EIM 227 Notes
EIM 227 Notes
2005
i
TABLE OF CONTENTS
ii
3.10 Transfer Lines and General Serial Systems...................................................................................................44
3.10.1 Introduction ...............................................................................................................................................44
3.10.2 Paced lines without buffers ...........................................................................................................................45
3.10.2.1 Operation - Dependent failures .............................................................................................................45
iii
1.0 CLASSIFICATION OF MANUFACTURING SYSTEMS
1. Project
Companies that produce one off, large scale, complex products will normally provide these on a
project basis. A project process concerns the provision of a unique product requiring the co-
ordination of large-scale inputs to achieve a customer’s requirement. *The resource inputs will
normally be taken to where the product is to be bought, since it isn’t feasible to move it once it is
completed. All activities, including all necessary support functions, will usually be controlled by a
total system for the duration the project.
2. Jobbing
A jobbing process is used to meet the one off order requirements of customers. The product
involved will be of an individual nature. This requires that the suppliers interpret the customers’
design and specifications and then apply relatively high skill levels in the conversion process. One
example is a tool room. The one off characteristic means that the product will not be required again
in its exact form, or if it is the demand will tend to be irregular with long time periods between
orders. For this reason, investment in the manufacturing process (jigs, fixtures and specialist
equipment) will not normally be warranted.
3. Batch
A Company decides to manufacture using batch processes because it is providing similar items on a
repeat basis usually in larger volumes than those associated in the jobbing process. This type of
process covers a wide range of volumes compared to other processes. At the low volume end, repeat
orders will be shown and infrequent. At the high volume end, the order quantities may involve many
hours, shifts or even weeks of work for the same product.
Each order quantity is manufactured by setting up that step of the process necessary to complete the
first operation for a particular product. The whole order quantity is completed at this stage. Then
the next operation in the process is made maybe and the total order quantity is completed, until all
stages required to make a product are completed. Meanwhile, the process used to complete the first
operation for the product is then reset to complete an operation for another product and so on.
Examples
1
4. Line
With further increases in volumes, investment is made to provide a process dedicated to the needs of
a single product or a small range of products. The product range is determined at the time of
investment.
In a line process, products are passed through the same sequence of operations. The standard nature of the
products allows for this.
5. Continuous
With continuous processing, a basis material is passed through successive stages or operations and
refined or processed into one or more products. E.g. Petrochemicals. The choice of process is based
on two features, the first is very high volume demand and the second is that the materials involved
can be moved easily from one part of the process to another e.g. Fluids, gases and foods.
The high volume nature of the demand justifies the very high investment involved. The processes
are designed to run all day and everyday in minimum shut downs, due to the high costs of starting up
and closing down. Normally the product range is quire narrow and often the products offered are
purposely restricted in order to enhance volumes.
Another feature in continuos processing is the nature of the materials being processed.
Whereas in line there are manual inputs into the manufacture of the products as they pass along, in
continuous processing, the materials will be transferred automatically from one part of the process to
the next, with the process monitoring and self adjusting flow and quality. The labour tasks in these
situations predominantly involve checking the system and typically do not provide manual inputs
into the process as they would on a line.
Process choice
wide
Engineering
Batch
Continuos petrochemicals
process
Low Volume High
2
1.2 Business implications of process choice (Hill 1993)
3
Process choice
wide
Project
Jobbing
NC machines
Range
dedicated use of a general
machining centres purpose process
Batch
Group technology
Flexible manufacturing
Line systems (FMS) Transfer line
narrow
Mix mode assembly
Continuos
process
Low Volume High
Look at the Companies on the Zimbabwe Stock Exchange for each company identify
the manufacturing system or process which predominates. Include service sector
companies.
4
D) Group technology
Group technology gains for batch processes some of the advantages in high volume line situations.
It does this by changing the process or functional layout associated to batch manufacturing into the
product layout associated to line.
LINE
Group technology
Mix-mode assembly isn’ t technically a hybrid, it is simply a line process that can accommodate the
requirements of a wider range of products that can typically be made on a classic line process.
G) Transfer lines
A transfer line is a hybrid between line and continuous processes. However its root process is still
line because it can be stopped without major cost. The high demand associated in this process
justifies investment designed to reduce the manual inputs associated in a line process and to move
more towards a process that automatically transfers a part from one station to the next positions it,
completes the task and checks quality. Furthermore, deviations from the specified tolerances will be
registered and automatic tooling adjustments and replacements will often be part of the procedure.
To achieve this, the process is numerically controlled in part or in full.
5
1.4 The Role of Numerical Control in Hybrid Processes
Of the hybrid processes mentioned above four are based on the concept of numerical control (NC). The
basis of choice between one NC hybrid process and another is volume.
The NC base of these processes brings in it a level of flexibility that is for greater than that inherent in non-
NC alternatives. This means therefore that the process is more able to cope with a wider range of products
and to handle product mix changes over time.
D
Hi ecre
gh a
er sin
Hybrid NC pr g p
oc ro
es ce
s i ss
Process Choice nv f
es lex
tm ibi
en lity
ta a
Machine Centre nd nd
low pro
er duc
Stardard co t r
st an
FMS m ge
an v
Dedicated uf ar
ac iet
tu y
rin
Mix Mode Assembly LIne g
o
pp
Process choice o
rt
wide
u n
Project civil engineering ity
co
one-off, purpose-built st
s
Range
Jobbing
O Engineering
Batch po ut o
ck f
et
co
narrow
Continuos petrochemicals
process
Low Volume High
Figure 9:
The area below the diagonal is characterized by out of pocket expenses. This area is where the rigidity and
capital intensity of the process are relatively further advanced than the acceptance of the process’ s products.
A company here places significant pressure on its marketing people to drum up the sales volumes needed to
sustain it relatively further advanced process characteristics. The Japanese have successfully employed this
strategy.
The area above the diagonal is characterized by, opportunity costs. Here, the processes characteristics are
relatively less advanced than its product acceptance.
The Company’ s profits suffer because process advances could manufacture the product for less i.e. for goes
the opportunity to earn more.
By positioning above the diagonal, the company places pressure on its manufacturing people to lower costs.
6
References
Hill T (1993) Manufacturing Strategy: The strategic management of the Manufacturing function (2nd Ed.) pp. 105-
MacMillan. ISBN 0-333-57648-9
Groover M P (1985), Automation, Production systems, and Computer-Aided manufacturing
Askin R G and Standridge C R (1993) Modeling and Analysis of Manufacturing Systems, John Wiley & Sons
7
2.0 FACILITY LAYOUT AND DESIGN
Layout is the physical organization or geography found at a facility/location.
Layout problems are stimulated by one of the following
x Product design change
x Introduction of new products
x Changes in volume of demand
x Facilities becoming obsolete
x Poor worker environment
x Change in location or market
x Cost reduction
The last 2 occur very infrequently whilst the first two are common in industry.
8
Job shop environments, for either goods or services, have tended towards process layout. The disadvantage
is that it puts distance between provider and customer
Two or more layout types in a single facility are very common. This is termed a mixed layout e.g. in the Sun
hotel the food can be brought to you whilst you are seated or you can choose your own food by moving in a
plate and picking the food-staffs you desire.
(2) Teamwork - Getting all staff into a cluster enhances teamwork and joint problem solving
9
(3) Rework
When a mistake occurs a product is normally sent back to the department or machine or workstation
where it occurred or to a separate rework line. In a U-shaped layout, the distance to return a mistake
is short, making it easier to follow the (Total Quality Management) TQM principle of correcting
mistakes at source.
