Landslide Mitigation Strategies: Prepared For
Landslide Mitigation Strategies: Prepared For
Mitigation Strategies
Prepared for:
Landslide Mitigation Strategies
Landslides are an unfortunate reality for Hennepin County, the
metropolitan area and other regions in the State of Minnesota. In
2013, a deadly landslide occurred in St. Paul’s Lilydale Regional Park.
Heavy rains in the spring of 2014 were responsible for several
landslides that closed roads, including the slide shown here on the
West Bank at the University of Minnesota’s Fairview Medical Center.
This landslide closed West River Parkway for over a year and resulted
in a $6 million stabilization project.
Page 2 of 35
Landslide Risk and Hazard Assessment
To enhance land-use planning and protection efforts, the first step is to create a GIS-based Landslide
Risk Assessment. The assessment identifies areas of higher landslide risk. At a minimum it uses
geographic data related to slopes, geology, and the location and extent of historic landslides. The
location of springs and vegetation type may also be useful data to include. The assessment should
be open to the public and participatory. Residents should be encouraged to share knowledge of
landslide occurrences and areas of concern. Through participation in the assessment, they will
become more knowledgeable about landslides and the types of activities that make landslides more
likely to occur.
The resulting map can be used in conjunction with existing land development ordinances, including
the Mississippi River Critical Area Overlay District and Shoreland Overlay District. Or it could be used to
take the next step, the creation of a Hazard Assessment.
A Hazard Assessment includes economic and societal impacts of potential landslides. It should
identify roads, utilities, and structures located in landslide hazard areas. Ideally it would include costs
associated with repair and stabilization. It can be used to prioritize site-based assessments of critical
facilities and infrastructure by qualified professional geologists or geotechnical engineers to
determine if those facilities would benefit from relocation, prevention, or protection strategies.
The Landslide Risk Map and Hazard Assessment should be publicly available. In order to improve
these products and promote education on the topic, communities and residents should be
encouraged to share information about landslides. The USGS Landslide Hazards Program has a
“Report a Landslide Tool” that is easy to use and the data will by archived by them and provided to
the State of Minnesota. http://landslides.usgs.gov/dysi/form.php
Page 3 of 35
Land-Use Planning
Several land-use planning and regulatory tools
have been used to mitigate landslide hazards.
For maximum effectiveness, the Landslide Risk
and Hazard assessments should be incorporated
into the comprehensive plan, which will enable
and support additional regulatory approaches
that could include the examples described
below.
Counties and municipalities can enact landslide-specific regulations in the form of an overlay zone or
development ordinance. These types of regulation are a low-cost alternative to keep development
and infrastructure away from sensitive slopes and prevent costly slope failures. County-level
regulations can fill gaps left by municipality-specific versions and can reinforce local bluff protection
ordinances in place to implement the Minnesota Department of Natural Resources’ statewide
Shoreland, Wild & Scenic Rivers, Lower St. Croix National Scenic & Recreational Riverway, and
Mississippi River Critical Area programs. 1 New landslide-related regulations should build on existing
policy and may include the following:
1 http://dnr.state.mn.us/waters/watermgmt_section/critical_area/index.html
Page 4 of 35
Transportation and Infrastructure Planning
Transportation systems, utilities, and other infrastructure are at risk from landslides. In many cases
those projects have contributed to conditions that resulted in landslides. The Landslide Hazard
Assessment can identify where existing infrastructure is at risk and areas that should be avoided in
future projects. Transportation projects are managed by multiple entities, including municipalities,
counties, townships, the Twin Cities Metropolitan Council and the Minnesota Department of
Transportation. Through comprehensive plans, capital improvement plans, and regional
transportation plans, policy and funding decisions can be crafted to mitigate landslide risk. This is
accomplished through policies that restrict transportation and utility projects in landslide-prone areas.
Additionally, projects that include landslide protection or that relocate at-risk structures can be
included in capital improvement plans and long-range transportation plans.
Page 5 of 35
Education & Outreach
Education and outreach efforts begin with
public participation in the Landslide Risk
Assessment. Private landowners and
elected officials are the target audience
for education and outreach efforts.
Elected officials are key because they can
enact regulatory changes and secure
funding for landslide mitigation efforts.
Private landowners are important
because they often are not aware their
property is at risk or do not know how to
identify warning signs.
Minnesota already has several effective tools that offer information related to landslide mitigation,
particularly for vegetation and drainage. The Minnesota Board of Water & Soil Resources issued the
Native Vegetation Establishment and Enhancement Guidelines in June 2015. This document details
methods for planting appropriate vegetation for a variety of situations, including streambank and
ravine stabilization.
The Department of Natural Resources’ Restore Your Shore program assists shoreland owners and
professionals in implementing shoreland restoration and protection projects. The guidance offered in
this program also applies to slope stabilization. Restore Your Shore also offers a good example for
showcasing demonstration projects. Links to several publications and programs that can assist in
education and outreach efforts are listed here:
Native Vegetation Establishment and Enhancement Guidelines, Minnesota Board of Water and Soil
Resources
http://www.bwsr.state.mn.us/native_vegetation/seeding_guidelines.pdf
Resources Guidelines for Restoring Natural Plant Communities along Trails and Waterways Chapter 4 –
Riparian Environments, Minnesota Department of Natural
Page 6 of 35
http://files.dnr.state.mn.us/assistance/nrplanning/community/trails_plantcommunities/chapter4.pdf
Cost-Effective and Sustainable Road Slope Stabilization and Erosion Control, National Cooperative
Highway Research Program
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_syn_430.pdf
The Landslide Handbook - A Guide to Understanding Landslides, United States Geological Survey.
http://pubs.usgs.gov/circ/1325/pdf/C1325_508.pdf
Overview of Landslide Mitigation Techniques, Dr. J. David Rogers, PE, Missouri University of Science
and Technology
http://dr-rogers.com/Puplications/hazard_mitigation_techniques/Rogers-
Overview%20Landslide%20Mitigation.pdf
Page 7 of 35
Sample Ordinances and Codes
1. Minneapolis, Mississippi River Critical Area Overlay District ........................................................................ 9
2. Minneapolis, Shoreland Overlay District...................................................................................................... 10
3. Olmsted County Decorah Edge Overlay District ....................................................................................... 14
4. Pittsburgh, Pennsylvania Landslide-Prone Overlay District ....................................................................... 18
5. Salem, Oregon Landslide Hazards Ordinance........................................................................................... 20
6. Cincinnati, Ohio Hillside Overlay Districts .................................................................................................... 25
7. Cincinnati, Ohio Excavation Or Filling Of Land Code ............................................................................... 30
Page 8 of 35
1. Minneapolis, Mississippi River Critical Area Overlay District
551.660. - Purpose.
