ACI 352-13 Guide To The Code For Evaluation, Repair, and Rehabilitation
ACI 352-13 Guide To The Code For Evaluation, Repair, and Rehabilitation
JOSÉ (PEPE)
IZQUIERDO ENCARNACIÓN
BSCE, MCE, PE, HACI
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
ACI 352-13 Code and
Guide 2
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
ACI 352-13 Repair Code
3
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Applicability
4
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Flowchart
Design Basic
Code
5
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Responsibilities of the LDP
6
• Evaluation
• Specifying repair materials and details
• Developing quality assurance programs covering the
repairs
• Advising the owner on future maintenance requirements.
• Report identified unsafe structural conditions to the owner
and jurisdictional authorities
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
4.2 Compliance method
7
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Preliminary evaluation
8
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
5.2—Load factors and
load combinations 10
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
STRUCTURAL EVALUATION
11
Structural Assessment Structural Analysis
Section 6.2 Section 6.5
Material Properties
Section 6.3 Analysis of Repaired
Serviceability
Design
Section 6.6
Section 6.7
Test Methods
Section 6.4
If determined by the Seismic Analysis of
structural assessment Repaired Structure
Section 6.7.4
that the strength of a
Destructive Non Destructive structure is not in
Testing Testing question, structural Strength Evaluations
analysis is not Section 6.8
Strength Evaluations required.
Section 6.8
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
12
Methodology
Evaluation
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Requirements for
Structural Evaluation 13
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural assessment
14
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Existing Condition
15
• Physical Condition
• Load Paths
• As-built Data
• Structural Members – Existing Conditions
• Material Properties
• Additional Considerations
• Seismic Resistance Assessment
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Material properties
16
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
In place testing
17
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Analysis
19
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural serviceability
20
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Strength and serviceability
24
• Designed For:
• Adequate Stiffness to limit
• Vibrations
• Cracking
• Deformations
• Considerations given to:
• In place internal forces
• Some forces and deformations may be
locked in by repair
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Bond
26
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Materials…
27
Issues to consider
• Corrosion
• Mechanical Damage
• Delaminated Concrete
• Strength
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Repair using supplemental
post-tensioning 29
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Repair using fiber-reinforced
polymer (FRP) composites 30
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
DURABILITY 31
Compatibility
Structure
Repair Environment
Materials
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Durability
32
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Inspection
33
Required
Inspections
Partial Mixing/Placing
Forms and Re‐ Construction Construction Post
Demo/Surface Placing Anchors Curing Repair
shoring Sequence/Erection Loads Tensioning
Prep Materials
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
34
Project Examples
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
352 Guide Example Projects
35
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
36
Example #1
Typical Parking Garage Repair
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Parking Example
37
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Situation
39
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Governing Building Codes
40
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Existing Conditions
41
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Docuemented Distress
42
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Reinforcement
44
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Strength of
existing structure 45
Effect of unsounded
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Strength of existing structure
47
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Strength of existing structure
48
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Design Basis Code
49
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural Evaluation
50
Concrete strength.
• Concrete core samples were extracted and tested in compression
to determine the slab concrete compressive strength. The strength
values were consistent with the strength assumed in the preliminary
analysis.
Reinforcing steel layout and strength.
• Reinforcing steel spacing and cover were determined with ground-
penetrating radar and confirmed at exposed bars and exploratory
openings. Exposed reinforcing bars were examined for identification
marks that might indicate the steel yield strength. No marks were
found.
• Coupons were removed from reinforcing bars and tested in tension
to determine the steel yield strength. The strength values were
consistent with the strength assumed in the preliminary analysis.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Analysis
51
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Punching Shear
53
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural Repair & Durability
54
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• Chloride-contaminated concrete around the top
reinforcing mat is removed and replaced with
uncontaminated concrete with low permeability,
improving durability and reducing future maintenance. 55
• The new concrete will have similar or slightly enhanced
properties compared to the existing concrete.
Option 2
• After concrete removal work has been completed, the
exposed concrete surfaces will be cleaned and a suitable
bonding procedure will be used to attain the minimum
required bond strength and ensure composite behavior
under service loads.
• Existing reinforcing bars, except for those embedded in
columns, are removed and replaced with new epoxy-
coated reinforcing bars, replacing bars with reduced
cross-sectional area. Because the new bars are
uncontaminated and coated with epoxy, their resistance
to corrosion is much improved, improving durability and
reducing future maintenance of the slab system.
• Existing bars to remain are cleaned and coated with a
corrosion-inhibiting material.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• Top reinforcing bars with shallow cover can be relocated
downward in the slab for increased corrosion protection
cover, assuming that the slab still has adequate 56
calculated shear capacity with the decreased the
effective depth and that additional bars are added as
…Option 2
necessary to provide adequate calculated flexural
capacity.
• New reinforcing bars are fully encapsulated and
developed in the replacement concrete.
