Project Control Plan
Project Control Plan
This Report, including the data and information contained in this Report, is provided to you on an
“as is” and “as available” basis at the sole discretion of the Government of Alberta and subject to the
terms and conditions of use below (the “Terms and Conditions”). The Government of Alberta has
not verified this Report for accuracy and does not warrant the accuracy of, or make any other
warranties or representations regarding, this Report. Furthermore, updates to this Report may not
be made available. Your use of any of this Report is at your sole and absolute risk.
This Report is provided to the Government of Alberta, and the Government of Alberta has obtained
a license or other authorization for use of the Reports, from:
Shell Canada Energy, Chevron Canada Limited. and Marathon Oil Canada Corporation, for
the Quest Project
Each member of the Project expressly disclaims any representation or warranty, express or
implied, as to the accuracy or completeness of the material and information contained herein, and
none of them shall have any liability, regardless of any negligence or fault, for any statements
contained in, or for any omissions from, this Report. Under no circumstances shall the Government
of Alberta or the Project be liable for any damages, claims, causes of action, losses, legal fees or
expenses, or any other cost whatsoever arising out of the use of this Report or any part thereof or
the use of any other data or information on this website.
The Government of Alberta’s intent in posting this Report is to make them available to the public
for personal and non-commercial (educational) use. You may not use this Report for any other
purpose. You may reproduce data and information in this Report subject to the following
conditions:
• any disclaimers that appear in this Report shall be retained in their original form and
applied to the data and information reproduced from this Report
• the data and information shall not be modified from its original form
• the Project shall be identified as the original source of the data and information, while this
website shall be identified as the reference source, and
• the reproduction shall not be represented as an official version of the materials reproduced,
nor as having been made in affiliation with or with the endorsement of the Government of
Alberta or the Project
By accessing and using this Report, you agree to indemnify and hold the Government of Alberta and
the Project, and their respective employees and agents, harmless from and against any and all
claims, demands, actions and costs (including legal costs on a solicitor-client basis) arising out of
any breach by you of these Terms and Conditions or otherwise arising out of your use or
reproduction of the data and information in this Report.
Your access to and use of this Report is subject exclusively to these Terms and Conditions and any
terms and conditions contained within the Report itself, all of which you shall comply with. You will
not use this Report for any purpose that is unlawful or prohibited by these Terms and Conditions.
You agree that any other use of this Report means you agree to be bound by these Terms and
Conditions. These Terms and Conditions are subject to modification, and you agree to review them
periodically for changes. If you do not accept these Terms and Conditions you agree to immediately
stop accessing this Report and destroy all copies in your possession or control.
These Terms and Conditions may change at any time, and your continued use and reproduction of
this Report following any changes shall be deemed to be your acceptance of such change.
If any of these Terms and Conditions should be determined to be invalid, illegal or unenforceable
for any reason by any court of competent jurisdiction then the applicable provision shall be severed
and the remaining provisions of these Terms and Conditions shall survive and remain in full force
and effect and continue to be binding and enforceable.
These Terms and Conditions shall: (i) be governed by and construed in accordance with the laws of
the province of Alberta and you hereby submit to the exclusive jurisdiction of the Alberta courts,
and (ii) ensure to the benefit of, and be binding upon, the Government of Alberta and your
respective successors and assigns.
Heavy Oil
Controlled Document
Quest CCS Project
Document Revision 01
ECCN EAR 99
Security Classification
Disclosure None
Revision History
REVISION STATUS APPROVAL
Rev. Date Description Originator Reviewer Approver
00 Feb. 19’ 2010 Issued for ESAR Arpit Desai Nayef Hattab Anita Spence
01 2010-11-15 Issued for Define Arpit Desai Nayef Hattab Nayef Hattab
• All signed originals will be retained by the UA Document Control Center and an electronic copy will be stored in Livelink
Summary
Add document summary info.