The MR Mississippi River Critical Area Overlay District is established to prevent and mitigate damage to the
Mississippi River, to preserve and enhance the Mississippi River's natural, aesthetic, cultural and historic
value for public use, to protect and preserve the biological and ecological functions of the Mississippi River
corridor, to comply with the requirements regarding the management of critical areas, and to protect the
public health, safety and welfare.
551.700. - Development on bluffs or within forty (40) feet of the top of bluffs.
Development not otherwise governed by section 551.680 shall not be located on a bluff or within forty (40)
feet of the top of a bluff, except where approved by a variance as provided in this article and Chapter
525, Administration and Enforcement, and shall be subject to the following additional conditions:
(1) The foundation and underlying material shall be adequate for the slope condition and soil type.
(2) The development shall present no danger of falling rock, mud, uprooted trees or other materials.
(3) The view of the developed slope from the protected water shall be consistent with the natural
appearance of the slope, with any historic areas, and with surrounding architectural features.
(2000-Or-048, § 10, 5-19-2000)
Page 9 of 35
2. Minneapolis, Shoreland Overlay District
551.440. - Purpose.
The SH Shoreland Overlay District is established to preserve and enhance the environmental qualities of
surface waters and the natural and economic values of shoreland areas within the city, to provide for the
efficient and beneficial utilization of those waters and shoreland areas, to comply with the requirements of
state law regarding the management of shoreland areas, and to protect the public health, safety and
welfare.
551.460. - Definitions.
As used in this article, the following words and phrases shall mean:
Best management practices. Erosion and sediment control and water quality practices that are the most
effective and practicable means of controlling, preventing and minimizing degradation of surface water.
Bluff. A steep outcropping, hill, cliff or embankment along a river or stream, with an average slope of
eighteen (18) percent or greater measured over a horizontal distance of fifty (50) feet or more, and that
rises at least twenty-five (25) feet above the ordinary high water mark of the protected water.
Clear cutting. The removal of an entire stand of trees, shrubs, bushes or similar vegetation.
Development. The erection, construction, reconstruction, relocation or enlargement of any structure
except walkways, stairways, retaining walls, light poles, piers, docks and similar structures where accessory
to a public park, unenclosed structures up to four hundred (400) square feet and not more than twenty
(20) feet wide used for the storage of watercraft where accessory to a public park and if located at least
ten (10) feet from the ordinary high water mark of any protected water, and stairways and seasonal docks
not exceeding four (4) feet in width where accessory to any other use.
Ordinary highwater mark. A mark delineating the highest water level which has been maintained for a
sufficient period of time to leave evidence upon the landscape. The ordinary highwater mark commonly is
that point where natural vegetation changes from predominantly aquatic to predominantly terrestrial.
Protected waters. The following lakes, ponds, wetlands, streams and rivers are protected waters: Brownie
Lake, Cedar Lake, Lake of the Isles, Lake Calhoun, Lake Harriet, Lake Nokomis, Lake Hiawatha, Mother
Lake, Legion Lake, Cemetery Lake, Diamond Lake, Grass Lake, Powderhorn Lake, Ryan Lake, Spring Lake,
Taft Lake, Birch Pond, Bridal Veil Pond, Loring Pond, Webber Pond, wetlands mapped by the city engineer
or classified by the United States Fish and Wildlife Service, Bassett Creek, Minnehaha Creek and Shingle
Creek and the Mississippi River.
Steep slope. Land having an average slope of eighteen (18) percent or greater measured over a
horizontal distance of fifty (50) feet or more. Steep slopes that are less than ten (10) feet in height shall not
be considered a steep slope.
Surface water oriented uses. Land uses in which access to or use of a surface water feature is an integral
component, such as boathouses, docks, marinas, observation platforms and water control structures
including locks and dams.
Top of steep slope. The contour at which the slope ceases to be eighteen (18) percent or more.
(2000-Or-048, § 3, 5-19-2000)
Page 10 of 35
(1) Development must currently exist on the steep slope or within forty (40) feet of the top of a steep slope
within five hundred (500) feet of the proposed development.
(2) The foundation and underlying material shall be adequate for the slope condition and soil type.
(3) The development shall present no danger of falling rock, mud, uprooted trees or other materials.
(4) The view of the developed slope from the protected water shall be consistent with the natural
appearance of the slope, with any historic areas, and with the surrounding physical context.
(b) Location restricted except as authorized by conditional use permit. Conditional uses authorized in the
primary zoning district are also authorized in the SH Overlay District and are subject to section (a) above.
Notwithstanding section (a) above, the following uses may be allowed in all areas of the SH Overlay District
by conditional use permit rather than variance as provided in this article and Chapter 525, Administration
and Enforcement.
(1) Public parks and surface water-oriented development on steep slopes or within forty (40) feet of the
top of a steep slope, other than bluffs, or within fifty (50) feet of the ordinary high water mark of any
protected water, where allowed by the primary zoning district, provided the development does not
cause a hazard to water navigation.
(2) Electrical transmission services of under two hundred twenty (220) kilovolts, subject to the following
conditions:
a. When routing transmission services, all of the following shall be avoided where practicable:
1. Steep slopes, streams, rivers, valleys and open exposures of water, wetlands, wooded areas,
ridge crests and open space recreation areas.