Since all stations in a U are immediately accessible from the centre it is easier to distribute materials, parts,
instruction sheets etc.
*total distance covered in a given period (Distance between machine * number of trips done in a period)
TO
FROM SAW LATHE DRILL MILL INSPECTION STATION
10
STEPS POSSIBLE TOOLS
Analyse Product flows From-to chart
Example
The five departments of a warehouse within approximate space requirement and activity relationships are as
follows.
2 ACTIVITY RELATIONSHIPS
Department AREA (m )
Closeness Rating
A- Absolutely necessary
E- Especially important
I- Important
O- Ordinary closeness
U- Unimportant
X- Not desirable
Reasons Code
1- Work flow
2- Supervision
3- Safety
4- Communication
(a) Develop an activity arrangement diagram based on the REL chart data
(b) Develop a space relationship diagram for the 5 departmental areas.
(c) Fit the 5 departments into a 100m x 150m building and try to maintain 10m aides between the
department
ANSWERS
(a) Activity Arrangement Diagram
This diagram shows the arrangement of all activities but without indicating requirements for space, utilities,
aisles etc.
11
Rating lines are introduced with 4 lines corresponding to A rating, 3 lines to an E rating etc.
12
Figure 12: Layout Plan
13
2.5 Potential Criteria for Evaluation of Layouts
These include:
(1) Ease of future expansion or contraction
(2) Adaptability & versatility
(3) Layout Flexibility
(4) Flow or movement effectiveness
(5) Material handling effectiveness
(6) Storage effectiveness
(7) Space utilization
(8) Safety and housekeeping
(9) Utilization of natural conditions
DLMHD
1. DLMH
DL
Direct labour material handling ratio = Direct labour material handling( dollars)
Direct labour total (people)
2. SSV = OSS
TSS
Storage Space utilization = Storage Space Occupied by materials or occupied storage space
Total storage space
3.
ASP= AS
TS
4.
MO = M
O
5.
ADM = TD
M
A special case of the facility layout - positioning problem involves what is termed simple facility location.
This problem arises where there are existing facilities at known distinct point and a new facility must be
located at some point within the layout. In real situations, there may be only a handful of practical positions
to locate the new facility.
14
The following are EXAMPLES
(i) A new pump in a chemical operation (factory)
(ii) A new warehouse relative to facilities and customer
(iii) A component in an electrical network
(iv) A new appliance in a kitchen
(v) A photocopier in a library
¦ w d ( X
m
f ( x) i i Pi ) .
i 1
Where the wi terms are sometimes referred to as weights.
The one facility location problem is to determine the location of the new facility that minimises f(x),the total
annual transportation cost.
The appropriately determined distance is typically a straight line distance or rectangular distance.
d X , Pi x a y bi
2 2
i
Where the coordinates for the new facility are x and y and for the existing facility i, are ai and bi so that
X= (x, y)
Pi = (ai, bi)
In movement practical location problems, travel only occurs along a aisle arranged in a rectangular pattern
parallel to the walls of the building. This is referred to as the rectilinear or rectangular distance and is given
d X , Pi
by
x a i y bi
In a typical factory situation, transportation cost is assumed to be a simple function of distance. In addition,
there is an associated load/unload cost per trip at each facility.
The total cost is therefore given by summing up the load/unload cost and the transportation cost. If Lk is the
load/unload cost index and Cx is the transportation cost index, the problem is formulated as follows:
f X ¦ L
R
Ck
Ri
d X , Pi
m
k i
i 1
Example
With reference to the table below customers 1 to 6 can be saved from either location A (30,30) or B(80,60).
Given that the load/unload cost per trip Lk = $1.00 and the cost per unit distance Ck = $0.001/m for all
customers 1 to 6 which is the best location.
15
Customer Co-ordinates No of trips/period Measurement type
x y
1 40 60 185 Rectilinear
2 50 20 300 Rectilinear
3 60 40 150 Rectilinear
4 80 40 205 Straight line
5 40 40 200 Straight line
6 60 60 175 Straight line
Solution
$43.005 $1 215
Choose location A
Example
Consider four depts of equal sizes. The material flows between departments are given in Table 2.7.1 and the
existing layout is shown in Figure 2.7.1. a distance matrix can be obtained based on the existing layout as
given in Table 2.7.2.
16
The total cost for the existing layout is computed as follows:
TC1234= 10(1) + 15(2) + 20(3) + 10(1) + 5(2) + 5(1) =125
The pairwise exchange method simply states that for each iteration, all feasible exchanges in the locations of
the dept pairs are evaluated and the pair that results in the largest reduction in total cost is selected. Since all
depts areas are assumed to be equal size, the feasible exchanges are 1-2, 1-3, 1-4, 2-3, 2-4 and 3-4.
(a) Iteration 0 1 2 3 4
(b) Iteration 1 3 2 1 4
(c) Iteration 2 2 3 1 4
The distance matrix is recomputed each time an exchange is performed. The total costs resulting from these
exchanges are:
TC2134(1-2) = 10(1) + 15 (1) + 20(2) + 10(2) + 5(3) + 5(1) =105
TC3214(1-3) = 95
TC4231(1-4) = 120
TC1324(2-3) = 120
TC1432(2-4) = 105
TC4213(3-4) = 105
Thus the pair 1-3 is selected and performs the exchange in the layout as shown in Figure 2.7.1(b)
For the next iteration all feasible exchanges are considered which consists of the same set as in iteration 1.
The resulting total costs are:
TC3124(1-2) = 10(1) + 15 (1) + 20(2) + 10(1) + 5(1) + 5(3) =95
TC1234(1-3) = 125
TC3241(1-4) = 110
TC2314(2-3) = 90
TC3412(2-4) = 105
TC4213(3-4) = 105
The pair 2-3 is selected with a total cost value of 90. Figure 2.7.1 (c) shows the resulting layout after 2
iterations. Continuing on to the third iteration calculations are:
TC3214(1-2) = 10(1) + 15 (2) + 20(1) + 10(1) + 5(1) + 5(2) =95
TC1324(1-3) = 120
TC3421(1-4) = 125
17
TC2134(2-3) = 90
TC3412(2-4) = 105
TC4123(3-4) = 95
Since the lowest total cost for this iteration, 95, which is worse than the cost value of 90 in the second
iteration, then the procedure is terminated. Thus the final layout arrangement is 2-3-1-4 as shown in Figure
2.7.2 (c).
The pairwise exchange procedure described above is not guaranteed to yield the optimal layout solution
because the final outcome is dependent on the initial layout. Thus we can claim local optimality.
Some of the drudgery effort can be avoided by using computer software in the search phase of layout
planning. One program CORELAP (computerized relationship layout planning), uses closeness ratings from
the chart as inputs. It produces a single layout of rectangular shaped departments.
It can be used for either office or factory layouts. A program called CRAFT (computerized relative
allocation of facilities technique) requires an existing layout as input. Its purpose is to improve the layout. It
uses flow data only (from-to) with the objective being to minimize material handling costs.
Tutorial
1. Collolog Coop, is building a new plant. 8 departments are involved. As part of a plant layout
analysis, the activity relationships and the area needs for the departments are shown on the REL Chart
below.
