Volume 3 Tender Document For SY 206 General Specification (Part 1 of 5)
Volume 3 Tender Document For SY 206 General Specification (Part 1 of 5)
TENDER DOCUMENT
FOR
VOLUME Ill OF VI
SPECIFICATIONS (PART 1 OF 5)
GENERAL SPECIFICATION
PROJEK MASS RAPID TRANSIT LALUAN 2: SUNGAI BULOH – SERDANG – PUTRAJAYA (SSP)
TABLE OF CONTENTS
TOC 1-5
PROJEK MASS RAPID TRANSIT LALUAN 2: SYSTEMS WORKS PACKAGE SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh – Serdang – Putrajaya (SSP) Table of Contents
Tender No. SSP-MRTC- SS06-OVPR-TEN-00066
VOLUME IV – DRAWINGS
TOC 2-5
PROJEK MASS RAPID TRANSIT LALUAN 2: SYSTEMS WORKS PACKAGE SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh – Serdang – Putrajaya (SSP) Table of Contents
Tender No. SSP-MRTC- SS06-OVPR-TEN-00066
TOC 3-5
PROJEK MASS RAPID TRANSIT LALUAN 2: SYSTEMS WORKS PACKAGE SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh – Serdang – Putrajaya (SSP) Table of Contents
Tender No. SSP-MRTC- SS06-OVPR-TEN-00066
TOC 4-5
PROJEK MASS RAPID TRANSIT LALUAN 2: SYSTEMS WORKS PACKAGE SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh – Serdang – Putrajaya (SSP) Table of Contents
Tender No. SSP-MRTC- SS06-OVPR-TEN-00066
TOC 5-5
PROJEK MASS RAPID TRANSIT LALUAN 2: System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh-Serdang-Putrajaya (SSP) Volume III – Specifications (Part I of II)
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066 General Specification
CONTENTS
1 INTRODUCTION ............................................................................................ 11
1.1 ABOUT THIS DOCUMENT ....................................................................................... 11
2 GENERAL ...................................................................................................... 12
2.1 APPLICATION OF THE GENERAL SPECIFICATION (GS) ................................................... 12
2.2 ABBREVIATIONS AND DEFINITIONS ........................................................................... 12
2.3 GLOSSARY OF TERMS AND STATION NAMES .............................................................. 12
2.4 DEFINITION OF SITE AND WORK AREA ..................................................................... 13
2.5 STANDARDS AND CODES OF PRACTICE ..................................................................... 13
2.6 REQUIREMENTS MANAGEMENT.............................................................................. 14
2.7 PHASED OPENING ................................................................................................ 15
2.8 DRAWINGS ......................................................................................................... 16
2.9 CONTRACTOR’S DRAWINGS ................................................................................... 17
2.10 UNITS OF MEASUREMENT ..................................................................................... 17
2.11 DIMENSIONS FROM DRAWINGS .............................................................................. 17
2.12 QUARTERLY REVIEW MEETINGS.............................................................................. 17
2.13 CLIMATIC CONDITIONS / OPERATING ENVIRONMENT ................................................. 18
2.14 PUBLIC RELATIONS ............................................................................................... 19
2.15 PROJECT CEREMONIES, PUBLIC AND MEDIA EVENTS ................................................... 22
2.16 ASSET MANAGEMENT........................................................................................... 22
2.17 COMMUNICATIONS WITH THE PDP ......................................................................... 25
2.18 IT SECURITY ........................................................................................................ 25
3 THE SITE ...................................................................................................... 26
3.1 APPLICABLE PROVISIONS ....................................................................................... 26
3.2 ACCESS TO THE WORK AREA .................................................................................. 26
3.3 WORK AREA RESTRICTIONS ................................................................................... 27
3.4 SITE SERVICES ..................................................................................................... 28
3.5 WORK AREA CLEANLINESS ..................................................................................... 30
3.6 PARKING FACILITIES .............................................................................................. 30
3.7 SITE PEST CONTROL ............................................................................................. 30
3.8 WORKS TRAINS ................................................................................................... 31
3.9 DEFINED AREA AND RESTRICTED AREA WORKING AND WORKS TRAIN OPERATIONS ......... 32
1 INTRODUCTION
This Document is the General Specification (GS) – Railway Systems for the
SSP Line. It shall be read in conjunction with Particular Specifications (PS) for
the seven System Work Packages shown below.
*END OF SECTION*
2 GENERAL
(1) The CAD Standards Manual contains a list of project abbreviations but
for the avoidance of any doubt the abbreviations listed in the System
Project Glossary, System Tagging and Labelling Standard shown in
Appendix A shall prevail. This Document will be updated throughout
the project.
(1) Words and expressions to which meanings are assigned in any Section
of the GS shall have the same meanings in other Sections of the GS
except when the context otherwise requires.
(2) Utilities are electrical power, lighting, traffic control, telephone and
other communication cables, gas, water supply, sewerage and
drainage, including all associated protection, supports, ancillary
structures, fittings and equipment.
(3) System Project Glossary, System Tagging and Labelling Standard:
refer to Appendix A.
(4) This System Project Glossary, System Tagging and Labelling Standard
will be updated throughout the project including all station and depot
names. The WPC shall not be entitled to claim for any additional
payment or extension of time against the PDP/Owner for any such
updates throughout the project.
(6) The WPC shall follow all requirements of the National Heritage Act
2005.
(7) The WPC shall fulfil all requirements stated in the Akta Pengangkutan
Awam Darat 2010 (Public Land Transport Act 2010) and take into
account the safety, quality and comfort of the public.
(1) The WPC shall use Requirements relational data base software
approved by the PDP/Owner.
(2) The WPC shall appoint a suitably qualified and competent person to
carry out requirements management. The CV of the Requirements
Manager shall be provided to the PDP/Owner for review and
acceptance and show that the Requirements Manager has an
appropriate level of knowledge and experience in the use of the PDP
approved Requirements database software. The PDP will provide
training in the use of the PDP Requirements database and provide a
number of licences to provide access to the PDP Requirements
database.
(3) The WPC shall prepare and submit for review and acceptance by the
PDP/Owner a Requirements Management Plan within thirty (30) days
of the date of the Letter of Acceptance. The Requirements
Management Plan shall define the processes employed by the WPC
to ensure that all appropriate requirements are managed to ensure
the proposed design solution meets the design requirements. The
Requirements traceability database will be managed through the
relational database and the scope will be defined by the PDP.
(4) The WPC shall develop a database of all requirements associated with
a number of definition documents defined by the PDP in the Letter of
Acceptance such as, but not limited to, the GS, the PS and the
Interface Specification’s (IS). The WPC will then provide evidence that
the identified requirements have been managed appropriately. The
database shall:
a) Ensure that the criteria for the purpose of verification and
validation of the Requirements has been recorded with
appropriate attributes assigned;
(1) The SSP Line shall be completed in two phases, namely Phase 1 and
Whole of the Works. Phase 1 means Works to be completed from
Kwasa Damansara up to and including the cross-overs to the South of
Kampung Batu Station to be operated and maintained from Sungai
Buloh Depot. The Whole of the Works means works to be completed
from Kwasa Damansara to Putrajaya Sentral, to be operated and
maintained from Sungai Buloh Depot and Serdang Depot. Further
details are shown in Appendix B.
2.8 Drawings
(1) Drawing numbers shall be in accordance with the latest version of the
CAD Standards Manual (PDP2/SSP/GENE/OVPR/PRO/000007) and
the QA Centralised Document Management Procedure
(PDP/SSP/GENE/OVPR /PRO/0011). All references to drawing
numbers shall refer to the latest version of that drawing, unless a
specific revision or version number is stated in such references.
(2) On completion of each section of the Works the WPC shall be
responsible for modifying and updating the Drawings to reflect the
as-built condition. “As Built” drawings shall incorporate all
amendments resulting from on-site instructions changes to
dimensions and routing or location of items, removal or amendment
to notes, changes from future tense to past tense and materials used.
(3) Refer to Appendix C for a list of PDP General Interface Drawings
associated with this project. The WPC shall consider all General
Interface Drawings listed in Appendix C to be contractual and
categorised as follows
a) Project Wide Directive Drawings – These are Contract
Drawings that include mandatory requirements that shall be
included within the System Design;
b) Infrastructure Drawings - These are Contract Drawings of the
Infrastructure Works and are a constraint on the System
Design;
c) Infrastructure Typical Drawings – These are Contract
Drawings of the Infrastructure Works, are a constraint on the
System Design and will be developed by Other Works
Contractors into Site Specific Drawings;
d) System Reference Design Drawings – These are Contract
Drawings that have been developed and coordinated with
Other Works Contractors as a reference solution for the WPC.
The reference design solutions are not warranted and the
WPC shall be liable and responsible for the actual and final
design solution.
(1) The WPC shall prepare all drawings, sketches, figures, diagrams,
illustrations and similar items needed for the execution of the Works.
(2) “As-Built” drawings shall be prepared and submitted in accordance
with the requirements specified in this GS.
(3) The WPC shall submit the following no. of copies of drawings:
a) Four sets of A1 size drawings comprising 1 set of original
reproducible drawings and 3 sets of non-fade prints;
b) Six sets of A3 size prints reduced from the original A1 size
drawings;
c) Four sets of electronic copies stored on CD-ROM or DVD;
(4) The WPC shall be responsible for the production of all drawings
required for submission to regulatory and statutory bodies,
Government departments, utility asset owners and any other
stakeholders as necessary, in order to avoid delay to and progress of
the Works.
(5) All WPC drawing submissions shall be endorsed by a practicing
Professional Engineer (PE).
Contract. The PDP shall provide reasonable notice to the WPC who
shall attend each quarterly review meeting.
(2) The PDP may convene quarterly review meetings to be held in
Malaysia. The PDP will notify the WPC of the meeting not less than
twenty eight (28) days before the meeting date.
(3) Quarterly review meetings will be held over a period of up to three
(3) days in order to review the overall progress of the Works in the
context of the Project as a whole, and to address and resolve any
issues relevant to the execution and progress of the Works. Such
meetings will be chaired by a member of the PDP directorate or other
senior manager with attendance by Senior Management of the
Owner. The WPC shall have in attendance one senior representative
of director level from each of the companies comprising the WPC,
together with the managing director of the company acting as a
leader of the WPC if it is a joint venture, consortium or partnership.
(4) Names of attendees proposed by the WPC shall be notified to the PDP
for approval not less than seven (7) days prior to each meeting.
(whichever comes sooner than the construction works) from the date
of the Letter of Acceptance.
(3) The content of the PR Action Plan shall be in accordance with the PDP
Public Relations & Stakeholders Management Manual.
(4) The WPC shall be responsible for the arrangements for the
ceremonies and other site visits and public events to the satisfaction
of the PDP/Owner. Such arrangements shall include the following:
a) Clearing and cleaning of the required area(s) so as to ensure
the safety of all persons and to promote a good public image;
b) Erection and dismantling of temporary staging, decoration of
the Work Area, tent roofs, seating, catering, barricades,
banners, a podium, microphones, loudspeakers and audio-
visual equipment, first-aid post, sanitary facilities including
temporary mobile toilets and hand wash facilities, etc., and
the requisite electrical supply to accommodate such
requirements, as appropriate;
c) Provision of all safety arrangements, security support,
personnel to escort visitors and safety equipment, including
new safety helmets. The WPC will be notified of the number
of safety helmets required and shall provide the safety
helmets including any logos, colouring and nameplates as may
be designated by the PDP/Owner. The WPC shall make safety
helmets available to the PDP upon completion of the
ceremonies as souvenirs for the VIPs and guests.
(5) The WPC shall arrange his work schedule such that the activities
related to the ceremonies and public events will have no impact on
the Works.
(6) The WPC shall provide two “Caring Ambassadors” who shall be
clearly identified by wearing armbands. The “Caring Ambassadors”
shall provide assistance to pedestrians, especially senior citizens,
pregnant women and disabled persons, in crossing carriageways at
pedestrian crossings and walking on temporary or narrow footpaths
and access points during the event.
(1) All assets will be subject to the requirements set out in the Asset
Management Plan.
b) Part number;
c) Functional use;
d) System, sub-system, equipment and component level
hierarchy for populating the CMMS Database configuration;
e) Maintenance Requirements;
f) Maintenance history;
g) Spares stock holding;
h) Supplier;
i) Contact name and address.
(11) The WPC shall provide administrative schedule information for
populating the CMMS Database Server. The schedule shall include
but not be limited to:
a) Personnel details;
b) Training;
c) Warranties;
d) Work schedule;
e) Job cards.
(1) The WPC shall produce an Obsolescence Management Plan for review
by the PDP/Owner within ninety (90) days of Letter of Acceptance
(2) The plan shall take into account the project related risks associated
with the obsolescence issues in connection with equipment/spare
parts, hardware and software during the design. And through to its
first estimated obsolescence phase.
(3) Obsolescence shall be evaluated by the WPC when planning the levels
of spares holding.
(4) The WPC shall submit an Obsolescence Management Report for
PDP/Owner approval at the conclusion of final design. The Report
shall contain details of the management of the system and
components throughout the life of each asset.
(1) Any communication from the WPC to the PDP and their
representatives whether for the purpose of clarification of any topic
or notification of any event or occurrence shall be made as a formal
written communication using the PDP approved document control
system. Any such communication made by e-mail or verbally or any
other means shall be confirmed by a formal written letter at the
earliest opportunity; failure to provide such formal confirmation may
render the communication to be deemed null and void.
2.18 IT Security
*END OF SECTION*
3 THE SITE
(1) Each WPC shall assess the provisions in this Section that are
applicable to their Work Package. The results of this assessment
shall be submitted for approval by the PDP/Owner prior to the
Letter of Acceptance.
(1) The WPC will be given access to the Work Area in accordance with
the Conditions of Contract. The WPC shall then be responsible for
access to the Work Area through the Site in coordination with the
Civil WPC.
(2) The WPC shall at all times permit and facilitate access to the Work
Area and the Works by staff of the Owner, PDP, Supervising
Consultant, and all other personnel authorised by the PDP. The WPC
shall provide suitable PPE for all site visitors.
(3) The WPC shall at all times permit and facilitate access to the Work
Area by Government Departments, Utility Undertakers and other
Relevant Authorities for the inspection and maintenance of their
facilities located within the Site.
(4) The WPC shall permit and facilitate access to the Work Area and the
Works by Other Works Contractors during the times specified in the
Contract or as otherwise instructed by the PDP.
(5) The WPC shall maintain safe access to and egress from the Work Area
at the locations stated in the Contract and/or as approved by the
PDP/Owner and the Relevant Authorities.
(6) The WPC shall introduce mechanisms to control access to avoid
trespassers and/or illegal entrants to the Work Area.
(7) The Civil WPC shall manage all pedestrian and vehicular entries to and
exits from the Site and shall man all Site access locations during
operation of the Site. The Civil WPC shall pave each Site access with
a smooth transition to tie in with the level of the adjacent
carriageway and/or pavement. The WPC shall ensure that any vehicle
or machinery leaving the Work Area shall be in a forward gear only.