2. Soils susceptible to erosion, which would create sedimentation and pollution problems, and
areas of unstable soils which would be subject to extensive slippage.
3. Areas with high water tables, especially if construction requires excavation.
b. The structural design of transmission services shall consider the following:
1. Underground placement shall be preferred in order to minimize visual impact. If above ground
placement is proposed, the applicant shall describe the economic, technological or land
characteristics which make underground placement infeasible.
2. If above ground placement is necessary, the appearance of any structures shall be made as
compatible as practicable with the natural area with regard to height, width, materials used
and color.
3. The cleared portion of the right-of-way shall be kept to a minimum.
4. Crossing points over protected waters shall be consolidated with other public facilities and
rights-of-way so that the smallest area possible is devoted to crossing.
c. In the construction of transmission service, effective erosion and sedimentation control programs
shall be conducted during all clearing, construction or reconstruction operations in order to
prevent the degradation of surface waters and adjacent lands.
d. Right-of-way maintenance shall comply with the following:
1. Natural vegetation of value to fish or wildlife, which does not pose a hazard to or restrict
reasonable use of the utility, shall be allowed to grow in the right-of-way.
2. Where vegetation has been removed, new vegetation consisting of native grasses, herbs,
shrubs and low- growing trees shall be planted and maintained on the right-of-way.
3. Chemical control of vegetation shall be avoided. Where such methods are necessary,
chemicals used and the manner of their use shall be in accordance with rules, regulations and
other requirements of all state and federal agencies with authority over the use, and best
management practices shall be followed.
(2000-Or-048, § 4, 5-19-2000; 2008-Or-010, § 1, 2-1-08)
Page 11 of 35
permit, as provided in Chapter 525, Administration and Enforcement. In addition to the conditional use
standards contained in Chapter 525, the city planning commission shall consider, but not be limited to, the
following factors when determining maximum height:
(1) Access to light and air of surrounding properties.
(2) Shadowing of residential properties or significant public spaces.
(3) The scale and character of surrounding uses.
(4) Preservation of views of landmark buildings, significant open spaces or water bodies.
(2008-Or-010, § 2, 2-1-08; 2014-Or-063, § 1, 8-29-2014, eff. 10-1-2014)
551.500. - Development on slopes between twelve (12) and eighteen (18) percent.
Development on slopes between twelve (12) and eighteen (18) percent, other than bluffs, where allowed
by the primary zoning district, provided the development is not located within fifty (50) feet of the ordinary
high water mark of any protected water, may be allowed in the SH Overlay District subject to the
regulations of this article, Chapter 535, Regulations of General Applicability, and the following conditions:
(1) The foundation and underlying material shall be adequate for the slope condition and soil type.
(2) The development shall present no danger of falling rock, mud, uprooted trees or other materials.
(3) The view of the developed slope from the protected water shall be consistent with the natural
appearance of the slope, with any historic areas, and with surrounding architectural features.
(2000-Or-048, § 6, 5-19-2000)
Page 12 of 35
(2) Selective removal of vegetation shall be allowed, subject to the requirements of this article and
Chapter 535, Regulations of General Applicability, provided sufficient vegetative cover remains to
screen parking areas, dwellings and other structures when viewed from the protected water and
provided a continuous natural cover is maintained.
(3) Vegetation shall be restored to the extent feasible after any construction project is completed to
retard surface runoff and soil erosion and to provide screening. Restoration shall be completed as
soon as feasible, but in no case later than the beginning of the next growing season following the
completion of a project.
(4) Best management practices to prevent erosion and trap sediment shall be employed to ensure that
soil loss levels do not degrade the protected water.
(2000-Or-048, § 7, 5-19-2000)
Page 13 of 35
3. Olmsted County Decorah Edge Overlay District
The regulations of this district are superimposed upon other existing zoning districts, superseding the
regulations of those other districts only to the extent that developments must meet the additional
standards of this chapter as well as those of the underlying district in order to comply with this ordinance.
Application: The Decorah Edge Overlay Zone applies to unplatted lands zoned to accommodate
commercial or industrial development or residential development at a density greater than four lots per
quarter quarter section within the Decorah Edge as defined and mapped in accordance with the Olmsted
County Wetland Conservation Ordinance. The Decorah Edge Overlay Zone does not apply to the
development of residential or agricultural uses on existing lots of record in existence at the time of
enactment of these provisions.
Page 14 of 35
affect wetlands and Edge Support Areas as defined in the Olmsted County Wetland Conservation
Ordinance, unless approved under the Wetland Conservation Ordinance.
Page 15 of 35
A. roads, treatment facilities, drains, pipelines, tiles, the building footprints of structures, and
driveways and other impervious surfaces avoid the Decorah Edge area to the maximum extent
feasible; and
B. all wetland areas and Edge Support Areas are maintained in managed open space; and
C. other areas of the original site in native vegetation, and other areas of the site on slopes over
18%, are maintained in managed open space to the maximum extent feasible, but in no case
less than 50% of such areas; and
D. pretreatment or other nitrate reduction sewage treatment systems are installed resulting in a
nitrate impact on groundwater equivalent to an overall 3.5-acre density of development.
Page 16 of 35
3. the portion of the parcel to be developed conventionally is contiguous; and
4. the portion of the parcel to be developed conventionally is at least 15 acres in area.
The determination that a reasonable use remains for residual portions of the original parcel shall reflect such
attributes of the residual portions as contiguity, compactness, topography, developable area, and natural
constraints on development for areas intended for development. Conservation easements or other means
of preserving natural resource or open space uses of residual parcels may be considered to provide for
reasonable use.
Page 17 of 35
4. Pittsburgh, Pennsylvania Landslide-Prone Overlay District
906.04. - LS-O, Landslide-Prone Overlay District.
906.04.A Purpose
The LS-O, Landslide-Prone Overlay District regulations require subsurface investigations by a registered
professional and approval of construction plans by the Chief of the Bureau of Building Inspection prior to
issuance of a Certificate of Occupancy for any development in the LS-O District. The purpose of these
regulations is to reduce the risk of damage or hazards of life that may occur as a result of construction and
land operations on lands susceptible to movement or sliding of earth.
