Template in Excel For PE's (By CPDEP)

The document outlines activities and tasks for a multi-phase project (PDA AFE 1) including conceptual engineering, detailed engineering, procurement, and project management milestones. Key phases include CPDEP 1-2 (conceptual engineering), CPDEP 2-3 (further conceptual engineering), and CPDEP 3-4 (detailed engineering and procurement). The phases involve generating alternatives, selecting options, engineering design deliverables, procuring long-lead materials, and getting approvals to proceed to subsequent project phases.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
324 views

Template in Excel For PE's (By CPDEP)

The document outlines activities and tasks for a multi-phase project (PDA AFE 1) including conceptual engineering, detailed engineering, procurement, and project management milestones. Key phases include CPDEP 1-2 (conceptual engineering), CPDEP 2-3 (further conceptual engineering), and CPDEP 3-4 (detailed engineering and procurement). The phases involve generating alternatives, selecting options, engineering design deliverables, procuring long-lead materials, and getting approvals to proceed to subsequent project phases.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 36

Activity ID

PDA AFE 1
CPDEP PHASE 1
CONCEPTUAL ENGINEERING
Opportunity Framing
FE Engineering
0AA-BBE-100110
Project Roadmap
FE Engineering
0AA-BBE-100210
0AA-BBE-100220
0AA-BBE-100230
Project Engineering
FE Engineering
0AA-BBE-100410
0AA-BBE-100420
0AA-BBE-100430
0AA-BBE-100440
0AA-BBE-100450
0AA-BBE-100460
0AA-BBE-100480
0AA-BBE-100490
0AA-BBE-100500
0AA-BBE-100510
0AA-BBE-100520
0AA-BBE-100530
0AA-BBE-100540
0AA-BBE-100550
0AA-BBE-100560
CPDEP 1-2 GATE
DRB
FE Engineering
0AA-BBE-120110
Funding Approval
FE Engineering
0AA-BBE-120210
Activity Name

Develop Framing Document

Develop Project CPDEP Roadmap


OE Screening Tool
Develop Project OE Roadmap

Project Framing Document & Roadmap


Preliminary Site Selection
Preliminary Scope & Capacity
Preliminary Designs
Class 1 Estimate
Preliminary Project Milestone Schedule
SID Focus Item Selection
DEQ Assessment
DQ Spider
Seek & Incorporate Lessons Learned
Execution Plan for Phase 2
Resource Plan for Phase 2
Phase 2 AFE Package - ready for Approval
Phase 2 DSP - ready for DRB
Log Project Metrics - Phase 1 - Generic Metrics

DRB Approval to Proceed to Phase 2

Phase 2 Funding (AFE) - commit and approve


Duration Start Finish
Activity ID
PDA AFE 1
CPDEP PHASE 2
ENGINEERING CONTRACTS
CPDEP 2 Engineering Contract
FE Engineering
0AA-BBE-210110
0AA-BBE-210120
CONCEPTUAL ENGINEERING
Generation of Alternatives
FE Engineering
0AA-BBE-200110
0AA-BBE-200120
0AA-BBE-200130
Analyze, Narrow & Select Alternatives
FE Engineering
0AA-BBE-200210
0AA-BBE-200220
Value Improving & Best Practices
FE Engineering
0AA-BBE-200310
0AA-BBE-200320
Project Engineering
FE Engineering
0AA-BBE-200510
0AA-BBE-200520
0AA-BBE-200530
0AA-BBE-200540
0AA-BBE-200550
0AA-BBE-200560
0AA-BBE-200570
0AA-BBE-200580
0AA-BBE-200590
0AA-BBE-200600
0AA-BBE-200610
0AA-BBE-200620
0AA-BBE-200630
0AA-BBE-200640
0AA-BBE-200650
0AA-BBE-200660
0AA-BBE-200670
0AA-BBE-200680
0AA-BBE-200690
0AA-BBE-200700
0AA-BBE-200710
0AA-BBE-200720
0AA-BBE-200730
0AA-BBE-200740
0AA-BBE-200750
CPDEP 2-3 GATE
DRB
FE Engineering
0AA-BBE-220410
Funding Approval
FE Engineering
0AA-BBE-220510
Activity Name