Keywords
Add document keywords
DCAF Authorities
Date Role Name Signature or electronic reference (email)
Heavy Oil
-3-
TABLE OF CONTENTS
Table of Contents
1. OVERVIEW & OBJECTIVES :.................................................................................................... 4
2. PROJECT CONTROL ORGANISATION & RESPONSIBILITY ...................................... 7
3. COST CONTROL : ....................................................................................................................... 12
a. Work Breakdown Structures ............................................................................................... 12
b. Cost, Time, and Resources (CTR) Catalog ....................................................................... 12
c. Value of Work Done (VOWD) .......................................................................................... 13
d. Commitment Management.................................................................................................. 13
e. Management of Change ....................................................................................................... 13
f. Earned Value Analysis ......................................................................................................... 14
g. Cost and Cash Forecasting .................................................................................................. 14
h. Manual of Authorities and Delegation (MoA) ................................................................. 15
i. Cost Management Tools ...................................................................................................... 15
j. Project Budget ....................................................................................................................... 16
k. Annual Budget....................................................................................................................... 17
4. INTEGRATED PLANNING AND SCHEDULE ................................................................. 17
5 PROGRESS MANAGEMENT ................................................................................................... 18
6. PROJECT CALENDAR ............................................................................................................... 18
7. REPORTING.................................................................................................................................. 18
7.1 Monthly Project Management Report ............................................................................... 19
7.2 Reporting Considerations for Partners and Other Key Stakeholders........................... 19
7.3 PROMIS Reporting .............................................................................................................. 19
8. COST ESTIMATING : ................................................................................................................. 20
9. PROJECT CONTROLS TOOLS : .............................................................................................. 22
10. PROBABLISTIC RISK ANALYSIS : ......................................................................................... 23
11. PRISM – OASYS – CONTRACTORS DATA FLOW ( TYPICAL ): ................................... 26
12.0 REFERENCES : ............................................................................................................................. 29
ACRONYMS .............................................................................................................................................. 30
Heavy Oil
-4-
Heavy Oil
-5-
o Management of Change along with the compilation of changes log, and PLT
involvement.
o Participate with the Heavy Oil/P&T Core Group estimation department in the
preparation of Owner’s costs, Contingency, etc and check estimates.
o Development of project specific PLIs ( Project leading Indicators ) that will be
used for control and reporting in Execute phase.
o Continued cost and schedule control of DEFINE ( FEED ) budget and baseline
schedule as per project standards 06.
o Reporting and analysis of DEFINE ( FEED ) performance to PLT in an Earned
Value context.
o Final configuration of scope to allow preparation of budget estimate.
o Delivery of budget estimate including Cost and Schedule Risk Analysis at the end
of DEFINE (FEED)
o Agreement with contractors on all project control systems, reports and data
DEFINE (FEED) back during the Execute phase.
During this phase, Shell’s Project Control team will have presence in the Contractors’ offices
in order to closely monitor the contractors’ performances, provide immediate support and
directions, as needed, and commence the team building process in order to ensure a smooth
transition into the Execute phase.
The project control team will ensure that the execution of DEFINE is executed with close
attention to the followings:
• Tight control of Management of Change in order to minimize any negative
cost and schedule impacts.
•
Leveraging of the knowledge acquired during the execution of SU Expansion
1 as similar Scotford site.
b. PCP during Execute Phase: ( Preliminary )
Key activities during DEFINE ( FEED ) phase is to develop robust and detailed Project
Control Plan for Execute phase. This PCP for execute phase is preliminary and to be
developed further with associated project specific project control procedure. The same
processes and tools identified in this PCP will be followed during the Execute phase. During
the DEFINE ( FEED ) phase, the Project Control Team will work with the selected
Contractors to set up their systems to be in line with the requirements of this PCP. The PCP
requirements are at high-level, hence, the contractors systems at lower levels are kept as
aiming to minimize the need for modifications and the contractors will be conform to Shells’
Work Breakdown Structure as outlined in Quest WBS procedure. This approach is in line
with Shell’s approach of working with the contractors’ systems rather than demanding
changes whilst maintaining its minimum standard on project control and reporting.