(8) The Civil WPC shall, from the date of possession of the Site, be
responsible for the management and maintenance of the traffic
within the Site and shall also be responsible for constructing and
maintaining all vehicular run-ins and temporary lay-byes or road
widening as necessary to avoid traffic congestion. The WPC shall be
responsible for any Civil WPC procedures that relate to WPC traffic or
vehicular access requirements in the Work Area that are approved by
the PDP.
(9) Where the WPC is undertaking Works within an isolated area with
adjacent running traffic lanes, the WPC shall prepare a Traffic
Management Plan for the Work Area and provide all necessary
support and assistance to the Civil WPC to enable the Civil WPC to
plan and design a safe means of access.
(10) Unless otherwise permitted by the Contract, the Civil WPC shall
maintain ingresses and egresses (including designated emergency
access routes) to all properties and facilities within and around the
Site. Any alternative access arrangements proposed by the WPC to
the Civil WPC shall be safe and free from hazards and shall be subject
to the approval of the Relevant Authorities and of the PDP. All access
routes (including emergency or alternative access routes) shall be
directed by proper, clear and visible signage.
(11) The WPC shall be responsible for and accountable to the Civil WPC
for damage to any roads, paths, access ways or other infrastructure
under the responsibility of the Civil WPC that is caused by the WPC or
his sub consultants.
(1) The particular application for which the Work Area is to be used shall
be submitted to the PDP/Owner for approval. The WPC shall:
a) Refrain from depositing rubbish, causing nuisance or
permitting nuisance to be caused; and
b) Refrain from obstructing manholes, utility access points and
the like.
(2) Work other than that necessary for completion of the Works shall not
be carried out in the Work Area.
(3) At all times whilst the WPC has access to the Work Area, he shall
provide means of distributing loads imposed by WPC equipment and
traffic and prevent damage to utilities and services.
(4) Except where otherwise provided and approved by PDP/Owner, the
WPC shall not permit any person to reside on the Work Area or Site.
(5) The WPC shall not allow animals to be brought onto the Work Area
or Site.
(1) Except for the Migration Section, the Civil WPC shall provide the
following site services to facilitate construction/installation of the
Works, which shall generally be available for use by each WPC:
a) Electricity;
b) Water;
c) Lighting facilities;
d) Garbage disposal facilities;
e) Welfare facilities e.g. toilets, rest areas, drinking facilities and
the like;
f) Contaminated material removal;
g) Ventilation (underground).
(2) Furthermore, the Civil WPC may also provide the other temporary
facilities listed below. The WPC shall make his own arrangements
with the Civil WPC if the WPC wants use of, or connection to, such
temporary facilities:
a) Compressed air;
b) Site communication facilities;
c) Drainage and sewage disposal;
d) Fire protection systems;
e) Lightning protection;
f) Dangerous goods stores;
g) Air conditioning (elevated only).
(3) In general the WPC shall make use of the site facilities provided by
the Civil WPC across the site. The Civil WPC shall respond to
(1) The Work Area shall be maintained in a clean, tidy and sanitary
condition. Materials, shall be stored in an orderly manner. Rubbish,
debris, disused packaging and the like shall be disposed of at least
once a day and the works areas cleaned so that the Work Area is kept
constantly clean and tidy.
(2) The WPC shall remove their debris daily to the central debris
collection points on Site which will be provided by the Civil WPC.
After every works shift, all work areas shall be cleaned and made tidy
to the satisfaction of the PDP.
(1) The WPC shall at no time permit any mobile equipment or vehicle to
be parked in areas that are not designated parking facilities.
(2) The WPC shall at all times ensure that public nuisance is not caused
by the parking of mobile equipment and vehicles (including shuttle
buses) associated with the Works.
Rodent Control
(1) The WPC shall at all times take effective measures to prevent damage
by rodents to the Permanent Works and constituent parts thereof,
such as cables, electronic cards, etc., during the execution of the
Works and shall advise the PDP of such measures taken.
(1) The PDP will arrange for Works Trains to be used by each WPC in
accordance with the TRIP.
(2) A limited number of Works Trains, which comprise single platform
flat wagon(s), will be provided free of charge by the PDP for the use
of the WPC and Other Works Contractors as described in the
Specifications. The length of each flat wagon is approximately 20m
and its maximum loading capacity is 30,000 kg. The WPC shall ensure
that all articles to be transported by the Works Trains are either
properly secured or contained and do not exceed the Construction
Vehicle Load Gauge, details of which will be issued by the PDP upon
request. The PDP/Owner will not be responsible for any damage and
loss to the Works, WPC Equipment or any articles whilst in transit or
stored on the Works Trains.
(3) The Works Train will transport the single platform wagon(s) to a
location along the Project in accordance with the TRIP.
(4) No modifications of the flat wagon may be carried out except with
the PDP’s written consent.
(5) The WPC shall take all necessary precautions to protect the Works
Trains from damage when in use.
(6) The WPC shall immediately report any breakdown or derailment of
the Works Train and associated equipment to the Works Train
Controller or Section Controller who will initiate actions to clear the
line, repair any damage and open the line as quickly as possible.
(7) The WPC shall submit detailed derailment reports on any derailments
that occur on any tracks within the Site and assist in the derailment
investigation by the PDP where necessary. Draft derailment reports
shall be submitted to the PDP/Owner within 24 hours of the incident
occurring with final reports issued within one week from the date of
derailment.
3.9 Defined Area and Restricted Area Working and Works Train Operations
(1) "Defined Area" means an area of track where Works Trains are
operating and where the Project’s Construction Railway Operations
Rulebook and Works Train Operation Safety Handbook apply,
including 1m back from the front edge of the platform and the full
width of the tunnel, viaduct or other enclosed structure. The Defined
Area at grade shall include an area within 3m from the track centre
line and where applicable, this may be extended to include the whole
of the track area within Depots. The WPC shall clearly mark and
protect Defined Areas with barriers and prohibitive signs as approved
by the PDP/Owner.
(2) All persons whose duties require them to work within a Defined Area
shall observe the safety rules and procedures issued by the PDP which
provides procedures and guidance for the safety of all persons in the
Defined Area.
(3) The WPC shall communicate the rules and procedures, which may be
published from time to time, to their workers and/or agents on the
Work Area, and to ensure all such rules and procedures are being
observed in the course of all works and construction activities.
(4) Persons working on or near tracks in a Defined Area either, by
themselves or supervising a working party, shall be suitably trained
and qualified by the PDP or his delegates in the provisions of the track
safety rules and procedures issued by the PDP. Persons who are not
qualified shall not attempt to gain access to the railway tracks unless
accompanied by a qualified person.
(5) Each PDP locomotive will be operated by a qualified operator
provided by the PDP.
(6) Works Trains shall be operated in compliance with the relevant
operating procedures and instructions.
(7) When the third rail is energised, trains may be running at high speed
for testing. The track area shall then be designated as a Restricted
Area. Both Up and Down tracks along the energised track shall be
isolated by barriers to prevent access by trespassers. No work may
be undertaken on either the Up or Down tracks when test trains are
running. Procedures for gaining access to the Restricted Area will be
detailed in the operating procedures and instructions to be issued by
the PDP. The WPC shall make requests for gaining access to the
energised track at the weekly Works Train Meetings.
(8) Persons working on or near energised tracks, shall be suitably trained
and qualified by the PDP or his delegates on the safe working
procedures in the Restricted Area.
(9) Any room containing electrical equipment which has been energised
or containing sensitive / specialist equipment shall also be designated
as a Restricted Area. Access controls and a Permit to Work System
shall be established by the key holder of the room (WPC, Other Works
Contractor, Utility Undertaker or PDP depending on the supplier of
the equipment in the room and the phase of the Works).
(10) The WPC shall make arrangements with the key holder of Restricted
Areas to gain access to complete any outstanding or remedial works
and shall comply with any restrictions imposed by the key holder at
that time. Likewise, the WPC shall provide access and shall specify
any restrictions to Other Works Contractors requesting access to
Restricted Areas for which the WPC is still the key holder.
(11) All workers accessing the track area shall be required to attend a
general track safety course conducted by the WPC’s safety supervisor
based on training provided by the PDP. As works progress, additional
requirements will be imposed and site supervisors will need to be
trained and qualified by the PDP accordingly.
(12) Prior to providing access to, or handing over, rooms/areas to Other
Works Contractors in accordance with the provisions of the Contract
to enable the Execution of the works of Other Works Contractors, the
WPC shall jointly record the condition of each room/area at the time
of provision of access/handover with the Other Works Contractor. A
copy of the jointly signed condition record shall be issued to the PDP
for record. Any subsequent claim of damage caused by Other Works
Contractors shall refer to the joint survey record and any necessary
repairs shall be managed in accordance with the Civils GS. The WPC
shall retain responsibility for Care of the Works including routine and
preventive maintenance, servicing and cleaning of the Works within
the Restricted Areas.
(1) This Clause shall apply to works in the vicinity of the Operating
Railway.
a) The WPC shall have regard to the Specification for work
within the vicinity of the Operating Railway and shall comply
strictly with the requirements as set out therein. The WPC
shall comply with any instructions given by the PDP/Owner
with regard to planning, methods of working, safety
requirements and on any other matters which may affect the
operation of the Operating Railway, and shall also comply
with all rules, regulations, procedures, manuals and notices
which may be published from time to time by the PDP or
Operator.
b) Should the WPC be unwilling or unable to conform at once
with a direct instruction from the PDP/Owner under the
provisions of this Clause or to carry out any remedial or other
work or repair, the PDP may, by written instruction to the
WPC, suspend the execution of the Works or of any part
thereof pursuant to the Conditions of Contract or authorise
the carrying out of such remedial work or other work or repair
by a person other than the WPC pursuant to the Conditions
of Contract.
c) Where any part of the Works has to be carried out during the
period of a speed restriction, track possession (track closed to
rail traffic) and/or electrical isolation and the period of such
speed restriction and/or track possession and/or electrical
isolation is prescribed in the Contract, the WPC shall plan and
execute that part of the Works so that such period is not
exceeded and so that no further periods are required.
d) Prior to commencement of work, the WPC shall submit a
method statement and hold discussions with the PDP who will
decide whether any part of the Works is to be carried out
during a period of a speed restriction and/or track possession
and/or electrical isolation and the PDP will notify the WPC
accordingly.
e) After the method of carrying out the work has been agreed
with the PDP (and taking into account any provisional
(1) Where the PDP/Owner has agreed that the WPC is to provide rolling
stock (either self-propelled or trailing) for use during the installation
and testing of the Works, the requirements shown in the preceding
two clauses shall apply. Rolling stock provided by the WPC shall not
(9) If the WPC shall be responsible for operating the rolling stock that the
WPC has provided, then all operations shall be carried out by
qualified and experienced personnel, whose qualifications have been
approved by the PDP/Owner, in accordance with operating
procedures that shall have obtained the prior approval of PDP.
(1) This Clause shall apply for transportation to the Work Area:
a) The WPC shall liaise with the Civil WPC in order to identify and
propose routes and rights of entry to the Site including the
production of Method Statements, for approval by the
PDP/Owner from time to time. Routes for very large or very
heavy loads shall be discussed and agreed with PDP in
advance of the need arising. All arrangements shall be
prepared by the WPC, with all necessary support by the Civil
WPC, and submitted for approval by the PDP/Owner.
b) In this context, the definitions of the terms "very large" and
"very heavy" refer to articles that cannot be transported by
normal road vehicles or be handled by readily available
methods. Where doubt exists, it shall be the responsibility of
the WPC to notify and discuss the nature of the load in
question with the Civil WPC and the PDP.
c) For the transportation of large or heavy loads, the WPC shall
comply with the requirements of the Lembaga Lebuhraya
Malaysia (Malaysian Highway Authority) I Polis Diraja
Malaysia (Royal Malaysian Police Force)/ any other Relevant
Authority regarding any special traffic arrangements that may
be necessary. The WPC’s attention is drawn to the Road
Traffic Act, Laws of Malaysia Act 333 Road Transport Act
1987.
d) Extraordinary traffic may be moved between areas of the Site
over public highways only by police escort and on a route and
at a time determined by the Relevant Authority.
e) The WPC shall make all arrangements through the Civil WPC
and assume full responsibility for transportation to the Site
and the Work Area of all WPC Equipment, materials, and
supplies needed for the proper execution of the Works.
f) The Civil WPC shall ensure that all roads and pavements
leading to and around the Site are kept free from obstructions
and shall not cause inconvenience or hindrance to traffic or
persons either by his vehicles or by his workmen, plant,
materials, equipment, etc.
g) Unless otherwise agreed between the WPC and Civil WPC, the
Civil WPC shall repair damage to existing roads, footpaths,
steps, cables, sewers, live drains, etc. and shall reinstate any
damage caused by the WPC actions. The WPC shall
compensate the Civil WPC for all costs incurred by the Civil
WPC in carrying out such repairs or reinstatements.
h) All special lifting tackle, plant or equipment which is used by
the WPC for the installation of Plant and Materials and
which is required for Plant and Materials maintenance, shall
become part of the Contract and shall be handed over to the
Owner suitably reconditioned and with a current test
certificate. Such lifting tackle shall be suitably identified.
(1) In above ground areas, where the WPC has a need to communicate
with his own staff or with the PDP, Owner or Other Works
Contractor’s over distances, he shall provide adequate items of
suitable equipment such as walkie-talkie sets. In such cases, the WPC
shall be responsible for obtaining any necessary licenses for their use.
(2) In underground areas, the WPC shall use the site communication
systems installed and maintained by the Underground WPC.
(1) The Civil WPC shall establish, operate, and maintain a security system
for the Site. The WPC shall provide all necessary support and
assistance to the Civil WPC to enable the Civil WPC to carry out his
responsibilities for Site security.
(2) The WPC shall be responsible for the security of all plant, equipment
and materials in his Work Area together with access to and egress
from the Work Area. The WPC shall submit a Security Management
Plan within ninety (90) days following the Letter of Acceptance,
incorporating as necessary the Civil WPC, security arrangements
including room key control and procedures for access control of
(1) The WPC shall become familiar with the Site and Work Area to the
extent that the WPC shall provide an induction to all employees and
subcontractors describing the activities and facilities including the
locations of first aid equipment, firefighting equipment and safe
working procedures relating to the Site and Work Area.
*END OF SECTION*
(1) The Site and Work Area shall not be used by the WPC for any purpose
other than for executing the Works or carrying out other work
associated with the Works which has obtained the prior agreement
with the Civils WPC and approval of the PDP.
(2) Access to and egress from the Site shall be only at the locations
approved by the PDP/Owner and the Relevant Authorities.
(3) The PDP reserves the right to order the immediate removal and
replacement of any WPC Equipment which the PDP considers is
unsatisfactory for its purpose.
