Geometric Design RDM AppendixK Example Calculations
Geometric Design RDM AppendixK Example Calculations
Example Calculations
Appendix K includes example calculations for the Road Design Manual. The examples are numbered
to correspond with the associated chapter material, as described below.
• Sight Distance (Chapter 2)
• Horizontal Alignment (Chapter 3)
• Vertical Alignment (Chapter 4)
• Roadside Safety (Chapter 9)
• Quantity Summaries (Chapter 13)
Page 2
MDT Road Design Manual Appendix K – Example Calculations
Problem: Determine the horizontal clearance requirements for the horizontal curve using the desirable
stopping sight distance (SSD) value.
Solution: Chapter 2, Exhibit 2-1 yields a SSD = 570’. Using Appendix F, Equation F.2-1 for horizontal
clearance:
90° ⋅ S
M = R 1 - c⋅s
π ⋅ R
(90°)( 570 )
M = 1400 1 - cos = 28.91'
(π )(1400 )
The exhibit below illustrates the horizontal clearance requirements for the entering and exiting portion of
the horizontal curve.
Page 3
MDT Road Design Manual Appendix K – Example Calculations
Given: The grade line for a 60-mph design speed, two-lane, two-way rural roadway is shown
below. Give consideration to the effect of grades on SSD.
Problem: Determine the appropriate profile that meets minimum stopping sight distance, as well as
consider passing sight distance for additional refinement.
Solution:
1. Since the grades are 3 percent and greater, determine stopping sight distance adjusted for
downgrades. The 5-percent grade is the maximum of the downgrades, and will be used for
calculating SSD. Using Chapter 2, Equation 2.8-3:
V2
SSD Downgrades = 1.47 Vt +
a
30 − G
32.2
where:
SSD = stopping sight distance, feet.
V = design speed, mph
t = brake reaction time, 2.5 seconds
a = deceleration rate, 11.2 foot per second squared
G = gradient, feet/feet
60 2
SSD − 5% = 1.47 × 60 × 2.5 + = 623.4, Round ⇒ 624'
30[(11.2 ÷ 32.2 ) − .05]
Page 4
MDT Road Design Manual Appendix K – Example Calculations
2. Second, calculate the minimum length for the crest curve for the calculated SSD using Equation
4.4-1:
𝐴𝐴𝑆𝑆 2
𝐿𝐿 =
200(�ℎ1 + �ℎ2 )2
Where:
𝐿𝐿 = length of vertical curve, feet
𝐴𝐴 = algebraic difference between the two tangent grades, percent
𝑆𝑆 = sight distance, feet
ℎ1 = height of eye above road surface, feet
ℎ2 = height of object above road surface, feet
AS 2 2 × 624 2
+= = = 360.87'
200 × ( h1 + h2 )2 2158
3. Since this length is less than the SSD, Equation 4.4-2 can be used :
2
200��ℎ1 + �ℎ2 �
𝐿𝐿 = 2𝑆𝑆 −
𝐴𝐴
Where:
𝐿𝐿 = length of vertical curve, feet
𝐴𝐴 = algebraic difference between the two tangent grades, percent
𝑆𝑆 = sight distance, feet
ℎ1 = height of eye above road surface, feet
ℎ2 = height of object above road surface, feet
L = 2S −
200 × ( h1 + h2 )
2
The minimum curve length providing SSD is 169 feet, however the minimum curve length based
on L min = 3V would be 180 feet.
Page 5
MDT Road Design Manual Appendix K – Example Calculations
4. Prior to finalizing the crest curve length, we’ll determine the needed length for the sag curve
based on SSD:
Calculate the minimum length for the sag curve using Equation 4.4-7:
𝐴𝐴𝑆𝑆 2
𝐿𝐿 =
200ℎ3 + 3.5𝑆𝑆
Where:
𝐿𝐿 = length of vertical curve, feet
𝐴𝐴 = algebraic difference between the two tangent grades, percent
𝑆𝑆 = sight distance, feet
ℎ3 = height of headlights above pavement surface, feet
AS 2 5.5 × 624 2
+= = = 828.78'
200 × h3 + 3.5S 200 × 2 + ( 3.5 × 624)
For this example, both curves can be designed to provide SSD adjusted for the 5 percent
downgrade, using a 180-foot long crest and 840-foot sag curves (lengths rounded up for design),
without curve overlap.
Page 6
MDT Road Design Manual Appendix K – Example Calculations
Additional Discussion: Rather than using the minimum lengths of curve calculated, consideration
should be given to increasing the curve lengths to provide additional sight distance and reducing the
length of the 5 percent grade. Using the curve lengths shown below, the 5 percent grade occurs at station
9+50 only, and reduces from that point in each direction.
Using equation 4.4-2 with the 500-foot crest length and solving for S, stopping sight and passing sight
distances provided are 789.5 feet and 950 feet, respectively. Since both are influenced by the adjacent sag
curve, graphical analysis shows that actual minimum sight distances provided are 825 feet SSD and 1080
feet PSD, meeting the criteria for 60 mph.
Since the sag curve is longer than the stopping sight distance provided, the minimum SSD provided
can be found using equation 4.4-7, and is 670 feet whenever the vehicle and 1 degree rise in headlight
are on the sag.
It is worth noting that the downgrade of the roadway during the braking operation is much lower than the
5 percent used to calculate required stopping sight distance for the sag curve. It varies from -3.65 to -.9
percent at the steepest point that SSD is at its minimum for the curve shown above. In this respect, using the
SSD adjusted for grades is significantly more conservative when applied to sag curves compared to crest
curves, and may warrant closer analysis for situations where site constraints or impacts limit curve length.
Page 7
MDT Road Design Manual Appendix K – Example Calculations
Problem: Graphically determine if the combination of horizontal and vertical curves provides
Stopping Sight Distance (SSD) using CAD software.
Solution:
1. Draw the horizontal curve showing travel lanes, center of travel lanes, shoulders and guardrail.
2. Determine SSD for 60 mph from table in Exhibit 2-1. (SSD = 570')
3. Draw a sight line the length of the SSD as a chord across the curve from the center of near travel
lane to the center of near travel lane. If the line crosses the guardrail the curve may not meet SSD.
4. If the horizontal curve appears to provide a SSD line of sight, check the vertical profile for
meeting SSD (step 5). If it appears that the curve does not meet the SSD, then graphically check
the roadway profile with the guardrail profile shown to determine if the line of sight clears the
top of the guardrail (step 6).