The mapped delineations of land that may be subject to sliding or subsidence do not necessarily
include all land that is subject to those hazards. While it is the purpose of the regulations contained in
this section to afford reasonable protection against damages caused by construction on or use of
hazard-prone land, neither the mapped delineations nor any regulations contained in this section shall
create any liability on the part of the City, its officers or employees for damages that may occur.
Within the LS-O District, land may be used and structures may be erected, altered or enlarged for any use
that is allowed in the underlying zoning district, in accordance with the site development standards of the
underlying zoning district and all other applicable requirements. The following requirements shall also apply
with the LS-O District.
Every new or changed use of land and every structure hereafter erected or enlarged within the LS-O
District shall comply with the Hillside Development Standards of the Subdivision Regulations.
(a) An applicant for approval of a Certificate of Occupancy in the LS-O District shall submit a
development plan for the site, which shall include a site plan, building plan and such other
information as determined by the Zoning Administrator to be necessary to evaluate the proposed
development for compliance with the Hillside Development Standards of the Subdivision
Regulations.
(b) The Zoning Administrator shall not approve an application for a Certificate of Occupancy in
the LS-O District unless the development plan for the subject property complies with the Hillside
Development Standards of the Subdivision Regulations.
No Certificate of Occupancy application shall be approved for zoning for any structure or for any use
of land requiring excavation, fill or removal of vegetation until the applicant has submitted evidence,
acceptable to the Zoning Administrator, that the proposed construction or development shall not
contribute to or create conditions of increased susceptibility to landslides, soil erosion or any other
movement of earth. Such evidence shall be based on field investigation performed by a registered
professional as defined in the Land Operations Ordinance or a geotechnical consultant with
appropriate professional insurance certification and the appropriate academic credentials and
professional association.
Page 18 of 35
No building permit or land operations permit application shall be approved for any structure or for any
use of land requiring excavation, fill or removal of vegetation in a Landslide-Prone District until
construction plans and land operations plans for the site in question have been approved by the Chief
of the Bureau of Building Inspection, based on findings and recommendations of the site investigation
required under Sec. 906.03.B.2. In the implementation of this requirement, the Chief of the Bureau of
Building Inspection may require that construction and land plans be prepared or approved by a
registered professional as defined in the Land Operations Ordinance or a geotechnical consultant
with appropriate professional insurance certification and the appropriate academic credentials and
professional association.
Page 19 of 35
5. Salem, Oregon Landslide Hazards Ordinance
810.001. Purpose
810.005. Applicability
810.010. Definitions
810.015. Map Adoption
810.020. Landslide Hazard Construction Permit
810.025. Landslide Hazard Risk Assessment
810.030. Standards for Geological Assessments and Geotechnical Reports
810.035. Certification of Compliance
810.001. Purpose. The purpose of this Chapter is to implement the Geologic Hazards policy of the Scenic and
Historic Areas, Natural Resources, and Hazards section of the Salem Area Comprehensive Plan and to promote
the public health, safety and welfare by:
(a) Assessing the risk that proposed uses or activities will adversely affect the stability and slide
susceptibility of an area;
(b) Establishing standards and requirements for the use and development of land within landslide hazard
areas; and
(c) Mitigating risk within landslide hazard areas. (Ord No. 31-13)
810.005. Applicability. This chapter applies to all areas of land designated as Moderate Landslide Hazard Risk or
High Landslide Hazard Risk pursuant to this Chapter. (Ord No. 31-13)
810.010. Definitions. Unless the context otherwise specifically requires, as used in this Chapter, the following
mean:
(a) Certified Engineering Geologist: Any Registered Geologist who is certified in the specialty of
Engineering Geology under provisions of ORS 672.505 to 672.705.
(b) Geological assessment: An assessment prepared and stamped by a Certified Engineering Geologist,
detailing the surface and subsurface conditions of the site and delineating the areas of a property
that might be subject to specified geologic hazards.
(c) Geotechnical Engineer: A Professional Engineer, registered in the State of Oregon as provided by ORS
672.002 to 672.325, who by training, education and experience is qualified in the practice of
geotechnical or soils engineering practices.
(d) Geotechnical report: A report prepared and stamped by a Certified Engineering Geologist and
Geotechnical Engineer, evaluating the site conditions and mitigation measures necessary to reduce
the risks associated with development in geologically hazardous areas.
(e) Graduated response tables: Those tables under SRC 810.025 that are used to determine the total
landslide hazard risk and required level of site investigation for regulated activities under this Chapter.
(f) Landslide: The down slope movement of soil, rocks, or other surface matter on a site. Landslides may
include, but are not limited to, slumps, mudflows, earthflows, debris flows, and rockfalls.
(g) Landslide Hazard Susceptibility Map: Cumulatively, the Oregon Department of Geology and Mineral
Industries (DOGAMI) Interpretive Map Series IMS-5, IMS-6, IMS-17, IMS-18, and IMS-22 maps, together
with the slope contour map.
(h) Mitigation measure: An action designed to reduce project-induced geologically hazardous area
impacts.
(i) Tree: Any living, woody plant, which grows to 15 feet or more in height, having a trunk which is 10
inches or more dbh.
(j) Tree removal: To cut down a tree or remove all or 30% or more of the crown, trunk, or root system of a
tree; or to damage a tree so as to cause the tree to decline or die. “Removal” includes, but is not
limited to, topping, damage inflicted upon a root system by application of toxic substances,
operation of equipment and vehicles, storage of materials, change of natural grade due to
Page 20 of 35
unapproved excavation or filling, or unapproved alteration of natural physical conditions. “Removal”
does not include normal trimming or pruning of trees. (Ord No. 31-13)
810.015. Map Adoption. Areas subject to this Chapter shall be shown on Landslide Hazard Susceptibility Maps,
which shall be adopted by administrative rule by the Director pursuant to SRC Chapter 20J. The Landslide
Hazard Susceptibility Maps shall indicate the general location of areas of low, moderate, and high susceptibility
to landslides, areas of known slide hazards, and slope contours. These maps shall be based on the best
available information. (Ord No. 31-13)
Page 21 of 35
subsection. Where any portion of a proposed activity is identified under multiple landslide susceptibility
ratings, the highest rating shall apply.