(1) The WPC shall provide and maintain a suitable office for himself and
his staff in a location or locations to be approved by the PDP/Owner.
(2) The WPC shall be responsible for all fees and other charges or
expenses incurred in connection with such offices and housing and
shall keep the whole area in a clean, tidy and well drained condition.
When instructed by the PDP, the WPC shall remove all such buildings
and associated works from the Work Area and Site, clean up the area
and restore it to its original condition.
(3) The WPC shall provide adequate first aid facilities appropriate to the
size and composition of his staff and labour force. The WPC shall
afford the PDP/Owner and the Supervising Consultant’s site staff full
use of the services and facilities as and when required.
(4) The WPC shall ensure that all of their office ICT systems are
compatible with the PDP/Owner IT systems including software
licenses. Servers and firewalls with a minimum internet bandwidth of
10MBps upgradable when deemed required by the PDP/Owner.
(5) The WPC shall not erect or operate canteen and kitchen facilities on
the Work Area unless approved by the PDP/Owner and, where
appropriate, the Relevant Authorities. Any such facilities shall, in
particular but without limitation, conform with all regulations and
standards to the extent required by the Relevant Authorities.
(6) When and where appropriate, the WPC shall comply with the
Centralised Labour Quarters Operation Manual SSP-PDP2-GENE-
OVPR-MAN-000004 at latest issue.
a) The allocated CLQ for System WPC workers including his
subcontractors is provided free of charge.
b) All workers of the WPC who stay in the CLQ shall comply with
the regulations and guidelines set in the Civil WPC CLQ
Operation Manual approved by the PDP/Owner.
c) The WPC shall make his own arrangements for the
transportation for his workers, including his subcontractors,
to and from CLQ worksite, including maintenance of the
transport equipment.
d) The WPC shall provide all furnishings necessary for the rooms.
(1) Works which are not to remain on the Work Area after completion of
the Works shall be removed on the practical completion of the Works
or at other times directed by the PDP. The Work Area shall be cleared
and reinstated to the lines and levels and to the same condition as
4.5 Attendances
(1) The WPC shall treat the Contract and everything written in it as
private and confidential. In particular, the WPC shall not publish any
information, advertisement, drawing or photograph related to the
Works and shall not use the Site or Work Area for advertising
purposes, except with the written consent of the PDP/Owner and
subject to such conditions as the PDP/Owner may prescribe.
*END OF SECTION*
5 THE WORKS
(1) Within thirty (30) days from the date of the Letter of Acceptance, the
WPC shall provide the PDP/Owner with an overview of his intended
methods of constructing/installing the various parts of the Works in
the form of a Project Execution Plan. This shall include, but not be
limited to, the following:
a) Organisation;
b) Roles and Responsibilities;
c) Reporting Methodology;
d) Design Methodology;
e) Manufacturing & Installation Methodology;
f) Testing & Commissioning Strategy;
g) Change Control;
h) Reporting (Cost & Programme).
(2) Within sixty (60) days from the date of the Letter of Acceptance
or by the date agreed with the PDP, the WPC shall supplement the
Project Execution Plan with:
a) Plans of the Method Statements which will be developed by
the WPC as specified in this GS;
b) Plans of any Temporary Works which will be required (or the
date by which they will be procured);
c) Plans of the personnel who will control the works;
d) Proposals for quality control; and
e) Safety precautions to be employed.
(3) The WPC shall, whenever required by the PDP, furnish further and
more detailed particulars in writing of his method of construction or
installation, the amount and nature of WPC Equipment and
manpower proposed.
(4) The Project Execution Plan shall follow the requirements set out in
Section 5.
(5) As part of the Project Execution Plan, the WPC shall submit within
sixty (60) days of the date of the Letter of Acceptance a statement
entitled "WPC Method of Manufacture and Installation". The basic
information required to be submitted shall include:
a) Contract technical report giving:
i. Details and use of Works Areas;
ii. References to drawings;
iii. Details of the manufacturing or assembly facility;
iv. Method statement describing the layout and
operation of the manufacturing and assembly
facility, method and sequence of transporting and
placing assembled units;
v. Construction materials to be used and their
sources of origin in production;
vi. Method of and particular requirements for
manufacture and testing of Plant and Materials
prior to delivery to Site and Work Area;
vii. Method of and particular requirements for
delivery and transportation of Plant and Materials
to and across the Site and Work Area;
viii. An appreciation of any access and phasing
constraints;
ix. Details of the design team;
x. Installation proposals;
xi. Method of and procedure for testing and
commissioning of Plant and Materials installed;
and
xii. Policy for training of operators in the use and
maintenance of specific tools and equipment
used.
b) Policy for allocation of work, computer and design resources,
manning levels and responsibility for supervision;
(2) The WPC shall provide to each of their site representative(s) involved
with the works approved Method Statement(s), Inspection and
Testing Plan(s) and other related document(s).
(3) Work Area representative(s) shall sign for the documents to say that
he or she understands the work methods and procedures.
(4) Work Area representative(s) shall coordinate and conduct
compulsory daily briefings/training on the safe work methods and the
safety precautions stipulated in the Method Statement for all related
disciplines to all involved workers before commencing any works on
the Work Area and shall document the list of attendees for future
reference. Briefings/ training shall be given in a language understood
by the attendees.
(5) No person shall start work without receiving the required training and
briefings for the work to be carried out.
(6) In the event of a change in the work methods a revised Method
Statement shall be issued to the PDP/Owner for approval and re-
training shall be given to all persons involved.
(1) Normal working hours at the Site and Work Area shall be defined as
the period between 0700 hours and 1900 hours on all days excluding
General Holidays. Any works performed by the WPC outside normal
working hours (i.e. Night Work) and on General Holidays shall be
subject to having given the PDP and Civil WPC prior written
notification.
(2) The WPC shall inform the PDP and Civil WPC twenty four (24) hours,
or such shorter period permitted by the PDP, in advance of any
occasion when work outside normal working hours is proposed.
(3) Work in the Work Area within the Migration Section may be required
to be carried out within or outside normal working hours. The WPC
shall submit full details of any work requested to be carried out within
the Migration Section. Full permission by the SBK operator and
approval by the PDP will be required before any such work can be
carried out by the WPC.
(1) Detailed manufacturing drawings for plant and equipment for the
Permanent Works shall be available on the WPC's or his sub-
contractor's premises if required for review by the PDP. The WPC shall
also maintain at the Work Area a comprehensive and up-to-date set
of drawings properly indexed and catalogued, which shall include
complete sets of detailed working and, where applicable,
manufacturing drawings and shall permit free access to such drawings
by the PDP/Owner at any reasonable time.
(1) Where all or part of the Works is within a Railway Protection zone,
the WPC shall follow the provisions specified in this GS.
(1) All scaffold and temporary works structures used on the Works shall
fully comply with the following Malaysian standards:
a) MS 544 Part 12:2006 – Code of Practice for the structural use
of timber;
b) MS 282 Parts 1 to 9:1975 – Code of Practice for building
operations;
c) MS 1462-1:2012 Metal scaffolding Part 1 Prefabricated
scaffolds;
d) MS 1462-2-1:2010 Metal Scaffolding – tubular scaffolds and
specification for steel tubes;
e) MS 1462-2-2:2010 Metal Scaffolding – tubular scaffolds and
specification for aluminium tubes;
f) MS 1462-2-3:2011 Metal Scaffold specification for steel and
aluminium couplers, fittings and accessories;
g) MS 1462-3-1:2011 Metal Scaffold specification for steel and
aluminium couplers, fittings and accessories;
h) MS 1462-3-2:2012 Metal Scaffolding - prefabricated
scaffolding – specification for steel and aluminium modular
system scaffolds;
i) MS 1462-4-1:2013 Metal Scaffolding – equipment
performance requirements and general design;
j) MS 1462-4-2:2013 Metal Scaffolding – equipment information
on materials.
(2) Prefabricated scaffold frame systems or their component tubes shall
not have a wall thickness of less than 2.3mm.
(3) A-frame scaffold shall not be used.
(1) The WPC construction equipment and plant shall be less than ten (10)
years old when first utilised on the Work Area for the Execution of the
Works. The WPC shall implement a preventive maintenance
programme to ensure that all plant and equipment is maintained in
safe working order. The plant and equipment shall have a full
maintenance history which shall be in accordance the manufacturer’s
specification.
(2) All lifting machines, lifting appliances and lifting gear used on the
Work Area shall be suitable for the task, used within their safe load
capacity, in good condition and in accordance with the
manufacturer’s specification.
(3) The WPC shall engage a 3rd Party Independent Inspector to inspect
the lifting machinery prior to mobilisation to the Work Area and this
includes all rental cranes. The WPC shall verify the relevant document
from the crane rental company before entry of the crane to the Work
Area.
(4) The independent inspection of lifting machinery shall be carried out
annually for materials lifting operations and every 6-months for
personnel lifting operations. The 3rd Party Independent Inspector
shall be subject to approval by the PDP/Owner.
(5) In situations where a pre-mobilisation independent check is not
practical, such as a lorry loader being used for a one-off delivery to or
collection from the Work Area, the WPC shall ensure that the
appropriate Lifting Plan for the scheduled activity is in place and that
the capacity of the lifting equipment matches that in the Lifting Plan.
In all such situations, the lifting equipment shall first be inspected by
the Lifting Supervisor to confirm that all statutory requirements are
in place and that the equipment and operator are fit for the purpose.
(6) The WPC construction and installation equipment and plant shall be
fitted with protection and safety related devices as follows:
a) Internal combustion engine exhaust mufflers less than three
(3) years old;
b) Reverse travel motion alarms on all wheeled equipment;
c) Travel and slew motion alarms on all crawler mounted
equipment;
d) At least one rotating beacon (yellow or orange) on all mobile
plant and equipment;
e) Fully functional directional indicator lights, brake warning
lights, reversing lights and driving lights on all wheeled
equipment;
Protection of Work
(1) Finished work shall be protected by methods reviewed without
objection by the PDP from damage which could arise from the
execution of adjacent work.
(2) As part of his coordination responsibilities, the WPC shall ensure, so
far as is practicable, that work carried out by him or by Other Works
Contractors or utility undertakings does not cause damage to the
previously completed works of any party and he shall be responsible
for programming the works to minimise this risk and for proposing
protective measures, when required, by the PDP.
Payment of Costs
(1) The WPC shall pay all money deposits, bank guarantees, fees, charges
and other associated costs required to be deposited, given or paid
under any written law, by-laws, ordinance, regulation, rules and
requirements in relation to the Execution of the Works which are in
effect or which may become effective during the Contract period.
(1) The WPC shall produce a Technology Transfer Plan to identify to the
Owner and PDP those areas of his expertise which may be considered
suitable pursuant to a programme for technology transfer (ref.
Industrial Collaboration Programme, ICP).
(1) The WPC shall submit to the PDP/Owner for review evidence of his
proposed subcontractor’s competency and ability to deliver the
subcontracted works, including the proposed design documents of
the subcontractors proposed by the WPC. Without prejudice to the
rights of the PDP/Owner or the obligations of the WPC under
Conditions of Contract, the PDP/Owner shall have the right to reject
any or all of the sub-contractors, equipment, materials and/or
systems if, in the opinion of the PDP, they do not meet the
requirements of the Contract.
(1) The WPC shall comply with the dimensions of the relevant load gauge
and construction gauge during loading of Works Trains and
installation of equipment during construction. The Works shall not
infringe the applicable structure gauge.
(2) The WPC shall participate in gauging and sighting surveys as required
by the PDP.
(1) The WPC shall provide sufficient full-time staff to supervise the
fabrication of any identified element for the Permanent Works that is
to be fabricated off-Site, either within or outside Malaysia. As a
minimum, the WPC shall appoint a full-time Quality Control Engineer
and Supervisor / Foreman to lead the supervision of the off-Site
fabrication. The Quality Control Engineer and Supervisor / Foreman
shall be directly employed by the WPC and shall have adequate
experience in the specific pre-fabrication element to ensure
compliance with the QA/QC Plan.
(2) The WPC shall provide details, including CV’s of the Quality Control
Engineer and Supervisor/Foreman for review and acceptance by the
PDP/Owner.
(1) The overall periods during which installation of the Works will be
permissible within individual station and tunnel areas or line sections
are specified in the PS. During installation of Plant and Materials, the
WPC may need to work within or in close proximity to Other Works
Contractors in Restricted Areas. The WPC, in consultation with the
PDP, shall prepare a realistic installation and commissioning
programme that includes details of when and where access will be
needed to Restricted Areas. The programme shall be regularly
updated with progress achieved and any actual or possible revisions
to the future programme shall be given to the PDP at the earliest
possible moment. The actual period of entry to any individual station
or section of the Railway under Construction by the WPC will be
mutually agreed between the WPC, Other Works Contractors and the
PDP as set down in the Contract.
(1) The WPC shall etch, stamp or engrave a serial number on each major
assembly and sub-assembly of the Plant and Materials. The form of
the number and the method and position of marking shall be included
on Design Data submitted under the Contract for the Approval of the
PDP/Owner. The assemblies and sub- assemblies on which such serial
numbers are required will be determined by the PDP but shall be
generally those assemblies and sub-assemblies listed in the Pricing
Document. Serial numbers shall be listed on the Certificate of
Practical Completion.
*END OF SECTION*
(1) The WPC shall plan in detail the full scope of the Works taking into
account the complex nature and different phases and aspects of the
Contract and shall provide programmes which reflect the detailed
planning undertaken so as to ensure that the programmes are
realistic and achievable. All programmes developed by the WPC shall
be accompanied with the detailed supporting information.
(1) The WPC shall provide a detailed organisation chart providing full
definition of the responsibilities and qualifications of all personnel to
be involved in the planning, programming, project management and
progress monitoring of the Works. The proposed Planning Manager
requires a minimum of 8 years’ experience on large scale rail systems
projects to manage the planning, programming, and progress
monitoring of the Works.
(2) The WPC shall at the commencement of the Works confirm the
proposed full time Planning Manager as identified in his Tender
Proposal. Any proposed alternative Planning Manager shall be subject
to approval by PDP.
(3) The WPC Works Programme shall comply with the dates and
conditions set out in the PS.
(4) The WPC Works Programme shall have sufficient flexibility to
accommodate changes in the sequence of the Works within the
overall construction/installation period.
(1) The WPC shall develop and submit to the PDP/Owner for approval an
integrated Baseline Programme that fully captures the following
major phases, elements and sub-programmes, but not limited to:
a) Design, Procurement, Manufacturing, Factory Testing and
Inspection Programme;
b) Installation Programme (IP);
c) Testing & Commissioning Programme; and
d) Trial running.
(2) The following supplementary programmes shall also be submitted to
the PDP as part of the Monthly Progress Report, or as requested by
PDP:
a) Three Month Rolling Programme;
b) Time Chainage Programme;
c) Recovery Programmes, reflecting the current sequence of the
Works and demonstrating how the WPC will achieve his
Schedule of Access Dates and completion obligations under
the Contract; and
d) Any other programmes required by the PDP.
