S Aa Civ Work (Rev.0 2010)
S Aa Civ Work (Rev.0 2010)
CIVIL WORKS
( SPECIFICATION )
526178307.doc Page 1 of 28
SWITCHGEAR
High Voltage Outdoor Wall Mounted Bushing
526178307.doc Page 2 of 28
CIVIL WORKS
Civil Construction Works
CONTENTS
1 GENERAL......................................................................................................................3
2 TECHNICAL DESCRIPTION......................................................................................3
2.1 Safety Precautions During Construction...........................................................................3
2.2 Material............................................................................................................................3
2.3 Auxiliary Work.................................................................................................................4
2.4 Surveying Work................................................................................................................4
2.4.1 General.............................................................................................................................4
2.4.2 Instruments.......................................................................................................................4
2.4.3 Auxiliary Work.................................................................................................................4
2.4.4 Site Survey........................................................................................................................5
2.4.5 Setting Out of Works........................................................................................................5
2.5 Dewatering During Construction......................................................................................5
2.5.1 General.............................................................................................................................5
2.5.2 Execution..........................................................................................................................6
2.5.3 Method of Dewatering......................................................................................................6
2.5.4 Discharging of Water........................................................................................................6
2.6 Earth and Rock Work.......................................................................................................7
2.6.1 General.............................................................................................................................7
2.6.2 Material............................................................................................................................7
2.6.3 Execution..........................................................................................................................7
2.6.4 Auxiliary Work.................................................................................................................8
2.6.5 Tests and Properties..........................................................................................................8
2.6.6 Open-Cut Excavation........................................................................................................9
2.6.7 Stockpiles and Disposal..................................................................................................10
2.6.8 Excavation and Manual Excavation................................................................................10
2.6.9 Backfilling......................................................................................................................11
2.6.10 Filling.............................................................................................................................11
2.6.11 Material for Structural Fill and Backfill..........................................................................11
2.6.12 Material for Non-Structural Fill and Backfill..................................................................12
2.6.13 Topping with Gravel “under foundation/ structural”.......................................................12
2.7 Piling Work....................................................................................................................12
2.7.1 General...........................................................................................................................12
2.7.2 Materials.........................................................................................................................13
2.7.3 Reinforcement................................................................................................................13
2.7.4 Execution of Work..........................................................................................................13
2.7.5 Basics for Test Piles........................................................................................................15
2.7.6 Details for Pile Tests.......................................................................................................16
2.7.7 Driving of Piles (if applicable)........................................................................................18
2.7.8 Foundation Work............................................................................................................21
526178307.doc Page 3 of 28
CIVIL WORKS
Civil Construction Works
2.7.9 Joints...............................................................................................................................22
2.8 Cable and Pipe Trenches/Channels.................................................................................22
2.9 Grout under Base Plates..................................................................................................23
526178307.doc Page 4 of 28
CIVIL WORKS
Civil Construction Works
1 GENERAL
This part of the Specification shall cover all items related to civil construction works of the
Project, including survey works, dewatering, earth and rockwork, piling work, foundation works
and auxiliary works. Works shall include all items required for the tendered Project, as well as
all auxiliary works.
All works shall further be carried out in full compliance with all local rules and regulations and
the Specification shall be read, if applicable for the Project.
For applicable technical standards, tests, reference shall be made to:
S-AA-CIVIL-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
526178307.doc Page 5 of 28
CIVIL WORKS
Civil Construction Works
2.2 Material
All equipment, machinery, materials and tools required for execution of the works shall be
workable and kept in good working conditions throughout the construction period, and shall be
listed in a schedule, which shall be subject to ADDC/AADC’s approval.
For all materials to be used and to be installed, the Bidder/Contractor shall give special attention
to manufacturer's written instructions and follow them carefully.