The goals of PCP for the Execute phase are to deliver as promised the budget and schedule
targets ( or better ) and this will be pursued with close attention to the followings:
• Monitoring of Leading Indicators (LIs) performances for recognition and
mitigation of early warning signs
Heavy Oil
-6-
Heavy Oil
-7-
Heavy Oil
-8-
Quest BOM
Ian Silk
Planning/Scheduling
Leonardo Arias
Legend:
Contractor
Banglore
Cost Control Lead
P&T – PES
Ramesh Kayala
Managers
Estimating Lead (P.T.)
Subodh Kumar/Louis S.
Risk Analysis/Co-ordination
Doreen Becker
*: Estimating lead from P&T Bangalore office plus some supervisory support from Onshore
Projects estimating team as needed
Heavy Oil
-9-
Project Services Lead is responsible for the overall project control function during
DEFINE ( FEED ) phase.
• Provide overall total project management to ensure that the Define Phase of the
project is carried out within the allocated budget and schedule parameters.
• Accountable for Reporting Project Performance via Project Monthly Report.
• Accountable for all Project Services deliverables.
• Update and maintain the Project Controls Plan for Define Phase. Develop and prepare
the Project control plan for Execute phase.
• Participate in the PLT, VLT and other project meetings, as appropriate.
• Work closely with Finance, C&P and Construction Leads to ensure continuity and
effective resolution of interface issues.
• Evaluate, monitor, and analyze Contractos’ progress and performance
• Participate and accountable for developing and review for in-house Type 2 estimate
preparations of the Execute phase.
Responsibilities specific to EPCM Contractor
• Review and participate in the preparation of EPCM contractors estimates.
• Identification of reporting structures required from Contractors.
• Ensure EPCM contractors compliance with WBS
• Provide guidelines to Contractor for the preparation of schedule activities to be in
line with the WBS structure.
• Identify the activities metrics (physical quantities and deliverables) for execute
phase that will be used as the basis for progress reporting.
• Review and evaluate Contractors’ key project control personnel for technical
capability and experience.
• Maintain a continuous evaluation and interpretation of the sub-contractors
project cost and schedule statuses and forecasts versus the established budget and
schedule baselines.
• Review and approve the sub-contractor’s project cost code of accounts and assist
in mapping to Quest Code of Accounts in PRISM .
• Evaluate the Contractor’s project cost and schedule procedures, reporting
programs, and cost systems and recommend improvements, if required.
• Monitor, analyze and interpret man-hour expenditures and forecasts against
planned baselines by major discipline and in total.
• Monitor, analyze and interpret status, progress actual and forecasts against
established baseline for total expenditures and commitment reports.
• Monitor, analyze and interpret status, progress, actuals and forecasts against
established baselines for the following on a periodic basis:
a. Progress Curves
b. Manpower costs, based on earned value
c. Manpower productivities, based upon earned quantities.
Project Control Plan 01
Heavy Oil
- 10 -
d. Manpower rates.
• Monitor schedule updates and deviations from the established baseline schedule
• Continuous analysis and monitoring of the Schedule Critical Path.
Heavy Oil
- 11 -
The project controls team key interfaces during Define phase are: Venture Leadership
team, Capture & Pipeline Project Leadership, Storage project Leadership, Regulatory and
Stakeholder management team, Capture EPCCM contractor, Pipeline EPC Contractor,
Scotford Site project group, Tie –in implementation contractor, JV partners for various
reviews/assurances, C&P, Finance.
The Quest Project control team resource plan for Define phase covers all resources and
support for the Quest Venture, Capture & Pipeline & Storage team in the Calgary office.
The detailed plan for the project control resources is developed and attached in CTR.
During Define phase, project services lead in discussions with Project Services manager –
Calgary will develop the overall project control resource plan for the execute phase
including site, module yard, home/engg. office etc.
Heavy Oil
- 12 -
3. COST CONTROL :
Cost control during any phase of a project comprises the setting up of the cost
procedures and systems and the monitoring and the reporting of the actual project
expenditure and commitments against the approved project budget. The early
identification and registration of deviations together with the following of trends enables
project management to control the project.