(1) The WPC shall monitor his performance against his programmes or
others as required by the PDP. The WPC monitoring of the Works
shall include for direct daily monitoring of the progress of the Works
and the preparation of written and computerised reports (including
all necessary supporting data) submitted in formats acceptable to the
PDP and at period(s) determined by the PDP. These reports shall
include as a minimum:
a) Installation Progress: a summary of installation progress, with
details of any areas of concern or delay and any areas of
technical difficulties incurred or expected specifically
highlighted, together with details of the WPC proposals for
corrective actions;
b) Layout plans marked up to identify the extent of work
completed in the reporting period and cumulative to date for
each major activity;
c) Comparative production curves and histograms showing
actual versus planned performance in respect of major
quantities as required by the PDP;
d) Details of actual manpower and plant on the Work Area for
the period, compared with that planned in the WPC
programmes;
e) Design: a design summary, including critical design issues and
interfaces and the status of design submissions;
(5) In addition to the requirements of Clause 6.6.1 (1) and (2), the WPC
shall submit his preliminary Baseline Programme to the PDP/Owner
within 21 days of the date of the Letter of Acceptance. The
preliminary Baseline Programme shall include the requirements set
down in 6.6.1 Sub Section (3), items a), b), c) and d). The WPC shall
obtain the PDP/Owner agreement to the full version of the Baseline
Programme within 60 days after submission of the initial version. Any
resubmission of the Baseline Programme shall be completed within
14 days of the receipt of PDP/Owner comments by the WPC.
(6) Baseline Programme Revisions: if it becomes apparent that the WPC’s
rate of progress may not achieve the Schedule of Access Dates or
other requirements of the Contract and the PDP requests it, or if an
extension of time has been granted by the PDP, the WPC shall revise
his programme clearly showing how he will ensure that the Schedule
of Access Dates and other requirements of the Contract are to be
achieved.
(7) The revised Baseline Programme shall be developed from the
accepted Baseline Programme, incorporating any necessary
mitigation and recovery measures, for the PDP’s review and
acceptance. Actual progress of activities shall be updated to a
minimum of one month before the submission of the revised Baseline
Programme. Once approved, the revised Baseline Programme shall
become the new accepted Baseline Programme.
(8) The acceptance of any programme shall not inhibit the revision of the
Baseline Programme to suit the needs of the Contract, nor shall it
specifically relieve the WPC of any of his obligations under the
Contract. The WPC shall not revise any part of the Baseline
Programme without the explicit agreement of the PDP.
(4) Details of the activities and the timing involved as required by the
Other Works Contractors shall be fully coordinated by the WPC.
(5) The IP shall be produced and agreed by the WPC with all Other Works
Contractors, indicating the access, sequence, nature of work and
extent of the Works including architectural finishes, at the various
stages of the Works. The WPC shall also assist the Other Works
Contractors in the preparation of their IPs and the Civils WPCs with
preparing their Coordinated Installation Programmes (CIP)s.
(6) The WPC shall co-operate and work with the respective Other Works
Contractors to achieve particular Degrees of Completion for all rooms
and areas to allow for access in accordance with the IP.
(7) The Installation Programme shall be developed with particular
reference to the Key Dates shown in the Conditions of Contract taking
into account the interfacing Schedule of Access Dates of the
respective Other Works Contractors. The requirements of the
Degrees of Completion as defined in the PS shall be complied with in
the preparation of the Installation Programme (IP).
(8) For all rooms and areas including public areas, the WPC shall
coordinate and schedule his Works and that of the Other Works
Contractors in the IP in such a manner and sequence so as to facilitate
the completion of System-wide Integrated Testing and
Commissioning before Test Running and shall include details of
mitigation proposals, where required.
(9) The WPC shall manage the access requirements as agreed in the IP.
The status of the work shall be tracked and reported regularly against
the accepted IP to reflect the progress of the interfacing co-ordination
with Other Works Contractors including the WPC. The format and
frequency of the report shall be agreed with and accepted by the PDP.
The WPC shall chair or attend meetings with the Other Works
Contractors, as required. Where access is not given, it shall be
highlighted to the PDP and this shall include information on the
parties failing to provide the access, the affected party and the
mitigation measures to be used to ensure the Schedule of Access
Dates and overall programme are achieved.
(10) The PDP will review the WPC’s IP to ensure that it is compatible with
the requirements of the overall Project. The PDP will then approve
the IP, or advise the WPC of any changes required. The WPC will
support the Civil WPC in responding to any issues relating to systems
aspects of the IP. Any approval, review or comment by the PDP shall
not constitute a waiver, nor relieve the WPC of any of his duties,
responsibilities, obligations or liabilities under the Contract. Once
approved, the IP shall be updated regularly by the WPC on dates to
be advised by the PDP. The WPC shall note that any such revision to
the activities and timing of the IP shall not be construed as a variation
under the terms of the Contract.
(11) The WPC shall also prepare a schematic version of his full IP, clearly
showing the interface activities and dates, signed off by the Other
Works Contractors involved and to the satisfaction of the PDP. The
format of this schematic version shall be agreed with the PDP.
(1) The WPC shall submit to the PDP a Schedule showing the dates when
he shall submit the design details (“the Schedule of Designs”) which
he is required to submit under the Contract.
(2) The Schedule of Designs shall comprise a complete listing of all design
packages, drawings and other design deliverables that the WPC shall
be required to submit for his design on a progressive basis and to
meet the programme requirements of the Contract. The Schedule of
Designs shall be included in the WPC programmes.
(3) The Schedule of Designs shall provide the baseline against which
design progress shall be measured and reported each month, along
with the Monthly Progress Report, or as required by the PDP. The
WPC shall submit an updated hard and electronic copy of the
Schedule of Designs stating the percentage completion for each
design package, drawings and design deliverables.
(4) The Schedule of Designs shall include but shall not be limited to the
following:
a) Specifications and design criteria, e.g. flow sheets, flow
diagrams, calculations, philosophy, specifications, staging
plans, schedules, certificates, computer data, safety studies,
models and letters of approval;
b) Drawings submissions, e.g. plans, general arrangements,
layout, cable/duct/pipe routing, sections/elevations,
isometrics, fixing details, assembly and detail drawings;
c) Samples, patterns, methods of manufacture and testing;
d) Software management and control, e.g. instrument indices,
utilities estimates, instrument datasheets, instrument
location drawings, control room layout drawings, logic
diagrams, hook-up drawings, block diagrams, connection
diagrams, loop diagrams, schematics and specifications;
e) CSDs, SEMs and shop drawings for Systems installation,
including openings and fixing requirements coordinated with
Systems, M&E and Other Works Contractors, to the approval
of Systems and PDP.
(5) The Schedule of Designs shall provide the following information for
each design package or design deliverable:
a) WPC Submission Form (SCSF) number;
b) Drawing number, equipment number, etc.;
c) Revision;
d) Description and reference to the Specifications.
e) Geographical location, chainage, grid line, etc.;
f) Planned submission and reply dates;
g) Actual submission and reply dates;
h) Status of approval;
i) Weighting factor;
j) Progress percentage.
(6) Each design package or design deliverable shall be weighted in terms
of percentage or agreed units of the whole scope of the design, in
order that the overall progress percentage of each major element,
stage, or phase of the design process can be accurately reflected. This
weighting factor shall be in accordance with the requirements of the
PDP’s Planning and Programme Guidelines shown in Appendix E.
(7) The Schedule of Designs shall be included in the WPC Baseline
Programme and other Programmes. It shall provide the baseline
against which the design progress is measured and reported. The
WPC shall provide updates of the Schedule of Designs at period(s) to
be determined by the PDP.
(1) The WPC shall submit to the PDP on a fortnightly basis or at such other
times as may be determined by the PDP, concise fortnightly returns
of all construction equipment and labour on site categorised
respectively by plant type and trade. The fortnightly returns shall be
prepared in a format to be provided by the PDP.
(2) If required by the PDP, the WPC shall also supply a weekly report
detailing quantities of major items of work completed on a daily basis.
(1) The PDP will chair monthly progress meetings with the WPC. These
meetings will be held at dates, intervals and times as determined by
the PDP. The agenda for the monthly progress meeting shall follow
the contents of the Monthly Progress Report.
(2) The WPC shall submit a Monthly Progress Report to the PDP on the
day of each month specified in the Contract or as directed by the PDP.
The Monthly Progress Report shall be prepared in accordance with
the PDP requirements and shall include, but shall not be limited to,
the following items:
a) Executive Summary;
A summary of major events, overall progress, delays, recovery,
and financial matters.
WPC organisation chart highlighting any changes to key
personnel.
b) Contract Summary;
Contract Particulars and Variation Orders. This section shall
contain detailed information about the financial and commercial
status of the Contract, including details of actual and anticipated
claims covering cost and time extensions.
Appendix A – List of Consultants
Appendix B – List of Subcontractors
c) Design Progress / Manufacturing Progress / Installation
Progress / Testing and Commissioning Progress / Trial
Operations;
A summary of the WPC’s manufacturing / installation progress
with details of any areas of concern or delay and any areas of
technical difficulties incurred or expected to be specifically
highlighted, together with details of the WPC proposals for
corrective actions. A summary of manpower, plant and
equipment on site shall also be included.
Appendix C - Hard copy of the current Three Month Rolling
Programme in bar chart format with a progress line representing
progress achieved up to the end of the month.
Appendix D - A turn-around document comprising a listing of
ongoing, forthcoming (next 3 months) and recently completed
programme activities showing actual start and finish dates,
percentage completions, forecast start and finish dates,
remaining duration and a status in terms of +/‐ weeks. The
format shall be in accordance with the PDP’s requirements.
Appendix E – Not Used.
Appendix F - Comparative production curves and histograms
showing actual versus planned performance in respect of major
preventive measures.
Appendix L - Safety and Health Statistics for Incidents (frequency,
severity and lost time injury rates), Status of all internal and
external Non-Conformities (observations, non-conformance
reports & stop work orders), Training Completion Records
(induction, tool box, job safety analysis briefings, plant operator
and other formal training activities).
h) Environmental Management;
A summary of the status of implementation of environmental
requirements, including details of; planned significant
environmental activities for the forthcoming month, external
parties’ inspection and audits and any significant environmental
incidents, non-conformities trends and associated corrective
and preventive measures.
Appendix M – Not Used.
i) Quality Assurance and Quality Control;
This section shall contain the status and progress reports on
Quality Assurance and Quality Control programme activities,
such as works inspection status, testing status, works non-
conformities trends, system audit activity highlights, findings and
corrective actions, problems discovered during inspections and
testing and how these problems were/will be resolved,
programme implementation issues, etc.
Appendix N – Works non-conformance statistics and Corrective
Action Report.
j) Progress Videos and Photographs;
k) Updated Baseline Programme (in .XER format) with progress
update status as at the report cut-off date as specified by PDP;
l) Risk Management / Register Report, as required by the GS Risk
Management Chapter;
m) Other items as required and to be advised by the PDP;
n) Systems Assurance – status and progress;
o) System Interface Management – status and progress.
(1) The WPC shall submit a Programme Analysis Report to the PDP
together with the Monthly Progress Report and all related
programme submissions which shall comprise a narrative statement
that identifies the basis of the WPC assumptions and to include:
a) The content required to be included in any programme or
supporting document needs to be clearly identified and
described to ensure a clear understanding of the scope /
requirements of each document provided, i.e. activity detail
and activity durations, sequence of working etc.;
b) The critical path of the Works;
c) Daily and weekly working hours, holidays and shift patterns;
d) Assumed production outputs for all major activities and areas
of the Works;
e) An overall manpower forecast detailing individual trades and
other sub-contract / indirect labour, commissioning teams
etc. to illustrate the build-up of manpower resources. The
format is to be in accordance with the PDP’s requirements;
f) Details of the total quantities and planned production
outputs, i.e. basis of durations and fully detailed typical cycle
time analyses;
g) List of major items of plant or equipment that are required to
be procured identifying the required lead times;
h) S-curves and histograms showing the planned weekly figures
for each principle quantity, major items of equipment and
major manpower trades;
i) Any programme constraints, giving details of the constraints
and the substantiation thereto;
j) When supplied with a Three Month Rolling Programme or
current Baseline Programme, it shall include a summary of
progress achieved in the previous period in terms of principle
quantities (planned versus actual) and time gain / loss in terms
of days for each activity;
*END OF SECTION*
7.1 Introduction
(1) This section applies to all project risks arising from all activities
undertaken by the WPC throughout all phases of the Contract and the
Defects Liability Period, inclusive of those activities undertaken by the
WPC’s subcontractors and suppliers.
(1) The WPC shall produce a Risk Management Plan in accordance with
ISO 31000 and/or PMI-Standard Practice for Project Risk
Management. The Risk Management Plan shall describe how the WPC
intends to:
a) Integrate risk management into the team culture, planning,
construction activities and decision making processes;
b) Anticipate and respond to the changing nature of the works,
social, environmental and regulatory requirements
proactively;
c) Mitigate risks pragmatically to an as low as reasonably
practicable level given the particular circumstances of each
situation;
d) Implement a robust and sustainable risk register that is in
accordance with the Risk Management Plan, and
e) Ensure consistency and uniformity for all project risk
mitigation measures as well as providing a basis for the review
and control of the mitigation measures.
(2) The WPC shall prepare and submit to the PDP his Risk Management
Plan in accordance with the RMP template provided in the
Specifications, for approval within thirty (30) days from the date of
the Letter of Acceptance.
(3) The Risk Management Plan shall describe the risk management
practices to be applied on a day-to-day basis by the WPC. The RMP is
a key communication tool for risk management and shall be made
accessible to the WPC’s personnel and those of his subcontractors.
(4) The WPC shall review the RMP periodically (at least once every 6
months) or as required by the PDP to ensure that the document is
(1) At all times throughout the duration of the Contract the WPC shall
engage at least one Risk Representative to be based full time on the
Project.
(2) The WPC shall submit the Risk Representative’s CV and credentials to
the PDP/Owner for approval.
(3) The Risk Representative shall be suitably qualified (minimum degree
qualification) and ideally shall have at least ten (10) years of
experience in risk management and as a minimum, Assistant Manager
level position.
(4) The Risk Representative shall be employed solely on project risk
management activities.
(1) The WPC shall establish an effective risk reporting structure to enable
structured communication in managing and supporting the risk
management process.
(2) The WPC senior site representative (Project Director or equivalent)
shall be responsible for the overall risk management function. The
Risk Representative shall have a direct line of reporting to the WPC
senior site representative. Details of the WPC risk management
organisational structure, including individual roles and
responsibilities, shall be included within the RMP.
(3) The WPC shall maintain its risk management organisational structure
throughout the duration of the contract and shall revise and submit
to the PDP/Owner for approval any proposed changes.