(1) Step One: Earthquake Induced Landslide Susceptibility. Select one assigned point value from
Table 810-1A and proceed to step two.
TABLE 810-1A
EATHQUAKE-INDUCED LANDSLIDE SUSCEPTIBILITY RATINGS
Table 810-1A: Earthquake-Induced Landslide Susceptibility Ratings
Physiographic and Geologic Categories Assigned Point Value
Property identified under Very Low or Low Categories on IMS-17 or IMS-18. 0 Points
Property identified under a Moderate Category on IMS-17 or IMS-18. 2 Points
Property identified under a High Category on IMS-17 or IMS-18. 3 Points
References:
Interpretive Map Series (IMS-17), Interpretive Map Series (IMS-18)
(2) Step Two: Water-Induced Landslide Susceptibility. Select one assigned point value from Table
810-1B and proceed to step 3.
TABLE 810-1B
WATER-INDUCED LANDSLIDE SUSCEPTIBILITY RATINGS
Table 810-1B: Water-Induced Landslide Susceptibility Ratings
Physiographic and Geologic Categories Assigned Point Value
(3) Step Three: Activity Susceptibility Ratings. Select one assigned point value from Table 810-1C
and proceed to step four.
Page 22 of 35
TABLE 810-1C
ACTIVITY SUSCEPTIBILITY RATINGS
Table 810-1C: Activity Ratings
Assigned Point
Type of Activity
Value
Excavation or fill, as an independent activity, exceeding 2 feet in depth or 25 cubic yards of
3 Points
volume.
Single Family, Duplex, or Manufactured Dwelling
1 Point
Installation or construction of any Building Permit
structure greater than 500 square feet in Multiple Family Building Permit 2 Points
area. Schools, Hospital, or Public Building Permit 3 Points
Commercial or Industrial Building Permit 3 Points
Single Family, Duplex, or Manufactured Dwelling
Alteration, enlargement, reconstruction, 1 Point
Building Permit
or relocation of a structure greater than
Multiple Family Building Permit 2 Points
500 square feet in area that requires any
Schools, Hospital, or Public Building Permit 3 Points
modification to the foundation.
Commercial or Industrial Building Permit 3 Points
Installation or construction of any structure greater than 500 square feet, not otherwise
1 Point
identified in table.
Land division, planned unit Partition 2 Points
development, or manufactured Subdivision, Planned Unit Development,
3 Points
dwelling park. Manufactured Dwelling Park
Tree removal, as an independent activity, on regulated slopes greater than 60% . 3 Points
(4) Step Four: Cumulative Score. Add the sub-totals from Tables 810-1A, 810-1B, and 810-1C.
Proceed to step five.
TABLE 810-1D
CUMULATIVE SCORE
Table 810-1D: Cumulative Score
(5) Step Five: Total Landslide Risk. Determine the total landslide hazard risk from Table 810-1E. If the
total landslide hazard risk meets or exceeds the thresholds for moderate or high landslide hazard
risk set forth in Table 810-1E, a geological assessment, geotechnical report, or both, as
applicable, shall be provided by the applicant, and the action specified therein undertaken or
insured before any regulated activity may be permitted or approved.
Page 23 of 35
TABLE 810-1E
TOTAL LANDSLIDE HAZARD RISK
Table 810-1E: Total Landslide Hazard Risk
Cumulative Score
Landslide Hazard Risk Requirement
(From Table 810-1D)
4 or fewer points Category A - Low No Requirements
Geologic Assessment/
5 - 8 points Category B - Moderate
Geotechnical Report
9 or more points Category C - High Geotechnical Report
(b) After determining the total landslide hazard risk under subsection (a) of this section, the following shall
be required:
(1) Low Landslide Hazard Risk. If application of Table 810-1E indicates a Low Landslide Hazard Risk,
all regulated activities may proceed without further investigation, permitting, or approval
required by this Chapter.
(2) Moderate Landslide Hazard Risk. If application of Table 810-1E indicates a Moderate Landslide
Hazard Risk, a geological assessment shall be submitted for all regulated activities. If the
geological assessment indicates that mitigation measures are necessary to safely undertake the
regulated activity, a geotechnical report prepared by a Certified Engineering Geologist and
Geotechnical Engineer shall be submitted.
(3) High Landslide Hazard Risk. If application of Table 810-1E indicates a High Landslide Hazard Risk,
a geotechnical report prepared by a Certified Engineering Geologist and Geotechnical
Engineer shall be submitted for all regulated activities. (Ord No. 31-13)
810.030. Standards for Geological Assessments and Geotechnical Reports. Geological assessments and
geotechnical reports required under this Chapter shall include the information required by this section.
(a) Geological Assessment. A geological assessment shall include information and data regarding the
nature, distribution of underlying geology, and the physical and chemical properties of existing soils; an
opinion as to stability of the site; and conclusions regarding the effect of geologic conditions on the
proposed development. The geological assessment shall bear the stamp of a Certified Engineering
Geologist.