Regular reporting of the Value of Work Done, Commitments and assessment of the cost
of work remaining should detect any potential over or under expenditure in good time for
proper management action. Project progress is continuously monitored, in physical and
financial terms. In addition to these primary objectives of cost control throughout the
various phases of a project, it should provide data for:
• Capital expenditure phasing reflecting the anticipated progress of the Value of Work
Done
• A breakdown of the value of the final fixed assets
• Future estimating and planning purposes
Cost control on this project will be accomplished by the implementation of the project
control processes and tools described in the following sub-sections.
The WBS shall be consistently applied in all planning and schedule documents, progress
control, cost control and reporting documents.
The WBS for Quest is developed and maintained in accordance with the project-specific
WBS procedure. - 07-0-FA-5792-0001 Rev. 02
The CTR catalog for Quest for Define phase ( 2011 & up to FID 2012 ) is developed
already and will maintained during Define phase. Project-specific CTR Catalog procedure
for Execute phase will be developed during Define phase and maintained in accordance
with the CTR Catalog procedure.
Project Control Plan 01
Heavy Oil
- 13 -
VOWD is a key financial measure of the project costs because it is consolidated and
published in the Group financial results, which are subject to external regulation (including
Sarbanes Oxley or other new applicable regulations).
VOWD will be calculated, recorded, and reported each month in accordance with the RDS
VOWD procedure PSM-I-U-001182-FA-6180-0022. During Define phase project team
will develop the project specific VOWD procedure for the project.
d. Commitment Management
Commitment status will be reported as part of the monthly project management report
which includes the comparison of Total commitments and forecast commitments against
Planned commitment and approved budget/funds.
Commitment is the value of any contract, purchase order or other agreement between the
project and a supplier of goods and/or services, including agreed changes as they are
approved and shall be recorded in the transactional currency of the agreement.
The Commitment process defines leading information to identify if, and when, corrective
action is needed to complete deliverables on time and within budget.
Commitments will be authorized, recorded, and reported each month in accordance with
the RDS Commitments procedure – PSM-I-U-001182-FA-6180-23
e. Management of Change
The Management of Change process consists of the following steps:
• Identifying and recording change
• Evaluating and approving change
• Reporting change
Heavy Oil
- 14 -
Fluor ( Capture Facilities EPC contractor ) and Tri-Ocean ( Pipeline Contractor) will
manage their scope’s TIC during the define phase and each month report the define phase
budget and overall TIC cost. Any changes to the scope and subsequent impact on TIC will
be manage through Quest Management of Change process.
The EVA process combines both cost and schedule based on analyzing the variances
between actual earned and planned cost of work performed.
The ES process is only applicable to schedule and is based on analyzing the variances
between the actual time and the planned time taking to reach the earned value.
The results of Earned Value Management supports early warning, cost earned, forecast,
communication and objective assessment.
Earned Value Analysis will be performed during Define phase, Capture sub-project EPC
contractor will performed EV process as per agreed physical progress measurement and
cost phasing of the contract and will report monthly. Pipeline sub-project EV process will
be performed by Shell cost engineer. Storage sub-project is excluded for EV analysis
during Define phase of the project. Overall integrated EV will be reported by Shell cost
engineer on monthly basis will provide early warning to project/venture leadership team.
Earned Value Analysis project specific procedure for the execute phase will be developed
by end of the Define phase based on Type 3 cost and L3 schedule estimates in accordance
with the RDS Earned Value Management procedure – PSM-I-U-001182-FA-6180-000?
Heavy Oil
- 15 -
The resulting EAC is compared to the project budget to determine if corrective actions
and/or supplemental budget funds are required.
During Define phase based on Define phase CTR, cost engineer will monitor the FEED
phase contractor’s cost, Owner’s cost and other misc. contracts cost and forecast and
report the overall Quest project cost for DEFINE (FEED) phase. Cost and Cash
Forecasting will be accomplished in accordance with the RDS Cost and Cash Forecasting
procedure – PSM-I-U-001182-FA-6180-0026.