2.4.1 General
Surveying works shall include the survey and setting out of survey points as particularly
described hereafter, as well as the determination of UTM Co-ordinates (Nahrawhan Datum) to
the satisfaction of Town Planning Department. The results of all surveying works carried out
shall be submitted to ADDC/AADC and shall be adjusted, if required.
2.4.2 Instruments
Only instruments, recently calibrated by the concerned gauging office, and acceptable to
ADDC/AADC, shall be used. The certificate of the gauging office, latest issue, shall be
submitted prior to the start of works and whenever required.
526178307.doc Page 6 of 28
CIVIL WORKS
Civil Construction Works
Providing adequate lighting and duly considering all obstacles, which may interfere with setting
out of survey, and providing adequate ventilation to ensure the necessary view and to enable
personnel to stay in tunnels and shafts.
Furnishing any marking as requested by ADDC/AADC in connection with control survey, and
providing survey points in lieu of and/or in addition to the Bidder’s/Contractor's marks, in
accordance with ADDC/AADC's instructions.
Provision of adequate number of unskilled labourers and materials, as deemed suitable by
ADDC/AADC for the control and auxiliary surveys; provision and maintenance of survey
instruments and accessories, supply of all materials required for survey and associated purposes,
protection of all survey points, etc.
526178307.doc Page 7 of 28
CIVIL WORKS
Civil Construction Works
2.5.1 General
Before the method of ground water lowering is selected, adequate knowledge of the ground and
water conditions has to be obtained from the results of a soil investigation and/or information,
which may be available from ADDC/AADC.
For the method and technique to be chosen by the Bidder/Contractor, the British Standard CP
2004 shall apply.
Where necessary, cofferdams, sheet piles, pump sumps, channels, troughs, inlet gutters, pipes
and any other required works to control and discharge water found in the work site to keep the
different work fronts free of any water during construction shall be part of the scope. The
dewatering system shall be designed and installed in such a way that alteration and extensions
can be made any time throughout the operating time, if necessary. Reserve unit shall be kept
ready for service when failure of any of the installed unit occurs.
The Bidder/Contractor has to consider the possibility of a temporary failure of the electric power
service and shall install emergency power units with sufficient capacity to feed the necessary
power to the installed unit at the moment of failure.
The Bidder/Contractor shall submit to ADDC/AADC, the detailed planning of the chosen
dewatering method and technique and the stand-by reserve units. The Bidder/Contractor has to
adjust the system if required by ADDC/AADC.
The Bidder/Contractor must ensure that drainage works will be eliminated without causing any
interference to his own work and that of other Bidder’s/Contractor’s operating elsewhere on the
construction site and to structures already erected or still in progress. Any damage occurring
during the above mentioned period shall then be made good by the Bidder/Contractor at his own
expense.
2.5.2 Execution
The Bidder/Contractor has to record all revealed data, which might occur during continuous
operation. The records have to be submitted to ADDC/AADC for information and checking by 9
a.m.
The Bidder/Contractor has to ensure the control of operation by manpower experienced in this
field round the clock, full operation of the dewatering systems during curing time of concrete
structures, removal of cofferdam, sheet piling, suction pipes, well points, channels, troughs, inlet
gutters, pipes, etc, after completion of dewatering.
526178307.doc Page 8 of 28
CIVIL WORKS
Civil Construction Works
In case of dewatering by means of the casing method the shells have to be extracted or filled up
with lean concrete.
Temporary buildings, structures and hard-standings and any other works required for installation
and operation of the dewatering systems, have to be removed after completion of the works.
2.6.1 General
This Article applies to all earth and rock-work required within the Project for establishing of the
buildings, structures and underground services.
Generally, all buildings and structures shall be founded on bearing strata and all excavation work
for foundations have to be carried out in accordance with the approved design and drawings.
2.6.2 Material
The characteristics of various types of ground and allowable bearing pressure are defined in
DIN, BS, or the equivalent EN (Euronorm). Values applicable during design shall be verified
through the Soil Investigation.