6. To graphically check the SSD on the roadway profile with the guardrail, draw the profile for the
area of the horizontal curve which in this case includes a crest vertical curve. Draw the top of
guardrail profile at the correct height above the roadway profile.
a. The guardrail profile elevation = roadway profile elevation + (guardrail post height -
(distance from the face of rail to the center of the travel lane x the roadway cross slope
rate)).
b. Draw an element, to the same scale the profile was drawn, representing the SSD.
c. Draw the element with a horizontal line of sight line the length of the SSD and with a
vertical leg under each end, 3.5' high on the driver's eye height side and 2.0' high on the
object height side.
d. Place the element on the roadway profile with the legs touching the profile.
e. Move the element along the roadway profile through the vertical curve.
f. If at any point the guardrail profile line crosses the horizontal part of the element, the
vertical curve does not meet SSD.
This method can be used to check SSD and passing sight distance (PSD) on any combination of
horizontal/vertical curves with possible sight restrictions caused by backslopes, rocks, fences, buildings,
crops, etc. It can also be used to check SSD and PSD on multiple short vertical curves with little or no
tangent grade between them.
Page 9
MDT Road Design Manual Appendix K – Example Calculations
The line of sight for the SSD is crossed by both the face of guardrail horizontal alignment and by the top
of guardrail profile. Therefore, this combination of vertical curve, horizontal curve, and guardrail offset
does not meet SSD. The design team may consider widening the shoulder, eliminating the roadside
hazard that is requiring guardrail, using a larger radius horizontal curve, flattening the grades, and/or
using a longer vertical curve. The exhibit shown below illustrates an example of modifications required of
the profile to meet the SSD. It appears that increasing the horizontal curve radius or increasing the
shoulder width/guardrail offset may be more practical ways to achieve the required SSD in this case.
Page 10
MDT Road Design Manual Appendix K – Example Calculations
Given: Refer to the below crest vertical curve for given information.
Problem: For a design speed of 60 mph on a rural, two-lane, two-way highway, does the following
crest vertical curve meet minimum passing sight distance (PSD)? Give consideration to the
multiple curves.
Solution:
1. From Exhibit 2-10, the minimum passing sight distance for a design speed of 60 mph for the
above crest vertical curve is 1,000’. Using the passing sight distance of 1,000’ to calculate the
length of vertical curve when S is greater than L, use Equation 4.4-2:
L = 2S −
200 × ( h1 L h2 )2
A
The length of vertical curve required would be 600’. From inspection, the crest vertical curve
(Length = 400’) is less than the minimum required crest vertical curve (Length = 600’) when
designing for passing sight distance. If this crest vertical curve was connected by lengthy
tangents sections extending at +1.0% and -1.0%, instead of short tangent sections connecting to
sag vertical curves as shown above, then this crest vertical curve would not meet the minimum
passing sight distance for 60 mph design speed.
Consideration must be given for passing sight distance across multiple curves when they are
connected by short tangents. If you plot the height of eye (3.5’) at the high point of the crest
vertical curve and the height of object (3.5’) at the low point of both sag vertical curves, you can
graphically determine if this crest vertical curve meets minimum passing sight distance.
Page 11
MDT Road Design Manual Appendix K – Example Calculations
Refer to the above diagram for plotting sight distance across the crest vertical curve. Plotting the
low points of both sag vertical curves (at 3.5 foot object height) and the high point of the crest
vertical curve (at 3.5 foot eye height), you can visually see that the sight distance is sufficient. If
passing sight distance is sufficient at the low points, then it will also be sufficient at 1,000 feet.
In conclusion, the crest vertical curve does meet the minimum requirements for 1,000 feet passing
sight distance. If consideration was not given to passing sight distance across multiple curves,
then this crest vertical curve would not have met the minimum passing sight distance.
Page 12
MDT Road Design Manual Appendix K – Example Calculations
Given: Minor road intersects a 4-lane highway with a two-way, left-turn lane (TWLTL).
Minor road is stop controlled.
Design speed of the major highway is 50 mph.
All travel lane widths are 12 feet.
The TWLTL width is 14 feet.
Trucks are not a concern.
Problem: Determine the intersection sight distance (ISD) to the left and right from the minor road.
1. For the vehicle turning right from the minor road, the intersection sight distance (ISD) to the left
can be determined directly from Appendix F, Exhibit F-11. For the 50-mph design speed, the ISD
to the left is 480 feet.
2. For the vehicle turning left, the ISD must reflect the additional time required to cross the
additional lanes. The following will apply:
a. First, determine the extra width required by the one additional travel lane and the
TWLTL and divide this number by 12 feet:
b. Next, multiply the number of lanes by 0.5 seconds to determine the additional time
required:
c. Add the additional time to the basic gap time of 7.5 seconds and insert this value into
Appendix F, Equation F.3-1:
3. Check the crossing vehicle, as discussed in Appendix F, Section F.3.2.2. The following will apply:
a. First determine the extra width required by the two additional travel lanes and the
TWLTL and divide this number by 12 feet:
(12 + 12 + 14 )
= 3.2 lanes
12
Page 14
MDT Road Design Manual Appendix K – Example Calculations
b. Next, multiply the number of lanes by 0.5 seconds to determine the additional time
required:
c. Add the additional time to the basic gap time of 6.5 seconds and insert this value into
Appendix F, Equation F.3-1:
The 595’ for the crossing maneuver is less than the 635’ required for the left-turning
vehicle and, therefore, is not the critical maneuver.
Page 15
MDT Road Design Manual Appendix K – Example Calculations
Given: A rural two-lane, two-way, level roadway with a design speed of 60 mph.
Problem: Determine the associated avoidance maneuvers for the given roadway and determine the
decision sight distances for each of the avoidance maneuvers.
Solution: From the footnotes of Exhibit 2-12: This is a rural facility, the two avoidance maneuvers that
address rural roads are A and C.
From Exhibit 2-12: Using the design speed of 60 mph, the decision sight distances for a
rural roadway are:
Problem: If a spiral curve is warranted, determine the curve data for the spiral curve.
1. From Chapter 3, Section 3.2.1, a spiral curve is warranted on a rural State highway where the
superelevation, e, is greater than or equal to 7%. From Chapter 3, Exhibit 3-5, e is 7% for V = 70
mph and Rc = 3,000 feet, therefore, use a spiral curve.
2. The length of the spiral curve ( Ls ) is set equal to the superelevation runoff (L) length. From
Chapter 3, Exhibit 3-5, L = 210’ for V = 70 mph and R = 3,000 feet, therefore, Ls = 210 feet.
