................................................................. 21
11.2. Foundation Inspection ...................................................................................................................................... 21
11.3. Lifting Drawings, Procedure ............................................................................................................................ 21
11.4. Lifting Equipment To Erection Point, Completion .......................................................................................... 21
12. QA/AC ........................................................................................................................................ 22
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 4 of 22
1. INSTRODUCTION
Follow of Technical requisition for Mechanical Fabrication and Erction Work . PVSB submit this
execution plan and method statement Fabrication of NT3&4 Combined Cycle Power Plant . This plan
briefly describes how PVSB plan to execute and manage the work, and it shall be updated and revised
during the project life.
TBA : To Be Advised
Revision No.: 0
EXECUTION PLAN Page 5 of 22
SUBCONTRACTOR’s Scope of Works will consist of fabrication & erection of NT3&4 Combined
Cycle Power Plant project
PVSB shall fulfill SUBCONTRACTOR’s scope of work in section IV _ NT34-BID-TRQ-001 _ TR
for Mechanical Fabrication and Erection Works Service
3. PROJECT OBJECTIVES
PVSB has set out key objectives for NT3&4 Combined Cycle Power Plant project as follows:
Overall Objectives
− Consistently meet or exceed Company/ Contractor’s specified requirements for the project.
Health, Safety and Environmental Objectives
− The primary safety goal for the project is to complete all phases of the work without a single
lost time incident.
− Achieve a continuous improvement over historical records for the number of Near Misses,
Medical Treatment Cases and Recordable Incidents.
− Ensure that the completion of the work realizes an improvement in the standard of the worksite
and local community environment.
Quality Objectives
− Manage the project to avoid or minimize non-conformance reports (NCR’s) and construction
re-work in fabrication yard.
4. CONSTRUCTION MILESTONE
The detail of progress about the WORK shall be General key milestones are shown as below:
Mechanical (Equipment Erection)
Start of the Works: Jan 2022 (Tentative)
End of the Works: July 2023 (Tentative)
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 6 of 22
Upon the contract award PVSB will develop and document a project risk management plan that is a
process of identifying, managing and mitigating the risks associated with the Prefabrication,
Installation for Piping, Equipment and Structure of NT3&4 Combined Cycle Power Plant project. The
risk management process is to assist PVSB and other related parties in assuring effective delivery of
the project against costs and schedule constraints. This will be developed and agreed with Contractor
in due course.
PVSB Project Management Team (PMT) together with Contractor PMT will organize risk
workshops/ brainstorming sessions to identify project risks and then allocate the risks to the party who
is best able to manage/mitigate them. The risks shall be registered and documented. This shall be
updated monthly by appropriate persons to ensure all risks have been assessed and mitigated.
6. PROJECT ORGANIZATION
Upon sanction of the project, PVSB will establish a dedicated Project Management Team mainly
utilizing its owned resources based in its office in Ba Ria Vung Tau,Vietnam for the management of
the Work. This team will be led by a dedicated Contract Project Manager and Project Key Personnel
normally are manned as follows:
− For the details of the Contractor Organization Chart, kindly refer to the following attachments:
Please refer: Technical Proposal /Section 2.3 – Nominated Key Personel & CVs
PVSB Project Personnel:
PVSB is responsible to supply all the necessary manpower resources for execution of the works under
PVSB’s scope. The manpower includes the direct and indirect manpower.
− Project key personnel, refer to: Technical Proposal/Section 2.2 – Project Organization Chart
− Detail mobilization plan, refer to: Technical Proposal\Section 2.8 – Manpower Shecdule &
Histogram
PVSB is very familiar with and competent in the fabrication structure for the oil and gas industry.
The fabrication organization chart of PVSB is developed in order to provide a view of the
organization of the fabrication team. Please refer to organization of the fabrication detailed in:
Technical Proposal/Section 2.2 – Project Organization Chart
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 7 of 22
PVSB is fully compliance with Contractor’s requirements management system and procedures.
Project controls
Project Control work as set out herein is the overall control of the Project including contract
management, cost control, coordination for risk management, coordination for progress control in
order to ensure the execution of the Project in compliance with contractual requirements.
Planning and scheduling
A Planning Manager assisted by other planning engineers from PVSB, will be assigned to work under
the direction of the Project Manager. PVSB will follow the Contractor’s schedule.