526178307.doc Page 9 of 28
CIVIL WORKS
Civil Construction Works
2.6.3 Execution
The Bidder/Contractor shall carry out all kind of earth and rock- works, either by manpower or
by use of fuel driven machinery and tools acceptable to ADDC/AADC for the following:
Clearing and grubbing
Excavation of top soil
Mining
Demolition of existing structures
Grading
Open cut excavation
Obstacles and archaeological findings
Replacement of material
Trench excavation for services
Backfilling
Safety precaution during earthwork.
If excavated material is rich in organic matter, it shall be stockpiled and after completion of all
civil and appertaining works, the green/agricultural area of the project area shall be reinstated by
placing the top soil layers as directed by ADDC/AADC. No additional payment shall be allowed
for such works.
Burning and blowing off of any material and use of explosives is generally not permitted except
where written order has been issued by ADDC/AADC and has been confirmed by the concerned
local authorities.
526178307.doc Page 10 of 28
CIVIL WORKS
Civil Construction Works
Removal of any groynes, buried pipes, wattle-work, fascines and the like that might
interfere with excavation profiles, irrespective of whether or not such structures are
specified in the Tender
Excavation /removal of concrete plates, beams, floors, boulders, rocks, large stones or
foundations
Eliminating unsuitable material from fills, and, if necessary, mixing of different soil
materials, spreading and compacting of filling materials in layers not exceeding 250 mm,
compaction tests every second layer all to maintain in the fills complying with the related
standard
Transport of excavated material to fill or deposit, placing and spreading in layers according
to conditions and drawings, and careful compaction
Grading of intermediate and top fill surfaces and slopes to fines and levels required
Sorting of excavated material which, if necessary, is to be used for special purposes
Providing, maintaining and later removal of driveways, maintaining existing ways and
roads; providing, placing, maintaining and later removing, conveying and dumping
equipment
Protection/support to existing adjacent building or structures during excavation or draw
down the under ground water table.
526178307.doc Page 11 of 28
CIVIL WORKS
Civil Construction Works
tests for density of soil in place of sand cone method for each second layer of
"Backfilling and/or replacement of material and/or roadwork" as per ASTM D
1556-64. Rate of testing shall be 1 test every 300 m2.
All tests have to be recorded in forms acceptable to ADDC/AADC. If not otherwise specified,
the minimum required degree of the compaction of the modified proctor density shall be:
Under blinding concrete for shallow foundations and slabs on grade 97%
Under pavements, under embankments. 95%
Parking areas and roads. 98%
Under blinding concrete for pilecaps and suspended grounds slabs 90%
526178307.doc Page 12 of 28
CIVIL WORKS
Civil Construction Works
Soil not accepted for re-use and excess excavation shall be removed and disposed off to areas
allowed by the municipality of the Government or other responsible authorities. The
Bidder/Contractor shall trim and form the edges of soil to profiles and levels as directed by
ADDC/AADC. He shall also maintain without interruption the flow of water courses affected by
the disposal of soil material.
The Bidder/Contractor shall observe any agreements concerning the site, which may exist
between ADDC/AADC and other persons or authorities concerned.
The placing of materials within waste areas shall be made in layers not exceeding 50 cm
thickness in order to obtain an appreciable degree of compaction by means of the transportation
equipment. All traffic towards or from the waste areas shall be continuously directed and
changed for the total covering of the surface of such areas in order to take advantage of the
weight of vehicles for compaction.
The Bidder/Contractor shall not have the right either to additional payment or to claim due to
work required for stockpiling materials or to take to waste areas.
The cost of the transportation of materials from the excavations to their final destination
including any necessary temporary stockpiling and the additional loading and transporting
operations shall be included in the total bid.
2.6.9 Backfilling
For backfilling of structures and areas, only selected imported material or approved well graded
granular material from the open-cut excavation shall be used. Use of any kind of waste or
building material or rock pieces for this scope shall not be permitted.
