Work Methodology PCC
Work Methodology PCC
System
ITP NO.:
L&T Construction WORK METHODOLOGY PCC LTC/PT&D/SS/CVIL/BIDCO
– 01
Power Transmission &
Distribution
CONTENT
1. Introduction
2. Scope
3. Reference specification/standards
4. Construction sequence
5. Record
6. Safety
7. Equipments
1.0 Introduction:
This document describes the step wise work methodology to carry out the PCC work of Main
Receiving 765KV & 220KV Switchyard and Control room Building for LSTPP at Lalitpur in
planned and controlled manner with reference to the drawings, technical specification and
standards.
2.0 Scope.
It includes PCC in substructure work etc. Plain/Lean concrete shall be 1:4:8 ,1:3:6 nominal mix
with aggregate of nominal size 40mm maximum or as indicated on drawing . The work shall be
carried out in accordance with the specification and corresponding approved drawings.
Following Documents/Drawings/Codes have been referred for the preparation of this method
statement:
1. Contract documents
2. Field quality plan
3. Relevant “ Good for construction “ Drawing
4. IS: 456
Concrete placing:‐
1. The excavated formation level shall be free from loose material.
2. The site engineer will ensure the line level, dimensions and surface to receive the concrete
according to drawings & specifications.
3. Grade of concrete shall be checked as per requirement. Concrete can start only after getting
Pour card clearance.
4. Engineer in charge will inform the client & quality engineer the timing of concrete well in
advance.
5. Water curing of finished concrete surface shall be done for 1 day with water wetting. When
shuttering and reinforcement is being placed / tied, then water sprinkling shall be done.
5.0 RECORD
6.0 SAFETY
8. Necessary measures safety shall be taken care as per the project safety plans .
9. The areas shall be barricaded.
10. Lighting shall be provided around the pits as required.
11. Concrete chute to be used to take the concrete to down.
7. EQUIPMENTS
8 Curing
L&T CLIENT