Spiral Cellars Technical Manual Nov 17
Spiral Cellars Technical Manual Nov 17
INTRODUCTION
second to none.
”
It covers all key aspects of the cellar installation and
the main cellar components, with detailed drawings
and specifications.
Email: [email protected]
Technical Manual November 2017. Check with customer advisers for latest version.
INTRODUCTION.......................................................................................2
WHY CUSTOMERS WANT A SPIRAL CELLAR IN THEIR HOME........4
PRODUCT OVERVIEW.............................................................................5
HOW THE CELLAR WORKS...................................................................6
A DESIGN GUIDANCE FOR ARCHITECTS...............................................7
1 Components............................................................................................................................................. 8
i. Water proof liner details.............................................................................................................. 10
ii. Water proof Butyl liner product specifications...............................................................11
2 Dimensions............................................................................................................................................. 12
i. White Spiral Cellar.......................................................................................................................... 12
ii. Original Spiral Cellar.................................................................................................................... 13
3 Building regulations, planning permission & listed buildings......................................... 14
4 Party wall agreements ..................................................................................................................... 16
5 Heating pipes & under-floor heating......................................................................................... 18
6 Structural impact of the spiral cellar.......................................................................................... 19
7 Our structural engineer’s methodology................................................................................... 20
8 Installation options............................................................................................................................. 21
9 What a contractor will be required to do................................................................................ 24
10 Our method statement: how we fit a Spiral Cellar.............................................................. 25
11 Ordering and installation timeline.............................................................................................. 26
12 Warranty................................................................................................................................................. 27
C DOOR DETAILS.......................................................................................47
1 Standard.................................................................................................................................................. 50
2 Reinforced for garages..................................................................................................................... 54
3 Concealed (timber)............................................................................................................................. 58
4 Concealed (standard tiles).............................................................................................................. 62
5 Concealed (heavy tiles).................................................................................................................... 66
6 Rectangular glass................................................................................................................................ 70
7 Half round glass................................................................................................................................... 74
8 Round glass............................................................................................................................................ 78
9 Retractable round glass................................................................................................................... 82
Sales of fine wine are increasing year on year By going underground, space is created rather than
in the UK and wine has always played a part in absorbing a room or space that could have other uses.
signifying status and a cultured lifestyle, and this
Concrete as a material has its advantages; it is very efficient
continues. Entertaining family and friends at home at retaining temperature — which compliments the slow
is all part of the modern lifestyle and people want change of ground temperature from summer to winter,
their wine collection close at hand for easy access. and further reduces any temperature spikes. It’s structural
integrity — it is capable of taking the weight of the wine and
The modern home is often required to reflect the owner’s style, stacked modules.
personality and position in life so functional additions that also
double up as design features are an obvious choice — a home Wine is a living product
wine cellar is a wow factor, a great party piece that also stores
wine in the ideal conditions. At the same time homeowners are Its ability to change with time is what makes it so interesting,
interested in value–added features for their home. but it also means that if it’s kept in the wrong conditions its
quality can quickly be affected.
Another incentive to store wine — it is a less volatile
investment area than other traditional avenues such as Temperature is the most critical aspect
property. It is also free of Capital Gains Tax.
in storing wine
Owners of an underground wine cellar Store wine somewhere too hot and it ages quickly, rapidly losing
its vibrancy and becoming tired and stale. The ideal temperature
• Go on holiday to wine regions and have the option of for wine is about 13°C but 5°C or so either side of this is
shipping home several cases to store in their cellar. acceptable. The key is that there are no sudden fluctuations —
wine likes things to change slowly — so while a gradual warming
• Save on external warehousing and delivery costs, and find and cooling between winter and summer is not a problem.
it much more convenient to have a full range at home and Insulated by the ground, an underground wine cellar keeps wine
have more to spend on wine! at a steady temperature, allowing it to age gracefully.
Technical Manual November 2017. Check with customer advisers for latest version.
PRODUCT
OVERVIEW
KEY FACTS:
WWW.SPIRALCELLARS.COM 5
HOW THE
CELLAR WORKS
A reinforced concrete
ring and base keep The concrete modules
everything in position and steps interlock.
and ensure your
existing foundations
won’t be affected.
Technical Manual November 2017. Check with customer advisers for latest version.
A
DESIGN
GUIDANCE FOR
ARCHITECTS
1 Components............................................................................................................................................. 8
i. Water proof liner details.............................................................................................................. 10
ii. Water proof Butyl liner product specifications...............................................................11
2 Dimensions............................................................................................................................................. 12
i. White Spiral Cellar.......................................................................................................................... 12
ii. Original Spiral Cellar.................................................................................................................... 13
3 Building regulations, planning permission & listed buildings......................................... 14
4 Party wall agreements ..................................................................................................................... 16
5 Heating pipes & under-floor heating......................................................................................... 18
6 Structural impact of the spiral cellar.......................................................................................... 19
7 Our structural engineer’s methodology................................................................................... 20
8 Installation options............................................................................................................................. 21
9 What a contractor will be required to do................................................................................ 24
10 Our method statement: how we fit a Spiral Cellar.............................................................. 25
11 Ordering and installation timeline.............................................................................................. 26
12 Warranty................................................................................................................................................. 27
WWW.SPIRALCELLARS.COM 7
A1 COMPONENTS
Technical Manual November 2017. Check with customer advisers for latest version.
WWW.SPIRALCELLARS.COM 9
A1i WATER PROOF
LINER DETAIL
Outer PVC liner Back filled area
• Butyl liner
Butyl liner
Concrete base
Geo-textile disc
Operating Temperature
BS903 -40 °C to + 130 °C
Range
The information herein is based upon data obtained by the manufacturer and is considered accurate. However, no
warranty is expressed or implied regarding the accuracy of this data. This information is furnished upon the condition
that the person receiving it shall evaluate its suitability for the specific application.
PROTECTIVE LINER
BP landflex PVC 610B/PVC 610G 610g/m² Reinforced PVC
Typical Properties Test Method Specification (Typical Values)
Width/Finish 150 / 205cm / Sateen
Colours available Blue / Green
Base fabric High tenacity polyester
Coating Flexible plasticised PVC - both sides
Total weight BS3424/5A 610g/m² +/- 25g/m²
Tensile Strength
BS3424/6B Warp 2400 / Weft 2100
N/50mm (ave.)
Tear Strength N (ave.) BS3424/7B Warp 500 / Weft 325
Coating adhesion N/50mm (ave.) BS3424/9B 100
The information herein is based upon data obtained by the manufacturer and is considered accurate. However, no
warranty is expressed or implied regarding the accuracy of this data. This information is furnished upon the condition
that the person receiving it shall evaluate its suitability for the specific application.
WWW.SPIRALCELLARS.COM 11
A2i WHITE SPIRAL
CELLAR DIMENSIONS
255
667
Elevation of White Cellar Module
Front Elevation
935
319
667
Plan Layout of White Cellar Module
Unit viewed from above.
White Cellar Cellar depth is measured from the FFL to top of cellar base slab
Number of bins 42 54 66
Excavation depth The excavation depth is determined by our structural calculations and confirmed by the Project Manager
Technical Manual November 2017. Check with customer advisers for latest version.
A2ii ORIGINAL SPIRAL
CELLAR DIMENSIONS
250 25
597 667
Elevation of Original Cellar Module Elevation of White Cellar Module
Front Elevation Front Elevation
848 935
300 319
597 667
Plan Layout of Original Cellar Module Plan Layout of White Cellar Module
Unit viewed from above. Unit viewed from above.
Each module has a solid back and an open side front. Each module has a solid back and an open side front.