Cost and Cash Forecasting project specific procedure for the execute phase will be
developed by end of the Define phase based on Type 3 cost and L3 schedule estimates in
accordance with the RDS Cost and Cash Forecasting procedure – PSM-I-U-001182-FA-
6180-0026.
Controlled systems may grant approval rights to users. The approval rights that delegates
have in the systems are already based on a controlled delegation process that is consistent
with the MoA at a higher level. The system allows for specific approvals without listing the
delegates for those approval rights in the MoA. However, MoA always takes precedence.
Within Shell there are already documents that list specific staff and process of MOA
authority and there is no value added to relist those individuals or processes in a project
specific document.
Quest project will adhere to Shell Canada – Heavy Oil – Manual of authorities for Project
which is based on AOSP JV partner agreements. Manual of Authorities and Delegation will
be accomplished in accordance with current heavy oil MoA process. Quest project’s
specific manual of authorities is under discussions/development and will finalize in 1Q-
2011.
Heavy Oil
- 16 -
Cost Management Tool (PRISM) will capture cost from EPC Contractors and JDE and
SERP. PRISM will also be used for maintaining plans, phasing and project reporting.
Currently Shell Canada – Heavy Oil is implementing SAP Blueprint and implementation is
planned for January 01’ 2012. During Define phase, with support from Quest project
control team and SAP Blueprint implementation team will develop the PRISM, SERP &
SAP Blueprint interface for smooth transition to Execute phase and which will replace the
Shell Canada JDE ERP tool for financial management. During Define phase, project
leadership team will also make decision around implementing Global cost management
tool Dassian during execute phase or continue with the PRISM tool during execute phase
depending upon the Dassion tool implementation timeline.
During Define phase, project control team will make decision on implementing the
Pipeline Group Financial system “Luminon” and C&P tool “Pipework” will interface with
SAP Blueprint for financial details and reporting for execute phase.
Budget control
j. Project Budget
The current approved Budget for the Define phase of Quest Project is the total of the Original
Budget as recorded in the JDE & PRISM and any approved changes. Where Co-Venturer
requirements, legal requirements and Group annual capital ceilings require an annual budget,
see Section 4.2.
The Quest Projects approved Define phase Budget will be distributed to the various scopes of
work defined in the CTR Catalog to ensure that there is a clear understanding of the budget
associated with each scope of work and clear ownership of the budget by the budget holders
defined in the CTR Catalog.
The Quest Project approved Budget will be entered in UA’s – Heavy Oil - JDE system in
accordance with their normal budget management process. This allows tracking and reporting
of commitments, expenditures, and Estimate at Completion (EAC) relative to the budget that
is distributed to the summary level WBS elements.
Quest Capex Budget Management for the execute phase after FID will be accomplished by
developing the project-specific Budget Management procedure during Define phase.
Heavy Oil
- 17 -
k. Annual Budget
The Annual Budget is used to delegate the authority to spend a defined part of the total
approved Quest expense on Capital ( Feasex ) Budget in the applicable year. Co-Venturer
requirements, legal requirements and Group annual capital ceilings are the main reasons for the
use of an annual budget.
Annual expenditures will be tracked and reported to allow stewardship of expenditures versus
the annual budgets of Shell and Co-Venturers/JV Partners.
Each sub-project contractor ( excluding storage ) has prepared Define phase L3 schedule and
Level 2 schedule for execute phase. Shell planning/scheduling lead in discussions with Storage
team developed storage Select phase Level-3 schedule and Define & Execute phase Level-2
schedule. Shell planning/scheduling lead in discussions and buy in developed the Quest
project Level-2 Commissioning and start up schedule. Overall integrated Quest Define phase
Level-3 schedule is developed by Shell planning/scheduling lead including scheduling basis.