Department 1 2 3 4 5 6 7 8 Area
1. Shipping and A I O E U U O
Receiving 3 3 1,2 600
2. Stores A E O O U O
3 3 3 3 1,2 1500
3. Fabrication E U E O O
3,4 1,3 3 1,2 800
4. Assembly E O O I
3 1,3 3 1,2 700
5. Painting U X U
5 500
6. Tool Room O U
3 300
7. Canteen O
3 600
8. Offices
1200
18
Closeness Ratings Code Reasons
A Absolutely necessary 1 Personal Contact
E Especially important 2 Paperwork Contact
I Important 3 Product/Resource Flow
O Ordinary 4 Use same equipment/tools
U Unimportant 5 Possible Fumes
X Not desirable
(a) Develop an Activity Arrangement diagram based on the REL chart date.
(b) Develop a space relationship diagram for the 8 departments
(c) Fit the 8 departments into a 100m x 80m building in as close to an optimal layout as you can include aisle
between departments in the layout.
Allowing for an aisle of 5m wide.
2. With reference to the table below, customers 1-6 can be served from either location A(x = 20, y=50)
or Location B (x = 80, y = 70) or C(x=40, y=60) given that the load/unload cost, Lk = $0.75 per trip
and the cost per unit distance, Ck = $0,002/m for customers 1,2 and 3 and Lk = $0,50 per trip and Ck
= $0,003/m for customers 4,5 and 6. Which is the best location
Reference/ Bibliography
1. Groover M P (1985), Automation, Production systems, and Computer-Aided manufacturing
2. Askin R G and Standridge C R (1993) Modeling and Analysis of Manufacturing Systems, John Wiley &
Sons,
3. Sule D R, (1994), Manufacturing Facilities: Location, planning and design, PWS Publishing Company
ISBN 0-534-93435-8
4. Tompkins, J A, White, J A, Bozer, Y A, Tanchoo, J M A and Trevino, J, (1996), Facilities Planning,
John Wiley & Sons
19
3.0 FLOW LINE DESIGN AND ANALYSIS
In flowline items are processed as they pass through a series of work stations along a line. Generally, raw
materials, items or components are fed in the beginning of and at certain points along the line, and goods are
delivered from the end of the line.
Assembly lines: flow lines which are engaged essentially, in product assembly.
Transfer lines: Flow lines which use automatic material transfer between the automatic machining stations.
Multi-model : processing of two or more products in separate batches
Mixed -model: processing of two or more products simultaneously on the line.
Table 3.1 summarises the classes and varieties of Flow-line.
Table 3.1: Classes and varieties of flow line
Flowline description Number of Product Flow of items Setting of
products changes equipment and
allocation of work
Class Variety
Single 1 No changes required
model None Regular
Transfer Multi- >1 Batch Regular Changes of equipment
line model changes batches setting and/or work
allocation required on
change of batch
Single >1 none Irregular (a) No change required
model
Assembly Multi- >1 Batch Irregular (a) changes of
Line model changes equipment setting
and/or work
allocation required
or batch change
mixed >1 Continualc Irregular changes of
model equipment setting
and/or work
allocation normally
requiredb
a
Because of variable work station times-characteristic of manual flow lines
b
Alternatively as in group technology; tasks and equipment might be permanently allocated a specific group
of components.
c
At any time the line contains a mixture of product types.
Manual assembly lines are another example of flow lines. They consist of multiple workstations in which
the assembly work is accomplished as the part or sub-assembly is passed from station to station along the
line. At each workstation one or more human workers perform a portion of the total assembly work on the
part. When the part comes off the final station the work has been completed.
Another variation is the automated assembly system, which makes use of automated methods of the
workstations rather than human beings.
20
Symbol Component
Workhead x Workstation
XXXX XXXX:
YYY PROC = Processing Station
ASBY = Assembly Station
INSP = Inspection Station
SORT = Sortation Station
YYY:
AUT = Automated
MAN = Manual
x Work part
Raw Work part
Partially Processed Part
Finished Part
Storage buffer
Automated flow lines are generally the most appropriate means of production in cases of relatively stable
product life; high product demand and therefore high rates of production; and where the alternative method
of manufacture would involve a large labour content. The objective of the use of flow lines automation are:
1. to reduce labour costs
2. to increase production rates
3. to reduce work in process or work in progress
4. to minimise distances between operations or distances moved between operations
5. to achieve specialisation of operations
The 2 general forms that a flow line can take are inline and rotary
AUT
PROC
AUT
PROC
PROC
AUT
AUT
PROC
PROC
AUT
21
A rectangular shape can still qualify as an in-line.
AUT
PROC
PROC
AUT
AU OC
T
Figure 15: Configuration of Automated Flow Rotary Type PR
These 3 categories are distinguished by the type of motion that is imported to the work-part/workpiece by the
transfer mechanism. The most appropriate transport system for a given application depends on features such
as:
I. The type of operation to be performed
II. The number of stations on the line
III. The weight and size of the work-part
IV. The existence of manual stations within the line
V. Production rate requirements
VI. Balancing the various process times on the line
22
3.2.1 Continous Transfer
Here work-parts are moved continuously at a constant speed. This requires the workheads
to move during processing to maintain continuous registration in the work-part i.e.
continuous contact with the work-part. Examples can be formed in beverage bottling
operations and manual assembly operations where the operator can move in a moving flow
line.
Because of breakdowns on the line, the actual average production time Tp will be longer than the ideal cycle
time. When a breakdown occurs at any station we assume that the entire line is shut down. Let Td represent
the average down time to diagnose the problem and make repairs when a breakdown occurs due to a
particular reason j. The frequency with which line stops per cycle occur for reason j is devoted by Fj. The
term FjTdj gives the mean time per cycle that the machine will be down for reason j. If there is only one
reason why the machine may be down, the average production time Tp is given by:
Tp Tc FTd (1)
If there are several reasons why the line is down the average production time becomes
Tp Tc ¦ FjTdj (2)
j
The average production rate Rp is based on the average production time Tp and is given by
1
Rp (3)
Tp
23
Because of the possibility of work-parts being scrapped during processing the theoretical production rate is
rarely achieved in practice and is given by
1
Rc (4)
Tc
The time efficiency E is the proportion of time that a line is up and operating and is given by:
Tc Tc
Tc FTd
E (5)
Tp
FTd FTd
Tc FTd
D (6)
Tp
Another measure of flow time performance is the cost per item produced. If Cm represents the cost of raw
materials per product, CL-the cost per minute to operate the line and Ct-the cost of disposable tooling per
workpiece, then the total cost per workpiece Cpc is given by:
C pc Cm C L Tp Ct (8)
Example 1
Suppose a 10 station transfer machine is being considered for production of a component used in a pump.
The item is currently produced by more conventional means that demand cannot be met. The production
department has estimated that the ideal cycle time Tc is 1 minute. From similar transfer times, it is estimated
that breakdown of all types will occur with a frequency F = 0.10 breakdowns per cycle and that the average
downtime per line stop will be 6 minutes (Td = 6 mins)
The scrap rate for the current processing method is 5% and this is considered a good estimate for the transfer
times. The starting costing for the component costs $1.50 each and it will cost $60 an hour ($1 a minute) to
operate the transfer line. Cutting tools are estimated to cost 15c per work-part.