Number of bins 42 54 66
Excavation depth The excavation depth is determined by our structural calculations and confirmed by the Project Manager
WWW.SPIRALCELLARS.COM 13
A3 BUILDING REGULATIONS,
PLANNING PERMISSION
& LISTED BUILDINGS
Building regulations
Building Regulations Approval is required when installing into
a habitable space such as in the home or an attached garage.
It is not required if the cellar is to be installed in most single
detached garages or outbuildings.
Planning permission
Planning permission is not normally required.
Listed buildings
For listed properties a Listed Buildings Application will need to be
made to the Local Authority for approval. It can take 8–10 weeks
from the application being accepted until approval is received.
Spiral Cellars can manage this application if required.
Technical Manual November 2017. Check with customer advisers for latest version.
WWW.SPIRALCELLARS.COM 15
A4 PARTY WALL AGREEMENTS
Party wall awards are applicable to a Spiral Cellar Tenant 1 year Free holder +
installation if the excavation is planned to be within tenancy 20 year lease
3000mm of a neighbouring owner’s building or
structure. This is a very straight forward process, and is
not comparable to obtaining planning permission. Leaseholder Free holder +
21 years 20 year lease
Boundary Line
Boundary Line
Freeholder +
leaseholder
90 years
Excavation below Excavation below
level of foundations level of foundations
within within
3m 3m
within 3000mm
NOTE
the under floor heating must be no less than No other services such as hot water pipes to run
300mm from the outside edge of the Spiral across cellar area or vent pipe run.
Cellar excavation.
Ventilation pipes should be run under the floor
construction. Where this is not possible, the under floor
heating must be kept 300mm from the ventilation pipes.
Technical Manual November 2017. Check with customer advisers for latest version.
A6 STRUCTURAL IMPACT OF
THE SPIRAL CELLAR
WWW.SPIRALCELLARS.COM 19
A7 OUR STRUCTURAL
ENGINEER’S
METHODOLOGY
These notes outline a design method used by our Surcharge live loads (vehicles etc.)
consultant structural engineers to cover various
Depending on the location, the cellar can be subject to
scenarios, which can occur while installing a Spiral additional surcharge live loads applied to the ground bearing
Cellar within close proximity to an existing structure. slab within the area where the cellar is located. The estimation
of the vehicle load is transferred on to the cellar structure can
Type of loadings be easily done by 45° load spread assumption.
The Spiral Cellar, located below soil surface and in close distance
to buildings, is subject to different types of surcharge loadings, Ground water pressure
which have to be resisted by the proposed concrete structure. In the scenario of a high water table in the specific location, the
The surcharge loads can be caused by: cellar structure can be subject to hydrostatic water pressure
acting on the cellar walls and base. The main concern is the
Adjacent foundations of existing or pressure acting on the base of the cellar, which can cause uplift
proposed buildings of the structure; therefore the flotation check is essential and
advised in every case.
Spiral Cellars are usually placed in residential buildings where
the footprint of the foundations is relatively small in relation Heave or shrinkage of cohesive soils
to the cellar diameter. This means that in most cases there is
going to be certain pressure from the foundations on the new If the cellar is placed in the cohesive soil there could be potential
underground structure. risk of movement caused by heave or shrinkage occurring
around the cellar structure. In cohesive soils the cellar should be
The quick check if the cellar is subject to the foundation loads kept independent from the floor structure e.g clay.
can be estimated from 45° load spread under the footing. In
reality the resultant pressure from applied force to the surface Design approach
of soil varies within depth and distance from applied force, and
can be illustrated by Soil Pressure Bulbs. The design approach has been modified in recent years from
a traditional reinforced concrete structure to the structure
Surcharge loads from soil reinforced with polymer fibres, without traditional steel bars.
The aim of the design is to save time and cost during the
The purpose of structurally analysing of the Spiral Cellar ring construction process.
is to calculate the highest bending moment under present
surcharge loadings. The analysis shows that the bending
moment can increase when uniform loadings (soil and water)
are reduced and mainly foundation surcharge pressure is taken
into account. In the calculations we have used active pressure
coefficient Ka instead of passive pressure coefficient Ko to
evaluate higher bending moment.
Technical Manual November 2017. Check with customer advisers for latest version.
A7 OUR STRUCTURAL
ENGINEER’S
METHODOLOGY
The structure has been analysed as a circular model instead of which can be caused by variable surcharge loading from the
a simplified retaining wall; this approach allowed for analysis adjacent foundations.
of a structure very closely behaving as a real model. For this
purpose finite element analysis software was used, where a On top of the structural analysis the minimum sizing has to
three dimensional model was created. The following parameters provide adequate dead weight against uplift forces which can
were considered: occur. The dead weight of the cellar consists of the ring (150mm
thick), the base slab (minimum 200mm thick) and internal
Structure concrete blocks used as wine storage shelves.
A Spiral Cellar is a retaining structure resisting surcharge loadings For the worst case design purpose the following assumptions
from the foundations, soil, and surface live loads. The circular were introduced:
shape of the structure with, more than 2000mm in diameter,
gives huge stiffness and moment of inertia. The structure is cast • Pressure under foundation 150kN/m2
from normal concrete reinforced with polymer fibres.
• Minimum distance from the edge of the foundation to the face
of the ring — 100mm
Material
• Width of the foundation 600mm
Given the analysis results in various loading scenarios it
• Distance from the wall to the centre of the cellar — 1400mm
was concluded that the required moment of resistance
can be achieved with fibre reinforcement additive to the • Foundation outstand — Bc = 0.1500mm
normal concrete. The new approach had been introduced • Cellar depth 3000mm
purely because of the time and cost, which could be saved
on standard installation of steel bars in circular structures. • The one quarter of ring has been considered to calculate the
The fibre reinforcement has been available on the European loading on the ring surface
market for a few years and has been widely used mostly in
the design of ground bearing slabs, but the product has been Analysis and results
tested for structural applications such as short beams or slabs.
Finite element analysis was used to calculate the resulting
For the design of the concrete structure the polymer fibres stresses in the structure under the varying load pattern.
STRUX 90/40 have been used. For the structure, C30 A 3D model of the circular structure has been created in
normal concrete is used with mix design recommended by a FEA software where appropriate parameters for geometry,
manufacturer. In the case of contaminated soil the suggestion is to materials, supports and loadings have been assigned.
use 70% GGBS (Ground–granulated blast–furnace slag) instead
and 30% Portland cement in the concrete mix. General results have been created for the different load case
scenarios, from the analysis it was concluded that the worst
Loadings situation occurs when there are two parallel walls situated on
opposite sides of the cellar squeezing the ring.
The shape of the structure means that the cellar under uniform
load from soil, water or surface live loads becomes a compressive In the situation of three or four walls around the cellar
ring with uniform membrane stresses at certain depths of the located at similar distances from the centre, the bending
ring. The ring, being made of concrete, can easily resist the moment in the ring is reduced by the fact that the
compression occurring from the given forces. The design limits surrounding forces are at approximately similar magnitude,
are given by bending moments along the perimeter of the cellar, which brings the structure into compression.
WWW.SPIRALCELLARS.COM 21
The two following cases can be taken as an illustration for worst SAND AND GRAVEL (LOW RISK INVOLVED)
case scenarios in most of the situations:
Standard construction as per the Spiral Cellars Ltd method
Two parallel walls (2800mm apart) statement and the suggested excavation procedure is
illustrated on page 18.
a. 150kN/m2 — assumed foundation pressure
b. 1400mm — distance to the centre SAND AND GRAVEL — HIGH WATER TABLE
c. Analysis for all types of cellars (MEDIUM RISK INVOLVED)
A high water table can cause certain difficulties during excavation
Two parallel walls (2800mm apart) + vehicles and casting of the concrete structure. It is recommended to use
an experienced contractor who is confident and can provide
a. 150kN/m2 — assumed foundation pressure adequate equipment for such conditions.
b. 1400mm — distance to the centre
c. Analysis for all types of cellars It is suggested to use lower water content in the concrete
mix and use a concrete plasticiser for better workability.
