MCL2601-Assignment 2
MCL2601-Assignment 2
Question 1
Your company was awarded a culvert contract. The contract manager has appointed you to manage
the project and has requested you to provide a schedule for the client. The contract manager
handed you the table below, showing a breakdown of activities involved, together with their
duration. The Start date is the 01/02/2021 (1st February 2021). Working week of 5 days, 40 hours
must be use.
Group: Concrete
Concrete Foreman Work R200.00/hr
Group: General Labour
General Labour Work R48.00/hr
Group: Material
Concrete Material R1 600.00/m³
Reinforcement Material R13 000.00/t
Group: Overhead
Surveyor Work R200.00/hr
General Forman Work R250.00/hr
Group: Plant
Excavator Work R750.00/hr
Compactor Work R62.00/hr
Poker Unit Work R62.00/hr
Group: Shuttering
Carpenters Work R65.00/hr
Group: Steel
Steel Fixer Work R65.00/hr
1. Draw up a Network diagram and Gantt chart and indicate the critical path.
a. Network Diagram (Arrow chart) (20)
b. Critical Path (10)
c. Start Slag (flout) (10)
d. Resource loaded Gantt Chart (Bar chart) (20)
e. Total Resource cost (20)
[80 marks]
Question 2
[20 marks]