CPDEP 2 Engineering Contract Package - develop


CPDEP 2 Engineering Contract - bid & award

Review and Refine Project Frame


Generate Alternatives
Define Scope for each Alternative

Evaluate Alternatives
Select Alternatives to Move to Phase 3

VIP & PB Selector Tool


Phase 2 VIP's & Best Practices

Preliminary Contracting Plan


Preliminary Procurement Strategy
OA - Start of Phase 2
Preliminary Scope, Equipment Lists, Selected Technology
Preliminary Project Safety Management Plan including SID
Issue Process Design
Resource Plan for Phase 3
Cost Control System (WBS) for Phase 3
Class 2 Cost Estimate
Preliminary Project Schedule
Cost & Schedule Risk Analysis Review
Decision Analysis Tools
DEQ Assessment
DQ Spider
Peer Assist
Seek & Icorporate Lessons Learned
Phase 2 PEP - ready for DSP
Phase 2 Framing Document Update
Phase 2 CPDEP Roadmap Session
Phase 2 OE Roadmap Session
OA - End of Phase 2
Phase 3 AFE Package - ready for Approval
Phase 3 DSP - ready for DRB
DRB Presentation
Log Project Metrics - Phase 2
DRB Approval to Proceed to Phase 3

Phase 3 AFE Request - commit & approve


Duration Start Finish
Activity ID
PDE AFE 2
CPDEP PHASE 3
ENGINEERING CONTRACTS
CPDEP 3 Engineering Contract
FE Engineering
0AA-BBE-310120
0AA-BBE-310130
FEL ENGINEERING
Process
FE Engineering
0AA-BBE-300110
0AA-BBE-300120
0AA-BBE-300130
Piping
FE Engineering
0AA-BBE-300210
0AA-BBE-300220
0AA-BBE-300230
Mechanical
FE Engineering
0AA-BBE-300310
0AA-BBE-300320
0AA-BBE-300330
Civil / Structural
FE Engineering
0AA-BBE-300410
0AA-BBE-300420
0AA-BBE-300430
0AA-BBE-300440
Instrument
FE Engineering
0AA-BBE-300510
0AA-BBE-300520
0AA-BBE-300530
0AA-BBE-300540
0AA-BBE-300550
Electrical
FE Engineering
0AA-BBE-300610
0AA-BBE-300620
0AA-BBE-300630
0AA-BBE-300640
0AA-BBE-300650
Value Improving & Best Practices
FE Engineering
0AA-BBE-300810
Project Engineering
FE Engineering
0AA-BBE-300910
0AA-BBE-300920
0AA-BBE-300930
0AA-BBE-300940
0AA-BBE-300950
0AA-BBE-300960
0AA-BBE-300970
0AA-BBE-300980
0AA-BBE-300990
0AA-BBE-301000
0AA-BBE-301010
0AA-BBE-301020
0AA-BBE-301030
0AA-BBE-301040
0AA-BBE-301050
0AA-BBE-301060
0AA-BBE-301070
0AA-BBE-301080
0AA-BBE-301090
0AA-BBE-301100
0AA-BBE-301110
0AA-BBE-301120
0AA-BBE-301121
0AA-BBE-301130
0AA-BBE-301140
0AA-BBE-301150
PROCUREMENT
Procurement Milestones
FE Engineering
0AA-BBE-330010
Piping Materials
FE Engineering
0AA-BBE-330210
Mechanical Equipment
FE Engineering
0AA-BBE-330310
Instrument Materials
FE Engineering
0AA-BBE-330610
Civil / Structural Materials
FE Engineering
0AA-BBE-330410
Electrical Materials
FE Engineering
0AA-BBE-330510
CPDEP 3-4 GATE
DRB
FE Engineering
0AA-BBE-320410
Funding Approval
FE Engineering
0AA-BBE-320510
Activity Name