• The repaired slab will have similar or larger strength and
stiffness to the originally constructed sections.
• Due to the new uncontaminated concrete with low
permeability, and the epoxy-coated reinforcement, new
surface coatings such as a traffic-bearing elastomeric
coating or a surface sealer were not recommended,
reducing initial and maintenance costs.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Option 2 Disadvantages
57
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• Only deteriorated concrete is removed and replaced, limiting repairs
and repair costs to current requirements.
• Re-entrant corners will be avoided in both the repair and existing
concrete. 58
• After concrete removal work has been completed, the exposed
concrete surfaces will be cleaned and a suitable bonding procedure
will be used to attain the minimum required bond strength and
approach repair
ensure composite behavior under service loads.
• Existing reinforcing bars that are exposed in removal areas will be
cleaned and coated with a corrosion-inhibiting material to reduce
ongoing corrosion in and around the replacement concrete areas.
Slab Area 2
• New epoxy-coated reinforcing bars will be lapped with existing bars
that are exposed in removal areas and have lost structurally
significant cross-sectional area.
• Discrete galvanic anodes will be installed around the perimeter of
Limited
slab concrete replacements to reduce corrosion in the existing
concrete around the concrete replacements. To function properly,
the anodes must be attached to uncoated portions of the
reinforcing bars in the removal areas before the bars are coated with
a corrosion-inhibiting material.
…Disadvantages
59
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• The repair specifications included quality assurance and
control measures for material approvals and field
verification of quality. The specified quality control
measures and construction observations were performed 60
during the construction, including the following:
• Review of material submittals and reinforcement shop drawings
Quality Assurance
for Slab Area 1.
• Visual inspection of the work in progress.
• Sounding of concrete surfaces to remain to determine if all loose
concrete was removed prior to repair.
• Observation of the prepared concrete surfaces and of the
concrete placement and curing operations.
• Testing of repair concrete, including slump, temperature, and
compressive strength.
• Bond strength testing of in-place repair concrete to confirm that
the bond strength was at least 1.5 times greater than the
calculated design bond strength.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Project Close-out
61
Periodic maintenance
• Periodic maintenance requirements were discussed with the owner
during the selection of the most appropriate repair concepts. A
schedule of recommended monitoring and possible maintenance
requirements was provided to the owner at the conclusion of the
repair construction, including the following:
• Periodic inspections every 3 to 5 years to monitor the condition of the garage.
• Limited concrete deck repairs every 5 years.
• Limited repair of the traffic-bearing elastomeric coating every 3 to 5 years to
address areas of high wear such as near the garage entrance/exit.
• Top coating the traffic-bearing elastomeric coating and restriping the garage
every 15 to 20 years.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
62
Example #4
Parking/Plaza Slab Strengthening
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Parking/Plaza
63
Description of Structure
• The facility consists of an 11-story office building over a two-story,
100,000 ft2 (9300 m2) parking structure supporting an open-air
plaza. The building is located in the northern U.S., and construction
was completed in 2013.
• The supported garage slab is a reinforced concrete flat plate, and
the plaza slab is a reinforced concrete flat slab with drop panels.
Project Initiation and Objectives
• Shortly after construction was completed and the certificate of
occupancy was obtained, excessive deflections and top surface
cracking were noted on the supported garage slab.
• The project was initiated to determine the causes of the cracking
and deflections and the overall safety of the as-built structure.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Crack Map
64
Governing Building Code
65
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Design Basis Code
66
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• Document review - The design drawings, construction
documents, and various reports were available and reviewed
by the LDP. The construction documents and reports
confirmed that the concrete and reinforcing bars met the
specified material properties. 67
Preliminary
member sizes, was measured on-site. The thickness of the drop
Evaluation
panels in the plaza slab was measured to be approximately 6
in. (150 mm) compared to the design thickness of 14 in. (355
mm).
• Existing concrete condition - The top surface cracks on the
supported garage slab were mapped and the top surface
elevations were surveyed to document the slab deflections.
• Reinforcement - The reinforcement layout was documented
using ground penetrating radar (GPR) supplemented by
exploratory chipping at isolated locations to expose
reinforcing bars and confirm the GPR findings. The investigation
revealed areas having over 4 in. (100 mm) of concrete cover
to the top reinforcing bars compared to the as-designed
cover of 3/4 in. (19 mm).
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Preliminary analysis
68
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Effects of shallow drop panels
69
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Slab
70
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural sections – Drop Panel
71
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Reinforcement Cover
72
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Effects of excessive cover
73
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Safety Concerns
74
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Effects of steel bracket or reinforced
concrete column capital 75
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Data
76
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
… Structural assessment
78
Concrete strength.
• The concrete compressive strength was assumed to be the
design strength, as confirmed by the construction testing
laboratory reports that were available.
Reinforcing steel layout and strength.
• Reinforcing steel spacing and cover were determined at all
locations with GPR and confirmed at exploratory openings.
Bar sizes were also measured at the exploratory openings.
