Work Methodology PCC

This document provides a work methodology for placing plain cement concrete (PCC) at the 765kV and 220kV switchyard and control room building project in Lalitpur, India. It outlines an 8-step construction sequence including preparing the excavated surface, placing concrete with the required grade and quantity per drawings, compacting, curing, and conducting quality checks. Safety measures are also addressed, such as barricading work areas and providing lighting in excavated pits. The document references contract documents, drawings, quality plans, and construction standards.

Uploaded by

lost love
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
348 views

Work Methodology PCC

This document provides a work methodology for placing plain cement concrete (PCC) at the 765kV and 220kV switchyard and control room building project in Lalitpur, India. It outlines an 8-step construction sequence including preparing the excavated surface, placing concrete with the required grade and quantity per drawings, compacting, curing, and conducting quality checks. Safety measures are also addressed, such as barricading work areas and providing lighting in excavated pits. The document references contract documents, drawings, quality plans, and construction standards.

Uploaded by

lost love
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Quality Management

System
ITP NO.:
L&T Construction WORK METHODOLOGY PCC LTC/PT&D/SS/CVIL/BIDCO
– 01
Power Transmission &

Distribution

PROJECT : 765KV & 220KV Switchyard for LSTPP at Lalitpur

CONTENT

1. Introduction
2. Scope
3. Reference specification/standards
4. Construction sequence
5. Record
6. Safety
7. Equipments
1.0 Introduction:

This document describes the step wise work methodology to carry out the PCC work of Main
Receiving 765KV & 220KV Switchyard and Control room Building for LSTPP at Lalitpur in
planned and controlled manner with reference to the drawings, technical specification and
standards.

2.0 Scope.

It includes PCC in substructure work etc. Plain/Lean concrete shall be 1:4:8 ,1:3:6 nominal mix
with aggregate of nominal size 40mm maximum or as indicated on drawing . The work shall be
carried out in accordance with the specification and corresponding approved drawings.

3.0 REFRENCE SPECIFICATIONS/STANDARDS:

Following Documents/Drawings/Codes have been referred for the preparation of this method
statement:
1. Contract documents
2. Field quality plan
3. Relevant “ Good for construction “ Drawing
4. IS: 456

4.0 CONSTRUCTION SEQUENCE

Concrete placing:‐
1. The excavated formation level shall be free from loose material.
2. The site engineer will ensure the line level, dimensions and surface to receive the concrete
according to drawings & specifications.
3. Grade of concrete shall be checked as per requirement. Concrete can start only after getting
Pour card clearance.
4. Engineer in charge will inform the client & quality engineer the timing of concrete well in
advance.
5. Water curing of finished concrete surface shall be done for 1 day with water wetting. When
shuttering and reinforcement is being placed / tied, then water sprinkling shall be done.

5.0 RECORD

6. IR with check list


7. Pour card. Format

6.0 SAFETY

8. Necessary measures safety shall be taken care as per the project safety plans .
9. The areas shall be barricaded.
10. Lighting shall be provided around the pits as required.
11. Concrete chute to be used to take the concrete to down.

7. EQUIPMENTS

12. Mixer Machine/Mini Batching Plant (Volumetric)


QUALITY CHECK LIST
CHECK LIST FOR PCC
(To be maintained by Site Engineer)
STRUCTURE: DATE:
LOCATION: QUANTITY:
DRG. NO.:
SL.NO. ITEM DESCRIPTION REQUIRED ACTUAL REMARKS
Check for

1 Bottom level of concrete

2 Surface dressing & preparation

Stability of excavated side slopes


3
ensured

4 Cleanliness of formation level

5 Top level of concrete

6 Compaction of concrete required

Grade of concrete & Quantity as


7
per drg.

8 Curing

L&T CLIENT