CPDEP 3 Engineering Contact Package - develop


CPDEP 3 Engineering Contact - bid & award

P&ID's - Issue AFD - received & checked


Utility P&ID's - Issue AFD - received & checked
End of Phase 3 Process Engineering Milestone

Plot & GA Plan - Issue AFD - received & checked


Piping Material Requisitions - Long Leads - MR received & PR in Ariba
End of Phase 3 Piping Engineering Milestone

Equipment Data Sheets - Issue AFD - received & checked


Mechanical Material Requisitions - Long Leads - MR received & PR in Ariba
End of Phase 3 Mechanical Engineering Milestone

Main Equipment Building Package - Issue AFD - received & checked


Key Civil & Structural Drawings - Issue AFD - received & checked
Civil Bill of Materials & Material Requisitions - Long Leads - MR received & PR in Ariba
End of Phase 3 Civil Engineering Milestone

Control Phylosophy - Issue AFD - received & checked


Key Fire & Gas - Issue AFD - received & checked
Cause & Effect Chart - Issue AFD - received & checked
Instrument Material Requisitions - Long Leads - MR received & PR in Ariba
End of Phase 3 Instrument Engineering Milestone

Hazardous Area Clasification - Issue AFD - received & checked


Key Single Line Diagrams - Issue AFD - received & checked
Trace Heating - Issue AFD - received & checked
Electrical Material Requisitions - Long Leads - MR received & PR in Ariba
End of Phase 3 Electrical Engineering Milestone

Phase 3 VIP's & Best Practices

Contracting Plan Update


Procurement Strategy Update
Project Scope by Each Discipline Work Package
Phase 3-4 Gate Regulatory Plan Developed & Agreed with TCO RA
Project Safety Management Plan including SID Update
Phase 3 PHA - develop & run
Resource Plan for Phase 4
Class 3 Cost Estimate
Resource Loaded Project Schedule for Phase 4 - ready for DSP
Risk Management Plan
End of Phase 3 OA Session
OA Session for Phase 4
Economic Assessment
DEQ Assessment
DQ Spider
FEL Assessment
Peer or Technical Assist
PEP for Phase 4
Phase 3 Framing Document Update
Phase 3 CPDEP Roadmap Session
Phase 3 OE Roadmap Session
Phase 3 Discipline Engineering Deliverables - received & approved
Regulatory Packages developed and ready to issue (phase 1 or 2 type as applicable)
DSP for Phase 4 - ready for Approval
Phase 4 AFE Supplement Package - ready for Approval
Log Project Metrics - Phase 3