Reporting:
The Planning manager shall be responsible for all reports related to planning & progress of the
project. He shall liaise with all relevant departments to provide information required for the
preparation of weekly/monthly progress reports.
All relevant departments shall furnish their respective works status to the Planning manager for
compilation.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 8 of 22
10. FABRICATION
10.1.1. General
Revision No.: 0
EXECUTION PLAN Page 9 of 22
Straight pipes, fitting and flanges shall be requested, received, handled and temporarily
stored in accordance with Project Procedure.
Special attention shall be give to protection of flange(s) faces to prevent any damage, by
ensuring that flanges received from storage are properly protected.
10.1.3. Fabrication
10.1.3.1. Cutting
Prior to cutting straight pipes, the following checks shall be carried out:
Material conform to Specification, Piping Drawings.
Spool No, is clearly marked on pipe to be cut.
Revision No.: 0
EXECUTION PLAN Page 10 of 22
Butt weld faces to be joined shall be aligned in accordance with approved welding
procedure (WPS).
Piping distortions: Any distortion of piping to bring it into alignment for joint assembly
which introduces a detrimental strain in equipment or piping components is prohibited.
Flange joints: Before bolting up, flange faces shall be aligned to the design plane
within 1 mm in 200 mm (1/16in./ft) measured across any diameter; flange bolt holes
shall be aligned within 3 mm (1/8 in.) maximum offset.
Minimum distance between longitudinal welds and pipe girth welds shall be at least
300 apart from the horizontal center line. Min. distance between attachment welds,
girth welds & branch connections shall be 50 mm.
The clear distance between edges of adjacent circumferential butt welds shall be 100
mm or half the pipe diameter whichever is greater.
As a general requirement, surfaces to be welded shall clean and free from grease, oil,
paint, or other material which is detrimental to welding.
Welding shall be carried out as per approved Welding Procedure Specification and by
qualified welders.
Fabrication work shall be carried out in a covered area and proper wind protection
shall be provided.
Revision No.: 0
EXECUTION PLAN Page 11 of 22
10.1.4. Preheating
Preheating is used, along with heat treatment, to minimize the detrimental effects of high
temperature and severe thermal gradients inherent in welding. The necessity for
preheating and the temperature to be used shall be specified in the engineering design and
demonstrated by procedure qualification. The requirements and recommendation herein
apply to all types of welding including tack welds, repair weld, and seal welds or threaded
joints.
b/ Heat treatment to be used after production welding shall be specified in the WPS
and shall be used in qualifying the welding procedure.
c/ The engineering design shall specify the examination and/or other production
quality control (not less than the requirement of this code ) to ensure that the final
welds are of adequate quality.
Revision No.: 0
EXECUTION PLAN Page 12 of 22
10.1.7. Painting:
10.2.1. Cutting:
After the cutting the components are to be marking and drilled bolts holes also weep holes
according to drawings
• Butt weld faces to be joined shall be aligned in accordance with approved welding
procedure (WPS).
• The compoments are to be fit-up togethers according to drawings
• Maximum allawable gap is 3mm for each guide and stoppers as unless in otherwise
specified.
• The strong back or reinforcing must be fit-up to the support before dimensional inspect
• Dimensional inspection shall be carried out on pipe support before welding, in
accordance with project specification.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 13 of 22
• As a general requirement, surfaces to be welded shall clean and free from grease, oil,
paint, or other material which is detrimental to welding.
• Welding shall be carried out as per approved Welding Procedure Specification and by
qualified welders.
• Fabrication work shall be carried out in a covered area and proper wind protection
shall be provided.
• Upon completion of welding, dimensional inspection shall be carried out in accordance
with the pertinent pipe support drawing.
10.2.5. NDE and Repair of defects :
• Extent of welding test shall be tested in accordance with drawing indicated.
• he surface of repair welding will be cleaned thoroughly before welding in accordance
with applicable WPS.
Filtered treated water and pigs shall be introduced into the pipeline to ensure removal of
any debris and complete filling of the pipeline system with water.
The volume of water separating the pigs shall ensure suspension and transportation of
debris, flushing of the pipeline and adequate separation of pigs throughout pigging
operations.
All debris received with the pig shall be recorded and then disposed of in accordance with
an accepted procedure which shall take due regard of environmental constraints.