526178307.doc Page 13 of 28
CIVIL WORKS
Civil Construction Works
Dumped soil material touching the faces of the structures shall be of soft material. The material
shall be placed in horizontal layers of not more than 25 cm in compacted thickness. The fill
moisture content shall be adjusted to achieve a maximum of compaction.
The material shall be compacted by vibrator plates and/or mechanical tampers. The minimum
required degree of compaction shall be as defined before under Tests and Properties above.
2.6.10 Filling
Filling shall be approved well graded and selected material from excavations of predominantly
granular materials and free from slurry, mud, organic and other unsuitable matter, capable of
compaction by ordinary means.
Filling shall be placed in 25 cm layers and compacted at optimum moisture content by
mechanical means, where possible. Alternatively, where allowed by ADDC/AADC, fill shall be
placed in layers and saturated with sufficient water or otherwise compacted to produce maximum
compaction.
Filling around pipes and cables shall be of fine material to cover the pipe or cable by at least
15cm before the normal in-filling is placed.
All filled areas shall be left neat, smooth and well compacted, the top surface consisting of the
normal site surface soil, unless otherwise directed.
The Bidder/Contractor shall be responsible for the reinstatement of any surfaces of structures,
which may move or otherwise be affected by settlement of backfill.
526178307.doc Page 14 of 28
CIVIL WORKS
Civil Construction Works
SIEVE % PASSING
25.4 mm 100
19.05 mm 70 – 100
9.53 mm 50 – 80
No. 4 35 – 65
No. 10 25 – 50
No. 40 15 –30
No. 200 5 –15
Note: the maximum allowable L.L. and P.I are 35
and 10 respectively
2.7.1 General
This Article applies to the foundation design/static analysis in view of necessary piling works.
Piling works shall be based on the findings of the soil investigations and/or information given in
writing by ADDC/AADC. Piles shall be designed for the required design loading (uplift,
compression and horizontal loads) in line with the approved foundation design.
526178307.doc Page 15 of 28
CIVIL WORKS
Civil Construction Works
Earthwork as well as all concrete and reinforced concrete work shall be as specified under the
relevant items. All site installations, auxiliary works, materials, services, safety measures, and -
as requested by ADDC/AADC - all tests and samples required for the completion of the piling
works are to be included.
The static analysis/pile design shall normally be in accordance with DIN EN 1536, DIN 1045,
1054, 1055, 4014 and 4026, or BS-8004, BS-8110 and other applicable DIN or British Standard.
2.7.2 Materials
All materials to be used for the piling works shall meet the requirements as specified below.
Cement to be used for concrete piles shall be selected according to the recommendations of the
soil investigations report. Sulphate resistant Type Cement (SRC), or under certain conditions,
‘Moderately Sulphate Resistant Cement’ (MSRC-type II to ASTM-C150) based on the
recommendations of the Geotechnical Engineer and approved by ADDC/AADC, shall be used.
All cements are to be in accordance with either DIN 1164, DIN EN 196, BS or the American
Standards ACI, ASTM C150.
2.7.3 Reinforcement
Only epoxy coated reinforcement shall be used for piled foundations located in areas of
aggressive soils according to the soil investigation. Such reinforcement steel shall be protected
against corrosion with a fusion-bonded epoxy coating. The coating shall be applied in
accordance with ASTM A775/775M-01, and shall be supplied from an approved coating factory
using approved epoxy resins.
If – based on the findings of the soil investigations - epoxy coated steel is not required, deformed
high tensile steel shall be applied.
All bending procedures shall be to the coating factory’s recommendations and instructions, as
agreed with ADDC/AADC. The coating factory representative shall ensure his product is used
fully in accordance with his recommendations.
The Bidder/Contractor shall furnish to ADDC/AADC a certificate of compliance for each
shipment of coated bars.