(b) Geotechnical Report. A geotechnical report shall include a comprehensive description of the site
topography and geology; an opinion as to the adequacy of the proposed development from an
engineering standpoint; an opinion as to the extent that instability on adjacent properties may
adversely affect the project; a description of the field investigation and findings; conclusions regarding
the effect of geologic conditions on the proposed development; and specific requirements for plan
modification, corrective grading, and special techniques and systems to facilitate a safe and stable
development. The report shall provide other recommendations, as necessary, commensurate with the
project grading and development. The geotechnical report shall bear the stamp of a Certified
Engineering Geologist and Geotechnical Engineer. (Ord No. 31-13)
810.035. Certification of Compliance. No regulated activity requiring a geotechnical report shall receive final
approval or be permitted for properties located in areas of High Landslide Hazard Risk until the Director receives
a written statement by a Geotechnical Engineer that all measures contained in the geotechnical report are
completed, in place, and operable. (Ord No. 31-13)
Page 24 of 35
6. Cincinnati, Ohio Hillside Overlay Districts
The purpose of the Hillside Overlay District regulations is to establish standards to assist in the development
of land and structures in existing hillside areas and procedures for the review of proposed development, so that
development will be compatible with the natural environment and respect the quality of the urban
environment in those locations where the hillsides are of significant public value. These regulations are intended
to prevent damage to the City's hillsides by minimizing:
(a) Blighting influences caused by the application of conventional land use regulations to lots in areas
having sensitive environmental qualities.
(b) Unstable land.
(c) Significant damage to or destruction of hillsides or valleys.
(d) Significant damage to the economic value and efficiency of operation of existing properties or new
developments due to the interdependence of their visual and functional relationships.
(e) Soil erosion and stream siltation.
(f) Destruction of mature trees and existing vegetation.
In hillside areas, the existence of a 20 percent slope, in combination with the KOPE geologic formation,
is evidence of a condition of natural critical stability and development under conventional regulations
may precipitate landslides or excessive soil erosion. The additional regulations embodied in the Hillside
District are needed to respect the contours and views of the hills for all equally, not for the sole benefit
of a few individuals.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
§ 1433-03. - Definitions.
For purposes of this chapter, words and phrases defined below have the meanings ascribed to them;
additional definitions are in Chapter 1401, Definitions.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
§ 1433-03-B. - Brow.
"Brow" means a brow of the hill that is the separator between the hilltop that is level or gently sloping and
the hillside that is steeply sloped.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
§ 1433-03-C2. - Colluvium.
"Colluvium" means soil material, rock fragments or both, moved by creep, slide or local wash deposited on
or at the base of hillside slopes.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
Page 25 of 35
§ 1433-03-I. - 1980 Inventory of Hamilton County Soils.
"1980 Inventory of Hamilton County Soils" means the report prepared by the Ohio Department of Natural
Resources Division of Lands and Soil in conjunction with the Soil Conservation Service of the U.S. Department of
Agriculture. This study may be used to evaluate the impact and feasibility of development.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
§ 1433-03-S. - Slope.
Slope means the inclination of the land surface from the horizontal. Percentage of slope is the vertical
distance divided by horizontal distance, then multiplied by 100. Thus, a slope of 20 percent is a rise of 20 feet in
100 feet of horizontal distance.
Page 26 of 35
A Hillside Overlay District is shown on the zoning map by a HS designator applied to the base district
designation. This designation is based upon a moderately high or high landslide susceptibility pursuant to the
landslide susceptibility study and map: Any real property either whole or in part within said moderately high or
high susceptibility areas should be classified as being within a HS District.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
§ 1433-07. - Applicability.
Except as otherwise provided in this chapter, all regulations of the underlying zone districts and other
applicable overlay districts apply to and control property in an HS District; provided, however, that in the case
of conflict between the provisions of an underlying zoning district and the HS District, the provisions of the HS
District govern.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
Page 27 of 35
In addition to the requirements for applications established in Chapter 1441, Application Procedures, Fees,
Permits and Certificates, applications for development in the HS District that are not exempt under § 1433-11
must include:
(a) A development plan, accompanied by a property survey, showing existing vegetation and proposed
development, and where applicable, streets, drives, parking areas, walkways, heights of structure(s),
location of structures, elevation and setback of proposed buildings, drainage, existing contours and
proposed grading and new landscaping plans, proposed uses and square footage of uses and
recreational facilities;
(b) A preliminary geotechnical evaluation;
(c) A determination of the maximum building envelope;
(d) Average slope/grade of the property; and
(e) Graphic illustrations demonstrating that the proposed improvement or new structure has not
exceeded the maximum building envelope.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
The maximum building envelope is the solid defined by vertical planes constructed at the HS rear, side and
front yard setbacks and the plane between the HS height of front and the HS height of rear.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004; a. Ord. No. 158-2008, § 1, eff. June 7, 2008)
Page 28 of 35
to support a specific development and a staff review is required to determine conformance with all
requirements of this chapter.
(h) The preliminary geotechnical evaluation should address relative hillside stability.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004; a. Ord. No. 412-2008, § 1, eff. Jan. 4, 2009)
§ 1433-21. - Approval.
(a) If the Zoning Administrator determines the application conforms to the requirements of § 1433-19 and the
requirements of this chapter and all other requirements of the Cincinnati Zoning Code, the Zoning
Administrator has the duty to approve a building permit for the proposed work. The Zoning Administrator
has the duty to notify all owners of property abutting the subject property and the community organization
recognized by the Council as representing the area that includes the subject property.
(b) If the Zoning Administrator determines the application does not conform to the requirements of § 1433-19,
a hearing and decision by the Zoning Hearing Examiner is required, pursuant to Chapter 1443, Zoning
Hearing Examiner Procedures, prior to the issuance of a building permit.
(c) The Zoning Hearing Examiner may approve, approve with conditions or disapprove an application for
development in the HS District based on written findings in accordance with § 1433-23, Hillside
Development Standards.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004; Emer. Ord. No. 141-2015, § 45, eff. July 1, 2015)
§ 1433-25. - Appeal.
Any party with standing may, pursuant to Chapter 1449, Zoning Board of Appeals, appeal to the Zoning
Board of Appeals within 30 days after the decision of the Zoning Hearing Examiner.