In the event of a wet buckle, flooding (pigging) shall be performed to clean the pipeline
prior to dewatering for recovery and continuation of pipelay. The time allowed between a
wet buckle and commencement of contingency flooding will be identified by Contractor
on a project basis.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 14 of 22
10.3.3. Gauging
Gauging shall be carried out in accordance with this Standard and DNV-OS-F101 Section
10 to ensure that the pipeline sections are uniform and undamaged.
A written and photographic record shall be made of each gauging plate condition before it
is loaded.
If any gauge plate indicates a change in pipeline geometry which is outside that permitted
by DNV-OS-F101 Section 10, the damaged section of pipe shall be located and rectified.
Pipelines shall not be pressurised unless thermal stabilisation is achieved after flooding.
Methods, calculations and models to demonstrate the thermal stabilisation of the pipelines
shall be accepted by Woodside’s Representative.
10.4.2. Pressurisation
Pressurisation operations shall not commennce until Contractor ‘s approval has been
given. All the relevant safety measure required by the project safety plans shall be in
place prior to commencing pressurization .
The pressurisation line shall be secured against vibration and positioned such that the
safety of personnel is ensured.
The pipeline shall be pressurised in accordance with DNV-OS-F101 Section 10. The
pipeline pressurisation shall be performed as a controlled operation with consideration for
maximum allowable velocities in the inlet piping. The last 5 % up to test pressure shall be
raised at a reduced rate to ensure that the test pressure is not exceeded.
The maximum quantity of air within the pipeline shall be determined in accordance with
DNV-OS-F101 Section 10, using calculation methods accepted by Woodside
Representative. If the air content of the pipeline exceeds 0.2 % of the calculated pipeline
volume at 35 barg, remedial action shall be taken using procedures subject to Contractor’s
acceptance.
During pressurisation, the time, volume pumped and gauge pressure shall be recorded at
fifteen (15) minute intervals, on a test report. This information shall also be used to
produce a plot of the pressure against volume during the initial filling and pressurisation.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 15 of 22
The pipeline shall be pressurised to the test pressure specified in the CDS. The test
pressure shall take account of the corresponding reference level. The elevation difference
between the sea-level/water surface and the test head on offshore facilities shall be
measured to check that the test pressure at the water surface and high point falls within
the specified limits.
Sea-level variations shall be accounted for when monitoring and conducting the
pressurisation operations. As a minimum, a calibrated pressure recorder, a calibrated
pressure gauge, a calibrated dead weight tester (or equivalent) and a calibrated flow
meter as defined in DNV-OS-F101 Section 10 and this Engineering Standard shall be
used.
Once test pressure is reached and the pressure is stabilised, a hold period specified in the
CDS and within the acceptable limits defined in DNV-OS-F101, shall commence. The
minimum hold period for the test of each pipeline shall be twenty-four (24) hours. If the
pressure variation during this period is outside the acceptable limits of DNV-OS-F101
Section 10, the hold period shall be extended until a hold period with acceptable pressure
variations has occurred.
The test shall be considered to have commenced when the pressurised pipeline has
stabilised. This point shall be subject to acceptance by Contractor.
Pipeline pressure and ambient temperature shall be continuously recorded. Test pressure
and pipeline temperature shall be logged at least every half hour. Pipeline pressure and
pipeline temperature against time shall be plotted at half hourly intervals. Test charts shall
be clearly marked with date, test section details, and shall be signed off by Contractor if
applicable. If pressure changes are occurring, then readings shall be taken more frequently
in order to determine whether a pressure/temperature correlation exists.
10.4.5. Depressurisation
On completion of the hydrotesting operation the pipelines shall be left full of chemically
treated and filtered water in accordance with this standard. Unless otherwise instructed,
the pipelines shall be left with a nominal residual pressure, at least 0.5 bar in excess of
the ambient external pressure, in order to prevent seawater ingress.
Revision No.: 0
EXECUTION PLAN Page 16 of 22
Surface preparation for coating application will be carried out after cutting and welding
have been completed.
Suitable abrasives to be used for blast cleaning shall be shot blast other suitable abrasive
blasting grits approved by contractor.
Before cleaning operation commences, all rough edges shall be reduced, surface slivers
and laps shall be ground out (all corners and edges are to be rounded to a 2mm minimum
radius), and weld spatter and welds exhibiting excessive surface roughness shall be
smoothed to ensure proper paint adhesion and uniform thickness.