The following loading was included: It is recommended to contact a local concrete supplier for
product specification.
• Vertical stress from the foundation
SAND AND GRAVEL/BASEMENTS/HIGH
• Soil surcharge loads
WATER TABLE (HIGHER RISK INVOLVED)
• Hydrostatic water pressure
• Vehicles surcharge loads For installations in basements a national guidance should be
used to justify the water uplift in the calculations. British
Standards require an assumption of 0.75 depth of the
Design conclusions
basement for the water table.
• Due to the geometrical properties of the structure the
surcharge forces acting on the cellar will cause mainly The weight of the cellar in these conditions is generally not
compression in the ring. The bending moment, which may satisfactory and the basement slab has to be used to provide
occur along the perimeter, is minor in magnitude and any adequate dead weight. The basement slab should be cast on top
tensile stresses in the section can be resisted by polymer fibre of the cellar ring. The proposed or existing basement slab should
reinforcement Strux 90/40. be justified by a Structural Engineer. Also, see notes in point 2.
Technical Manual November 2017. Check with customer advisers for latest version.
A8 INSTALLATION
OPTIONS
We offer two options, ‘full’ where we complete Excavation takes on average 3 days by hand or ¾ day
NOTE
the excavation and installation or ‘fit’ where with mechanical excavator.
the contractor completes the excavation and we
3–5 days for the Spiral Cellars team to fit the cellar.
install the cellar.
6 weeks later After Sales Visit and the cellar is ready to use.
EXCAVATION AND INSTALLATION (FULL)
The hole should be shuttered with our hole protection rings
We are able to undertake the full installation into existing and the rest of the build programme can continue. The slab
buildings, even when the property is fully occupied. We should be poured to the outside of the shuttering and the
can also carry out a full installation on refurbishment and contractor will be required to provide an electric supply to
new build projects if the contractor prefers not to do the the cellar and to fit two ventilation pipes (50mm UPVC pipes)
excavation. We dig and remove the spoils by hand, and as within the floor construction to the nearest external wall.
such we are able to install in most ground floor rooms or This will be agreed in advance by Spiral Cellars and guidance
basements regardless of construction build up. notes will be provided.
The Original Spiral Cellar, takes between 5 and 6 working The Spiral Cellars team then supply, deliver and install the
days. The White Spiral Cellar is more likely to take 8 working cellar. The construction method for the cellar involves:
days. Access for materials and skip positions is considered installing the Butyl liner, PVC bag and sleeve and casting the
carefully by Spiral Cellars at site survey stage. base, constructing the cellar modules, casting a reinforced
concrete ring in–situ, if required.
The Spiral Cellars team will also organise skips for removal of
waste, gain the necessary permits from your local authority, The door and ventilation pipes are connected and the
and supply all building materials, waterproof liner, Spiral installation is complete. On a well prepared site, this process
Cellar modules, door and lighting. will take 3–5 days. The final electrical connection should be
completed by the contractors’ certified electrician, or Spiral
INSTALLATION INTO A PREPARED EXCAVATION (FIT) Cellars’ own electrician.
WWW.SPIRALCELLARS.COM 23
A9 WHAT A CONTRACTOR WILL
BE REQUIRED TO DO
The Fit Installation of a Spiral Cellar has a 4. Electrical Supply: The cellar requires a power supply
number of critical elements that must be executed for lighting and for the motorised door (if applicable).
Electrical feeds to the cellar will need to be installed
as per our specification. These elements will be
within the floor construction in conduit, with no
checked ahead of our attendance. Any variances junctions. Leave approximately 3500mm of cable
will become chargeable. within the cellar. Tape ends. Provide a 5Amp fused
spur for cellar supply and to make final connections
1. The contractor should excavate a hole as per the outside the cellar. See page 37.
structural calculations package, on average 2300–
2500mm diameter and up to 3600mm deep (depending 5. Finished Floor Level Datum: A datum level mark on a wall
upon cellar size selected — the exact dimensions would (or similar) indicating Finished Floor Level (FFL) is to be
be confirmed by Spiral Cellars once the engineering provided within 3000mm of the cellar location on Day 1
calculations have been prepared, which are project of our installation — this cannot be changed thereafter.
specific). Any larger excavation will result in additional
backfill and incur additional costs to the client or 6. The Project Manager will be in touch in the run up to
contractor. the installation to agree a suitable start date for the
installation and answer any queries that may arise. A
2. The hole should be protected with our steel shuttering pre–installation visit may be conducted to confirm the
rings. These will be delivered to site at one week’s site and excavation are ready for our team’s arrival. We
notice, prior to the excavation date. All fixings are will expect to be able to arrive at the site on the agreed
supplied. See page 28. date, remove the protection and fit the cellar, pour
reinforced concrete ring, make final connections to the
3. Ventilation Pipes: Once the excavation is complete and ventilation pipes and then finally fit the door. Any delays/
made safe, it is critical that the preparation for the vent incomplete works which cause the project to run beyond
pipes is given consideration. 2 x 50mm internal diameter the scheduled programme will be charged in accordance
UPVC pipe with solvent welds must be installed in line with our terms and conditions.
with Spiral Cellars’ designs. Where possible 90° bends
must be minimised. At the external end the 50mm pipes If there are any doubts concerning the installation
can be terminated 100mm beyond the brickwork if they procedure and requirements the contractor should contact
are contained within the cavity. the main office for direct referral to our Project Manager
for technical guidance, or to arrange a site meeting.
If the vents are to be outside the external wall, the
2 x 50mm pipes can be terminated side by side and 7. We will expect good, clear, safe site access and an area
protected. The low level ‘cold — in’ pipe will be 525mm for materials in line with the discussions and agreements
above hard landscape, the high level ‘warm — out’ pipe at site survey stage.
will be at 2025mm height, unless agreed differently at
survey stage. All pipe ends to be taped up. Vents to be The Health and Safety Executive does not consider
marked ‘upper’ & ‘lower’. See page 35. other teams working overhead or obstructing scaffold
to be a safe working environment.
Please note, the vent pipes must not have hot water
pipes for radiators or under floor heating set over. The
vent pipe run must be executed as per our specification.
Services must be kept 300mm away from vent pipes.
Technical Manual November 2017. Check with customer advisers for latest version.
A10 OUR METHOD The door must be left open for a minimum of two
STATEMENT:
weeks to allow the cellar to dry out.
NOTE
Do not allow rubbish and site debris to fall into the cellar
HOW WE FIT A
— this increases the risk of the cellar being damaged.
The door should remain protected until the After
SPIRAL CELLAR
Sales Visit is complete.
1. The team will check site datum, in particular the finished This is then sealed and made weather tight. One pipe
floor level and that the hole is at the right depth and will be raised to 525mm height and the other pipe will
shape. be raised to a minimum height of 2025mm. The pipes
will be clipped to the wall and the open pipes will have
2. Upon completion of the excavation a heavy duty PVC rodent guard covers fitted.
liner and Butyl tanking liner will be fitted inside the
shuttering. Both will be clamped/supported at the top 7. Electric bulk head lights or LEDs will be fitted in the
of the hole, using scaffolding planks as a safe working cellar. They will be linked and a switch fitted at the head
platform, to keep the bags taut. of the cellar. A feed for connection to an existing ring
main will be linked from a socket to the cellar light switch
A geotextile base disk will be laid in the base of the liner, and all cabling will be routed in conduit underground. A
and a further reinforced PVC sleeve will be installed into fused spur may be fitted where applicable.
the liner.