Find
(a) the production rate
(b) the number of hrs required to meet a demand of 1500 units per week
(c) Line efficiency
(d) cost per unit produced
Solution
(a) average production time Tp = Tc + FTd
Tc = 1 min
Tp = 1+ 0.1(6) = 1.6 minutes
(b) Assuming that we want 1500 good units plus scrap. The Number of hrs required are:
24
hours = 1500 =42.1 hrs
35.625
In the previous example, a breakdown frequency was estimated. In considering the analysis of continuous
and intermittent transfer machines without internal buffer storage capacity we must consider further what
happens when a workstation breaks down.
There are 2 possibilities and their analyses are referred to as the upper bound and lower bound approach.
With the upper bound approach, we assume that the work-part is not removed from the workstation when
breakdown occurs at that station. With the lower approach the work-part is taken out of the station and the
station breaks down.
¦ P
n
F i (9)
i 1
Example
In a 10 station transfer mine the probability that a station breaks down will occur for a given work-part is
0.01. The probability is the same for all workstations. Determine the frequency of line stops per cycle on
this flow-line using the upper bound approach.
Solution
F = nP
= 10 * 0.01
= 0.1
25
The term (1-Pi) is the probability that the part would not join at station 1 and thus be available from
subsequent processing. The quantity P2(1-P1) is the probability that the given part would jam at station 2. In
general the quantity Pi(1-Pi-i)(1-Pi-2) … (1-P2)(1-P1) for i = 1, 2, … , n. Is the probability that the given part
would jam at station. Summing all these probabilities from i= 1 through to n would give the probability of
line stops per cycle.
Alternatively; the frequency may be determined as follows: The probability that a given part will pass
1 P
through all n stations without a line stop is given by:
n
i
i 1
1 1 Pi
n
F (11)
i 1
1 1 P
If the probabilities, Pi that a part would jam at a particular station are equal P1 = P2 = … , Pn = P then
n
F (12)
gives the frequency of time stops per cycle.
With the lower bound approach a number of work-parts coming off the line would be less than the number
starting on the line. Therefore the production rate formula becomes:
1 F
Rp
Tp
Where F represent the frequency of line stops per cycle.
Therefore the term (1-F) represents the yield of the transfer machine. Tp is the average cycle time.
Example
Compute the value of F, using the lower bound approach for the data in the previous example.
F = 1-(1-0.01)10 = 0.0956
Rp = (1-0,0956)/ Tp
The difference between the UBA and the LBA is usually small but grows in high p and n.
Observations
1. Line efficiency decreases substantially as the number of stations increases.
2. The UBA leads to lower efficiency values but higher production rates.
26
To analyze performance, we initially assume an automated flow line without buffer. The ideal cycle time
Tc is determined by the slowest machine which we assume to be a manual station. We also assume that no
breakdown occurs at a manual station. Let P be probability of station breakdown and n be the total number
of workstation, na be number of automated station, no = number of manually operated stations.
na no n
Tp Tc na PTd (14)
Example
A proposal has been made to replace one of the current manual stations with an automatic workhead on a 10
station transfer line. The current system has 6 automatic workheads and 4 manual stations. The proposed
automatic station would allow the cycle time to be reduced to 24s. The new station is cost at $0.25/min.
Other cost data for the existing line are: Co = $0.15/min
Cas = $0.10/min
Cat = $0.10/min
Breakdowns occur at each of the 6 automatic workstations to a probability p= 0.01. The average down time
per breakdown is 3 mins. It is estimated that the value of P for the new automatic station is P = 0.02. The
average down time for the line will be unaffected. Material for the cost 50c per unit (Cm = $0.50/Unit).
Tooling costs can be neglected (Ct=0). It is desired to compare the new automated station with the current
manual station on the basis of cost per unit.
Solution
The current line
27
Cpc = Cm + CLTp + Ct
= 0.5 + 1.40*0.64 + 0
= $1.396/unit
The line balancing problem is to arrange the individual processing and assembling tasks at the work stations
so that the total time required at each station is approximately the same. If the work elements can be grouped
so that all the station times are exactly equal, there is perfect balance on the line. In practice perfect balance
is unachievable and the slowest station determines the production rate of the line.
3.7.1 Terminology
In order to spread the job done on a line among its station, the job must be divided into its component tasks.
The minimum rational work elements are the smallest practical indivisible tasks into which the job can be
divided.
Let Tj be the minimum rational work element, where j is used to identify the element out of the elements that
make up the total work or job. Then the total work content, Twc, is given by
¦ T
n
Twc j (1)
j 1
Workstation Process Time: A workstation is a location along the flow line where work is performed either
manually or by some automatic device. The work performed at the station consists of one or more of the
individual work elements and the time required is the sum of the times of the work elements done at the
station.
¦ Tsi ¦ T
n n
(2)
i 1 j 1
j
28
The cycle time Tc must meet the following condition
Tc d
E
(3)
Rp
The balance delay is a measure of the line efficiency, which is a result of idle time due to imperfect
allocation of work among stations. It is given by
nTc Twc
d
nTc
Example
Considering the work elements shown in the table below.
Work elements
¦ T
n
Twc j = 4.0 min
j 1
E.g. 1 2 3 4 5
n=5 0.6 1 0.5 1 0.9
29
3.7.2.1 Largest candidate rule method
This is the easiest method. The work elements are selected for assignment to stations simply on the basis of
the size of their Tej values. The steps used in solving the line balancing problem are:
(a) List all elements in descending order of Tej value, in the largest Tej at the top of the list.
(b) To assign elements to the 1st workstation, start at the top of the list and work down, selecting the 1st
feasible element is one that satisfies the precedence arrangements and does not cause the sum of the
Tej values at the station to exceed the cycle time Tc.
(c) Continue the process of assigning work elements to the station as in step (b) until no further elements
can be added wont exceeding Tc.
(d) Repeat steps (b) + (c) for the other stations on the line until all the elements have been assigned.
Example continued
Precedence diagram
0.11
6
0.7 0.27
3 7 9
0.2 0.5 0.12
0.32 4
1 11 12
0.1 0.6
4 8
0.4 0.3
2 5 10
0.38
(b) Tc = 1 min
30
Station Elements Tej(min) ¦Tej at Station
1 2 0.4 0.4
5 0.3 0.7
1 0.2 0.9
4 0.1 1.0
2 3 0.7 0.7
6 0.11 0.81
3 8 0.6 0.6
10 0.38 0.98
4 7 0.32 0.32
9 0.27 0.59
5 11 0.5 0.5
12 0.12 0.62
0.11
6
0.7 0.27
3 7 9
0.2 0.32 0.5 0.12
1 11 12
0.1 0.6
4 8
0.4
0.3
2 5 10
0.38
I II III IV V VI
31
Step 2.
Tc = 1
32
Work Element RPW Tej (min) Immediate Predecessor
1 3.3
2 2.67
3 3
4 1.97
5 1.3
6 1.0
7 1.21
8 1.87
9 0.89
10 1.0
11 0.62
12 0.2
Actual Solution
3.7.3.1 Comsoal
It involves selecting a seed work element from a predefined list and then iterating through a sequence of
attendance solutions and then choosing the best one.
33
To minimise total delay time ** with four workstations
Step 1 Construct list A with work elements in one column and the total number of elements that immediately
precede each element in a adjacent column.