526178307.doc Page 16 of 28
CIVIL WORKS
Civil Construction Works
Spacers to be used shall be of the concrete type only. Other materials shall only be used upon
explicit approval of ADDC/AADC.
526178307.doc Page 17 of 28
CIVIL WORKS
Civil Construction Works
Installation procedures shall be such that adjacent piles shall not heave or move laterally. All
installation procedures shall be subject to ADDC/AADC's approval. Permanently installed shells
shall be cut off at the pile cut-off level.
Daily records of each pile shall be produced by the Bidder/Contractor. The records shall give
detailed information on the type, diameter, length, location, penetration into bearing strata, piling
platform level related to zero level, date driven, date of casting, volume of concrete consumed,
depth from piling plat form level to toe, cut off level, top concrete level, length of temporary
casing, length of permanent casing and details of any obstructions encountered. Records shall be
submitted in duplicate to ADDC/AADC every following working day by 09 00 HRS.
Each cast-in-situ pile shall be filled with quality concrete up to at least 60 cm above the cut-off
level of the pile to allow for complete removal of slush and other foreign matters etc. from the
main pile and thus obtain sound and uniform concrete. Pouring concrete into the pile shall be
carried out using the tremie pipe method as well as the concrete pump. Pouring concrete into pile
shall only be stopped once complete removal of slush and other foreign matter has been ensured,
or as directed by ADDC/AADC.
The heads of concrete piles shall be incorporated with in-situ concrete pile caps, etc., and the
concrete in the head of the pile shall be carefully broken away from the reinforcement which
shall then be cleaned and straighten as shown on the Drawings or as directed. The pile shall be
cut off at the specified level and the concrete surface must be horizontal, plane and free from all
loose aggregate.
The top portion of the pile reinforcement shall be protected with PVC pipes, polythene sheet
wrapping or equivalent means to prevent damages to the epoxy coating of the reinforcement
when trimming the pile heads.
526178307.doc Page 18 of 28
CIVIL WORKS
Civil Construction Works
The Bidder/Contractor shall carry out successful foundation load tests in order to prove the
suitability of the pile foundation selected. The results of the tests shall be submitted in a format
for approval by ADDC/AADC.
The following types of tests are to be considered:
a) Piling Type Tests (Preliminary Pile Test)
Prior to piling commencement the Bidder/Contractor shall install one test piles of each type of
pile proposed.
The piles shall be considered as acceptable in case the obtained load-settlement/heave-diagrams
do not indicate movements beyond permissible limits as per Tender Documents or the relevant
Standards.
Other (working) piles shall not be installed until the load tests have been conducted and the
results evaluated.
Type test piles shall not be utilised within the works and shall be treated in such a way that they
do not obstruct the further works.
b) Piling Foundation Routine Test (Working Pile Test)
The Bidder/Contractor shall perform routine tests on at least 2 % of the working piles, with a
minimum of 2 tests for each pile type.
c) Integrity Tests
The integrity of the piles shall be checked successfully after installation by means of sonic pile
testing equipment, at 100% of piles.
2.7.6.1 Loading
The Bidder/Contractor shall execute the test piles using the same equipment, which he intends to
use for execution of all the piles. The test piles should be of the same length and same type as the
piles proposed for the project. Loads shall be applied in the direction of the resultant force acting
on the pile.
526178307.doc Page 19 of 28
CIVIL WORKS
Civil Construction Works
The loading tests of piles shall be in accordance with the procedure outlined in DIN 1054,
DIN 4014 and DIN 4026 as well as ISSMFE recommendation on "Axial pile loading tests", Part
1, static loading.
Type tests (preliminary pile tests) are to be loaded to either 250% of the anticipated design load,
or to the ultimate bearing load. At least two load cycles have to be made during type testing, the
first reaching from 0% to 100% and the second - after off-loading - to 250% of the design load.
Load steps shall normally not exceed 25% of the design load.
