2.IEC Short Circuit
2.IEC Short Circuit
Procedure
1. Open LF-Example1 OTI file shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 1 of 18
ETAP Workshop Notes
5. Select “Fault 3Phase” from Short Circuit study case and proceed to Edit Study Case
option as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 2 of 18
ETAP Workshop Notes
ii. Study case editor page ‘standard’ for selection of standard user defined C factor or
Voltage factor & X/R method:
Select IEC standard for performing short circuit calculation as per standard IEC-60909.
C factor default values are as per standard IEC-60909, it is Ok as in ETAP, unless this need to be
changed. For the user defined C factor check box shown below need to be clicked.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 3 of 18
ETAP Workshop Notes
In peak short circuit current calculation, two separate methods are used for non-meshed and
meshed networks.
For three-phase short circuits fed from non-meshed networks, the contribution to the peak short-
circuit current from each branch can be expressed by:
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 4 of 18
ETAP Workshop Notes
Fig (i)
In meshed networks, the above equation (equation no: 54 of IEC 60909 standard) of determining
peak fault current shall be used with k determined using one of the following methods A, B, or C.
The value of the k factor is determined by multiplying the k factor by a safety factor of 1.15,
which covers inaccuracies caused after obtaining the R/X ratio from a network reduction with
complex impedances.
As long as R/X remains smaller than 0.3 or X/R smaller than 3.33 in all branches, it is not
necessary to use the factor 1.15. It is not necessary for the product 1.15 * k(b) to exceed 1.8 in
low-voltage networks or to exceed 2.0 in medium- and high-voltage networks.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 5 of 18
ETAP Workshop Notes
The value of the k factor is calculated using a frequency-altered R/X. R/X is calculated at a lower
frequency and then multiplied by a frequency-dependent multiplying factor.
In this method, an equivalent impedance Zc, of the system as seen from the short-circuit location
is calculated assuming a frequency& = 20 Hz (for a nominal frequency off = 50 Hz) or fc = 24 Hz
(for a nominal frequency off = 60 Hz). The R/X or X/R ratio is then determined according to
below equations:
where
Zc = Rc + jXc is the equivalent impedance of the system as seen from the short-circuit location for
the assumed frequency fc;
Rc is the real part of Zc (R, is generally not equal to the R at nominal frequency)
Xc is the imaginary part of Zc, (Xc is generally not equal to the X at nominal frequency).
Depending on the product f * t; where f is the frequency and t is the time, the equivalent
frequency fc should be as follows:
Method C is most appropriate method adopted in most cases of IEC 60909 short circuit
calculations.
The alert page of briefcase for critical and marginal alert display is shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 6 of 18
ETAP Workshop Notes
7. Select “All Buses” and Click “<<Fault” to create a fault on the selected buses.
8. To study different faults for the selected buses, click “60909” & give name for Output
File Name as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 7 of 18
ETAP Workshop Notes
10. Go to Display Options to change the type of fault on the selected buses as shown below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 8 of 18
ETAP Workshop Notes
12. To view the short circuit report, go to Report Manager in Short Circuit Toolbar and
Click on Result & select Short-Circuit Report as shown below. Select the type of file
format to view it.
13. Sizing of HV and LV switchgear can be done from short circuit results obtained from
3-Phase Device Duty (IEC 60909) in Short Circuit toolbar.
14. Run 3-Phase device duty calculation and check Peak Short Circuit Results as shown
below.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 9 of 18
ETAP Workshop Notes
15. Proceed to Alert View in short circuit toolbar for list of alerts for inadequate sizes of
breakers.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 10 of 18
ETAP Workshop Notes
In order to ensure that an overtly conservative approach is not taken, that could increase
equipment requirements leading to weight and space constraints on mobile or fixed
offshore installations, IEC 61363 standard is also being used for short circuit studies in
shipping and offshore industry as per the title of the IEC 61363 standard which is
‘Electrical installations of ships and mobile and fixed offshore units – Part 1:
Procedures for calculating short-circuit currents in three-phase a.c.’
The IEC 61363 standard is known to evaluate short-circuit currents within sufficient
accuracy that is suitable for practical applications after allowing for generator pre-
loading and appropriate fault current attenuation based on actual data of generator
impedance and time constants.
IEC 60909 is used for both meshed and unmeshed systems whereas IEC 61363 is
applicable only for unmeshed systems.
To start the IEC-61363 calculation in Etap set the briefcase with revised C factor value
which need to be use for IEC 61363 calculations. This is because the current version of
ETAP software for Short Circuit calculation using IEC 61363 is only suited for
unloaded generator fault calculation. For loaded generator cases, the multiplying factor
for voltage behind Xd’’, Xd’ have to be worked out separately and adjusted as a
correction factor (by suitable adjustment of c factor) on the ETAP IEC 61363 results of
Ik’’ (subtransient Id’’& Ipeak) and transient Id’ for evaluating the net peak make short
circuit current and asymmetric break short circuit current.
IEC 61363 calculates and plots of iinst, Iac rrms, idc, idc (%) & ienv at various instants of
time from 0 to selected plot time in the study case editor (as shown below) in the Etap
14 and above version.
Note: In previous versions of Etap the plot time was fixed to 0.1 sec.
Typically 0.1 sec plot time is adequate unless the CB opening time is more than that 0.1
sec. However the plot step is fixed at 1msec.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 11 of 18
ETAP Workshop Notes
C factor for ETAP IEC 60909 is taken as maximum value (1.05) as mentioned in IEC
60909 and this also is seen to match with the Ik’’ of ETAP IEC 61363 as seen in the
table above. Results from ETAP IEC-61363 have been multiplied by appropriate
factors to account for appropriate voltages behind Xd’’, Xd’ and Xd with bus/generator
terminal voltage as 1 p.u. This is required because ETAP’s IEC 61363 software module
does not consider change in fault level due to generator loading. No such factors will be
applicable for motor contribution on ETAP IEC 61363 results with the main bus
voltage maintained at 1 p.u. Typically average factor of 1.15 have been consider for
IEC -61363 calculation in this exercise. However this has to be worked out separately.
To achieve this c factor for calculation can be set as 1 and factor of 1.15 need to be
applied on all the SC current results, for the present version of Etap.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 12 of 18
ETAP Workshop Notes
16. To see the plots of short circuit currents, run transient short circuit as per standard IEC-
61363.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 13 of 18
ETAP Workshop Notes
18. The plots of i, Iac rrms, idc, Idc (%) & I env for bus 1 are as below. This is graphical
representation of the fault currents.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 14 of 18
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 15 of 18
ETAP Workshop Notes
19. However, to check the tabulated results of above fault currents, go to Report Manager
>> Result >> Short Circuit Report. The below results are shown for bus 1.
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 16 of 18
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 17 of 18
ETAP Workshop Notes
This document is confidential and proprietary to ETAP / ETAP Automation and may not be reproduced, published
or disclosed to others without written authorization of ETAP / ETAP Automation. All Rights Reserved. Page 18 of 18