(1) The WPC shall establish a risk function which comprises a qualified
and competent project team with clearly defined roles and
responsibilities pertaining to effective risk management
implementation throughout the WPC organisation.
(1) The WPC shall ensure that managerial staff in the WPC project team
are trained and made aware of their roles, responsibilities and
accountabilities to ensure the effectiveness of the implementation of
risk management within the contract.
(2) The WPC shall ensure that the Risk Representative and key
managerial staff are trained (external/internal) on specific project risk
management courses in order to improve their risk management
competency development. Refresher training on risk awareness shall
be conducted at least once a year.
(3) The WPC shall invite the PDP to observe all risk training sessions.
(4) The PDP will provide risk database training for the WPC Risk
Representative on “train the trainer” concept. More specifically, the
training will include the risk management elements and requirements
as stated in the Contract, ISO 31000 and/or PMI-Practice Standard for
Project Risk Management.
(1) The WPC shall implement a risk management process which shall:
a) Identify risks and associated risks and their impact on the
Works in terms of programme, cost, third parties and
environmental impact;
b) Analyse risks by estimating the probability of their occurrence
and the time and cost impact of each risk event;
c) Minimise the impact of risks on the project objectives through
the identification and implementation of appropriate risk
mitigation measures;
d) Allocate risks to the most appropriate risk actionee to
implement the risk mitigations, and
(1) Within thirty (30) days from the submission date of the WPC RMP, the
WPC shall undertake an initial risk workshop to consider all associated
risks on the Contract and to populate the WPC risk database.
Following the initial populating of the WPC risk database, the WPC
shall be responsible for the regular updating and use of the risk
database as a management tool.
(2) The WPC shall review and update the risks stored in the risk database
regularly (at least once every month) to ensure that the risk
information is current.
(3) The PDP will provide an initial risk register for the WPC information in
the Specifications. The initial risk register shall not relieve the WPC of
its obligations to identify and mitigate the contract risks.
(4) The WPC shall systematically identify all possible risks which have a
potential impact on the Project.
(1) The WPC shall schedule and attend regular monthly risk workshops to
identify and review risks on the Contract and to update his risk
database. The risk workshops shall be held at the PDP’s office or other
location as approved by PDP.
(2) The risk workshops shall be led by a competent member (ideally
Project Director/ Project Manager) of the WPC team who has
experience in the construction methods proposed and in risk
management and shall be facilitated by the WPC’s Risk
Representative. Other WPC management staff, including risk owners,
who are involved in daily construction activities, shall be required to
attend the risk workshops.
(3) The WPC shall invite representatives from the PDP to attend each risk
workshop to assist and actively participate in risk identification and
the review and development of associated risk mitigation measures.
From time to time, the PDP may instruct the WPC to invite
representatives of the Owner, Independent Consultant Engineers and
(1) The PDP will provide the risk database and one user licence for the
WPC use. The WPC shall maintain a record of all identified risks and
issues and opportunities, including their status and history, in the risk
database. The WPC shall be responsible for updating and maintaining
the risk database on an ongoing basis throughout the Contract
duration.
(1) The WPC shall use the Probability Cost/Time Impact Grid in the PDP
risk management template to estimate the probability of occurrence
of a risk and the time and cost impacts of each risk event.
(1) The WPC shall minimise the impact of risks on the project through the
identification and carrying out of appropriate mitigation actions.
(2) Risk mitigations shall be SMART i.e. specific, measurable, attainable,
realistic and time-bound.
(3) Risk mitigations recorded in the risk database shall be complete,
unambiguous and sufficient to reduce the risk level to as low as
reasonably practicable (ALARP). They shall also be described in
sufficient detail that they can be readily understood.
(4) Risk mitigations for each single risk shall be allocated a risk owner who
shall be a staff member of the WPC and shall be responsible for
ensuring that the mitigation measures identified on that risk are
completed as required.
(5) Evidence of actions completed shall be submitted via the risk
management check list in the PDP’s web-based project risk database.
(1) Through the monthly risk workshops the WPC shall review the current
risk exposure and as appropriate the probabilities of occurrence and
associated impacts.
(2) Through the monthly risk workshops the WPC shall actively monitor
the implementation of risk mitigation measures. Any necessary
changes to previously agreed mitigations shall be recorded in the risk
database.
7.14 Reporting
Progress Dashboard
(1) On a monthly basis the WPC shall include the top five risks and issues
in its progress dashboard.
(1) Residual project risks are defined as those project risks that have a
probability of occurrence greater than zero and could affect future
railway operations. The WPC shall use the risk close out process to
identify residual project risks for handover to the Owner at
completion of the handover phase of the Project.
(2) The WPC shall submit to the PDP/Owner for approval its Project Risk
Close-Out Register prior to issuance of the Certificate of Practical
Completion. The Project Risk Close-Out Register shall form one of the
conditions precedent to issuance of the Certificate of Practical
Completion.
(1) The PDP will undertake audits on the WPC on the effectiveness of
their implementation of risk management activities as stated in the
Risk Management Plan and on the policy and procedures as set out in
the Contract. Audits will be conducted once every six (6) months
throughout the duration of the Contract.
(2) Should there be any unsatisfactory observations or non-
conformances identified during the audit, the WPC shall propose
corrective / preventive actions, together with an appropriate close
out date, within 14 days after receiving the audit report to the
PDP/Owner for approval.
(3) The PDP/Owner will approve the proposed corrective actions and
verify and accept the proposed corrective / preventive actions by the
WPC. Subsequently the PDP will verify the evidence for closure of the
unsatisfactory observation/NCR during the next audit.
(4) The PDP will inform and may invite the Owner to attend and observe
the audit sessions.
*END OF SECTION*
8 ENVIRONMENTAL MANAGEMENT
(1) Each WPC shall assess the provisions in this Section that are
applicable to their Work Package. The results of this assessment shall
be submitted for approval by the PDP/Owner.
(2) In performing the Works, the WPC shall comply with all statutory
requirements of ISO14001 and the particular requirements set out in
this Chapter, in order to preserve and take due care of the local
environment.
(3) The WPC shall be responsible for obtaining any necessary
environmental approvals from the Relevant Authorities. Untimely
receipt of approvals which may affect the WPC construction
programme shall not in any way be a basis for consideration of time
extension or variation to the Contract.
(4) The WPC shall take all necessary actions to comply with all
requirements for protecting the environment. Should the WPC fail to
do so, the PDP may appoint others to take the necessary actions and
all associated costs shall be borne by the WPC.
(5) Any complaints relating to environmental issues that are received by
the WPC shall be immediately forwarded to the PDP and attended by
the WPC. A record of any such complaint and the actions taken by the
WPC and a summary of such complaints, shall be provided in the
Monthly Report.
(6) The WPC shall submit a copy of all correspondence sent to or received
from the Environmental Authorities to the PDP upon transmission or
receipt.
(7) The WPC shall ensure that all subcontractors employed on the Work
Area comply with all environmental requirements. The WPC shall
ensure that adequate provisions are included in all of their
subcontracts.
(8) The WPC shall bear the cost of complying with all environmental
requirements.
(9) The WPC shall provide a written Environmental Policy stating that
environmental concepts are a proactive and integral part of his
business strategy. The Environmental Policy shall be formally
(1) The WPC shall identify all Legal and other Statutory Requirements
related to the work activities and shall communicate the
requirements to their employees and subcontractors.
(2) Prior to and during the execution of the Works, the WPC shall comply
with the Environmental Quality Act 1974 (Act 127 & Subsidiary
Legislation) and other related environmental legislation and
associated guidelines including, but not limited to:
a) National Land Code (Act 56 of 1965);
b) Town and Country Planning Act 1976, (Act 172);
c) Street, Drainage and Building Act, 1974: Act 133 and
Amendment, 1978;
d) Protection of Wildlife Act, 1972 (Act 76);
e) Land Conservation Act 1960 (Act 385);
f) Occupational Safety and Health Act 1994 (Act 514);
g) Solid Waste and Public Cleansing Management Act 2007 (Act
672);
h) Federal Territory (Planning) Act 1982;
i) Local Government Act 1976 (Act 171);
j) Land Transport Act 2010;
(1) The DEIA has been prepared by The Owner in association with the
PDP as required in the Environmental Quality (Prescribed Activities)
(Environmental Impact Assessment) Order of 1987. Approval of the
DEIA has been obtained by The Owner. The WPC shall fully comply
with all relevant DEIA approval conditions from the Department of
Environment (DOE) for this Project.
(2) Prior to and during the execution of the Works, the WPC shall fully
comply with all relevant DEIA approval conditions (Refer to
Attachment AG8.1) from the Department of Environment for this
Project, including:
a) Compliance with Mitigation and Control Measures as stated
in the DEIA Report;
b) Installation and Operation Design;
c) Monitoring of Noise and Vibration;
d) Control and Monitoring of Air Quality;
e) Control and Monitoring of Water Quality;
f) Management of Solid Waste and Scheduled Waste;
g) Environmental Management Plan, EMP;
h) Environmental Audits;
i) Reports;
j) Administrative.
(3) The DEIA approval conditions shall be displayed in a suitable place
and be clearly visible at the WPC’s Work Area office.
(4) The WPC shall provide his subcontractors with copies of the DEIA
approval conditions and shall incorporate a requirement to comply
with it into all of his sub-contracts.
(5) The WPC may coordinate and liaise with the Civil WPC when
developing and implementing work plans and procedures,
monitoring, enforcement, training etc. needed to comply with the
DEIA approval conditions and approval by the PDP. However, nothing
shall take away the ultimate responsibility of the WPC for complying
with all of the DEIA approval conditions for his Works.
(6) If the WPC considers that any requirements of the DEIA do not apply
to his works, he may apply for an exemption(s) from the relevant
governing bodies. Unless and until an exemption(s) is granted then all
relevant requirements of this Clause 8 shall apply. Any costs
associated with applying for an exemption shall be borne by the WPC.
(1) The Master EMP for the overall Project has been prepared by The
Owner and approval for it has been obtained. The WPC shall comply
with the Master EMP for this Contract.
(2) Within thirty (30) days from the Letter of Acceptance, the WPC shall
prepare and submit for the approval of the PDP/Owner a Package
EMP that details the way in which the WPC will comply with the
environmental requirements that relate to the Works with reference
to the Master EMP. In the formulation of the Package EMP the WPC
shall refer to the Master EMP, General Specification and Particular
Specification and shall adopt the standards and instructions
contained therein. The Package EMP shall follow the format given by
Department of Environment (DOE) as per “Lampiran A” in the DEIA
Approval Conditions.
(3) The WPC shall submit its Package EMP to the Department of
Environment in the respective states (via the Owner) for approval.
(4) The WPC shall provide his subcontractors with copies of the approved
WPC Package EMP and shall incorporate the Package EMP
requirement into all sub-contracts and ensure that his subcontractors
fully comply with the EMP requirement.
(5) No construction or installation activities shall commence and no WPC
invoices shall be processed until the WPC Package EMP has been
reviewed and approved by the Department of Environment (DOE).
(6) The WPC Package EMP shall contain the WPC Environmental Policy.
The Environmental Policy shall indicate that a pro-active approach
will be adopted by the WPC on environmental requirements.
(7) The roles and responsibilities of both the Environmental Manager,
Environmental Officer and other supporting staff shall be clearly
defined in the WPC Package EMP.
(8) The WPC Package EMP shall include a reference to and indicate
compliance with the following:
a) The approved DEIA and related approval conditions;
b) The Master Environmental Management Plan (EMP);
c) The Master Erosion and Sedimentation Control Plan(ESCP);
d) General Specification and Particular Specification;
e) Department of Environment Guidelines on preparation of
EMPs, and
f) ISO 14001 Environmental Management System.
(9) The Package EMP is a document for practical use on the Work Area
and shall at all times be concise, current and specific to the Work
Area.
(10) The Package EMP shall be formally reviewed at least half yearly and
within 30 days after the appointment of sub-contractors and shall be
revised after any changes in the design or construction of the Works
that may affect the environment. In the event that changes are made,
approval from Department of Environment (DOE) is required (via The
Owner’s submission).
(1) The Master ESCP for the overall Project has been prepared by the
Owner and approval has been obtained. The WPC shall comply with
the Master ESCP at all times.
(2) The WPC shall prepare and implement a Package ESCP for the
stormwater management design and construction works which shall:
a) Be prepared in accordance with the Guideline for Erosion and
Sediment Control in Malaysia, Urban Stormwater
Management Manual for Malaysia, MSMA published by the
Department of Irrigation and Drainage (DID) with reference to
the Master ESCP;
b) Be endorsed by a practicing Professional Engineer and
reviewed by a Certified Professional in Erosion and Sediment
Control (CPESC) and approved by the Department of Irrigation
and Drainage (DID);
(1) The WPC shall liaise and coordinate with the Civil WPC and establish,
implement and maintain the Waste Management Plan (WMP). The
WMP shall include the solid waste, unsuitable material disposal,
muck and scheduled waste management.
(2) The WMP shall conform to the requirements of the relevant
authorities.
(3) The WMP shall be formally reviewed at least once per year and
revised after any changes in the storage location, licensed contractor
or disposal location. The WMP shall be submitted to PDP for review
and approval by PDP and the relevant authorities (via the Owner’s
submission).
8.9 Deliverables
(1) The following documents shall be submitted by the WPC to the PDP:
No of Copies
No of Copies
(1) The WPC shall carry out a detailed Environmental Aspects and
Impacts assessment for each site activity and for particular conditions
on the Work Area. Environmental Aspects and Impacts shall include
those environmental risks related to the prevention of actual or
potential threat of adverse effects on living organisms and living
environment by effluent, emissions, waste resources depletion and
material loss.
(2) The results of this process shall be compiled into an Environmental
Aspects and Impacts Register and shall be reviewed and approved by
the PDP/Owner. The Environmental Aspects and Impacts Register
shall be endorsed by the WPC representative and Safety, Health and
Environmental Head of Department.
(3) The WPC shall comply with the PDP Environmental Aspects and
Impacts procedure (Refer to Attachment AG8.2) in developing the
Environmental Aspects and Impacts Register.
(4) The Environmental Aspects and Impacts Register shall be reviewed
following any changes to the design, operating processes,
specification, Management System, modification in equipment,
occurrence of incidents, changes to legal and other requirements and
other relevant changes. The reviewed and revised Environmental
Aspects and Impacts Register shall be submitted to the PDP/Owner
for review and approval.
(5) The control measures that are necessary to eliminate or minimise
pollution shall be put in place prior to commencing the associated
work and all personnel involved in the work shall be made aware of
the actual or potential threat of adverse effects and necessary control
measures.
(6) Specific Environmental Aspects and Impacts assessment shall be
conducted for every trade of work and attached in the Method
Statement.
and within the stipulated time frame, and shall use the findings to
update the Risk Register to prevent any re-occurrence.
(12) The outcome of the Report shall be communicated among the WPC
staff, workers and subcontractors and shall be included as an item in
the WPC monthly Safety, Health and Environmental Report.