3. Calculate the curve parameters by using the spiral curve formulas provided in Appendix H.1.3:
6. Route Location and Design, Hickerson provides two methods for determining p and k
transition spiral values. The formula method from Hickerson’s Route Location and Design pg.
375 is shown below;
[ ]
p = +s 0.00145444 θ s − 1.582315 θ s 3 (10 )−8 + 1.022426 θ s 5 (10 )−13 ...
[ ]
k = +s 0.5 − 5.076957 θ s 2 (10 )−6 + 4.295915 θ s 4 (10 )−11 ...
Calculating using these formulas and the length of spiral and theta calculated above:
p = 0.612’ and k = 104.996’
Hickerson’s Route Location and Design also provides Functions of Unit Spiral Length Tables
for interpolating unit values p unit and k unit . These are calculated by setting Ls equal to 1, and
tabulated for integer values of θ s . Interpolating from the table p unit = 0.002917 and k unit =
0.49998.
The values above are for a unit spiral length and need to be adjusted for L s . Multiply the unit
values by L s to obtain the actual values for p and k.
p = p unit ( Ls ) = (0.002917) (210) = 0.612473’ rounding p = 0.612’
Therefore:
Ts = (3000 + 0.612) tan (15/2) + 104.996’
Ts = 500.034'
Es = 26.504’
Es = 26.50’(rounded value)
Given: ∆ = 7°00’00”
R = 5,700 feet
e max = 8%
PI Station = 154+56.42
Design Speed = 60 mph
Refer to Appendix H.2.1 for a diagram of the different elements of a circular curve and
Appendix H.2.2 for the associated definitions for these different elements.
Problem: According to Chapter 3, Section 3.2.1 use a circular curve when the superelevation is less
than 7%. From Chapter 3, Exhibit 3-5, e is 3% for V = 60 mph and R = 5700’, therefore, use a
circular curve. Calculate the curve parameters by using the circular curve formulas provided
in Appendix H.2.3.
∆ 7
L= 2πR = ( 2π )( 5700)
360 360
L = 696.3863'
R 5700
E= −R= − 5700
cos( ∆ / 2) cos(7 / 2)
E = 10.6515'
LC = 695.9533'
M = 10.6316'
Given: A two-lane, two-way, rural roadway with a design speed of 45 mph and the following
reverse curves (circular):
Curve 1 Curve 2
PI Station = 27+27.45 PI Station = 46+47.67
∆ = 73° 08’ 53” RT ∆ = 61° 14’ 40” LT
R = 1,800 feet R = 1,050 feet
PC Station = 13+91.92 PC Station = 40+26.15
PT Station = 36+89.94 PT Station = 47+92.30
Problem: Calculate the reverse curve superelevation transition, assuming a continuously rotating
plane, between the two circular curves.
Solution:
1. Determine if the curves meet the criteria for superelevation transition by the continuous rotating
plane method.
Curve 1 requires a 5% superelevation (e1), with 110’ of Runoff (L1), and 44’ of Tangent
Runout (TR1) for normal superelevation development.
Curve 2 requires a 7% superelevation (e2), with 154’ of Runoff (L2), and 44’ of Tangent
Runout (TR2) for normal superelevation development.
The distance outside of the curves required for normal superelevation development is 70%
of the runoff for each curve + the runout distances. For these curves, normal superelevation
transitions between the curves would require:
The length of normal crown between transitions is 336.21’ – 272.80’ = 63.41’. The TR distance
for all superelevated curves with a design speed of 45 mph is 44’. The length of normal
crown section provided (63.41’) is less than twice the TR distance (2 x 44’ = 88’) and
therefore, it is not desirable to attain a normal crown section. The continuously rotating
plane method is applicable in this situation.
Note that the minimum tangent distance between these two curves would be 70% of the two
runoff distances, or 184.80’. Any tangent distance less than this would require either an
increase in the normal transition rate or locating more of the transitions on the curves if the
curves cannot be moved further away from each other. Either option requires approval of
Page 21
MDT Road Design Manual Appendix K – Example Calculations
the Highways Engineer as documented in the Alignment and Grade Review Report (AGR
Report).
2. Locate the stations of full superelevation.
For continuous rotating plane transitions, the points of full superelevation are held and the
transitions are combined into a continuous transition with a constant rate of change.
Points of full super elevation are determined normally, that is 30% of the standard runoff
distances onto each curve.
The point where the superelevation starts to transition from 5% RT (point A on the exhibit
below) is:
The point where the transition ends at full 7% superelevation LT (point C on the exhibit
below) is:
The total length of continuous superelevation transition (L REV ) is the distance between points
A and C.
The length of superelevation transition from 5% RT to level (L1’) is the distance between
points A and B.
e1 5
L1’ = × L REV = × 415.41 ’ = 173.09’
( e1 + e 2 ) (5 + 7)
For checking the superelevation at a given station (point X) within the transition, identify
whether the location is within L1’ or L2’. If the station is less than Station B, it falls within
L1’; otherwise, it is within L2’.
Determining the superelevation at a point can be useful in checking rollover and the effect
of cross slope on approach turning movements, drainage or other cross slope critical criteria,
and elevation/clearance for overhead structures.
In this example, if one wanted to determine the superelevation at Station 37+20.00:
37+20.00 is less than 38+30.03, therefore is located within the L1’ section.
Given: A four-lane, two-way, open roadway with a design speed of 55 mph and the following
reverse curves (w/ spiral transition):
Curve 1 Curve 2
PI Station = 314+76.54 PI Station = 323+93.50
∆ = 23° 30’ 00” LT ∆ = 21° 18’ 00” RT
R = 1,150 feet R = 1,500 feet
Problem: Calculate the reverse curve superelevation transition, using a continuously rotating plane
between the two curves with spiral transitions.
Solution:
1. Determine if the curves meet the criteria for superelevation transition by the continuous rotating
plane method.
Curve 1 requires an 8% superelevation (e1), with 312’ of Runoff (L1) which will coincide with the
Spiral Transition (L1 = L S 1), and 78’ of Tangent Runout (TR1) for normal superelevation
development.
Curve 2 requires a 7% superelevation (e2), with 273’ of Runoff (L2) which will coincide with the
Spiral Transition (L2 = L S 2), and 78’ of Tangent Runout (TR2) for normal superelevation
development.