Project Procurement Start - Milestone

Long Lead Item PO2 - Actual on Site

Long Lead Item PO1 - Actual on Site

Long Lead Item PO4 - Actual on Site

Long Lead Item PO3 - Actual on Site

Long Lead Item PO5 - Actual on Site

DRB Approval To Proceed to Phase 4

Phase 4 AFE Supplement - commit and approve


Duration Start Finish
Activity ID
CPDEP PHASE 4
ENGINEERING CONTRACTS
Project Management Milestones
0AA-BBE-410010
CPDEP 4 Engineering Contract
FE Engineering
0AA-BBE-410110
0AA-BBE-410120
DETAILED ENGINEERING
Project Management Milestones
0AA-BBE-400010
0AA-BBE-400020
Process
FE Engineering
0AA-BBE-400110
0AA-BBE-400120
0AA-BBE-400130
0AA-BBE-400140
0AA-BBE-400150
0AA-BBE-400160
0AA-BBE-400170
Piping
FE Engineering
0AA-BBE-400210
0AA-BBE-400220
0AA-BBE-400230
0AA-BBE-400240
0AA-BBE-400250
0AA-BBE-400260
0AA-BBE-400270
0AA-BBE-400280
0AA-BBE-400290
Mechanical
FE Engineering
0AA-BBE-400310
0AA-BBE-400320
0AA-BBE-400330
0AA-BBE-400340
0AA-BBE-400350
Civil / Structural
FE Engineering
0AA-BBE-400410
0AA-BBE-400420
0AA-BBE-400430
0AA-BBE-400440
0AA-BBE-400450
Instrument
FE Engineering
0AA-BBE-400510
0AA-BBE-400520
0AA-BBE-400530
0AA-BBE-400540
0AA-BBE-400550
Electrical
FE Engineering
0AA-BBE-400610
0AA-BBE-400620
0AA-BBE-400630
0AA-BBE-400640
0AA-BBE-400650
0AA-BBE-400651
0AA-BBE-400661
0AA-BBE-400671
Value Improving & Best Practices
FE Engineering
0AA-BBE-400810
Project Engineering
FE Engineering
0AA-BBE-400910
0AA-BBE-400930
0AA-BBE-400940
0AA-BBE-400920
0AA-BBE-400921
0AA-BBE-400931
0AA-BBE-400950
0AA-BBE-400960
0AA-BBE-400970
0AA-BBE-400980
0AA-BBE-400990
0AA-BBE-401000
0AA-BBE-401010
0AA-BBE-401020
0AA-BBE-401030
0AA-BBE-401040
0AA-BBE-401050
PROCUREMENT
Procurement Milestones
FE Engineering
0AA-BBE-430010
0AA-BBE-430020
Mechanical Equipment
FE Engineering
0AA-BBE-430310
0AA-BBE-430320
Piping Materials
FE Engineering
0AA-BBE-430210
0AA-BBE-430220
0AA-BBE-430230
0AA-BBE-430240
0AA-BBE-430250
0AA-BBE-430260
0AA-BBE-430270
0AA-BBE-430280
Civil / Structural Materials
FE Engineering
0AA-BBE-430410
0AA-BBE-430420
0AA-BBE-430430
0AA-BBE-430440
Electrical Materials
FE Engineering
0AA-BBE-430510
0AA-BBE-430520
0AA-BBE-430530
0AA-BBE-430540
Instrument Materials
FE Engineering
0AA-BBE-430610
0AA-BBE-430620
0AA-BBE-430630
0AA-BBE-430640
0AA-BBE-430650
0AA-BBE-430660
0AA-BBE-430670
0AA-BBE-430680
0AA-BBE-430690
0AA-BBE-430700
0AA-BBE-430710
Paint & Insulation
FE Engineering
0AA-BBE-430810
0AA-BBE-430820
HANDOVER TO CONSTRUCTION
Project Management Milestones
0AA-BBC-420010
0AA-BBC-420020
Key Activities / Milestones
FE Construction
0AA-BBC-420710
Civil / Steel Works
FE Construction
0AA-BBC-420110
0AA-BBC-420120
Piping / Mechanical Works
FE Construction
0AA-BBC-420210
0AA-BBC-420220
Electrical Works
FE Construction
0AA-BBC-420310
0AA-BBC-420320
Instrument Works
FE Construction
0AA-BBC-420410
0AA-BBC-420420
Tie-In Works - Piping
FE Construction
0AA-BBC-420510
0AA-BBC-420520
CONSTRUCTION CONTRACTS
Project Management Milestones
0AA-BBC-440010
0AA-BBC-440020
Civil / Steel Works
FE Construction
0AA-BBC-440110
0AA-BBC-440120
Piping / Mechanical Works
FE Construction
0AA-BBC-440210
0AA-BBC-440220
Electrical Works
FE Construction
0AA-BBC-440310
0AA-BBC-440320
Instrument Works
FE Construction
0AA-BBC-440410
0AA-BBC-440420
Tie-In Works - Piping
FE Construction
0AA-BBC-440510
0AA-BBC-440520
Tie-In Works - Utility
FE Construction
0AA-BBC-440610
0AA-BBC-440620
CONSTRUCTION
Construction Milestones
FE Construction
0AA-BBC-450010
0AA-BBC-450020
0AA-BBC-450030
0AA-BBC-450040
0AA-BBC-450050
0AA-BBC-450060
0AA-BBC-450070
0AA-BBC-450080
Construction Kickoff Activities
FE Construction
0AA-BBC-450130
0AA-BBC-450110
0AA-BBC-450120
0AA-BBC-450140
0AA-BBC-450160
0AA-BBC-450150
0AA-BBC-450251
0AA-BBC-450180
0AA-BBC-450170
0AA-BBC-450190
0AA-BBC-450210
0AA-BBC-450200
0AA-BBC-450220
0AA-BBC-450240
0AA-BBC-450230
0AA-BBC-450250
Offsite Fabrication
FE Construction
0AA-BBC-460130
0AA-BBC-460140
0AA-BBC-460110
0AA-BBC-460120
0AA-BBC-460150
Disinvestment
FE Construction
0AA-BBC-470110
Onsite Installation
FE Construction
0AA-BBC-480110
0AA-BBC-480120
0AA-BBC-480280
0AA-BBC-480130
0AA-BBC-480140
0AA-BBC-480150
0AA-BBC-480160
0AA-BBC-480170
0AA-BBC-480180
0AA-BBC-480190
0AA-BBC-480200
0AA-BBC-480210
0AA-BBC-480220
0AA-BBC-480230
0AA-BBC-480240
0AA-BBC-480250
0AA-BBC-480260
0AA-BBC-480270
COMMISSIONING
Pre Commissioning
FE Construction
0AA-BBS-490110
0AA-BBS-490120
0AA-BBS-490130
0AA-BBS-490140
Commissioning
FE Construction
0AA-BBS-490150
0AA-BBS-490160
0AA-BBS-490170
0AA-BBS-490180
0AA-BBS-490190
Activity Name