(1) The WPC shall establish, for the approval of the PDP, a Work Area
monitoring, inspection and auditing regime in accordance with the
Project and Package EMP, the GS and the PS. The PDP has the right to
conduct monitoring, inspection and auditing at any time. The WPC
shall cooperate fully with these activities and shall rectify any
deficiencies at its own cost and within the specified time limits.
(2) The WPC shall engage an accredited laboratory to carry out
monitoring proposed in the WPC Package EMP, namely river water
quality, air quality, noise and vibration levels and others stated in the
DEIA and associated approval conditions.
(3) The WPC shall carry out the necessary baseline monitoring in
accordance with the DEIA to measure air quality, water quality, noise
levels, and vibration levels at locations to be approved by the
Department of Environment, prior to commencing the Works on Site.
Noise and vibration shall be monitored prior to construction by
recognised acoustic experts.
(4) The WPC shall have adequate in-situ instruments i.e. pH Meter,
Dissolved Oxygen Meter, Total Suspended Solid, Turbidity, noise level
measurement etc. on the worksite and the instruments shall be
calibrated by an accredited service provider within the allowable
period.
(5) The WPC shall submit the Quarterly Environmental Monitoring
Report to the PDP on the first day of each quarter month.
(6) The WPC shall provide evidence of ongoing performance of the
environmental management and control implementation
performance in the form of a monthly progress report, the contents
of which will be specified by the PDP.
(1) The WPC shall establish and conduct physical site environmental
inspections on a weekly basis and shall submit the summary of
inspection status to the PDP.
(2) The WPC Environmental Officer shall:
a) Supervise and monitor all the erosion and sediment control
components as stipulated in the WPC Package ESCP and EMP;
b) Update the daily log book;
c) Update the rainfall data;
d) Take readings and record the rain gauge data, and
e) Conduct inspections of pollution control measures and
structural best management practices of erosion and
sediment control.
(3) The WPC senior site representative shall lead the weekly Work Area
inspection with the environmental manager and their sub-
contractors’ representatives. He shall record his findings in the Work
Area Inspection records and act immediately upon any deficiencies
found.
(4) The PDP has the right to inspect the environmental performance of
the WPC at any time. The WPC shall cooperate with such inspections
and shall take action to correct any deficiencies. The corrective action
evidence shall be submitted to the PDP within 7 days for review.
8.14 Auditing
(1) The PDP has the right to conduct environmental audits on the WPC.
Any such audits will be formally notified and subsequently reported
to the WPC. However, the PDP reserves the right to conduct
unscheduled audits. The WPC shall co-operate with such audits and
shall take action to correct any non-conformities reported at the
WPC’s own cost.
(2) Within 7 days of receiving the PDP Audit Report, the WPC shall submit
to the PDP a Post Audit Action Plan detailing the actions to be taken
to rectify the auditor’s observations, the person(s) who will carry out
the actions and the date by which they will be completed.
(3) The WPC shall establish a procedure and schedule to conduct its own
site environmental audit at each Work Area on a quarterly basis and
submit the summary of audit status to the PDP.
(4) The WPC shall cooperate with any 3rd Party environmental audit
programme. The WPC shall take appropriate corrective and
preventive actions at the WPC’s own cost, for all identified
deficiencies relating to audit findings.
8.16 Meetings
(1)
` The WPC shall attend any environmental management meetings held
by the PDP.
(2) The WPC shall ensure that environmental issues relating to DEIA
Approval Conditions Compliance, Best Management Practices (BMPs)
and ESCP condition status are discussed at all senior management
meetings and sub-contractors meetings every fortnight. In addition,
they shall ensure that they deploy competent representatives to
attend any environmental meetings with stakeholders that they are
required to attend.
(3) The WPC shall facilitate site meetings on the environment with the
PDP and other stakeholders as required. Arrangements for such
meetings shall include the provision of adequate equipped meeting
rooms, recording and distribution of written minutes of the meeting
within three (3) days after each meeting.
(1) During the performance of Works, if the PDP observes that the WPC
is:
a) Not conducting the work in compliance with the approved
Environmental Management Plan, Method Statements,
procedures, relevant legislation, PDP’s Environmental
Operational Control requirements or contractual
requirements; and / or is
(1) The WPC shall be subject to the PDP Safety, Health and Environmental
performance measurement scheme whereby payment against the
SHE Bill is linked to the WPC Safety, Health and Environmental
performance on a monthly basis. The PDP will measure the WPC
Safety, Health and Environment performance based on the defined
Safety, Health and Environmental Key Performance Indicators (KPIs)
in accordance with, but not limited to, the following:
a) Monthly Safety, Health and Environmental Assessment;
b) NCR Closure Rate;
c) Number of Incidents threatening public safety and caused
inconvenience to public;
d) Incident Rate (reportable incidents);
e) Number of Stop Work Orders.
(2) The Safety, Health and Environmental KPIs and evaluation criteria will
be reviewed periodically to ensure they meet the project
requirements and to facilitate continual improvements.
(1) The WPC shall establish, implement and maintain the Environmental
Operation Controls as per listed below. Environmental Operation
Controls shall include, but not be limited to:
a) 8.21 Air Quality Control;
(17) Activities producing dust such as drilling, hacking, cutting and etc.
shall be sprayed with water to prevent dust being churned up.
(18) Blasting mats shall be used whenever blasting works are carried out.
(14) Oil storage and workshop facilities shall be located away from water
courses.
(15) Pumping facilities shall be made available for pumping oil.
(16) All oil and grease accumulations in bunded areas shall be cleaned and
disposed of as scheduled waste.
(17) Clean rainwater that accumulates in bunded areas shall be pumped
out and drained to the adjacent waterway.
(18) Workshop areas shall have a concrete base and drainage with oil and
grease traps.
(19) All portable fuel storage containers not limited to fuel tank, fuel
drums, diesel containers or any vessel containing oil shall be provided
with a drip tray as secondary containment at all times.
(20) All portable equipment not limited to water pumps, bar bending
machines, generator sets, compressors that use liquid as a fuel shall
be provided with a drip tray at all times.
(21) Temporary toilet facilities shall be provided and fulfil the specification
specified from ‘Kementerian Kesihatan Suruhanjaya Perkhidmatan
Air Negara (SPAN)’ and shall be maintained in good condition at all
times.
(22) Sewage discharge into water courses is prohibited. Sewage shall be
collected in tanks or routed to an approved sewer.
(23) Desludging shall be carried out regularly to prevent any overflow from
the sewage collection tank. Only licensed contractors shall carry out
desludging work.
(24) All necessary precautions shall be taken to prevent debris,
overburden, slurry, rubbish, silt, waste materials and pollutants from
entering existing waterways, public roads, commercial and residential
areas.
(25) Water from all canteen facilities shall be routed through a grease trap
which shall be regularly maintained by the WPC.
(26) Used containers shall not be scattered on the worksite.
(27) Organic solvents shall be stored in closed containers at designated
hazardous material storage areas which shall be located away from
water courses and drainage systems.
(28) Emergency spill kits shall be provided at the worksite to contain any
oil or used oil spillage.
(1) Site clearing works shall be limited to construction areas only. As far
as practicable, existing vegetation shall be preserved as a natural
buffer zone between cleared land and watercourses.
(2) All earthwork activity shall be conducted in accordance with the
sequence of the approved Method Statement. Construction activities
shall be conducted in stages to reduce the amount and duration of
exposed soil areas. Exposed soil areas shall be compacted and graded
to channel surface runoff.
(3) Earth stockpiles shall be protected with protective sheeting.
Protective sheeting for earth stockpiles shall be securely anchored.
Bunds and drains shall be constructed around earth stockpile areas to
channel surface runoff.
(4) Earth stockpile areas shall be located away from the surface runoff
channels and watercourses.
(5) Top soil and unsuitable materials shall only be disposed of at
approved landfill sites operated by the Local Authority.
(6) Temporary erosion protection for exposed slopes under construction
shall be provided until such time as permanent protection measures
are provided.
(7) Temporary earth slopes that are to be exposed shall be covered
immediately upon formation with organic erosion control blanket
(ECB). The ECB shall be secured to the slope(s) by suitable fasteners
in accordance with the manufacturer’s recommendation. The ECB
shall be organic type similar to Envirofelt CF 250, Fibromat DC 250 or
approved equivalent. Details/samples of the proposed ECB shall be
submitted to the PDP for approval no less than 2 months prior to such
slope formation. Where such slopes will remain unmodified for
periods longer than 4 months they shall be hydroseeded in addition
to the ECB covering. In all such cases where the ECB will be used, the
provisions of subclause 110.6.10(v) of the Materials and
Workmanship Specification shall not apply. Permanent slope
protection measures shall comprise closed turfing or organic erosion
(19) Worksite area sediment control measures such as silt fences, silt
traps, gabion walls and check dams shall be provided and maintained
at all times in a satisfactory condition.
(20) All temporary measures, including silt traps, for environmental
control shall be removed and the area reinstated, including
landscaping, on completion of the Works.
(21) Slurry containment ponds shall be provided for bored piling activities
and temporary sumps provided during concreting of bored piles.
Where necessary, concrete slurry waste shall be immediately
pumped to a truck and removed from the worksite.
(22) Slurry from piling shall be suitably treated before discharging residual
water to watercourses.
(23) Exit roads from the worksite shall be paved. All vehicles leaving the
worksite shall use vehicle wheel washing facilities. Water runoff from
vehicle wheel washing facilities shall be channelled into
sedimentation ponds or silt traps.
(24) Any activity that involves changing the flow of rivers and streams shall
not be allowed without prior approval from the PDP and the Relevant
Authorities.
(25) The WPC shall comply with all requirements stipulated in Master ESCP
and Package ESCP and its approval conditions.
(11) Silt trap discharge samples shall be collected in a clean sterile bottle
and clearly labelled. Silt trap discharge samples shall be taken at the
final discharge point. Silt trap discharge samples shall be taken 30
minutes after every rain event in addition to the agreed schedule. A
rain event is rainfall intensity measured in the rain gauge of more than
12.5mm.
(12) Rain gauges shall be provided at each site at open space areas where
silt traps are located to measure the rainfall intensity.
(13) All Best Management Practices (BMPs) shall be checked within 24
hours after every rain event. An online report shall be submitted to
the Department of Environment (DOE) within 24 hours after
examination and maintenance was carried out. The format of the
Report shall follow as per “Lampiran B” in the DEIA Approval
Conditions.
(1) Movement of heavy vehicles and activities with high noise emissions
shall be restricted to daytime working hours 8am to 7pm and
minimised during night time, weekends and public holidays. Overall
noise levels arising from the movement of heavy vehicles shall be
controlled by using routes that will cause minimum disturbance in the
vicinity of the Work Area.
(2) Construction or installation works that need to be carried out at night
shall be subject to a permit or approval from the PDP/Owner and the
Local Authorities. No major disturbances shall be allowed near to the
residential areas for night works.
(3) Hoarding with noise barriers shall be installed by the WPC wherever
required on or around the Work Area to isolate the unsightly
construction or installation activity from nearby sensitive residents/
buildings.
(4) Acoustic panels shall be used at all times in temporary noise barriers.
(5) Temporary noise barriers shall be installed to contain noise at
sensitive areas.
(6) Noise generating equipment and machinery shall be inspected
regularly and maintained in good working condition to reduce noise
generation at source.
(7) All noise generating equipment and machinery shall be shut down
when not in use.
(8) Noise and vibration emitting from construction or installation
equipment shall be placed away from sensitive receptors.
(9) Stationary construction or installation equipment generating noise
shall be placed away from sensitive areas.
(10) Low noise diesel generator sets with acoustic enclosures and silencers
shall be used.
(9) All flood prone areas shall be identified based on historical flood data
and past experience.
(10) Inadequate downstream drainage provisions and any clogged existing
drains outside of the worksite shall be notified to Local Authorities for
improvement works to prevent flooding.
(11) Suitably sized water pumps shall be provided at flood prone areas to
pump and disperse the rain water from the flooded area.
(1) The WPC shall notify the Department of Environment (DOE) if there is
any installation of batching plant at the worksite and shall obtain
approval from the Relevant Authority. The batching plant operation
shall comply with all batching plant conditions from the Department
of Environment (DOE).
(2) The batching plant shall operate in accordance with the “Technical
Guidance Document on Best Practical Means for The Concrete
Batching Industry in Malaysia published by Department of
Environment (DOE).
(3) The batching plant shall be operated and maintained based on the
control measures listed below but shall not be limited to the
following:-
a) A silt fence shall be provided at the perimeter of the plant and
a sediment pond shall be provided to control the surface
runoff and suspended solids prior to discharge into the
8.32 Attachments
(1) The WPC shall ensure that all related Attachments in the General
Specification are implemented and incorporated into the WPC Safety,
Health and Environment Management system.
a) Attachment AG8.1 – Detail Environment Impact Assessment
Approval Conditions for MRT2 SSP Line;
b) Attachment AG8.2 – Environmental Aspects and Impacts
Procedure.
START
Responsibilities
Yes
Rev No
Location: Station S01 Damansara Damai
Date
#
SSP-PDP2-GENE-OVPR-SPC-000002
Risk Rating Significant
Operational Control Measures
Sungai Buloh-Serdang-Putrajaya (SSP)
(LxS)
Project Manager /
Excavation Water Pollution Siltation in watercourse 4 4 16 Yes To provide silt fence and silt trap
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066
Construction Manager
to cater the silt prior discharge into
the river
GS-151 of 472
Prepared by Reviewed By Approved By
Name
Signature
Date
Revision: 00
Volume III – Specifications (Part I of II)
Appendix B
Risk Rating Calculation
SEVERITY
1 2 3 4 5
No environmental Adverse impact may Adverse impact is not Can cause adverse Can cause severe
change occur, but the effect is permanent, short term impact, but the damage adverse impact, major
easily recoverable or and repairable or is not permanent / only pollution, e.g.
contribution to the contribution to the medium term or permanent / long term
impact is very low. impact is low. contribution to the environmental damage
impact is high. or contribution to the
impact is very high.
SSP-PDP2-GENE-OVPR-SPC-000002
No rectification needed Rectification can be Rectification can be Rectification can be Rectification can be
done immediately done within 1 day done within 1 week done more than 1 week
Sungai Buloh-Serdang-Putrajaya (SSP)
GS-152 of 472
a history of occurrence.
3 3 6 9 12 15
May happen once a
LIKELIHOOD
month in normal
*END OF SECTION*
situation.
Unlikely. Not expected,
but there's a slight
possibility it may occur
2 at some time. 2 4 6 8 10
May happen once a
year or only happen in
abnormal situation
Rare. It may only occur
in exceptional
circumstances.
1 1 2 3 4 5
May happen more than
once a year in abnormal
situation.