Using spiral formulas found in Appendix H.1.3, the following parameters are calculated:
Curve 1 Curve 2
PI Station = 314+76.54 PI Station = 323+93.50
∆ = 23° 30’ 00” LT ∆ = 21° 18’ 00” RT
R = 1,150’ R = 1,500’
L s = 312’ L s = 273’
θ s = 7° 46’ 20” θ s = 5° 12’ 50”
p = 3.52464’ p = 2.06964’
k = 155.90436’ k = 136.46233’
T s = 395.84’ T s = 418.92’
∆ c = 7° 57’ 20” ∆ c = 10° 52’ 20”
L c = 159.68’ L c = 284.63’
TS Station = 310+80.70 TS Station = 319+74.58
SC Station = 313+92.70 SC Station = 322+47.58
CS Station = 315+52.38 CS Station = 325+32.21
ST Station = 318+64.38 ST Station = 328+05.21
The distance outside of the curves required for normal superelevation development is the sum of
the Tangent Runout distances:
The length of normal crown between transitions is 110.20’ – 156.00’ = -45.80’. This distance is less
than 2 times the TR length (2 x 78’ = 156’), and the continuous rotating plane method is applicable
in this situation.
2. Locate the stations of full superelevation.
For continuous rotating plane transitions, the points of full superelevation are held and the
transitions are combined into a continuous transition with a constant rate of change.
The points of full superelevation are the SC and CS of each curve, with the entire circular curve
section between these points at the full superelevation. The end of full 8% LT (point A on the
exhibit below) is the CS of Curve 1, Station 315+52.38 and the SC of Curve 2, Station 322+47.58 is
the beginning of full 7% super RT (point C on the exhibit below).
3. Determine the location of level roadway (point B on the exhibit below).
The total length of continuous superelevation transition (L REV ) is the distance between points A
and C.
The length of superelevation transition from 8% LT to level (L1’) is the distance between points A
and B.
e1 8
L1’= × L REV = × 695.20' = 370.77'
( e1 + e 2 ) (8 + 7 )
This point is not identified in the plans specifically, except in the cross sections, but it indicates
where the roadway surface drainage changes, and is helpful in determining the cross slope at any
point within the transition. From 319+23.15 the roadway drains left to right back on station, and
drains right to left ahead on station.
e2 7
L2’= × L REV = x 695.20’ = 324.43’
( e1 + e 2 ) (8 + 7)
For checking the superelevation at a given station (point X) within the transition, identify
whether the location is within L1’ or L2’. If the station is less than Station B, it falls within L1’;
otherwise, it is within L2’.
Page 26
MDT Road Design Manual Appendix K – Example Calculations
Determining the superelevation at a point can be useful in checking rollover and the effect of
cross slope on approach turning movements, drainage or other cross slope critical criteria, and
elevation/clearance for overhead structures.
321+00.00 is greater than 319+23.15, therefore is located within the L2’ section.
Given: Superelevation transition for horizontal curves in the same direction (broken-back curves).
The exhibit below represents the relative grade lines of each edge of the traveled way for a
roadway transitioning through two superelevated curves in the same direction:
When the standard transition lengths result in a normal crown (NC) section between the
curves less than 200 feet long, do not transition down to normal crown. Instead, transition
down to a section with less superelevation, but not less than the normal crown cross slope
that can be maintained for at least 200 feet.
Problem: Given the following alignment, determine the superelevation transition between the curves
assuming a 60 mph design speed, two-lane, two-way roadway rotated about the centerline,
and a normal crown of 2 percent:
Page 28
MDT Road Design Manual Appendix K – Example Calculations
Solution:
1. Determine the normal transition lengths and locations for each curve.
For a design speed of 60 mph, Exhibit 3-5 indicates that 27 feet of transition length is needed for
each 1 percent change in cross slope.
The first curve is circular, with 6 percent superelevation. For circular curves, 30 percent of the
runoff length is located on the curve:
Start of transition (6%) = [PT station] – 0.3(L) = [90+74.65] – 0.3(162’) = Sta. 90+26.05
For the second curve, the 8 percent runoff length is applied through the corresponding spiral
transition length (216 feet). The tangent runout distance (54 feet) back from the TS station is the
station where normal crown would end, and the transition to 8 percent superelevation begins:
If the length of NC section provided is 200 feet or more, standard transitions may be provided.
Otherwise, proceed on to Step 3. (A negative value, as in this case, indicates the distance that the
transition locations overlap each other.)
3. Determine the intermediate rate of superelevation that can be held for at least 200 feet between
transitions using the following equation:
where:
S’ = intermediate percent superelevation
NC = normal crown cross slope
200'−(− 39.09') 239.09'
S'= −2= − 2 = 2.43, round ⇒ 3%
2 × 27' 54'
Note: Round up to the next integer value equal to or greater than the normal crown cross
slope (2% is typical for paved roadways).
Page 29
MDT Road Design Manual Appendix K – Example Calculations
4. Determine the stations within the transitions where the superelevation is 3 percent:
Working from the end of each transition where NC would be provided, the distance, d, to the 3
percent superelevated section is calculated:
The figure below represents the relative grade lines for the edge of traveled way for this example.
These transitions would be indicated in the plans by the stationing callouts on the superelevated
typical section, rather than transitioning back and forth between typicals.
For example:
XX+XX.XX to 90+26.05 6% LT
90+26.05 to 91+07.05 Trans. 6% LT to 3% LT
91+07.05 to 93+37.96 3% LT
93+37.96 to 94+72.96 Trans. 3% LT to 8% LT
94+72.96 to YY+YY.YY 8% LT
Page 30
MDT Road Design Manual Appendix K – Example Calculations
Given: Δ = 40°
R1 = 600 feet
R2 = 250 feet
p = 5’
Refer to Appendix H.3.1 for a diagram of the different elements of a compound curve.
Solution: Use the compound curve formulas from Appendix H.3.2 to calculate the curve parameters:
T1 = 92.81'
R − R2 − p −1 600'−250'−5'
2. ∆ 1 = cos −1 1 = cos
R1 − R2 600'−250'
∆ 1 = 9.6963°
T = 151.7591'
T2 = 50.7036'
R2 + p 250'+5'
5. E= − R2 = − 250'
cos(∆ / 2) cos(40° / 2)
E = 21.3653'
40°
6. M = R 2 − ( R 2 cos (∆ / 2 − ∆ 1 )) = 250'− 250' cos − 9.6963°
2
M = 4.0316'
y = 8.5714'
Problem: The proposed alignment reduces the overall length of the alignment, creating a stationing
discrepancy at the end of the project. Determine a station equation to correct the stationing
discrepancy.
Problem: The proposed alignment increases the overall length of the alignment, creating a stationing
discrepancy at the end of the project. Determine a station equation to correct the stationing
discrepancy.
Note: This scenario can create an undesirable condition where project features can have coincident
stations (see culverts in figure above for example). See the following example for a solution to
this condition.