CPDEP 4 Engineering Contact - award Milestone

CPDEP 4 Engineering Contact Package - develop & approve


CPDEP 4 Engineering Contact - bid & award

Phase 4 Detailed Engineering Start - Milestone


Phase 4 Detailed Engineering Finish - Milestone

Process Data Sheets - Issue IFRC - received & commented


Process P&ID's - Issue IFRC - received & commented
Process Data Sheets - Issue AFC - received & approved
Process P&ID's - Issue AFC - received & approved
Utility P&ID's - Issue IFRC - received & commented
Utility P&ID's - Issue AFC - received & approved
End of Phase 4 Process Engineering - Milestone

Utillity Tie-in Job Pack - Issue IFRC - received & commented


Mechanical & Piping Job Pack - Issue IFRC - received & commented
Piping Tie-in Job Pack - Issue IFRC - received & commented
Piping Material Requisitions - PO's raised in Ariba
Piping Tie-in Job Pack - Issue AFC - received & approved
Utillity Tie-in Job Pack - Issue AFC - received & approved
Mechanical & Piping Job Pack - Issue AFC - received & approved
Mechanical & Piping Job Pack - Issue AFC - Milestone
End of Phase 4 Piping Engineering - Milestone

Equipment Data Sheets - Issue IFRC - received & commented


Mechanical Material Requisitions - PO's raised in Ariba
Equipment Data Sheets - Issue AFC - received & approved
Mechanical Equipment Data Sheets - Issue AFC - Milestone
End of Phase 4 Mechanical Engineering - Milestone

Civil & Structural JP - Issue IFRC - received & commented


Material Requisitions - PO's raised in Ariba
Civil & Structural JP - Issue AFC - received & approved
Civil & Structural JP - Issue AFC - Milestone
End of Phase 4 Civil Engineering - Milestone