(Ordained by Ord. No. 15-2004, eff. Feb. 13, 2004)
Page 29 of 35
7. Cincinnati, Ohio Excavation Or Filling Of Land Code
Chapter 1113 - EXCAVATION OR FILLING OF LAND
Page 30 of 35
(i) Soils types for the site, including the location and extent of visibly evident existing excavations or
fills, slope instability, erosion and water seepage or wet conditions, unstable or highly erodible soils,
or other areas with potentially serious existing or future erosion problems;
(j) Existing and proposed two-foot (2') contours, unless site conditions require more detailed
topography to depict site drainage conditions;
(k) Drainage patterns;
(l) Erosion prevention and sediment control best management practices within, entering, and exiting
the site during each phase of construction, including any existing and/or constructed combined
and separate stormwater drainage conveyance and drainage inlet facilities within the site,
beyond the site, and/or within the larger common plan of development if utilized during
construction;
(m) Drainage watersheds at the site expected before, during, and after major excavation and fill
activities;
(n) Location and approximate depth of existing and proposed utilities including appurtenances,
structures and outfalls;
(o) Water resource locations including known springs, wetlands, streams, lakes, water wells, and
Stream Corridor Protection Overlay District and/or other setbacks on or within 200 feet of the site,
including the boundaries of wetlands or streams and any first subsequent named receiving water
resource(s) intending to be filled or relocated under an approval from the Army Corps of
Engineers and/or Ohio EPA;
(p) Existing and proposed locations of buildings, roads, and parking facilities;
(q) In-stream activities including stream crossings;
(r) Existing and proposed property boundaries, including bearings, distances, and survey monument
information, and subdivision lot numbers;
(s) Existing or proposed easements or other restrictions placed on the use of the property and the
responsible party under such easement or restriction;
(t) Areas vulnerable to erosion and sediment damage;
(u) Areas that do not drain to erosion prevention and sediment control best management practice
structures;
(v) Locations where soil is to be stockpiled; and
(w) Location and size of permanent stormwater control best management practices and other
stormwater facilities, drawn to scale.
(3) A narrative that describes how stormwater discharges from the site will be controlled during
construction that includes:
(a) A description of the overall erosion prevention and sediment control plan that highlights specific
areas of concern;
(b) A maintenance and inspection plan for erosion prevention and sediment control best
management practices;
(c) An implementation schedule that describes the sequence of major construction operations (i.e.,
grubbing, excavating, grading, utilities and infrastructure installation) and the implementation of
erosion prevention and sediment control best management practices to be employed during
each operation of the sequence;
(d) Standards and specifications for the installation and maintenance of all temporary erosion
prevention and sediment control best management practices;
(e) Temporary stabilization requirements and timelines for specific areas of the site;
(f) Standards and specifications for all vegetative practices including seeding, mulching, and
fertilizing rates;
(g) Standards and specifications for any turf re-enforcement matting or other stabilization practices;
(h) Procedures for the stabilization of areas receiving stockpiled soils immediately after stockpiling is
completed;
(i) Schedule indicating the anticipated starting and completion times of the development
sequence, including clearing land, grubbing, stripping, rough grading and construction, final
grading and vegetative establishment, and maintenance including the time of exposure of each
area prior to the completion of erosion prevention and sediment control best management
practices;
Page 31 of 35
(j) Inspection and maintenance guidelines for each erosion prevention and sediment control best
management practice;
(k) Calculations for proposed stormwater runoff flows, volumes, and timing into and through all
temporary erosion prevention and sediment control best management practices that shall
include the underlying assumptions and hydrologic and hydraulic methods and parameters,
under pre- and post-development land use conditions, for flood control, water resource
protection, and water quality, which calculations shall demonstrate that the runoff from upper
watershed areas have been considered in the calculations and indicate that no adverse impacts
are conveyed downstream of the proposed project; and
(l) An investigation of immediate downstream conditions that addresses anticipated temporary
impacts on the downstream water resource and floodplain morphology, hydrology, and water
quality.
(4) A narrative that describes how the quantity and quality of stormwater discharges from the site and/or
into a water resource will be controlled after completion of construction that includes:
(a) Standards and specifications for the installation and maintenance of all permanent stormwater
control best management practices including vegetation, amended soil composition, structural
materials, and rationale for the selection of each practice;
(b) Operations and maintenance requirements for all permanent stormwater control best
management practices during and after construction;
(c) Permanent stabilization requirements and timelines for specific areas of the site;
(d) Calculations for proposed stormwater runoff flows, volumes, and timing into and through all
stormwater control best management practices that shall include the underlying assumptions and
hydrologic and hydraulic methods and parameters, under pre- and post-development land use
conditions, for flood control, water resource protection, and water quality, which calculations
shall demonstrate that the runoff from upper watershed areas have been considered in the
calculations and indicate that no adverse impacts are conveyed downstream of the proposed
project;
(e) An investigation of immediate downstream conditions that addresses anticipated permanent
impacts on the downstream water resource and floodplain morphology, hydrology, and water
quality;
(f) Soil and subsurface conditions, including tests of infiltration rates for native and amended soils
underlying post construction stormwater control best management practices, and borings or
equivalent data indicating seasonal high groundwater levels, top of bedrock elevations, and
perched groundwater elevations;
(g) Installation of permanent stormwater control best management practices off-site may be
considered if it is shown that installation of these structures are not feasible on the site and a
maintenance agreement for off-site structures in a form acceptable to the city solicitor is
recorded.
(5) A narrative that describes how non-sediment pollutants will be controlled during construction that
includes:
(a) The type, location, and dimensions of structural and non-structural non-sediment pollution best
management practices incorporated into the site and the rationale for their selection; and
(b) An inspection and maintenance plan for the non-sediment pollution best management practices
used on the site.
(6) Drawings that include:
(a) Each permanent stormwater control best management practice providing sufficient dimensions,
construction details, design calculations, volumes and sizes of contributing drainage areas, and
elevations;
(b) For subdivided developments where a centralized erosion prevention and sediment control best
management practice capable of controlling multiple individual lots is not provided, a detail
drawing of a typical individual lot showing standard individual lot erosion prevention and
sediment control best management practices.