Blasting is not permitted if the relative humidity is greater than 85%, or if the surface
temperature is less than 3 Deg. C above the air dew point.
Blast cleaned surface shall be primed before visible re-rusting occurs or within four hours
of the commencement of blasting. If visible re-rusting occurs then the metal surface shall
be lightly re-blasted and where necessary washed to remove rust blooming and
accumulation of soluble salts. Spent blast abrasive shall be completely removed from the
prepared surface by either vacuum cleaning or stiff-brush sweeping.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 17 of 22
When additional areas are blasted adjacent to newly primed areas, at least 50mm of the
previously primed area shall be re-blasted, with the abrasive directed away from the
coated surface.
The maximum vertical distance between the summit of any peak and the depth of an
immediate adjacent trough on blast cleaned surfaces shall be 80 microns. The minimum
peak-to-valley height shall be 30 microns. Surfaces are to be abrasive blast cleaned to Sa
2.5.
Salt test is required equal to ISO 8502-6 with a maximum conductivity corresponding to
20mg/m2 NACL or paint manufacturers’ recommendation.
Damaged area surface preparation with Power Tool or Hard Tools shall be pursued to
achieve a level of Cleanliness equivalent to the Swedish Pictorial Specification St 3.
Cleanliness Grade Comparison for Abrasive Blast Cleaning
After erection at field surface preparation local to weld areas shall be prepared by use of
Power Tool Cleaning or Hand Tool Cleaning or a combination of these methods.
Surface preparation with Power Tool shall be pursued to achieve a level of Cleanliness
equivalent to the Swedish Pictorial Specification St 3.
The cleaning method(s) undertaken shall remove all weld flux slag and fume weld heat
oxides and weld metal spatter in addition to all loose mill scale or loose paint if present
after welding and testing has been completed.
The use of grinding discs may be included to achieve the removal of tightly adhering
weld splatter, but great care shall be taken to ensure that surface shall not be polished nor
left with a detrimental roughness or gouge marks.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 18 of 22
The coating shall be applied under the environmental conditions established by the
coating manufacturer. No coating shall be applied under the following circumstances:
• Temperatures are below 10℃ or relative Humidity is above 85% (The minimum
temperature limits may be changed from 10℃ to 0℃ in accordance with paint
manufacturer’s recommendations).
• Metal surfaces having temperatures in excess of 38℃ or less than 3℃.
• When temperatures are expected to fall to 0℃ before the paint has dried.
• In rain, snow, fog or mist, nor to wet or damp surfaces.
Compressed air supply used for blast cleaning shall be free from water and oil. Adequate
separators and traps shall be provided and installed in the coolest part of the system; they
shall be regularly emptied to prevent carryover of water and oil. Accumulations of oil and
moisture shall be removed from the air receiver by regular purging. Air compressor shall
not deliver air at a temperature in excess of 110℃.
Nozzles shall be discarded and replaced when over worn.
Where air-operated Equipment is used, the operator’s hood or head gear shall be
ventilated by clean cool air served through a regulator filter, to prevent blast cleaning
residues from being inhaled.
Prior to application, all coating materials shall be vigorously stirred and /or agitated in
spray pots until pigments, vehicles, and catalysis are thoroughly mixed. During
application, coatings shall be continuously stirred by mechanical spray pot agitators or
other approved means.
Coating material shall not be mixed or kept in suspension by using a bubbling air stream.
If settling has occurred, it must be remixed immediately before using. No thinner shall be
added unless necessary for proper application. The type of thinner used shall comply with
the manufacturer’s instructions
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 19 of 22
The comb-type gauge shall be use. The surface selected for measurement should be
smooth. The comb is placed in the newly applied wet paint film. The WFT will be
indicated where the tooth has touched the paint.
(DFTx100)/%Volume solid
The dry film thickness (DFT) measured by a properly calibrated film thickness gauge
(ELCOMETER 456 which range from 0 - 1500 microns).
10.5.2.5. Application:
Paint materials shall only be applied by the paint manufacturers recommended method.
Spray guns shall be held perpendicular to the surface being coated at a maximum distance
of 300 mm from the surface and no closer than 200 mm to the surface. Wet film thickness
(comb) gauges shall be used by paint spray gun operatives to ensure an even and adequate
DFT will be achieved.
