Assignem4 SimSo
Assignem4 SimSo
A sporadic job
arrives at t=50 having the execution time of 10 and a relative deadline of 30. Create the sporadic
task in SimSo by selecting:” generate task set” and then list of acts. Dates to the release time
No
Consider the tasks T1(3, 0.5), T2(4, 1.5, 3), T3(7, 1.0, 5) and the RM scheduler. A sporadic job
arrives at t=50 having the execution time of 10 and a relative deadline of 30. Create the sporadic
task in SimSo by selecting:” generate task set” and then list of acts. Dates to the release time :
• What is the minimum/maximum/average response time of all tasks?
Yes.