Step 2 Construct list B showing all elements from list A that have no immediate predecessors
Step 3 Select at random one of the elements from list B The only constraint is that the element selected must
not cause cycle time Tc, to be exceeded
Step 4 Eliminate the element selected in step 3 from list A and B and update both lists
Step 5 Again select one of the elements from list B which is feasible for cycle time
Step 6 Repeat steps 4 and 5 until all elements have been allocated to stations within the cycle time
constraints
Step 7 Retain the current solution and repeat steps 1 to 6 in an attempt to determine an improved solution. If
an improved solution is found it should be retained
3.7.3.2 Bryton
There are 2 types of line balancing scenarios:
x Fixed production Rate to optimise number of stations
x FIXED work stations to minimise cycle time
The Bryton procedure will find a local optimum, given a set number of workstations. The procedure
minimises overall idle time whilst also improving the production rate
Solution Procedure
The procedure here is a convergence procedure. It gets closer and closer to the solution in each step The
steps are:
1) Establish required data (element times, precedence requirements and the production volume
required for a given time interval)
2) Make preliminary calculations of cycle time Tc the minimum number of stations, nmin and the
cycle time associated with the minimum number of stations Tcmin
3) Devise a feasible arrangement
4) Select maximum and minimum Tsi
5) Interchange the elements
6) Re-examine all Tsi values after interchange
7) Repeat interchanging procedure
8) Repeat steps 6 and 7 until total delay appears constant
Example
Element times
Element Tej/ minutes per piece Precedence
Requirements
1 1.0
2 0.6 1
3 2.7 2
4 1.2 2
5 3.4 4
6 0.9 3
7 1.6
8 1.1 5, 6, 7
Total 12.5
The assembly line operates 2 shifts a day ( Assume shift is 8 hrs and a week is 5 days) Management would
like 1300 units per week. Our task is to find the optimum assembly line balance
Solution
1. Establish all the data required
2. Tc=8*2*5*60/1300=3.7 min/cycle
nmin=12.5/3.7=3.4 therefore we work with 4 stations
Tcmin=12.5/4=3.125
34
Deriving a precedence matrix from a precedence graph
||P|| =Pij where I represents row position and j column position
Pij =1 if i precedes j
Pij =0 if I and j are unordered
Pij =2 if I follows j
Elements j
1 2 3 4 5 6 7 8
1 0 1 1 1 1 1 0 1
2 2 0 1 1 1 1 0 1
3 2 2 0 0 0 1 0 1
4 2 2 0 0 1 0 0 1
Element i 5 2 2 0 2 0 0 0 1
6 2 2 2 0 0 0 0 1
7 0 0 0 0 0 0 0 1
8 2 2 2 2 2 2 2 0
3 You can use any method e.g. LCR (largest candidate rule)
(b) Repeat step 5 (a) until all stations have been examined with respect to maximum Tsi. If no interchange
has occurred it is now a local optimum. If the local optimum seems to be the best solution to the problem,
select the next rated maximum and compare it with the minimum Tsi etc. (as above). But if this local
optimum is just a satisfactory solution go to step 5 (d)
(d) If the local optimum is not satisfactory, a large element may be shifted out of the maximum Tsi or the
largest element in the whole group may be moved. Let this element be assigned permanently to the new
station and start the procedure again with step 4
n maxTsi ¦Tsi
Stations
¦ d
1 2 3 4 Max ds n n
i 1
s
i 1
etc.
35
To check precedence restrictions, the computer adds the row of the interchanged element from the proposed
solution matrix ||S||. If a 3 appears in the sum then the precedence restrictions have been violated.
1
1,2,3,4,8 3 4
2 5,6,7,9 10,11
1,2,3,4,8
There is no formalized procedure for developing a solution that utilizes 11 stations. The use of 11 stations is
easier to implement on manual lines because of the inherent flexibility of the human operator.
36
Base part Completed assembly
As by As by As by
Aut Aut Aut
At any station i, there are 3 possible events that might occur when the feed mechanism attempts to feed the
component and the assembly device attempts to join it to the existing assembly.
Pi mi qi ........................................................................................................................... (1)
The 2nd possible event, when the component is defective but does not cause a station jam, has a probability
given by (1 mi ) qi .
The 3rd possibility, that the component is not defective, is given by (1-qi)
mi q i 1 mi q i 1 qi 1 ........................................................................................ (2)
mq 1 mi q 1 q
For the special case where qi = q + mi = m for all i, then
1 ............................................................................................. (3)
To determine the complete distribution, of possible outcomes that can occur on an n-station assembly line,
> m q 1 m q 1 q @
the terms in equation 2 are multiplied together for all n stations to give:
n
i i i i i 1 ............................................................................ (4)
i 1
>mq 1 mq 1 q @
n
1 ......................................................................................... (5)
Expansion of equations 4 and 5 will reveal the probabilities for all possible sequences of events which can
take place on the assembly line.
37
3.8.2 Measures of Performance
We are not required to calculate every term to make use of the concept of assembly machine operation. Get
1 q mi qi .................................................................................................. (6)
the proportion of acceptable product coming if the line, Pap, we use.
n
Pap i
i 1
The above is the proportion of assemblies with no defective components, the proportion of assemblies that
contain least one defect is given by
1 1 qi mi qi ............................................................................................. (7)
n
Pqp
i 1
1 q mq n .......................................................................................................... (8)
The case where mi = qi the above 2 equations become
1 1 q mq .................................................................................................... (9)
Pap
n
Pqp
The proportions given by equations 6 & 8 give the yield of assembly machine.
Calculate production rate. We must first determine the frequecy of down time occurrences per cycle, F,
which given by:
¦ P ¦ m q
n n
F i i i ........................................................................................................ (10)
i 1 i 1
Tc ¦ mi qi Td ......................................................................................................... (12)
n
Tp
i 1
(From Tp =Tc + FTd)
1 q mi qi
Therefore the rate of production of acceptable product, Rap is given by
n
i 1
i Pap
Rap ...................................................................................... (14)
Tp Tp
Where the production rate has been corrected to give the rate of output of assemblies that contain no defects.
When all mi and q i are equal the equation then becomes
1 q mq n
Rap ......................................................................................................... (15)
Tp
38
The line efficiency is given by
Tc Tc
Tc nmqTd
E ..................................................................................................... (16)
Tp
nmqTd nmqTd
Tc nqmTd
D ............................................................................................. (17)
Tp
The cost per assembly produced, which is corrected for yield is given by
Cm C L T p Ct Cm C L Tp Ct
1 q mq
C pc n ..................................................................... (18)
Pap
Example
A 10 section in-line assembly line/machine has a 6s ideal cycle time Tc = 6s. The base part is automatically
headed prior to the 1st station, and components are added at each of the stations. The fraction defect rate at
each of the 10 stations is q = 0.01 and the probability that a defect will jam is m = 0.5.
When a jam occurs the average downtime, is 2 mins. Determine the average production rate, the yield of
good assemblies and the up time efficiency of the assembly machine.
The optimum sequence for the batches of different models is influenced by the cost of setting up the line.
The total cost of setting up the line comprises the cost of tool and machine changeover, tool and machine
resetting, machine and labour idle time etc., and is clearly influenced by the nature of the preceding and
succeeding models. The problem therefore is to determine the sequence order of the model batches to
minimize the total setting-up cost over a given period of time.
Example
Applying Hungarian method in allocation considering the costs.