For routine tests (working pile tests) a loading to 150% of the design load is required. At least
two load cycles have to be carried out, the first reaching from 0% to 100%, and the second - after
off-loading to 150% of the design load. Load steps shall be worked out in line with the latest
edition of the “Building Regulations and Guidelines” of Abu Dhabi Municipality, whereby
following load steps/cycles shall normally be applied:
526178307.doc Page 20 of 28
CIVIL WORKS
Civil Construction Works
Vertical movements have to be measured by means of at least three dial gauges; horizontal
movements have to be measured by two dial gauges only, with a precision of 1/100 mm. On
every increment, settlements shall be recorded after 30”, 2’, 4’, 8’, 15’, 30’, 1h. Movement of the
pile head shall be less than 0.25 mm within that hour, or until 2 hours have elapsed, whichever
occurs first, before the application of the new load increment.
2.7.6.3 Evaluation/Conclusion
A safe design pile capacity shall be the least value determined in accordance with the
Municipality Regulations and this specification.
526178307.doc Page 21 of 28
CIVIL WORKS
Civil Construction Works
Alternatively, the Bidder/Contractor may scale down the safe design load, and the pile layout
shall be revised with the modified pile capacity.
526178307.doc Page 22 of 28
CIVIL WORKS
Civil Construction Works
ADDC/AADC. Any piles that are split, warped, buckled, damaged or imperfect in any way shall
be removed and discarded. If any driven pile shall have been raised by the subsequent driving of
any adjacent pile or by any cause, the raised pile shall be re-driven to its original penetration and
resistance. The refusal shall be with HILEY formula or any other dynamic formula subject to the
approval of ADDC/AADC.
Debris from pile cut-offs and damaged piles shall not be buried in required fill under slabs at
grade or in required embankments, but shall be disposed by the Bidder/Contractor off the Site of
the work.
A record of the driving of all piles shall be kept by the Bidder/Contractor, and a signed copy
submitted to ADDC/AADC daily. The records shall show the pile type, length, location,
penetration for driving stages and the results of any tests.
After driving, the concrete heads of the piles are to be stripped off, to the elevation required, the
binders removed, and the main reinforcement bent to form an anchorage into the concrete of the
pile cap. Care must be taken in breaking out concrete that no damage is done to the lower section
of the piles.
526178307.doc Page 23 of 28
CIVIL WORKS
Civil Construction Works
design depth and driving resistance. Sufficient information shall be provided on the efficiency
and energy of the driving equipment. Dynamic evaluation and analysis shall be provided where
requested by ADDC/AADC.
Weight and fall of the hammer/ram and the number of blows for each 25 mm of penetration shall
be recorded, as well as the “Set”.
Hammer blows shall only be applied along the line of the pile axis and the impact surface shall
be perpendicular to the pile axis.
2.7.7.2.4 Set
Set limits shall be defined based on the working load, factor of safety soil condition and driving
equipment. During measurement of the “set”, exposed parts of the casing shall not be damaged
or deformed and the dolly, helmet, etc., shall be in good condition. Set, i.e. the achieved
penetration during driving and the temporary compression after completion of driving shall be
measured and recorded for each pile. The set shall be recorded either as the number of blows
resulting in a penetration of 25 mm or the penetration in millimetres achieved by imposing 10
blows.
2.7.7.2.6 Reinforcement
Once the casing has been driven to the design depth, the reinforcement cage shall be installed.
Reinforcement details shall be as for bored cast in situ piles.
2.7.7.2.7 Concreting
Concreting shall be facilitated by pump, flexible hose, tremie-pipe or by bucket, as per the
approved method statement. Concrete quality and consistency shall be provided in line with
guidelines for cast in situ piles.
526178307.doc Page 24 of 28
CIVIL WORKS
Civil Construction Works
Temporary casings shall be extracted while the concrete within them remains sufficiently
workable to ensure that the concrete is not lifted. Vibrating casing extractors must only be used if
their application has been accepted in the method statement.