8. The door is fitted onto the open half side of the cellar. It
3. A base slab of concrete, specified by the engineer, will be is set on a 25mm bed of mortar and the finished detail
poured into the bags and left to set. inside is haunched to leave a smooth finish.
4. The modules are lowered into the bag via supports and one 9. The door is tested for opening and closure.
man will be at the bottom setting out/fitting the modules
and step modules. The top ring is fitted just below finished 10. Thereafter the floor area around the cellar is
floor level and one half of the ring is covered by soffit reconstructed as directed and in accordance with the
boards, unless a round glass door is specified. order specification.
5. The ring/void outside the bag is then back filled with wet 11. The site is then cleared of waste and cleaned/washed
concrete and Strux fibre reinforcement (refer to Strux down as required.
engineering bulletin for Strux technical specification).
12. All protective coverings are removed and disposed of. The
6. The plastic ventilation pipes are fitted. One length of pipe sequence for point 5, 8, 9 differs for a round glass door.
is fitted down the centre column and one pipe is fitted
through a pre cast hole in the flat soffit board. Both pipes The Spiral Cellars team leader will fill in a job completion
are then directed to the nominated outside wall (In a fit form illustrating any differences to the pre order
only project, the pipes are already channelled beneath requirements, risk assessment variations, incidents/
floor level to this wall by the contractor). accidents, snags required, difficulties, incomplete items
or other. At stages through the construction process the
The pipes will rise up either on the inside or outside of the Project Manager will have visited the site. We will have also
wall with any joints being solvent welded. The pipe will requested that the Local Authority Building Inspector visits
exit the wall via a hole prepared with a 55mm core drill. the site to ensure approval of the construction method.
WWW.SPIRALCELLARS.COM 25
A11 ORDERING &
INSTALLATION
TIMELINE
If required Site Surveyor visits the property Site Surveyor visits the property to confirm the
to confirm the Spiral Cellar location access, Spiral Cellar location access, logistics and price.
logistics and price.
10% deposit is paid to place the order and secure an 10% deposit is paid to place the order and secure an
installation date. Lead times can be up to 8 weeks. installation date. Lead times can be up to 8 weeks.
Spiral Cellars instruct their engineers, structural Spiral Cellars instruct their engineers, structural
calculations are prepared and the building calculations are prepared and the building
regulations application is drafted. regulations application is drafted.
80% payment due 14 days before installation date. 80% payment due 14 days before installation date.
The Spiral Cellar Installation takes place in The Spiral Cellar Installation takes place
1 or 2 phases (dependant on site conditions in 1 or 2 phases (dependant on site conditions
and programme). and programme).
The After Sales Visit (scheduled for 6-8 weeks The After Sales Visit (scheduled for 6-8 weeks
post installation) takes place; additional extras post installation) takes place; additional extras
such as treads are fitted at this point. The final such as treads are fitted at this point. The final
10% payment is due. 10% payment is due.
5-year warranty is issued, which is effective from 5-year warranty is issued, which is effective
the date of practical completion. from the date of practical completion.
Technical Manual November 2017. Check with customer advisers for latest version.
A12 WARRANTY
WWW.SPIRALCELLARS.COM 27
Technical Manual November 2017. Check with customer advisers for latest version.
B
CONSTRUCTION
GUIDANCE FOR
CONTRACTORS
1 How to excavate the hole and install the steel shuttering rings................................... 30
2 How to install temporary propping............................................................................................ 32
3 How to prepare the hole with block & beam construction............................................. 33
4 How to install the ventilation pipes ........................................................................................... 36
5 Details of electrical supply required. ...................................................................................... 39
6 How the waterproof liner can be integrated with tanking systems........................... 40
7 How to reconstruct the concrete slab around the cellar................................................. 41
8 How to reconstruct the concrete slab around the cellar in a basement.................. 42
9 How to reconstruct the existing block and beam floor around the cellar................ 43
10 How to reconstruct a raft floor around the cellar............................................................... 44
11 How to reconstruct a timber suspended floor around the cellar................................ 45
WWW.SPIRALCELLARS.COM 29
B1 HOW TO EXCAVATE THE HOLE
AND INSTALL THE STEEL
SHUTTERING RINGS
Where the ‘Fit only’ option for the installation of The Finished Floor Level (FFL) and Datum Grid
the Spiral Cellar has been selected, the contractor line must be provided within 3000mm of the
is required to prepare several elements on site cellar. This FFL must be established before the
prior to the installation of the cellar: hole for the cellar is dug.
1. Excavation of the hole for the Spiral Cellar and insertion 5. E
stablish the proposed cellar location in accordance with
of steel shuttering rings. the site location plan. The levels must be taken from the
Finished Floor Level. Refer to our engineering calculations
2. Installation of temporary propping. Spiral Cellars will not supplied for the exact depth of excavation.
fit a cellar into an unsupported excavation.
6. M
ark out excavation with chalk/spray paint to
3. Installation of ventilation pipes. required diameter.
8. F
ive pre–drilled steel panels bolt together to form a
complete ring of effective height of 750mm.
9. F
ix together one complete shuttering ring using fixings
supplied in ALL of the holes in the shuttering. All bolts to
be installed with the heads facing INSIDE the shuttering,
and the nuts on the OUTSIDE against the earth.
10. L
ower the shuttering into the excavation and prop under
the shuttering so that the top row of fixing holes are still
above. See below ground level.
Second row of corrugated
steel sheets bolted together as
per manufacturer specification
Technical Manual November 2017. Check with customer advisers for latest version.
Do not install a concrete base into the excavated hole.
NOTE
Spiral Cellars will do this as part of our installation.
Do not excavate the hole until calculations have
been supplied.
11. Dig another 700mm, leaving some of the soil under the 19. B
ackfill to the external side of the shuttering when
shuttering to support. complete, using a slurry mix.
12. Fix another complete ring and offer it to the top of the 20. I f there is groundwater
first ring, overlapping, and bolt together. present in the excavation,
it will be necessary for a
13. Lower down to the bottom of the excavation. 300mm diameter pipe to
See diagram below. be installed vertically down
the outside of the rings
Third row of corrugated steel
sheets bolted together as per
to 300mm below the full
manufacturer specification depth. This is to give width
access for a submersible
pump to remove water from
the excavation during the
construction.
21. T
he top of shuttering should be set to the top of base
slab/block and beam level, or advised by Spiral Cellars. If
the excavation is through a timber suspended floor, then
the top of the steel shuttering is to be set at just under
the timber floor structure itself.
14. Fix another ring together.
22. D
o not install a concrete base into the excavated hole.
15. Attach straps or ropes to the top of the shuttering Spiral Cellars will do this as part of our installation.
through the fixing holes.
An additional charge will be made if further excavation to the
16. Dig out the soil holding the shuttering in place. correct depth is required. This charge will be made without
prior notification to the client, as per our terms and conditions.
17. Lower the shuttering ensuring that it is
perpendicular (plumb). Milton Rings
An alternative to the steel shuttering panel earth support
18. Repeat steps 5–9, digging 700mm at a time until required system supplied by Spiral Cellars is to install precast concrete
depth is achieved. See diagram below. ‘Milton’ Rings (or similar supplier). The Milton Rings are not
supplied or installed by Spiral Cellars. The rings usually sit on
Forth row of corrugated steel
a concrete slab. Note that a 2400mm diameter ring x 500mm
sheets bolted together as per
manufacturer specification deep weighs approx 1.05 tonne.