• The reinforcing steel tensile strength was assumed to be the
design strength, as confirmed by the mill certificates in the
construction records.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Strengthening concept 1
79
• At locations with thin drop panels. For the plaza slab, steel
brackets would be installed on the columns at the
underside of the slab.
• The steel brackets would move the critical punching shear
section further from the column, increasing the perimeter of the
section, bo, and thus the punching shear capacity.
• The brackets also would move the critical negative moment
section further from the column, decreasing the design negative
moment to the moment capacity of the slab section with the
reduced drop panel thickness
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Strengthening concept 1
81
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Strengthening concept 2
82
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Strengthening concept 2
83
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
… Strengthening
84
concept 2
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Evaluation of strengthening
concepts 85
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
86
Column Capital
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
87
Column Capital
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Structural Analysis
for Repair Design 88
Structural Repairs
• The column capitals were designed and detailed to integrate
and act compositely with the columns and the slab above.
• The column surfaces were intentionally roughened and hoop
and Durability
reinforcement was included in the capitals to transfer forces into
the columns by shear friction. Self-consolidating concrete (SCC)
was used to facilitate filling of the forms to the slab soffit.
• The supplemental drop panels were also designed and detailed
Design of
to integrate and act compositely with the columns and slab
above.
• Reinforcing steel extended between the column capitals and
the drop panels, and the capitals and drop panels were placed
monolithically. Epoxy-grouted dowels were installed in the slab
soffit to transfer the horizontal flexural shear by shear friction. SCC
was used to facilitate filling of the forms to the slab soffit.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• The CFRP strips were designed as a supplemental
strengthening measure, based on the
recommendations of ACI 440.2R.
90
• The structural strength of the repaired slab was
adequate to carry the factored loads specified in the
current building code without the CFRP strips.
Structural Repairs
• The CFRP strips were used to increase the calculated
slab positive moment capacity to account for the
and Durability
increased positive moments due to moment
redistribution that occurred before the repairs were
installed, and to limit further deflections from these
Design of
moments.
• The CFRP strips were detailed and bonded to the slab
soffit per the manufacturers recommendations and
ACI 440.2R. Bond pull off testing was performed to
verify the bond.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• The injection of epoxy into cracks on the top surface of
the supported garage slab was requested by the owner
and also served to increase the slab stiffness and seal the
cracks against intrusion of water and deicing salts into the 91
concrete, improving the durability of the slab.
• A traffic-bearing elastomeric coating was applied on the
Structural Repairs
top slab surface in the negative moment regions around
the columns on the supported garage slab to prevent the
intrusion of water and deicing salts into cracks that may
and Durability
not have been sealed and to minimize the intrusion of
water and deicing salts into the concrete and improve
the durability of the slab.
Design of
• As the column capital and drop panel repairs and the
CFRP reinforcement were all installed on the undersides of
the slabs, the repairs are not directly exposed to the harsh
top slab surface service environment and the repairs were
judged to be durable.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Construction
92
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Construction
93
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
…Construction
94
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
CFRP installation
95
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
96
Epoxy Injection of
cracks
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Contract Documents
97
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Quality Assurance
99
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
• Observation of the concrete placement and curing
operations.
• Testing of repair concrete, including slump flow, air content,
temperature, and compressive strength. 100
• Impact-echo testing to verify the continuity between the slab
soffit and the new capitals.
Assurance
• Observation of the surface preparation and installation of the
CFRP strips.
…Quality
• Bond strength testing of installed CFRP strips (ASTM
D7522/D7522M-15, “Standard Test Method for Pull-Off Strength
for FRP Laminate Systems Bonded to Concrete Substrate”).
• Impact-echo testing was performed on the top slab surface
over drop panel and capital repairs to detect possible gaps
between the slab soffit and the repairs.
• Some areas with gaps were detected.
• Open joints between the slab soffit and drop panel and
capital repairs were injected with epoxy to fill the joints and
bond the repairs to the soffit. Continuity was confirmed by
impact-echo testing.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
101
Impact Echo
testing
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
102
Impact Echo
testing
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Epoxy Leakeage
103
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Load Test
104
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Test procedure
105
• ACI 562 references ACI 437-13 for load testing, which is meant to read as
ACI 437.2-13. The 2009 IBC, the design basis code, references ACI 318-08,
which includes Chapter 20, Strength Evaluation of Existing Structures.
• Based on ACI 562 Section 1.1.7, ACI 562 governs for all matters pertaining
to evaluation and shall govern when in conflict with other referenced
standards.
• Accordingly, the monotonic load test procedure described in ACI 437.2-
13 was used for the evaluation.
• The monotonic load test was selected after consultation with the
Contractor’s available means, methods, and familiarity with the
monotonic test.
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
Monotonic load test
106
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
108
Load Test
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
109
Test Setup
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo
FIN 110
ACI 352 & GUIDE ‐ 2016 Beca Dr. Ramón Carrasquillo