When the casing is being extracted, a sufficient quantity of concrete shall be maintained within
the casing to ensure that pressure from external water or soil is exceeded and that the pile is
neither reduced in section nor contaminated.
Concrete shall be topped up as necessary while the casing is extracted until the required head of
concrete to complete the pile in a sound and proper manner has been provided. No concrete is to
be placed once the bottom of the casing has been lifted above the top of the concrete.
526178307.doc Page 25 of 28
CIVIL WORKS
Civil Construction Works
* Minimum value to be considered for routine testing only, for further testing, BS 4449 is to
be observed
* Epoxy-coated reinforcement as per ASTM A 775-01 shall be used for foundation piles only,
where there is no direct contact between the epoxy-coated bars used in the piles and non-
coated bars used in the pile caps and the tie beams.
Foundations shall be externally protected as indicated in the substructure water proofing system
of the technical specification.
2.7.9 Joints
All joints in concrete below ground shall be sealed by means of water bars.
Details of all waterbars, joint fillers, sealants and cover shall be fully described on all relevant
drawings and shall be approved by ADDC/AADC prior to materials being ordered.
Further reference is made to the below listed sample drawing, which is provided in the Drawings
Section.
Drawing No. Title
DWG AA CIV 04 05 Details of Expansion Joints
526178307.doc Page 26 of 28
CIVIL WORKS
Civil Construction Works
Cable and pipe channels at surface elevations shall be covered by prefabricated concrete covers,
designed for a traffic load SLW 60 according to DIN 1072. The length of each plate shall
normally not exceed 2.0 m. Provisions shall be made for lifting the cover plate by crane.
The edges of the recesses in walls and the edges of plates, pit recesses, lids, slabs, trenches,
trench covers, etc., shall have edge-protection of rolled steel sections, minimum size
40/40/4 mm. The steel sections shall be hot dip galvanised and –if required – in addition suitably
corrosion protected and finished as specified. The surface of the plates shall be plain trowelled to
receive dust proof hardener to be applied during concreting.
Concrete trenches, base and walls shall be protected externally as detailed for sub structural
concrete, and shall also be protected and sealed internally by the application of approved
pigmented sealant. Pre-cast concrete trench covers shall be protected on all sides by application
of two coats of approved clear sealer or approved dust proof hardener.
Compressive strength shall be in accordance with BS 1881, Part116 and BS 6319, Part 3
(epoxies), the cubes size shall be 100 mm, and the flexural strength shall be tested in accordance
with BS 4551.
Surfaces of the concrete base, which shall receive grouts shall be cleared of all defective
concrete, latency, oil, grease, other chemicals and dirt, and shall be roughened by chipping,
hammering or other techniques. The surfaces of all equipment bases or base-plates to be in
contact with the grout shall also be thoroughly cleaned of harmful matter, i.e. oil, grease, rust,
etc.
Before grouting, concrete surfaces shall be thoroughly wetted, if possible saturated with water.
When a dry grout is used, surfaces shall be pre-treated with cement slurry.
526178307.doc Page 27 of 28
CIVIL WORKS
Civil Construction Works
All shuttering, if any, shall be of adequate strength and securely fixed to withstand the pressure
of the grout and shall be sufficiently tight to prevent leakage.
Care shall be taken to ensure that the grout completely fills all voids to be grouted and is
thoroughly compacted and free of air pockets. Any areas or pockets, which are not to receive
grout, shall be properly sealed with an approved material.
The Bidder/Contractor shall take care that after the completion of grouting operations, all surplus
grout has to be removed and after a period of not more than 10 hours, the work shall neatly be
pointed and trowelled off and left in a workmanlike condition. Exposed edges of the grout shall
be adequately protected against damage and the effects of the environment during the airing
period.
526178307.doc Page 28 of 28