Page 34
MDT Road Design Manual Appendix K – Example Calculations
Problem: The proposed alignment increases the overall length of the alignment, creating a stationing
discrepancy at the end of the project. Determine alternate stationing for the proposed
alignment to correct the stationing discrepancy and to avoid coincident stations.
Note: This scenario corrects the undesirable condition where project features can have
coincident stations (see culverts in figure above for example). See the previous example
describing the undesirable condition.
Page 36
MDT Road Design Manual Appendix K – Example Calculations
Given: G 1 = -1.75%
G 2 = +2.25%
Elevation of VPI = 577.43’
Station of VPI = 15+00
L = 1,200’
Symmetrical Vertical Curve
Refer to Appendix H.4.1 for a diagram of the different elements of a symmetrical vertical
curve and Appendix H.4.2 for the associated definitions for these different elements.
Problem: Compute the vertical curve elevations for each 50-foot station. Compute the low point
elevation and stationing.
1. Draw a diagram of the vertical curve and determine the station at the beginning (VPC) and the
end (VPT) of the curve.
2. Use the symmetrical vertical curve formulas from Appendix H.4.3 to calculate the elements of
the vertical curve:
Where:
Left of VPI (X 1 measured from VPC): Right of VPI (X 2 measured from VPT):
(a) TAN E+EV . = VPC E+EV . + G1 X 1 (a) TA− ELEV . = VPT ELEV . − G 2 X 2
100 100
Z1 = X 12
(G 2 − G1 ) (G 2 − G1 )
(b) (b) Z 2 = X 22
200 L 200 L
3. Set up a table to show the vertical curve elevations at the 50-foot stations, substituting the values
into the above equations.
Tangent Grade
2 2 1
Station Inf. Elevation X X Z=X /60,000 Elevation
9+00 VPC 587.930 0 0 0 587.93
9+50 587.055 50 2,500 0.0417 587.10
10+00 586.180 100 10,000 0.1667 586.35
10+50 585.305 150 22,500 0.3750 585.68
11+00 584.430 200 40,000 0.6667 585.10
11+50 583.555 250 62,500 1.0417 584.60
12+00 582.680 300 90,000 1.5000 584.18
12+50 581.805 350 122,500 2.0417 583.85
13+00 580.930 400 160,000 2.6667 583.60
13+50 580.055 450 202,500 3.3750 583.43
14+00 579.180 500 250,000 4.1667 583.35
14+50 578.305 550 302,500 5.0417 583.35
15+00 577.430 600 360,000 6.0000 583.43
15+50 578.555 550 302,500 5.0417 583.60
16+00 579.680 500 250,000 4.1667 583.85
16+50 580.805 450 202,500 3.3750 584.18
17+00 581.930 400 160,000 2.6667 584.60
17+50 583.055 350 122,500 2.0417 585.10
18+00 584.180 300 90,000 1.5000 585.68
18+50 585.305 250 62,500 1.0417 586.35
19+00 586.430 200 40,000 0.6667 587.10
19+50 587.555 150 22,500 0.3750 587.93
20+00 588.680 100 10,000 0.1667 588.85
20+50 589.805 50 2,500 0.0417 589.85
21+00 VPT 590.930 0 0 0 590.93
1 The 60,000 value is calculated according to 200L/(G 2 -G 1 ) (200*1,200)/(2.25 – (1.75)) = 60,000.
Page 38
MDT Road Design Manual Appendix K – Example Calculations
L G1
To determine distance " XT " from VPC: XT =
G1 − G 2
L G12
ELEVLOW POINT = ELEV VPC −
(G2 − G1 )200
Elevation of the low point on the curve equals:
1,200' (− 1.75)
2
LG12
Elev.VPC − = 587.93'− = 583.34'
(G2 − G1 )200 (2.25 − (− 1.75))200
Page 39
MDT Road Design Manual Appendix K – Example Calculations
Problem: At Station 28+35, the new highway must pass under the center of an existing railroad which
is at elevation 669.00’ at the highway centerline. The railroad bridge that will be constructed
over the highway will be 4.0’ in depth, 20.0’ in width and at right angles to the highway.
What would be the length of the symmetrical vertical curve that would provide a 16.5’
clearance under the railroad bridge?
Solution:
2. Determine the station where the minimum 16.5’ vertical clearance will occur (Point P):
From inspection of the sketch, the critical location appears to be on the left side of the railroad
bridge. The critical station is:
1
STA. P = BR(DGE CENTERL(NE STAT(ON N (BR(DGE W(DTH )
2
20'
STA. P = [28 + 35] −
2
STA. P = 28 + 25
ELEV . P = 648.50'
D
TAN . ELEV . AT P = ELEV . VP( N G1
100
175
= 642.10 N (N 1.5 )
100
= 644.73'
− b ± b 2 − 4 ac
X=
2a
Page 41
MDT Road Design Manual Appendix K – Example Calculations
where:
X = Horizontal Distance: Measured from the VPC (or VPT) to any point on the vertical curve
(feet)
a = A = Algebraic Difference in Grade: The difference between the two tangent grades (G 1 -
G 2 ) (percent)
b = Z = Tangent Offset: The vertical distance from the tangent line to any point on the
vertical curve (feet)
c = D x Z = Product of D (distance from the VPI to the subject point, P) and Z (tangent offset)
(square feet)
X L D = L 2 or L = 2(X L D )
L = 2( X + D )
L = 2(564.44'+175')
L =1,478.88'
9. Check the critical point assumption from Step 2. Since the sketch is based on an assumed length
of curve, the low point of the curve is also at an assumed location. In this example, the tangent
grades of the curve are not “sketched” correctly. They indicate that the low point of the curve is
on the right side of the VPI. In fact, the low point is on the left side of the VPI, as the magnitude
of G 1 is less than that of G 2.
L G1
Using the equation for finding the low point of the curve (see example 4-1): XT =
G1 − G 2
The station of the low point of the sag is 28+94.37, which is on the right side of the center of the
railroad bridge station of 28+35.00. Therefore, the critical point assumption made in Step 2 is
confirmed. Proceed to the next step.
Note: If the low point station had been on the left side of the bridge centerline, the length of
curve required for clearance would need to be recalculated for the correct critical location on the
right side of the bridge. Completing the sketch as accurately as possible for the known elements
will lessen the likelihood of assuming the incorrect critical point, particularly for cases where the
overhead structure is much wider.