WWW.SPIRALCELLARS.COM 31
B2 HOW TO INSTALL
TEMPORARY PROPPING
DIAGRAM 1 DIAGRAM 2
4 2
If an excavation is to be left for more than 7 days before the cellar Details of components 10/3” Corrugated steel sheets 0.9mm
is installed, it is necessary to prop the hole securely. 5 x 0.7500mm x 1300mm panels, numbered
1–5
The steel shuttering should be propped with 3 x 50011 Type
Props as per Diagram 2. Moment of resistance 0.64kNm
Technical Manual November 2017. Check with customer advisers for latest version.
B3 HOW TO PREPARE THE
HOLE WITH BLOCK &
BEAM CONSTRUCTION
WWW.SPIRALCELLARS.COM 33
OPTION 1. DWARF WALL
4. Back fill between the steel rings and the inside of the
block work to the top of the block and beam floor. Vent
pipes will also need to be placed in this area, diagram 1.
5. Sit the new block and beam floor on the block work
around the cellar.
Steel Shuttering rings
6. Lay the normal required damp proof membrane and
215mm blockwork or
insulation and then concrete to the top of the block and
100mm layed flat up to the
beam floor between the steel rings and the inside of the
underside of the B&B floor
block work.
Concrete backfill
Contractor to construct a footing around the cellar diameter
area (depth is subject to engineer’s calculations).
Technical Manual November 2017. Check with customer advisers for latest version.
OPTION 2
4. Back fill between the steel rings and the inside of the
block work to the top of the block and beam floor. Vent
pipes will also need to be placed in this area.
See diagram above.
5. Sit the new block and beam floor on the block work
around the cellar.
Concrete backfill
WWW.SPIRALCELLARS.COM 35
B4 HOW TO INSTALL THE
VENTILATION PIPES
The pipes can be fed through the cavity in a new build • To enable the slab to be poured prior to the cellar
construction and exit the wall with rodent grill. Where they installation a soft box, 400mm x 400mm plywood, should
cannot be fed through the cavity, pipes will be directed to the be fitted to the edge of the shuttering.
outside wall, and both feed up outside the wall. The differential
height of the vent pipes causes warm air to be sucked out • The ventilation pipes should temporarily terminate within
through the top pipe and hence cold air flows in through the the soft box, allowing the slab to be poured up to the
bottom pipe displacing the warm air. The positioning of the shuttering and soft box. Once the cellar is installed the
vent pipes is crucial to ensure an efficient cellar. ventilation pipes will be run from the soft box into the
cellar by the Spiral Cellars’ Installation team.
There are two ventilation pipes required to
enter the cellar, which will run within the floor • The run of pipes should be no more than 5000mm
if possible, with minimal bends to ensure the cellar
construction or below a block & beam floor. performs efficiently.
• The size of the UPVC plastic vent pipes required are 50mm
ID (56mm OD) fitted with long radius bends to •B
oth pipes to be run parallel,
gain a greater flow of air to and from the in tandem with a 50mm gap
cellar. All joints to be solvent welded between the two pipes.
using Osma solvent weld. The fewer the
number of bends, the better the flow •O
ne pipe is nominated as the
of air. Avoid 90º bends. warm pipe, the other as the
cold pipe — as shown in the
diagram opposite.
•B
oth pipes will be set in a channel
cut out of the floor in a solid base
or below the block & beam floor.
Refer to the Under Floor Heating
details on page 16.
Technical Manual November 2017. Check with customer advisers for latest version.
CONCRETE SLAB
WWW.SPIRALCELLARS.COM 37
B4 HOW TO INSTALL THE
VENTILATION PIPES
Before the cellar is installed, access should
NOTE
be created to allow the ventilation pipes
to be fed through the shuttering (using a
core drill piece suitable for cutting steel) to
create two openings for each pipe.
EXTERNAL
• The cold air vent pipe will then bend up the outside wall
to a height of 525mm from ground level to be fixed to the
wall with pipe brackets.
• The top of the pipe will require a 90° bend with a rodent
grill fitted.
• The warm air vent pipe will then bend up the outside wall
to a height of 2025mm from ground level to be fixed to
the wall with pipe brackets.
• The top of the pipe will require a 90° bend with a rodent
grill fitted.
Technical Manual November 2017. Check with customer advisers for latest version.
B5 DETAILS OF ELECTRICAL
SUPPLY REQUIRED
On ring main-
FCU with 5 amp fuse
Power cable to
run in 50mm
conduit from
FCU to Cellar
WWW.SPIRALCELLARS.COM 39
B6 HOW THE WATERPROOF
LINER CAN BE INTEGRATED
WITH TANKING SYSTEMS
Technical Manual November 2017. Check with customer advisers for latest version.
B7 HOW TO RECONSTRUCT
THE CONCRETE SLAB
AROUND THE CELLAR
DPM (damp-proof
membrane)
The steel shuttering installed by the contractor will need to Once the cellar has been installed, Spiral Cellars will pour a
be trimmed to either the top of the proposed concrete slab concrete slab or screed over the top of the cellar to meet the
or screed, depending on your schedule of works and at what edge of the concrete slab or screed layed by the contractor. If
stage the cellar is due to be installed. the contractor has not completed either the slab or screed at
the time of install, then the contractor can pour their screed all
the way up to the edge of the door concrete haunching box.
WWW.SPIRALCELLARS.COM 41
B8 HOW TO RECONSTRUCT THE
CONCRETE SLAB AROUND
THE CELLAR IN A BASEMENT
NOTE
before the screed is completed around the
The steel shuttering installed by the contractor door, allowing the butyl liner collar to be
will need to be trimmed to the top of the proposed connected to the tanking system by the
concrete slab. contractor or specialist installer.
Technical Manual November 2017. Check with customer advisers for latest version.
B9 HOW TO RECONSTRUCT THE
EXISTING BLOCK AND BEAM
FLOOR AROUND THE CELLAR
FFL FFL
Screed PVC Sleeve
Insulation Butyl Liner with collar
Block&Beam floor PVC liner
Concrete Blockwork
Footing Spiral Cellar precast
Reinforced top rings
Concrete Ring Spiral Cellar door
Soil
Spiral Cellar
precast Modules
Shuttering
WWW.SPIRALCELLARS.COM 43
B10 HOW TO RECONSTRUCT
A RAFT FLOOR AROUND
THE CELLAR
Screed
Raft
DPM (damp-proof
membrane)
Technical Manual November 2017. Check with customer advisers for latest version.
B11 HOW TO RECONSTRUCT A
TIMBER SUSPENDED FLOOR
AROUND THE CELLAR
Once the joists have been installed and fixed correctly, the
timber floor planks can be laid.
Soil / Concrete
Spiral Cellar
precast Modules
Shuttering
PVC Sleeve
Butyl Liner with collar
PVC liner
WWW.SPIRALCELLARS.COM 45
Technical Manual November 2017. Check with customer advisers for latest version.
C
DOOR DETAILS
1 Standard.................................................................................................................................................. 50
2 Reinforced for garages..................................................................................................................... 54
3 Concealed (timber)............................................................................................................................. 58
4 Concealed (standard tiles).............................................................................................................. 62
5 Concealed (heavy tiles).................................................................................................................... 66
6 Rectangular glass................................................................................................................................ 70
7 Half round glass................................................................................................................................... 74
8 Round glass............................................................................................................................................ 78
9 Retractable round glass................................................................................................................... 82
WWW.SPIRALCELLARS.COM 47
C CELLAR DOOR DETAILS
Technical Manual November 2017. Check with customer advisers for latest version.