During Define phase, each sub-project contractor ( Fluor EPCCM for Capture & Tri-Ocean
for Pipeline ) will update their level-3 Define ( FEED ) schedule and approved updated
schedules native primavera .XER file send to Shell. Shell planning/scheduling lead will update
monthly Quest Venture, storage schedule and integrate each sub-projects updated schedule
monthly. Each month Shell planning/scheduling review the updated schedule and analyse
overall Quest project schedule.
Schedule management will be accomplished in accordance with the RDS Integrated Project
Planning procedure PSM-I-U-001182-FA-6180-0010.
During Define phase, Shell planning/scheduling will developed the project specific integrated
planning procedure.
Heavy Oil
- 18 -
5 PROGRESS MANAGEMENT
Progress measurement is the assessment of the proportion of actual work accomplished
towards completion of specific project deliverables. Detailed agreed upon rules of credit for
the measurement of physical progress on each relevant activity, including evidence required, is
already agreed with the Capture EPCM Contractor and to be agreed upon with Pipeline
contractor. During Define phase ( Storage – is still in Select phase ), project team will assess
physical % progress by milestone for the storage sub-project. Storage schedule will be monitor
via monitoring key milestones. Eg. “Integrated Reservoir modeling Gen 4”, FDP Complete
etc.
Shell planning/scheduling lead will integrated Capture, Pipeline & Storage projects agreed upon
rules of credit and weighing factor physical % progress and report overall Quest project
physical progress in the monthly report. Shell planning/scheduling lead will also monitor
contractors productivity and forecast the schedules and provide early warnings to project
manager.
Progress should be measured for all progress earning activities. If additional progress earning
activities/changes are encountered, they should be added to the base scope of work and
measured consistent with the progress management strategy.
Progress measurements will be carried out such that physical progress of the work can be
related to both the WBS and Level 2 Integrated Master Schedule. To ensure data consistency,
each level of schedule should be coded to enable roll-up and summary to higher levels. S-Curve
reporting as per Appendix B is necessary with actual and forecast plotted against planned
progress for the required duration
Progress Management for execute phase will be accomplished by preparing project-specific
Progress Management procedure at the end of Define phase.
6. PROJECT CALENDAR
The purpose of the project calendar is to provide clarity of key dates across the Project.
Typically the key dates comprise, but are not limited to project, contract and financial cut-off
and reporting dates; important project meetings; key project milestones (progress and
contractual) and holidays.
The Quest Project Team has established a Project Calendar and it is available in livelink.
Maintenance and use of the Project Calendar will be by Shell project services lead in accordance
with the Project Calendar procedure – PSM-I-U-001182-FA-6180-00013.
7. REPORTING
Heavy Oil
- 19 -
Heavy Oil
- 20 -
8. COST ESTIMATING :
The Project Control Team will be heavily involved with the contractors estimation
departments, in the review, guiding, defining basis of estimate, negotiation and support
during the DEFINE ( FEED )estimate (budget estimate) preparation The Project control
Team will also participate with the Heavy Oil/P&T Project Control Group in preparation of
Check Estimates and estimates of other costs outside the Contractors Scopes like Owner’s
costs, etc.
Introduction
At the end of DEFINE ( FEED )a Level III Budget Authorization Estimate will be
completed as part of the DEFINE ( FEED )deliverables to support Final Investment
Decision (FID). The estimate will be based on a minimum requirement of a 30%
model review to support estimate definition. It will be expected that in order to
support a 30% model review, a certain amount of detailed engineering will be
required to be completed. The Contractor, and Shell will agree upon the level of detail
engineering required to complete the estimate, prior to developing the estimate. The
final estimate accuracy range shall be determined after the risk analysis has been
completed.
It should be noted that during the DEFINE ( FEED )phase, the Shell cost estimators
will be preparing a Check Estimate in parallel with the Contractor estimate. All
MTO’s, and technical data used by the Contractor to develop their estimate, will also
be used by the Shell estimators to develop their Check Estimate. All documents to be
used in the development of the DEFINE ( FEED )estimate, shall be stamped
“Issued for Estimate”, and deposited into Livelink. The Shell Project team will also
develop estimates for items outside of the Contractors scope, such as Owners Costs,
and Operation Capital.