Page 42
MDT Road Design Manual Appendix K – Example Calculations
10. Determine if the solution meets the desirable stopping sight distance for the 55 mph design
speed. From Exhibit 4-5, the desirable K-value:
K = 115
From Equation 4.4-9, the minimum length of vertical curve which meets the desirable stopping
sight distance:
L M(N = KA
= (115 ) × 3.5
= 402.5'
Note: This would be rounded down to 1,450’ for recording on the plans.
Page 43
MDT Road Design Manual Appendix K – Example Calculations
Problem: Determine the clear zone distance for both sides of the roadway.
Solution: Using the procedure in Chapter 9, Section 9.2.2.2 for each side of the roadway:
1. For the left side of the roadway, the entire slope is flatter than 4:1, so the clear zone can be
determined directly from Exhibit 9-1.
2. For the right side of the roadway, the 3:1 slope is non-recoverable. The procedure in Chapter 9,
Section 9.2.2.2, Step 2 must be used.
3. Checking the recovery area beyond the toe, the slope of 10:1 is flatter than 4:1. This 10:1 slope is
then used to determine the clear zone distance required from Exhibit 9-1.
4. The recovery area beyond the toe is calculated by subtracting the 8 feet of recoverable slope
between the edge of traveled way and the hinge point from the 20 feet obtained in Step 3:
5. Since 12’ > 10’, 12’ will be used as the recovery distance beyond the toe. (Chapter 9, Section
9.2.2.2, Step 2c)
6. Using the 12 feet recovery distance beyond the toe, the total clear zone width is calculated by
summing the distance beyond the toe and the distance from the edge of traveled way to the toe:
Solution: Using the procedure in Chapter 9, Section 9.2.2.2 for each side of each roadway:
1. For the outside in each direction of travel, the slope is flatter than 4:1, so the clear zone can be
determined directly from Exhibit 9-1:
2. In the median, for the inside in each direction of travel, the inslope of 6:1 is flatter than 4:1, so a
clear zone distance can be obtained from Exhibit 9-1:
3. The toe of the backslope is located at the center of the median which is 22 feet (4’ + 18’) from each
inside edge of traveled way.
4. Since the toe is within the clear zone, the median toe must be checked for traversability. Using
Exhibit 9-10, the median is determined to be traversable.
Page 46
MDT Road Design Manual Appendix K – Example Calculations
5. The percentage of the clear zone available up to the toe of the backslope is computed:
22’ ÷ 32’ = 0.6875
6. This value is subtracted from Step 2 and multiplied by the adjusted backslope clear zone factor of
30 feet obtained from Exhibit 9-6:
(1 - 0.6875) x 30’ = 9.38’ (Clear zone distance required beyond the toe)
7. The total clear zone is obtained by adding the value from Step 6 and the distance to the toe:
8. This value is rounded up to the next foot, yielding a Total Median Clear Zone Width of 32 feet.
Page 47
MDT Road Design Manual Appendix K – Example Calculations
Example 9-3: Guardrail Length of Need for Obstacle Extending Beyond the Clear
Zone
Problem: Determine the length of need for guardrail on each side of the road on this end of the bridge
(obstacle extends to the edge of the clear zone).
Solution:
1. Using Exhibit 9-16 the runout length is obtained by linear interpolation between 50 and 60 mph:
L R = 185 feet
L O = L C = 34 feet
L 1 = 8 feet
L R = 185 feet
L O = L C = 34 feet
L 1 = 12’ + 8’ = 20 feet
NOTE: Some of the length of need will be covered by terminal end sections and the bridge
approach section. These lengths should be determined before computing the final length of rail
required for each side.
Page 49
MDT Road Design Manual Appendix K – Example Calculations
Problem: Determine if the bridge or the sign controls the barrier length and find the length of need for
guardrail on each side of the NB side of the highway.
Page 50
MDT Road Design Manual Appendix K – Example Calculations
Solution:
1. Using Exhibit 9-16 the runout length is determined to be 360 feet.
2. A non-flared design will be used. Equation 9.4-2 will be used to compute length of need.
b. The length of need for the bridge abutment wall is computed as follows:
L R = 360 feet
L O = L C = 32 feet (hazard extends beyond the clear zone)
L 1 = 4 feet
c. Guardrail must extend at least 315 feet from the abutment wall and 216 feet from the sign
support. Adding 216 feet to the 85 feet from the abutment wall to the sign support gives 301
feet, which is less than 315 feet, so the bridge drop-off is the controlling feature and the final
length of need is 315 feet from the abutment wall.
L R = 360 feet
L O = 10’ + 10’ = 20 feet
L 1 = 10 feet
b. The length of need for the bridge abutment wall is computed as follows:
L R = 360 feet
L O = L C = 32 feet (hazard extends beyond the clear zone)
L 1 = 10 feet
c. Guardrail must extend at least 247.5 feet from the abutment wall and 180 feet from the sign
support. Adding 180 feet to the 85 feet from the abutment wall to the sign support gives 265
feet, which is greater than 247.5 feet, so the sign is the controlling feature and the final length
of need is 265 feet from the abutment wall.
Page 52
MDT Road Design Manual Appendix K – Example Calculations
Problem: Determine the minimum overall length of culvert to make sure that the concrete edge
protection is out of the clear zone.
Solution:
2:1 Step Bevel Formula:
(sin ϕ (0.5𝐷𝐷 + 4′) × 2 + Total Clear Zone Width)
+ (2′ + 2𝑋𝑋 + 𝐻𝐻) × 2 = min. pipe length
cos ϕ
(sin 12° ((0.5 × 18′) + 4′) × 2 + (36′ + 12′ + 12′ + 36′))
+ (2′ + (2 × 4.5′) + 18′) × 2
cos 12ᶱ
= min. pipe length
(0.2079 × 13′) × 2 + 96′)
+ (29′ × 2) = min. pipe length
0.9781
101.4054′
+ 58′ = min. pipe length
0.9781
= 161.68', round to 162'
Page 54
MDT Road Design Manual Appendix K – Example Calculations
tZ
WS = W f +
1 − CZ
where:
WS = half width of subgrade, feet
W f = half width of finished grade, feet
t = total surfacing thickness at finished shoulder, feet
Z = numerator of side slope ratio
(e.g., Z = "6" for a 6:1 side slope)
C = crown, feet/feet (e.g., 0.02 for 2% cross slope)
Round the computed value for W s to the nearest 0.1’. Because of the rounding process, the side slope
through the surfacing courses will not be exactly 6:1, but the difference is negligible.