C CELLAR DOOR DETAILS
White:
L: 1584mm
W: 892mm
White:
L: 1584mm
W: 892mm
WWW.SPIRALCELLARS.COM 49
C1 STANDARD DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
Laying flooring around a Standard Door
1. The flooring is to be set parallel to the door.
WWW.SPIRALCELLARS.COM 51
C1 STANDARD DOOR
FRAME
DOOR
Materials of door and Pine timber door with four 18mm plywood panels, finished with two layers of 30%
pan polyurethane lacquer
Lifting mechanism A manual gas strut arm (820N) is fixed from the stainless steel back plate to the
centre steel trim of the door
Handle 75mm x 75mm Squash court handle finished in brushed stainless steel
Technical Manual November 2017. Check with customer advisers for latest version.
C1 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the
cellar area or vent pipe run.
WWW.SPIRALCELLARS.COM 53
C2 REINFORCED DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
DOOR
Reinforcement 3 x steel reinforcement bars fitted to the underside of the door. Designed to take the
load of a vehicle
Materials of door/ Door Pine timber doors with four 18mm plywood panels, finished with two layers of 30%
pan polyurethane lacquer
Lifting mechanism A manual gas strut arm (1200N) is fixed from the stainless steel back plate to the
centre steel trim of the door
Handle 75mm x 75mm Squash court handles finished in brushed stainless steel
WWW.SPIRALCELLARS.COM 55
C2 POST-INSTALLATION:
REINFORCED
DOOR (GARAGE)
Concrete / Screed
Adjustable Back Plate
50mm x 50mm S/S Frame
Spacer Plate
Hinge Tie bar for Fixing Frame
Trapdoor S/S Frame
900mm
1. Ensure the concrete/screed is finished level with top of 5. Contractors must not store any materials, substances or
the stainless steel frame. tools on top of the protection box.
2. Protect the timber door and frame before concreting/ 6. Do not stand or sit on the protection box.
screeding around the door.
7. To prevent damage, due care and attention to the area
3. The door protection sheet must not be removed at any time. around the door must be given.
4. The timber protection box over the door may only be 8. Failure to adhere to the above instructions can lead to
removed when laying the finished floor material. Once damage of the door/mechanism and can incur further costs.
the floor material has been completed the protection
box must be re–positioned back over the door.
Technical Manual November 2017. Check with customer advisers for latest version.
C2 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the
cellar area or vent pipe run.
WWW.SPIRALCELLARS.COM 57
C3 CONCEALED DOOR
(TIMBER)
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
DOOR
Recess 18mm recess designed for timber, laminate and engineered wood floors
Spiral Cellars will set the hinges of the door to the FFL agreed during installation
Materials of door and Pine timber doors with four 18mm plywood panels, finished with two layers of 30%
pan polyurethane lacquer
Hinges 3 butt hinges set 18mm above the top of the stainless steel frame
Motor is fixed to a stainless steel back plate, onto top rings of cellar, and connected to a
control box which sits within a top cellar module. Arm of motor is fixed through two holes
to centre steel trim of door. Two recessed hex head machine screws hold the arm in place.
Removal of these two screws (from the topside of door) will release the motor arm in
case of failure
A manual gas strut arm is also fixed from stainless steel back plate to centre steel trim
of door. Door takes approximately 30 seconds to open to 85° maximum Duty cycle: 2
minutes continuous use followed by 18 idle minutes
WWW.SPIRALCELLARS.COM 59
C3 LAYING FLOORING:
CONCEALED DOOR
INSTALLATION
Laying Flooring Around a Concealed Door Fitting Carpet onto a Recessed Concealed Door,
with an Edge Bead
The floor is to be set parallel to the door. Flooring should be
laid once the screed has fully dried out. Timing for this may If required a timber or metal edge bead can be fitted. The
vary, according to local site/climate conditions. When laying hinges are set at 18mm higher than the door, with finished
timber floor, please ensure that the timber is level with the floor level (FFL) set to the top of the hinges.
top of the hinges. The flooring must not be higher than the
hinge, as this will cause the door to bind on the hinge–side Fitting Instructions:
when opened back to 85°.
• Check the thickness of underlay and carpet to determine
To ensure that the gap between the timber on the door and the correct build up from the door to top of hinge — this
the timber flooring laid on the screed is as tight as possible, will determine the thickness of the bead.
the timber flooring will need to be rebated over the stainless
steel frame and around the door hinges (as shown in the • Fit the timber outer edge level bead to the top of the
diagram). A cut out should be made for the hinges. The hinges and around the frame of the door.
flooring behind the hinges on the frame side will need a
chamfered edge to prevent the door from binding. • Ensure an adequate gap is left around all four sides of the
door, to allow it to open cleanly.
When affixing the flooring to the top of the recessed door, it
can either be glued or secret nailed. • Check door operation throughout the works.
The door can be left with the edge of the flooring visible and
stained when the door is in the open position or you can picture
frame the timber floor if you prefer.
Timber flooring
Cut out around hinge
Timber flooring
Notched over Frame
Machine screw
Concrete/Screed
Technical Manual November 2017. Check with customer advisers for latest version.
C3 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the
cellar area or vent pipe run.
WWW.SPIRALCELLARS.COM 61
C4 CONCEALED DOOR
(STANDARD TILES)
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
(from underside
of frame to top of
hinge block)
DOOR
Tiles should be laid inside the frame of the door panel, and up to the internal edge of the outer frame.
A cut out should be made around the hinges and tiles to be laid to the level of the top of the hinge
Spiral Cellars will set the hinges of the door to the FFL given during the installation
Hinges 2 hinge plates set level with top of frame, 60mm deep
Weight 90 kg approx
A manual gas strut arm is also fixed from stainless steel back plate to centre steel trim of door. Door
takes approximately 30 seconds to open to 85° maximum
Motor approved to: EN 60601-1/UL 60601-1 in connection with CB8, CB12, CB14, CB18 AND CBJ
Locking A retractive switch and key operated isolation switch are located in line of sight of the cellar
mechanism
WWW.SPIRALCELLARS.COM 63
C4 LAYING FLOORING:
CONCEALED DOOR
FLOORING INSTRUCTIONS
1. Flooring should be laid once the screed has fully dried 8. There are two options regarding the finishing of the
out. Timings for this may vary according to local site/ door tile edge around the door frame:
climate conditions.
Floor finish to be left with cut edge on show internally
2. The door will be set to the confirmed finish floor level. when door is open. The cut edge can be polished and
stained to match if necessary. This option gives the door
3. Please ensure the flooring is set parallel to the cellar a more discreet look when in the closed position. Keep
door. Spiral Cellar’s Project Manager will set the door in mind the door is only open for a very short period of
parallel to the confirmed grid line. time during it’s lifetime.
4. When laying the flooring, please ensure that the top of A tile beading edge or similar can be installed to the edge
the floor finish is level with the top of the door hinges. of the floor finish to hide the cut floor finish edge. Please
This includes the flooring laid inside the door tray. ensure an adequate gap is left between the tile bead and
door trim to prevent the two catching when the door is
5. A flexible tile adhesive should be used when laying the opening and closing.
floor finish in the door tray and Ditra matting.
The floor finish inside the door tray can be finished up against the
6. Please ensure that the hex head machine screws are door trim and level with the door hinges.
left exposed on the top of the cellar door and are not
IMPORTANT
covered by the tiles or grout. These bolts are required to
access the cellar in the event of a motor failure.
Please ensure that the motor fixing bolts are left exposed
7. The floor finish around the outside of the door frame will level with the top of the door, and are not covered by the
need to be finished in line with the internal edge of the tiles or grout. These bolts are required to access the cellar
door frame. The floor finish may need to be rebated to in the event of a motor failure.
pass over the frame edge depending on the overall floor
finish thickness.
Technical Manual November 2017. Check with customer advisers for latest version.
C4 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the
cellar area or vent pipe run.
