ITP &checklist For Installation and Testing of LV Cables
ITP &checklist For Installation and Testing of LV Cables
MIR: Material Inspection Request should be raised and inspected as per Approved Material Approval and sampling for testing (wherever applicable as per MARAFIQ Standard Specification) shall be followed prior to using / consuming the same
for construction / installation. Based on acceptance of the MIR material will be further issued to site for utilization.
Type or Inspection By
Description of Extent of Reference MARAFIQ
S.No. Characteristics Category Method of Acceptance Norms Format of Record Sub Cons Wabag/TPI /JACOBS Remarks
Activity Check Documents
Check Cons. QC Cons. QC Repres.
1.0 MATERIAL
As per approved MAR Visual MQ-SP-E-6018 As per Manufacturer’s
1.1 LV Cables & Drawings Major 100% Delivery Note P H P W W
Inspection RC Spec. 16120 Catalogue
As per
Storage, Handling Visual As per Manufacturer’s
1.2 As per approved MAR Minor 100% Manufacturer ICL -E-02-01 P H P W W
& Preservation Inspection
Catalogue
Catalogue
Continuity Test
As per Approved
Insulation Drawings Witness of MQ-SP-E-6018
1.3 Major 100% MQ-SP-E-6018 ICL-E-02-03 P H P H W
resistance Test Test ICL-E-02-03
MQ & RC Spec
(On Cable Reel)
2.0 INSTALLATION
As per Approved MQ-SP-E-6018
Cable Trench Visual Drawings Visual MQ-SP-E-6018
2.1 Minor 100% RC Spec. 16120 P H W W S
Inspection MQ & RC Spec. Inspection RC Spec. 16120
Approved Drawings ICL -E-02-01
Sand Bedding
As per Approved
Visual
MQ-SP-E-6018 MQ-SP-E-6018
Drawings
2.2 (before cable Major inspection 100% RC Spec. 16120 RC Spec. 16120 ICL -E-02-01 R H W W S
MQ & RC Spec.
laying) cable trench Approved Drawings
As per Approved MQ-SP-E-6018
Visual MQ-SP-E-6018
2.3 LV Cable Laying Drawings Major 100% RC Spec. 16120 ICL -E-02-01 P H P W W
MQ & RC Spec. inspection RC Spec. 16120
Approved Drawings
Continuity Test As per Approved Witness for MQ-SP-E-6018
2.4 Insulation Drawings MQ-SP-E-6018 ICL -E-02-03 P H P H W
Resistance Test (IR) MQ & RC Spec. Major
Cable Testing
100%
Approved Drawings
INSPECTION AND TEST PLAN (ITP) FOR INSTALLATION AND TESTING OF LV CABLES
Legend: RFI: Request for Inspection; MIR: Material Inspection Request; P: Perform; W: Witness; H: Hold; R: Review; S: Surveillance Perform (P) = For the Performer attendance at the site is a must, the signature is always on Inspection
Request and Checklist.
Witness (W) = Attendance at the site is expected for the Witness, the signature is required on check sheet of Inspection Request (IR) and Checklist, but if the signatory is not present to sign at the time, follow on work may proceed and the
document(s) to be signed off later.
Hold Point (H) = Attendance at the site is mandatory and signature is required on the check sheet of Inspection Request at the time of the inspection to release the following work.
Review (R) = Documents to be reviewed, no signature required on the Inspection Request or its accompanying documentation or records or test reports.
Surveillance (S) = Random attendance at site, no signature required on the Inspection Request (IR) or its accompanying documentation.
Note: Inclusion & exclusion of further items other than listed above can be addressed with an ammonium of this document or by separate submission (as per Project Scope of Work).
Project Name: EXPANSI ON OF SWTP 9 STAGE 6 PROJECT Project No.: Subcontractor: NIC
Description of Inspection:
To be verify the cable drum on reel Testing (Insulation resistance and continuity test) are
2 completed and documented.
Verify cable voltage rating, cable Size, core number, and conductor color coding with
6 respect to the cable schedule
11 Verify the cable arrangement and tagging as per specification and drawing.
Verify the spacing between other cables (LV, Control, Instrument &
15
Communication Cable) and UG Piping as per project specification and standard.
No joint shall be made in a single drum length of cable or in a single cable run without
16 special written Approval by the Client
17 Insulation resistance and continuity test are complete d and documented
19 Cable is free of kinks, neat and cable lay is accordance with design and specification.
20 underground cable route markers shall be installed along the route as per approved drawing
Comments:
Check proper terminal and crimping dies are used on cables and that MQ-SP-E-6005
8
crimping procedures is correct
9 Stress cone fitted as per manufacturer instruction MQ-SP-E-6005
Check cable type, size, color coding, location, installation, and routing MQ-SP-E-6005
14
Bend Radius in accordance with drawing and specification and vendor MQ-SP-E-6005
15
requirements
Cable termination neat, free of kinks, free of surface damage in cable MQ-SP-E-6005
16
jacket and evenly spaced
Termination support, clamping and banding and support spacing are in MQ-SP-E-6005
17
accordance with drawing and specification
Only the skilled personnel that have necessary qualification and MQ-SP-E-6005
18 experience shall carry out high voltage power cable termination and
joints.
Termination shall be performed using an approved shrink type MQ-SP-E-6005
19 termination kit of the correct size and type for the cable and in
accordance with the manufacturer’s instructions.
20 Cable Armoring shall be clamped and earthed at termination point MQ-SP-E-6005
Metallic sheaths, shield and armor are grounded in accordance with MQ-SP-E-6005
21
termination detailed
TERMINATION IDENTIFICATION – Identification of cables shall MQ-SP-E-6005
22 include the cable number and destination (e.g., load equipment tag
number) as per Specification.
Comments:
Project Name : EXPANSION OF SWTP 9 STA GE 6 PROJECT Project No. : . RFI No. :
Description of Inspection :
10
Comments :