This document provides a progress report for Project Seabird, contract MWC01, covering work done from July 31st to August 16th, 2020. It summarizes the status of various construction tasks including revetment construction, quarrying, dry filling, and vibrocompaction across several work sites. Overall, 84% of the scheduled revetment work, 17% of quarrying targets, and substantial portions of dry filling and vibrocompaction have been completed to date. Some tasks like revetment construction at MW-3 are lagging behind schedule.

Uploaded by

Vinit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views

Seabird - DPR 16 Aug 20

This document provides a progress report for Project Seabird, contract MWC01, covering work done from July 31st to August 16th, 2020. It summarizes the status of various construction tasks including revetment construction, quarrying, dry filling, and vibrocompaction across several work sites. Overall, 84% of the scheduled revetment work, 17% of quarrying targets, and substantial portions of dry filling and vibrocompaction have been completed to date. Some tasks like revetment construction at MW-3 are lagging behind schedule.

Uploaded by

Vinit
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Seabird Phase IIA

Dredging, Reclamation, Revetment, Quarrying and Navigational Aids


(MWC01)
DGSB-Contract 01 of 2017

DPR FTM-Aug 20_Project Seabird, MWC01


EMPLOYER: : DIRECTOR GENERAL PROJECT SEABIRD REPORTING DATE: Sunday 16 August 2020
ENGINEER: : AECOM INDIA PVT. LTD. PREPARED DATE: Monday 17 August 2020

CONTRACTOR: : L&T - ISDPL - DI JOINT VENTURE 16/Aug/20 Week 2 (Plan) Week 2 (Actual) Achieved FTM FTM Revise Plan

Total Scope Achieved upto Basic Rate Amount Qty Amount Amount Amount Amount Cumulative Cumulative
Sl.no. Description of Works Unit As per GFC 31 July 20
Qty Qty Qty Qty Remarks
excluding taxes (Crs) (Crs) (Crs) (Crs) (Crs) (Qty) (%)

# Revetment Construction
I MW-1 m³ 108,957 115,727 115,727 106% Work completed.

II MW-2 m³ 160,877 151,713 0 0 151,713 94% Substantially completed.


III MW-3 m³ 541,368 413,726 0 3,429 13,807 411,401 76%
A MW-3 South m³ 285,266 162,760 0 3,429 13,807 168,365 59%
1 Filter material m³ 97 32 1,025.00 0 0.00 0 0 0 0 0 0.00 0 0.00 32 33%
2 Preliminary bund m³ 103,288 74,766 1,002.00 0 0.00 0 0 0 0 0 0.00 0.00 74,766 72%
3 Core placing m³ 147,221 79,715 1,002.00 0 0.00 2,625 0.3 994 0 994 0.10 8,078 0.81 80,709 55%
5 Armour below +2.5CD m³ 13,952 6,442 1,573.00 0 0.00 0 0.0 207 0 1,175 0.18 1,997 0.31 7,617
6 Core above +2.5CD m³ 8,540 1,472 1,002.00 0 0.00 0 0.0 466 0 703 0.07 1,733 0.17 2,175
7 Armour above +2.5CD m³ 8,118 333 1,573.00 0 0.00 934 0.1 56 0 557 0.09 1,999 0.31 890
8 Bedding layer m³ 4,050 2,176 1,058.00 0 0.00 - - - - 0 0.00 0.00 2,176 54%
9 Geotextile layer m2 27,000 18,119 378.00 - 0.00 - - - - 0 0.00 0.00 18119.41 67%
B MW-3 North m³ 130,431 143,113 0 0 133,069 102% Work completed.
C MW-3 Armament wharf m³ 125,671 107,853 0 0 109,967 88% Revetment bund work completed.

Total m³ 811,202 681,166 0 0 3,429 0.44 13,807 1.61 684,595 84%

Sensitivity: LNT Construction Internal Use


#
Page 1 of 5
Seabird Phase IIA
Dredging, Reclamation, Revetment, Quarrying and Navigational Aids
(MWC01)
DGSB-Contract 01 of 2017

DPR FTM-Aug 20_Project Seabird, MWC01


EMPLOYER: : DIRECTOR GENERAL PROJECT SEABIRD REPORTING DATE: Sunday 16 August 2020

ENGINEER: : AECOM INDIA PVT. LTD. PREPARED DATE: Monday 17 August 2020

CONTRACTOR: : L&T - ISDPL - DI JOINT VENTURE 16/Aug/20 Week 2 (Plan) Week 2 (Actual) Achieved FTM FTM Revise Plan

Total Scope Achieved upto Basic Rate Amount Amount Amount Amount Amount Cumulative Cumulative
Sl.no. Description of Works Unit As per GFC 31 July 20
Qty Qty Qty Qty Qty Remarks
excluding taxes (Crs) (Crs) (Crs) (Crs) (Crs) (Qty) (%)

