Assignment 1 EPM
Assignment 1 EPM
TECHNOLOGY
ASSIGNMENT 1
SUBMITTED BY:
WAJIHA JAWWAD
BETE 54D
QUESTION:
Project X costs $15,000 and is expected to produce cash flows of $4,500 per year for 5 years.
Project Y costs $37,500 and is expected to produce cash flows of $11,100 per year for 5 years.
Calculate the two projects payback periods, NPVs and IRRs, assuming they are mutually exclusive,
and cost of capital is 14 percent.
Which project would be selected according to payback, NPV, IRR criterion? Why?
SOLUTION:
Years 0 1 2 3 4 5
Project X -15,000 4,500 4,500 4,500 4,500 4,500
Project Y -37,500 11,100 11,100 11,100 11,100 11,100
PAYBACK PERIOD
Years Project X Cumulative CF Project Y Cumulative CF
0 -15,000 -15,000 -37,500 -37,500
1 4,500 -10,500 11,100 -26,400
2 4,500 -6,000 11,100 -15,300
3 4,500 -1,500 11,100 -4,200
4 4,500 3,000 11,100 6,900
5 4,500 7,500 11,100 18,000
unrecovered amount
Payback Period of a Project: No. of years before full recovery + ( )
Total amount in full recovery period
4,200
• Payback Period of project Y= 3+ ( ) = 3.3784 years
11,100
Acceptance Criterion
If two projects are compared, that project should be selected whose payback period is less than that of
the other project.
According to this Criteria Project X should be selected because it has a less payback period than
Project X. Meaning Project X will recover the initial investment earlier than Project Y.
Next, we will find the Net Present Values for both projects:
NET PRESENT VALUE
For project X, i =14 % i.e. 0.14
4,500 4,500 4,500 4,500 4,500
NPV = -15,000 + + + + +
(1+0.14)1 (1+0.14)2 (1.014)3 (1+0.14)4 (1+0.14)5
According to this Criteria Project Y should be selected because it has a higher NPV than Project X.
Next, we will find the Internal Rate of Returns for both projects:
Internal Rate of Return IRR:
We calculate IRR using function in excel.
Acceptance Criterion
For two mutually exclusive projects, select the one with greater IRR value.
According to this Criteria Project X should be selected because it has a higher IRR than Project Y.
IRR of X > IRR of Y