WWW.SPIRALCELLARS.COM 65
C5 CONCEALED DOOR
(HEAVY TILES)
Suitable for installations with tiles between 12mm and 20mm
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
(from underside
of frame to top of
hinge block)
Materials Stainless steel, satin finish to 240 grit Stainless steel, satin finish to 240 grit
DOOR
Hinges 2x hinge plates set 2–3mm higher than the top of frame
16mm bronze pivot pin inserted through the hinge plate
From outside of stainless steel trim to back edge of hinge block = 70mm
Lifting Linak actuator motor 24V with a thrust of up to 2000N Door takes approximately 30 seconds to open to
mechanism 85° maximum
Motor is fixed to a stainless steel back plate onto the top
rings of cellar and connected to a control box, which sits Duty cycle: 2 minutes continuous use followed by
within a top cellar module 18 idle minutes
Arm of motor is fixed through two holes to the centre Ambient operating temperature of motor: from
steel trim of door. 4x recessed hex head machine screws 5ºC to 40ºC
hold the arm in place. Removal of these two screws
Motor has protection class IPX5
(from the topside of door) will release the motor arm in
case of failure Motor approved to: EN 60601-1/UL 60601-1
in connection with CB8, CB12, CB14, CB18 and
A manual gas strut arm is also fixed from stainless steel
CBJ
back plate to centre steel trim of door
Locking A retractive switch and key operated isolation switch are located in line of sight of the cellar
mechanism
WWW.SPIRALCELLARS.COM 67
C5 LAYING FLOORING:
CONCEALED DOOR FOR
12mm-20mm TILES
3. When laying a tiled floor, please ensure that the tiles are
level with the top of the hinges. A flexible tile adhesive
should be used inside the door tray and Ditra matting.
4. Please ensure that the hex head machine screws are left
Door frame
exposed on the top of the door and are not covered by
the tiles or grout. These bolts are required to access the
cellar in the event of a motor failure.
Flooring
Hinge block
Tile to edge
of frame
Technical Manual November 2017. Check with customer advisers for latest version.
C5 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the
cellar area or vent pipe run.
WWW.SPIRALCELLARS.COM 69
C6 RECTANGULAR GLASS
DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
Materials Stainless steel angle satin finish to 240 grit Stainless steel angle satin finish to 240 grit
DOOR
Weight:
Individual glass 98.5 kgs 98.5 kgs
door panel
Complete assembled 158.5 kgs 158.5 kgs
unit
Operational safety A retractive switch and key operated isolation switch are located in line of sight of the cellar. Key
features operated isolation switch is provided. Emergency door release switch inside the cellar
WWW.SPIRALCELLARS.COM 71
C6 LAYING FLOORING:
GLASS DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
C6 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the • Only Spiral Cellars Staff are permitted to enter the cellar
cellar area or vent pipe run. whilst the door is still protected.
WWW.SPIRALCELLARS.COM 73
C7 HALF-ROUND
GLASS DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
Materials Stainless steel angle satin finish to 240 grit Stainless steel angle satin finish to 240 grit
DOOR
Weight:
Individual glass 68 kgs 78 kgs
door panel
Complete assembled 128 kgs 138 kgs
unit
Operational safety A retractive switch and key operated isolation switch are located in line of sight of the cellar. Key
features operated isolation switch is provided. Emergency door release switch inside the cellar
WWW.SPIRALCELLARS.COM 75
C7 LAYING FLOORING:
HALF-ROUND GLASS DOOR
INSTALLATION
1. The floor is to be set parallel to the door.
Technical Manual November 2017. Check with customer advisers for latest version.
C7 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the • Only Spiral Cellars Staff are permitted to enter the cellar
cellar area or vent pipe run. whilst the door is still protected.
WWW.SPIRALCELLARS.COM 77
C8 ROUND GLASS DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
ORIGINAL SPIRAL CELLAR WHITE SPIRAL CELLAR
FRAME
Materials Stainless steel angle satin finish to 240 grit Stainless steel angle satin finish to 240 grit
DOOR
Weight:
Individual glass panel 68 kgs 78 kgs
Operational safety A retractive switch and key operated isolation switch are located in line of sight of the cellar. Key
features operated isolation switch is provided. Emergency door release switch inside the cellar
WWW.SPIRALCELLARS.COM 79
C8 LAYING FLOORING:
ROUND GLASS DOOR
INSTALLATION
1. The floor is to be set parallel to the door.
Technical Manual November 2017. Check with customer advisers for latest version.
C8 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • The door should remain protected until the After Sales
box for approximately 6 weeks to allow the cellar to dry out. Visit is complete. We will require the client or contractor
to sign to confirm the condition of the door.
• The door protection sheet must not be removed at any time.
• Approximately 6–8 weeks after the completion of the
• The timber protection box over the door may only be cellar or when all building works are complete, we will
removed when laying the finished floor material. Once carry out an After Sales Visit. The cellar will be checked
the floor material has been completed the protection box in terms of its performance; (humidity and temperature
must be re-positioned back over the door. levels). Any extras such as step coverings will be fitted if
these have been ordered. Then once signed off, the cellar
• Contractors must not store any materials, substances or will be ready to stock.
tools on top of the protection box.
• If there are any doubts concerning the installation
• Do not stand or sit on the protection box. procedure and requirements you should contact your
Project Manager for technical guidance, or to arrange a
• Do not allow rubbish and site debris to fall into the cellar site meeting.
— this increases the risk of the cellar being damaged.
• To prevent damage, due care and attention to the area
• If there is under floor heating in the same room, then around the door must be given.
no under floor heating pipes or matting are to be laid
within the ‘circular area of excavation plus 300mm all • Failure to adhere to the above instructions can lead to
round’. Vent pipes are to be fully wrapped and insulated damage of the door/mechanism and can incur further costs.
if shallow, or may have to run under the slab. No other
services such as hot water pipes are to run across the • Only Spiral Cellars Staff are permitted to enter the cellar
cellar area or vent pipe run. whilst the door is still protected.
WWW.SPIRALCELLARS.COM 81
C9 RETRACTABLE ROUND
GLASS DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
WHITE SPIRAL CELLAR ONLY
FRAME
Internal opening
Height 233mm
(from underside of
frame
to top of stainless steel
bezel)
DOOR
Materials Low iron toughened glass, 3 ply toughened glass, 32mm with sandblasted edge
feature
Configuration One fixed half round, one opening half round. The door is built to open in an anti–
clockwise direction (the cellar steps will also be set in an ANTI–CLOCKWISE direction)
Features a discreet hatch outside the cellar within the floor finish, to access the
motor for maintenance
Motor is fitted to side of door, accessible from a access hatch to be created within floor
finish. Motor can be isolated at this point
Locking mechanism A retractive switch and key operated isolation switch are located in line of sight of the
cellar
WWW.SPIRALCELLARS.COM 83
C9 MAINTENANCE HATCH FOR
THE RETRACTABLE ROUND
GLASS DOOR
Technical Manual November 2017. Check with customer advisers for latest version.
C9 LAYING FLOORING:
RETRACTABLE ROUND
GLASS DOOR
INSTALLATION
1. Flooring should be laid once the screed has fully dried 5. The flooring around the external motor box will need to
out. Timing for this may vary according to local site/ be cut to provide access to the motor box compartment
climate conditions. in the case of a motor failure. The flooring will also need
to be installed on the motor box lid.
2. The door will be set to the confirmed finish floor level.
6. Attach a ply board flooring to the motor box lid before
3. Please ensure the flooring is set parallel to the cellar installing the floor finish on top.
door. Spiral Cellars’ Project Manager will set the door
parallel to the confirmed grid line. 7. The flooring joint gap around the motor box will need to
be filled with a flexible sealant: this allows the motor box
4. The door bezel (trim) can be installed following two compartment to be easily accessed (please see diagram
different methods. The bezel detail will be confirmed showing motor box details).
by the Spiral Cellars Project Manager during the pre–
installation visit, and will be ordered in advance.