# Quarry Works

I Rock Production MT 11,050,287 1,802,721 0 0.00 41,904 0.00 14,976 0 32,280 150,000 1,835,001 17%

II Production for Revetment works MT 556,865 0 0.00 14,341 0.00 3,190 0 7,777 50,000 564,642

Quarry, transport and stockpile


III MT 8,840,600 297,475 128.00 0 0.00 10,989 0.1 7,061 0.09 11,261 0.14 39,000 0.50 308,736
rocks sizes not more than 1 MT
IV Rock shifting from MW 6 MT 220,750 133,797 - 0.00 - 0 133,797 Work Completed

# Dry Filling Works


1 MW5A (MW2 Revetment) m³ 700,000 773,396 17.25 0 0.00 0 0 0 0 0 0.00 0.00 773,396 Substantially completed.
2 MW4 (MW3 North Revetment) m³ 395,000 280,509 15.00 0 0.00 0 0.00 0 0.00 0 0.00 0.00 280,509 Substantially completed.

# Vibrocompaction in MW4 and MW5A


1 MW-4 vibrocompaction m³ 1,769,094 1,176,720 47.00 0 0.00 0 0.00 0 0.00 149,841 0.70 150,000 0.71 1,326,561 Substantially completed.
2 MW-5 vibrocompaction m³ 4,336,607 3,244,824 47.00 28,000 0.13 150,003 0.71 156,400 0.74 249,600 1.17 250,000 1.18 3,494,424 Substantially completed.
3 MW-4 & 5 surface compaction m2 166,597 116,972 47.00 18,000 0.08 114,482 0.54 114,750 0.54 168,889 0.79 400,000 1.88 285,861

# General works

1 Maintenance of Engineer’s Office Months 48 1,164,343.00 0.03 0.00 0.29 0.03 0.52 0.06 0.52 0.06 1 0.12
Maintenance of Engineer’s Field
2 Months 48 395,871.00 0.03 0.00 0.29 0.01 0.52 0.02 0.52 0.02 1 0.04
Office
Maintain Field Laboratory for the
3 Months 48 330,372.00 0.03 0.00 0.29 0.01 0.52 0.02 0.52 0.02 1 0.03
duration of contract.
Maintenance of Engineer’s Vehicle (4
5 Months 48 73,890.00 0.03 0.00 0.29 0.00 0.52 0.00 0.52 0.00 1 0.01
wheel drive)
Operation and maintenance of
6 Months 48 1,452,034.00 0.03 0.00 0.29 0.04 0.52 0.07 0.52 0.07 1 0.15
Security Gate
Allow for security guards at Work Site
7 Months 48 2,664,198.00 0.03 0.01 0.29 0.08 0.52 0.14 0.52 0.14 1 0.27
and Security Gate

8 Site Traffic Management Months 48 96,324.00 0.03 0.00 0.29 0.00 0.52 0.00 0.52 0.00 1 0.01

Total Amount (In Crs) 0.24 1.83 1.87 3.58 6.49

Sensitivity: LNT Construction Internal Use


#
Page 2 of 5
Chart Data
Revised Plan Time Achieved
Revetment - MW3 South 13,807 16 3,429
Vibro compaction work 400,000 16 399,441
MW-4 & 5 surface compaction 400,000 16 168,889
Quarry production for Revetment 50,000
works 16 7,777
39,000
Rock supplied to other contractors 16 11,261

Revised Plan Time Achieved


Revetment - MW3 South 100% 52% 25%
Vibro compaction work 100% 52% 100%
MW-4 & 5 surface compaction 100% 52% 42%
Quarry production for Revetment
works 100% 52% 16%

Rock supplied to other contractors 100% 52% 29%

Achieved/
Planned
 S.No Invoice (In Crs) Expected Remarks
(In Crs)
1 Apr'20 0.00 1.96
2 May'20 7.00 6.64
3 June'20 7.00 7.35
4 July'20 6.53 6.98
5 Aug'20 6.91 3.81 As on 16th Aug

# Sensitivity: LNT Construction Internal Use


Date 8/16/2020 8/1/2020
7/4/2020 31

Project Seabird_Progress for the Month


120%
13807 cum 400000 cum

100% 100% 100% 100%


100%
399441

80%

60%
52% 52% 52%

3429 42%
40%

25%

20%

0%
Revetment - MW3 South Vibro compaction work MW-4 & 5 surface
compaction

Revised Plan Time Achie

# Sensitivity: LNT Construction Internal Use


rd_Progress for the Month - Aug 20

400000 Sqm 50000 MT 39000 MT

00% 100% 100% 100%

52% 168889 52% 52%

42%
7777 11261

29%

16%

n work MW-4 & 5 surface Quarry production for Rock supplied to other
compaction Revetment works contractors

Revised Plan Time Achieved

# Sensitivity: LNT Construction Internal Use