Risk Rating
Rating Significant
1 - 2 No
3 - 25 Yes
General Specification
System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Revision: 00
Volume III – Specifications (Part I of II)
PROJEK MASS RAPID TRANSIT LALUAN 2: System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh-Serdang-Putrajaya (SSP) Volume III – Specifications (Part I of II)
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066 General Specification
(1) The Earthing and Bonding Strategy has been developed for the
Systems Works and is attached for reference in Appendix F.
(2) The WPC shall develop their earthing and bonding system in line with
the Earthing and Bonding Strategy.
(1) The Lightning and Surge Protection Strategy has been developed for
the Systems Works and is attached for reference in Appendix G.
(2) The WPC shall develop their lightning and surge protection system in
line with the Lightning and Surge Protection Strategy.
General
(1) In order to produce well-designed, visually and functionally consistent
Graphical User Interfaces (GUI) for the system, it is essential to have
a common Human Machine Interface (HMI) design. The purpose of
this section is to provide the HMI scope and to specify the design
review requirement for the designers and system providers. The
scope includes the user interface design principles, overall screen
design layout, screen objects, user interaction and design review
requirements.
(2) This scope shall be read in conjunction with the HMI requirements as
specified in the main body of the appropriate PS.
(3) This scope shall be applied to equipment consisting of a Video Display
Unit (VDU) to ensure that the design is user friendly, easy to use,
thoughtfully organised, supporting effective and efficient operations,
and compatible with current industry’s Window standards.
(4) This scope applies to the VDU used in the Operations Control Centre,
Backup Control Centre, Depot Control Centre, Station Control Room,
Incident Management Room, on board the Train and within station
premises wherever applicable. In addition, some of the equipment
shall also be used in the training simulators.
User Control
(1) To assist the user to be in control, the following design issues shall be
adopted:
a) Flexibility - make choices available to the user;
b) Customisation - allow for personalised aspects of the
interface;
c) Responsiveness - design with interactive and responsive
behaviour; and
d) Direct manipulation of real world objects.
(2) The HMI design shall have the flexibility to enable users to choose the
methods of access to functions based on their experience, personal
preference and circumstances.
(3) The common and essential functions shall be presented in a clear and
logical manner. The more sophisticated and less frequently used
functions shall be hidden from immediate view but constantly
available.
(4) A HMI application shall be designed to allow users to personalise
aspects of the interface such as colour and fonts.
(5) Users shall be able to control applications by directly manipulating
symbols on a graphical display representing real world equipment. It
shall also provide a visual response to each action. The function shall
be achieved by a symbol or group of symbols being selected and an
action being performed on the selected symbols. This allows the user
Consistency
(1) Consistency is important, both within a single HMI application and
among various HMIs under the same system. Coherence between
different screens and the form and colours of the symbols used shall
be achieved.
(2) Consistency shall include the following:
a) Similar components shall operate similarly and have similar
uses. Components shall be organised in a familiar manner. The
user shall be able to quickly find the proper component for
each task;
b) The same action shall always have the same result;
c) The function of components shall not change based on
context. The result of the action may, however, change with
context;
d) Common terminology, wording and symbols shall be used
throughout;
e) The position of components shall not change based on
context. Components shall not be removed and added, rather
they shall be made functional or non-functional. This shall not
apply to menus and other windows which are allowed to pop-
up and pop-down;
f) The position of the mouse pointer shall not warp, i.e. the
application shall not move the pointer; and
g) Interaction is familiar, i.e. the same window shall have similar
functionality in different applications.
Feedback
(1) Applications shall provide feedback to users to indicate that the
computer has received their input. Feedback shall be provided to let
the user know that the operation is being processed.
(2) (Types of visual feedback shall be appropriate to the situation in a
simple form, such as a pointer changing to an hourglass shape. A more
(4) The Operator shall be provided with control button/drag & drop
functionality to control train movements, as applicable.
(5) Priority levels shall be allocated by the WPC and submitted to the
PDP/Owner for review.
(6) It shall be possible to assign any change of state/limit violation based
on priority of alarms to the user so that the user can distinguish
between the importance of the alarm. Different levels of prioritisation
shall be represented via a different colour.
(7) The alarm display shall present the alarms in chronological order with
the most recent alarms on the top row. A number of unacknowledged
alarms shall be provided in one end of the alarm banner.
(8) It shall be possible to acknowledge single or multiple alarms.
(9) On occurrence of a new alarm, an audible and visual warning shall be
given.
(10) A dedicated key shall be provided on the keyboard for the purpose of
alarm silencing and/or a soft key provided in the alarm window for
the same purpose.
(11) By pointing to the activated symbol in the alarm banner, the operator
shall be guided rapidly to the relevant diagram display, through which
it shall be possible to carry out alarm acknowledgement.
Objectives
(1) The main objectives are as follows:
a) To identify the principles related to system and interface
design under normal, degraded and emergency modes of
operation of the SSP Line.
b) To provide the basis to validate the various functional
performances under normal, degraded and emergency
modes. The validation tests shall be performed during the Off-
Site Integrated Tests.
Scope of Work
(1) The WPC shall jointly develop and produce the Operating Modes and
Principals Documents (OMPD) with the PDP. The PDP will facilitate the
development of OMPD with the WPC through meetings and working
sessions.
(2) The WPC shall attend meetings and working sessions to develop the
OMPD.
(3) Periodic meetings shall be carried out until the completion of OMPD
development. The PDP will provide the schedule for the discussion
Documentation
(1) The WPC shall jointly develop with the PDP each volume as shown in
Appendix H as a collated document. The document shall be signed off
jointly by the WPCs as a preliminary design submission of the OMPD.
This shall be submitted to the PDP/Owner for acceptance within
ninety (90) Days from the date of the Letter of Acceptance.
(2) The PDP will assign and distribute various chapters/sections of the
OMPD to the appropriate WPC(s) for their inputs. The WPC shall
subsequently jointly submit revised versions in accordance with the
PDP’s comments.
(3) The final version of both OMPD and OMPD OSHA documents shall be
submitted and have been accepted by the PDP/Owner prior to the
end of the Concept Design phase of the project.
(4) The OMPD shall become a live document to be further updated during
the various phases of the SSP project. The updates shall include all
changes affecting the drawings and design and operational
information etc. The WPC shall assess the impact of all changes on the
Other Works Contractor’s systems.
(5) For each operating principle, the WPC shall take into consideration
the following:
a) Scenarios / Facilities Description;
b) Cases of Application;
c) Actions to Be Taken by the Operator and System;
d) Structured Description / Process Flow Chart.
(6) In each area, the operational interface of the various functional
systems involved shall be clearly defined. This is to reinforce the
coherence of each core system design with regard to the system
operation requirements, taking into account all operating modes of
the system. All safety related operations and functions shall be clearly
defined and analysed, to ensure that all possible scenarios are
covered.
(7) The level of detail on operating principles provided by the WPC shall
be in line with the design of the respective systems and of sufficient
depth to allow the production of the Operation Rule Book and Railway
Operating Procedures for the SSP Line.
*END OF SECTION*
10.1 General
(1) The WPC shall make all necessary arrangements with and obtain all
necessary approvals, permits and consents from Relevant Authorities,
Utilities Companies and stakeholders for the design, execution,
commissioning and handing over of the Works. The WPC shall be
deemed to be fully aware of the requirements and procedures of all
Relevant Authorities, Utility Companies and other duly constituted
authorities. All correspondence, meeting minutes and submissions
made pursuant to this sub-clause shall be submitted to the PDP for
information.
(2) The WPC shall maintain close liaison with all Other Works
Contractors, Utility Companies and Relevant Authorities who are
carrying out work on or adjacent to the Site. The WPC shall ensure as
far as practicable that the progress of the Works shall not be adversely
affected by the activities of such other parties and vice versa. In the
event of potential disruption, the WPC shall inform the PDP
immediately.
(3) The WPC shall maintain, at his own cost, Internet access capability, to
enable communication with the PDP/Railway Operator/Civil
WPC/Other Works Contractors and others. Over the Internet,
communication shall include, but shall not be limited to, exchanges of
e-mail, electronic forum discussions, data exchange and access to
computers, as required under the Contract.
(4) The list of Other Works Contractors including the Civil WPC is shown
in Attachment AG10.1.
(1) The WPC shall attend regular meetings to facilitate coordination and
cooperation between the PDP, the Civil WPC, the WPC, his sub-
contractors and Other Works Contractors. The meetings, which shall
typically be at monthly intervals during the planning phase and
weekly during installation/construction, shall in particular facilitate:
a) Discussion and timely determination of all relevant
requirements relating to the coordination and progress of the
Works;
b) Review of, and timely decisions in relation to submissions by
the WPC, the Civil WPC and Other Works Contractors on
matters relating to the design, coordination and progress of
the Works (including programming, quality and procedural
matters);
c) Review of actual progress by the WPC and Other Works
Contractors and the need, if any, for instructions to be given
by the PDP to rectify any programming anomalies;
d) Protection of the WPC, the Civil WPC and Other Works
Contractors’ works from the effects of subsequent activities;
e) Review of all proposed ground works prior to commencement
of any works. Particular reference shall be made to drawings
and information on existing utilities;
10.5 Interface Management Plans (IMP) and Interface Control Documents (ICD)
(1) The WPC shall interface and liaise with the Other Works Contractors
in accordance with the GS as part of the integration processes for
Systems Engineering.
(2) Within ninety (90) days of the date of the Letter of Acceptance the
WPC shall develop and submit for approval by the PDP/Owner an
Interface Management Plan. The Interface Management Plan shall:
a) Identify civil works, facilities and systems that require
interfacing with the WPC;
b) Define the authority and responsibility of the WPC and any
relevant sub-contractors’ staff involved in interface
management and development;
c) Identify the information to be exchanged at each phase of the
project life-cycle;
d) Specify the configuration and version control procedures in
accordance with the WPC (and any relevant sub-contractors’)
quality management system;
e) Specify the process for managing interface requirement
changes and verification of interface requirements;
f) Specify the process for exchange of information and interface
hazard management. Any information to be exchanged
pertaining to works which the WPC proposes to be
incorporated in to the Permanent Works, or proposes to be
incorporated in to the works of the Other Works Contractors,
shall be approved by the PDP/Owner before such information
is provided to the Other Works Contractors; and
g) Be updated at least once every twelve (12) months, or such
other period as required by PDP.
(3) Once the Interface Management Plan has been approved by the
PDP/Owner, the WPC shall execute the Works in accordance with the
Interface Management Plan.
(4) Within four (4) months of notification from the PDP of the identity of
each Other Works Contractor, the WPC shall develop and submit for
approval by the PDP/Owner an Interface Control Document for each
sub-contractor and Other Works Contractor. The Interface Control
Document shall be a common document between the WPC, his sub-
contractors and Other Works Contractors and shall be signed off by
the WPC, his sub-contractors and Other Works Contractors, prior to
submission. The submission date of each Interface Control Document
10.7 Coordination with Other Works Contractors in preparing CSDs and SEMs
SEMs for review. Stage I CSDs and SEMs shall be based on the
latest Drawings, WPC’s design/as-built information, Other
Works Contractors input and PDP’s Stage 0 CSDs and SEMs.
Stage I CSDs and SEMs shall include items such as, but not
limited to, high and low level CSDs, under raised floor CSDs, at
grade CSDs, cast-in services CSDs, individual room CSD and
SEM openings in RC structure.
c) STEP 3 - Within three (3) weeks of receipt of the Stage I CSDs
and SEMs, the WPC shall mark their proposed service
routings, plant / equipment locations and delivery routes (as
agreed with the Civil WPC), penetrations through the
structure, temporary openings, plinths, kerbs and all other
pertinent information onto the CSDs / SEMs and submit to the
PDP. The PDP will check the submissions from the Other
Works Contractors prior to passing the submissions to the
Civil WPC for compilation of the CSDs and SEMs.
d) STEP 4 - The WPC shall liaise and convene meetings with the
Civil WPC and Other Works Contractors in order to resolve any
conflicts, discrepancies or other problems with the WPC’s
proposed service routings and/or structural requirements.
The WPC shall provide the PDP with advance notice of any
meetings and permit the PDP to attend such meetings.
e) STEP 5 - Within four (4) weeks of receipt, the PDP will review
the Final CSDs and SEMs. The PDP will approve the Final CSDs
and SEMs based on the results of coordination in steps 2, 3
and 4, and inputs from the WPC, Civil WPC and Other Works
Contractors. The Civil WPC shall proceed with his construction
of the Works according to the approved Final CSDs and SEMs.
(3) Any changes required by the WPC after approval of Final CSDs and
SEMs shall only be incorporated following approval by the
PDP/Owner. All costs incurred by the PDP/Owner as a result of these
changes shall be deducted from any monies due or to become due to
the WPC under the Contract. The WPC shall coordinate with Other
Works Contractors in developing and producing the As-built CSD’s
and SEM’s.
(4) All drawings and other information produced by the WPC and
submitted to the Civil WPC and all communications, including records
(1) Where the WPC is required to use the PDP or Railway Operator’s
computer systems to fulfil the requirements of the Contract, the WPC
shall observe the proper code of practice as applicable to the Laws of
Malaysia and International Laws, as well as any particular
requirements as stipulated in the Contract.
(2) The WPC shall be required to register with the PDP if access to the
PDP or Railway Operator’s computer systems is required. The use of
such computer systems shall be strictly confined to the works in
relation to the Project and shall be restricted to registered personnel
only.
(3) In respect of any system user accounts and passwords established for
access to the PDP or Railway Operator’s computers the WPC shall
observe the PDP or Railway Operator’s password policies for their
respective computer systems, which will be advised by the PDP in due
course. The PDP reserves the right to revoke access and change user
passwords to these computer systems without advance notice, as and
when deemed necessary.
