Creating Basic Time Schedule in MSP

The document provides instructions on creating a basic time-schedule in Microsoft Project. It includes creating a work breakdown structure (WBS) for a villa project, adding activities with durations and predecessors, and sequencing the activities to generate a schedule report.

Uploaded by

Priyanshi Mittal
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views

Creating Basic Time Schedule in MSP

The document provides instructions on creating a basic time-schedule in Microsoft Project. It includes creating a work breakdown structure (WBS) for a villa project, adding activities with durations and predecessors, and sequencing the activities to generate a schedule report.

Uploaded by

Priyanshi Mittal
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Creating Basic Time-schedule in MSP

Learning Objectives:

➢ Creating WBS
➢ Adding Activities
➢ Sequencing activities
➢ Scheduling project and generating schedule report

Lab Exercise

1. Create the following WBS in the Project

Villa Project

Post-
Preconstruction Construction
construction
Phase Phase
phase

Subctructure Ground Floor


Terrace Work External Work Final Finishes
Work Work

2. Create the following schedule in activity window:


S.No. WBS Task Name Duration Predecessors
0 VILLA PROJECT 90 days
1 1 Project Start 0 days
2 2 Preconstruction Phase 5 days
3 2.1 Site Mobilization 3 days 1
4 2.2 Layout 2 days 3
5 3 Construction Phase 78 days
6 3.1 Substructure Works 10 days
7 3.1.1 Excavation 6 days 4
8 3.1.2 Foundations 7 days 7SS+3 days
9 3.2 G.Floor Works 53 days
10 3.2.1 Walls and Columns 10 days 8
11 3.2.2 Roof slab 7 days 10SS+7 days
12 3.2.3 Conduiting, water and sanitary pipes 4 days 11FS+14 days
13 3.2.4 Fixing of wooden frames and plastering 7 days 12SS+2 days
14 3.2.5 Kitchen and toilet tiling 10 days 13SS+4 days
15 3.2.6 Flooring 10 days 14SS+6 days
16 3.3 Terrace Works 28 days
17 3.3.1 Parapet, Waterproofing etc. 7 days 11
18 3.3.2 Services 10 days 17
19 3.3.3 Terrace Finish 7 days 18
20 3.4 External Works 59 days
21 3.4.1 Outside plastering 8 days 17,13SS+4 days
22 3.4.2 External services and Boundary wall 7 days 8
23 3.4.3 Paths and Pavements 7 days 22,21
24 3.4.4 Boundary wall gates 7 days 23
25 3.5 Final Finishes 23 days
26 3.5.1 Doors and Windows fixing 3 days 21,15
27 3.5.2 Internal Painting (Initial Coats) 3 days 26
28 3.5.3 External Painting (Initial Coats) 3 days 21
29 3.5.4 Wood Polishing 3 days 27,28
30 3.5.5 Hardware, Sanitary, Plumbing, Electrical
3 days 29
fixtures fixing
31 3.5.6 Final coats (Internal and External painting) 3 days 30,28
32 4 Post Construction Phase 7 days
33 4.1 Defects Rectification and Handing over 7 days 31,24
34 4.2 Project finish 0 days 33

3. Schedule the Project to see the schedule log report.