Page 55
MDT Road Design Manual Appendix K – Example Calculations
The second step is to establish the width of the intermediate surfacing courses. Compute each horizontal
course dimension proportionately to its thickness. The width at the top of any surfacing course is
determined by using the following equation:
(WS − W f )
WX = W f + t
t X
where:
WX = half width of top of intermediate surfacing course, feet
W f = half width of finished grade, feet
WS = half width of subgrade, feet
t = total surfacing thickness at finished shoulder, feet
t X = cumulative thickness of courses above WX at finished
shoulder, feet
Solution:
tZ
WS = W f +
1 − CZ
(1.8' )(6)
WS = 20.0'+
1 − (0.02)(6)
WS = 20.0'+12.27' = 32.27'
The second step is to establish the width of the intermediate surfacing courses, which is shown in
more detail in Example 13-2.
Page 57
MDT Road Design Manual Appendix K – Example Calculations
Given: t x = 0.80’
Problem: Using the values given in Example 13-1, determine the intermediate surfacing course half
width.
Solution:
(WS − W f )
WX = W f + tX
t
(32.3'−20.0' )
W X = 20.0'+ 0.80'
1.8'
W X = 20.0'+5.467' = 25.467'
Superelevated Sections.
To compute subgrade widths for superelevated sections, use the equations shown below:
Low Side
tZ
Wsl = W f +
1 − CZ
High Side
tZ
Wsh = W f +
1 + SZ
where:
Wsl = width from centerline to edge of subgrade on low side
of superelevation, feet
Wsh = width from centerline to edge of subgrade on high
side of superelevation, feet
Wf = width from centerline of finished grade, low or high side, feet
t = total thickness of surfacing at finished shoulder, feet
S = slope of superelevation, feet/feet (e.g., 0.07 for 7% superelevation)
Z = numerator of side slope ratio (e.g., Z = "6" for a 6:1
side slope)
C = cross slope of tangent typical section, feet/feet (e.g., 0.02 for 2% cross slope)
Round each computed value for Wsl and Wsh to the nearest 0.1’.
Divided Highways.
For both tangent and curved sections of divided highways, compute the subgrade widths left and right of
centerline as follows:
Page 59
MDT Road Design Manual Appendix K – Example Calculations
Tangent
tZ
WS ( median) = W f ( median) +
1 − CZ
tZ
WS ( outside) = W f ( outside) +
1 − CZ
Curve
tZ
WS ( median high side ) = W f ( median) +
1 + SZ
tZ
WS ( outside high side ) = W f ( outside) +
1 + SZ
Solution:
a. Ensure that the right-of-way width is sufficient (i.e., far enough from the shoulder to get
the full IRT installed without encroaching onto private property). The width required
from the edge of the roadway (face of rail) to the R/W line is equal to the IRT radius +
26.5 feet.
b. Determine the best fit IRT radius based on the approach radii, R/W availability, and the
location requirements of the normal run of w-beam. Minor adjustments to the approach
stationing or minor grading along the edge of the approach may be necessary to fit the
IRT to the approach without impacting turning movements or extending beyond the R/W
limit.
d. The following table lists available IRT radii and associated pay limits:
8’ 12.5’ 37.5’
Given: W-beam guardrail is warranted between Stations 9+90 and 15+00 on the left side of a two-way
roadway. There are no roadway approaches or other features that influence the guardrail
location.
Problem: Determine the beginning and ending stations and the length of rail for payment.
Solution:
1. [15+00.00] – [9+90.00] = 510.00’ actual length of need
4. Per the detailed drawings, 37.5’ of each OTS provides full strength for length of need.
6. In this case, no features have been identified to restrict guardrail placement. Locate the guardrail
to provide the additional length on the advancement side of the adjacent traffic. Since the rail is
on the left side of the roadway, adjacent traffic is moving opposite the direction of increasing
stationing, therefore start the calculation from the lower station value:
[9+90.00] - 12.50’ (the portion of the OTS outside of the length of need)
= 9+77.50 Beginning Station
Additional discussion: If the rail had been on the right side, providing the additional length on the
advancement side of the adjacent traffic would be calculated from the end station of the length of need
working back on stationing (15+12.50 back to 9+75.00).
Page 64
MDT Road Design Manual Appendix K – Example Calculations
Given: A bridge replacement project (on a two-way, two-lane highway) calls for guardrail lengths of
need from the end of the bridge rail of 141.5 feet and 76.2 feet, for the approach and departure
sides respectively. (See Example 9-3). The roadway width is 40 feet (12 foot lanes and 8 foot
shoulders) and R/W is 80 feet from centerline on each side of the road. There are private
approaches needed on each side of the roadway at station 123+80. The approaches are currently
designed 24 feet wide with 25 foot radii per MDT Detailed Drawings and cannot be relocated
beyond minor adjustments.
Problem: Determine appropriate w-beam guardrail treatment for the end of the bridge with the private
approaches, and determine the station limits and quantities for the guardrail.
Solution:
1. Determine the appropriate treatment for the bridge approach rail connecting to the bridge rail
on the right side:
Calculate the available distance from the end of the bridge rail to the beginning of the
approach radius.
Approach station [123+80.00] – 12’ half approach width – 25’ radius = begin of
radius station [123+43.00]
Begin of radius station [123+43.00] – end of bridge rail station [122+36.75] =
106.25’ of available space.
Page 65
MDT Road Design Manual Appendix K – Example Calculations
Divide the departure length of need by the standard increment to determine the full
strength guardrail needed.
76.2’ ÷ 12.5’/section = 6.096 sections, Round ⇒ 7 sections of rail for length of need
Since the last 12.5’ of a W-beam OTS is not full strength, add 12.5’ to the needed guardrail
length.
(7 sections x 12.5’/section) + 12.5’ = 100.0’
100.0’ of needed guardrail < 106.25’ of space available, therefore use standard w-
beam approach rail with a Bridge Approach Section and OTS.
The guardrail on the right side will be from station 122+36.75 to 123+36.75 and will
include one 25-foot Bridge Approach Section (bid per each), one 50-foot OTS (bid per
each), and 25 feet of w-beam.
2. Determine the appropriate treatment for the bridge approach rail connecting to the bridge rail
on the left side:
Calculate the available distance from the end of the bridge rail to the beginning of the
approach radius.
Begin of radius station [123+43.00] – end of bridge rail station [122+59.75] = 83.25’
available. This distance is long enough to allow the minimum length of blunt end
protection with an OTS for the bridge end (25’ Bridge Approach Section and 50’ OTS).
However, this option does not provide the calculated advancement length needed for
shielding the crossing hazard.
