Rig Move Operational Process Flowchart New A4

1) The document outlines the rig move process from planning through execution and demobilization. It includes pre-job meetings, developing rig move packages, pre-move meetings, loading and transporting the rig equipment, obtaining clearance, and de-briefing. 2) Key aspects of the planning include developing rig move packages, conducting pre-job meetings with stakeholders, surveying roads, and preparing rig move plans including load sequences and critical lift plans. 3) Execution involves meetings to review safety, loading the rig equipment according to the sequence, supervision by field supervisors, and transport. Demobilization consists of clearing equipment and personnel, and conducting a de-briefing meeting.

Uploaded by

aymenmoataz
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
423 views

Rig Move Operational Process Flowchart New A4

1) The document outlines the rig move process from planning through execution and demobilization. It includes pre-job meetings, developing rig move packages, pre-move meetings, loading and transporting the rig equipment, obtaining clearance, and de-briefing. 2) Key aspects of the planning include developing rig move packages, conducting pre-job meetings with stakeholders, surveying roads, and preparing rig move plans including load sequences and critical lift plans. 3) Execution involves meetings to review safety, loading the rig equipment according to the sequence, supervision by field supervisors, and transport. Demobilization consists of clearing equipment and personnel, and conducting a de-briefing meeting.

Uploaded by

aymenmoataz
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

I I I 4

Rig Move Plan Rig Move Execution Demobilization

u u

Start Start Start

Pre-Job meeting includes the


following: ', 1
• Aramco Client (Company
Report toTool • Final Instruction from RigTool Pusher
Foreman)
Meet with the Pusher, QHSE Fleet Assembled and Overview of Overall performance.
• Well-site Engineer
Client/Company Inductionand after final setting of i--- -- -- -- • Preparation of all equipments for
• RigTool Pusher Minutes of Meeting include:
Representative Submissionof Rig Equipment sequence of demobilizingback
• Truck Pusher • JSA Documents/
• Safety Representatives • Load Sequence Requirements
to Yard.
Vehicle assignment to

Rig Move Package Includes:


• Full DescriptionofTruck/
Preparation of Rig •
load specific
Critical Lift plans ,, Rig Move Clearance includes :
• Client Satisfactory Report
Move Package (Fleet Permit to Work if
Trailer units Document applicable FieldSupervisorObtain • Signingof work ticket for work
• Crane and Forklift Units / Summary) • Daily Update of work Pre Move Safety
final ClearanceandJobf---- - - - - - , accomplishment
• Riggers, Drivers, Operators • Journey managementI Meeting
Completion Document
fromRigManager
• Clearance/ release form for all
• Field Supervisors/Truck Convoy Plan equipmentand manpower -coming
Pushers from Client.
- -

'
• Safety representatives I
Demobilized • Review of performance rendered in
• Certificates I Inspection • Designatedload list the rig move with all concerned
• LicensesI H2S cards Pre-Move Meeting initiated with close personnel
Supervision and assistance • Implementationof actions points to
Road Survey Meeting Includes the following: by Field Supervisor / Truck
• Load of Rig Debriefingmeeting be taken from learned lessons to
Committee: Expected date of release of Pusher I QHSE Officer.
Equipment by at Head Office improve performance of Rig Move
• Truck Pusher Rig • Critical Loads loaded by -
• Sequence in Load operations.
• Well Site Locationof old and new site
Road survey
Crane in Single I tandem
List • Additional training I Instructions or
Engineer Pre-Move Inspection Lift Supervised by Certified supplementary process and
• Distance of move
.,
RigTool Check of all Rigger 1 with Liftingplan
• procedures for work flow.


Pusher Required manpower Equipment and provided and approved by Quality and HSE Performance.
• Aramco Client Load list Requirements Aramco Client I Tool Pusher Move to New Site
I

• QHSE Officer • Plan and sequence of • Proper re-assessment, service and


Loading,transportingand Daily Report includes: Re-assessment and
maintenance in preparation for next
unloadingRig equipments • Load List Completionand maintenance of all
work. Coordinationfrom Operations
Necessary documents for Transported to new location Daily Activity Report vehicle units
Pre-Job Safety I Coordinator, mechanic and drivers to
adherence to requirement/ • Obstacle encountered - submitted to Rig
Meeting - Final re-condition their respective unit for
policy Debriefingprior to • Unsafe Acts I Hazards/ Office by 1900 Hrs.
full operational status.
Critical lifts and setting Mobilization Conditionswith their report •
• Possible obstacles/ JSA • Incident encountered -
Check / Follow Up PM
• Maintaining a safe
Preparations include:
mobilizationof all trucks
Preparation and checkingto

and equipment
maintain operational function Re-checkingof Preparation of Rig • Regular Safety Meeting and Updates
PPE Package for Next Rig • Update of personnel requirements I
Mobilization to Rig
Site Location
and report if any anomaly/
problems is raised in the units
- vehicles, trailers,
crane and forklift Move after Cleared - - - - - - documents/ training when applicable
to the mechanic for next job units. Refuelingof Service and • Maintenance of all equipment cleared from
all equipment. Maintenance of Fleet Mechanic
task.
• Re-checkingof Fleet Safety requirements
for next Mobilization.

I .,
End End End

ADDITIONAL NOTES PROCEDURE TITLE PROCEDURE NUMBER


Rig Move Operational Process
ISSUE DATE CHANGE REF CHANGE DESCRIPTION INDEX ISSUED BY SIGN APRVD BY SIGN

PAGE 1 OF 1