DIAGRAM 1 DIAGRAM 2
Laying flooring around the retractable door (Bezel finished, Laying flooring around the retractable door (Bezel finished,
flush with FFL) above FFL)
Top of bezel installed at FFL. The bezel is finished with Floor finish installed to touch underside of bezel. Bezel
a square edge for the contractor to finish the floor up to. sits 3mm above FFL and is finished with a chamfered edge,
Contractor may need to allow for an expansion gap between preventing a trip hazard and hiding the finished floor cut edge.
floor finish and bezel. A flooring specialist will advise how to
finish expansion gap.
WWW.SPIRALCELLARS.COM 85
C9 HOW TO PROTECT THE
CELLAR AND DOOR
POST-INSTALLATION
• The door must be propped open underneath a protection • Approximately 6–8 weeks after the completion of the
box for approximately 6 weeks to allow the cellar to dry out. cellar or when all building works are complete, we will
carry out an After Sales Visit. The cellar will be checked
• The door protection sheet must not be removed at any time. in terms of its performance; (humidity and temperature
levels). Any extras such as step coverings will be fitted if
• The timber protection box over the door may only be these have been ordered. Then once signed off, the cellar
removed when laying the finished floor material. Once will be ready to stock.
the floor material has been completed the protection box
must be re-positioned back over the door. • If there are any doubts concerning the installation
procedure and requirements you should contact your
• Contractors must not store any materials, substances or Project Manager for technical guidance, or to arrange a
tools on top of the protection box. site meeting.
• Do not stand or sit on the protection box. • To prevent damage, due care and attention to the area
around the door must be given.
• Do not allow rubbish and site debris to fall into the cellar
— this increases the risk of the cellar being damaged. • Failure to adhere to the above instructions can lead to
damage of the door/mechanism and can incur further costs.
• If there is under floor heating in the same room, then
no under floor heating pipes or matting are to be laid • Only Spiral Cellars Staff are permitted to enter the cellar
within the ‘circular area of excavation plus 300mm all whilst the door is still protected.
round’. Vent pipes are to be fully wrapped and insulated
if shallow, or may have to run under the slab. No other • The metal cover plate over the motor housing unit must
services such as hot water pipes are to run across the remain in place at all time before and after the electrical
cellar area or vent pipe run. connection has taken place.
Technical Manual November 2017. Check with customer advisers for latest version.
D
LIGHTING &
ELECTRICALS
WWW.SPIRALCELLARS.COM 87
D1 CELLAR WIRING:
STANDARD &
REINFORCED DOORS
DIAGRAM
for standard door 1 - INSIDE
and reinforced door (garage)
Inside cellar wiring for standard door and reinforced door (garage)
Technical Manual November 2017. Check with customer advisers for latest version.
D2 CELLAR WIRING:
CONCEALED DOORS
DIAGRAM 1 - INSIDE
To internal
release switch
Feed from
switch
internal
& Earth
3 core
release switch
L To retractive
switch
E CAT 5 cable
S/L To switch
Lighting
L1 L2
Large Junction box
Multi core switch
Common cable: Remove plug
from end, cut away
excess cables retaining
Red = COM
Switch cable Dark Green = L2
Power in from Linak controller Orange = L1
multi-core
Linak controller
LED Driver
Actuator
WWW.SPIRALCELLARS.COM 89
D3 CELLAR WIRING:
RECESSED CONCEALED
DOOR (TIMBER)
Wiring for outside the cellar for recessed concealed door (Timber)
2 position retractive
One way switch Key switch “rocker” switch
Earth
c
Twin knock out bok
3 gang grid
3 gang face plate
Com c1 c2 3x MK grid switches
CAT 5. 12V
Note: CAT 5 cable MUST NOT be
energized with a 240V supply
Technical Manual November 2017. Check with customer advisers for latest version.
D4 CELLAR WIRING:
GLASS & EXTERNAL
DOORS
WWW.SPIRALCELLARS.COM 91
D5 CELLAR EQUIPMENT
SET OUT
KEY
1 Control Unit Fuse
2 230V Mains In
3 230VAC Mains Out
4 Motor Out
5 Control Cable In
6 Programming Unit
7 24VDC Out
8 Power Indicator for DC
9 Unit Power Indicator
10 Error Light
Motor Unit
Technical Manual November 2017. Check with customer advisers for latest version.
D6 CONNECTIONS FOR
COLUMN LEDS
Bulkhead Light and Marker &
LED Diagrams
Control unit
switched to
230 VAC Out
Soffit / Roof
LEDs run out of
Female PSU Lead the same driver
3 – 16W
Bulkhead lights 350mA Constant
connected to PSU current driver
cable in JB
Junction Box
1.0mm Flex
or T+E
Loom supplied
by Spiral Cellars
Aurora LED
marker lights
Bulkhead light
WWW.SPIRALCELLARS.COM 93
D7 CONNECTION OF LOOM
FOR STRIP LED LIGHTING
am
LED connection
LED supplied by
Spiral Cellars
Loom supplied
by Spiral Cellars
Technical Manual November 2017. Check with customer advisers for latest version.
D8 RETRACTABLE DOOR
SWITCH CONNECTIONS
WWW.SPIRALCELLARS.COM 95
D9 LIGHTING
NOTE
PREPARATION
Please refer to electrical diagrams from page 86.
FOR LEDS
As standard there are two lights in our cellars, 4. The cables need to be run in conduit from the module
one on the ‘ceiling’ and one at the foot of the under the first step inside the cellar and then out to the
switching position outside the cellar.
spine. We use exterior grade bulk head lights,
with 40 watt bulbs in a chrome finish. There is 5. The feed cable from the fused connection unit or consumer
a manual switch to operate the light. We offer an unit also needs to be run to the switching position.
upgrade LED option for the Original and White
Spiral Cellars. 6. The column LED loom must be installed in the central
cellar column with the ends fed out through each of the
The White Spiral Cellar system incorporates a circular ring pre–drilled holes. The remaining cable must then pass
in the floor of the cellar, a strip under each step and the through the vent pipe under the top step and come
ceiling soffit. out of a small cut in the pipe, then into the under step
module with the other cables.
Column LEDs are also available to fit in both the Original and
White Spiral Cellars. 7. The column LED marker lights can then be solder or
crimp connected to each loop in the loom where it exits
1. The LED Lighting options require a pre–drilled hole to the column, and then adequately heat shrink covered
allow cables to be fed through from the central column before being placed in the column and twisted to lock in
to the relevant position for each step. on spring clips.
For LED Strip lights the hole will be 20mm and for the 8. The soffit strip LED cable must run from the step
Spot (Marker) LED the hole will be 25mm. The position support module and through to the soffit channel,
of the holes for the Spot LEDS will depend upon the ensuring the male end is at the soffit. The LED back strip
direction of the steps, clockwise or anti clockwise. should be cut to the length needed and stuck in place
Please see the photographs to identify these positions. before the LED strip can be fitted.
2. The cellar wiring requires a fused connection unit with a 9. All the connections for the junction box in the cellar and
5A or 6A fuse or a direct feed from a consumer unit with at the switching position can be seen on the Electrical
an RCD protected 6A MCB or a 6A RCBO. Diagrams datasheet.
Technical Manual November 2017. Check with customer advisers for latest version.
WWW.SPIRALCELLARS.COM 97
0203 815 3329 [email protected]
Spiral Cellars Ltd, Woodcock House, High Street, Wimbledon Village, SW19 5BY
www.spiralcellars.com