Cost Succeeding Model
A B C D A B C D
A 0 100 150 80 A 1000 100 150 80
B 50 0 100 75 B 50 1000 100 75
C 80 40 0 110 C 80 40 1000 110
D 115 100 60 0 D 115 100 60 1000
39
A B C D ?Sequence = {Do C o B o A o D}
A 920 20 70 0 (80) Ao D
B 0 950 50 25 (50) BoA
C 40 0 960 70 (40) CoB
D 55 40 0 940 (60) Do C
{A o D o C o B o A o D o C}
This has the advantage that a steady flow is produced in order to meet demand requirements, theoretically
without the need of large stocks of finished goods. The major disadvantage arise from the differing work
contents of the models, resulting in the uneven flow of work and consequent station idle time and/or
congestion of semi-finished products.
In a case of dissimilar models independent balancing will result in dissimilar work elements being allocated
to each station. Thus balancing should be undertaken in a way to ensure the similar work elements are
allocated to the same work stations or groups of stations irrespective of which model is being processed.
This can be achieved by assigning elements to stations on a total time rather than a cycle time basis.
Consider two dissimilar models A and B for which the precedence relationship of the elements are shown
below.
11 12 13 7
0 2 5 6 8 9 10
17
1 3 4
14 15 16 18
Model A (200/week) {0,1,2,3,4,5,6,7,8,9,10}
Model B (100/week) {1,3,4,7,8,9,11,12,13,14,15,16,17,18}
40
Table : Data for two model line balancing
Element Element Total time/wk Positional weight
No Duration (h) A B Total/wk (hr) (using total times)
0 0.32 200 0 200 64 411
1 0.1 200 100 300 30 463
2 0.2 200 0 200 40 347
3 0.05 200 100 300 15 292
4 0.1 200 100 300 30 277
5 0.23 200 0 200 46 307
6 0.2 200 0 200 40 247
7 0.05 200 100 300 15 125
8 0.32 200 100 300 96 206
9 0.1 200 100 300 30 110
10 0.3 200 0 200 60 60
11 0.1 0 100 100 10 167
12 0.15 0 100 100 15 157
13 0.17 0 100 100 17 142
14 0.08 0 100 100 8 61
15 0.07 0 100 100 7 53
16 0.13 0 100 100 13 46
17 0.2 0 100 100 20 20
18 0.13 0 100 100 13 13
It has been necessary to combine several work stations because the total time for elements (0,5,8 and 10) is
greater than the available 40 hours.
Balancing loss = 5.1% which is a respectable line balance for the week’ s production. However this method
of line balancing is justified only when production is truly mixed-model. If there is a tendency to send
models through the line in batches rather than individually a quite unsatisfactory situation would result.
When model-utilised and incur a great deal of balancing loss and while the batch of model B is being
processed stations 2,3,4,5,6,7,13 and 14 will be under-utilised.
41
Thus this method of ‘combined’ line balancing for a shift’ s or week’ s production of all models is beneficial
where:
a) models are to be processed concurrently on the line and not in batches
b) dissimilar work elements are involved and it is desirable to ensure that work of a similar nature is
allocated to separate stations or groups of stations
Example
Three models A, B&C of a particular product are assembled concurrently on an assembly line.
The quantities required over a given period and the model cycle times are as follows:
Calculate the fixed interval at which nuts must be launched onto the line, and show how the sequence of
models might be determined in order to avoid station idle time:
¦N C 30 66 44
¦N
D
60 110 55
j j
0.62
Units must be launched onto the line in such a way that multiples of the launching interval are less than, but
¦
as nearly equal as possible to, the sum of the model cycle time, j C
h
h 1
Assuming that the desired product mix is known. Let qj be the proportion of product type j, j=1, ---, P to be
produced. First step is to develop an assembly line balance for the weighted average product. Let tij be the
time to perform task i on product type j and Sk the set of tasks assigned to workstation k.
42
Average feasibility condition can be stated as:
¦
¦
q j t ij d C
p
k=1,- - -,K
i Sk j 1
This condition states that averaged across all items produced in the long term, no workstation is overloaded.
¦
The feasibility condition indicates that there is need only solve one single product assembly-line balancing
p
problem. In solving this problem task times of t i j 1
q j t ij are used.
Sequencing products on the line now becomes the issue. For each item j we must produce Qj items this
period (shift). Let r be the greatest common denominator of all Qj. There is need to construct a repeating
¦
cycle comprised of Nj = Qj/r units of product type j, j=1, ----, P. The cycle will be repeated r times to satisfy
p
period demand. N j 1
N j items are produced each cycle. A cycle that both smoothes the production
rate of each item and prevent excessive idle (delay) time at workstations is the aim because of mix-induced
starving of workstations. A workstation is starved if on completion of all its tasks there is no item available
for it to work on because the next item has not yet been completed at the prior station. Maintaining a
¦
constant flow is most important at the bottleneck station. Define the relative work load for station k as
Ck t . The bottle neck station kb is the station with maximum total work (or equivalent average
i S i
arg max k Ck
To determine the dispatch sequence, Let Xjn be 1 if item type j is placed in the nth position and 0 otherwise.
Likewise j(n) will denote the type of item placed nth. The approach becomes selecting the nth item to be
entered to the line to optimise the following problem.
¦" ¦
! t , j (n) nC
n
Minimize max
1 n N
i kb
j 1 i Skb
¦# X
N
subject to jn Nj j = 1,-------P (1)
n 1
S1 d ¦ X jh d S1
nN j n nN j
n = 1, ---- N, j = 1, ----- P (2)
N $
h 1 N
¦& ¦& ¦ X jh d n s2 Ck
n P
t n=1, ----N; k=1, ---,K; Xjn = 0 or 1 (3)
%
h 1 j 1 i Sk
ij
The objective function minimizes the maximum deviation from assigning average work load to the
bottleneck station at any point during the period. Constraints (1) insure that all items are produced during the
cycle. Constraints (2) restrict the production rate of each product to be within Si of its average rate at all
times. Constraints (3) limit maximum over-utilization at all times. These constraints attempt to restrict
unplanned station idle time due to starving.
Sequencing Heuristic
Step 0. Initialization. Create a list of all products to be assigned during the cycle. Call this list A.
Step 1: Assign a product for n=1,---, N from list A, create a list B of all product types that could be assigned
without violating any constraint. From list B select the product type (j*) that minimizes;
max ¦
# ¦i
t , j (n) nCkb
n
1 n N
j 1 i Skb
Add product type j* to the nth position. Remove a product type j* from A and if nN goto 1
43
Example
It would be foolish to market just one toy car. Every child wants to “ collect the whole set.” Suppose the
times used to balance the line are actually averages over all the models in this product line. The estimate
sales by model are:
Table: Estimated weekly sales by model type.
Model Sales Percentage Station 2 Time
Red Z 250 16.7 1/6 72
Blue Q 250 16.7 1/6 68
Black R 500 33.3 2/6 68
RWB American 500 33.3 2/6 66
Solution
Required production of each model in a cycle is 1 Red, 1 Blue, 2 Black, and 2 RWB per cycle (NZ=1, NQ=
1, NR = 2, NRWB = 2). Thus N=6.
3.10.1 Introduction
Assembly lines previously discussed assume 100% reliability (workstation never break down) and
processing times are deterministic. In this case flow-line systems are subject to breakdown and processing
time variability. A breakdown can be cause by fractured tool or jamming of the transport mechanism in a
transfer line. Or it may be due to temporary unavailability of worker on an assembly line or blockage on
upstream station.
Transfer line may be defined as a set of serial, automatic machine and or inspection stations linked by a
common material transfer and control system.
Transfer lines and automated flexible flow lines are capital intensive and must be kept running to be
justifiable. Thus the objective is to determine the effectiveness of a line given both buffer capacities and
failure and repair rates for each workstation. Effectiveness is measured by the net production rate.