The Contractor shall follow the Estimating Guidance Document within the RFP, this
document will help guide the Contractor as to what Shell’s expectations are for the
Execute Budget Control estimates.
DEFINE Estimate Plan
The major estimating deliverable in DEFINE will be the Level III Budget
Authorization estimate. The Owner will use the budget authorization estimate to
support the Final Investment Decision (FID). The estimate will be a “bottoms-up”,
material take-off (MTO) based estimate.
Heavy Oil
- 21 -
Heavy Oil
- 22 -
Heavy Oil
- 23 -
Formal, quantitative cost risk analysis will be performed at FID and in Execute
phase to analyse the variables and uncertainties present in the base cost.
The results of the risk analysis will assist with the following :
Methodology :
Each element of the base cost will be analysed to determine uncertainty ranges.
The ranges will be quantified as minimum, most likely and maximum cost.
The analysis will consider potential impact to the estimated values arising from
uncertainties in scope, duration and productivity along with the impact of
technological, environment, market conditions, and statutory requirements and
experience factors.
Output :
The results of the risk analysis will include the following output.
Frequency :
Heavy Oil
- 24 -
The cost risk analysis will be performed by Shell P&T as an outsider of the project team
with significant input from QUEST Project Control team.
Quest project will follow RDS approved “Cost & Schedule Risk Analysis procedure –
PSM-I-U-00182-FA-6180-0090.
General :
The results of the risk analysis will assist with the following :
Methodology :
The risk analysis will utilise the Level –2 base schedule generated by the
contractor/Shell from Primavera software.
The analysis will consider potential impact to the estimated values arising from
uncertainties in scope, duration and productivity along with the impact of
technological, environment, market conditions, and statutory requirements and
experience factors.
Output :
The results of the risk analysis will include the following output.
Heavy Oil
- 25 -
Frequency :
The schedule risk analysis will be performed by Shell P&T as an outsider of the project
team with significant input from QUEST Project Control team.
Quest project will follow RDS approved “Cost & Schedule Risk Analysis procedure –
PSM-I-U-00182-FA-6180-0090.
Heavy Oil
- 26 -
General :
The scope and purpose of this document is to define the tasks and roles of the
QUESTProject Services Lead on a project that uses PRISM Project Manager.
PRISM Project Manager integrates information from multiple sources including
project cost estimates, (including changes and revision estimates), schedules (baseline
and current), incurred costs, and physical progress measurements. PRISM may
include data regarding contracts, purchase orders, engineering progress, document
control, equipment and materials management, and incident reporting.
The PRISM-specific role of the Project Services Lead relates to the management or
coordination of all of the above noted information. He/She must enable the inclusion
of all of this data into PRISM and initiate the calculations in PRISM that integrate the
data. To perform his/her task adequately he/she must be well informed of the status
of the project as a whole and of the individual data sources. He/She must coordinate
the input of all the information. He/She must provide timely reports for project
management. The tasks required can be divided into initial tasks and periodic tasks.
The initial tasks must be performed at the start up of the PRISM project. The
document “PRISM Project Execute Plan” details these tasks. In brief they are as
follows:
• Establish and implement coding structures and codes that enable integration of all
sources of data.
1. Initiate the creation of the PRISM project files and set up of the basic project
parameters – project name, dates, code tables, cost elements and etc.
2. Establish persons responsible to obtain and enter data.
3. Initiate training of personnel in PRISM.
4. Coordinate input of baseline estimates.
5. Coordinate input of original schedules.
6. Calculate the project baselines.
7. Confirm results with the project team and publish to others.
8. Archive data.
• The periodic tasks are similar to the initial tasks but repeated on a monthly or
other periodic basis.
1. Coordinate periodic input of data – changes, incurred costs, physical progress,
updated schedules, and other data that may include engineering progress,
purchase orders, contracts, documents, or incidents.
2. Calculate integrated data.
3. Confirm and report earned value performance results.
4. Archive data.
Heavy Oil
- 27 -
PRISMPM , contractor and Shell Finance data flow is as per the below figures Fig 5 & 6.