(7) An inspection and maintenance plan for each permanent stormwater control best management
practice in a form acceptable to the city solicitor that must be recorded that includes:
(a) The parties who:
(i) Own the permanent stormwater control best management practice;
Page 32 of 35
(ii) Are responsible for inspecting and maintaining the permanent stormwater control best
management practice;
(iii) Own property contributing stormwater to the permanent stormwater control best
management practice; and
(iv) Are required to install the permanent stormwater control best management practice.
(b) A schedule for the regular inspection and maintenance of the permanent stormwater control
best management practice.
(c) A requirement that if the party listed in the plan as responsible for inspecting and maintaining the
permanent stormwater control best management practice fails to do so, each property owner
contributing stormwater to and/or required to install the permanent stormwater control best
management practice shall be proportionally responsible for such inspection and maintenance.
(d) The legal description for each property served by the permanent stormwater control best
management practice.
(e) The legal description for the property on which a permanent stormwater control best
management practice is located.
(f) A description of the funding for the long-term maintenance and inspection of the permanent
stormwater control best management practice.
(g) A requirement that reports of all inspections of and maintenance operations on the stormwater
control best management practice must be filed with the utility engineer within thirty days after
such inspection or maintenance.
(h) A prohibition on alteration of the stormwater control best management practice without prior
written approval from the utility engineer.
An operational plan is also required for an excavation or fill comprising the movement of less than 1,000
cubic yards of material or on less than one acre if the work area borders one or more work areas under
separate excavation and fill permit and the total amount of material being moved in all contiguous areas is
more than 1,000 cubic yards or the contiguous areas comprise more than one acre and the areas have some
common ownership or the work in all areas is under common control.
1113-03.2 Certification of Excavation and Fill Quantities and Operational Plan Compliance: Every six months
after the issuance of an excavation and fill permit and on completion of operations, the holder of permit for an
excavation or fill comprising the movement of more than 1,000 cubic yards of material must file with the
Director a certification prepared by a registered surveyor, registered architect or professional engineer of the
quantities of materials placed or removed since the issuance of the permit and that the work has been
conducted in accordance with the operational plan.
1113-03.3 Revocation of Excavation and Fill Permits: The Director may revoke an excavation and fill permit
if the holder of the permit has failed to comply with the operational plan or if the Director determines that the
operations have become offensive or objectionable due to erosion, siltation or dust.
1113-03.4 Excavations and Fills in Residential Districts: If the proposed work is wholly or partially within a
residential zone district, work must be completed within one year from the date of permit issuance. The Director
may extend the time for completion of the work if the Director determines after conducting a public hearing
that the operations have been conducted in compliance with the permit and have not been offensive or
objectionable due to erosion, siltation or dust. The Director has the duty to notify the owner or occupant of the
subject property, any owner or occupant of property abutting the subject property and any community or
neighborhood association or organization whose boundaries include or abut the subject property, recognized
by the council as representing the area. Notice must be sent by ordinary U.S. Mail at least ten days in advance
of the date set for the public hearing.
1113-03.5 Slope: An excavation and fill permit may not be issued for an excavation or fill to be made with a
face steeper in slope than three horizontal to one vertical.
Exception: The director of buildings and inspections may permit an excavation or fill to be made with
steeper face if an applicant demonstrates satisfactorily by means of appropriate soil exploration and analysis
Page 33 of 35
and the written opinion of the geotechnical engineer that the materials are capable of standing on a steeper
slope without creating any of the hazards described in §§ 1101-17.1.1 and 1101-63.5 CBC.
(Ordained by Ord. No. 67-1996, eff. Apr. 5, 1996; a. Ord. No. 343-2001, eff. Nov. 23, 2001; a.
Ord. No. 058-2012, § 1, eff. March 29, 2012)
The tops and toes of excavation and fill slopes shall be set back from property boundaries and structures as
far as necessary for the safety of adjacent properties and adequacy of foundation support and to prevent
damage as a result of water runoff.
All excavations and fills shall be performed so as to minimize soil erosion and sedimentation.
If, in the opinion of the director of sewers or director of public works, it is necessary to adjust, relocate, add
to, or otherwise modify the existing sewer system or drainage course serving the area affected by an
excavation or fill operation area or protecting the existing sewer system or drainage course from damage, a
permit shall be issued in accordance with this Chapter only if the applicant for the permit obtains a permit to
provide, relocate, or modify the sewer system or drainage course for the affected area pursuant to the
regulations under Chapter 719, Sewers, of the Cincinnati Municipal Code, and the current rules and regulations
of the metropolitan sewer district of Greater Cincinnati and the department of public works at the expense of
the applicant and such easements as may be necessary shall be granted.
When in the opinion of the Director of Buildings and Inspections, the termination before completion of a
proposed excavation or fill operation would create an actual or potential hazard to the public, the Director of
Buildings and Inspections prior to issuing the permit shall require a bond in an amount sufficient to cover the
estimated cost of restoration of any affected land or to cover the cost of performance of the operations under
such permit, whichever is greater.
Page 34 of 35
References
2014 National Climate Assessment. U.S. Global Change Research Program
http://nca2014.globalchange.gov/report/regions/midwest
Kockelman, W. J. (1986). Some techniques for reducing landslide hazards. Bulleting of the Association
of Engineering Geologists. v. 23, no. 1, pp. 29-52
Wold, R. J. & Jochim, C. L. (1989). Landslide Loss Reduction: A Guide for State and Local Government
Planning. Federal Emergency Management Agency.
http://www.fema.gov/media-library-data/20130726-1440-20490-1637/fema_182.pdf
Mitigation Ideas: A Resource for Reducing Risk to Natural Hazards. (2013). Federal Emergency
Management Agency
http://www.fema.gov/media-library-data/20130726-1904-25045-
0186/fema_mitigation_ideas_final508.pdf
State of California Hazard Mitigation Plan. (2013). California Emergency Management Agency
http://hazardmitigation.calema.ca.gov/docs/SHMP_Final_2013.pdf
Fact Sheet 2004-3072 - Landslide Types and Processes (2004). United States Geological Survey
http://pubs.usgs.gov/fs/2004/3072/pdf/fs2004-3072.pdf
Page 35 of 35