1 1 2 2 3 3 4
# workstation # # Buffer #
44
ii) Total line failure - exists in all stations are in operative- power outrage or error in central line controller
iii) Station blocked - when if on completion of a cycle it is unable to pass the part to station it 1. This may
be due to a failure in handling system, failure of a down stream station prior to the next buffer or failure
of a down stream station with the intermediate buffer between these stations currently being full.
iv) Station starved - if an upstream failure has halted the flow of parts into station I - Thus station will be
idle.
E (uptime)
E (uptime downtime)
E
E(.) -refers to the expected value, uptime - interval during which production is occurring and downtime -
period during which finished product is not leaving the line
Let Qr be the event that all m stations survived r cycles. The probability that the line first fails at the end of
the tth cycle ( t good products are produced but the tth cannot be passed on) is given by
¯ i' 1 ¿ ¼
1
i' 1
*
P(T=t)= «1 3(1 D i )»®1 >1 @ 3(1 D i )]¾
ª M º ½
M t 1
¬ i1 ¼¯ ¿
(3.1)
) )
i 1
45
E = ª1 3+ (1 D
? º
« )»
M
(3.2)
¬ ¼
i
i 1
P(7 t) E (1 E ) t , 1
This is a geometric distribution with E as parameter. Thus M station line behaves like a single station but
with failure parameter E replacing Di
Expanding terms in E
§ ·
E = 1 - ¨1
©
¦ D ¦- D D
i
i
i j
i j .......
-.¦
-/- D
i j ... m
j D j D m
¹̧
Since Di is small, higher order terms approach zero
E| ¦0 D
m
i (3.3)
i 1
Line effectiveness can now be calculated by the ratio of expected productive cycles between failures
(uptime) divided by expected total cycles between failures (uptime and downtime). Using equation 3.3 and
repair the distribution assumptions.
E 1
1 1
E 1 b 1 Eb
E= 1 1 1 1 1
(3.4)
Example
Consider a two-station line where the first station fails on the average every 10 cycles and the second station
averages a failure every 15 cycles. Average repair time is two cycles. Find line availability.
Solution:
1 1 1
Di D2 b
10 15 2
1 1
1 Eb 1 ( 115)2
E= 2 1 1
0.75
10
E (uptime) t 1
t of E (uptime) E (downtime)
Ei = lim lim
D t D
t i 1 i
bi bi
In cycle-dependent failures, time was suspended when any station failed. Thus is not the case with time-
dependent failures. As stations are independent;
46
41
¦3
ª Di º
«1 »
M
¬ bi ¼
E= 3.5
i o
Example
Consider a two-station line where the first station fails on the average every 10 cycles and the second station
averages a failure every 15 cycles. Average repair time is two cycles. Assuming that the line is subjected to
time-dependent failures. How is the effectiveness affected?
Solution
1 1 1
Di D2 and b
10 15 2
51 61
§ 2· § 2·
E = ¨1 ¨1
© 10 ¹̧ © 15¹̧
= 0.735
Effectiveness has reduced from 0.75 to 0.735 since station 1 and 2 can now continue the ageing process
while idle as a result of a failure at the other station.
1-b1
RR0 RW1
RW0 WW1
WW0 WR1
WR0 RR1
47
Table: Transitions for Two-Stage line with Buffer
Initial State Station 1 Station 2 Probability Resultant State
Up Up (1-D1)(1-D2 ) | 1-D1-D2 WWx
WWx,0xZ Up Fail (1-D1)D2 | D2 WRx
fail Up D1(1-D2) | D1 RWx
RW0 Repaired Idle b1 WW0
Down Idle 1-b1 RW0
Fixed Up b1 (1-D2) | b1 WWx-1
RWx,0<xZ Down Up (1- b1)(1-D2) | 1- b1-D2 RW x-1
Down Fail (1-b1) D2 | D2 RR x-1
Up Down (1-D1)(1- b2) | 1-D1 -b2 WR x+1
WRx, 0x<Z Up Repaired (1-D1)b2 | b2 WW x+1
Fail Down D1(1- b2) | D1 RRx+1
WRZ Idle Down 1- b2 WRZ
Idle Repaired b2 WWZ
Down Down (1- b1)(1-b2) | 1-b1 -b2 RRx
RRx, 0xZ Down Fixed (1- b1) b2 | b2 RWx
Fixed Down b1(1-b2) | b1 WRx
if S is the set of states of the system the stead-state balance equations can be defined by applying the
Chapman-Kolomogorov result as
where P(s) is the probability of being in state S and p(u,v) is the transition probability for ending in state v
given that we began the cycle in state u.
¦ P(WWx ) ¦7 P( RWx )
z z
Ez (3.8)
8
x o x 1
Expression (3.8) could be used regardless of whether the low-probability exerts such as two station failures
on the same cycle are excluded from the Markov chain model. However for the case of their exclusion.
Buzacott presents a closed-form expression for the effectiveness of this model
48
Di
Let xi be the ratio of average repair time to uptime.
bi
x2 D2 (D1 D 2 )(b1 b2 ) D 1b2 (D1 D 2 b1 b2 )
(D1 D 2 )(b1 b2 ) D 2b1 (D1 D 2 b1 b2 )
Then s r and C =
x1 D1
1 sC z
1 x1 (1 x2 ) sC z
Ez = when Sz1
1 r b2 (1 x) Zb2 (1 x)
(1 2 x)[1 r b2 (1 x)] Zb2 (1 x) 2
or when S= 1 (3.9)
Meaning as the buffer capacity is increased asymptotic effectiveness approaches the capacity of the least
effective station.
Example
1 1 1
Given D 1 D2 b
10 15 2
Find the availability of the line if a buffer of four spaces is placed between the work stations. Also, find the
availability if unlimited buffer space is available between the workstations.
Solution
First compute the model parameters
D1
1
.
01 15
x1 = 0.2 x2 0133
.
b1 0.5 0.5
since S z 1
x2 2
S=
x1 3
1 SC 4
1 x1 (1 x 2 ) SC 4
E4 0.81
Thus the addition of buffer space for four units has increased availability from 0.75 to 0.81. In every 100
cycles an average of six additional good nuts are produced maximum possible production rate is:
1 1
E9
1 max(0.2,01333
0.833
. ) 12
.
49
3.10.3.2 Deterministic Failures and Repairs
Assuming identical stations thus failures will alternate between stations, when station 1 fails, station 2 will
continue to operate from buffer until 1 is repaired or buffer empties. If Z t b-1, the cycles to repair then
station 1 worked through station 2’ s previous repair time at least enough to ensure buffer of b-1 parts.
for Z t b-1
1
1 x
Thus E Z
5
4
7LPH
1 2 2 1 1 2 2 1 1
UHSDLUHGIDLOVUHSDLUHGIDLOVUHSDLUHGIDLOVUHSDLUHGIDLOVUHSDLUHG
From this example a general rule that buffers should normally be large enough to accommodate at least
average repair time production.
D cj ¦: D
m
i and bj=b provided that all stations must stop if any individual station fails
i 1
Di D2 D3 D4 D5
D1 + D2 = D 2+ D4 + D5
a) Single line
50
D6
D1 D2 D3 D4 D5
Di + D 2 + D3+ D6 D4+ D5
D1
D3 D4 = D1
D2
D2 + D3 + D4
c) Feeder line (buffered)
Figure: Equivalent transfer lines for analysis
Example
An engineer is to decide where to place a buffer in a four-stage production process. Each stage has the same
fixed cycle time. Uptimes are unpredictable but the mean cycle time between failures is 250 for each station.