Material and air pressure on the spray guns shall be regulated to achieve optimum
atomization of the paint with the lowest possible pressures to avoid spray ricochet from
the surface being painted.
Overlapping horizontal passes shall be made for each spray coat to obtain uniform
application. Particular care shall be exercised to ensure that a uniform, complete wet coat
is applied. Semi-dry spraying results in poor flow-out with excessive pinholing and shall
be avoided.
All runs, air bubbles, sags and other imperfections shall be brushed out immediately or
the coating shall be removed and the surface re-sprayed.
Shop primed surfaces contaminated during transport and site storage shall be thoroughly
washed down with fresh clean water and allowed to dry before the application of further
paint coatings.
When paints are applied by brushing, brushes shall be of a style and quality that will
permit proper application of the material. Brushing shall be done so that a smooth coat as
nearly uniform in thickness as possible is obtained. There shall be no deep "detrimental"
brush marks.
Damage to each coat of paint, whether shop or field applied, shall be repaired by
preparing the affected surface, in accordance with the specified and as originally carried
out, cleaning and spot priming before succeeding coats of paint are applied. Surface
preparation shall be carried out by using hand tool until achievement requirements. Paint
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 20 of 22
10.5.3. Inspection
To ensure the quality control and painting inspection requirements are maintained during
painting operations, inspection will be carried out by the paint manufacturer's
representative and representative of sub-contractor in accordance with the requirements of
this procedure.
The blast cleaned surface shall be inspected to ensure that areas are clean, dusty free, dry
and comply with procedure requirements.
Surface profile shall be check with Keane Tator or ISO 85031-1 Surface profile
Comparator. Surface profile Comparator check shall be recorded and recommended photo
shot as port of traceability and documentation.
Individual coats and completed coating shall be visually inspected for appearance. The
coating shall be free from excessive sagging, dry spray, pinholes, blisters and other types
of coating application defects and shall bear no coating damages.
During coating, the wet film thickness shall be spot- checked, thickness of each coat shall
be measured DFT by means of a magnetic type thickness gauge E456
WFT Measurements
The comb-type gauge shall be used. The surface selected for measurement should be
smooth. The comb is placed in the newly applied wet paint film. The WFT will be
indicated where the tooth has touched the paint.
WFT= (DFTx100)/%Volume solid
WFT Measurement
The thickness of each coat shall be determined prior to the application of subsequent coats
in accordance with SSPC PA-2.
The results of coating thickness shall be recorded on the "Blasting and Painting Inspection
Report" - Appendix I which shall be filled by QAQC team.
The paint manufacturer shall provide a field supervisor during the painting work.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 21 of 22
Subcontractor will receive equipment from carrier and arrange crane to unload the equipment
to storage area.
Inspection will be performed immediately after the equipment is unload storage area. The
subcontractor will coordinate with contractor to inspect, make an inspection record and take
responsibility for the visual inspection and quantity control.
Based on the requirements according to the Spec / Data sheet of the equipment, the
Subcontractor will arrange to preserve the device in a covered area, covered with a canvas or
outdoors. Small equipment can be transported by forklifts, truck cranes will be arranged in the
indoor area. Large equipment (heavy lift group) will be covered and stored in the outdoor area
(in other cases, the Contractor should give specific requirements). Layout of material storage
area according to the attached drawing ...
Subcontractor will arrange fences, barricade and security box to protect the equipment
After receiving and hand over the foundation, the Subcontractor will conduct an inspection of
the bolt position and bolt status according to the foundation drawing of equipment erection , in
case of any deviation or damage, subcontract will report to contract for remedy plan.
All heavy lift equal or above 10T, the Subcontractor shall prepare drawings and lifting
procedure to do with these loads which shall be presented to Contractor's Construction
Manager for study and approval
After the preparation works are completed, the crane procedure is approved by contractor. The
Subcontractor will conduct a final inspection of the entire work, GA meeting and carry out the
lifting according to the procedure.
After the equipment is placed in the correct position, the Subcontractor will conduct the
alignment of the bolts, the ground alignment and tighten bolts. Grouting process will be done
immediately after removing the crane.
After the installation and alignment of equipment is completed, the Subcontractor will invite
Contractor to witness and inspection for preparation of next tasks.
SAO MAI BEN DINH PETROLEUM JOIN STOCK COMPANY(PVSB)
Revision No.: 0
EXECUTION PLAN Page 22 of 22
12. QA/AC