SSP-PDP2-GENE-OVPR-SPC-000002
be defined by SY202. Support Lead Support Support Support Support Support SY202 ALL All
Sungai Buloh-Serdang-Putrajaya (SSP)
Ergonomics Studies. SY202 shall provide the ergonomics requirement for the operation of the
PROJEK MASS RAPID TRANSIT LALUAN 2:
railways Systems (OCC, BCC & SCR). SY202 shall coordinate and manage the compliance to the
4
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066
requirement resulting from the ergonomics studies as and when approved by PDP (OCC, BCC, DCC
and SCR). Support Lead Support Support Support SY202 All
Operational Console. SY202 shall lead the design of the operational console. SY202 shall supply
5 and fix the operational console for OCC, BCC, SCR. OWC are expected to coordinate with SY202 as
the lead for integration of OWC equipment into the console. Support Lead SY202 SY202
OCC/BCC/SCR. SY202 shall lead the design of ergonomics and layout of the OCC/BCC/SCR. OWC
6
shall supply and fix equipment with SY202 as lead. Support Lead Support Support Support ALL All
On-board Equipment fit out. SY203 shall lead in coordinating the on-board equipment with input
GS-184 of 472
7
from OWC. Support Lead Support SY203 ALL ALL
General Tools. SY203 shall lead in the standardisation and quantity rationalisation of General
8 Tools for use in Depot and Maintenance of the Railway Systems. OWC are expected to provide
their requirements to SY203. Support Support Lead Support Support Support Support SY203 SY204 SY204
KE and SG. SY204 shall take the lead in coordinating the use and compliance enforcement of the
9
KE and SG as SY204 define the DATUM for KE and SG. OWC shall align with SY204 Support Support Support Lead Support Support ALL ALL All
Track Cable Route and crossing. SY204 shall provide the Crossing requirements for OWC and
10 coordinate interfaces with OWC ensuring that the Track Cable Route and Crossing are fully
integrated between all OWCs. Support Lead Support Support SY204 SY204
Track Chainages. SY204 shall lead the coordination to compile inputs and update the track
11
chainage for use by all OWC. Support Lead Support SY204 SY204
Space for Wayside equipment. SY204 shall lead in coordinating the Wayside Equipment space
12
proofing with the input from all OWC. Support Lead Support Support SY204 ALL ALL
General Specification
System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Revision: 00
Volume III – Specifications (Part I of II)
Design Interfacing Leads by Contract
No Interface Activities Design Supply Fix
SY201 SY202 SY203 SY204 SY205 SY206 SY207
Station Primary Power Cable Ducting, Trays and Containment (up to System Room sub-DB). SY205
shall lead the interfacing of cable routing for power cables for Railways Systems. OWC shall
13
provide input needed for SY205 to coordinate the design up to supply and installation fix. The
scope of this terminates at each system room/equipment where applicable. Support Support Lead Support Support SY205 SY205 SY205
Power Equipment. SY205 shall lead in the standardisation of Power Equipment needed for
14 Railway Systems. This is to realize the maintenance/replacement spares commonality. OWC shall
provide requirements for SY205 to supply. Each OWC shall install their equipment. Support Support Lead Support Support SY205 SY205 All
Earthing and Bonding. SY205 shall lead the E&B strategy Railway System Wide. OWC shall abide by
15
the strategy/plans/requirement to be approved by PDP/Owner Support Support Support Support Lead Support Support SY205 ALL All
Power System Study (Power Simulation). SY205 shall update the simulation to ensure compliance
SSP-PDP2-GENE-OVPR-SPC-000002
16 of all parameters used and requirements resulting from the output of the simulation ensuring
Sungai Buloh-Serdang-Putrajaya (SSP)
alignment with the Employers Requirement. Support Support Lead SY205 All
PROJEK MASS RAPID TRANSIT LALUAN 2:
IT equipment. SY206 shall lead in the standardisation of IT equipment needed for the Railway
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066
17 Systems. This is to achieve the maintenance/replacement spare commonality. OWC shall provide
requirements for SY206 to supply. Each OWC shall install their equipment Support Support Support Support Lead Support SY206 SY206 All
IP address allocation. SY206 shall lead the coordination and allocate the IP address for the BTN
18
communication network of the railway Support Support Support Support Lead Support SY206 SY206
Radio Frequency allocation. SY206 shall lead the coordination and allocate the frequency for the
19
communication network of the railway Support Support Support Support Lead Support SY206 SY206
Station Primary Data Cable Ducting, Trays and Containment. SY206 shall lead the interfacing of
GS-185 of 472
cable routing for data cables for Railways Systems need. OWC shall provide input needed for
20
SY206 to coordinate the design up to supply and installation fix. OWC are shall lay their own
cables on the installed ducting/trays/containment. Support Support Support Lead Support SY206 SY202 SY202
General Specification
System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Revision: 00
Volume III – Specifications (Part I of II)
PROJEK MASS RAPID TRANSIT LALUAN 2: System Works Package SSP-SY-206: COMM, GIRN, CMTS and ITS
Sungai Buloh-Serdang-Putrajaya (SSP) Volume III – Specifications (Part I of II)
Tender No. SSP-MRTC-SS06-OVPR-TEN-00066 General Specification
Finish Level
Waterproofing
Painting
Fixture
Fitting Out
Furniture
Schedule
Layout
Others
Type Illuminated/
Signage Non Illuminated
Location
Others
Services Crossing
Delivery Route Size (E&M Room)
ELECTRICAL SERVICES
Type of Light Fitting
Quantity of SSO
Other provision for Electrical Services
MECHANICAL SERVICES
Type of ECS (AC, MV Design Air Change for -
or NV) Mech. Ventilation
Design Room Temp Fresh Air Requirement
-
(°C)
Design Relative Noise Level Criteria -
Humidity (%) (dBA)
ACS/VRF/CHW/PAC Power Supply -
Environmental Control CHW/PAC DX Requirement (Normal /
System Essential / Very
essential)
Provisional of standby Provisional of standby -
air-conditioning unit fans
Provisional of -
Pressurization
System/Smoke Spill
System
Fire Suppression
System
Fire Detection & Portable Extinguishers
Protection System Fire Alarm and
Detection System
Floor Trap
Water Tap -
CW, Drainage,
Sewerage Water Basin -
WC -
Urinal -
Equipment Heat Load -
Other provision for
Mechanical Services
SYSTEMS
Security Provision
Delivery Route Door Size Lift Size
Staircase Size
Roller Shutter Size
(Clearance Width )
Yes Speaker Yes
Camera
No No
Emergency Stop Yes Help Point Yes
Plunger No No
Communication
Yes Radio Antenna Yes
PIDS
No No
Yes Yes
Emergency Telephone Others
No No
ITS Services -
Other Provision For Systems
1 CSD/SEM Details for Stations, Tunnels, TPSS, Ancillary and Utility Buildings
Cable Routing Primary cable routing for systems at Detail cable wiring/routing inside each
station and service corridors room.
complete. Cable containment, cable routing design,
Cable details (specs & size). equipment layout and design including
Opening/penetration/sealing details. plinth requirement, earthing connection
Cable routing design, equipment detailing, SEM openings & cast-in
layout and design including plinth locations, cable sizes and specifications,
requirement, earthing connection detail and installation from opening/
detailing, SEM opening & cast-in penetration/sealing details from each
location cable sizes and specifications, WPC, DC, DS (1st fix, 2nd fix and 3rd fix).
detail and installation from Verify equipment delivery route,
opening/penetration/sealing details headroom and width.
3. Remarks
a) The above tables describes the details that shall be included in the CSD/SEM drawings.
b) The lists are not exhaustive and may include other equipment and components that are required and part of the scope of the WPC
and Other Works Contractors.
c) Stage 1/Pre-final CSD/SEM may already contain all of the elements required by the other stages but requires further review and
verification by the interfacing parties for accuracy and correctness of information.
d) All details are expected to be verified and agreed among the interfacing parties at the conclusion of Stage 2/Final CSD/SEM.
4. Abbreviations
APG Automatic Platform Gate H/P Help Point
BL Bottom Level ITB Interface Terminal Box
BSS Bulk Substation LHD Linear Heat Detector
C&S Civil and Structural LV Low Voltage
DB Distribution Board MCC Motorised Control Centre
DC Designated Contractor OTE Overhead Track Exhaust
DS Designated Supplier OWC Other Works Contractor
EAD Exhaust Air Duct PSD Platform Screen Door
ECS Environmental Control System RCP Reflected Ceiling Plan
F/A From Above SSO Switch Socket Outlet
F/B From Below TPSS Traction Power Substation
FCU Fan Coil Unit
FFL Finished Floor Level
*END OF SECTION*
*END OF SECTION*
11.1 General
(1) In order to organise the various submissions required by the PDP and
to ensure the WPC understanding of and compliance with the
requirements of the Contract, a series of management plans and
submissions shall be developed.
(2) The management plans and submissions shall be categorised as, but
shall not be limited to, the areas of project management, system
assurance management, design, procurement, manufacturing and
delivery management, installation management, and completion
phase management. Other specific submission requirements are
stipulated in the Specifications.
(3) Plans and submissions shall be co-ordinated with each other and shall
collectively define, describe and encompass the WPC proposed
methods, procedures, processes, organisation, sequencing of
activities, etc. The plans and submissions shall show how these
combine together to ensure that the Works meet the requirements
of the Specification in respect of the subjects listed.
(4) Unless otherwise stated in the Specifications, the WPC shall issue all
management plans and submissions in accordance with the
requirements in this GS, or as directed by the PDP. The principal items
to be submitted to the PDP are listed in the following Section.
(5) Further issues of the management plans and submissions shall be
made:
a) when required in accordance with the Works Programme;
b) whenever the development of the WPC designs or planning
requires the Plans to be updated;
c) in response to comments made by the PDP;
d) within fourteen (14) Days of any change that invalidates the
information contained in the previously submitted and
approved document or when requested by the PDP.
(1) The WPC shall submit the Systems Assurance Plan in accordance with
Section 21.5 of this GS.
(2) Project Quality Plan In accordance with the requirements of Section
12.4 of this GS.
Electromagnetic Compatibility (EMC) Management Plan.
(3) The WPC shall submit an EMC Management Plan in accordance with
Section 19.5 of this GS.
(4) Software Quality Assurance Plan.
(5) A White Paper or Evidence Paper shall be prepared by the WPC as
when requested by PDP including, but not limited to the following
occurrences:
a) When the proposed Equipment/product/system has a history
of failure in the other projects;
b) When the proposed Equipment/product/system has
interfered with other systems/equipment and improvements
have been made;
c) When the proposed Equipment/product/system has been
impacted/interfered with by other systems and
improvements have been made;
d) When the proposed Equipment/product/system is not proven
in service.
(1) Throughout the design period, the WPC shall attend monthly design
review meetings with the PDP. At these review meetings, the WPC
shall present information, drawings and other documents to the PDP
in respect of all submissions programmed to occur during the
following five-week period.
(2) Design reviews shall be arranged prior to the conclusion of each
design stage. The design review process shall incorporate the
following formal reviews at each stage of the design. The WPC shall
minute each of these formal reviews and record any actions agreed.
a) WPC Design Review
The WPC Design review is a meeting to confirm that the WPC has
undertaken the proper checking and approval of the design
deliverables in accordance with quality procedures. The WPC
shall demonstrate that all disciplines, including all work
undertaken by his sub-contractors has been fully coordinated.
b) Interface Design Review (IDR)
The IDR is a review meeting that is held jointly with
representatives of all interfacing parties. The purpose of the IDR
is to ensure that the interfacing consultants have all reviewed
and commented on the WPC design deliverables using design
review forms and that all review comments have been actioned
or closed. A representative from each interfacing party shall sign
the IDR form to confirm that their comments have been closed.
c) Constructability Reviews (CR)
The CR is a review meeting attended by competent construction
specialists to confirm that the design deliverables are
constructible and that the design is construction-friendly. The
meeting shall be held at least fourteen (14) days after the issue
Gates
(1) Gates are control points that the WPC shall be required to pass to the
satisfaction of the PDP before continuing with the next stage of the
design. These Gates cover the following Criteria:
a) Meeting Requirements;
b) Design and Management Review;
c) System Assurance;
d) Management of Risk;
e) Interface Management;
f) Quality;
g) Occupational Safety and Health;
h) Obtaining Approvals.
(2) The Gate reviews are managed by the PDP and the WPC shall provide
evidence that the design has achieved essential criteria. Details of the
Gate process are set out in the PDP document entitled “Gate
Procedure for System Work Packages”. A copy of this document will
be provided to the WPC following issue of the Letter of Acceptance.
Manufacturing Submissions
(1) The WPC shall identify the specific methods of manufacture for major
components, equipment and systems in the manufacturing method
statements and develop those method statements to a degree of
sufficient detail to be approved by the PDP/Owner. All manufacturing
method statements shall be submitted for approval by the
PDP/Owner no later than sixty (60) Days prior to the commencement
of the respective manufacturing activities.
(2) The WPC shall prepare and maintain a full list of all the manufacturing
method statements required for the Contract with their submission
and approval status, and shall submit the same to the PDP upon
request. The manufacturing method statements shall include, but
shall not be limited to, the following:
a) Particulars of the materials to be incorporated into the items;
Installation Management
(1) Installation shall mean all site construction and installation activities.
Plans for installation management shall encompass a list of "stand-
alone" plans and associated documents covering each of the subjects
depicted below.
(2) Plans shall be submitted and co-ordinated with each other and shall
collectively define, describe and encompass the WPC’s proposed
methods, procedures, processes, organisation and sequencing of
activities. Plans shall show how these elements combine together to
ensure that the Works meet the requirements of the Specification in
respect of the subjects listed.
Installation Plan
(1) The WPC shall prepare a plan for installation activities and shall
ensure that these are properly related to the subsequent testing and
commissioning activities. Separate parts of the Plan shall be prepared
by the WPC and his subcontractor(s) of any tier and these shall include
any off-site activities. The Installation Plan shall identify the scope of
the activities to be controlled and shall define:
a) The organisation of the WPC staff directly responsible for the
day-to-day management of each activity on or off the Work
Area;
b) The specific allocation of responsibility and authority given by
the WPC to identified personnel for the day-to-day
management of the Works with particular reference to the
supervision, inspection and testing of the Works;
c) The interfacing or co-ordination required with the WPC’s
other related plans which shall be developed fully and co-
ordinated with the Interface Management Plans and Interface
Control Documents;
d) A list of method statements and a programme for the
submission of all method statements;
e) A list of procedures and work instructions to manage and
control the safety and quality of installation works including:
i. Descriptions and flow charts of installation processes
including installation of all temporary works and their
removal;
ii. Arrangements for storage including identification of
all off-site and on-site storage areas, details of which
are to be approved by the PDP/Owner prior to their
use;
iii. Delivery method statements for all large plant and
equipment or plant and equipment with special
delivery requirements to the installation sites or for
any other product as directed by the PDP;
iv. The list of lead interfaces contained in Attachment
AG10.2 is by no means comprehensive and does not
negate the responsibility of the WPC to perform his
obligations under his scope of work. It is anticipated
that the WPC shall identify additional items to be
included in Interface Management Plans and Interface
Control Documents as appropriate, the details shown
Installation Submission
(1) Particulars of agent:
a) The WPC shall provide all necessary superintendence during
the execution of the Works for as long as the PDP considers
necessary to ensure the fulfilment of the WPC obligations
under the Contract.
b) The WPC shall ensure that he is at all times represented on
the Work Area by a competent and authorised English-
speaking agent approved by the PDP/Owner. Such agent shall
be based in the Work Area and shall provide full time
superintendence of the Works.
c) The PDP shall have the authority to withdraw his approval of
the agent at any time. If such approval is withdrawn, the WPC
shall immediately remove the agent from the Work Area and
shall not employ him again in the Work Area in any capacity
and shall immediately replace him by another competent
English-speaking agent approved by the PDP/Owner.
d) Such authorised agent shall receive on behalf of the WPC
directions and instructions from the PDP.
e) The following particulars of the proposed agent shall be
submitted to the PDP/Owner for approval:
i. Name;
ii. Details of qualifications, including copies of his CV and
certificates; and
iii. Details of previous relevant experience.