Repair time averages 10 cycles. The buffer will have a station. Repair time averages 10 cycles. The buffer
will have a capacity of 20 units since most repairs can be completed in 20 cycles
Solution
There are three possible location - Repair time parameter b=0.1 while the individual workstations have Di =
0.004.
Table: Possible Buffer location
Buffer after WS D‘1 D0 E20 E;
1 0.004 0.012 0.885 0.893
2 0.008 0.008 0.895 0.926
3 0.012 0.004 0.885 0.893
Therefore the best location to place buffer is between station 2 and 3.
Rule 2: Medium Buffer location if only one buffer is to be inserted, it should be placed in the middle of the
line.
Reference/ Bibliography
1) Groover M P (1985), Automation, Production systems, and Computer-Aided manufacturing
2) Askin R G and Standridge C R (1993) Modeling and Analysis of Manufacturing Systems, John Wiley &
Sons,
3) Sule D R, (1994), Manufacturing Facilities: Location, planning and design, PWS Publishing Company
ISBN 0-534-93435-8
4) Tompkins, J A, White, J A, Bozer, Y A, Tanchoo, J M A and Trevino, J, (1996), Facilities Planning,
John Wiley & Sons
5) McMahon C and Browne J, (1993), CADCAM: form principle to practice, Addison-Wesley
51
APPENDIX A: FACILITY PLANNING
FACILITY PLANNING
Facility planning determines how an activity’ s tangible fixed assets best support achieving the activity’ s
objective.
In manufacturing, facility planning involves the determination of how the manufacturing facility best supports
production.
Facility Location - placement and orientation with respect to customers, suppliers, and other facilities with which it
interfaces.
Facility design components- the facility systems, the layout, & the handling system.
9 Manufacturing facility systems – the structure and envelope systems, power, light, air conditioning, water,
sewage
9 Facility Layout - the production areas, production-support areas, personnel areas within the building
9 Handling system – the materials, personnel, information equipment handling systems for supporting
production
Facilities location-the determination of how the location of the facility should support the facility’ s objective. It
addresses macro issues.
Facilities design - determination of how the design components should support achieving the facility’ s objective. It
addresses micro issues.
Plant
location
Manufacturing
facilities Facility
planning system
Materials
handling
Discuss….
So, which comes first, the material handling system or the facility layout ?
Appropriate answer is, "Both!"
The layout and the handling system should be designed simultaneously.
The complexity of the design problem generally requires that a sequential process be used. For this
reason, it is recommended that a number of alternative handling systems be developed and the
appropriate layout be designed for each.
52
The impact of facilities planning on employee moral, and the impact of morale on operating costs
How convertible are the lots of capital investments in facilities
The impact of facilities planning on the management of the facility
The impact of facilities planning on a facility’ s capability to adapt to change and satisfy future requirements
Yes
Develop alternative plans
and evaluate
Implement plan
53
Redefine the objective of the facility :-As in Step 1, identify products (services) to be produced (provided)
specific quantifiable terms. Any potential modifications/expansion?
Model of Success
x presents a clear direction of where a business is headed
x -model used to best achieve the set objectives of p
The vision:-a description of where you are headed
The mission:-how to accomplish the vision
The requirements of success
The guiding principles
The evidence of success
Physical aspects
Control
Time
54
Product design and development decisions affect processing and materials requirements-affect layout
and material handling
Manufacturing decisions will have an impact on both facilities location and facilities design, e.g.,
decisions concerning the degree of vertical integration, types and levels of automation
An electronics manufacturer was faced with rapid growth. Management received proposals that required
approximately equivalent funding for large warehouses at two sites having essentially the same storage and
throughput requirements. Management questioned the rationale for one "solution" being a high-rise AS/RS and
the other being a low-rise warehouse with computer-controlled industrial trucks.
55
Flow-Line Layout
Mill Drill
• Lack of flexibility in timing: the product can not flow through the line faster than the slowest task can
be accomplished unless that task is performed at several stations.
• Large investments: special-purpose equipment and duplication is required to offset lack of flexibility
in timing.
• Dependence of the whole on each part: a breakdown of one machine or absence of enough operators
to staff all work stations may stop the entire line.
• Worker fatigue: workers may become bored by the endless repetition of simple tasks.
56
Process Layout
Lathe Lathe Drill Weld Weld
Process Layout
Grouping together of machines and/or workers doing similar tasks.
Applicable to both manufacturing and non manufacturing operations.
Advantages
– Flexibility: equipment and personnel can be used where they are needed.
– Smaller investment in equipment: duplication is not necessary unless volume is large.
– Expertise: supervisors for each department become highly. knowledgeable about their functions
– Diversity of tasks: changing work assignments make work more satisfying for people who prefer
variety.
Disadvantages
– Lack of process efficiency: backtracking and long movements may occur in the handling of materials.
– Lack of efficiency in timing: workers must wait between tasks.
– Complication of production planning and control.
– Cost: workers must have broad skills and must be paid higher wages than assembly line workers.
– Lowered productivity: because each job is different it requires different setups and operator training.
• Move machines and/or workers to the site; products normally remains in one location for its entire
manufacturing period.
57
Group Technology Layout-GT
¾ Definition of Group Technology
“ Group technology is the technique of identifying and bringing together related or similar parts in a production
process in order to utilize the inherent economy of flow production methods.”
Concept-GT
¾ Many problems are similar, by grouping similar problems, a single solution can be found to a set of problems,
thus saving time and effort.
¾ A manufacturing philosophy in which similar parts are identified and grouped together to take advantage of
their similarities in design and manufacturing.
¾ A technique for identifying and bringing together related or similar components in order to take advantage of
their similarities in the production process.
Concept-GT
Concept D esign Manufacturing
Many problems are Similar Shapes Sim ilar
similar Manufacturing
Processes
G roup Similar D esign Families Production Family
Problems
Single Solution of O ne standard design O ne standard
Problems plus m inor process plan to a
m odification fam ily and
m odification and
extension
58
• The 5% direct working time includes 30% actual processing and 70% for positioning,
chucking, gauging, etc.
• Hence, only 1.5% is accounted for actual machining.
z Cellular manufacturing directs its effort towards the remaining 98.5% by organizing the plant
layout according to work cell, rather than functions. A work cell is a unit that includes all of the
machines required to produce a family of parts.
¾ Advantages
z Reduced material handling; reduced interdepartmental roundabout movements
z Reduced set-up time, production time
z Reduced tooling, pallets, jigs & fixtures
z Reduced in-process inventory
z Easy identification of bottlenecks
z Increase operator expertise
z Improved human relations, team-work spirit, & morale.
z Implied reduction of necessary control
z Better output quality, reduced scrap, increased accountability of operators and supervisors
¾ Disadvantages
z Reduced shop flexibility (compare with job shop)
z Possible reduced machine utilization
z Possible extended job flow times
z Possible increased job tardiness.
¾ Implementation Issues
z Reorganization - machine layout need reorganization every so often.
z Work cell supervision - supervisors must be expert in several field (e.g., milling, turning, grinding,
etc.) represented in the cell.
z Shop floor control / production planning - cell concept might lead to unbalanced workload on
machines.
Discussion-current layout
¾ Discuss basic layout types in your company
59