Determine a bridge approach rail solution using an IRT:
The edge of the current approach station is [123+80.00] – 12’ half width of
approach = [123+68.00]
The space for rail with an IRT = [123+68.00] - [122+59.75] = 108.25’
IRT radii are available in increments of 8 feet, up to 32 feet. Subtracting each radius from the
space available leaves available lengths of tangent guardrail of 100.25’, 92.25’, 84.25’, and 76.25’.
The closest fit configuration for each IRT radius option is shown below (approach end is at the
R/W limit for all cases).
Page 66
MDT Road Design Manual Appendix K – Example Calculations
For this example, all options fit within the available R/W and could potentially be used with
minor widening, narrowing, and/or relocation of the approach location. In this instance, the 24
foot radius was selected (with the approach being relocated 4 feet ahead on station), based on the
anticipated traffic needs. Selecting this option does not require any additional width in guardrail
widening in front of the rail or a reduction in approach radius. It also provides nearly 10 feet of
space between the R/W line and the end of rail for maintenance/utility access.
Determine stationing:
[122+59.75] + 25’ (bridge approach section) + 62.5‘ (normal run w-beam) + 24’ (IRT radius)
= [123+71.25]
The guardrail on the left side will be from station 122+59.75 to 123+71.25 and will include
one 25-foot Bridge Approach Section (bid per each), 62.5 feet of normal run w-beam, and
62.5 feet of Intersecting Roadway Terminal.
Page 67
MDT Road Design Manual Appendix K – Example Calculations
Problem: Determine the beginning and ending stations for the cable rail, the length of rail for payment,
and the number of terminal sections needed and measured for payment.
Solution:
2. 5,500.0’ ÷ 2000’ (maximum run length) = 2.75, Round ⇒ 3 runs of rail needed
Problem: Determine the beginning and ending stations and the length of rail for payment.
Solution:
1. [([32+75.00] – [17+50.00]) - (2)(33.0’ of full strength rail per OTS)] ÷ 18’ increment = 81.06 sections,
Round ⇒ 82 sections of Box Beam guardrail
3. Because of the approach located at station 33+40, locate the rail as far back on stationing as
possible to reduce impacts to sight distance and turning maneuvers associated with the
approach.
[32+75.00] + 15.2‘ of OTS outside of length of need = 32+90.20 Ending Station
[32+90.20] - 1476.0‘of standard run rail - (2 x 48.2’ OTS length) = 17+17.80 Beginning Station
Pavement section:
0.30’ Plant Mix
1.20’ Crushed Aggregate Course
2.00’ Special Borrow
Problem: Determine the amount of finish grade control staking required for the project.
Solution: Calculate the course mile of finish grade control staking for the mainline, ramps and
intersecting roadway (round up to nearest 50-foot increment):
FACTOR
FACTOR
SHRINK
SWELL
DOUBLE DOUBLE ADJ.
AREA AREA ACTUAL ACTUAL EMB. +
AREA AREA EXC.
0+00.0 0 0
11.6 0 65.2 0 14
0+11.6 0 65.2
7.5 0 125 0 17
0+19.1 0 59.8
2.5 0 137.8 0 6
0+21.6 0 78.0
14.1 0 78 0 20
0+35.7 0 0
10.9 109.4 0 22 0
0+46.6 109.4 0
12.5 132.8 0 31 0
0+59.1 23.4 0
TOTAL 53 * 57 *
STATION EROSION
TOPSOIL
SEED FERTILIZER CONDITION CONTROL REMARKS
MULCH
SALVAGING SEEDBED BLANKET
& PLACING (LONG-TERM)
FROM TO NO. 1 NO. 2 NO.3 NO. 1 NO. 2
53+81.86 83+00.00 1,450 4.4 2.0 0.2 4.4 2.0 4.6 2.0
83+00.00 113+00.00 2,348 0.2 6.2 2.1 0.2 6.2 2.3 6.2
93+52.02 94+01.48 106 BRIDGE END GRADING EROSION CONTROL
113+00.00 143+00.00 721 0.3 1.0 0.3 1.3
143+00.00 170+19.65 767 5.2 1.5 5.2 6.7 INCLUDES CONNECTION TO PTW
TOTAL 5,286 10.1 8.2 4.8 10.1 8.2 14.9 8.2 106
Solution: Topsoil replacement is a grading quantity that is needed to adjust the earthwork on a project to
account for the topsoil that is salvaged from the roadway construction limits prior to the general grading
operation. This material was in place when the project was surveyed and the digital terrain model (DTM)
was created, and is included in the line representing the existing ground to which cut and fill quantities
are measured. The removal of this material prior to grading has the effect of lowering the existing
ground line wherever it is removed, thereby underestimating the amount of embankment needed in fill
sections, and overestimating the amount of material generated from cut sections. For either condition,
embankment material must be added to the earthwork run to account for the topsoil that is removed.
To estimate the amount of embankment required for topsoil replacement, the quantity of topsoil
salvaged needs to be adjusted by the project shrink factor. The Standard Specifications require that the
contractor salvage enough topsoil from within the construction limits to dress the finished slopes with
four inches of topsoil. For this reason, the depth, quality and distribution of the topsoil on the existing
slopes is somewhat irrelevant. Similarly, areas where topsoil is not removed (e.g. Foundation Treatment
areas) do not typically need special consideration when calculating Topsoil Salvaging and Placing
quantities. The Topsoil Salvaging and Placing quantities have already been calculated for this example
and are indicated in the summary frame above. Although the Summary is Topsoil & Seeding, the
quantity splits are intended to aid in calculating topsoil replacement grading quantities, and to show the
distribution of these quantities more uniformly in the mass diagram and earthwork run.
Since grading on this project is measured as Unclassified Excavation, an earthwork run and mass
diagram are developed. The unadjusted quantities of topsoil salvage should be entered into the
earthwork run as point additional embankment quantities for each section, and adjusted according to the
project shrink factor. It isn’t critical whether the “from” or “to” station is used to identify the locations
where these quantities are added in the earthwork run, only that the method used is consistent for the
project.
Page 78
MDT Road Design Manual Appendix K – Example Calculations
ADDITIONAL GRADING
cubic yards
SUBTOTAL ~ ~ ~
Note: # EXCAVATION QUANTITIES-MATERIAL UNSUITABLE FOR ROADWAY EMBANKMENTS
Additional discussion: For projects measuring grading as Embankment-in-Place, the entire quantity of
topsoil salvaged is identified on a separate line of the Grading Frame, and identified as “TOPSOIL
REPLACEMENT” in the Remarks column. For these projects, no adjustments to grading are made, and
additional grading items are not included in the earthwork run.