Instrument Job Pack - Issue IFRC - received & commented


Instrument Material Requisitions - PO's raised in Ariba
Instrument Job Pack - Issue AFC - received & approved
Instrument Job Pack - Issue AFC - Milestone
End of Phase 4 Instrument Engineering - Milestone

Electrical Job Pack - Issue IFRC - received & commented


Electrical Material Requisitions - PO's raised in Ariba
Electrical Job Pack - Issue AFC - received & approved
Electrical Job Pack - Issue AFC - Milestone
End of Phase 4 Electrical Engineering - Milestone
Regulatory Plan finalized and agreed with TCO RA / PE
Regulatory Package issued (full package or type 2)
Permit to construct requested

Phase 4 VIP's & Best Practicies

SID Compliance - checked by Each Discipline Work Package


Phase 4 Regulatory Plan & Package - expert review/approve
Phase 4 Environmental Package - expert review/approve
Phase 4 PHA
Regulatory approval positive conclusions recieved
Permit to construct recieved
AFC Job Packs - received and ready for Turnover to Construction
PEP Update (if needed)
MOC Documentation
OPS OE & OA Input
Commissioning Plan
Operating & Maintenance Procedures
Operator Training Procedures
Project Safety Startup Review Procedure
Facility Acceptance & Technical Commission Procedures
Construction AFE Supplement Package - ready for Approval
Log Project Metrics - Phase 4

Phase 4 Procurement Start - Milestone


Project Procurement Finish - Milestone

Mechanical Equipment PO1 - Actual on Site


Mechanical Equipment PO 2 - Actual on Site

Piping Valves PO1 - Actual on Site


LTCS Pipe & Fittings PO2 - Actual on Site
HDPE Pipe & Fittings PO3 - Actual on Site
SS Pipe & Fittings PO4 - Actual on Site
Motor Operated Valves PO5 - Actual on Site
Piping Specials PO6 - Actual on Site
Bolts & gaskets PO7 - Actual on Site
Bulks for piping tie-ins (piping & utility) PO8 - Actual on Site

Main Equipment Building Package PO4 - Actual on Site


Structural steel-piperack bulks PO1 - Actual on Site
Miscellaneous and Top ups PO2 - Actual on Site
Civil Bulks PO3 - Actual on Site

Switchboards PO1 - Actual on Site


Electrical Cables & Glands PO2 - Actual on Site
Electrical Bulks, Lighting & Earthing Materials PO3 - Actual on Site
Trace Heating Package PO4 - Actual on Site

Shut down valve (on-off valve) PO1 - Actual on Site


Control Valves PO2 - Actual on Site
Relief Valves PO3 - Actual on Site
F&G Detectors PO4 - Actual on Site
Orifice Plates PO5 - Actual on Site
Pressure Gauges PO6 - Actual on Site
PT/TT/FT/LT/ diff pressure transmitters PO7 - Actual on Site
Temperature Gauges PO8 - Actual on Site
DCS - fail safe controller & HPM cabinet PO9 - Actual on Site
Level Gauges PO10 - Actual on Site
Instrument bulks PO11 - Actual on Site

Paint PO1 - Actual on Site


Insulation PO2 - Actual on Site

Handover to Construction - Start


Handover to Construction - Finish

Construction AFE Supplement Package - Approved

Handover Checklist for Civil & Structural JP AFC - approved to accept JP


Handover Checklist to Start Civil/Steel Works - approved to start construction

Handover Checklist for Piping/Mechanical JP AFC - approved to accept JP


Handover Checklist to Start Piping/Mechanical Works - approved to start construction
Handover Checklist for Electrical JP AFC - approved to accept JP
Handover Checklist to Start Electrical Works - approved to start construction

Handover Checklist for Instrument JP AFC - approved to accept JP


Handover Checklist to Start Instrument Works - approved to start construction

Handover Checklist for Tie-Ins - Piping JP AFC - approved to accept JP


Handover Checklist to Start Tie-Ins - Piping Works - approved to start construction