The data flow coding requirement is as per the attached PRISM requirement document.
Heavy Oil
- 28 -
Heavy Oil
- 29 -
12.0 REFERENCES :
The PCP processes and the Quest project-specific project control procedures are in
accordance with the following project process procedures:
Ref. Shell Project Processes - Procedure;
• PSM-I-U-001182-FA-6180-0001 Monthly Project Management Report
• PSM-I-U-001182-FA-6180-0002 Management of Change
• PSM-I-U-001182-FA-6180-0004 Glossary of Terms
• PSM-I-U-001182-FA-6180-0005 Project Services and Finance Handover
• PSM-I-U-001182-FA-6180-00010 Integrated Project Planning
• PSM-I-U-001182-FA-6180-00011 Progress Management
• PSM-I-U-001182-FA-6180-00012 Job Pack Management
• PSM-I-U-001182-FA-6180-00013 Project Calendar
• PSM-I-U-001182-FA-6180-0020 Project Cost Reporting
• PSM-I-U-001182-FA-6180-0021 Cost Contingency
• PSM-I-U-001182-FA-6180-0022 Value of Work Done
• PSM-I-U-001182-FA-6180-0023 Commitment (Assigned Budget)
• PSM-I-U-001182-FA-6180-0024 Work & Cost Breakdown Structures (WBS)
• PSM-I-U-001182-FA-6180-0025 Earned Value Analysis
• PSM-I-U-001182-FA-6180-0026 Cost & Cash Forecasting
• PSM-I-U-001182-FA-6180-0028 Cost Time Resources (CTR) Catalogue
• PSM-I-U-001182-FA-6180-0029 Project Finance Procedure: Cost Breakdown Structure (CBS)
• PSM-I-U-001182-FA-6180-0040 Cost Recovery
• PSM-I-U-001182-FA-6180-0041 Budget Management
• PSM-I-U-001182-FA-6180-0043 Manual of Authorities and Delegation
• PSM-I-U-001182-FA-6180-0044 Invoice Management
• PSM-I-U-001182-FA-6180-0045 Project Cost Allocation
• PSM-I-U-001182-FA-6180-0046 Exchange Rate Application
• PSM-I-U-001182-FA-6180-0060 Data Collection
• PSM-I-U-001182-FA-6180-0070 Cost Management of Contracts
• PSM-I-U-001182-FA-6180-0090 Project Cost & Planning Risk Procedure Cost & Schedule
Risk Analysis
Heavy Oil
- 30 -
ACRONYMS
AENV – Alberta Environment
AUC – Alberta Utilities Commission
CCP1 - Carmon Creek Project Phase 1
CPF – Central Processing Facility
CSU – Commissioning and Start Up
DG - Decision Gate
DG & C – Distribution, Gathering, and Corridor Construction
DRB – Decision Review Board
EIA – Environmental Impact Assessment
EP – Exploration and Production
EPEA – Environmental Protection and Enhancement Act
ERCB – Energy Resource and Conservation Board
ESAR – Estimate and Schedule Assurance Review
ESD – Emergency Shutdown
FID – Final Investment Decision
GIP – Group Investment Proposal
GTG – Gas Turbine Generator
HRSG – Heat Recovery Steam Generator
IPS – Integrated Planning Session
LT – Leadership Team
MAC – Main Automation Contractor
MC – Mechanical Completion
OIC – Order in Council
OPMG – Opportunity and Project Management Guide
ORM – Opportunity Realisation Manual
OPS – Operations
OR&A - Operations Readiness and Assurance
OTSG – Once Through Steam Generator
PCS – Process Control Systems
PDA – Pre-Disturbance Assessment
PRC – Peace River Complex
PO – Purchase Order
RFSU – Ready for Start-Up
SCM – Supply Chain Management
SDI – Sustainable Development Integration
SEIA – Socio-Economic Impact Assessment
TOR – Terms of Reference
VAR – Value Assurance Review
VIE– Value Improvement Exercise
Heavy Oil