Construction Contracts - Start


Construction Contracts - Finish

Civil & Structural Works - bid and review


Civil & Structural Works - commit and award WR

Mechanical & Piping Works - bid and review


Mechanical & Piping Works - commit and award WR

Electrical Works - bid and review


Electrical Works - commit and award WR

Instrumentation Works - bid and review


Instrumentation Works - commit and award WR

Tie-ins Works - Piping - bid and review


Tie-ins Works - Piping - commit and award WR

Tie-ins Works - Utility - bid and review


Tie-ins Works - Utility - commit and award WR

Construction WR Signed - Milestone


Facility Turnover from Operations - Milestone
Disinvestment Start - Milestone
Offsite Fabrication Start - Milestone
Disinvestment Finish - Milestone
Offsite Fabrication Finish - Milestone
Onsite Construction Start - Milestone
Onsite Construction Finish - Milestone
Construction Pre-Job Meeting with Civil & Structural Contractor
Construction Pre-Job Meeting with Piping & Mechanical Contractor
Piping & Mechanical Contractor - Prepare Construction Paperwork & Permits
Construction Pre-Job Meeting with E&I Contractor
Civil & Structural Contractor - Prepare Construction Paperwork & Permits
E&I Contractor - Prepare Construction Paperwork & Permits
Materials ROK Certification and Permit to use obtained (as applicable)
Civil & Structural Construction Work Permits - obtain from Operations
Piping & Mechanical Construction Work Permits - obtain from Operations
E&I Construction Work Permits - obtain from Operations
Civil & Structural Contractor Construction Kickoff Meeting & Mobilization
Mechanical Contractor Construction Kickoff Meeting & Mobilization
E&I Contractor Construction Kickoff Meeting & Mobilization
Material Withdraw to Start Civil & Structural Works
Material Withdraw to Start Piping & Mechanical Works
Material Withdraw to Start E&I Works

Fab Civil Activities


Fab Structural Steelwork Activities
Fab Piping Activities
Fab Insulation Activities
Fab Electrical & Instrumentation Activities

Disinvestment Activities

Install Civil Activities


Install Structural Steelwork Activities
Approval of ROK Certification and Permit to use
Install Piping/Mechanical Activities
Install Electrical Activities
Install Instrumentation Activities
RoK Agency (GGT) Notification for Inspection
SID Walkdown @ 25% Construction Complete
Tie-in Piping Activities
RoK Fire Department Notification for Inspection
SID Walkdown @ 50% Construction Complete
Tie-in Utility Activities
SID Walkdown @ 75% Construction Complete
Install Insulation Activities
SID Walkdown @ 90% Construction Complete
FECG/OPS Walkdown by System/Subsystem
FECG - Clear "A" Items List
FECG - Clear "B" Items List
Compile As-builts & Documentation & TCO Review
PSSR
FECG/Pre-commissioning - Clear "A" Items List from PSSR
Turnover to Commissioning/OPS

OPS - Piping/Mechanical Commissioning - Leak Test


OPS - E&I Commissioning
RoK Agency (GGT) Notification for Inspection for Technical Commission
Facility/System/Subsystem Technical Commission (TC)
Working Commission (If required)
Duration Start Finish
Activity ID
START-UP AFE 3
CPDEP PHASE 5
START-UP
Project Management Milestones
0AA-BBS-510010
Start-up
FE Construction
0AA-BBS-510110
0AA-BBS-510120
PROJECT CLOSE-OUT
Close-out
FE Engineering
0AA-BBF-520110
0AA-BBF-520120
0AA-BBF-520130
0AA-BBF-520140
Activity Name

Facility Turnover to Operations - Milestone

Facility Turnover to Operations/Maintenance


Start-up

Log Project Metrics - Phase 5


AFE Close-out Documentation
Project Close-out Lookbacks (Lessons Learned)
Project Close-out
Duration Start Finish

You might also like